Académique Documents
Professionnel Documents
Culture Documents
Abstract
The Cathedral of Noto was damaged after the earthquake that hit Sicily in 1990. Soon after the event, cracks appeared on the
domes of the lateral naves, and also on the pillars. In 1992 some provisional work had been carried out in view of confining the
pillars of the central nave that were damaged. Some pictures made after the earthquake also show clearly the presence of moisture
rise on the pillars and walls. A sudden collapse due to the damages was probably not expected, so that no other measures were
taken to better strengthen and repair the structures. Only after the collapse of the Civic Tower in Pavia (1989) and the following
research (Masonry Int J 6 (1992) 11, Second International Conference RILEM on Rehabilitation of Structures, Highett, Australia
(1998) 542), it was clearly shown that in case of high stresses on low-strength masonry an existing damage can slowly lead to
partial or total collapse of the structure over a long time. It seems a confirmation of this long-term behaviour of the structures
that the Cathedral collapse took place in 1996, 6 years after the earthquake, which had certainly caused high damages to the
structure.
䊚 2003 Elsevier Ltd. All rights reserved.
0950-0618/03/$ - see front matter 䊚 2003 Elsevier Ltd. All rights reserved.
doi:10.1016/S0950-0618(03)00057-6
544 L. Binda et al. / Construction and Building Materials 17 (2003) 543–555
Fig. 4. Longitudinal section of the Cathedral with the left order of the
pillars of the central nave.
Fig. 2. The right pillars of the central nave before the collapse: there
is clear evidence of moisture presence at the base of the pillars (photo
Coll. Arch. P. Giannone). Fig. 5. Longitudinal section with the remaining of the left pillars.
L. Binda et al. / Construction and Building Materials 17 (2003) 543–555 545
Fig. 8. Sample no. 2: view from the top of the foundation soil with
the foundation masonry of the transept.
Fig. 7. (a) Foundation of pillar E (sample no. 6). Survey of the foundation. (b) View from the top of the foundation of pillar E (sample no. 6).
546 L. Binda et al. / Construction and Building Materials 17 (2003) 543–555
Fig. 9. Survey of the prospect of pillar C: (a) graphical restitution; (b) photo.
Fig. 10. Horizontal section of pillar C: (a) graphical restitution; (b) photo.
3.2. Survey of the masonry sections and of the wall appeared very weak and dusty surrounded by an external
connections leaf made with regular blocks of calcarenite for the base
of the pillar (up to 1.50 m) and of a sort of ‘travertine’
The layer-by-layer removal of the components of the in the upper part. The connections between the external
collapsed pillars allowed to understand the poor tech- and the internal leaves were missing (Fig. 10a and b)
nique of construction used (Fig. 9a and b). Layers of and the ‘travertine’ leaf was highly porous with large
large rounded river stones were found in the core of the voids. The poor technique of construction and the wrong
elements, with thick mortar joints, where the mortar choice of the materials were probably the cause of early
damages to the pillars of the Cathedral even if the
evidence of damage appeared only after the 1990 earth-
quake. The walls were built in a similar way; neverthe-
less the internal part was made with smaller sharp stones
alternated with a slightly stronger mortar. In some way
this seems to be a better masonry (Fig. 11).
Also the buttresses of the highest part of the nave,
built successively to the Cathedral construction, were
made with a better technique, similar to the one of the
walls (Figs. 12 and 13).
Furthermore, characteristic of the structure of the
Cathedral, common to other constructions in Noto, is
the presence of numerous scaffolding holes that some-
times occupy the entire cross section (Fig. 14).
Some stones were sampled from pillars and walls and
mortar samples were taken from the horizontal and
Fig. 11. Prospect of the external wall of the left nave. vertical internal and external joints (Fig. 9b and Fig.
L. Binda et al. / Construction and Building Materials 17 (2003) 543–555 547
Fig. 15. Spring of the arch on pillar B9 and sampling location of the
Fig. 13. Detail of the buttress masonry. mortar.
548 L. Binda et al. / Construction and Building Materials 17 (2003) 543–555
Fig. 16. (a) Check point for removal to study the connection pillar-wall. (b) Photographic survey of the connection.
Fig. 17. Crack pattern survey of the face of pillar B9 toward the nave. Fig. 19. Example of a crack filled with gypsum mortar in the sixties.
L. Binda et al. / Construction and Building Materials 17 (2003) 543–555 549
Fig. 21. (a) Photographic survey of the test CSJ3S. (b) Plot of the CSJ3S results.
