Vous êtes sur la page 1sur 2

M Sand

Item Cement Quantity


Sl No Unit Ratio Quantity Remarks
Quantity (Bags)
(Cum)
CEMENT & SAND
RR MASONRY
1 Cum 239 1:6 259 91

BLOCK WORK
Cum 227 1:4 148 23
MASONRY SAND 114 CUM
12MM PLASTER
Sqm 1493 1:4 134 15

20MM PLASTER
Sqm 2273 1:5 318 45
PLASTERING SAND 60 CUM

CEMENT 859 BAGS

Item
Sl No Unit Rate Amount (Rs) Remarks
Quantity
SHUTTERING
FOOTING
1 Sqm 386 450 173889
PEDESTAL
2 Sqm 446 450 200854
COLUMN
3 Sqm 263 450 118362
PLINTH BEAM
4 Sqm 359 450 161587
654692
REINFORCEMENT STEEL
FOOTING
1 MT 12.734 46000.000 585769
PEDESTAL
2 MT 5.343 46000.000 245757
COLUMN BASC
3 MT 3.243 46000.000 149186 RATE :
PLINTH BEAM RS.38000
4 MT 8.918 46000.000 410232
GRADE SLAB
5 MT 65.810 46000.000 3027275
MT 96.05 4418218
Item
Sl No Unit Rate Amount (Rs) Remarks
Quantity
PAINTING

INTERNAL PAINTING
Sqm 1493 130 194126

EXNTERNAL PAINTING
Sqm 2273 150 340886
535012

Item
Sl No Unit Rate Amount (Rs) Remarks
Quantity
MS WORKS
WINDOW GRILLS
1 Sqm 103 1350 138534

DOORS
2 Sqm 15 1700 26122

ROLLING SHUTTER
2 Sqm 9 1850 16650

Vous aimerez peut-être aussi