Académique Documents
Professionnel Documents
Culture Documents
Project Description
Improvement
APPROVED:
SAMUEL B. SUBAGAN JR
Municipal Mayor
_________
Estimates for the for the Improvement of Suyo Farmer's Multi Purpose Building
Poblacion,Suyo, Ilocos Sur
III. Excavation/Demolition
Quantity 100.55 sq.m.
Output 20.00 sq.m./day
a. MATERIALS
Quantity Unit Description Unit Cost Total
403.7 kg 16 mm Reinforcing Bars 50.00 20,183.31
324.7 kg 12 mm Reinforcing Bars 50.00 16,233.00
274.2 kg 10 mm Reinforcing Bars 50.00 13,712.03
34.5 kg # 16 G.I. Tie Wire 90.00 3,101.97
53,230.30
B. Labor 6 days
1 Construction Foreman @ P 524.36/day 3,146.16
2 Steelman @ P 440.15/day 5,281.80
4 Laborers @ P 293.36/day 7,040.64
15,468.60
c. Equipment Rentals
1 Unit Cutting machine P 556.00/day 6 days '= 3,336.00
Minor Tools (10% of Labor) = 1,546.86
Sub-total 4,882.86
V. Structural Concrete
Quantity 13.00 cu.m.
VOLUME
FOUNDATION 1.0m x 1.0m x .4m x 6pcs 2.4 cu.m.
COLUMN .25m x .25m x 4m x 6pcs 1.5 cu.m.
TIE_BEAM .15m x .20m x 27.5m 1.35 cu.m.
GROUND FLOOR BEAM 1 .20m x .25m x 27.5 0.825 cu.m.
GROUND FLOOR BEAM 2 .2m x .25m x 13.54m 1.375 cu.m.
SLAB 52.115 Sq.m. x .1m 5.21 cu.m.
TOTAL VOLUME 12.66 cu.m.
SAY 13.00 cu.m.
a. MATERIALS
Quantity Unit Description Unit Cost Total
117.0 bags Portland Cement 280.00 32,760.00
6.5 cu.m. Sand 500.00 3,250.00
13.0 cu.m. Gravel 600.00 7,800.00
25.0 pcs 1/4' Thick Ordinary Plywood 420.00 10,500.00
800.0 bf Coco Lumber 20.00 16,000.00
15.0 kg Assorted CWN 90.00 1,350.00
71,660.00
B. Labor 10 days
1 Construction Foreman @ P 524.36/day 5,243.60
4 Carpenter @ P 440.15/day 17,606.00
4 Laborers @ P 293.36/day 11,734.40
34,584.00
c. Equipment Rentals
1 unit 1 bagger C-Mixer @ 1520.00/day 4 days '= 6,080.00
1 unit Water Pump at P 556.00/day 4 days '= 2,224.00
Minor Tools (10% of Labor) = 3,458.40
Sub-total 11,762.40
a. MATERIALS
Quantity Unit Description Unit Cost Total
1653 pcs. 4" Concrete Hollow Blocks 10.00 16,530.00
143 bags Portland Cement 280.00 40,040.00
7.9 cu.m. Fine Sand/Wash Sand 500.00 3,963.95
334.00 kg 10 mm Reinforcing Bars 50.00 16,700.00
14.696 kg # 16 G.I. Tie Wire 90.00 1,322.64
78,556.59
b. Labor 8 days
1 Construction Foreman @ P 524.36/day 4,194.88
2 Masons @ P 440.15/day 7,042.40
5 Laborers @ P 293.36/day 11,734.40
22,971.68
c. Equipment Rentals
1 unit 1 bagger C-Mixer @ 1520.00/day 4 days = 6,080.00
1 unit Water Pump at P 556.00/day 4 days = 2,224.00
Minor Tools (10% of Labor) = 2,297.17
Sub-total 10,601.17
VIII. Ceilings
Quantity 150.80 sq.m.
a. MATERIALS
Quantity Unit Description Unit Cost Total
23 pcs 25mm x 25mm x 5m Wall Angle 320.00 7,360.00
40 pcs 19mm x 50mm x 5m double furring 160.00 6,400.00
150 pcs 200mm x 5.8m Pvc Platic Panel 385.00 57,750.00
25 pcs Suspension rod (3m) 150.00 3,750.00
45 pcs W-clip 15.00 675.00
1025 pcs Blind Revits 1.00 1,025.00
100 pcs Tokscrew 2.50 250.00
2 kg Concrete nail 100.00 200.00
2 pcs Drill Bit ( concrete ) 85.00 170.00
2 pcs Drill Bit ( metal ) 115.00 230.00
1 pcs Cutting Disc 580.00 580.00
78,390.00
b. Labor 12 days
1 Construction Foreman @ P 524.36/day 6,292.32
2 Skilled/ @ P 440.15/day 10,563.60
2 Laborers @ P 293.36/day 7,040.64
23,896.56
c. Equipment Rentals
Minor Tools (10% of Labor) 2,389.66
Cutting Machine @ 300.00/day 3,600.00
Sub-total 5,989.66
Direct Cost = 108,276.22
15% OCM = 16,241.43
10% CP = 10,827.62
5% VAT = 6,767.26
Sub-total = 142,112.53
Unit Cost = 942.39 per sq.m.