550 L. Binda et al. / Construction and Building Materials 17 (2003) 543–555
Fig. 22. (a) The internal core of pillar A9 after removal of the external leaf. (b) Plot of the results of single and double flat-jack tests on the
pillars.
is, approximately 1.1 Nymm2. The lateral displacements of the built-in pillars. Therefore, their behaviour can
were higher, reaching 5.0 mmymm. Since this area of give some information on the one of the internal
the pillar was probably already cracked since a long conglomerate. Furthermore, these walls have to be pre-
time and certainly damaged by the collapse, it is possible served, and then they have to be known. In Fig. 23a the
to think that the initial strength of the internal rubble results of the three tests are reported. Two of them
material, when the mortar was completely hardened, CNJ4D and CNJ5D gave similar results and were
could have been approximately 1.5–2.0 Nymm2. Fig. stopped at 1.2 Nymm2; the test CNJ6D was stopped at
22b reports the results of the three tests carried out on only 0.8 Nymm2 showing a result similar to the test
pillars A9 and E9. It is possible to observe the different CNJ2D of the inside of pillar A9. So it was confirmed
behaviour of the internal and external parts of the pillars that the wall masonry is similar to the rubble masonry
and that the stress due to the dead load of the pillar is inside the pillars, even if its stiffness is higher and this
already greater than the strength of the interior. There- material is much weaker than the regular stone masonry
fore, the internal part had probably settled down some- of the outer leaf.
time after construction, leaving the external leaf as the The detailed results of the flat-jack tests are reported
only load-bearing last of the pillar. in Table 1.
Three double flat-jack tests were performed on the
external walls of the Cathedral (Fig. 23b). The interest 3.5. Grout injectability tests in pillars and walls
deserved by these walls, which are not load-bearing
walls, is due to the fact that they seem to be made with Small areas (500=500 mm2) of the external surface
a technique similar to the one used for the internal part of the remaining of pillars A and C and of the built-in
Fig. 23. Double flat-jack tests on external walls: (a) plot of the test results; (b) prospect of the masonry.
L. Binda et al. / Construction and Building Materials 17 (2003) 543–555 551
Table 1
Results of double flat-jack tests
ing the soil slope. Concerning the pillars of the central pillars seem to be more reliable than the ones of the
nave, the maximum depth of the foundations reaches central nave.
3.00 m for the pillar B. In the cases when the depth Nevertheless, a common problem of pillars and walls
was greater, a pyramidal foundation was made, and in is represented by the frequent presence of scaffolding
the cases when the depth was smaller, the foundation holes crossing the whole section of the masonry. This
was enlarged (Fig. 6). The constructive technology of peculiarity should be taken into consideration in the
the foundations seemed to be good even if they were design for reconstruction.
built with regular courses of round river stones. It was
not possible to excavate near A9, B9, C9, D9, E9 for safety 4.2.1. Materials
reasons. The material characterisation has been described in
Also, the mortar analyses shows that they are better detail by Binda w4,5,8,12x. Nevertheless, a general infor-
than the ones used for the pillars. The foundation soil mation and comment is given here. The calcarenite used
from the chemical analysis results to be calcium carbon- for the external leaf of the pillars is characterised by a
ate for the 95%. The aggregate size detection gave an fairly good strength when tested dry up to constant mass
8% of clay, a 72% of silt and a 20% of sand. (18.0 Nymm2 in compression, 2.2 Nymm2 in tension of
cylinders of 50-mm diameter and 100-mm height) and
4.2. Morphology of pillars and walls a lower strength when tested saturated up to constant
mass (11.6 Nymm2 in compression and 1.3 Nymm2 in
tension). This means a reduction of the 35.5% of the
The removal by layers of the remains of pillar C compressive strength and of the 39% of the tensile
allowed to understand how the internal and external strength. The ‘travertine’ used in the core of the pillars
courses of the masonry were built and their connection. and in the external leaf above the base has a much
The technique of construction used had created a weak lower strength than the calcarenite (5.2 Nymm2 in
internal part made with a sort of low strength and high compression as an average value measured on dry prisms
deformability conglomerate. Along the time under the of 100=100=200 mm3 dimension). The different
dead load and the effects of earthquakes, the external mechanical characteristics of the two stones were also
and the internal leaves of the masonry were certainly detected by sonic tests in laboratory and on site w13x.
