3.3 Interpersonal Communication Skills ............................................................................................................................. 9
3.4 Team Playing Skills ........................................................................................................................................................ 9
3.5 Leadership Skills .......................................................................................................................................................... 10
3.6 Ethics Issues ................................................................................................................................................................ 11
3.7 Entrepreneurship skills................................................................................................................................................ 12
?Human resource management ....................................................................................................................................... 12
?Equipment utilization management ............................................................................................................................... 12
?Financial management .................................................................................................................................................... 13
CHAPTER FOUR ..................................................................................................................................................................... 14
4. My project work covering necessary contents ................................................................................................................. 14
4.1 Office works ................................................................................................................................................................ 14
?Reading drawing ............................................................................................................................................................ 14
4.2 Site work ..................................................................................................................................................................... 14
4.2.1 Sub structure work................................................................................................................................................... 15
4.2.1.1 Trench excavation and Masonry work .................................................................................................................. 16
4.2.1.2 Grade beam........................................................................................................................................................... 16
Procedure used to construct a grade beam.................................................................................................................. 17
Hard core and mesh work or ground floor slab ................................................................................................................ 19
Procedure to work ground floor slab ............................................................................................................................ 19
4.2.2 Super Structure ........................................................................................................................................................ 20
4.2.2.1 Column .............................................................................................................................................................. 20
4.2.2.2 Stair work .......................................................................................................................................................... 21
4.2.2.3 Beam ................................................................................................................................................................. 22
4.2.2.4 Slab .................................................................................................................................................................... 22
4.2.3 Reinforcement bar (Re-bar) ..................................................................................................................................... 24
4.2.4 Form work ................................................................................................................................................................ 24
4.2.5 Concrete work .......................................................................................................................................................... 25
CHAPTER FIVE .................................................................................................................................................................. 30
5. RECOMMENDATION AND CONCLUSION.......................................................................................................................... 30
5.1 Conclusion ................................................................................................................................................................... 30
5.2 Recommendation ........................................................................................................................................................ 30
6. References......................................................................................................................................................................... 32
7. Appendix ........................................................................................................................................................................... 33
ii
iii
Declaration
I,FIREHIWOT MENGISTU, student of Wolaita Sodo University Institute of Technology hereby declare that
this internship report is submitted by my own and it describes my four months stay in Haile mixed use
construction at Wolaita Sodo municipality town. I affirm that all the materials and pictures used while
compiling this report contains actual events and facts that was observed and performed during my internship
program. All the contents are my own and it has not been submitted to any other institute.
Approval of supervisor:
iv
Acknowledgements
First of all I would like to thanks the almighty GOD for his guidance through all the challenges and eases that I
have faced. Then I would like to tanks Wolaita Sodo University institute of technology and university industry
linkage office and my department civil engineering for arranging this internship program. Also I would like to
express my thanks to Wolaita Sodo municipality Construction Office for its positive response of my request to
host me as an intern and availing this opportunity to practice and learn about the practical world of building
construction and project management.
I would also like to thanks my site supervisor Feleke Dogiso, site engineer Alembrahan and my beloved
academic advisor Epherem.E for their guidance during my practice.
Finally I would like to express my thanks to all persons who, in one way or another way, contributed for the
accomplishments of my practice.
v
Executive Summary
It is a clear fact that the knowledge of civil engineering cannot be upgraded without practical experience in each
field of the subject matter. This paper is a written report about the internship program which was planned to
help internship students grasp practical know- how of engineering projects, their design, implementation,
evaluation and management in general. It reports about the background of my internship hosting company
including its brief history and major achievements, my overall internship experience, my tasks and the
procedures I followed, the practical and theoretical knowledge I faced while preforming those tasks with
conclusionsandrecommendations
vi
CHAPTER ONE
• It follows and controls design implementation whether it is based on the design approved or not
1
• Constructing site works
Vision
• To be an international Engineering and Architectural consultancy firm known for professional and business
integrity.
• To see the people of Ethiopia at large get standardized infrastructure by rendering quality study, design, and
construction supervision and consultation services and be cases and proficient enterprise in east Africa
• To become competent in the construction and other similar sectors undertaking to have better contribution
in the area.
?Mission
To construct high standard and quality building few of them are listed above
• To create large amount of job opportunities for skilled and unskilled labor who lived in the town and the
country as whole.
