Develop a project network consisting of at least 20 steps that should be done to complete the
project. As the case suggests, keep the level of detail for these activities general, rather than
specific. Be sure to indicate some degree of precedence relationship among the activities.
Answer:
The network consists of the following 20 steps that should be done to complete the project:
13. BCC management approval for the project scope, constraints and plan 12
A Design 5
B Specifications 5 A
C Budget 3 B
D Draw up contract 2 C
E Client meeting 1 D
F Project launch 1 E
G Subcontracting 3 F
H Permitting 3 F
I Purchasing 6 F
J Interior preparation 3 G
K Exterior preparation 2 G
L Material Delivery 10 I
M Electrical 6 G, H, L
N Plumbing 4 G, H, L
O HVAC 3 N, M
P Interior construction 25 L, M
Q Exterior construction 10 L
R Flooring 5 P
S Finishing work 10 R
T Quality control 3 S
U Client presentation 1 T
V Exterior landscaping 3 Q
W Inspections 5 S
X Client delivery 1 W