Académique Documents
Professionnel Documents
Culture Documents
Outline
Page 2
1
10/2/2017
Page 3
Page 4
2
10/2/2017
• As grounding practices affect fault current levels, they have a direct bearing upon
relay system designs.
• The main reason for operating the power system ungrounded is that there is no
ground fault current.
• As the vast majority of faults on a power system are ground faults, service
interruptions due to faults on an ungrounded system are greatly reduced.
• As the number of transmission lines connected to the power system grows, the
capacitive coupling of the feeder conductors with ground provides a path to ground,
and a ground fault on such a system produces a capacitive fault current.
Page 5
Page 6
3
10/2/2017
• Ungrounded systems produce good service continuity, but are subjected to high
overvoltages on the unfaulted phases when a ground fault occurs.
• When a ground fault occurs on phase a, the steady-state voltages of phases b
and c become √3 times their normal value and transient overvoltages become
correspondingly higher.
• This places additional stress on the insulation of all connected equipments.
• For system operating at a voltage higher than 100 kV, the fault-induced
overvoltages begin to assume a critical role in insulation design, especially of
power transformers.
• At high voltages, it is therefore common to use solidly grounded neutrals (more
precisely “effectively grounded”).
Page 7
• Such systems have high ground fault currents, and each ground fault must be
cleared by CBs.
• In certain heavily meshed systems, particularly at 69 and 138 kV, the ground fault
current could become excessive because of very low zero-sequence impedance at
some buses.
• If ground fault current is beyond the capability of the CBs, it becomes necessary to
insert an inductance in the neutral in order to limit the ground fault current to a safe
value.
• In several LV networks, a very effective alternative to ungrounded operation can be
found if the capacitive fault current causes ground faults to be self-sustaining. This is
the use of a Petersen coil, also known as the ground fault neutralizer (GFN).
Page 8
4
10/2/2017
Page 9
Page 10
5
10/2/2017
Page 11
Page 12
6
10/2/2017
Page 13
Substation Configuration
• Substations are designed for reliability of service and flexibility in operation and to
allow for equipment maintenance with a minimum interruption of service.
• Most common bus bar arrangements are,
˗ Single bus, single breaker scheme
˗ Double bus-double breaker scheme
˗ Main-and-transfer bus scheme
˗ Double bus-single breaker scheme
˗ Ring bus scheme
˗ Breaker-and-a-half scheme
Page 14
7
10/2/2017
Advantages:
• Simple in design
• Lowest cost
Disadvantages:
• Failure of bus or any circuit breaker results
in the shutdown of entire substation
• Difficult to do maintenance
• Bus cannot be extended without de-
energization of substation
Page 15
Advantages
• Each circuit has two dedicated breakers.
• Flexible in permitting feeder circuits to be
connected to either bus.
• Any breaker can be taken out of service for
maintenance.
• High reliability.
Disadvantages:
• Most expensive
• Would lose half the circuits for breaker failure if
the circuits are not connected to both buses
Page 16
8
10/2/2017
Advantages:
• Low initial and ultimate cost.
• Any breaker can be taken out of service for
maintenance.
Disadvantages:
• Requires one extra breaker for the tie bus.
• Switching is complicated when maintaining
a breaker.
• Failure of bus or any breaker results in
shutdown of entire substation.
Page 17
Advantages:
• Permits some flexibility with two buses.
• Either bus may be isolated for maintenance.
• Circuit can be transferred readily from one bus
to the other using bus-tie breaker and isolators
Disadvantages:
• One extra breaker is required for the tie bus.
• Four switches are required per circuit.
• Bus protection scheme may cause loss of
substation when it operates if all circuits are
connected to that bus.
Page 18
9
10/2/2017
Disadvantages (Continued):
• Line breaker failure takes all circuits connected to that bus out of service.
• Bus-tie breaker failure takes entire substation out of service.
Page 19
Advantages:
• In ring bus scheme, the bus bars and
breakers. are connected in series to form a
ring.
• Requires only one breaker per circuit.
• Each circuit is fed by two breakers.
• Low initial and ultimate cost.
• Flexible operation for breaker maintenance.
• Any breaker can be removed for
maintenance without interrupting load.
Page 20
10
10/2/2017
Disadvantages:
• If a fault occurs during breaker maintenance period, the ring can be separated into
two sections.
• Protective relaying circuitry is complex
• Breaker failure during a fault on one of the circuits causes loss of one additional
circuit owing to operation of breaker-failure relaying.
