Vous êtes sur la page 1sur 17

KINGDOM OF SAUDI ARABIA Page: 2 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

TABLE OF CONTENTS

1.0. GENERAL ....................................................................................................................... 3


1.1. Introduction ................................................................................................................... 3
1.2. Scope of this document ............................................................................................... 3
1.3. Purpose of this document............................................................................................ 3
1.4. Definitions...................................................................................................................... 3
1.5. Abbreviations ................................................................................................................ 5
1.5.1. Parties ............................................................................................................................ 5
1.5.2. Institutes for Standardization ...................................................................................... 6
1.5.3. Systems / Locations / Stations .................................................................................... 6
1.5.4. Equipment, Hydraulic Indications ............................................................................... 7
1.6. Units ............................................................................................................................... 9
2.0. REFERENCES................................................................................................................ 9
3.0. DESIGN PARAMETER: ............................................................................................... 10
4.0. U VALUE FOR WALL, ROOF, DOOR & GLASS: ....................................................... 11
4.1. Coefficient of Transmission (U) for Roof: ................................................................ 11
4.2. Coefficient of Transmission (U) for External Wall: .................................................. 11
4.3. Coefficient of Transmission (U) for Door: ................................................................ 12
4.4. Coefficient of Transmission (U) for Glass: ............................................................... 12
5.0. EQUIPMENT HEAT DISSIPATION:............................................................................. 13
6.0. LIGHTING HEAT DISSIPATION: ................................................................................. 13
7.0. OVERALL LOAD SUMMARY OF VSD BUILDING: .................................................... 13
8.0. SAND TRAP LOUVER CALCULATION & SELECTION: ........................................... 14
9.0. VENTILATION CALCULATION ................................................................................... 14
9.1. AS PER AIR CHANGES PER HOUR (ACPH): ........................................................... 14
9.1.1. As per Air Changes per Hour for VSD ROOM-1:...................................................... 14
9.1.2. As per Air Changes per Hour for VSD ROOM-2:...................................................... 14
9.1.3. As per Air Changes per Hour for VSD ROOM-3:...................................................... 15
9.1.4. As per Air Changes per Hour for Cooling Pump Room: ......................................... 15
9.2. AS PER HEAT DISSIPATION:..................................................................................... 15
9.2.1. As per Heat Dissipation for VSD ROOM-1:............................................................... 15
9.2.2. As per Heat Dissipation for VSD ROOM-2:............................................................... 16
9.2.3. As per Heat Dissipation for VSD ROOM-3:............................................................... 17
9.2.4. As per Heat Dissipation for Cooling Pump Room: .................................................. 17
10.0. PRESSURE RELIEF DAMPER SIZING: ..................................................................... 18
10.1. Pressure Relief Damper Sizing for VSD ROOMS:.................................................... 18
11.0. LIST OF APPENDICES: ............................................................................................... 18
12.0. APPENDIX-1................................................................................................................. 19
13.0. APPENDIX-2................................................................................................................. 20
14.0. APPENDIX-3................................................................................................................. 21
15.0. APPENDIX-4................................................................................................................. 22
16.0. APPENDIX-5................................................................................................................. 23
17.0. APPENDIX-6................................................................................................................. 24
18.0. APPENDIX-7................................................................................................................. 25
19.0. APPENDIX-8................................................................................................................. 26
Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 3 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

1.0. GENERAL

1.1. Introduction

The Yanbu-Madina Phase 4 WTS has been designed to supply (mainly) Madina with
potable water as an extension to the capacity of the existing lines. Its water sources are
the existing and new Desalination Plants located at PS1 area in the region of Yanbu.

The pumped system is operated as a closed system with one initial pump station located
at PS1 Yanbu and one intermediate pump station PS2. The diameter of the mainline
from PS1-D to Tap-off HPR-D1 is 84” reducing to 80” up to HPR-D2.