subjected to differential movements also due to the lack Another type of stone called giuggiolena (a sort of
of connection between the two parts and in the four compact ‘travertine’) was used for the construction of
corners of the pillars. These movements caused a differ- the dome. This stone also shows a different behaviour
ential stress distribution with concentration of stresses when tested dry or saturated: 5.3 Nymm2 in compression
in the external leaf w8x. The dilatancy of the conglom- and 1.0 Nymm2 in tension when dry, and 5.05 Nymm2
erate as also detected by the double flat-jack test in the in compression and 0.8 Nymm2 in tension when
core of pillar A9 also could have caused a distribution saturated.
of stresses normal to the external leaf. The situation was The mortars based on putty lime were obtained by
evolving for a long time (it should be remembered that using probably a local calcareous aggregate with an
it was already present in the 1950s) also due to a excessive fineness; this property was the cause of the
possible creep behaviour of the calcarenite; the syner- low physical and mechanical characteristics of the mate-
getic effect of the earthquake damages caused a quick rial. The mortars used for the walls, the arches and the
evolution toward the collapse, which certainly took place dome were of better composition.
in the pillars.
The use of ‘travertine’ above the pillar base has 4.3. Crack pattern survey of the remaining pillars of the
certainly contributed in the reduction of the load-carry- central nave
ing capacity of the element.
Another negative aspect of the structure was the
From the survey the following remarks can be made:
presence of niches in each pillar at a certain height and
– all the cracks surveyed on the rendering penetrate
the presence of a pulpit excavated in pillar D, which
into the external leaf of the pillars and in some cases
probably was bearing the highest damage.
they reach the core showing that the damage either
It was possible to state that the built-in pillars and caused by the collapse or already present before it
the external walls of the Church were built at the same was deep and serious;
time and connected with continuity. Furthermore, long – the removal of the rendering has shown that many
transversal stones were found connecting the two exter- large and long vertical cracks had been filled with
nal leaves of the pillars, while the internal conglomerate gypsum mortar in the fifties.
was made with sharp pieces of calcarenite and ‘traver-
tine’ with thick mortar joints apparently stronger than Among the surveyed pillars only E9 seems to have
those of the central pillars. Therefore, these external less damage, even if it is also showing vertical cracks.
554 L. Binda et al. / Construction and Building Materials 17 (2003) 543–555
The high state of damage found in pillar A9 already of construction and the poor materials that cannot be
present before the earthquake suggests that by symmetry strengthened in any way. Therefore, they should be
also pillar A was badly damaged before the collapse, demolished and rebuilt as the collapsed ones. In fact,
even if no provisional confinement has been carried out in the case that a decision would be taken to preserve
for this pillar as it was done for B, C, D. Therefore, the them, the structure will be affected by a high lack of
collapse could have started from A instead of from D. symmetry and this characteristic would be unsafe
against future earthquakes. The demolition and recon-
4.4. On-site mechanical tests struction of the pillars even if apparently non-respect-
ful of the conservation theories will lead to a better
The double flat-jack tests have shown the low strength safe structure taking into account the seismicity of
and high deformability of the internal core of the pillars the place.
and the limited strength of the ‘travertine’ leaf. Taking – The materials to be used for the reconstruction of the
into account the different behaviours investigated pillars must be more reliable than the original ones:
between the internal and external parts of the pillars, hydraulic mortars, use of the calcarenite in the exter-
the hypothesis can be formulated that soon after the nal leaf and in the core filling, transversal stones to
construction of the structure the stress distribution was connect the external and the internal parts.
rather uniform. As differential movements took place – The soil and the foundations are reliable, except for
between the internal and the external leaves caused by the foundations of the reconstructed pillars that will
the higher deformability of the first one and by the lack support higher stresses than the original ones; there-
of good connection between the two, the highest stress fore they have to be rebuilt or strengthened.
was supported by the second one, which was also built
with two different materials. In fact, from 1.50 m up to Acknowledgments
the top the travertine was used. So the damage probably
started above the base with thin vertical cracks that The authors wish to thank L. Cattaneo, C. Colla,
slowly propagated during the centuries after the con- M.Garau, G. Paccapelo for the collaboration at the on-
struction. On the other side, the bad connections in the site survey, and M. Antico, M. Cucchi, M. Iscandry, P.
corners did not help the external leaf to act as a Perolari for their collaboration to the on-site and labor-
confinement. atory tests. The investigation was supported by the
Prefettura of Siracusa.
