Académique Documents
Professionnel Documents
Culture Documents
100mm thk bed 25.20 25.80 26.70 27.70 28.80 30.10 31.50
115mm thk bed 28.98 29.67 30.71 31.86 33.12 34.62 36.23
125mm thk bed 31.50 32.25 33.38 34.63 36.00 37.63 39.38
150mm thk bed 37.80 38.70 40.05 41.55 43.20 45.15 47.25
175mm thk bed 44.10 45.15 46.73 48.48 50.40 52.68 55.13
200mm thk bed 50.40 51.60 53.40 55.40 57.60 60.20 63.00
9. Formwork System
b. plywood ( 48.00 per pcs use 2 time) 0.33 18.00/M2 1.67
c. others / mics 0.80 1.13 0.44 2.11
d. 10% Wastage 0.11
e. Labour 1.80 1.80
3.05 per fs 3.91 per fs
say, 32.78 per m2 22.00 per m2
11. Excavation
a. < 300mm through-out 8.00 per m2
b. General < 1.5m 15.00 per m3
c. General >1.5m<3.0m 20.00 per m3
d. remove excavate materials 12.00 per m3
e. backfill 15.00 per m3
ARCHI
2. Clay Bricks Half brickwall (115mm thick) One brickwall (230mm thick)
a. Cement per 50 kg bag 14.00 14.00
Unloading per bag 0.40 0.40
Total per 50 kg cement bag 14.40 14.40
b. Sand per lorry load 550.00 550.00 10 wheel
-ditto - per m3 84.33 84.33
c. Clay bricks per no. 0.35 0.35
d. 1m3 of cement mortar (1:3)
= cement - 357 kg 102.82 102.82
= sand - 0.75 m3 63.25 63.25
166.06 166.06
e. 1 m2 of brickwall
= clay bricks 54 nos. 18.90 108 nos. 37.80
= cement mortar 0.0305 m3 5.06 0.0610 m3 10.13
23.96 47.93
Add 7% wastage 1.68 3.36
25.64 51.28
f. Exmet 0.50 1.00
g. Labour (1.00/fs) 10.76 21.52
h. Machinery - Hoists/Concrete Mixer 4.00 8.00
40.90 81.80
i. Profit
say, 40.90 81.80
3. Cement Sand Bricks Half brickwall (115mm thick) One brickwall (230mm thick)
a. Cement sand bricks per no. 0.17 0.17
b. 1m3 of cement mortar (1:3) 166.06 166.06
c. 1 m2 of brickwall
= cement sand bricks 60 nos. 10.20 120 nos. 20.40
= cement mortar 0.0305 m3 5.06 0.0610 m3 10.13
15.26 30.53
d. Add 7% wastage 1.07 2.14
16.33 32.67
e. Exmet 0.50 1.00
f. Labour (1.12/fs) 10.76 21.52
g. Machinery - Hoists/Concrete Mixer 0.50 1.00
28.09 56.19
h. Profit
say, 28.10 56.20
7. Waterproofing (sika-kimia 107) Toilet Area Wall Nito Proof 600 Sika Monogum Sika Flex
a. Supply & Lay 17.25 20.70 34.50 24.15 33.35
b. Hoist
17.25 20.70 34.50 24.15 33.35
say,
#REF!
0.00
11. Wall Tiles Backing Screed (m2) 1:6 Screed 1:3 Screed
a. 1m3 of cement sand mortar (1:6) 97.77 136.85
b. Add 7% wastage 6.84 9.58
104.62 146.43
c. 1m2 of 13mm thick cement mortar 1.36 1.90
d. Labour (0.80/fs) 8.61 8.61
e. Machinery - Hoists/Concrete Mixer 1.00 1.00
10.97 11.51
f. Profit
11.00 11.50
#REF!
