Method Statement
Company Name: Rakan Trading and Contracting Company
Contract Name: P&C of Labor Camp – Phase 1
Contract No: 021-C09
Document Number: 01-710-00
1. Description of Works
Supply, installation & Testing of the chilled water piping and its accessories for all
applications in line with project requirements.
3. Access/Egress
SEE ATTACHED TMP
6. Work Methodology
Number Activity Description and sequencing
1. Material Storage & Handling
All material shall be inspected, handled and stored properly upon receipt
at site.
It shall be stored in a place free of water, dust and adequately covered to
avoid any kind of damages.
All insulation materials shall be inspected for the thickness and densities.
While unloading, shifting and storage, it should be ensured that there are
no transit damages.
Any discrepancies, damage, and etc. found to the materials will be
notified and reported to QA/QC Engineer and Project Engineer for further
action.
Materials found not suitable for site use should be removed from site
immediately.
2. Pipes preparation
Before primer, all dirt, dust, grease, oil or other foreign matters shall
be removed by scrapers, wire brushes and solvents or grit blasting if
required.
All finished surfaces shall be free from runs, drops, ridges, waves,
laps, brush marks and variations in color, texture and finish.
Coverage shall be complete, and each coat shall be so applied
as to produce a film of uniform thickness. Special attention shall
be given to ensure that all surfaces including edges, corners,
crevices, welds and rivets receive a film thickness equivalent to that
of adjacent painted surfaces.
Adjacent areas and installations shall be protected by the use of
masking tape, drop cloths or other approved precautionary
measures. Metal surface adjacent to surfaces to receive water
3. Pipe painting @ ground level and touch up above (RC specification shall be
followed)
a) Primer coat (Anticorrosive primer paint)
After pipe surface cleaned primer paint shall be applied immediately
i. red oxide paint as approved from RC engineer
2
ii. Spreading rate: 0.182kg/m /coat
iii. Paint brush or roller coating
b) Second coat (Finishing primer paint)
After pipe installation and prior insulation
i. red oxide paint as approved from RC engineer
2
ii. Spreading rate: 0.059kg/m /coat
iii. Paint brush or roller coating
The proposed chilled water pipes above grade is black steel SCH 40 in
accordance to ASTM A-53 Grade-B SCH-40 as per manufacturer
recommendation and approval.
Fix the sleeves as per approved shop drawings and specification, during
the construction of structural elements.
Pipe sizes 65mm and larger shall have welding joint. Pipe sizes 50mm and
smaller shall have threaded ends as per manufacturer recommendation.
Also refer to point #. 7.4.1 for threaded connection procedure and 7.4.2
for welding connection procedure.
Flexible Pipe connectors shall be installed at all air handling units, pumps,
and chillers.
All the open ends of the pipes shall be protected properly at the end of
each day’s work.
Drains shall be installed at low points in mains and branch lines (Vertical /
Horizontal) consisting of gate valve and short threaded nipple and cap so
that the system shall be drained completely.
Unions shall be provided adjacent to each screwed type valve and shall be
on the outlet side of the valve.
All valves shall be installed suitably to permit easy access for future
maintenance.
Automatic Air vents shall be installed at high points and where ever
required in order to trap air from the chilled water system.
Condensate drain piping will be extended to the nearest floor drain and
connected to the drain system.
Plug all open ends of pipes at the end of each day’s work using end caps.
Plug all connections / branches / drains and fill with clean water for hydro
testing.
A. Welder:
I. The welders to be trained and certified
II. The welder must be healthy
III. The welder must be trained for safe work i.e.
toolbox talk etc.
B Equipment:
On site, arc welding is usually carried out with direct current (DC), supplied from
diesel driven generator or Power source. Welding leads and welding return cables
are frequently dragged over rough surface, their insulation should therefore be
suitable for resisting fear and wear.
D Working requirements:
Ensure All Valves are in open condition before starting pressure test, NO
pressure shall be applied against closed valves.