The connection line from HPR-D2 to MET and TSS is operated as a gravity line. The
diameter of this section down to the tap-off TSS is 80” followed by 68” pipeline to MET.

The maximum design flow rate at the beginning of the pipeline at PS1-D is 578,947m³/d,
whereby the standard operation will be 473,684m³/d.

Additionally the YMWTS-4 shall be operated in backflow operation from HPR-D1 and/or
HPR-D2 to PS1 tank farm as an exceptional load case with a flow rate of 233,000m³/d.

The storage capacity of the existing Yanbu Plant Tank Farm at PS1 will be increased by
additional two (2) steel tanks of 140,000 m³ and two (2) steel tanks of 100,000 m³. The
entire tank farm will be in pool operation. In case the Pump Stations of Phase 2 or
Phase 3 are in operation the tank farm can be operated down to a TLmin of 6.8masl.

The system of YMWTS-4 can be operated with down to a TLmin of 4.5masl.


The YMWTS-4 is hydraulically connected to Yanbu Phase 2 Pumps Station PS2 at PS2-
D, to Phase 3 MST and MET and Phase 2 HPR at HPR-D1. Nevertheless YMWTS-4
shall be operated separately and independently.

1.2. Scope of this document

This document contains ventilation and cooling system, which shall be applied for “PS2-D VSD
Building” of the Yanbu Madina Water Transmission System Phase-4 (YMWTS4).

1.3. Purpose of this document

The purpose of this document is to provide the technical input data for preparation of material
specifications for purchase, and to give the ruling guidelines and boundaries for the guide
design, as well for the detail design of the mechanical systems, equipment and material.

1.4. Definitions

For the purpose of this document, the following definitions shall apply:

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 4 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

PROJECT : YANBU – MADINA WATER TRANSMISSION SYSTEM


PHASE 4

EMPLOYER : Saline Water Conversion Corporation (SWCC)

ENGINEER : Refers to the Organization or Engineering Firm assigned by


the EMPLOYER to perform vetting of the design and to
supervise the implementation of the Contract and Works.

EPC CONTRACTOR : Refers to the Organization or Engineering firm assigned by


the EMPLOYER to perform the Engineering, Procurement
& Construction (EPC) of the Contract and Works.

Engineering : Refers to the Organization or Engineering firm assigned by


SUBCONTRACTOR the EPC CONTRACTOR to perform the Detailed
Engineering of the PROJECT. The ENGINEERING
SUBCONTRACTOR refers to IBK Consulting Engineers.

VENDOR : Manufacturers/Suppliers of goods/equipment

SUBVENDOR : Part of Manufacturers/Suppliers of goods/equipment


Vendor

Pipeline or Pipeline : Mean the complete entity of a particular pipeline, including


System all the pipeline segments, the pumping stations, the
reservoir stations, the tie-in stations, the tap-off station, the
one-way surge tanks and the line valve, vent and drain
stations.

System : Shall mean the Yanbu-Madina Water Transmission System


Phase 4, containing the complete works including the
pipeline segments, the pumping stations, the reservoir
stations and tank farms, the tap-off and tie-in stations and
the line valve, vent, drain and wash-out stations.

Mainline : Shall mean all pipeline segments (with all accessories like
cathodic protection facilities, etc.), which connect the initial
pumping station, the intermediate pumping station, the
highpoint reservoir stations and the tap-off stations with
each other. The pipeline segments together with these
stations form the backbone of the system.

Branch Line : Shall mean a lateral pipeline segment which connects a


tap-off station from the mainline with a distributed reservoir
or tie-in station.

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 5 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

Station : Shall mean all works for the system which are related to the
starting, intermediate or endpoint as well as all other
special locations along the pipeline routes (e.g. tap-off
station, line valve station, vent station, tie-in station). When
referring to a “station” without specifying a certain part
thereof, this expression shall mean all installations at the
given location.

