Académique Documents
Professionnel Documents
Culture Documents
allaboutpipelines.com/article/PipelineArticle
Introduction
Transportation of liquids by pipelines has been used for thousands of years. The first
major exploitation and commercialization using pipelines started 150 years ago, and the
building of long distance, large diameter pipelines was pioneered in the 1940’s (Hopkins,
2007). Today’s pipeline industry has originated from the oil business that brought
considerable amount of profit to the energy producers and pipeline operators. In
addition to be one of the most environment-friendly and the safest means for oil and
natural gas transportation, pipelines have integrated in the components of national
security.
Pipelines are lifelines of the global oil/gas industry, providing most convenient, eco-
friendly, efficient and economical mode of transportation for oil and natural gas from
upstream production to downstream refineries, power station, industries, domestic
consumers and markets, crossing nations, oceans and continents. Pipelines are
underground highways which may involve higher cost initially but in the longer run
pipelines provide the most economic, safe and reliable means to transport products
from one place to another place compared to rail, road and marine transportations.
Pipelines can be broadly bifurcated into two types based on location of installation i.e.:
1/13
Onshore Pipelines
It covers all inland cross country pipelines which are not in offshore areas.
It includes the main pipelines, spur lines and feeder lines, crossings/other
features en route, associated despatch terminals, sectionalizing valve
station, compressor stations, pump stations, intermediate terminals and
receiving terminal facilities. The upstream and downstream handling
storage and process facilities are excluded from the scope of onshore
pipeline systems.
It covers all pipelines in offshore areas beyond the line of ordinary high
water, along that portion of the coast that is in direct contact with the open
seas and beyond the line marking the seaward limit of inland coastal waters.
It includes trunk lines, inter-field/ inter platform lines, lines from offshore
terminal to Land Fall Point, crossings/ other features en-route, associated
risers, subsea PLEMs, subsea isolation valves (SSIV)/ laterals and termination
at land fall point as applicable. The upstream and downstream facilities at
terminal ends are excluded from the scope of offshore pipelines.
This article introduces the key topics contained in the lifecycle of pipeline, such as pipeline
design, procurement, installation & testing and a fundamental basic understanding of
2/13
pipelines.
The design & engineering stage of the pipeline can be fragmented broadly into four
major phases i.e.:
3/13
Fig. Phases of Engineering and Design
[1] CONCEPTUALIZATION
– Seismic Design
– On-bottom Stability
– Valves
– Insulating joints
– Assorted Pipes
– Equipment Layouts
– Alignment Sheets
– Clamps Drawings
Following activities are required to be carried out for construction of onshore pipelines:
6/13
Topographical survey & soil
investigation
Pegging
Bench Marking
Pipeline Centerline marking
Profile
Crossing identification such as
water bodies, railway lines, roads
etc.
Trenching
Trenching by excavator
Separation of arable soil in fertile
land
Trenching by blasting / rock
breaker in rocky area
Protection of underground
facilities
Stringing
Pipe Handling and
Transportation on trailors at site
Pipe placement on sand bags/
wooden blocks
7/13
Cold Field Bending
Classification of location for
bend installation
Bend Radius (R), equals to
– 40D (For pipe dia. 18” & above)
Field Welding
Weld procedure qualification
Welder qualification
Fit-up & pre-heating
Root pass
Hot pass
Filling passes
Capping
8/13
Lowering
Trench inspection
Pre-padding
Holiday testing
Lowering
Cover check
Backfilling
OFC installation
Post-padding
Installation of warning mat
Backfilling
Crowning
Hydrostatic Testing
Air cleaning
Gauging and Pigging
Water-filling
Thermal stabilization
Pressure holding
Acceptance
Pre-commissioning &
Commissioning
De-watering
Swabbing
Drying
Nitrogen/ Inert gas purging
Fluid charging
Following activities are required to be carried out for construction of offshore pipelines:
9/13
Pre-construction Survey
Verification of pre-engineering
survey data
Firming-up of seabed
preparation and intervention
methodologies
Identification of as laid position
of any stub-ends and their
extremities
Equipemnts: Sub-bottom profiler, echo sounder, side scan SONAR, magnetometer
Trenching/ Dredging
Mechanical amphibian dredger
for shore approach
Trenching sledge/ jetting
dredger for post trenching in
deeper waters
Rock blasting in rocky seabed
10/13
Welding
Weld procedure qualification
Welder qualification
Pipe end preparation, fit-up &
pre-heating
Root pass/ Hot pass
Filling passes
Capping
Non-destructive testing
Visual inspection
100 % NDT by Automatic
Ultrasonic Testing
Pipelaying
Conventional pipelay methods are:
S-Lay (for shallow waters) – rigid
pipes
J-Lay (for ultra deep waters) -
rigid pipes
Reel-Lay (for rigid/flexible
pipelines)
11/13
Shore Pull
Length of shore pull based on
minimum barge draft
requirements
Firming up the requirement of
number of buoyancy unit and
pulling force
Preparation of winch foundation
and Anchor block
Preparation of pipe string on barge
Pipeline Crossing
Analysis for acceptable pipeline
configuration above existing
pipeline
Placement of pipe supports at
designated locations
Laying of new pipeline on the pipe
supports
Back-filling of trench
Engineered backfilling or
backfilling the excavated
material in shore approach area
Backfilling is performed using
Split Hopper Barge
12/13
Post-construction survey
As-laid survey
Free span survey (extent of
unsupported span)
Checking of depth of cover
Identification of pipeline
alignment; Diving survey
13/13