Académique Documents
Professionnel Documents
Culture Documents
CHAPTER – 1
INTRODUCTION
1.1 Background
The Chief Engineer PWD (N.H. Works), Meghalaya will be the employer and
executing agency for the consultancy services for design of the proposed road :
Rongjeng Mangsang Adokgre (44th to 55th Km) Eldek Akong to Adokgre in Meghalaya
West and the standards of output required from the appointed consultants are of
international level both in terms of quality and adherence to the agreed terms &
conditions and time schedule.*
The instant proposal is to carryout Detailed Project Report (DPR) of the above-
mentioned road project.
1.2 Objective of the Project: To improve transport connectivity and efficiency and
modernization of transport institutions in Meghalaya. The project will focus “to provide
a well-connected efficient, good quality and safe transport network on long-term basis
in a cost-effective manner maximizing economic and social outcomes”. This will
involve:
1.3 Project Scope: The project will emphasize leveraging of annual sector investments
using the two-pronged approach:
(i) introducing an improved delivery framework for transport infrastructure using
a rational criterion for investment decision; innovative, climate resilient, green,
cost-effective designs; and improved contracting practices through direct
funding of critical transport infrastructure gaps; and
(ii) expand this improved delivery framework to the entire transport sector.
The entire scope of services would, inter-alia, include but not limited to the items
mentioned in the ToR (Terms of reference) and comprise as below:
i. Preparation of plan and profile of the existing roads, covering all the existing
features within the existing Right of Way (ROW)
ii. Road and Bridge Inventory
iii. Traffic Surveys
iv. Soil and Material testing
v. Pavement design
vi. Road side drainage plan
vii. Road signs, Markings and Traffic safety devices
viii. Environmental and Social Baseline
ix. Evaluation of existing protection works and designs of new protection works
required
x. Engineering designs
xi. Road side amenities (Project facilities)
xii. Cost Estimate.
xiii. Preparation of Bill of Quantities Package wise along with Technical
Specifications
The objective of Consultant is to prepare all the items required for Bidding, Execution
& Operation of the Project Highway as per latest Standards & Specifications and as
per the Good Industry Practice. *-
The commencement of services at the Project site are made as scheduled below and
the team member for the job will consist of the following.
At Guwahati Office
Assam- 781038
Email : find.aps.here@gmail.com
1.6 Reports and Documents are to be submitted by the Consultant to the Chief Engineer
Meghalaya PWD (NH Works).
Project preparation activities are split into three stages as brought out below.
The Consultant will submit to the client the reports and documents separately for each
of the traffic homogenous sections of project road & in bound volumes (and not spiral
binding form) after completion of each stage of work as per TOR
The Inception Report is to be submitted within 15 (fifteen) days after the date of
commencement of consultancy services. This Inception Report is prepared in
accordance with ToR. The report gives the Consultant’s understanding of the RFP and
Work Plan with methodology proposed and proposal for traffic count locations &
requirement of some of the critical decisions and directives from the client in order to
comply the project report within time schedule.
1. Introduction – Introduction to the study and cites the objectives and scope of
the services.
2. Project Appreciation – Site appraisal & important aspects of the project road.
3. Proposed Traffic Survey Stations.
4. Detailed Methodology – To meet the requirements of TOR the detailed
methodology and approach including scheduling of various sub-activities to be
carried out for completion of various stages of work for project preparation
and collection of necessary information.
7. Work Programme – Explains the proposed work programme for study and
preparation of DPR.
CHAPTER 2:
PROJECT APPRECIATION
The existing road network of 13,000 km has been developed in bits and pieces rather than
according to a well-designed plan: consequently, it is non-coherent and has many deficiencies
like missing links, bridges, drainage and protection structures, and road safety engineering
measures; and inadequate pavements and poor riding quality. Large part of the network has
failed due to poor quality of initial construction, lack of maintenance, and extreme climate
events (high rainfall). There are about 800 semi-permanent timber bridges in failed condition
– posing a serious safety issue and need immediate replacement. Particularly, the road
network towards Bangladesh Border is relatively underdeveloped and the population living in
that part is deprived of even the basic facilities like access to health and education. About half
of the 5,362 habitations lack all-weather road access, out of these 1,700 not covered under
PMGSY1 as their population (of individual habitation) is below 250. Due to hilly and difficult
terrain conditions, road construction is not always possible in many areas. In such situations,
alternate solutions such as ropeways, foot bridges and foot paths are to be considered.
