Freeze design
Financial planning
Eligibility
• Complete credentials of the Bidder with respect to their financial and technical
capabilities to satisfy the “Qualification Criteria” as set out above.
• The jobs undertaken by the Bidder and executed during the last three
years, which satisfy the above “Qualification Criteria” along with brief scope of
work. Certificates of satisfactory project completion also need to be provided.
• List of litigation pending by/against the Company / Firms along with value.
• Details of own Plant and Machinery, Tools and tackles for Construction,
Infrastructure facilities.
• Organization Chart and details of Personnel.
• Audited financial statements / Annual reports for the past three years.
• Solvency Certificate from reputed banks.
Bid process Management
Type of contract
(QCBS/Sole
sourcing/Lump Financial bids Financial
sum/cost +fixed opened for
fee contract,etc qualified bidders Evaluation
Prepration of bid
documents (General Technical Negotiation with
conditions of Evaluation bidders
contract, BoQ etc)
Submission of
Clarification to pre- report to tender
Pre-Bid Meeting Award of Work
bid queries committee for
approval
Bid process Management
Notice Inviting Submission of
Expression of Technical
Bids by
Interest Evaluation
contractor
Evaluation of
Expression of Financial bids
Clarification to
Interest opened for Award of Work
pre-bid queries
qualified bidders
Package Submission of
wise/Location Financial report to tender
wise tender and Pre-Bid Meeting
Evaluation committee for
type of contract approval
Prepration of bid
documents
(General Request to bid to Negotiation with
Final Pricing
conditions of sucessful bidders bidders
contract, BoQ
etc)
General conditions of contract.
Condition Clause
Contractors submission with tender document
Bid Processing fee Rs. 10,000 + service tax (Not refundable)
EMD 1% of estimated value (Converted to PBG for successful contractor,
returned to other non-successful bids)
For Successful Contractor
Performance Bank 5% of contract value (will be returned to the contractor after
Guarantee defect liability period (generally 1 year))
Retention amount 5% in all RA Bills
(50% released with final bill and 50% after 6 months of final bill):
Penalty Clause (for time 0.5% of the total value of work or part there of per week upto 5 %
delay) of total contract value
SPV to successful contractor
Mobilization Advance 10% Mobilization advance on Bank Guarantee. (will be
periodically deducted from RA Bills (10%))
Bid document - contents.
Book Contents
Compound wall
CPC / PPC
Cold Storage
Electrical works
STP / ETP
Tender process - timeline
Process Timeline