Page 21
Breaker-and-a-half Scheme
Advantages (Continued):
• Simple and flexible operation.
• High reliability.
• 3 breakers for 2 circuits, so one and a
half breaker per line.
• Failure of bus side breakers removes
only one circuit from service.
• Simple operation; no disconnect
switching required for normal operation
• Either main bus can be taken out of
service at any time for maintenance.
Page 22
11
10/2/2017
Breaker-and-a-half Scheme
Advantages (Continued):
• Bus failure does not remove any feeder circuits from failure.
• Widely used in EHV systems.
Disadvantages:
• One and a half breaker per circuit.
• Relaying and automatic reclosing are involved since the middle breaker must be
responsive to either of its associated circuits.
Page 23
Nature of Relaying
Page 24
12
10/2/2017
Nature of Relaying
Page 25
Nature of Relaying
Better to have high dependability and less security than vice versa.
Page 26
13
10/2/2017
Nature of Relaying
Page 27
Nature of Relaying
Page 28
14
10/2/2017
Nature of Relaying
Page 29
Nature of Relaying
Page 30
15
10/2/2017
Nature of Relaying
Page 31
Nature of Relaying
Page 32
16
10/2/2017
Nature of Relaying
Page 33
Nature of Relaying
Page 34
17
10/2/2017
Nature of Relaying
Page 35
Nature of Relaying
Page 36
18
10/2/2017
Nature of Relaying
Page 37
Nature of Relaying
Speed
• Speed is the ability of relaying system to initiate operation in the shortest possible
time.
˗ Instantaneous: No intentional time delay
˗ Time-Delay: Intentional time delay is inserted
˗ High Speed: Operates less than 3 cycles on a 60 Hz system
˗ Ultra High speed: Operates less than 4 ms.
Sensitivity
• The relaying system should be sensitive to detect smallest fault current that may
occur during abnormal conditions.
Page 38
19
10/2/2017
Nature of Relaying
Economy
• The ability of relaying system to function at minimum cost.
Simplicity
• The ability of relaying system to function and to operate with minimum equipment
and circuitry.
Page 39
Nature of Relaying
Page 40
20
10/2/2017
Nature of Relaying
• The alternate to duplications is the backup relaying. Backup relays are generally
slower than the primary relays and remove more system elements than may be
necessary to clear a fault.
• Backup relaying may be installed locally, that is, in the same substation as the
primary protection, or remotely.
• Remote backup relays are completely independent of the relays, transducers,
batteries, and CBs of the protection system they are backing up.
• Local backup relaying does not suffer from these deficiencies, but it does use
common elements such as the transducers, batteries, and CBs, and can thus fail to
operate for the same reasons as the primary protection.
Page 41
Nature of Relaying
• Breaker failure relays are a subset of local backup relaying that is provided
specifically to cover a failure of the CB.
• The breaker failure relay system consists of a separate timer that is energized
whenever the breaker trip coil is energized and is de-energized when the fault
current through the breaker disappears.
• If the fault current persists for longer than the timer setting, a trip signal is given to all
local and remote breakers that are required to clear the fault.
Page 42
21
10/2/2017
Nature of Relaying
Page 43
Nature of Relaying
Page 44
22
10/2/2017
Nature of Relaying
• Automatic reclosing of CBs is initiated by dedicated relays for each switching device,
or it may be controlled from a substation or central reclosing computer.
• Some of the common interlocks for reclosing are the following,
˗ Voltage check
˗ Synchronizing check
˗ Equipment check
Page 45
Page 46
23
10/2/2017
Page 47
Page 48
24
10/2/2017
• From the design point of view, circuit breaker is classified into two types:
˗ Line-tank
˗ Dead-tank
• In the live tank design, the interrupting chamber is located in an insulator bushing
which is at the line voltage above ground, that is, the interrupter unit in live tank
breakers is not grounded during operation.
• The interrupting chamber should therefore be provided with insulated supports.
• Live tank circuit breakers are cheaper than dead tank and require less space. Since
the entire equipment is at line potential, it is not possible to incorporate CTs that have
their secondary windings essentially at the ground potential.
Page 49
• It then becomes necessary to design the CTs with their own insulating system, as
separate free-standing devices.
• In dead tank circuit breakers, the interrupting chamber is at ground potential.
• As the incoming and outgoing conductors are taken through insulated bushings, it is
possible to place current transformers on them.
Page 50
25
10/2/2017
Page 51
26