The absence of last mile connectivity and transport services impact the transport costs which
are about 25 percent higher compared to other places in India reducing the competitiveness of
agriculture and businesses.
Due to limited road space, traffic management and parking issues, Shillong and other
urbanized locations experience long traffic congestions, especially during peak working
hours. The reasons for the under-developed transport network are inadequate funds, their
inefficient utilization, and low institutional capacities and knowledge base of the transport
agencies
Location Plan
END
START
institutions that have existed for hundreds of years. These political institutions were
fairly well developed and functioned at various tiers, such as the village level, clan
level, and state level. Dance is central to the culture of Khasi life, and a part of the
rites of passage. Dances are performed in Shnong (village), a Raid (group of villages),
and a Hima (conglomeration of Raids). Some festivals include Ka Shad Suk
Mynsiem, Ka Pom-Blang Nongkrem, Ka-Shad Shyngwiang-Thangiap, Ka-Shad-
Kynjoh Khaskain, Ka Bam Khana Shnong, Umsan Nongkharai, Shad BehSier.
2.2 Climate
The state of Meghalaya is directly influenced by the south west monsoon and the
northeast winter winds. The four seasons of Meghalaya are: Spring - March and April,
Summer (Monsoon) - May to September, Autumn - October and November and
Winter - December to February. During March and April, the atmosphere gradually
warms up with the advent of Spring. From the middle of April, the temperature starts
rising to the maximum in the month of June and then decreases gradually. This period
may be termed as the Summer (Monsoon) Season. The maximum temperature
recorded is 34 Celsius at Tura and West Garo Hills District and 28 Celsius at
Shillong.
October and November are the two months when the climate is cool and temperate.
After November, the winter season sets and continues upto the end of February.
During these months the temperature comes down to as low as 2 Celsius in the Khasi
Hills. Rainfall starts by the third week of May and continues right up to the end of
September and sometimes well into middle of October. The maximum rainfall occurs
over the southern slopes of the Khasi hills, i.e over Cherrapunjee and Mawsynram
platform which receives the heaviest rainfall in the world. The average rainfall in the
State is 12,000 mm.
North and the North Eastern side. The North Garo Hills Police organization was
restructured right after the creation of the district on the 27th July 2012.
Geography and Climate
The district North Garo Hills is located in between Longitude 89E & 91E and in
between Latitude 25N & 26N. The area receives heavy rainfall during monsoon
season and basically tropical in nature due to which maintenance of the un-surface
road is very difficult. The annual rainfall in the district recorded is about 4188 mm.
Population
The population of North Garo Hills district consists of two major groups - tribal and
non-tribal. The tribal population comprises of the Garos and other indegenous tribes
like Rabhas, Kochs, Rajbangsis, Kacharis and others. The non-tribal population are
mostly concentrated in the urban settlement of Resubelpara and the plain fringes of
the district. The people of the district are blessed with raw talent in arts and craft
besides having a natural flair for singing and music. They are highly skilled in
handicrafts and bamboo crafts. There is a lot of untapped potential which through
proper guidance and leadership can bring a big change to the region.
Economy
The economy of the North Garo Hills district is basically agrarian and rural based.
Agriculture is the mainstay of about 90% of the population of North Garo Hills and
most earn their living directly or indirectly from agriculture. Rice is the most
important food crop that is grown in the district, both in the plains and the hills. Other
food crops that are widely grown in the district are tapioca, yam, maize, millet and
pulses Due to widespread practice of shifting cultivation and deforestation, the
production of food crops is decreasing and Government has intervened to provide
alternative measures of farming practices like terracing, contour farming etc. to the
people. Horticulture is one of the flourishing sector in the region and much needed
attention has been given by the Government to develop this sector. The important fruit
crops of the district are oranges, pineapple, litchi, banana, jackfruit and other citrus
fruits.
Flora & Fauna
The flora and fauna of the region has a very diverse distribution and is a hot to many
of the indigenous and exotic species of plants and wildlife. The region also boast of
thick natural vegetation mostly comprising of bamboo, teak and sal forests and many
other species of plants having varied uses. This diverse spread of vegetation favours
the undergrowth of many shrubs and herbs and hence the biomass reserves rich in
fertility are well preserved.
