Vous êtes sur la page 1sur 21

Add project/client logo

RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement and Risk Assessment for


Installation of Electrical Containment &
Wiring/Cable Pulling, at AMC Connectivity
Corridors & Concourse Bridge Project , Maryah
island,
ABUDHABI
Project No-M- 1467

Document Ref No: MCL-ME-A-MST-MSS-004

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 1 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Project name AMC Connectivity Corridors & Concourse Bridge Project Project No M1467
Main Contractor McLaren Construction Ltd. Document No MCL-ME-A-MST-MSS-004
Title/Task Installation of Electrical Containment & Wiring Revision No 00
Document
Date of issue 21/02/2019 Prepared By
Syed Faisal
Duration of
Proposed start date 03/03/2019 task 60 DAYS

Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken:
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures:
Section G McLaren Site Specific HSE Safety Induction:
Section H Welfare facilities:
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used.
Section L Communication/Toolbox Talks/Training Requirements:
Section M Works Permits
Section N Environmental and Waste Management:
Section O Programme for the Works:
Section P Housekeeping and Storage:
Section Q Hygiene and cleanliness
Section R Working at Height
Section S Occupational Health
Section T Sequence of Works/Activities

Appendices

Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Risk Assessment
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 2 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section A - Register of Revisions

Revision Date Reason for Amendment Amended By Signature Has this amendment been briefed
No (Name) to the operatives involved and have
the operatives signed the register.

This method statement has been prepared in conjunction with the following documents;
1. OSHAD regulation and requirements
2. OHSAD- Code of Practices, HSE Regulations, Technical Guidelines, Mechanisms
3. GR HSE Guidelines and Requirements
4. Federal Environmental Authority Law No 24/1999 and its supplements.
5. Federal Labour Law No 8
6. Articles (3,4,5,7) Local Law No 21/2005 (Waste Management)
7. McLaren SHE Procedures
8. McLaren’s site specific SHEQ Plan (including TMMS, SWMP, EPP).
9. McLaren’s Integrated Management System Policy Statement (IMS).

Section B- Scope of Works to be undertaken:


The work Describes the installation activity of electrical containment system and laying of wires and armoured
cables through the containment system.
The following Critical Hazards have been identified during the preparation of the scope of works, please refer to
the Risk Assessments within Appendix D.

1. Manual Handling Injuries


2. Slip Trips and Falls
3. working at Height/ Ladders
4. Fall from Height
5. Electrical Hazard
6. Struck by Objects
7. Use of ladders
8. Falling objects

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 3 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section C- Location of the Project


Location of the Project;
Our project is located is located AMC CONCOURSE BRIDGE in between Almaryha and Galleria Mall as marked
below.

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 4 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section D- Location of the Works to be Undertaken within the Project

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 5 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section E- Site Access/Egress and Access to the Work Zone

Entrance to the Site will be from Gate no 1 as per attached drawing.

Section F- Emergency Contacts Details and Procedures:


The following staff from both McLaren and Genfocus will be on site during the execution of the works and will be
responsible for managing the works;
Name Position Company Contact Details
Paul Carlin Operations Director McLaren 056-1054691
Luke Watson Project manager McLaren 052-1022402
Prabhu Srinivasulu Construction Manager McLaren 050-9709963
Joby John HSE Manager (First Aider) McLaren 050-6372060
Evangeline Huerto First Aider McLaren 056-1852727
Jijo Mathew Safety Advisor/First Aider McLaren 055-2152903
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 6 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Ramil Magano QA/QC Engineer (Fire marshal) McLaren 050-2923058


Biju MEP Engineer McLaren 056-8059139
Syed Faisal Ahmed Project Manager Genfocus 056-5465814
Anu Baby Project Engineer Genfocus 0565465807
Prabir Kumar Chattarjee Safety Officer Genfocus 0547937312
Prabir Kumar Chattarjee First Aider Genfocus 0547937312

In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly Point,
which is indicated on the site logistics drawing, as indicated by the symbol below. Where the registers will be
checked to ensure that no one is un-accounted. No one will be allowed to leave the assembly point until the
Emergency response Controller confirms that it is safe to do so.