The Piping system shall be tested closed by plugging all openings in the
system in a proper way and filled slowly with water.
Ensure all system is free from air lock, if so all the vent all entrapped air
from the system.
Repair the leaks and defects if any until satisfactory results are obtained
Check all required approved chilled water pipe insulations materials are
readily available on site.
Aluminum jacket shall be used for all external piping it should be as per
RC approval.
Pipes shall be generally insulated as per scope of work with rigid sections
of aluminum foil faced glass fiber/rock wool fiber insulation with density
of not less than 64 Kg/m3 having a thermal conductivity factor of 0.029
w/m.k at 10 deg. C.
External chilled water pipes (on roofs and in chiller yard) shall be
insulated as per scope of by not less than 50mm thick rigid insulation for
pipe sizes up to 40 mm dia and 75 mm for for 50mm dia and above.
For both internal and external pipes, the insulation shall be finished as
per scope of work or finished with a water proof Aluglass Cloth backing
(18u / FR Glue / 8x8 Mesh Aluglass Cloth), combined with a high-
performance flame retardant solvent acrylic adhesive, protected by an
easy-release silicone release paper.
Where insulated pipework is run on roof, in plant room, chillers yard and
tunnels it shall be clad using an outer covering of plain aluminum sheet of
0.7mm or thicker.
Make-up for pipe insulation shall be provided for consultant review and
approval.
Ensure all insulation materials are in dry condition during the application.
Apply insulation with longitudinal seams at top and horizontal pipe runs
For flanges, elbows, fittings and valves mitered section of pipe insulation
of same material shall be used.
In case of rising steam valves used in chilled water system, insulation shall
be extended and insulation joints and valve seams shall be sealed
properly in order to prevent passage of air to pipe surface.
Use Thermo foil recommended Tape to seal the joints in a way no air can
penetrate through the joints
Identification for Chilled Water Supply and return line and valves and
specialties shall be done as per specification with approved identification
materials. RC specification for identification requirements must be
followed.
7. Resources
c.
Materials and Tools
Item Reason for use
Drill machine / Portable drill For Drilling
Measuring tape For measuring
Steel Hammer For hammering
Spirit Level For leveling
Hole saw Cutter For cutting hole
Marking Pen / Chalk Line For marking
d. Chemicals Required
Item MSDS Number Specific Requirements
01 95370 Wear protective gloves/protective
clothing/eye protection/face protection. Eye
wash station.
02 29208 Wear protective gloves/protective
clothing/eye protection/face protection. Eye
wash station.
03 OK 63.30 (Electrode) Use respirator or air supplied respirator. Wear
hand, head, eyes, ear and body protection like
welders gloves, helmet or face shield with
filter lens, safety boots, apron, arm and
shoulder protection. Eye wash station.
04 ZL-60D Wear protective gloves/eye protection. Eye
wash station.
05 NPD-4 Wear protective gloves/eye protection. Eye
wash station.
Note that all works require mandatory PPE as follows Hardhat, gloves, safety glasses, safety
boots, hi-vis vest.
9. Permits
Permit Type Issued By Additional Information (Reference No. etc)
Hot work permit Foreman Inspected by the safety officer
Product description
Chain Block Safe Working Load - 1 Ton (1000KG) Lift - 6 Meters Minimum Distance Between Hooks -
340MM Chain Falls - 1 Load Chain Diameter - 6MM Hand Chain Length - 5.8 Meters Factor Of Safety
- 4:1 Conforms To: BS EN 13157: 2004+A1: 2009 These Are Manufactured With A Chain Guide To
Provide Smooth Chain Operation And Lightweight Steel Construction For Ease Of Use And Transport.
The Safety Hooks Are Drop Forged And Heat Treated To Ensure Safety And Durability.
OPERATOR
S/N NAME TPC EXPIRY DATE REMARKS
1 Geronimo Jr. Ostaga (Scissor lift operator) 19 August 2020 Active
2 Muhammad Arif (Forklift operator) 19 August 2020 Active