After receipt of the acceptance letter, the Project team visited the project road sites
from dt. 15.09.2019 to 20.10.2017 & important aspects of the Project road has been
noted down in the detailed site reconnaissance which is provided in Vol.II. This
includes general description about the project road, topographic details, site features,
important structures, junctions, pavement characteristics and road safety
requirements. The land use details have been collected and strip plans have been
prepared as per the requirement of ToR. The Strip plans have been appended with this
Inception Report in Vol.II and the description of the Project road is given here under.
Project road is under Meghalaya PWD NH Works. The proposed Project road under
study will start at Rongjeng and ends at Adokgre.
The Project Road traverses from North to South direction. The location of the Project
Road lies between Latitude: 250 12' 38.76" N to 250 52' 57.97" N Longitude: 900 13'
46.09" E to 910 00' 03.37" E. The entire project road passes through the Hilly Area.
Land used along the road is either cultivable land, grazing land, private, submerged
area or government land. However, the exact information about the land in question
can be obtained from the revenue authority of the concerned area. The average ground
level of area varies between 76.00 m to 465.00 m from the Mean Sea Level. The
proposed road will be constructed in Single Lane MDR standard, with paved
shoulders. There are about 23 Nos. of Minor Junctions out of which 19 Nos are T
Junctions and 4 Nos are Y Junctions. There are 5 No. of Major Bridge, 2 No. of
Minor bridges, 69 Nos of Slab Culverts and 75 nos. of HP culvert are found along the
existing road. Howerver, exact no. of above items can be finalized after the detailed
ground survey and fixing of final alignment.
Site Photographs :
2.5.3 Topography
The entire project road passes through the Hilly area. Land used along the road is
either cultivable land, grazing land, private, submerged area or government land.
The Road is proposed within the existing ROW as per TOR clause No.6 Task-1.
Details are shown in road inventory Vol.II.
2 44+077 T-Junction
3 44+257 T-Junction
4 45+207 T-Junction
5 45+932 T-Junction
6 46+240 T-Junction
7 47+224 Y-Junction
8 47+227 Y-Junction
9 47+288 T-Junction
10 47+774 Y-Junction
11 47+786 Y-Junction
12 47+879 T-Junction
13 48+244 T-Junction
14 48+272 T-Junction
15 48+765 T-Junction
16 49+276 T-Junction
17 49+376 T-Junction
18 52+665 T-Junction
19 52+867 T-Junction
20 53+070 T-Junction
21 53+107 T-Junction
22 53+162 T-Junction
23 53+390 T-Junction
The entire project road passes through the Hilly Terrain but not passes through Forest
land. Details are shown in Road Inventory Vol.II.
2.5.13 Utilities
The major utilities along the corridor are:
a) Electric Poles are laid throughout Project Corridor.
The 11 km long project road will have one homogeneous section [HS]. The start &
end km, length of HS is as below.
Section
Sr.
At km. Homogenous
No. Adokgre Remark
From Rongjeng Section
1 0.0 10.00 HS 1 Adokgre
Sr. Location
Type of Survey Remarks
No Activities Planned
1 Classified HS 1
Traffic Volume HS 1
Count HS 1
Origin-
Destination and HS 1
2 Commodity
Movement
Characteristics
Intersection
4
Volume Count
Pedestrian/anim
5 al cross traffic HS 1
count
CHAPTER 3:
PROPOSED CROSS SECTIONS & PROJECT FACILITIES
3.1 General
The requirements, if any, for the construction of roads would be identified on the basis of
data derived from reconnaissance and traffic studies and proposed typical cross sections will
be incorporated in the Inception Report for approval by World Bank / PWD NH works,
Meghalaya.
The typical cross sections are proposed for Intermediate Lane as per IRC: SP:48-1998 Hill
Road Manual and are appended with the Volume II.
The existing road conditions are BT/Gravel/Earthen. The proposed Road alignment stretch
falls under the definition of Mountainous terrain.
Existing Road include Pipe, Slab and Box culverts and will be replaced by Box
Culverts as per Standard. However, these numbers may vary in accordance to the
detail ground survey and after finalization of the alignment.