Tap-off Station : Shall mean all installations at the starting point of a branch
line from the mainline to a distributed reservoir or tie-in
station.

Tie-in Station : Shall mean all installations at the connection to existing


(third party) facilities at the end of a branch line or mainline.

Endpoint Station : Shall mean the general term for terminal station

Reservoir Station : Shall mean all installation at the given location of the
branch line or mainline including erection of new
reservoir(s) or tank(s).

Final Design : Shall mean the design to be performed by the Contractor in


accordance with the requirements stipulated in the Contract
Documents.

System Operator : Person in the Central Control Room (CCR), who is


responsible for operation of pipeline system

Station Operator : Person receiving instructions from the System Operator


and who is responsible for the operation of a station

Shall : Indicates a mandatory requirement

Should : Indicates a strong recommendation

1.5. Abbreviations
1.5.1. Parties

SWCC Saline Water Conversion Corporation


ILF ILF Consulting Engineers
MAPA MAPA CONSTRUCTION & TRADE COMPANY
IBK IBK Consulting Engineers
MEWA Ministry of Environment, Water & Agriculture
MOT Ministry of Transport
NWC National Water Company
SEC Saudi Electric Company
STC Saudi Telephone Company
Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 6 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

1.5.2. Institutes for Standardization

ANSI American National Standards Institute


API American Petroleum Institute
ASME American Society of Mechanical Engineers
AWWA American Water Works Association
DIN German Institute of Standardization

1.5.3. Systems / Locations / Stations

Systems:

YMWTS-1 Existing Yanbu-Madina Phase 1 WTS


YMWTS-2 Existing Yanbu-Madina Phase 2 WTS
YMWTS-3 Existing Yanbu-Madina Phase 3 WTS
YMWTS-4 New Yanbu-Madina Phase 4 WTS

Pipelines:

Line 4 (First) Mainline of new YMWTS-4 included in base and optional offer
Line 5 Second mainline of new YMWTS-4 included in base offer only

Pumping Stations:

PS1-B Existing Pumping Station PS1 for YMWTS-2 at Yanbu Plant


PS1-C Existing Pumping Station PS1 for YMWTS-3 at Yanbu Plant
PS1-D New Pumping Station PS1 for YMWTS-4 at Yanbu Plant
PS2-A Existing Pumping Station PS2 for YMWTS-1 in Musayjid
PS2-B Existing Pumping Station PS2 for YMWTS-2 in Musayjid
PS2-C Existing Pumping Station PS2 for YMWTS-3 in Musayjid
PS2-D New Pumping Station PS2 for YMWTS-4 in Musayjid

Reservoir, Terminal and Tap-off Stations:

HPR-D1 New Highpoint Reservoir Station at Mufrihat


HPR (Phase 2) Existing Highpoint Reservoir Station of YMWTS-2 at Mufrihat
HPR-C Existing Highpoint Reservoir Station of YMWTS-3
HPR-D2 New Highpoint Reservoir Station of YMWTS-4
MWT Madina West Terminal Station owned by MEWA
MST Madina South Terminal Station owned by MEWA
MET Madina East Terminal Station owned by MEWA
TSS Terminal Station Shoran owned by MEWA
TO-HPR-D1 New Tap-off Station for Branch line to HPR-D1 and MWT of YMWTS-4
TO-MST New Tap-off Station for Branch line to MST of YMWTS-4

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 7 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

