Académique Documents
Professionnel Documents
Culture Documents
41
Presupuesto Contratado = S/.385,250.00 77050.00
Factor de Relacion = 0.97213
VALORIZACIÓN N°01:
MARZO
UBICACION:
FECHA:
VALORIZACIÓN N°02:
ABRIL
UBICACION:
FECHA:
A SUMA ALZADA
Pb= S/.43,789.98 INICIO DE OBR MAYO
FPb= Jan-18 TIEMPO = 3 MESES
Po= S/.42,850.55
Fr= 0.97855
VALORIZACIÓN N°03:
MAYO
UBICACION:
FECHA:
Anterior ACTUAL ACUMULADO SALDO %
Descripción Unid Cant PU Parcial Importe
Cant Importe Cant Importe Cant Importe Cant Importe Avance
CONCRETO ARMADO
COLUMNA 107,435.80
CONCRETO F'C=210Kg/cm2 m3 220 333.94 73,466.80 220.00 73466.80 0.00 0.00 220 73,466.80 0.00 0.00
ENCOF. -DESENCOF. m2 650 42 27,300.00 650.00 27300.00 0.00 0.00 650 27,300.00 0.00 0.00
ACERO CORRUGADO kg 1350 4.94 6,669.00 1350.00 6669.00 0.00 0.00 1350 6,669.00 0.00 0.00
VIGA 64,177.50
CONCRETO F'C=210Kg/cm2 m3 150 305.15 45,772.50 110.00 33566.50 40.00 12,206.00 150 45,772.50 0.00 0.00
ENCOF. -DESENCOF. m2 300 46.53 13,959.00 200.00 9306.00 100.00 4,653.00 300 13,959.00 0.00 0.00
ACERO CORRUGADO kg 900 4.94 4,446.00 700.00 3458.00 200.00 988.00 900 4,446.00 0.00 0.00
LOSA ALIGERADA 76,721.66
CONCRETO F'C=210Kg/cm2 m3 98 279.22 27,363.56 25.00 6980.50 73.00 20,383.06 98 27,363.56 0.00 0.00
ENCOFRADO-DESENCOFRADO m2 780 33.07 25,794.60 580.00 19180.60 200.00 6,614.00 780 25,794.60 0.00 0.00
ACERO CORRUGADO kg 1500 4.94 7,410.00 500.00 2470.00 1,000.00 4,940.00 1500 7,410.00 0.00 0.00
LADRILLO 0.15x0.30x0.30 unid 6050 2.67 16,153.50 1050.00 2803.50 5,000.00 13,350.00 6050 16,153.50 0.00 0.00
MUROS 68,699.77
LADRILLO KK 18 HCO SOGA m2 489 48.84 23,882.76 298.00 14554.32 191.00 9,328.44 489 23,882.76 0.00 0.00
LADRILLO KK 18 HCO CABEZA m2 589 76.09 44,817.01 370.00 28153.30 219.00 16,663.71 589 44,817.01 0.00 0.00
COSTO DIRECTO 317,034.73 227,908.52 89,126.21 317,034.73 0.00
GASTOS GENERALES(15%) 47,555.21 34,186.28 13,368.93 47,555.21 0.00
UTILIDAD (10%) 31,703.47 22,790.85 8,912.62 31,703.47 0.00
SUBTOTAL 396,293.41 284,885.65 111,407.76 396,293.41 0.00 100.00%
% DE AVANCE 100% 71.89% 28.11% 100.00% 0.00%
ACUMULADO = ANTERIOR+ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
CASO OBRA RITMO NORMAL ARA =APA
A SUMA ALZADA
FP PARA LA VALORIZACIÓN N°01
Pb: S/.396,293.41
FECHA : MARZO
AREA GEOGRAFICA: 3
N N°01
118888.02 87987.03
AVANCE
N° FECHA APA ARA ESTADO DE LA OBRA
1 MARZO 118,888.02 87,987.03 RETRASADO
Rprog=Vprog(K-1)
R=V(K-1)
Rreal=Vreal(K-1)
REINTEGRO
N° FECHA Vpro Vre K-1 Rprog Rreal
1 MARZO 115,575.00 85,535.11 0.018 2,041.65 1,510.99
2° ABRIL
FORMULA POLINOMICA UNICA
A= MONTO DE ADELANTO DIRECTO (SIN IGV)
C= MONTO CONTRAACTUAL (SIN IGV) Fr=
K= COEFICIENTE DE REAJUSTE
Ka= COEFICIENTE DE REAJUSTE AL MES DEL ADELANTO EN EFECTIVO
D= DEDUCCION
VRC VxK AxV / C ( K / K a 1)
AVANCE
N° FECHA APA ARA ESTADO DE LA OBRA
1 MARZO 118,888.02 87,987.03 RETRASO
2 ABRIL 269,479.52 284,885.65 ADELANTADO
Rprog=Vprog(K-1)
R=V(K-1)
Rreal=Vreal(K-1)
REINTEGRO
N° FECHA Vpro Vre K-1 Rprog Rreal
1 MARZO 115,575.00 85,535.11 0.020 2,286.56 1,692.24
2 ABRIL 146,395.00 191,411.70 0.020 2,896.30 3,786.92
3°
FORMULA POLINOMICA UNICA
A= MONTO DE ADELANTO DIRECTO (SIN IGV)
C= MONTO CONTRAACTUAL (SIN IGV) Fr=
K= COEFICIENTE DE REAJUSTE
Ka= COEFICIENTE DE REAJUSTE AL MES DEL ADELANTO EN EFECTIVO
D= DEDUCCION
VRC VxK AxV / C ( K / K a 1)
