Vous êtes sur la page 1sur 15

SHRIRAM EPC LTD.

DAILY PROGRESS REPORT


i Project Start Date:- 04.12.2018 CLIENT :-
ii Project End Date:- 03.09.2021 CONSULTANT:-
iii Project Name :- Dhanbad Water Supply Scheme Phase-I REPORT DATE:
iv Weather Report :- Cold & Sunny HOLIDAY
MAN POWER - MACHINE - MATERIAL DESCRIPTION
Manpower Strength Machine Description Materi
Manpower Opening
No. of Labour Machine Description Qty Working Material
Balance
i Skilled 15 JCB 4 1 Cement (Bag) 1765
ii Un-Skilled 88 Hydra 2 1 Sand (m³) 92
iii Surveyor 5 JCB Breaker 3 0 Aggregate (m³) 30
iv - Tractor 4 1 Steel (MT) 7.502
Truck 1 1
Tractor Breaker 7 4
Mixer Machine 1 0
Total 108 Total 22 8
1.Rising & Gravity Mains.
Supply Details Laying Details
Sl No Description of Works Pipe Size BOQ Qty.
Previous Today Cumulative Previous Today
100 mm Dia 0 - - - - -
150 mm Dia 0 - - - - -
200 mm Dia 0 - - - - -
250 mm Dia 580 - - - - -
Supply, Laying,Testing and
Commissioning of Clear 300 mm Dia 5618 - - - - -
1 Water Rising and Gravity 350 mm Dia 1587 - - - - -
Main Pipelines(DI-K9)
400 mm Dia 8417 - - - - -
450 mm Dia 1839 - - - - -
500 mm Dia 3347 - - - - -
600 mm Dia 4,426 - - - - -
Total Length 25,814 0 0 0 0 0
SHRIRAM EPC LTD.
2. Distribution Pipelines(19 Zones)
Supply Details Laying Details
Sl No Description of Works Pipe Size BOQ Qty. (Mtr)
Previous Today Cumulative Previous Today
100 mm Dia 284712 206202.0 0 206202 35692.50 575.26
150 mm Dia 42521 - - - - -
200 mm Dia 19597 - - - - -
250 mm Dia 9897 - - - - -
Supply, Laying,Testing and 300 mm Dia 9443 - - - - -
1
Commissioning of 350 mm Dia 4523 - - - - -
Distribution Pipelines(DI- 400 mm Dia 4469 - - - - -
K7) Total Nos. of Zone- 19
450 mm Dia 1513 - - - - -
500 mm Dia 2854 - - - - -
600 mm Dia 295 - - - - -
Total Length 379824 206202 0 206202 35692.50 575.26

