CONSTRUCTION SAFETY AND HEALTH PROGRAM

PROJECT DETAILS
Project I.D. No. : PRO – 09 – 19 – 0001
Specific Name of Project : CONSTRUCTION OF ADMIN OFFICE
.,
Project Classification : EXPANSION

Project Owner : SFI MULTIMIX CORPORATION

Name of main Contractor : MKE CONSTRUCTION COMPANY


.
Estimated number of workers : 20
Estimated start of execution : OCTOBER 24, 2019
Estimated duration : 120 CD
Scope of work to be undertaken :
ADDITION
ACCESSORY BUILDING/STRUCTURE

HEALTH AND SAFETY COMMITTEE


CHAIRMAN : EDWIN CABRERA
SAFETY OFFICER : GERLINDA M. SENTILLAS
MEMBERS :
First Aider - CLEA LEEN ZAINAB E. IMLAN
Project Engineer – ENGR. AGAPITO DEL ROSARIO JR.
Foreman - ARNEL GARCIA
Carpenter - JUN ALVAREZ
Mason - JAY-AR VALENCIA
Clark Development Corporation

Subject : APPROVAL OF CONSTRUCTION SAFETY AND HEALTH PROGRAM

Dear Sir/Ma’am :

In compliance with the requirements of the Department Order No. 13 series of 1998
Guidelines Governing Occupational Safety Health in the Construction Industry and the
applicable provisions of the Occupational Safety and Health Standard ( OSH ),MKE
CONSTRUCTION COMPANY is submitting three (3) sets of Construction Safety and
Health Program for the Construction of Admin Office at Clark Freeport Zone, Clark
Pampanga(Contract I.D No:PRO-09-19-0001) for your approval.

Thank you very much for your consideration of this Construction Safety and Health Program.

Respectfully yours,

MARY KATHRYN M. ENRIQUEZ


President
Ma. Eusebia Angara- Campita
Regional Director
Department of Labor and Employment (DOLE)

Subject : CONSTRUCTION SAFETY AND HEALTH PROGRAM

Dear Ma’am :

We are requesting your good office for the approval of Construction Safety and Health
Program for : Construction of Admin Office at Clark Freeport Zone, Clark Pampanga
(Contract I.D No:PRO-09-19-0001)

This is in compliance to Safety and Health Standard Art. 162 of Labor Code of the
Philippines and the Department Order No. 13 series of 1998 Guidelines Governing
Occupational Safety and Health in the Construction Industry.

Respectfully yours,

MARY KATHRYN M. ENRIQUEZ


President
CONSTRUCTION SAFETY AND HEALTH IMPLEMENTATION COST
Construction of Admin Office at Clark Freeport Zone, Clark Pampanga(Contract I.D
No:PRO-09-19-0001)

QUANTITY UNIT PRICE TOTAL COST


A. MEDICINES
Antipyretic 200 pcs. 2.00 400.00
Analgesic 200 pcs 2.00 400.00
Antihistamine 100 pcs. 3.00 300.00
Antispasmodic 100 pcs. 1.50 150.00
Povidone Iodine 20 bot. 40.00 800.00
B. MEDICAL SUPPLIES
Alcohol 20 bot. 65.00 1,300.00
Band – aid 200 pcs. 2.00 400.00
Cotton Balls 5 packs 40.00 200.00
Gauze 10 packs 52.00 520.00
Plaster 20 rolls 27.00 540.00
C. PPE
Goggles 20 pcs. 75.00 1,500.00
Gloves 100 pairs 25.00 2,500.00
Hard Hat 50 pcs. 130.00 6,500.00
Harness 10 pcs. 1,030.00 10,300.00
Lanyard 10 480.00 4,800.00
Safety Shoes 50 pairs 310.00 15,500.00
D. SAFETY STAFF
Safety Officer 120 days 500.00 60,000.00
First Aider 120 days 310.00 37,200.00
E. OTHERS
Drinking Water ( water 4 mos. 300.00 1200.00
district )
Safety Signage’s 6 75.00 450.00
Random Drug Testing 1 pax 300.00 300.00

OVERALL TOTAL SAFETY COST: 145,260.00

Prepared by : Approved by :