1.5.4. Equipment, Hydraulic Indications

AoR Allocation of Responsibility


BP(x) Booster Pump (number x)
BEP Best Efficiency Point
CA Central Automatic
CC Control Center
CCTV Closed Circuit Television
CM Central Manual
CP Command Power
CV Control Valve
CVHFP Control Valve High Flow Protection
CVLFP Control Valve Low Flow Protection
CWS Cooling Water System
DP Demand Predictor
DS Drain Station
ESD Emergency Shut-Down
FAT Factory Acceptance Test
FC Flow Control
FCV Flow Control Valve
FOC Fiber Optic Cable
HMI Human Machine Interface
I/O Input / Output (panel)
LAL Level Alarm Low
LALL Level Alarm Low Low
LAH Level Alarm High
LAHH Level Alarm High High
LCH Level Control High
LCL Level Control Low
LCP Local Control Panel
LDS Leak Detection System
LSL Level Switch Low
LSLL Level Switch Low Low
LSH Level Switch High
LSHH Level Switch High High
LV_yy Line Valve (number yy)
LVS Line Valve Station
MAOP Max. Allowable Operating Pressure (pipe pressure bearing capacity)
MATP Max. Allowable Transient Pressure (MAOP +10%)
MOP Maximum Operating Pressure (max. HGL in Steady State Hydraulics)
MDF Maximum Design Flow Rate
MP(x) Main Pump (number x)
MTP Maximum Transient Pressure
NPSHavail Available Net Positive Suction Head (System Conditions)
NPSHrec/req Recommended / required Net Positive Suction Head (Pump Conditions)
OOS Operation Optimization System
OVR Override

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 8 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401
P Pressure
PABX Private Automatic Branch Exchange (Telephone)
PAH Pressure Alarm High
PAL Pressure Alarm Low
PCH Pressure Control High
PCL Pressure Control Low
PFD Process Flow Diagram
PHFP Pump High Flow Protection
PISH Pressure Indicator Switch High
PISL Pressure Indicator Switch Low
PK Pipeline Kilometer, horizontal length
PLC Programmable Logic Controller
PLFP Pump Low Flow Protection
PS Pump Station
PRV Pressure Relief Valve
PSH Pressure Switch High
PSL Pressure Switch Low
PPL Pipeline
P&ID Piping & Instrumentation Diagram
QBEP Flow rate at best efficiency point
Qmax Maximum possible flow rate
REC-BY Recirculation Bypass
RES Reservoir
RPM Rounds per minute
SA Station Automatic
SCADA Supervisory Control and Data Acquisition
SCS Station Control System
SD Shut-down
SDS Shut-down sequence
SM Station Manual
SP Set Point
SSS Station Safety Sequence
STATCON Station Control System
SVP Surge Vessel Plant
SVS Station Valve Sequence
SV Surge Vessel
SYS System
SYSAD System Administrator
SYSCON System Control
T Temperature
TC Telecontrol
TCS Telecontrol System
TDR Technical Document Register
TL Tank Level
TOS Tap-off Station
TO Tap-Off
UNCON Unit Control System
UPS Uninterruptable Power Supply

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 9 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401
VS Vent Station
VSD Variable Speed Drive
WAN Wide Area Network
WITCS Operation with TCS
WOTCS Operation without TCS
WL Water Level
WST Water Storage Tank
WPCC Water Pipeline Control Center
WQM Water Quality Monitoring
WTP Water Treatment Plant

1.6. Units

°C degree Celsius
bara absolute pressure
barg relative pressure, gauge pressure
db(A) Sound pressure level, decibel
gpm gallon per minute
h hour
km kilometer
m meter
Mbps Mega bit per second
m³ cubic meter
m³/d Flow rate, cubic meters per day
m³/h Flow rate, cubic meters per hour
m³/s Flow rate, cubic meters per second
masl meters above sea level
mlc Pressure, metres liquid column, according to Bernoulli formula
N Newton
Pa Pascal
s second
A, kA current, ampere or kiloampere
W, kW, MW active power, watt or kilowatt or megawatt
VA, kVA, MVA apparent power, volt-ampere, kilo or megavolt-ampere
V, kV Voltage, volt or kilovolt

2.0. REFERENCES

Package of Tender/FEED Documents


0
QA10-G-9057 Rev.2 General Specification G02 - Description of Project and Works
QC10-H-055 Rev. 4 Specification M15-HVAC Equipment
Package of Detailed Design Documents