CHAPTER – 4
DETAILED METHODOLOGY
4.1 General:
1. Preparation of plan and profile of the existing roads, covering all the existing
features within the existing Right of Way (ROW)
2. Road and Bridge Inventory
3. Traffic Surveys
4. Soil and Material testing
5. Pavement design
6. Road side drainage plan
7. Road signs, Markings and Traffic safety devices
8. Environmental and Social Baseline
9. Evaluation of existing protection works and designs of new protection works
required
10. Engineering designs
11. Road side amenities (Project facilities)
12. Cost Estimate
13. Preparation of Bill of Quantities Package wise along with Technical Specifications
4.2.1 Preparation of plan and profile of the existing roads, covering all the existing
features within the existing Right of Way (ROW)
APS Corporations Pvt. Ltd. 22 PWD NH works, Meghalaya West
Preparation of Detailed Project Report (DPR) For Rongjeng Mangsang Inception Report
Adokgre (44th to 54thKm) Eldek Akong to Adokgre Under Meghalaya
Integrated Transport Project (MITP) Funded by World Bank.
The detailed design for geometric elements covers the following, but not be limited to
major aspects:
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements at 30m interval.
iv. junctions, intersections and interchanges
v. Widening of service roads.
4.2.2 Road and Bridge Inventory
Deliverables under this component includes:
1. Detailed road inventory surveys will be carried out to collect details of all existing
road and pavement features along the existing road sections. The proforma for road,
culverts and bridge inventory & other structures is provided at VolI:
The inventory data include the following but not be limited to following:
2. The data collection will be in sufficient details. The data are compiled and presented
in tabular as shown in Vol.II
Sr.
Description Location Remark
No.
Classified Traffic Volume
1. Adokgre As per TOR
Count
1. The classified traffic volume count surveys will be carried out for 7 days
(continuous, direction-wise) 24 hours at the selected survey stations. The vehicle
classification system as given in relevant IRC code will be followed. The following
classes of vehicles will be counted separately in view of the requirements of traffic
demand estimates and economic analysis:
Motorized Traffic Non-Motorized Traffic
2-Wheeler Bi-Cycle
3-Wheeler Cycle-Rickshaw
Passenger Car Animal Drawn Vehicle (ADV)
Utility Vehicle (Jeep, Van etc.) Hand Cart
Other Non- Motorized Vehicle
Bus Mini Bus
Standard Bus
LCV LCV-Passenger
LCV-Freight
Truck MCV : 2-Axle Rigid Chassis
HCV : 3-Axle Rigid Chassis
2. The traffic count data would be analyzed to depict hourly and daily variations.
3. The traffic volume count per day will be averaged to show a weekly Average
Daily Traffic (ADT) by vehicle type. The Annual Average Daily Traffic
(AADT) will also work out by applying seasonal factors.
4. The consultants will compile the relevant traffic volume data from secondary
sources also. The salient features of traffic volume characteristics brought out
and variations if any will explain suitably.
5. The Abstract of traffic data for selected survey station will be provided
TRAFFIC GROWTH
RATE
LEGEND:
PIA Project Influence Area
GV Goods Vehicle
2W / 3W 2 Wheelers / 3 Wheelers
B Bus & Mini-Bus
P Population
NSDP Net State Domestic Product
GDP Gross Domestic Product
APS Corporations Pvt. Ltd. 26 PCI PWD
NH works,Income
Per Capita Meghalaya West
GR Growth
Preparation of Detailed Project Report (DPR) For Rongjeng Mangsang Inception Report
Adokgre (44th to 54thKm) Eldek Akong to Adokgre Under Meghalaya
Integrated Transport Project (MITP) Funded by World Bank.
For conducting the intersection volume count, the turning movement traffic
surveys will be carried out as per IRC: SP:41-1994 at all locations where the
Project Road intersects/meets the NH, SH or MDR. The turning movement
surveys will be undertaken from 08:00 to 12:00 hours in the morning and
16:00 to 20:00 hours in the evening. The details regarding composition and
directional movement of traffic will be furnished by the Consultant.
b. Design
i. The data at each location will be presented and analyzed to identified suitable
treatment viz. at-grade intersection, grade separator without ramps or
interchange with ramps in the light if warrants and criteria specified in the
Manual. The type and layout proposed for each location will be furnished
along with the analysis supporting the same.
ii. The amount of additional land required, if any, at each of the intersection on
the Project MDR will be clearly stated and brought out.
iii. For all cases where grade separators without ramps or interchanges with ramps
will be proposed, the possibility of their provision on the Project MDR in a
phased manner will be duly examined and a report on the cost effectiveness of
the proposal will be submitted for consideration of the Authority to enable it to
specify such requirements in the relevant Schedules of the Concession
Agreement.