12. Floor Rendering (m2) 50mm thick 25mm thick 19mm/20mm thick
a. Cement per 50 kg bag 14.00 14.00 14.00
Unloading per bag 0.40 0.40 0.40
Total per 50 kg cement bag 14.40 14.40 14.40
b. Sand per lorry load 550.00 550.00 550.00
-ditto - per m3 45.38 84.33 84.33
c. 1m3 of cement mortar (1:3)
= cement - 357 kg 102.82 102.82 102.82
= sand - 0.75 m3 34.03 63.25 63.25
136.85 166.06 166.06
Add 7% wastage 9.58 11.62 11.62
146.43 177.69 177.69
1m2 of cement mortar 7.32 4.44 3.55
d. Labour (0.80/fs) 8.61 8.61 8.61
e. Machinery - Hoists/Concrete Mixer 1.00 1.00 1.00
16.93 14.05 13.16
f. Profit
16.90 14.10 13.20
13. Staircase Rendering Landing Slab (m2) Treads < 255mm (m) Risers < 200mm (m) Stringer sides < 450mm
a. 1m2 of 25mm thick cement mortar 7.32 1.87 1.46 3.29
b. Labour 3.80 4.00 4.00 4.00
c. Machinery - Hoists/Concrete Mixer 1.00 1.00 1.00 1.00
12.12 6.87 6.46 8.29
d. Profit
12.10 6.90 6.50 8.30
14. Floor Tiles Backing Screed (m2) 50mm 40mm 32mm 25mm 20mm 13mm
a. 1m3 of cement sand mortar (1:3) 136.85
b. Add 7% wastage 9.58
146.43 146.43 146.43 146.43 146.43 146.43
c. 1m2 of cement mortar 7.32 5.86 4.69 3.66 2.93 1.90
d. Labour (0.80/fs) 8.61 8.61 8.61 8.61 8.61 8.61
e. Machinery - Hoists/Concrete Mixer 1.00 1.00 1.00 1.00 1.00 1.00
16.93 15.47 14.29 13.27 12.54 11.51
f. Profit
16.93 15.47 14.29 13.27 12.54 11.51
15. Staircase Backing Screed Landing Slab (m2) Treads < 255mm (m) Risers < 200mm (m)
a. 1m2 of 20mm thick cement mortar 4.44 1.13 0.46
b. Labour (0.80/fs) 8.61 1.94 1.72
c. Machinery - Hoists/Concrete Mixer 1.00 1.00 1.00
14.05 4.07 3.18
d. Profit
14.10 4.10 3.20
#REF!
0.00
17. Backing Screed to Drops (m) 50mm 100mm 150mm 200mm 100mm skirting
a. 1m3 of cement sand mortar (1:3) 136.85
b. Add 7% wastage 9.58
146.43 146.43 146.43 146.43 146.43
c. 1m2 of 13mm thick cement mortar 1.90 1.90 1.90 1.90 1.90
d. 1mr of cement mortar to drop 0.10 0.19 0.29 0.38 0.19
e. Labour (0.80/fs) 8.61 8.61 8.61 8.61 8.61
f. Machinery - Hoists/Concrete Mixer 1.00 1.00 1.00 1.00 1.00
9.70 9.80 9.89 9.99 9.80
g. Profit
9.70 9.80 9.90 10.00 9.80
18. WINDOW FRAMES (Kempas) 225 x 38 150 x 50 150 x 38 100 x 38
a. Supply (m) 22.42 12.75 10.68 7.58
b. Labour 1.65 1.65 1.65 1.65
24.07 14.40 12.33 9.23
c. Wastage (2%) 0.48 0.29 0.25 0.23 0.03
24.55 14.68 12.58 9.46
d. 3% Profit 0.10
24.55 14.68 12.58 9.46
23. DOOR LEAF (4mm thick plywood) D1/CD1 D2/CD2 CD3 CD6
900 X 2100 750 X 2100 650 X 2100 1500 X 2100
Supply (no.) 43.05 43.05 43.05 96.60
Labour (no) 25.00 25.00 25.00 25.00
68.05 68.05 68.05 121.60
Wastage (5%) 3.40 3.40 3.40 6.08
71.45 71.45 71.45 127.68
3% Profit
PER NO. 71.45 71.45 71.45 127.68
say 60.00 60.00 60.00 129.00
PER M2 31.75 38.10 43.96 40.95
2. Floor Tiles (m2) 600 x 600 300 x 300 300 x 300 (semi-glazed) 200 x 200 (non-slip)
a. Supply 15.000 3.000 1.670 1.500
After ….% discount 15.000 3.000 1.670 1.500
No. of Pieces per m2 2.77 11.11 11.11 25.00
41.55 33.33 18.55 37.50
b. Wastage @ 10% 4.16 3.33 1.86 3.75
45.71 36.66 20.41 41.25
c. Labour (2.00/fs) 21.52 21.52 21.52 21.52
d. Screed Joint 1.00 1.00 1.00 1.00
e. Hoist 1.00 1.00 1.00 1.00
69.23 60.18 43.93 64.77
f. UPVC Tile Trim - - - -
say, 69.23 60.18 43.93 64.77
TILES
0
TILES
0