1.3 Its Main Customers or the end users of its products or services
The main customers of this company are the society weather the project is governmental or private.The major
activities in which the company has engaged are the following.
• Building construction
• Design works.
• Town’s people
• Private owner
2
• Consulting firms
• Housing association
CHAPTER TWO
The first step in the internship is choosing which construction site is best to get the better experience and
knowledge for my future. So I distributed few copies of the form for different companies to ask their
willingness to host me as an intern student in their company. Finally, wolaita Sodo to municipality construction
office announced me that they have confirmed my request and they told me to begin my internship at Haiel
mixed use construction site. According to their announcement I started my internship from March 01 up to June
30, 2010 E.C.
3
2.2 Section of the company I have been working in
During the first weeks I was getting myself familiar with the overall construction works, the structural and
architectural drawings and staff members and my site supervisors.I was immediately placed in the site
engineering department when I started practicing to observe and learn the construction procedures and also
assist the site engineers in all possible ways I can.
• Afternoon routine
• Analyzing, arranging and summarizing data for the monthly report
• preparing site diary
Here are the detail procedures:-
• I take a photo especially for each site work by using a mobile camera
• I ask any question the site engineer and daily labors if there was doubt for me
• I refer the books that are related to the work for better understanding.
• I attended the work properly
I observed all work flows in site work and also I try to attend the work every day, because it helps me to saw the
work flow correctly.
I mostly want to concentrate on things that are related to my work activity’s and try to avoid topics which may
not help me to make a good impression at work. But it will keep me from making a bad one. Subject that do not
make for good work place conversion including, political, religion, health problems and other personal issues
5
should be avoided, this factors are responsible to make the work efficiency and work process more less.
Managing my time effectively is crucial thing to my work. My ability to complete my work in a timely manner
will help me to be more lovable and more believable to my jobs. I should demonstrate that I know how to
manage my time effectively by handling project when or even before my deadline. But there are some things
that greatly influence how to manage my time as well as the working progress. Some of these factors are
scarcity of material, nature of the work, lack of skilled man power. Material is not always available to the
contractors when they need it. This happens because of the current price of material or the inflations and it may
be the financial problems. But in our case the client are responsible for the availability of the material. The
nature of the work also makes the work more difficult. Skilled man power is not available as desired.
Sometimes the contractors use less number of laborers than the assumed one. This also makes the work not to
complete in a time. Finally in construction work a team work is more crucial. This team work is crucial for my
effectiveness as working as supervisors or managing the works. Even if I am not in management or leadership
role yet, better understanding a team work can make more effective employee. The other crucial element of
team work success is that all the team effort are directed toward the same clear goals, the team goals relies
heavily on a good communication in the team and the harmony in member relationship.
6
• When I move here and there on the site I moved with great care. As a result I finished the tasks safely
without any danger.
?CHAPTER THREE
• The exact position in work- this means the position of responsibility they gave me as a data collector and
site engineer made me tough.
7
• Many theoretical lessons taken before the internship
• Self-interest in my profession
• Construction of masonry
• How to bend, cut, lay, erect and tie reinforcement bars each other
8
enhance my understanding of constructing a building. Theoretical knowledge is dependable on principles, logic
and calculations.
It is interesting when the theoretical knowledge & the practice meet exactly as you wanted to.
Sometimes this relationship fails to some degree. Theoretical knowledge doesn’t show you the tasks which are
processed in the site. Generally speaking, my theoretical knowledge got strengthen more by those practical
techniques invested on site.
• To know more technical knowledge, listen and respect technical people like the carpenter and mason.
• Communicates constructively
• Listens actively
• Functions as an active participant
• Shares openly and willingly
• Cooperates and pitches in to help
• Exhibits flexibility
• Shows commitment to the team
• Works as a problem-solver
• Treats others in a respectful and supportive manner
My supervisor was the site engineer so I spent most of my time with him & that helped me a lot to improve my
leadership skills. He explained to me that a construction work is like a dictatorship & that a site engineer should
control & know about every work that is done on the site. And from what I saw I have to say I agree with him.
For effective leadership I understood that personal values like confidence, effective communication and
devotion are very important.
11
• Honesty:-Regarding this value each worker regardless of its status should abstain from bad behaviors
such as cheating, bias, corruption etc.
