Appendix 2

LEEDS TEACHING HOSPITALS NHS TRUST

BUSINESS CASE FORMAT

FOR CAPITAL INVESTMENT

1. INTRODUCTION AND SUMMARY

Brief outline of business case and summary of recommendation.

2. BACKGROUND

Outline of the original mandate for the project – explaining the impetus for the
project.

Statements of constraints within which the project must operate such as town
planning requirements, DH requirements, legislation etc.

Other background information.

3. STRATEGIC CONTEXT

Strategic context and drivers for the project as well as fit with the organisational
strategy.

4. OPTIONS APPRAISAL

4.1 Non financial options appraisal


• Outline of long list of options identified
• Basis of short listing of options if some are discounted from the long list
• Do nothing option must be identified
• Non financial appraisal of each option including at least:
o Impact on clinical services provision (both direct and associated
services)
o Impact on clinical support services
o Impact on non clinical services
o Impact on workforce and training
o Impact on estate and infrastructure (including IT)

4.2 Financial options appraisal


a. Financial appraisal of each option
b. Financial assessment of risk adjusted value for money of each
short listed option over the life of the project
c. Sensitivity analysis if required to look at different possible outcomes
under different scenarios
Page 1 of 3
/opt/scribd/conversion/tmp/scratch2520/46915835.doc
d. Consideration of different financing methods where appropriate
e. Identification of preferred option

4.3 Identification of preferred option

f. Comparison of the costs and benefits of each option to identify a


preferred option

5. PREFERRED OPTION

Further details of preferred option if required.

6. AFFORDABILITY

Affordability of preferred option (net position of costs and income) covering whole
life

• Statement of capital costs and constituents, with source of funding

• Statement of revenue costs and constituents, with source of funding.

7. RISKS AND ISSUES

Outline of each key risk with probability and impact (£).

Risk log either attached to case or available showing all risks with probability,
impact (£), proximity and risk management plan for each risk.

Outline of all major issues identified to date.

8. EXTERNAL APPROVALS

Statement of any external approvals and support required and whether these
have been obtained, such as SHA approval, commissioner support.

9. BENEFITS EXPECTED

Outline of key expected benefits against current position.

Benefits can be ‘negative’ such as setting out what will happen if the project is
not done.

All benefits should be expressed in clearly measurable terms.

Page 2 of 3
/opt/scribd/conversion/tmp/scratch2520/46915835.doc
10. TIMESCALES

Outline of project timescales including all key milestones.

11. TOLERANCES AND CHANGE CONTROL

Outline of any tolerances on the cost/quality/benefits/timescales etc of the


project.

Outline of how changes on the project will be authorised.

12. KEY RESPONSIBILITIES

Outline of
• Executive responsible
• Project manager
• Project structure
• Project team

Statement of how the project itself (rather than its outcomes) will be funded.

Outline of stakeholder involvement.

Outline of communications plan.

13. POST PROJECT EVALUATION

Statement of who will be responsible for carrying out post project evaluation and
assessing the realisation of expected benefits.

14. CONCLUSION AND RECOMMENDATIONS

Concluding statements.

Recommendations for authorisation from HQMG/Trust Board.

Page 3 of 3