1. The data on soil classification and mechanical characteristics for soils along
the existing alignments may already be available with the Authority. The
testing scheme is, therefore, proposed as given under:
i. For the widening of existing road, at least three subgrade soil samples
for each homogenous road segment or three samples for each soil type
encountered, whichever is more will be tested.
APS Corporations Pvt. Ltd. 27 PWD NH works, Meghalaya West
Preparation of Detailed Project Report (DPR) For Rongjeng Mangsang Inception Report
Adokgre (44th to 54thKm) Eldek Akong to Adokgre Under Meghalaya
Integrated Transport Project (MITP) Funded by World Bank.
ii. For the roads along new alignments, the test pits for subgrade soil @2
km or for each soil type, whichever is more. A minimum of three samples will
be tested corresponding to each homogenous segment.
works. Design of pavement structure would take due account of the type,
characteristics of materials used in the respective courses, variability of their
properties and also the reliability of traffic predictions. The methodology
adopted for the design of pavement will be in complete with flow charts
indicating the various steps in the design process, their interaction with one
another and the input parameter required at each step.
5. The paved shoulders will be designed as integral part of the pavement for the
main carriageway. The design requirements for the carriageway pavement will
be applicable for the design of shoulder pavements. The design of granular
shoulder will be taken into account the drainage considerations besides the
structural requirements.
1. The requirement of roadside drainage system and the integration of the same
with proposed cross-drainage system will be worked out for the entire length of the
project road section.
2. The drainage provisions will be worked out for road segments passing through
urban areas.
3. The designed drainage system will show locations of turnouts/outfall points
with details of outfall structures fitting into natural contours.
Responsibilities Include:
(i) To review land and access requirements, land use, and involuntary
resettlement if any;
(ii) To prepare, based on available data,a socio-economic and cultural
profile of the population and available infrastructure facilities for
services (disaggregated by gender, ethnicity, vulnerable groups,
socially and economically backward communities, youth and aged, and
economic aspects) in the project area;
(iii) To carry out social analysis of project area based on proposed activities
envisaged under the project;
(iv) To review current and proposed development activities within the
project's area of influence, including those not directly connected to the
project;
(v) Document the extent of land to be acquired; collect land ownership
records and review of the land take/lease process to assess any legacy
or current/existing issues (like informal settlers, livelihood
dependence, other usage, etc.).
4.2.9, Evaluation of existing protection works and designs of new protection works
required
To evaluate the soundness of the existing protection works like retaining walls, breast
walls, slope pitching etc. along with the remedial measures, taking into consideration
bio-engineering measures for slope protection. The new protection works locations
APS Corporations Pvt. Ltd. 30 PWD NH works, Meghalaya West
Preparation of Detailed Project Report (DPR) For Rongjeng Mangsang Inception Report
Adokgre (44th to 54thKm) Eldek Akong to Adokgre Under Meghalaya
Integrated Transport Project (MITP) Funded by World Bank.
with proper justification and design will be given in the reports and also shown in the
drawings.
Geometric Design
1. Based on the data collected from reconnaissance and topographic surveys, the
sections with geometric deficiencies, if any, will be identified and suitable
measures for improvement will be suggested for implementation.
2. The data on accident statistics will be compiled and reported showing accident
type and frequency so that black spots are identified along the project road
section. The possible causes (such as poor geometric features, pavement
condition etc.) of accidents will be investigated into and suitable cost-effective
remedial measures suggested for implementation.
3. The detailed design for geometric elements covers the following, but not be
limited to major aspects:
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements at 30m interval.
iv. junctions, intersections and interchanges;
v. Widening of service roads.
