Logo MONTHLY SUMMARY DASHBOARD Run date 03.11.

09

PROJECT HEADLINES
Project : Al Raha Beach - Al Muneera Key Design Issues:
Project Id. : CC001 Poor quality of VSL design / detailing to podium leading to errors on site causing delays - increased QA from VSL to address.
Logo Main Contractor : AL-FUTTAIM CARILLION Workpackage design interfaces - workshops ongoing to resolve.
Contract Type : NEC 3 - Option C Target Cost = Immediate Action Req'd Programme Progress:
Current Stage : Construction - post contract = Action within 14 days Balance of J&H shop drawings to be submitted for approval 5th Nov. Team visit China to inspect PMU test early Nov.
= OK Drake and Scull drawing and material submission programme confirmed - submissions following to suit.
Approvals / Information Required.
PROGRESS ADM approval of remaining post tension shop drawings. Clarification on provision of access panels or lay in grid ceilings
Temporary Works Design Summary Current Abu Dhabi Municipality Submissions Progress Updated blockwork set out drawings basement and ground floors. Release of balance of MEP fixtures set out drawings for townhouses
Permit Week req'd on and villas. . Signage and external lighting drawings for construction req'd. Home Automation PMI required to allow final containment
No. Class Description Action Issued Permit Rec'd 1. Project Pre-qualification (Consultant)
Pending Site design to be issued for construction.
Affection Plan: Obtained from Client 1
6 A Crane Base √ √ 0 2 2. PRELIMINARY Concept Design Approval (Consultant) 2 Key Procurement Issues
3a. Temporary Building Permits (Contractor)
8 B Blwk Pile Caps √ √ 0 Accurate scoping of remaining packages. Design docs for following packages collated for issue during November - roller shutter doors,
Mobilization Permit Application 3a
9 A Slipform (BRM) √ √ 0 5 landscaping - hard and soft, glazed shower partitions and doors, louvres. Clarification on specific items required from WME in respect of
Excavation & Shoring Permit Application 3a louvres, shower screens and metal doors.
10 A Tables (Aluma) √ √ 0 11 Piling & Foundations Permit Application 3a
11 A Formwork(Peri) √ √ 0 5 Substructure Permit Application 3a Key Cost Plan Issues
12 De-watering 3b. Final Design Approval (Consultant)) Incomplete design leading to additional scope and consequential increase in package value after award
Conc placing Superstructure Towers 3b
13 A
booms
13 Original cost plan allowance both quants and cost not matching latest design information eg wet areas waterproofing
√ √ 0 Superstructure Podium, Townhouses, Villas & Retail 3b
14 A Hoists √ √ 0 15 4. Building Permit (Contractor) Impact of numerous design changes introduced by both AFC and consultant.(refer to separate register) weekly rev
Superstructure Towers 4
15 A Load Platforms √ √ 0 16
Superstructure Podium, Townhouses, Villas & Retail
Risk Areas : Recommended actions Status
4
MV package re-tendered - room layouts on hold pending selection ALDAR to confirm MV contractor, WME to update substation footprint to suit Ongoing

Sufficient WME design resource to complete reviews of tenders, shop Ongoing


KEY: drawings and respond to RFI's . (impact of WME lump sum contract) Continue to monitor against programme and report any slippage to Turner