• Cooperation:-Each worker should interact and cooperate with each other while working that is because
it is through such system problems could be easily solved.
?Financial management
Wide financial flow is achieved through detailed market studies and also taking long term contracts with the
best material suppliers in terms of quality and cost.
During my internship experience I have been able to grasp ideas about human resources management,
equipment utilization and financial flow and also develop self-confidence to play my strength in believing in
myself and taking risks in my future career.
Generally, I can say I have gained the potential benefits by taking this Internship Program.
13
CHAPTER FOUR
From office work I have seen and go knowledge and experience about how can I read structural, architectural,
sanitary and electrical installation drawing.
?Reading drawing
Drawings are the means by which the designer conveys the physical, quantitative, and visual description of the
project to the contractor. The drawings are a two-dimensional representation of the physical structure that meets
the objectives of the owner. They are also known as plans or blueprints. It is the main language between the
architect, designer and any worker at the site or office to build the model in position as specified by the designer
and the client, based on the agreement. Thus to work as an engineer in the construction site it is mandatory
knowing drawings and any other specification. Drawings are the most common means of communication for all
types and sizes of project. Thus I understand each drawing and knew every symbol abbreviation for every
section and I able to communicate with different workers using it.
• Arrangement of building
• Arrangement of bars
• To know where column, beam, stair, door, window and etc. are found.
Super structure
14
Reinforcement bar
Concrete works
• Excavation work: - excavation work is the act of making hallow by cutting, scoping or digging out a part
of a soil
• Earth work: - Earth work is any work which is related to the excavation, backfill and cart away of surplus
material in the site.
• Concrete work:- concrete work includes all activities that begin from inserting and adjusting of the footing
pad and the foundation column bar up to casting of the pad and the column respectively.
• Masonry work: - masonry work includes trench work and construction of retaining wall
Steps which were followed during the sub structure work are: -
• Site clearance
• Bulk excavation
• Pit excavation
15
• Grad beam work
But in our site I have not seen this all step because when I start my interns the project company finished works
up to back filling of pit, and I started from trench excavation
• To brace columns, by bracing column, it used to avoid slenderness of the foundation column.
• Ground is covered by lean concrete. The purpose of the lean concrete is to separate the grade beam and
the soil, to prevent from resting of the reinforcement and used as supporting for the grade beam the lean
concrete have 5cm in thickness. And it is C-5 characteristic concrete strength.
• Preparing side form works that is used resist initial pressure of the concrete. This formwork must be
fixed by a supporting material called joist and strict. Joist is a horizontal timber that is used to support a
strut. Strule is gun from the joist to the form work diagonally to support to the form work.
• Insert spacer 50mm b/n the bars and the form work which used to resist cracking due to corrosion of
bar
• Concrete cast
17
Figure- 2 Construction of grade beam
Backfill
Selected material used to fill in trench or excavation work. The act of filling or excavation, usually after a pipe
or some type of structure has been placed in trench or excavation. Compaction of soil:it is the process in which
a stress applied to a soil causes densification as air and water is displaced from the pores between the soil
grains. They compact the soil by both compacter machine and by man power.
18
Hard core and mesh work or ground floor slab
Ground floor slab is a slab that lay on a specially prepared ground and constructed with a great care to prevent
capillary action and subside with passage of time. Ground floor slab is specially supported by the ground unlike
the suspended slabs.
Hard core materials to be placed should be properly selected and preferably be granular, most commonly
crushed basaltic stone
• stretching of string from one grade beam to other side to find the level of hard core fill
• Hard core was placed on a properly compacted, and well consolidated soil
• Crushed and well graded rocks was provided to fill the void space
• The ground slab bar was laid down on the hard rock
• Provision of Styrofoam between the slab and the grade beam to create expansion joint
19
Figure-4 Hardcore and mesh work for floor slab
4.2.2.1 Column
Column is a structural part of a building which is a vertical member that support vertical, horizontal and
moments coming from the beam, slab, stair and other member of the structure and transfer in to sub structure
that is foundation. They are given different shapes such as circular, rectangular and square as per architectural
consideration of a structure. In our site they constructed both rectangular and circular column.
Column construction: - Construction of a column starts by setting out the alignment for the corner columns
using string, plumb bob .These corner columns are used as a reference for setting out the rest of the columns.
