O023 Labour to cut, bend & fix steel bar tonne 550.00 26/04/2011
O027 Labour to lay damp proof course, 230mm wide m 0.30 26/04/2011
O028 Labour to lay cement & sand acreed to floor; m2 5.50 26/04/2011
25mm thick, steel trowel
O029 Labour to plaster wall; cement & sand; 28mm m2 12.50 26/04/2011
thick; 3 coats; external
O030 Labour to plaster wall; cement & sand; 28mm m2 8.50 26/04/2011
thick; 3 coats; internall
O031 Labour to lay tiles; homogeneous m2 16.00 26/04/2011
O033 Labour to install timber door frame for single no 36.00 26/04/2011
leaf door including sub-frame
O034 Labour to install timber door frame for double no 39.00 26/04/2011
leaf door including sub-frame
O035 Labour to install timber door; single leaf no 50.00 26/04/2011
Piling
OO02 Extracting
O076 Allow for mobilisation of labour, plants and Item 18,000.00 16/12/2008
hydraulic hammer piling equipment to site,
moving around and demobilisation from site
O077 Handle, sling and pitch initial and extension no 64.00 16/12/2008
vertical piles not exceeding 12m long
O078 Handle, sling and pitch initial and extension no 80.00 16/12/2008
raked 1:4 piles not exceeding 12m long
O079 Drive vertical pile to the required depth m 45.00 16/12/2008
O080 Drive raked 1:4 piles to the required depth m 60.00 16/12/2008
O082 Cut off piles to the required level and roughen no 120.00 16/12/2008
inner surface of pile
O083 Provide labours, plants, temporary staging, no 15,000.00 10/12/2008
kentledge, testing equipment and load 500mm
diameter test pile to 1200KN
O084 Subsequent load test no 10,000.00 10/12/2008
O089 Cut off pile head, strip concrete and exposed no 39.00 23/12/2008
reinforcement to a length of 600mm including
bending and binding exposed reinforced rods to
the reinforcement in the pile cap
O090 Supply and fix 'concrete plug' no 70.00 23/12/2008
O096 Cut off and remove surplus length and strip off no 37.50 23/12/2008
pile head, bend back reinforcement for
connection
O097 Initial pile test to 1100KN no 14,500.00 23/12/2008
O100 Allow for the provision of necessary hydraulic Item 15,000.00 19/02/2009
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
O101 Allow for moving and handling piling Item 3,000.00 19/02/2009
equipment about the site
O102 Allow for submission of records of all piles Item 3,700.00 19/02/2009
O103 Allow for the provision of necessary testing Item 4,750.00 19/02/2009
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
O104 Handle, transport, pitch and drive initial and m 16.50 19/02/2009
extension pile to the required depth
O105 Fillet weld pile joint no 34.00 19/02/2009
O106 Cut off pile head to required level, strip off no 35.80 19/02/2009
concrete to expose reinforcement, bend the pile
reinforcement excess length to dispose to
Contractor's own dump site
O107 Initial pile test to twice working load of 1500KN no 29,030.00 19/02/2009
O114 Handle, transport and pitch only, 12m long no 43.00 16/12/2008
initial/extension pile
O115 Drive only initial/extension pile m 14.50 16/12/2008
O117 Cut off pile head and cart away surplus length no 35.00 16/12/2008
from site
O118 Preliminary load test 2 x 1000KN no 14,166.67 16/12/2008
O120 Allow for moving and handling jacked-in piling no 42,500.00 23/12/2008
equipment, plants, tools at the site as often and
whenever necessary for the operation of the
whole piling operation including for moving the
plants, tools and ancillary equipment from
different levels of the site and all necessary
staging, platform and any idling standing time.