1 Assembly Point No-01 (TBA)


2 Assembly Point No-02 (TBA)

Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available either in the
Induction/First Aid Room or in the Main Office.
McLaren: (details of First Aiders) Subcontractors(Details of First Aiders )
Joby John- 050-6372060 Syed Faisal Ahmed 056-5465814
Jijo Mathew 055-2152903

Please see below the Emergency contact details

Authority/Company Contact Telephone No.


McLaren Construction Ltd 04-3417964
Police 999
Ambulance 997
GR Emergency No 058-2864950
AMC Emergency No 056-7459621

Section G- McLaren Site Specific HSE Safety Induction:


Prior to any works taking place, all Operatives arriving at AMC project will be required to undergo a
Multiplex/Gulf Related safety induction followed by McLaren Site Safety induction, which will be held in the
induction room, by McLaren’s HSE Representative or other designated person. Once the operatives have received
the site specific safety induction, they then will be briefed on the contents of this RAMS, by their respective Site
Supervisor, from which they will then be required a sign a RAMS Briefing Register (SAF019 UAE) confirming that
they have been briefed and that they fully understand the RAMS and what is expected from them during the
execution of the site works. The Operatives will also be briefed on the Emergency and Security Procedures for the
project, which is also a part of site safety induction programme.
Any operative who will be operating any plant and equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider, to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Section H- Welfare facilities:
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 7 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Drinking Water-
Clean drinking water will be provided on site (as per approved Logistics plan) and all operatives are to ensure they
take on enough fluids throughout the day.

Comply with Summer Working Requirements .

Rest areas and toilet-


Rest area and toilets are being provided at site and located as per AMC logistics layout plan

Section I- Personal Protective Equipment (PPE)


The Following Personal Protective Equipment must be worn/be available during the execution of the works
activities

Type of PPE Required Yes No


Safety Helmet (as per standards) Yes
Safety Footwear (as per standards) Yes
Eye protection (as per standards) Yes
Gloves (as per standards) Yes
Hi- viz Vests Yes
Overalls (for operatives only) Yes
Ear protection Yes
Face Respirator No
Body Harness Yes
Respiratory masks Yes
Others (other specific requirements)
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 8 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section J- Plant and Equipment to be Used


It is anticipated that the following hand tool will be used during the execution of the works; other items will also
be identified on the schedule below;

 Various hand tools


 Tools (Drilling machines, hammer,etc)
 Grinders
 Manual Lifting Jacks and spindle for placing cable drums
 Multi-meter. (valid calibration certificate will be provided before use)
 Rubber Padded Ladders
 Cable Pulling Rollers

*Note: All relevant competency certificates (as per OHSAD /GR requirements) to be submitted to HSE
Manager/Eng./Advisor prior to start of any activity.

(Below schedule to be completed by subcontractor)


Type of Plant/Equipment to be Used Yes No Type of Plant/Equipment to be Used Yes No
Lifting No Cradle No
Mechanical hoist No Excavation shoring No
Mobile elevating working platform No Hand tools Yes
Ladder Yes Electrical tools Yes
Hoist No CAT & Gen Set No
Test Equipment No Ventilation/Extraction Equip No
Task Lighting Yes Pump No
Tubular Scaffolding Yes Lifting slings/chains No
Mobile scaffolds Yes Mechanical plant No
Podium Scaffold No Others:
Section K- Materials To be used.
The following Materials will be utilised during the execution of the works, the Material Data sheets being
provided, which will allow the relevant COSHH assessments to be carried out; (See Appendix C)

Item Material Description Has MSDS been Has the COSHH


provided and Assessment sheet been
attached? completed and attached?
1 Cable Tray/Trunking N/A N/A
2 GI/PVC Conduits N/A N/A
3 Wires and Armoured cables N/A N/A

Section L- Communication/Tool Box Talks/Training Requirements:

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 9 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Once the RAMS has been briefed to the workforce, we will also hold Tool Box Talk relative to the work activities
being carried out, these will be conducted by the HSE team, in conjunction with the relevant site supervisors, this
will ensure that the message gets across to the workforce, in their own language, thus avoiding any
misinterpretation of the RAMS/Toolbox Talk.

