Converting a CPM Diagram into Precedence

Network Diagram
Once you have drawn the CPM diagram:
1. Replace the 1st event or node of the CPM with a Start node (they are equal)
2. Replace every activity on the CPM with a precedence diagram node
3. Replace the last event or node on the CPM diagram with a Finish node (they are equal)
4. Do the forward pass
5. Do the backward pass

EXAMPLE 1:
1. The naming convention for Activity-on-arrow (CPM) network diagram 
EVENT
NUMBER
2
3 6 EARLIEST LATEST
A=3 3 C=6 DATE DATE

1 4 SLACK
0 0 12 12
0 0

B=5 3 D=7
5 5
0

Activity-on-node (Precedence) network diagram

0 3 3 3 6 9
A C
3 3 6 6 3 12

START FINISH

0 5 5 5 7 12
B D
0 0 5 5 0 12
EXAMPLE 2
Activity-on-arrow (CPM) network diagram

3 6
54 62 81 81
B=20 12 E=12 0
H=30
1 2 F=7 8 9
A=34 5
34 34 J=6
0 0 74 74 111 111 117 117
0 0 0 0 0
G=6
C=15 D=25 I=28
4 7
49 49 80 83 28
0 3
Critical Path

Activity-on-node (Precedence) network diagram


COPIED from Assignment 3