APS Corporations Pvt. Ltd. 31 PWD NH works, Meghalaya West
Preparation of Detailed Project Report (DPR) For Rongjeng Mangsang Inception Report
Adokgre (44th to 54thKm) Eldek Akong to Adokgre Under Meghalaya
Integrated Transport Project (MITP) Funded by World Bank.
4. The alignment design will be verified for available sight distances as per the
standard norms. The provision of appropriate markings and signs will be made
wherever the existing site conditions do not permit the adherence to the sight
distance requirements as per the standard norms.
5. The prepare detailed analysis of traffic flow and level of service for the
existing road and workout the traffic flow capacity for the improved project
road. The analysis clearly establishes the widening requirements with respect
to the different horizon periods taking into account special problems such as
road segments with isolated steep gradients.
6. To prepare design and other details in respect of the parallel service roads and
other locations to cater to the local traffic.
It includes for providing roadside amenities like bus stops, passing places, parking
places, huts for road maintenance staff, toilet blocks, village market platform, view
point and any other amenity as per the direction of the PWD and to prepare the designs
along with cost estimates of the same. The locations of these features will be given in
the reports and also shown in the drawings.
CHAPTER – 6
TASK ASSIGNMENT & MANNING schedule
6.1 Tasks Assignments:
Task assignment is given in table below:
B. Support Staff
Sr. Name Position Task Assigned
No
1. Nabanita kakoty Asst. Highway Engineer Collection & compilation of existing data on
road section & previous studies & Highway
Engineer in collecting and compilation of
engineering investigation reports, highway
design & estimation of quantities
2. Parishmita Bora Asst. Bridge Engineer Assist Engineer in condition survey of existing
bridges & design of new bridges & associated
highway structures, including rehabilitation
Appendix 6.2
COMPOSITION OF TEAM PERSONNEL
Sl. No Name Position
1 Mr. Satyajit Banerjee Sr. Highway Engineer cum team Leader.
1. 2 Mr. Babulal Sahu Highway design Engineer
2. 3 Mr. V.R. Gopal Raju Bridge Engineer
3. 4 Mr. Ashok Satyandra Sr. Geotechnical Engineer cum Pavement
Specialist.
Kumar
4. 5 Mr. Monjit Gogoi Senior Survey Engineer
5. 6 Mr. Prafulla Hazwary Leo Social Specialist
6. 7 Dr. Bhrigu Prasad Saikia. Environment Specialist
Sl. Months
Name Position Report Due / Activities
No. 1 2 3
Sr. Highway Engineer cum team
1. Mr. Satyajit Banerjee Responsible for all Activities of the Project
Leader.
Alignment Design, Plans, Junctions, Intersection Design,
2. Mr. Babulal Sahu Highway design Engineer Drainage, Road Safety, Pavement Investigation and assistance to
Team Leader for Preparation of all Reports
Bridge condition Survey and Investigations, Preparation of GAD
3. Mr. V.R. Gopal Raju Bridge Engineer
for Bridges, Grade Seperators
Mr. Ashok Satyandra Sr. Geotechnical Engineer cum
4. All Reports pertaining to geotechnical and Material Investigation
Kumar Pavement Specialist.
Road Inventory, Topographical Survey and Fixation of Bench
5. Mr. Monjit Gogoi Senior Survey Engineer marks, compilation of details related to shifting of utility shifting
of utilities and ROW in general
6. Mr. Prafulla Hazwary Leo Social Specialist EIA Reports
7. Dr. Bhrigu Prasad Saikia. Social & Environment Specialist EMP Reports
Quantity Surveyor /
8. Mr. Arup Kumar Misra Rate Analysis, Bill of Quantities, Cost Estimation & DPR
Documentation Expert
Drainage Engineer cum Collection and preparation of Hydraulogical Data of Major /
9. Mr. Vasanth Kr. TH
Hydrologist Minor Bridges, Culverts, preparation of Reports
CHAPTER – 7
WORK PROGRAMME
8.1 Work programme table is below:
DELIVERABLES 1
A. Mobilization & Finalization of Methodology and Work Plan Investigation
Months Number of
SI.No Item of Work/Activities
1 2 3 Months
1 Consultation with Client & Local Bodies
2 Collection and Review of Existing Data
3 Review of Methodology & Work Plan 7 Days
based on the actual site
4 Interaction with Client & Their Input
CHAPTER – 8
KEY PLAN AND LINEAR PLAN