O121 Handle, transport, pitch and drive initial and m 29.50 23/12/2008
extension pile to the required depth
O122 Fillet weld pile joint no 22.75 23/12/2008
O123 Cut off and remove surplus length and strip off no 29.50 23/12/2008
pile head, bend back reinforcement for
connection
O124 Initial load test to 660KN no 10,350.00 23/12/2008
O130 Cut off pile head and cart away surplus length no
from site
OO11 150 x 150mm R.C pile
O131 Allow for the provision of necessary hydraulic Item 4,500.00 19/02/2009
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
O132 Allow for moving and handling piling Item 1,000.00 02/01/2009
equipment about the site
O133 Allow for submission of records of all piles Item 2,000.00 02/01/2009
O134 Allow for the provision of necessary testing Item 10,000.00 02/01/2009
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
O135 Handle, transport, pitch and drive initial and m 4.38 19/02/2009
extension pile to the required depth
O136 Fillet weld pile joint no 8.83 19/02/2009
O137 Cut off pile head to required level, strip off no 16.83 19/02/2009
concrete to expose reinforcement, bend the pile
reinforcement, excess length to dispose to
Contractor own dump site
O138 Subsequent load test to twice working load of no 5,250.00 19/02/2009
400KN
Concretor
O147 150mm thick ground floor slab and apron slab m3 19.00 03/12/2008
Bar Bender
O158 In ground floor slab, apron slab, trench slab, m2 1.30 03/12/2008
suspended floor slab and roof slab
Formwork
O161 To sides and soffits of suspended floor beam and m2 13.00 03/12/2008
roof beam
O162 To sides and soffits of suspended floor slab m2 13.00 03/12/2008
O167 Hollow core slabs & planks in thickness 360mm m2 4.60 26/02/2009
O196 Concrete G40 to beam infill & beam top m3 340.00 31/12/2008
Bricklayer
Plasterer
Door
Pavior
OO43 Mason
OO44 To floor
O240 25mm thick cement and sand render with steel m2 5.40 04/12/2008
trowelled finish to a smooth and level surface
O241 20mm thick cement and sand base screed with m2 5.40 04/12/2008
steel trowelled finish to a smooth and level
surface to receive finishing
Tiling
Roofer
O260 Cleats, stiffeners and plates and the like kg 0.90 04/12/2008
OO55 Roofer
O268 Lay concrete roof tile to pitch not exceeding 30 m2 6.00 03/12/2008
degree
O269 Lay metal deck to pitch not exceeding 30 degree m2 5.00 03/12/2008
O270 Lay 50mm thick fibre wool insulation & wire m2 1.50 03/12/2008
mesh netting to slope
O271 Lay sisalation to slope m2 1.00 03/12/2008
Ceiling Installer
Sanitary
O279 Wall hung handicap wash basin complete set no 45.00 24/12/2008
O283 Hand bidet with flexible hose complete set no 20.00 24/12/2008
O287 Stainless steel floor trap complete with insect no 10.00 24/12/2008
cage, size 150mm x 150mm
O288 40mm diameter stainless steel grab rail for OKU no 35.00 24/12/2008
WATER TANK
Scaffolder
O292 Erect frame including cross braces, base plate frame 6.00 27/11/2008
and joint pin
O293 Dismantle frame, cross braces, base plate & frame 3.00 27/11/2008
joint pin including stacking up properly directed
on site
O294 Fix 6.0m g.i pipe bracing including all no 6.00 27/11/2008
accessories and coupler
O295 Dismantle 6.0m g.i pipe bracing & accessories no 4.00 27/11/2008
and coupler including stacking up properly as
directed on site
O296 Fix 3.0m g.i pipe bracing including all no 3.00 27/11/2008
accessories and coupler
O297 Dismantle 3.0m g.i pipe bracing & accessories no 2.00 27/11/2008
and coupler including stacking up properly as
directed on site
O298 Fix wall tie including drilling hole for anchor no 4.00 27/11/2008
bolt (bolt by Main Contractor)
O299 Dismantle wall tie including making good bolt no 2.00 27/11/2008
hole
O300 Fix netting size 6'0"x17'0" including tying in pc 10.00 27/11/2008
position by wires
O301 Dismantle netting including rolling up properly pc 6.00 27/11/2008
and return to store as directed
Drainage
O302 Concrete base & P.C half round drain m 18.00 27/11/2008
OO60 Gutter
Road furniture