a. MATERIALS
Quantity Unit Description Unit Cost Total
6 sets 1.0 m. x 2.10 m. Panel Door (Hard Wood) 8,500.00 51,000.00
5 sets .8 m. x 1.8 m. Aluminum Door 2,100.00 10,500.00
4 sets 1.2m x .8m reflected Glass Window 3,360.00 13,440.00
10.98 sq.m. Steel Window And Grills 3,500.00 38,430.00
9.33 sq.m. Aluminum Wall/partition 3,000.00 27,990.00
2 sets Stainless Grab Bars (1.4 x 1.2m x 1 1/2") 2,500.00 5,000.00
4 sets Stainless Grab Bars (1.2 x 1.2m x 1 1/2") 2,350.00 9,400.00
155,760.00
b. Labor 10 days
1 Construction Foreman @ P 524.36/day 5,243.60
2 Skilled/ @ P 440.15/day 8,803.00
2 Laborers @ P 293.36/day 5,867.20
19,913.80
c. Equipment Rentals
1 unit Cutting Machine @ P 556.00/day 4 days = 556.00
Electrical Consumption (lumpsum) = 300.00
Minor Tools (10% of Labor) = 1,991.38
Sub-total 2,847.38
X. Electrical Works
Quantity = 1.00 lot
a. MATERIALS
Quantity Unit Description Unit Cost Total
3 box 2.0 mm THHN Electrtical Wire 2,800.00 8,400.00
2 box 3.5 mm THHN Electrtical Wire 3,200.00 6,400.00
50 mtr 5.5 mm THHN Electrtical Wire 35.00 1,750.00
5 rolls Flexible Hose 1/2" Ø 630.00 3,150.00
35 pcs 1/2 Ø PVC Pipe 65.00 2,275.00
4 rolls Flexible Hose 3/4" Ø 930.00 3,720.00
2 pcs 1 1/2 Ø PVC Pipe 135.00 270.00
1 pcs 1 1/2 Entrance Cup 400.00 400.00
1 pcs Panel Board Center Main( 8 holes) 12,000.00 12,000.00
1 pcs 100 amp ACB 2,600.00 2,600.00
2 pcs 20 amp ACB 650.00 1,300.00
1 pcs 30 amp ACB 650.00 650.00
14 pcs Utily Box 2' x 4" 25.00 350.00
14 pcs Junction box 25.00 350.00
3 set 2 Gang Switch 150.00 450.00
11 set 1 Gang Switch 80.00 880.00
4 rolls Electrical Tape 45.00 180.00
5 roll Rubber tape 150.00 750.00
8 pcs 40w Flourescent Light 1,250.00 10,000.00
22 pcs 10w Hidden LED Light 650.00 14,300.00
3 pcs Emergency Light 2,200.00 6,600.00
6 set Convenience Outlet 550.00 3,300.00
80,075.00
b. Labor 5 days
1 Construction Foreman @ P 524.36/day 2,621.80
2 Electrician / @ P 440.15/day 4,401.50
2 Laborers @ P 293.36/day 2,933.60
9,956.90
c. Equipment Rentals
Minor Tools (10% of Labor) = 995.69
Electric Drill @ P 300.00/day 1,500.00
Sub-total 2,495.69
XII. Painting
Quantity 883.84 sq.m.