90-UV00-H-400 Rev. 0 HVAC Basic Design Criteria


11-ZG20-S-005 Rev. A PS1-D Line4 VSD Building Guide Drawings

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 10 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

3.0. DESIGN PARAMETER:

Site Location Al-Musayjid


Site Elevation (Altitude) 440 m. Above mean sea level
Site Latitude 24° 04' 17.52'' N

DESIGN CONDITION
Out Door Temperature during summer
Design ambient Dry bulb temperature 44.0 °C
Design ambient Wet bulb temperature 24.3 °C
Daily Range 12.5 °C
Out Door Temperature during winter
Design ambient Dry bulb temperature 11.6 °C
In Door Temperature during summer & winter

Design ambient Dry bulb temperature <50.2 °C


YANBU VSD BUILDING HVAC INTERNAL DESIGN CRITERIAS
WEATHER DESIGN PARAMETERS

HOT SEASON COLD SEASON


SPACE
DB RH DB RH
˚C % ˚C %
VSD ROOM 30°C 30-60 5°C N/A
COOLING PUMP ROOM 30°C 30-60 5°C N/A

Note: Indoor/Outdoor condition during summer and winter are designed as per General
Specification G 02.

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 11 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

4.0. U VALUE FOR WALL, ROOF, DOOR & GLASS:


4.1. Coefficient of Transmission (U) for Roof:

Roof Details
Outside Surface Color………………….Medium
Absorbtivity………………………………0.675
Overall U-Value………………………....0.305 W/(m²·K)

Roof Layers Details (Inside to Outside)


Specific
Thickness Density R-Value Weight
Ht.
Layers m kg/m³ kJ / (kg K) (m²·K)/W kg/m²
Inside surface resistance 0,000 0,0 0,00 0,13000 0,0
Concrate 0,250 2400,0 1,27 0,10000 600,0
Slopıng Screed 0,800 2000,0 0,84 0,05700 160,0
Water Insulation 0,010 2000,0 1,84 0,05300 20,0
Heat Insulation 0,100 25,0 1,30 2,85700 2,5
Slopıng Screed 0,020 2000,0 0,84 0,01400 40,0
Gravel 0,500 1700,0 1,26 0,02500 85,0
Outside surface resistance 0,000 0,0 0,00 0,04000 0,0
Totals 0,510 - 3,27600 907,5

4.2. Coefficient of Transmission (U) for External Wall:


Wall Details
Outside Surface Color………………….Medium
Absorbtivity………………………………0.675
Overall U-Value………………………....0.328 W/(m²·K)

Wall Layers Details (Inside to Outside)


Specific
Thickness Density R-Value Weight
Ht.
Layers m kg/m³ kJ / (kg K) (m²·K)/W kg/m²
Inside surface resistance 0,000 0,0 0,00 0,13000 0,0
Cement Mortar 0,020 2000,0 0,84 0,01300 40,0
Heat Insulation 0,080 200,0 0,84 2,28600 16,0
Common brick 0,340 650,0 0,96 0,57100 221,0
Cement Mortar 0,020 2000,0 0,84 0,01300 40,0
Outside surface resistance 0,000 0,0 0,00 0,04000 0,0
Totals 0,460 - 3,05300 317,0

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 12 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

4.3. Coefficient of Transmission (U) for Door:

D1_2.70x3.30

Door Details:
Gross Area ..................................... 8.9 m²
Door U-Value ............................. 6.000 W/(m²·K)

D2_1.10x2.40
Door Details:
Gross Area ..................................... 2.6 m²
Door U-Value ............................. 6.000 W/(m²·K)

D3_1.36x3.30
Door Details:
Gross Area ..................................... 4.5 m²
Door U-Value ............................. 6.000 W/(m²·K)

4.4. Coefficient of Transmission (U) for Glass:

W1_4.50x0.90
Window Details:
Detailed Input ................................. No
Height .......................................... 0.90 m
Width ........................................... 4.50 m
Overall U-Value ......................... 1.500 W/(m²·K)
Overall Shade Coefficient .......... 0.400

Note: (U) Values are taken from Carrier Hourly Analysis Program 5.11 version.