4.5. Grout injection tests
References
The investigation by sonic tests carried out after
injection and furthermore by demolition showed that w1x Binda L, Gatti G, Poggi C, Sacchi Landriani G. The collapse
apart from grout C, all the others were effective. Nev- of the Civic Tower of Pavia: a survey of the materials and
ertheless, the grouts are successful in filling voids and structure. Masonry Int J 1992;6(1):11 –20.
w2x Binda L, Tiraboschi C, Tongini Folli R. On site and laboratory
even thin cracks, but they do not improve the behaviour
investigation on materials and structure of a Bell-Tower in
of a weak mortar because the mortar cannot be injected. Monza, Second International Conference RILEM on Rehabili-
Therefore, the grout injection can be successful for the tation of Structures, Highett, Australia, 1998; p. 542–556.
external walls and pillars, but not to strengthen the w3x De Benedictis R, Tringali S, Gavarini C, Binda L, Baronio G.
central nave pillars. Methodology applied to the removal of the ruins and to the
survey of the remains after the collapse of the Noto Cathedral
in Sicily International Conference Structural Studies, Repairs
5. Conclusions and Maintenance of Historical Buildings, STREMAH 99,
Dresden, Germany, 1999; p. 529–538.
The following answers could be given by the authors w4x Binda L, Baronio G. Cathedral of Noto–Preliminary investi-
to the designers De Benedictis and Tringali after the gation to the reconstruction, Relazione Finale, Contratto Pre-
fettura di Siracusa, 1998.
investigation carried out in laboratory and on site: w5x Binda L, Baronio G. Contratto di Consulenza: Studio sullo
– The partial collapse of the Cathedral was not only stato di conservazione dei materiali e delle structure e sulla
possibilita` di un loro recupero in base ai risultati delle prove e
caused by the damages due to the 1990 earthquake dei rilievi di laboratorio e in situ, Relazione Finale, Contratto
but was also due to the already unsafe condition of Prefettura di Siracusa, 1998.
the central pillars. w6x ASTMC 1196 (1991). Standard test method for in-situ com-
– The lateral walls, the arches and the remaining lateral pressive stress within solid unit masonry estimated using the
domes that were built with a better technique can be flat-jack method, Philadelphia, ASTM. ASTM C 1197 (1991).
Standard test method for in-situ measurement of masonry
repaired and preserved by grout injection and local
deformability properties using the flat jack method.
reinforcements. w7x Binda L, Tiraboschi C. Flat-Jack Test as a Slightly Destructive
– The left central pillars cannot be preserved or repaired Technique for the Diagnosis of Brick and Stone Masonry
due to the high state of damage, the poor technique Structures, International Journal for Restoration of Buildings
L. Binda et al. / Construction and Building Materials 17 (2003) 543–555 555
and Monuments, Int. Zeitschrift fur Bauinstandsetzen und w11x Binda L, Colla C, Saisi A, Valle S. Application of Georadar
Baudenkmalpflege, Zurich, 1999; p. 449–472. to the Diagnosis of Damaged Structures, Sixth International
w8 x Binda L, Baronio G, Gavarini C, De Benedictis R, Tringali S. Conference Structural Studies, Repairs and Maintenance of
Investigation on Materials and Structures for the Reconstruc- Historical Buildings, STREMAH 99, Dresden, Germany, 1999;
tion of the Partially Collapsed Cathedral of Noto (Sicily), p. 13–22.
International Conference Structural Studies, Repairs and Main- w12x Baronio G., Binda L., Tedeschi C., Tiraboschi C. Caratteriz-
tenance of Historical Buildings, STREMAH 99, Dresden, zazione dei Materiali della Cattedrale di Noto, Seminario
Germany, 1999; p. 323–332.
Internazionale su: Cattedrale di Noto e Frauenkirche di Dresda:
w9 x Binda L, Modena C, Baronio G, Abbaneo S. Repair and
Indagini e Studi per il Progetto di Ricostruzione, Noto.
investigation techniques for stone masonry walls. Constr Build
Mater 1997;11(3):133 –42. w13x Binda L, Saisi A, Tiraboschi C, Valle S, Colla C, Forde M.
w10x Binda L, Saisi A, Tiraboschi C. Application of sonic tests to Application of Sonic and Radar Tests on the Pillars and Walls
the diagnosis of damage and repaired structures. Int J Non- of the Cathedral of Noto, Seminario Internazionale su: Catted-
destructive Testing Evaluation (NDT&E Int) 2001;34(2):123 – rale di Noto e Frauenkirche di Dresda: Indagini e Studi per il
38. Progetto di Ricostruzione, Noto, 2000.