2 Fittings & Specials 429000.4 (Kg) 38436 0 38436 3784 34


SHRIRAM EPC LTD.
Earthwork in excavation (As per I.S 3114 /
1965 for laying of different
Description types and sizes
of Works BOQ Qty. Previous Today Cumulative
of pipes so as to give one meter average
cover over in theexcavation
socket of of pipe with disposal
3 Earthwork
Extra for earthwork in all kinds
foundation
oflead
soil for 220849.04 22486.275 362.4138 22848.6888
of excavated
trenches earth within
of toewall, spillway, initial
head and
regulator
each
lift asadditional
intake per
wellspecificationlift of 1m
and outlet andordirection
etc.as part
per thereof
designof
4 over the initial
Engineer-in-Charge lift of
section in ordinary or soft rock(b)1.5m
As as
per per
classification
(vide 191.38
specification
of soil item -Band
classification of direction
soil item-C) ofand
Engineer-in-
disposal of
5 Charge. 24538.78
soil (beyond 50 M away from the edge of
the trenches) toolswith andinitial leadroadofas150 wellMrestoring the same as
6 Supplying cutting
and initial lift of 1.5 m
per specification and direction of E/I. as per
specification
Pucca Road (Except and direction
black topofonly E/Itaken
(where out
blasting
7 material is not
be required).
Water bound macadam road (takenasout
to used) for cutting road per 11245.47
Dismantling
requirement.
material will plain
be cementfor
used) or lime
cutting concrete
road
8 Providing
work coarsestacking
clean sand in filling in 17492.96
as perincluding
foundationrequirement
trenches and
or in
serviceable
making
plinth good the
including
materials in countable stacks within 15
9 same.
ramming and watering 1936.72 218 21 239
meter lead
Providing and
PCC disposalin
M-150 oflayers
inwithnominal
not
un-serviceable mix of
exceeding
Providing 150mm
designation thick75A one all leads
brick and
flat
10 materials
(1:2:4) in with all leadswith
foundation all complete
approved as per 1811.77
lifts
solingincluding
directionjointof costwith
filled
E/I of all materials,
local sand labour,
including
11 quality
royalty
cost of stones
and taxes taxes,
of watering, chips
all complete20 mm
royalty, to
asallper 6 mm
complete 24156.94
size graded
Earthwork
building in and
back
specification
as per building clean
filling
and
specification coarse
the sand
trenches
direction
and of
directionof
E/IFM
afterof
Providing
12 laying coarse
2.5 todifferent clean sand in filling in
(mode
E/I.
foundationof3.0 including
measurementtypes and
trenches
screening,
sizes ofshuttering,
incompacted
orexcavation
pipes with
volume) 3623.54
mixingremoved
earth cement concrete
during inplinth
mixerincluding
and
within
13 ramming inand 225339.07 22171.46 357.34 22528.80
placinglead
initial andwatering
position,lift as in specification
vibrating,
per layers not and
striking,
exceeding 150mm thick with all leads and
14 curing,
design of taxes and royalty
Engineer -in- chargeall complete
(for as per 31335.48
lifts including
building cost
specification
classification of soilofitem
all
and materials,
& B ) labour,
Adirection of E/I
3. Consumer
royalty and taxes Survey
all complete as per
building specification and direction of E/I
SL No. (mode ofDescription
measurement compactedUnits volume) BOQ Quantity Previous Today Cumulative Remarks

Consumer Survey Sample 55245 42369 449 42818

4. ELEVATED SERVICE RESERVOIR


ESR-1 ESR-3 ESR-4 ESR-5 ESR-6
(18 Lakh Litre) ESR-2 (13 Lakh Litre) (17 Lakh Litre) (24.5 Lakh Litre) (24 Lakh Litre)
Sl No Description Units (21 Lakh Litre) Tetulmari near
Chatabad near Jamia Jila Parishad Gadeyriya WTP JMADA
Liloro Asthan sarswati sisu
Masjid Bhandardih Plant Officer Colony
mandir

1 soil analysis (SBC ) Job Completed Completed Completed Completed Completed Completed
under
2 Excavation Job - Completed Completed - Completed progress
3 Anti-termite Spray Job - Completed Completed - 6 Nos Completed -
SHRIRAM EPC LTD.
4 PCC Job - Completed Completed - 6 Nos Completed -

5 RCC work in foundation Job - Completed Completed - - -

6 Pedestals Job - Completed 50% Completed

7 Grade Beam Job - 25% Completed

8
1st half of staging height Job - - - - -
including room roof slab
Balance staging botton
9 dome circular beam , head job - - - - - -
beam and conical wall
SHRIRAM EPC LTD.
10 Vertical Side Wall job - - - - - -

11 Top dome job - - - - - -

12
C.I/D.I pipe fitting of inlet job - - - - - -
valve
13
Fixing of C.I , D/F pipes job - - - - - -
specials and sluice valve
Fixing of MS Ladders ,
14 railling,lightning arrester, job - - - - - -
and water level indicator
Wood work, Brick work
15 and steel work in door and job - - - - - -
windows
Snowcem/painting ,white
16 washing, colour, washing job - - - - - -
etc
Testing of full hydraulic
17 structure of elevated water job - - - - - -
tank

