SECTION-A GENERAL
1. General
2. Site conditions
3. Units, Language and Form of all documents and drawings
4. Test and Inspection
5. Painting Procedure and Painting Color
6. Packing
7. Warranty
8. Indemnification and Limitation of Liability
9. Rules and Standards
10. Conflicting Requirement
11. Operation Mode
12. Modification
13. Out of Scope
14. Steam quality
15. Sub Vendor
SECTION-D GENERATOR
APPENDIX
-1-
A-1
SECTION-A
GENERAL
INDEX
1. General
2. Site conditions
3. Units, Language and Form of all documents and drawings
4. Test and Inspection
5. Painting Procedure and Painting Color
6. Packing
7. Warranty
8. Indemnification and Limitation of Liability
9. Rules and Standards
10. Conflicting Requirement
11. Operation Mode
12. Modification
13. Out of Scope
14. Steam quality
15. Sub Vendor
-2-
A-2
1. GENERAL
2. SITE CONDITIONS
*)Manufacture's Standards Form will be applied for All documents and drawings
All shop inspection and no-load mechanical running test are included as our standard.
No-load mechanical running test will be carried out in our factory according to
manufacturer's standard procedure before shipping to the site.
The test will be performed with live steam from our shop boiler and with our
shop lube oil unit.
Following test and inspection will be performed during the no-load mechanical
running test.
- Mechanical running test (at No-load for One hour)
- Vibration check
- Overspeed trip test
- Overspeed running test (120% of rated speed for 2 min.)
- Protection device check
Test and inspection for aux. equipment such as lube oil unit, reduction gear, control
panel and etc. will be carried out separately as per manufacturer's standard procedure.
Witness inspection and test will be included as per test and inspection plan.
Test report will be submitted as final.
6. PACKING
All the equipment and its accessories shall be packed in accordance
with our standard practice for export shipment, so as to avoid any loss
or damage during transportation and rough handling.
Shall the limit of transportation is exceeded, some parts on turbine baseplates will be
transported loosely. Reassembling of those parts on site shall be performed by customer.
Auxiliaries equipments (e.g: Lube oil, Reduction gear, Generator) may also be transported
in divisions. Assembilng shall be performed by customer.
(SNM will dispatch Technical Advisor)
-3-
A-3
7. WARRANTY
All equipments covered in this specification shall be guaranteed for operation
under normal operation conditions. The guaranteed covers defective design,
materials and workman ship only and shall not be applicable to damages
sustained through misuse of the equipment.
The covered defects shall be made good by us at no charge to the client.
But the guarantee period is for a period of eighteen(18) months after commissioning
or twenty four(24) months after the date of shipment, whichever comes earlier.
Warranty period will be commercial matter and confirmed at contract stage.
Generator : IEC
Internal piping confined with : JIS
turbine baseplate & oil piping
Flange Type : ASME B16.5 except for Special Flange
Panel : Mfr.'s standard / IP20
-4-
A-4
1) Minutes of Meeting
2) Performance Generat or Data Sheet (Performance Table)
3) This TECHNICAL SPECIFICATION with Clarifications
4) International Codes & standards
5) Project Specification
2) Turbine Operation
a) Start Up of Aux. Equipment : Manual (Local, Turbine Panel)
b) Start Up of Steam Turbine : Manual (Turbine Panel)
c) Stop of Steam Turbine : Manual (Turbine Panel)
d) Stop of Aux. Equipment : Manual (Local, Turbine Panel)
-5-
A-5
12. MODIFICATION
The price quoted (separately) is for equipment as specified herein. Any deviation
from this specification may require a price modification, upwards or downwards.
13. OUT OF SCOPE
This proposal includes only the items specified-herein and specifically excludes the
following equipments, materials and work which are to be provided by the purchaser.
1. Civil works
2. Equipment foundation and it's mechanical strength calculation (Foundation planning drawing will be submitted by SNM.)
3. Embedded parts in foundation(s) of equipment (Necessary information drawing and Loading data will be submitted by SNM)
(SNM will provide the required information. SNM provide anchor bolts, nuts, shim plate etc.
Embedded pipe information will be provied by SNM.)