During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed(Date)
1 3rd party training for operative of plant and N/A
equipment
2 3rd party competency card for operators N/A
3 Riggers, Banksman N/A
4 First aid training Yes
5 Scaffolding inspection and erection Yes
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.

Section M- Works Permits


The following works permits will be required during the execution of the Works;

Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren 
5 Permit to Work in Ceiling Void McLaren 
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps McLaren 
8 Permit to Work at Height McLaren 
9 Permit to Work – Electrical above 110V McLaren 
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Existing MEP Service Isolation McLaren
Any other permits if required to be added

Section N- Environmental and Waste Management:


During the execution of the project, waste will accumulate. Skips will be provided by McLaren and will be
required to put all waste in the skips provided. All waste will be segregated for recycling as per below sequence
1. Metal
2. Plastic
3. General waste
4. Concrete waste
5. Food waste
6. Hazardous waste
7. Wood Waste
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 10 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Due to the nature of the works and the actual conditions of the present site, airborne dust will be minimal,
however where necessary the area affected by the installation of the temporary works, the dust will be
suppressed by spraying water.
Drip trays to be placed under plant and generator to catch any excess oil. Approved Waste Collection Contractor
will then remove excess oil from site in oil containers and sent back to store for collection.
Section O- Programme for the Works.
The works will commence on 03/03/2019 For a duration of 4 weeks, as the works are scheduled, there will be
requirement for additional lighting in the working area.
However if Night shift starts, adequate task lighting will be required.
Section P- Housekeeping and Storage:
Housekeeping will be carried out as and when required and storage of materials will be in an agreed location (as
per approved site logistics plan) within the segregated area and as agreed in subcontractor prestart meeting. The
subcontractor will remove from site.
Section Q- Hygiene and cleanliness:
Hygiene and cleanliness are the upmost requirements for the project. All works carried out with AMC Projects
Procedures and requirements.

Section R- Working at Height


During the preparation of the RAMS, the following activities for working at height have been identified and have
been addressed within the risk assessments within Appendix D. (to be filled if applicable to your works)

Item Activity Risk Assessment Reference


1 Installation of GI/PVC Conduits Refer attached risk assessment
2 Installation of Cable Tray/Trunking Refer attached risk assessment
Pulling of wires and Cables over Refer attached risk assessment
3
containment

Section S- Occupational Health


During the preparation of the RAMS, the following Occupational Health items have been reviewed and addressed
within this Method Statement.
Item Description of OH Item Preventative Measures, (see also within the Risk Assessments)
1 Manual handling As much as possible Eliminate the need for manual handling by
using mechanical aid
2 Respiratory diseases Area will be watered to minimise dust and dust mask will be
provided
3 Falling from height Safety harness must be worn and hooked at secured place.
injuries/Fatalities Working at height training to be conducted by supervisor.
4 Cut and laceration injuries Wearing loose cloths shall be avoided and wearing proper
PPEs .

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 11 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section T- Sequence of Works/Activities


The works will be carried out in the following sequences;