18
Commissioning and Trail job - - - - - -
run
5. Compound Wall
SL No. Description Units BOQ Quantity Previous Today Cumulative Rem
1 Excavation m 3
352.64 226.6 0.0 226.6
2 Removal of Unserviceable Soil m3 222.72 203.9 0.0 203.9
3 PCC-M 15 m 3
68.05 23.6 0.0 23.6
4 RCC- M 20 work in foundation m3 163.95 22.6 0.0 22.6
5 Steel Consumption MT 16.39 3.73 0.0 3.73
6 Brick Work m3 197.97 70.3 0.0 70.3
7 Plaster m² 1741.55 232.3 0.0 232.3
SHRIRAM EPC LTD.
6. House Service Connections
SL No. Description No of Quantity Previous Today Cumulative Rem
1 House Service Connections 55245
AM EPC LTD.
Date 12/31/2019
JUIDCO Ltd.
NJS Engineers India Pvt. Ltd.
1/2/2020
-
ACHINE - MATERIAL DESCRIPTION
Material Details
Received Issued Balance

3650 1885 1765


250 158 92
255 225 30
58.932 51.430 7.502

Laying Details
Remarks
Cumulative
-
-
-
-
-
-
-
-
-
-
0
AM EPC LTD.

Laying Details
Remarks
Cumulative
36267.76
-
-
-
-
Pipe laying progress hampered
due to stoppage of work by BCCL
- in 6 zones.
-
-
-
-
36267.76

3818.00
AM EPC LTD.
Cumulative

22848.6888

239

22528.80

Remarks

ESR-7 ESR-8
(18 Lakh Litre) (20.5 Lakh Litre)
JMADA JMADA
Officer Colony Officer Colony

Completed Completed

- -

- -
AM EPC LTD.
- -

- -

- -

- -
AM EPC LTD.
- -

- -

- -

- -

- -

- -

- -

- -

- -

Remarks
AM EPC LTD.

Remarks
MATERIALS DETAILS FOR JUIDCO
SL. CEMENT SAND AGGREGATE 8 MM 10 MM
SITE
NO. PUR USED PUR USED PUR USED PUR USED PUR
1 Near Talab,Chattabad Masjid Road

2 Way to Lilori Sthal,Opposite Lilori Park 2400 704 140.28 61 98.44 82 1.5 0.8 4.21
Near Sarsawati Shisu Mandir,
3 800 730 70 66 107 105 4.5 4 5.00
Tetulmari(Baba Chowk)
4 Near Chetudih Malkera Road,Chhatabad
In & Around Gareriya Water Treatment
5 15 1 1
Plant

6 JMADA Officers Colony

7 JMADA Officers Colony

8 JMADA Officers Colony

3 Tetulmari- Boundry Wall 450 436 40 30 50 37 1.5 1.4 0.5

TOTAL 3650 1885 250 158 255 225 8 6 10

BALANCE 1765 92 30 1.3 -7.6


O
10 MM 12 MM 16 MM 20 MM
USED PUR USED PUR USED PUR USED

2 3.45 2.6 6.32 3.5 6.55 1.8


15 8.00 10.00 7.00 4 8.00 4

0.3 2.2 1.9 0.2 0.15 0 0

17 14 14 14 8 15 6

-7.6 -0.8 6 9
Laying Details as on date
Date Today Cumulative Area
8/19/2019 16.5 16.5 Zone-1
8/20/2019 55 71.5 Zone-1
8/22/2019 82.5 154 Zone-1
8/23/2019 165 319 Zone-1
8/24/2019 38.5 357.5 Zone-1
8/26/2019 77 434.5 Zone-1
8/27/2019 148.5 583 Zone-1
8/28/2019 109.5 692.5 Zone-1

Vous aimerez peut-être aussi