a. MATERIALS
Quantity Unit Description Unit Cost Total
12 qrt Concrete Neutralizer 90.00 1,080.00
35.00 gals Acrylic Latex Paint 680.00 23,800.00
35.00 gals Acrylic Gloss Latex Paint 750.00 26,250.00
20 m Sand Paper 40.00 800.00
7.00 sack Skim Coat 850.00 5,950.00
5 pcs Putty Knife 150.00 750.00
3 gals Paint thinner 225.00 675.00
3 pcs Roler Brush 50.00 150.00
4 pcs Paint Brush 150.00 600.00
60,055.00
b. Labor 8 days
1 Construction Foreman @ P 524.36/day 4,194.88
2 Painter / @ P 440.15/day 7,042.40
3 Laborers @ P 293.36/day 7,040.64
18,277.92
c. Equipment Rentals
Minor Tools (10% of Labor) = 1,827.79
Sub-total 1,827.79
XIII. Plumbing
Quantity 1.00 lot
a. MATERIALS
Quantity Unit Description Unit Cost Total
9 pcs 1/2" G.I. Pipe 320.00 2,880.00
1 LS 1" Assorted G.I. pipe Fittings 1,200.00 1,200.00
10 pcs 2" PVC pipe 210.00 2,100.00
1 ls 2" Assorted PVC pipe Fiitings 900.00 900.00
8 pcs 4" PVC pipe 620.00 4,960.00
1 ls 4" Assorted PVC pipe Fiitings 2,500.00 2,500.00
20 pcs 3" PVC pipe 490.00 9,800.00
1 ls 4" Assorted PVC pipe Fiitings 3,500.00 3,500.00
2 qrt Epoxy A & B 425.00 850.00
3 can Pvc Solvent 500cc 85.00 255.00
7 set Water Closet With Accessories 7,500.00 52,500.00
3 set Urinal for men 4,500.00 13,500.00
8 pcs Faucets 320.00 2,560.00
3 set Slab Tiles 3/4" 2,600.00 7,800.00
2 set Kitchen Sink & Accessories 5,500.00 11,000.00
1 set Wall Hanged Lavatory & Accessories 3,500.00 3,500.00
13 pcs stainless Floor Drain 420.00 5,460.00
125,265.00
b. Labor 12 days
1 Construction Foreman @ P 524.36/day 6,292.32
2 Master Plumber / @ P 440.15/day 10,563.60
2 Laborers @ P 293.36/day 7,040.64
23,896.56
c. Equipment Rentals
Minor Tools (10% of Labor) = 2,389.66
Sub-total 2,389.66
b. Labor 14 days
1 Construction Foreman @ P 524.36/day 7,341.04
2 Tile Setter @ P 440.15/day 12,324.20
2 Laborers @ P 293.36/day 8,214.08
27,879.32
c. Equipment Rentals
Cutting Machine @ P 300.00/day = 4,200.00
Minor Tools (10% of Labor) = 2,787.93
Sub-total 6,987.93
XV. Ramp
Quantity 1.00 lot
a. MATERIALS
Quantity Unit Description Unit Cost Total
10 bags Portland Cement 280.00 2,800.00
0.672 cu.m. Gravel 700.00 470.40
0.336 cu.m. Sand 600.00 201.60
14.8 kg 10Ømm RSB 45.00 666.00
1 kg Asst. CWN(1" ,2" ,3") 90.00 90.00
1 kg Tie Wires # 16 90.00 90.00
1 ls Stainless Railings 10,500.00 10,500.00
31 pcs 40cm x 40cm Ceramic Tiles 75.00 2,325.00
3 kg Tile Grout 60.00 180.00
0.25 bags Tile Adhisive 280.00 70.00
17,393.00
b. Labor 4 days
1 Construction Foreman @ P 524.36/day 2,097.44
2 Welder / Mason/ Tile Setter @ P 440.15/day 3,521.20
2 Laborers @ P 293.36/day 2,346.88
7,965.52
c. Equipment Rentals
Minor Tools (10% of Labor) = 796.55
Sub-total 796.55
Direct Cost = 26,155.07
15% OCM = 3,923.26
10% CP = 2,615.51
5% VAT = 1,634.69
Sub-total = 34,328.53
Unit Cost = 34,328.53 per lot
S U M M A R Y
SAMUEL B. SUBAGAN JR
Municipal Mayor
20.00
0.00
18.00
15,969.09
0.00
90.00
21,498.00
34,584.00
104.71824 5.75157
39.17376 2.17632
64.00
23,566.98
22,971.68
0.00
161.00
64,479.45
59,296.30
60.00
23,517.00
23,896.56
0
0.2
50.00
46,728.00
19,913.80
25.00
24,022.50
9,956.90
28.00
12,782.16
10,312.40
48.00
18,016.50
18,277.92
60.00
37,579.50
26,286.22
0.00
70.00
28,311.00
27,879.32
20.00
5,217.90
0.00
0.00
114.00
55,730.06
43,410.06
2,298,450.66
1,851,623.58
MATERIAL COST 1,274,082.96
labor 444,631.27
equipments 213,236.57
OCS 256,249.35
CP 192,895.08
VAT 118,904.76