4. Erection and commissioning of equipment
5. Welding rods, paints and other material for the installation work and start- up operation
6. Maintenance stair case, ladder, stage, hand rail and etc. (SNM will provide the basic information drawings.)
7. Earthing device (Earthing device location and information drawing (if any) will be provided by SNM.)
8. Air conditioning equipment
9. Fire extinguishing system
10. Compressed air supply system
11. Overhead traveling crane. (for erection and/or maintenance)
12. Consumable materials, such as flushing oil, lubrication oil, waste, etc.
13. Piping and valve not specified in this specification
14. Wiring materials and works for electricity and instrument not specified this specification
15. All other equipment, materials and works not specified in this specification
(SNM will provide the information such as cable size & material from MCC to J/B or others point.)
16. Center Panel
17. DCS system
18. HP & LP feedwater heaters, Deaerator, BFWP(s), if any
19. Turbine By-pass station (PRDS) or PRDS for process steam and for Deaerator, if any
20. Flow measuring device for steam & cooling water
21. Isolation valves (except Turbine emergency stop valve) for all steam & cooling water line
22. Inlet steam, extraction(if any), exhaust steam piping
23. Cooling water supply system with piping
24. Instruments air and service air tubing/piping
25. Companion flange(with fasteners) at all terminal points
26. Power cable between generator and circuit breaker panel
27. Inter-connecting piping(s) between turbine and gland condenser, if any
28. Inter-connecting piping(s) between condenser and air ejector/condenser, if any
29. Inter-connecting piping(s) between condenser and hotwell level control valve ,if any
(SNM will provide the P&ID with attention items information for connecting size & rating.)
30. Inter-connecting wiring between local and local panel, remote panels(if any)
31. DC battery and Battery Charger
32. UPS system
33. AC motor starter (MCC)
34. Expansion Joint for inlet steam line, if any
35. Drain separator for inlet steam line, if any
36. Drain tank and drain transfer pump for exhaust steam line, if any
37. Flow measuring device(inlet steam, extraction(if any)
38. Safety valve for extraction steam line (Design condition will be provided by SNM in tapping point.)
-6-
A-6
14. STEAM QUALITY
Deposits on the turbine blading due to steam contamination may bring about
thermodynamical and mechanical disturbances. Moreover, if chlorides are
involved under certain circumstances blade fractures might occur.
Corrosion depending strain, caused by aggressive deposites, affects above
all in the state of commencing steam wetness the alternating bending strength
of the blade material.
These recommendations concerning the steam quality are in line with the
guide lines for continuous turbine operation issued by the VGB(Vereinigung
der Groβkesselbetreiber in Deutschland).
To avoid misunderstandings we point out that even full compliance with the
guide lines does not guarantee absolutely safe a depositfree turbine.
The steam contaminations and their portion of mixture represent the most
essential factor as to precipitation, however, this problem is not fully
solved up to now. If there is a chance to improve the steam cleanliness in
comparison with the guide lines, make use of it.
Supervision
Continuous monitoring of the water/steam system by means of recording instru-
ments is recommended for the electrical conductivity at 25℃ and
for the Silica content. The monitoring instruments should be provided on
the inlet steam or on the exhaust steam side.
All sub vendors(world wide) must complete screening and selection process
conducted by our Quality Management System.
-7-
B-1
SECTION - B
INDEX
-8-
B-2
1-2. Output :
-9-
B-3-1
PERFORMANCE TABLE
REMARKS
2. Uncertainty value to be applied for performance test result as per IEC 953-Ⅱ.
- 10 -
B-3-2
- 11 -
B-3-3
- 12 -
B-4
- 13 -
B-5
(Kingsbury type)
Quantity : One (1) set / one unit
(Double side)
NEMA CLASS : D
- 14 -
B-6
Turbine casing and emergency stop valve are insulated and jacketed
to maintain jacket temperature below 60 deg C.
1-17. Coupling :
Type
for Steam turbine : Baseplate
for Reduction gear : Soleplate
for Generator : Soleplate
Reservoir is furnished with oil level indicator, drain valve, oil charging nozzle,
gas vent fan .
Equipments, such as oil pumps, oil filters and etc.,
will be mounted on top of oil reservoir.
