3D Prototype Project 3A UPDATE 01-Jan-20 11:49

Activity ID Activity Name Original Duration Activity % Start Finish Actual Total Cost Budgeted Total Cost 2020 2021
Complete
A S O N D J F M A M J Jul A S O N D J F
3D Prototype Project 138 02-Jul-12 17-Jan-13 P0.00 P1,167,033.86

PD9001 Gate 1 - Idea Screen 0 0% 30-Jul-12 P0.00 P0.00


PD9002 Gate 2 - Second Screen 0 0% 12-Sep-12 P0.00 P0.00
PD9003 Gate 3 - Go to Development 0 0% 11-Oct-12 P0.00 P0.00
PD9004 Gate 4 - Go to Testing 0 0% 19-Dec-12 P0.00 P0.00
PD9005 Gate 5 - Go to Launch 0 0% 17-Jan-13 P0.00 P0.00
Scoping Stage 20 02-Jul-12 30-Jul-12 P0.00 P40,000.32
PD1000 Scope New Product Idea 21 0% 02-Jul-12 30-Jul-12 P0.00 P40,000.32
Business Case Stage 30 30-Jul-12 12-Sep-12 P0.00 P74,655.23
PD1010 Analyze New Product 12 0% 30-Jul-12 16-Aug-12 P0.00 P38,480.70
PD1020 Define Business Case 19 0% 16-Aug-12 12-Sep-12 P0.00 P36,174.53
Development Stage 21 12-Sep-12 11-Oct-12 P0.00 P864,958.12
PD1030 Design New Product 12 0% 12-Sep-12 28-Sep-12 P0.00 P47,735.60
PD1040 Develop New Product * 14 0% 21-Sep-12 11-Oct-12 P0.00 P817,222.52
Testing and Validation Stage 31 11-Oct-12 26-Nov-12 P0.00 P72,794.58
PD1050 Test New Product 32 0% 11-Oct-12 26-Nov-12 P0.00 P72,794.58
Launch Stage 36 26-Nov-12 17-Jan-13 P0.00 P114,625.60
PD1060 Commercialize New Product 17 0% 26-Nov-12 19-Dec-12 P0.00 P78,583.65
PD1070 Evaluate New Product 21 0% 19-Dec-12 17-Jan-13 P0.00 P36,041.96

Project Baseline Bar Remaining Work Milestone Page 1 of 1 TASK filter: All Activities

Actual Work Critical Remaining Work Summary © Oracle Corporation