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 13 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

5.0. EQUIPMENT HEAT DISSIPATION:

Zone Name Equipment load in Watts

Cooling Pump Room 1000

VSD Room-1 30000

VSD Room-2 30000

VSD Room-3 30000

6.0. LIGHTING HEAT DISSIPATION:

Zone Name Lighting load in Watts

Cooling Pump Room 126

VSD Room-1 1113

VSD Room-2 988

VSD Room-3 996

Note: See Appendix 1 for lighting loads.

7.0. OVERALL LOAD SUMMARY OF VSD BUILDING:

TOTAL (Watts)
Sensible Latent
DESCRIPTION (W) (W)
Window & Skylight Solar Loads 1907 -
Wall Transmission 2124 -
Roof Transmission 2625 -
Window Transmission 425 -
Door Loads 1803 -
Overhead Lighting 3223 -
Electric Equipment 90996 -
Safety Factor 5155 -
>> Total Zone Loads 108256 -
Central Cooling Coil 233231 -
>> Total Conditioning 341487 -

Note: Please refer Appendix-2 for Overall Load Summary.

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 14 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

8.0. SAND TRAP LOUVER CALCULATION & SELECTION:

Data :
Required Fresh Air = 19200 m³/h
Face velocity through louvers = 1.5 m/s
Minimum required face area to keep above velocity = 3.56 m²
From the Catalogue Selected size = See Appendix 3 for details
(1)

L= 1350 mm 55 in
H= 1350 mm 55 in

(2)

L= 1350 mm 55 in
H= 1350 mm 55 in

Actual face velocity = 5.333 m³/s /[(1.35m x 1.35m) x 2] = 1.46 m/s

9.0. VENTILATION CALCULATION


9.1. AS PER AIR CHANGES PER HOUR (ACPH):
9.1.1. As per Air Changes per Hour for VSD ROOM-1:
Data:
AREA OF VSD ROOM = 242 m²
HEIGHT OF VSD ROOM = 5.6m
No. OF AIR CHANGES PER HOUR = 1 ACH/h

Calculation :
Cooling Air Required = Room volume x No. of Air Changes/h
= 242 m² x 5.6 m x 1 ACH/h
Ventilation cooling air required = 1355.2 m³/h

9.1.2. As per Air Changes per Hour for VSD ROOM-2:


Data:
AREA OF VSD ROOM = 215 m²
HEIGHT OF VSD ROOM = 5.6 m
No. OF AIR CHANGES PER HOUR = 1

Calculation :
Cooling Air Required = Room volume x No. of Air Changes/h
= 215 m² x 5.6 m x 1 ACH/h
Ventilation cooling air required = 1204 m³/h

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 15 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

9.1.3. As per Air Changes per Hour for VSD ROOM-3:


Data:
AREA OF VSD ROOM = 217 m²
HEIGHT OF VSD ROOM = 5.6 m
No. OF AIR CHANGES PER HOUR = 1

Calculation :
Cooling Air Required = Room volume x No. of Air Changes/h
= 217 m² x 5.6 m x 1 ACH/h
Ventilation cooling air required = 1215.2 m³/h

Note: As per specification minimum number of air changes per hour required is 1.

9.1.4. As per Air Changes per Hour for Cooling Pump Room:
Data:
AREA OF PUMP ROOM = 28 m²
HEIGHT OF PUMP ROOM = 4 m
No. OF AIR CHANGES PER HOUR = 1

Calculation :
0
Cooling Air Required = Room volume x No. of Air Changes/h
= 28 m² x 4 m x 2 ACH/h
Ventilation cooling air required = 224 m³/h

Note: As per specification minimum number of air changes per hour required is 2.

