Construction Sequence

SN Construction Sequence
A Building
(a) Civil-Structural
1 Layout demarkation
2 Excavation
3 PCC
4 RCC-Foundation
5 RCC-Plinth
6 RCC-Columns
7 Staircase
8 Roof-Shuttering, Reinforcement
9 Electrical-Conduit,GI/MS Box
10 RCC-Roof
(b) Terraces & Finishing
1 Mumty
2 Overhead tank
3 Machine Room
4 Parapet
5 Coping
Foundation for machines, Solar panels, Ventilations fans,
6 etc
7 Water proofing
8 Screed-M15
PUF insulation/Heat Resistant Tiles( Puf-
Hospital+Academic+Married+Single and rest with HRT in Type A,
9 B, C, D, DB)
10 Block works
11 wall conduiting and GI Box fixing
12 Door Frame Fixing
13 Wall plaster
14 Ceiling plaster
15 Floor Tiling
16 Window Fixing
17 Protection of Tiles/Stone
18 POP
19 Putty and OBD, Painting
20 Door Frame polishing
21 Electrical wiring, Swich, Sockets
22 Final Coat-Painting
B Plumbing and Finishing-Toilets and Kitchen
1 Block works
2 Wall conduiting and GI Box fixing
3 Kitchen counter
4 Door Frame Fixing
5 Soil, waste pipe laying in Bathroom and kitechen
6 Water supply pipe laying
7 Soil and waste risers pipe
8 Water supply riser pipe
9 Testing-water, smoke, pressure
10 water proofing-
11 Wall plastering and Tiles-One job
12 Floor Tiling
13 Window Fixing
14 POP
15 Putty and OBD, Painting
16 Door Frame polishing
17 Door shutter Fixtures
18 Electrical wiring, Swich, Sockets
19 Plumbing Fixtures
20 Electrical Fixtures
21 False Ceiling
22 Final Coat-Painting
C Finshing-Residential
1 Block works
2 Wall conduiting and GI Box fixing
3 Door Frame Fixing
4 Wall plaster
5 Ceiling plaster
6 Floor Tiling
7 Window Fixing
8 Protection of Tiles/Stone
9 POP
10 Putty and OBD, Painting
11 Fire Fighting-Risers
12 Door Frame polishing
13 Door shutter Fixtures
14 Electrical wiring, Swich, Sockets
15 Plumbing Fixtures
16 Electrical Fixtures
17 FHC-Fixtures
18 Final Coat-Painting
19 External Plaster
20 External Painting
D Finshing-Hospital and Academic Block
1 Block works
2 HVAC-Ducting
3 Wall conduiting and GI Box fixing
4 Wall plaster
5 Ceiling plaster
6 Acoustics-rough-in
7 Floor Tiling
8 Door Frame and Shutter
9 Protection of Tiles/Stone
10 POP
11 Putty and OBD, Painting
12 Fire Fighting-Risers
13 Door Frame polishing
14 Electrical wiring, Swich, Sockets
15 Plumbing Fixtures
16 Electrical Fixtures
17 FHC-Fixtures
18 Final Coat-Painting
19 Acoustics-Fixtures
20 HVAC- Fans, AHU, Chillers
21 Lifts Installation
22 External Plaster
23 External painting
24 Handover-snag list, commissioning

E Infra
1 STP
2 ETP
3 ESS
4 UGT and Pump room
5 Road
6 Electrical-Road Crossing,
7 Electrical- Cables Routing and Terminations
8 Drainage-Sewerage
9 Drainage-Storm water, RWH
10 Landscape/hardscape
11 Horticulture
F Statutory compliances
1 Electrical
2 Lifts
3 Water connenctivity
4 Sewer Connectivity
5 Completion certificates