This will facilitate the construction process and make it simple and easy. Then fixing of the column
reinforcement bars on the starter bar (over laps) takes place. Over laps are bar lengths which are extensions of
previously fixed reinforcement bars. Overlap lengths (development length) are obtained by the formula 4 Ø,
where Ø is diameter of reinforcement. The main bars are tied by the stirrup to give better strength and keep the
bars in place. Concrete spacers are then tied randomly around the column bars before the formwork are placed.
This will help to hold the reinforcement bars away from the sides of the formworks, So that when the concrete
sets. It completely envelops the reinforcements. They should have the same strength as the concrete that is going
to be placed and have equal thickness with the clear cover provided on the design. Next column formworks are
20
fixed around the column bars and the concrete covers provided the exact size of the column. The formworks
must be painted with form oil to make dismantling easy. Then concrete is filled in to the formwork. The concrete
must be compacted at regular interval by a concrete vibrator. In order to avoid the presence of air bubbles the
compaction should not exceed to prevent segregation. After that the formwork is removed.
21
4.2.2.3 Beam
Beam is a structural element that is capable of withstanding load primarily by resisting bending. The bending
force induced in to the material of the beam as a result of the external loads, own weight, span and external
reactions to these loads, is called bending moment.
Beam construction:-The beam construction is the same as the case of column, but in this case the formwork is
set up in the horizontal direction. While the case of column it laidvertical. The placing, compacting and curing
processes are to other chemicals that are bonded together in such a way that creates one of the best building
material.
In solid slab bottom reinforcement bars are in both direction covers the entire slab panel whereas, the top bars
cover the area of one-third of from nearby beams. It is made of reinforcement concrete. In this bottom and top
reinforcement steel spacer (kebeleto) is used to provide the required spacing between them. Negative bars
provided on top to take negative tension. Main bars and distribution bars can be bent up to serve as negative
bars. Before casting of concrete electrical conduit installation are placed within the reinforcements. Also
circular and rectangular boxes will be positioned later to be used for locating junction boxes and to spaces
sanitary pipes.
• Lengths of negative bars and where supports are provided to hold negative bars in places
23
Figure-8 kebeleto
The deformed Surfaces help to minimize slippage of concrete and to develop a great bond between concrete and
steel.
?Plain or smooth bars: - is the reinforcement in the shape of smooth surface. The range of diameter that where
available in the site is: - Ø6, 8, 10, 12, 16, 18, 20, 24.
?Stirrup: - serve as shear reinforcement. Also it tied on longitudinal reinforcement to provide resistance against
out ward buckling.
?Longitudinal reinforcement: - provide resistance to compressive and tensile loads with concrete.
• Cristae
24
• Prop (fonte)
• Scaffolding
In no circumstances, formwork shall be struck until the concrete reaches strength of at least twice the stress to
which the concrete may be subjected at the time of striking. The operation of removing the formwork is
commonly known as stripping. The stripping time differs from different structural parts.
?Requirements of formwork
• The material of form work should be cheap and it should be suitable for re-use several times.
• It should be strong enough to with stand all loads coming on it, such as, dead load of concrete and live load
during its pouring, compaction and curing.
?Components of concrete
Cement: - is a material with a binding property in a concrete. It is the most expensive material in a concrete
making. Therefore, it should be fresh and stored in an enclosed ventilated space that would protect it from
deterioration. In the site they had stored in dry media. So almost there is no freeing of deterioration.
Aggregate:-is filler material of grade size from fine sand to piece of stone of varying diameters and shapes.
From 70% to 80% of the volume of concrete is aggregate keeping the cost of the concrete low.
Types of aggregate
-Fine aggregate:-is usually sand
-Course aggregate:-is usually gravel or crushed stone.
Water: - is one component of the concrete that facilitate the chemical reaction which cause setting and
hardening.
Types of concrete
I have observed two types of concrete in the site:-
•Lean concrete
•Reinforced concrete
Lean concrete: - is a mixture of cement, sand,aggregate and water with compressive strength of C-5 and C-7. It
has a mix proportion of one bag of cement, four box of sand and six box of aggregate by volume. It laid under
footing pad, masonry wall and grade beam with 30 cm thickness and 50 cm off set without reinforcement.
• It protects all structure element from moisture
• It prevents the soil particles that are present under structure from any relative
movement.