Receipt of complete design info from WME where IFC incomplete eg Ongoing
GREY = Submission being prepared. Early warning raised. Turner to ensure that design information released.
blockwork, MEP set out, external lighting and signage.
YELLOW = Submitted / Submission Being Processed Meeting held with VSL - add resource to be provided to address - continue to
Reduction in quality of VSL detailing leading to delays to approvals weekly rev
monitor
Site Wide Material Submittal Summary GREEN = Approved RED = Not Approved Headline News
Total Submitted - 451
Note: Please refer to WME schedule for detailed submissions.
PMI-P received re mock up apartments - design issues being highlighted which should assist with resolution project wide
Status
Returned Material sample review process has been adjusted to incorporate Aldar review of materials with visual impact
A B C Pending Info Only Updated WME wall set out and MEP set out drawings being released for construction.
127 162 65 53 44 Instruction awaited from Turner in respect of LEED cancellation. Gap analysis circulated for info.
28% 36% 14% 12% 10% Shop Drawings Summary Construction Stage
Status
Subcontractor Total Submitted IFC - Information for Construction 100% - in respect of RC frame and Fit-Out
AFC Raised Closed Open A B C Pending Area
Internal TQs RFI Summary 780 717 63 Swissboring 24 **** 16 0 0 2 ARCH STRUCT MEP
Remarks
92% 8% VSL 633 592 6 0 35 TOWER - AA P A P A P A
WME
Site Raised Closed Open Closed Open BRM 15 5 8 2 0 Superstructure frame 28.01.09 28.01.09 13.12.08 Structure Frame complete
Raised
250 212 38 RFI Summary 127 111 16 AFC (615 +SW) 253* 47 183 8 9 superstructure fit-out 28.01.09 28.01.09 15.03.09 Clarification on revised WME const info required
85% 15% 87% 13% TECON 50 11 21 17 1 TOWER - AB
Stairmaster 207 195 12 0 0 superstructure frame 28.01.09 28.01.09 13.12.08
Method Statement Summary (Sitewide) EMCO 34 0 21 0 13 superstructure fit-out 05.02.09 05.02.09 22.03.09 Clarification on revised WME const info required
Total Submitted: 123 J & H (615 + SW) 507*** 263 26 100 96 TOWER - BA
Status
Returned
AD Precast (SW) 10 10 0 0 0 superstructure frame 28.01.09 28.01.09 13.12.08 Structure Frame complete
A B C Pending Info Only ALUMA 81** 0 0 0 30 superstructure fit-out 28.01.09 28.01.09 15.03.09 Basement and grnd fl block work set out info req'd.
15 45 43 2 18 SYSTEMS ENG. 14 6 5 0 3 TOWER - BB
13% 38% 36% 2% 15% DSI 633 0 395 8 230 supertsructure frame 28.01.09 28.01.09 13.12.08
* = 6 drawings issued for information *** = 16 drawing issued for information & 3 dwgs no comment superstructure fit-out 10.02.09 10.02.09 14.04.09 Basement and grnd fl block work set out info req'd.
** = 51 drawings issued for information **** = 6 drawing issued for information VILLAS & TOWNHOUSES

PROCUREMENT / TENDER ENQUIRY SCHEDULE substructure 03.02.09 03.02.09 13.12.08 Pool pipework layouts for villas received
Design Management Activities and Responsibilities Superstructure frame 11.02.09 11.02.09 30.04.09 PC shop drawings to be updated to match details on BBS

Scope Meeting GW6 Tender info


Held date actual
RETAIL & Ext AREAS
Scope Works Drwg GW6 Tender inf
Work Package DM Responsible Drawings Status Specification Status IFC info Rec'd Remarks
Doc Register date planned
substructure 23.02.09 23.02.09 20.11.08
Ironmongery discrepancies to BBS for external stairs, parapets, planters etc. .received and
Metal Doors MY Yes Yes Yes IFC IFC 15.02.09 16.04.09 30.05.09 be clarified by WME superstructure frame 23.02.09 23.02.09 30.04.09
under review
Fire stopping MY Yes No Yes IFC IFC 28.01.09 30.04.09 09.09.09 AFC completing typ details