9.2. AS PER HEAT DISSIPATION:


9.2.1. As per Heat Dissipation for VSD ROOM-1:
Data :
Q in : Heat Dissipation from Internal Load in VSD Room-1 = 6257 W
Qex : Heat Dissipation from External Load in VSD Room-1 = 30000 W
Q TOTAL : Total Heat Dissipation in VSD Room-1 = 36257 W
Cp : Specific Heat of Air = 1005 J/kg°C
ρ : Weight per Unit Volume of Air = 1.22 kg/m³
ΔT : Temperature Difference = 17 °C

V = Q TOTAL / (Cp x ρ x ΔT)


V = 36257 W / (1005 J/kg°C x 1.22 kg/m³ x 17 °C)
V = 1.739 m³/s = 6262 m³/h

Total Volume of Cooling Air Required V = 6262 m³/h


Since, the volume of cooling air as per heat dissipation greater than volume of ACPH, cooling air
flow rate is accepted as for VSD Room-1 is 6300 m³/h.
Supply Air to the VSD Room-1 = 6300 m³/h

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 16 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

Pressurized Air = 5% of Total volume of supply air


= 0.05 x 6300
= 400 m³/h

Total Exhaust Air = Total supply air - Total Pressurization air


= 6300 – 400
= 5900 m³/h

Note-1: Exhaust air shall be relieved through pressure relief damper.


Note-2: See Appendix-2 for detailed heat load calculations.

9.2.2. As per Heat Dissipation for VSD ROOM-2:


Data :
Q in : Heat Dissipation from Internal Load in VSD Room-2 = 5027 W
Qex : Heat Dissipation from External Load in VSD Room-2 = 30000 W
Q TOTAL : Total Heat Dissipation in VSD Room-2 = 35027 W
Cp : Specific Heat of Air = 1005 J/kg°C
ρ : Weight per Unit Volume of Air = 1.22 kg/m³
ΔT : Temperature Difference = 17 °C

V = Q TOTAL / (Cp x ρ x ΔT)


V = 35027 W / (1005 J/kg°C x 1.22 kg/m³ x 17 °C)
V = 1.682 m³/s = 6054 m³/h

Total Volume of Cooling Air Required V = 6054 m³/h


Since, the volume of cooling air as per heat dissipation greater than volume of ACPH, cooling air
flow rate is accepted as for VSD Room-2 is 6300m³/h.
Supply Air to the VSD Room-2 = 6300 m³/h

Pressurized Air = 5% of Total volume of supply air


= 0.05 x 6300
= 400 m³/h

Total Exhaust Air = Total supply air - Total Pressurization air


= 6300 – 400
= 5900 m³/h

Note-1: Exhaust air shall be relieved through pressure relief damper.


Note-2: See Appendix-2 for detailed heat load calculations.

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 17 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

9.2.3. As per Heat Dissipation for VSD ROOM-3:


Data :
Q in : Heat Dissipation from Internal Load in VSD Room-3 = 5692 W
Qex : Heat Dissipation from External Load in VSD Room-3 = 30000 W
Q TOTAL : Total Heat Dissipation in VSD Room-3 = 35692 W
Cp : Specific Heat of Air = 1005 J/kg°C
ρ : Weight per Unit Volume of Air = 1.22 kg/m³
ΔT : Temperature Difference = 17 °C

V = Q TOTAL / (Cp x ρ x ΔT)


V = 35692 W / (1005 J/kg°C x 1.22 kg/m³ x 17 °C)
V = 1.712 m³/s = 6165 m³/h
Total Volume of Cooling Air Required V = 6165 m³/h
Since, the volume of cooling air as per heat dissipation greater than volume of ACPH, cooling air
flow rate is accepted as for VSD Room-3 is 6300 m³/h.
Supply Air to the VSD Room-3 = 6300 m³/h

Pressurized Air = 5% of Total volume of supply air


= 0.05 x 6300
= 400 m³/h
Total Exhaust Air = Total supply air - Total Pressurization air
= 6300 – 400
= 5900 m³/h
Note-1: Exhaust air shall be relieved through pressure relief damper.
Note-2: See Appendix-2 for detailed heat load calculations.