- 15 -
B-7
- 16 -
B-8
- 17 -
B-9
2. MATERIAL LIST
- 18 -
B-10
2-9. Piping
- 19 -
B-11
3. INSTRUMENTATION
3-1. General
a) Specification : Non-Hazardous
Indoor
*with air conditioner (Design Temp. : 10 to 40 deg.C [IEC/JEC])
b) Supply item : Instruments
PLC(SIEMENS MAKE)
CPU : Redundant
Power supply : Redundant
Communication : Redundant (MODBUS RS-485)
I/O : Single
- 20 -
B-12
3-3. Instruments Arrangement
EXTRACTION
NON-RETURN VALVE
POSITION : ZSx2 LAMP ZI
OIL RESERVOIR :
LEVEL LS LG L COM
TEMPERATURE TG
OIL COOLER :
WATER INLET TEMPERATURE TG
WATER OUTLET TEMPERATURE TG
LUBE OIL :
PRESSURE PT PI PI L L COM
PS LL LL DC
TEMPERATURE TE TI TI H H COM
- 21 -
B-13
TRIP OIL :
PRESSURE PG
TURBINE :
Governor 505 XT
BEARING MATAL TEMP. TE(X4) TI(X4) TI(X4) H H HH HH COM DC
SPEED (FROM GOVERNOR) SE(x2) SI COM
VIBRATION (SHAFT) VE(x2) VI(x2) VI(x2) H H HH HH COM DC
AXIAL DISPLACEMENT ZE(x1) ZI(x1) ZI(x1) H H HH HH COM DC
*) Trip signal is connected as hard wire, alarm etc. is connected as remote (communication signal).
- 22 -
B-14
ABBREVIATION
PT : PRESSURE TRANSMITTER
PI : PRESSURE INDICATOR
TI : TEMPERATURE INDICATOR
PS : PRESSURE SWITCH
ZS : LIMIT SWITCH
SE : SPEED SENSOR
VE : VIBRATION PROBE
ZE : POSITION PROBE
SI : SPEED INDICATOR
VI : VIBRATION INDICATOR
ZI : POSITION INDICATOR
● : SUPPLIED BY SNM
DC : DRY CONTACT
COM : COMMUNICATION
- 23 -
B-15
- 24 -
B-16
- 25 -
B-17
- 26 -
C-1
SECTION - C
CONDENSING SYSTEM
INDEX
- 27 -
C-2
- 28 -
C-3
1-5. Material
- 29 -
C-4
- 30 -
C-5
2-5. Material
Condenser
Shell side : 0.88 bar.G & Full vacuum
: 120 deg C
Tube side : 12 bar.G
: 80 deg C
Ejector
Inlet steam section : 16.0 bar.G
: 450 deg C
Air suction section : 0.88 bar.G & Full vacuum
: 120 deg C
- 31 -
C-6
3-4. Drive
Electrical supply
Voltage : AC 400 V
Cycle : 50 Hz
Phase : 3
Pole : 2
Speed : App. 3000 rpm
Output 37 Kw
Remarks
*1 LCV outlet pressure (Terminal point) : App.6 bar.G
Pressure drop *To be confirmed by customer
Piping (between CP and LCV) : (App.0.5) bar
*To be confirmed by customer
Level Control Valve : App.0.5 bar
Tube of air ejector condenser : App.0.5 bar
Tube of gland steam condenser : App.0.5 bar
- 32 -
C-7
3-5. Material
- 33 -
D-1
SECTION - D
GENERATOR
INDEX
- 34 -
E-1
SECTION - E
UTILITY LIST
- 35 -
E-2
4. ELECTRIC SUPPLY
- 36 -
E-3
- 37 -
EXPECTED PERFORMANCE CURVE
REF.NO. E18-3516-01 ITEM No.
MFG.NO. MCL-8E-11940 DRIVEN MACHINE GENERATOR
RATED OUTPUT 19400 (KW) TURBINE MODEL C7-R11-ER
RATED SPEED 7016/1500 (RPM)
STEAM CONDITION
INLET STEAM PRESSURE NOR. 70 (Bar.G)
TEMPERATURE NOR. 480 (Deg.C)
EXHAUST STEAM PRESSURE 0.1 (BarA)
EXTRACTION STEAM PRESS. NOR. 13 (Bar.G)
OPERATING CONDITIONS
OPERATING POINT OUTPUT SPEED INLET FLOW EXT. FLOW SYMBOL
(KW) (RPM) (T/Hr) (T/Hr)
Case 1-1 (Rated) 19400 7016/1500 123.7 80 ●
Case 2-1 9350 7016/1500 90.9 80 ◆
Case 2-6 (Max. ext.) 11570 7016/1500 117 110 ■
90
Ext. 60 t/h
80
70
Ext. 40 t/h
60
50
Ext. 20 t/h
(Minimun)
40
Ext. 0 t/h
30
20
10
0
0 2000 4000 6000 8000 10000 12000 14000 16000 18000 19400
OUTPUT AT GENERATOR TERMINAL ( KW )
- NOTE -
Turbine cannot operate continuously in hatched area
because this area is chattering range of QCNRV.
- 38 -