Académique Documents
Professionnel Documents
Culture Documents
PROGRAM MANAGEMENT
Construction Management
Pre Planning
Project identification
Needs assessment
Team assembly
ROM definition
Financial pro forma
Programming Phase
Consultant participation
Functional definition
Space requirements
Master plan
Design Phase
Schematic
Design development
Construction Document
Bid / Contract Documents
Agency Approvals
Licensing
Final inspections
Operations
Project Close-out
Maintenance
Program/Project Management vs
Construction Management
Estimating
Planning & scheduling
Document management
− Contract documents
− Submittals and approvals
− Change management
Cost Engineering
− Revenue
− Expense
Risk Management
Risk Management
100
80
Safety 60
40
Scope 20
Budget 0
Time
Quality
Scope
• Need by date
• Someone’s “guesstimate” of duration
To- do list
Calendar – “Day Planner”
Barchart – Gantt Chart
“Logic Based” Methods
− Precedence Diagram
Work activities are represented by the arrow, ends are only points in time.
If multiple activities are related but no effort is required “DUMMY” activities are used to show requirements.
Critical Path Methodology
Pour Set
Foundation Pump
Work activities are linked by relationships. The activity consumes time, the
relationship may or may not have additional time (called LAG).
ADM vs. PDM
ADM PDM
A C
1 3 5 A C
=
B D
2 4 6 B D
Logic Relationships
Hard
− REQUIRED sequence
− Physical Relationship between activities
− Successor is dependent on predecessor
Soft
− Optional or desired sequence
− Resource (Crew) Flow from location to location
− Availability of Multiple Crews
FS (finish to start) – First activity must be complete for the second activity to begin
SS (start to start) – The start of the second activity is related to the start of the first, usually
with a lag duration between them
FF (finish to finish) – The second activity cannot finish until the first activity finishes
SF (start to finish) – holds the finish of the second activity in relationship to the start of the
first
Activity Time Values
Adjustments
− Improve efficiency
− Recovery
− Manage change
Dispute / Claims Resolution