Vous êtes sur la page 1sur 31

Project Controls

Planning & Scheduling

The Key to Successful Project


Management
Purpose of Project Controls

• Set project goals and objectives


• Identify & manage risk(s)
• Establish a clear project approach (expectations)
• Document our assumptions
• Communicate roles and responsibilities
• Monitor performance
• Resolve claims and disputes
Project Goals and Objectives

• Complete the project on time and on budget


• Benefits to the client
– Maximize program usefulness
– Quality product
– Meet established budget
– On-time delivery
• Benefits to the company
– Profitability
– Client satisfaction
– Employee satisfaction
Project Life Cycle

PROGRAM MANAGEMENT
Construction Management
Pre Planning

 Project identification
 Needs assessment
 Team assembly
 ROM definition
 Financial pro forma
Programming Phase

 Consultant participation
 Functional definition
 Space requirements
 Master plan
Design Phase

 Schematic
 Design development
 Construction Document
 Bid / Contract Documents
Agency Approvals

 “Use” permits (CUP)


 Environmental permits (EIR)
 Location permits (Coastal Commission)
 “Building & Safety” permits
− Federal (FAA, GSA, DOE, DOT)
− State (DSA - schools, OSHPD - hospitals)
− Local (Plan Check)
 Fire department approvals
 Special permits (AQMD)
Construction Phase

 Bid and award


 Pre-construction
 Construction
 Inspection
 Operations
 Close-out
Start-up & Occupancy Phase

 Licensing
 Final inspections
 Operations
 Project Close-out
 Maintenance
Program/Project Management vs
Construction Management

 Program and Project Management provides leadership


− Set the course or direct the team
− Make decisions to maintain the plan

 Construction Management provides execution


− Validate the methodology (means and methods)
− If “at risk” manage means and methods

 The Contract defines the duties and responsibilities as


well as the deadlines and objectives
Project Controls

 Estimating
 Planning & scheduling
 Document management
− Contract documents
− Submittals and approvals
− Change management
 Cost Engineering
− Revenue
− Expense
 Risk Management
Risk Management

 Today greater concern is given to demonstrating


the probability of success
 Risk Management quantifies that probability
 Risk can be classified
− Threat
− Opportunity
 Probability can be modeled
Project Risks (Threats)
120

100

80

 Safety 60

40
 Scope 20

 Budget 0

Time

 Time impacts Unknowns Amount At Stake Risk

 Risks to the client


 Risks to the company
Project Definition

Quality
Scope

 Established by the design


− Size and function
− Configuration
− Materials
− Quality
 Estimating is the act of recording your
understanding of scope
 Includes an understanding of means and methods
employed
Resources

 Resources are the project consumables


− Labor
− Material
− Equipment
− Other
 Cost engineering is associated with resource
management
− Budget
− Actual
− Forecast
Time
 Time of performance may include all phases of the project. Often
contract duration or end date is set before any planning or scheduling is
performed based on:

• Need by date
• Someone’s “guesstimate” of duration

 Many factors influence the project


− Safety & logistics
− Quantity of work
− Type of work
− Resource availability
− Means and methods
− Skills and abilities
Planning vs. Scheduling

 Planning deals with the “Big Picture” approach


− What scope is included?
− Are there any priorities – by phase or component?

 Scheduling is based on a detailed methodology


− Top Down – defining the Work by component
− Bottom Up – putting it together brick by brick

Two means to the same end –


defining a project duration
Planning and Scheduling Approach

 Consider alternatives PRIOR to cost expenditure


− Challenge approach
− Gain consensus
Incorporate various issues and concerns
 Represents full project scope
 Based on logical development
− Physical requirements
− Resource availability
− Project efficiencies
 Meets project deadlines
Planning & Scheduling Methodologies

 To- do list
 Calendar – “Day Planner”
 Barchart – Gantt Chart
“Logic Based” Methods

 CPM Network - deterministic


− Arrow Diagram
Plumbing Drywall
Wall
A Framing B Rough C D

− Precedence Diagram

 PERT Analysis - probabilistic


Critical Path Methodology

 Arrow Diagramming Method (ADM)

Prepare Purchase Fabricate


A B C D
Specifications Equipment & Deliver
IJ = A-B IJ = B - C IJ = C - D

Work activities are represented by the arrow, ends are only points in time.

If multiple activities are related but no effort is required “DUMMY” activities are used to show requirements.
Critical Path Methodology

 Precedence Diagramming Method (PDM)

Activity “A” Activity “B”

Pour Set
Foundation Pump

Work activities are linked by relationships. The activity consumes time, the
relationship may or may not have additional time (called LAG).
ADM vs. PDM

ADM PDM
A C
1 3 5 A C

=
B D
2 4 6 B D
Logic Relationships

 Hard
− REQUIRED sequence
− Physical Relationship between activities
− Successor is dependent on predecessor

 Soft
− Optional or desired sequence
− Resource (Crew) Flow from location to location
− Availability of Multiple Crews

 Hard logic takes priority over soft logic


Relationship Types

FS (finish to start) – First activity must be complete for the second activity to begin

SS (start to start) – The start of the second activity is related to the start of the first, usually
with a lag duration between them

FF (finish to finish) – The second activity cannot finish until the first activity finishes

Also associated with a lag duration

SF (start to finish) – holds the finish of the second activity in relationship to the start of the
first
Activity Time Values

 Each activity has four time values associated with it:

− Early Start (ES): The earliest possible time an activity


can begin based on network logic

− Early Finish (EF): The earliest possible time an activity


can finish based on network knowledge

− Late Start (LS): The latest possible time an activity can


start without delaying project completion

− Late Finish (LF): The latest possible time an activity can


finish without delaying project completion
Communications Tool

 Organizational structure - WHO

 Work breakdown structure (physical work) – WHAT /


WHERE

 Resource management – HOW MUCH


− Cost / quantity
− Productivity

 Time distribution - WHEN


− Plan availability
− Increase efficiency
Monitor Performance

 Document project history


− Schedule and cost impacts
− Not detailed project accounting

 Ensure meeting project objectives

 Prioritize conflicting efforts

 Adjustments
− Improve efficiency
− Recovery
− Manage change
Dispute / Claims Resolution

 A CPM Schedule is the recognized tool to


− Quantify impact
− Identify responsibility
 Excusable
 Non-excusable
− Establish liability
 Compensable
 Non-compensable

Vous aimerez peut-être aussi