• It helps as host stratum to hold sub- structure on the soil and other.
Reinforced concrete: - it differs from lean concrete being massive, having high compressive strength, used
with reinforcement and for structural parts.
Reinforcement concrete can have different quality in different parts of sub structure and super structure as it is
designed. In our site they have used concrete with compressive strength of C-25.
Batching of the concrete
The process of mixing cement, water, fine aggregate and course aggregate in suitable
proportion is known as mixing concrete.
In our site the mixing method is machine mixing. Concrete produced by machine mixing is more homogeneous.
27
Figure-10 Compaction of concrete using Vibrator
Curing of concrete
Curing is the maintaining of a satisfactory of moisture content and temperature in concrete, So that the concrete
may develop the desired strength and hardness. Correctly cured, concrete shrinks, cracks and dusts less, while
gaining strength, durability and wear resistance during the hardening of concrete, heat is generated and this
would result in rise in the temperature of the concrete.
To prevent rise in temperature on account of the heat of hydration developed during hardening of cement to
prevent drying of concrete.
Spacer
A spacer is material which is made up of steel or mortar. Spacers are used to maintain uniform thickness of cover
to reinforcement in substructure and superstructures which were reinforced. They were pre-made at the site by
using plain concrete with its required dimension of cover to reinforcement in substructure and super structure in
which were reinforced. Spacers were put between the formwork and reinforcement bars by using metal ties
which were connected with the spacer while preparing them.
28
Figure-11 Spacer
29
CHAPTER FIVE
5.1 Conclusion
The internship program is to enable the intern to experience the practical activities carried out on the site and
correlate it with the theoretical back ground gained through learning. Other include if problems exist to identify
its cause and take engineering measures to solve it, to get familiarized to the working environment, to be
governed by the rule and regulation of the employer, to be more of team player. There was a gap between the
things which we know in the class with the outside environment and this gap is now narrowed. I have got
practical work experiences and benefits from my internship program.
Some of them are;
• Communication skills with professionals
• Work flow
• Leadership skill
• Working standards
• Work ethics
Nowadays Construction is the most undertaking investment in Ethiopia. There are many companies which work
on construction. These companies may be Consultants in which the design the Structural, Architectural,
Sanitary, Electrical and Mechanical are made and Contractors which change the designs on paper into
something tangible. The General and social experience which I gained from the internship are :-
• In the launch and tea time there was a good time with our boss.
• Work flow and work order in the company had a good experience.
5.2 Recommendation
For the company:-It is well known that health and safety are priority of everyone at the construction site. Since
the construction site contain different employees of the country. Emphasis should be given for safety case. In
30
my site they have not used helmets and safety shoe. Concerning this I recommend the company should provide
helmets’ and safety shoe for the workers.
The other negative side of the company was shortage of daily labor. Since the construction work is mostly
depend on daily labor that there should be sufficient number of labor.
I observed that some daily labors were not executing their work properly, like suitable backfill compaction.
I also observed that there was shortage of construction materials like formwork/panels. So the labors obligated
to use by attaching the panels these leads to unnecessary flow of concrete these means separation of aggregate
from cement and water especially in case of the column. For this, the contractor must supply enough materials
to the site we direct these to site engineer.
31
6. References
Data recorded from the site
• Reinforced Concrete Book
• Company Profile and other Related Book
32
7. Appendix
• Cabeleto- A four leg ladder which masons and carpenters use
• Tumbi-plumb bob to check vertical alignment for all vertical formwork.
• Armata-Concrete
• Soleta-Slab
• Panel-Formwork
• Ferayo-bar bender.
• Ferro-reinforcement bar.
• Stanga-an inclined wood used to tauten column formwork
• Fonte-scaffolding
• Kerebat-piece of woods used to fasten the ‘Fonte’
• Barella-a box with different sizes to measure fine and course aggregate
• Sekelo-small plastic bag labours use to handle concrete
• Kebeleto-z-bar used in slab
• Cristae: pole like structure made from wood used for supporting vertical formwork of beam during
construction.
• Sponda: vertical panel formwork of beam supported by KISIT and used to cover width beam.
• Staffa: stirrups used to resist shear failure and can hold the bars to give a required shape.
• Fondo(bottom soffit): horizontal panel for beam formwork placed on CRISTY to cover thickness of
beam.
33