1 RAMS to be briefed to all the operatives involved in the work.


2 STARRT card to be prepared by assessing the area of work prior starting the work.

3 Supervisor to ensure all operatives have received a McLaren and Multiplex site basic induction
4 Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.
5 Supervisor to ensure that the site is clean and ready to start the work.
6 Supervisor to ensure adequate tools are provided and advise Site manager if more tools are needed.
7 Works will be carried out in such a way as to minimize the impact of the work.
INSTALLATION OF CABLE TRAY/ TRUNKING:
Tray/trunking sizes are based on the local authority requirements and as per the shop drawings approval
1
by consultant.
Electrical Supervisors shall use consultant approved shop drawings for marking the route of the
2
tray/trunking.
Ladders and scaffoldings shall be placed along the tray/trunking route at required heights, as per the
3 requirements/locations. The same shall be checked by the safety officer before starting the installation
works.
Technicians shall perform drilling operations for fixing 10mm unifix bolts at wall/ceiling for the purpose of
4 hanging the 10mm thread rods. A pair of thread rods and a 41x41mm unistrut channel forms a support for
cable trunking/tray hung from ceiling or from beam clamps.
5 Approximately 1.50M uniform distance shall be maintained between supports.
6 Thread rods shall be placed at a distance of 50mm on both sides of tray/trunking.
Tray/Trunking shall be cut and grinded as per the site requirements using cutting wheels or hacksaw
7
blades and grinders.
The bottom support of tray/trunking shall be of 41x41mm unistrut channel and is hanged using thread
8 rods using Hex nuts and washers. The length of this unistrut shall be 150mm greater than the size of
trunking so as to maintain 75mm distance on both sides.
Tray/trunking is fixed permanently to the 41x 41mm unistrut using spring nuts of suitable sizes as per the
9
requirements.
10 Typical supporting details with sections shall be provided in the Shop Drawings.
The location of the supports shall be marked on ceiling, walls and if the supports are to be installed on
11
the structural beams, suitable clamps shall be used to clamp the tread rods, as per the site conditions.
12 Earth tags shall be provided at the joints of two tray/trunkings.
Proper labelling shall be done after installation of tray/trunking, indicating the service which it has been
13
provided for.
The ends and other finished ends of tray/trunking shall be provided with bushes such that cables/wires
14 do not sustain damage at the time of installation.

INSTALLATION OF GI /PVC CONDUITS:


Electrical supervisor shall identify the start and end points of each circuits by seeing the approved shop
1
drawings, in order to lay the GI/PVC conduits.
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 12 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

2 Supervisor shall mark the electrical points on the slab/wall by using approved shop drawings.
The route of GI/PVC conduits shall be checked to make sure that it is free from debris and any other
3
services.
4 Solvents shall be used for joining PVC conduits and couplers while installing PVC conduits.
Size of electrical conduits shall be minimum 20mm dia for lighting circuits and 25mm for other electrical
5
power circuits.
6 Conduit shall be installed with a maximum of two 90º bends or three 120º bends
The minimum internal radius of any bend or elbow fitting in a conduit shall be 2.5 times the diameter of
7
the conduit.
Technicians shall make holes on wall/ceiling using drilling machines for fixing rawal plugs inside these
8 holes. Saddles of appropriate sizes shall be fixed to the rawal plugs using screws. Saddles shall be fixed at
every one meter span.
GI/PVC conduits shall not be laid below water services, crossing vents and disturbing any wall/slab
9
openings.
Where a PVC conduit is installed within a wall, floor or ceiling it must be at a minimum depth of 50 mm
10
from the surface.
11 Couplers and circular boxes of suitable sizes shall be used to join the conduits.
Where conduits are connected to GI trunking or Distribution Boards conduits shall be connected using
12
threaded adaptors.
GI conduits to be used for all external/exposed locations. Earthing to be done for GI conduits and
13
checked for continuity.
Conduits shall be run neatly either horizontal or vertical. Overlapping of conduits shall be avoided as
14
much as possible.
In case of concrete pouring, the installation of PVC conduits shall be inspected by consultant and
15
approval to be obtained for the same.
At the time of concrete pouring, electricians shall be provided for taking care of conduits to avoid any
16
damage or dislocation.
WIRING:
All the materials intended for wiring shall be obtained approval from consultant prior to the starting if
1
activity.
Prior to the installation of wires/cables in trunking or conduits the entire containment system shall be
2 checked to ensure that it is free from any sharp edges which may damage the wires at the time of
pulling.
Before pulling the wires/cables, additional care to be taken to make sure that the wires/ cables are not
3
damaged.
Electrical supervisors shall refer to the approved load schedules and Lighting/Power layouts for
4
identifying the colour/size of wires to be pulled for any particular circuits.
Light switches shall be installed at a height of 1.30M from FFL and sockets at 300MM or 450MM from
5
FFL.
6 Rating of switches and sockets shall be as per the authority requirements and approved shop drawings.
Before Cable pulling commences, the actual length of the route will be measured and checked to ensure
7
adequacy of provided cable length.
Cable/Wire rolls or drums to be placed in a safe position, such that they are free to rotate at the time of
8
pulling.
Where wires are to be pulled in trunking, each circuits shall be segregated by using cable ties at every 2m
9
span.
Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 13 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

