Marina Bay Sands IR - Hotel Project United Engineers (Singapore) Pte Ltd.

Bayfront Avenue 257 Jalan Ahmad Ibrahim


Tel: 63278888 Fax:65348919 Singapore 629147
Tanjong Pagar Post Office PO Box 045 Tel: 62660988 Fax: 62686993
Singapore 910802

METHOD STATEMENT –
MAIN DISTRIBUTION BOARD & DISTRIBUTION BOARD/MSB

REV Date Description Prepared Checked Approved

A 24-Jan-08 Issued for Acceptance Anbu Christopher Tan Edgardo

Project: The Marina Bay Sands


Document: 2100_6140_MS_TC_HTL_5400
Produced by: UES
Revision A 1
Marina Bay Sands IR - Hotel Project United Engineers (Singapore) Pte Ltd.
Bayfront Avenue 257 Jalan Ahmad Ibrahim
Tel: 63278888 Fax:65348919 Singapore 629147
Tanjong Pagar Post Office PO Box 045 Tel: 62660988 Fax: 62686993
Singapore 910802

CONTENTS
Page
1. Scope of works ……………………………………………………... 03
2. Method Statement ………………………………………………….. 04
3. Approved Materials ………………………………………………… 05
4. Project organization for Health & Safety Control………………… 05
5. Health & Safety Risks and Control………………………………… 05
6. Access / Egress…………………………………………………….. 05
7. Lighting………………………………………………………………. 05
8. Plant & Equipment………………………………………………….. 06
9. Hazardous Materials & Substances………………………………. 06
10. Waste Management………………………………………………… 06
11. Special Control Measures………………………………………….. 07
12. Appendixes ………………………………………………………….. 08

Project: The Marina Bay Sands


Document: 2100_6140_MS_TC_HTL_5400
Produced by: UES
Revision A 2
Marina Bay Sands IR - Hotel Project United Engineers (Singapore) Pte Ltd.
Bayfront Avenue 257 Jalan Ahmad Ibrahim
Tel: 63278888 Fax:65348919 Singapore 629147
Tanjong Pagar Post Office PO Box 045 Tel: 62660988 Fax: 62686993
Singapore 910802

1. Scope of Works

Scope of Activities

This scope defines the minimum standards to be adopted when installing Electrical
Distribution Boards is installed in surfaced concrete/brick wall according to construction
co-ordination drawings. A distribution board divides the electrical mains feed into
various circuits, providing a fuse or circuit breaker for each circuit. They usually include
a main switch, and often one or more Residual-current devices (RCD) or Residual
Current Breakers with over current protection (RCBO)

Site Procedure
Site mobilization shall be done with real time monitoring the conditions & progress of
builder works. Before commencement of the work, carry out examination of the physical
condition of the area. Photographs should be taken where necessary, prior to
commencement and during works.

Project: The Marina Bay Sands


Document: 2100_6140_MS_TC_HTL_5400
Produced by: UES
Revision A 3
Marina Bay Sands IR - Hotel Project United Engineers (Singapore) Pte Ltd.
Bayfront Avenue 257 Jalan Ahmad Ibrahim
Tel: 63278888 Fax:65348919 Singapore 629147
Tanjong Pagar Post Office PO Box 045 Tel: 62660988 Fax: 62686993
Singapore 910802

 Method Statement 

1. Installation stage
a. Site survey of the proposed conduit routing based on approved CSD by
foreman / sub-contractor together with Engineer.
b. Installation must be carried out based on approved shop drawings & samples by
foreman / sub-contractor.
c. Mark the exact position of the distribution board using respective template.
d. Drill the anchor location and install the distribution board.
e. Fix all the metering equipment in the distribution board.
f. Name or label all sub-switch boards and distribution boards.
g. After installation of distribution board, Engineer-in-charge shall check the
complete works and complete the Inspection checklist EE-INS-13 for Electrical
distribution board installation works. ( See annex. 1 )
h. Engineer-in-charge shall arrange and request for inspection with the Owner’s
representative M&E clerks of works (COW) using approved Main con Request for
Inspection (RIN) form. ( See annex.2 )

2. Preferred Materials

Main Distribution Board SMB, Sun light, ABB, ATCO, Terasaki, GSM, Total Automation Pte
Ltd.

3. Project organization for Health & Safety Control


( See annex. 3 )

4. Health & Safety risks and controls


(Please refer to attach Risk assessment in respect to above scope of works – Annex.4)
5. Access / Egress
Proper step ladders shall be provided for access and egress into Distribution board as
applicable.

6. Lighting

Project: The Marina Bay Sands


Document: 2100_6140_MS_TC_HTL_5400
Produced by: UES
Revision A 4
Marina Bay Sands IR - Hotel Project United Engineers (Singapore) Pte Ltd.
Bayfront Avenue 257 Jalan Ahmad Ibrahim
Tel: 63278888 Fax:65348919 Singapore 629147
Tanjong Pagar Post Office PO Box 045 Tel: 62660988 Fax: 62686993
Singapore 910802

Adequate temporary/task lighting shall be provided if work to be carried at night or at dark


places.

7. Plant & Equipment

S/N Description Unit


1 Center punch 1 lot
2 Brace 1 lot
3 Hammer 1 lot
4 Electrical drill (only for surface installation works) 1 lot
5 Diagonal-Cutting Pliers 1 lot

6 Wire Stripper/Cutter with Spring 1 lot

7 Side-Cutting Pliers 1 lot

8 Level 1lot

9 Shank Screwdriver 1 lot

10 P.P.E. – Personal Protective Equipment (safety 1 set per worker


helmet,Boots,gloves & safety vest )
*The above machinery & Equipment used quantity will be varied depending on site conditions and
production rate.

8. Waste management
The Rubbish which would be created from our scope of works will be disposed to the designated
dumping ground.
9. Special Control measures
The following general control measures against Safety, Environment and Quality shall be required
for our scope of work and special control measures are not applicable for us

 Proper PPE must be worn at all time

Project: The Marina Bay Sands


Document: 2100_6140_MS_TC_HTL_5400
Produced by: UES
Revision A 5