Drawings and specification


Painting SA Yes No Yes IFC IFC 19.03.09 06.04.09 30.05.09 available. Status of Work Packages currently let incl self delivery
Roller Shutters incl Car Drawings and specification
SM Yes No Yes IFC IFC 18.06.09 16.04.09 30.05.09
park fire comp available.
Drrake and Scull to advise re
Miscellaneous Metalwork MY No No No IFC IFC 26.05.09 30.05.09
scope Drwg
Workpackage / Element Des Mgr Subcontractor Specs Comments
Clarification on fire rating Status
Louvres SM Yes Yes Yes IFC IFC 21.05.09
required from WME
Drawings and specification
Soft Landscaping NC Yes Yes Yes IFC IFC 27.06.09 08.06.09 20.09.09
available.
Façade MY J & H Emirates IFC IFC Shop drawings in progress - approvals ongoing
Drawings and specification
Hard Landscaping NC Yes Yes Yes IFC IFC 08.06.09 08.06.09 20.09.09
available.
Superstructure Blockwork MY AFC Self Delivery IFC IFC Revised set out drawings for basement and ground required.
Information outstanding from
Signage SM No No No Unavailable Unavailable 26.08.09 Not rec'd Not rec'd
WME
Drywall (Advance Works) SA Future Décor IFC IFC Updated wall set out drawings received
Shower screens and Clarifications on spec required
doors
SA Yes Yes Yes IFC IFC 09.04.09 05.02.09 30.05.09
from WME
MEP CF Drake & Scull IFC IFC Fixtures setting out rec'd - access panels / lay in grid to clarify
Archl Metalwork (handrail Clarifications on spec required
/ balust)
NC Yes No Yes IFC IFC 26.05.09
from WME
Post Tension Frame MY VSL IFC IFC Shop drawing approval ongoing for remainder
AFC Design Responsibility
Tensile Fabric Structures SM Yes Yes Yes IFC IFC 08.02.09 05.02.09 27.08.09 WME perf spec & des intent Pre-cast floors NC Abu Dhabi Pre Cast IFC IFC Shop drwgs to be updated to match details on BBS.

Structural Steelwork MY Yes Yes Yes IFC IFC 30.04.09 05.05.09 11.08.09 Additional scope identified Stairforms MY Stairmaster IFC IFC All shop drawings completed and approved.
Drawings and specification
Kitchens & Vanity Units SA Yes Yes Yes IFC IFC 09.04.09 05.02.09 30.05.09
available.
CURRENT STAGE DESIGN DELIVERABLES

Milestones Planned Actual


Cuml. % Cuml. %
Interior Design Hotel and Podium. 1% 1%
Interior Design Condo. 1% 1%
Interior Design Resort. 1% 1%
Civil/Structural. 1% 1%
Architectural 1% 1%
Façade Design. 1% 1%
MEP systems. 1% 1%
Landscape Design. 1% 1%
8% 8%
0.01 0.01
OVERALL PROGRESS PLANNED TO ACTUAL
20-04 27-04 4-05 11-05 18-05 25-05 1-06 8-06 15-06
26-04 10-05 17-05 24-05 31-05 7-06 14-06 21-06 28-06
W3 W7 W11 W1 W19 W23 W27 W31 W35
Plnd. 0.00 5.56 5.56 5.56 5.56 5.56 5.56 5.56 5.56
Act. 0.00 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11

Plnd. Cuml. 0.00 5.56 11.11 16.67 22.22 27.78 33.33 38.89 44.44
Act. Cuml. 0.00 1.11 2.22 3.33 4.44 5.56 6.67 7.78 8.89
22-06 29-06 6-07 13-07 20-07 27-07 3-08 10-08 17-08 24-08
5-07 12-07 19-07 26-07 2-08 9-08 16-08 23-08 30-08 30-08
W39 W43 W47 W51 W55 W59 W63 W67 W71 W75
5.56 5.56 5.56 5.56 5.56 5.56 5.56 5.56 5.56 5.56
1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11 1.11

50.00 55.56 61.11 66.67 72.22 77.78 83.33 88.89 94.44 100.00
10.00 11.11 12.22 13.33 14.44 15.56 16.67 17.78 18.89 20.00