0.00
2,500,000.00
APPROVED BUDGET FOR THE CONTRACT
ITEM Description Quantity Unit ESTIMATED DIRECT MARK-UPS TOTAL MARK-UP VAT TOTAL TOTAL COST UNIT
No. COST IN PERCENT INDIRECT COST COST
OCM PROFIT % VALUE
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5)x(8) 5%(5+9) (9)+(10) (5)+(11)+(11a) (12)/(3)
I.Project Sign Board Lump Sum 3,000.00 3,000.00
II.Occupational Safety and Health Program 140.00 days 144,779.92 10% 10% 14,477.99 7,962.90 22,440.89 167,220.80 1,194.43
III.Excavation/Demolition 100.55 sq.m. 75,841.86 10% 10% 7,584.19 4,171.30 11,755.49 87,597.35 871.18
IV. Reinforcing Steel Bars 1,002.57 kg 73,581.76 15% 10% 25% 18,395.44 4,598.86 22,994.30 96,576.06 96.33
V. Structural Concrete 13.00 cu.m. 118,006.40 15% 10% 25% 29,501.60 7,375.40 36,877.00 154,883.40 11,914.11
VI. Masonry with Plaster 132.22 sq.m. 112,129.43 15% 10% 25% 28,032.36 7,008.09 35,040.45 147,169.88 1,113.07
VII. Roofing Materials 189.00 lm 317,373.43 15% 10% 25% 79,343.36 19,835.84 99,179.20 416,552.63 2,203.98
VIII.Ceilings 150.80 sq.m. 108,276.22 15% 10% 25% 27,069.05 6,767.26 33,836.32 142,112.53 942.39
IX. Doors ,Windows And Grab Bars 1.00 lot 178,521.18 15% 10% 25% 44,630.30 11,157.57 55,787.87 234,309.05 234,309.05
X. Electrical Works 1.00 lot 92,527.59 15% 10% 25% 23,131.90 5,782.97 28,914.87 121,442.46 121,442.46
XI. Septic Tank 1.00 lot 53,950.84 15% 10% 25% 13,487.71 3,371.93 16,859.64 70,810.48 70,810.48
XII. Painting 883.84 sq.m. 80,160.71 15% 10% 25% 20,040.18 5,010.04 25,050.22 105,210.93 119.04
XIII.Plumbing 1.00 lot 151,551.22 15% 10% 25% 37,887.80 9,471.95 47,359.76 198,910.97 198,910.97
XIV. Tile Works 121.88 sq.m. 129,237.25 15% 10% 25% 32,309.31 8,077.33 40,386.64 169,623.89 1,391.73
XV. Ramp 1.00 lot 26,155.07 15% 10% 25% 6,538.77 1,634.69 8,173.46 34,328.53 34,328.53
XVI. Roofing Extention 185.86 l.m. 266,857.93 15% 10% 25% 66,714.48 16,678.62 83,393.10 350,251.03 1,884.49
TOTAL 527,339.37 449,144.43 118,904.76 568,049.20 2,500,000.00
Address : Date
Mode of Procurement
Gentlemen:
Please furnish this office the following articles subject to the terms and conditions
contained herein:
Place of Delivery : Suyo, Ilocos Sur Delivery Term :
Date of Delivery : Payment Term :
Item No. Unit Quantity Description Unit Cost Amount
1 pcs. 12 1/4" Ordinary Plywood 380.00 4,560.00
2 bd.ft. 290 2x2 Ro. Lumber 40.00 11,600.00
3 kls. 5 4" CWN 100.00 500.00
4 kls. 2 2" CWN 100.00 200.00
5 kls. 2 1/2" Fin. Nail 100.00 200.00
6 bags 20 Portland Cement 280.00 5,600.00
7 cu.m. 1.5 Sand 750.00 1,125.00
8 set 1 1.0 x 2.10 Flush Door 7,500.00 7,500.00
9 -
10 -
11 -
12 -
13 -
14 -
15 -
16 -
TOTAL 31,285.00
Date
Funds Available:
Section 369 (a) of R.A. 7160, this portion must Amount:
be accomplished).
Approved to be purchased thru negotiated
purchase per Sangguniang Res. No. _____ R.O. No.:
Certified Correct:
GILBERT L. GIACAO, JR. IAN RICHARD D. LORENZANA
(Authorized Official) Accountant
PURCHASE REQUEST
SUYO, ILOCOS SUR
Total 31,285.00
PM
Uso vs Suyo Proper 1:00pm - 3:00pm
Poblacion vs Cabugao 3:00pm - 5:00pm
PM
Urzadan vs Cabugao 1:00pm - 3:00pm
Man-atong vs Suyo Proper 3:00pm - 5:00pm
PM
Poblacion vs Patoc-ao 1:00pm - 3:00pm
Man-atong vs Baringcucurong 3:00pm - 5:00pm
PM
Urzadan vs Baringgcucurong 1:00pm - 3:00pm
Cabugao vs Man-atong 3:00pm - 5:00pm
PM
Suyo Proper vs Poblacion 1:00pm - 3:00pm
Man-atong vs Uso 3:00pm - 5:00pm