9.2.4. As per Heat Dissipation for Cooling Pump Room:


Data :
Q in : Heat Dissipation from Internal Load in Pump Room = 782 W
Qex : Heat Dissipation from External Load in Pump Room = 1000 W
Q TOTAL : Total Heat Dissipation in Pump Room = 1782 W
Cp : Specific Heat of Air = 1005 J/kg°C
ρ : Weight per Unit Volume of Air = 1.22 kg/m³
ΔT : Temperature Difference = 17 °C

V = Q TOTAL / (Cp x ρ x ΔT)


V = 1782 W / (1005 J/kg°C x 1.22 kg/m³ x 17 °C)
V = 0.086 m³/s = 300 m³/h
Total Volume of Cooling Air Required V = 300 m³/h
Since, the volume of cooling air as per heat dissipation greater than volume of ACPH, cooling air
flow rate is accepted as for Cooling Pump Room is 300 m³/h.
Supply Air to the Cooling Pump Room = 300 m³/h

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.


KINGDOM OF SAUDI ARABIA Page: 18 of 26

Saline Water Conversion Corporation


YANBU-MADINA PHASE 4 WTS
Subject: PUMPING STATION PS2-D LINE 4 VSD BUILDING Spec. No.
HVAC DESIGN CALCULATION REPORT ILF

Rev First Rev. A 0 Document Number


Index
Issue Date: 21.10.19 31.12.19 12-UV00-J-401

Pressurized Air = 5% of Total volume of supply air


= 0.05 x 300
= 100 m³/h
Total Exhaust Air = Total supply air - Total Pressurization air
= 300 – 100
= 200 m³/h
Note-2: See Appendix-2 for detailed heat load calculations.

10.0. PRESSURE RELIEF DAMPER SIZING:


10.1. Pressure Relief Damper Sizing for VSD ROOMS:
Air Required to Relief = Pressurization Air
= 400 m³/h
= 112 L/s
Pressure difference in relief damper (PRD) @ (AP)= 50 Pa
According to “Air Leakage Methods” from the Ashrae Handbook 2017;

(SI) Q = 840 x A x (AP)1/2

Where,
• Q is the airflow leakage in Liters per Second (L/s)
• A is the total leakage area in Square Meters
• AP is the differential pressure in Pascals

A = 228 L/s / 840 / (50 Pa)1/2


A = 0.02 m²

At 0.02 m² area, selected size as per catalogue


Selected size of the PRD = W = 200 mm, 8 in
H = 200 mm, 8 in See Appendix 5 for details

Note: There are 3 Relief Dampers in total. Each VSD Room has a Relief Damper.

11.0. LIST OF APPENDICES:


APPENDIX NO. TITLE
0 APPENDIX-1 LIGHTING LOAD DETAILS
APPENDIX-2 HEAT LOAD CALCULATION & PSYCHROMETRIC GRAPH
APPENDIX-3 SAND TRAP LOUVER SELECTION
APPENDIX-4 AIR CONDITIONING UNITS & AIR COOLED CONDENSING UNITS
SELECTION
APPENDIX-5 PRESSURE RELIEF DAMPER SELECTION
APPENDIX-6 VAV SELECTION
APPENDIX-7 PRESSURE LOSS CALCULATION IN DUCT
APPENDIX-8 DUCT SIZING CALCULATION

Engineering Subcontractor Subcontractor Subcontractor

IBK MAPA CONSTRUCTION & TRADE Co. Inc.

Vous aimerez peut-être aussi