AVANCE
N° FECHA APA ARA ESTADO DE LA OBRA
1 MARZO 118,888.02 87,987.03 RETRASO
2 ABRIL 269,479.52 284,885.65 ADELANTADO
3 MAYO 396,293.41 396,293.41 NORMAL
Rprog=Vprog(K-1)
R=V(K-1)
Rreal=Vreal(K-1)
REINTEGRO
N° FECHA Vpro Vre K-1 Rprog Rreal
1 MARZO 115,575.00 85,535.11 0.020 2,286.56 1,692.24
2 ABRIL 146,395.00 191,411.70 0.019 2,753.50 3,600.21
3 MAYO 123,280.00 108,303.19 0.019 2,318.74 2,037.04
385,250.00 385,250.00
Rrecon
1,510.99
0.97213
Rrecon
1,692.24
3,786.92
5,479.16
1,510.99
3,968.17
0.97213
Rrecon
1,692.24
3,600.21
2,037.04
7,329.50
5,479.16
1,850.33
CURVA S
S/ 450,000.00
S/ 250,000.00
S/ 200,000.00
S/ 150,000.00
S/ 100,000.00
S/ 50,000.00
S/ 0.00
MARZO ABRIL
APA
MINIMO
ARA
O ABRIL MAYO
ADELANTO DIRECTO
1. DEDUCCIONES
DE LA 1° VALORIZACION
DE LA 2° VALORIZACION
DE LA 3° VALORIZACION
1. AMORTIZACION
ADELANTO DE MATERIALES
INDICES MATERIALES
N° FECHA MONTO OTORGADO I.U. MAT
Io
1 MARZO S/ 75,000.00 21 426.29
2 ABRIL S/ 75,000.00 21 426.29
3 MAYO S/ 75,000.00 21 426.29
�=𝑉∗%(𝐾/𝐾𝑎−1)
DE LA 1° VALORIZACION
febrero
K mes K adelanto D prog. D real D reconocida
1.018 1.018 S/ 0.00 S/ 0.00 S/ 0.00
DE LA 2° VALORIZACION
febrero
K mes K adelanto D prog. D real D reconocida
1.020 1.018 S/ 24.07 S/ 17.81 S/ 17.81
1.020 1.018 S/ 30.48 S/ 39.86 S/ 39.86
DE LA 3° VALORIZACION
febrero
K mes K adelanto D prog. D real D reconocida
1.01978 1.01767 S/ 24.07 S/ 17.81 S/ 17.81
1.01881 1.01767 S/ 16.45 S/ 21.51 S/ 21.51
1.01881 1.01767 S/ 13.85 S/ 12.17 S/ 12.17
D total = -S/ 51.49
-S/ 57.67
S/ 6.18
DEUDA SALDO
S/ 38,525.00 S/ 29,971.49
S/ 29,971.49 S/ 10,830.32
S/ 10,830.32 S/ 0.00
𝐴𝑚𝑎�=𝐶𝑢∗𝑃𝑢∗𝐹𝑟∗(𝐼𝑚𝑎/𝐼𝑚𝑜)
𝑀�=(𝐼𝑜/𝐼𝑎)∗𝑀𝑜�𝑜𝑟𝑔.
2. Muro de soga
UND 1m2 APU
Metrado Cantidad
MATERIAL Unidad Cant. Precio Metrado valor actual Utilizado
Cemento BLS 0.218 23.5 98.00 21.36
3. Muro de cabeza
UND 1m2 APU
Metrado Cantidad
MATERIAL Unidad Cant. Precio Metrado valor actual Utilizado
Cemento BLS 0.408 23.5 120.00 48.96
2° VALORIZACION
1. Concreto en columna
Metrado Cantidad
MATERIAL Unidad Cant. Precio Metrado valor actual Utilizado
Cemento BLS 9.73 23.5 120.00 1167.6
2. Concreto en viga
Metrado Cantidad
MATERIAL Unidad Cant. Precio Metrado valor actual Utilizado
Cemento BLS 8 23.5 110.00 880.00
0.00
0.00
0.00
87,046.10
8,553.51
25,128.15
33,681.66
53,364.44
53,364.44
9,605.60
62,970.04
S/.62,970.04
ALORIZACION N°02
RIL DEL 2018
19,141.17 27,694.68
49,871.85 75,000.00
69,013.02 102,694.68
126,309.18 179,673.63
126,309.18 179,673.63
22,735.65 32,341.25
149,044.84 212,014.88
S/.149,044.84 S/.212,014.88
ALORIZACION N°03
IO DEL 2015
6.18 -51.49
0.00 0.00
6.18 -51.49
110,159.70 392,528.01
10,830.32 38,525.00
0.00 75,000.00
10,830.32 113,525.00
99,329.38 279,003.01
99,329.38 279,003.01
17,879.29 50,220.54
117,208.67 329,223.55
S/.117,208.67 S/.329,223.55
VALORIZACION POR INTERES
RESUMEN DE VALORIZACIONES
ITEM VALORIZACION ULTIMO DIA DE PAGO MONTO PAGADO VALORIZADO (VN) FECHA DE PAGO INTERES SE GENERA INTERES A LA VALORIZA
1 MAYO 2018 6/30/2018 S/. 53,364.44 6/28/2018 NO AL IGV
2 JUNIO 2018 7/31/2018 S/. - 8/8/2018 0 -8
3 JULIO 2018 8/31/2018 S/. - 9/22/2018 0 -22
S/. 53,364.44
I=Vn(FAt/FAo-1)
GENERA INTERES A LA VALORIZACION NETA
FAt 8/8/2018 UN DIA ANTES DEL PAGO FAo 7/31/2018 ULTIMO DIA DE PAGO
FAt 9/21/2018 UN DIA ANTES DEL PAGO FAo 8/30/2018 ULTIMO DIA DE PAGO