10 At expansion joints, adequate slack shall be left for cables/wires.


Where conduits are installed for pulling wires, a draw wire/pulling wire shall be provided between each
11
draw in points.
Maximum number of wires/cables that can be pulled through a conduit of particular diameters, shall be
12
as per ADDC requirements.
A slack of at least 200mm of wire will be left at each electrical outlet, and at the DBs side 800mm for
13
termination purpose.
About a length of 1 meter in DB’s and 2 meters in SMDB’s shall be left for cables for glanding and
14
termination purposes.
The ends of the wires and cables shall be marked with proper identification for testing and connection
15
purposes.
After completion of the activity, all the waste materials and debris shall be removed and materials shall
16 be shifted back to store.

ARMOURED CABLE PULLING OVER CABLE TRAY:


1 Suitable place shall be identified to place the cable drums, jack and spindle.
2 Cable drum shall be placed on jack and spindle arrangement to ensure free rotation of the drum.
Cable rollers shall be placed below cables for pulling over long distances. Standoff rollers to be used at
3
acute bends such that cable are pulled with minimum effort.
Cables shall be pulled by using rope at an end and care to be taken to prevent the damage for cables as
4
well as containment system.
Supervisors shall check the size of the cables on approved Electrical schematic diagrams /Load schedules,
5
prior to the commencement of the work.
Relevant earth cables also to be pulled along with the main cables and shall be run adjacent to the main
6
cables throughout the length. (Sizes as mentioned in approved shop drawings).
Care shall be taken at bending locations that minimum bending radius for cables shall be maintained as
7
per the manufacturer recommendations.
8 A slack of 800mm shall be kept at the distribution board side for the purpose of termination.
9 Cables shall be secured to the containment system by using cable ties at regular intervals.
10 Cables shall be caped and sealed at both ends after pulling until glanding and termination is done.
Glanding and termination shall be carried out with approved materials – glands, lugs, cable ties(for
11
dressing of cables inside DBs) and proper crimping tools.
Cables shall be identified at both ends mentioning size, type and where it is fed, using appropriate labels
12
as per the specifications at 50mm below the gland.

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 14 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX A

Site Logistics Plan

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 15 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX B

CRISIS PLAN

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 16 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

CRISIS PLAN

1. Upon an incident, being discovered the first member of McLaren’s staff or the site operative
discovering the incident shall inform the Project Manager and Site HSE team through AMC Project
emergency Contact No-056-7459621.

2. Both the HSE Engineer/advisor and the First Aider are to attend the scene with their mobile. The
project Manager or authorised person waits in office ready to contact relevant emergency
services.

3. Both the HSE Engineer/advisor and the first Aider are to assess the situation and put in place the
relevant systems to end/deal with the emergency.

4. Both the HSE Engineer/advisor and the first Aider are to ensure all trades are gathered at the
assembly point and liaise with supervisor to account for all operatives - no person should leave
site.

5. Either the HSE Engineer/advisor or the first Aider phones the project Manager or site receptionist
and informs him/her of which emergency services are required.

6. The Project Manager calls all relevant McLaren staff.

7. Both the HSE Engineer/advisor and the first Aider waits for the emergency services at scene.

8. Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
the HSE/Client’s Safety Advisor/QHSE Manager/McLaren’s operations Director.

9. Both the HSE Engineer/advisor and the first Aider keep trades informed of the situation and
releases trades to return to work or leave site only when emergency services or The Project
Manager instruct that it is safe to do so, and all names of witnesses are recorded.

10. Project Manager or Construction Manager are to arrange for photographs of the scene to be
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
11. photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 17 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX C

COSHH ASSESSMENTS AND MSDS

(Not Applicable)

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 18 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX- D

RISK ASSESSMENTS

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 19 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX-E

TECHNICAL INFORMATION

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 20 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement Title Installation of Electrical Containment &Wiring/Cable Pullling Doc Ref No: MCL-ME-A-MST-MSS-004
Project Location: AMC Connectivity Corridors & Concourse Bridge Project Revision No: 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 21 of 21 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET

Vous aimerez peut-être aussi