Vous êtes sur la page 1sur 6

78 • MBJ110

Construction Contract
and Management Issues
In this 1st quarter issue of Master Builders Journal for 2018, BKAsiaPacific (Malaysia)
Sdn Bhd, a subsidiary of BK Asia Pacific, an international construction consultancy
group providing project, commercial and contractual management services joins with
Entrusty Group, a multi-disciplinary group, collectively named BK Entrusty, to
present a new series of construction contract and management articles in areas
related to project, commercial, contracts, risks, quality, value and the like. This quarter
issue is on “Time at Large – Issues and Implications”.

Introduction reasonable time in the context of time extension for


construction works are often issues of contention, which need
In almost all construction projects, the common project
to be understood and appreciated by the contracting parties
objectives are to complete on time, within budget, meet
and players in the Malaysian construction industry.
quality and standard/statutory requirements. In addressing
time to complete the construction works, most employers In this article, BK Entrusty aims to provide readers with a
would require completion on time or within the extended time better understanding of the issues and implications of ‘time at
under the construction contract. Likewise, under large’ and ‘reasonable time’ for completing construction
subcontracts, subcontractors are faced with similar demands works, supported with related case law, by the following
for subcontract works. article contents: -
Unlike costs, which can be objectively determined and • Time of Essence
valued, construction completion period or duration and any • Extension of Time
time extension/s are often subjective usually subject to • Relevant Extension of Time Provisions
application and assessment under certain contractual • Time at Large Issues
procedures which are often not complied with, unfortunately. • Time at Large Implications
These circumstances usually lead to difficulties in • Summary/Conclusion
determining the extent of extension of time entitlement under
the contract. Time of Essence
It is therefore not surprising that contractors and Almost every construction contract in Malaysia contains a
subcontractors when faced with such extension of time provision or clause in the contract for time of essence,
difficulties, often resort to adopting the ‘time at large’ whereby the works must be completed within a certain
argument, particularly when they have been prevented and completion period or date. The employer is usually entitled to
delayed by event/s for which they are not culpable for. If impose liquidated damages on the contractor as a
successful, time at large releases them from being obliged to consequence of failure to complete the construction works
complete the construction works within the contractual within the contractual completion period, unless it has been
completion period. Instead, they are then entitled to complete extended, accordingly.
within a reasonable time, thereby rendering liquidated Under Section 56(1) of the Contract Act 1950, failure to
damages unenforceable. perform by a party within the contractual completion period,
What constitutes a ‘reasonable time’ to complete the works, where time is of essence, would render the contract null and
is another subjective matter as it is usually dependent on the void, at the option of the promisee. In other words, if the
factual matrix and circumstances of the events causing the contractor defaults by failing to complete the works within
delay and/or prevention. Consequently, both time at large and the completion period, the employer may be entitled to
MBJ110 • 79

dismiss the contractor from the site or terminate the contract, a. Retains a defined time for completion;
and is then not liable to pay for the unfinished work. However,
b. Preserves employer’s right to impose liquidated damages;
this is not usual practice in the construction industry, as
finishing late does not automatically entitle the employer to c. Relieves contractor from his obligation to complete the work
such remedies. Instead, the employer is entitled to damages within the contract completion period.
for such breach. However, extension of time provisions are often mistaken to
The principles in identifying when time would be of the solely benefit the contractor, as he is given a longer period to
essence can be found in the case of Tan Ah Kian v. Haji complete the works, thereby reducing the liquidated damages
Hasnan [1962] MLJ 400, whereby Gill J had expounded that liability. In fact, Chow K.F. (2004) rightfully pointed out that under
time is of the essence when: - English common law, such provisions are there for the benefit of
the employer instead, since the entitlement for liquidated
a. The parties have expressly stipulated time is of the essence
damages to be imposed in the event of any delay due or act of
in the contract;
prevention caused by the employer is preserved.
b. It was not originally stated in the contract but had been
made so by reasonable and timely notification on the Relevant Extension of Time Provisions
defaulting party; Relevant events concerning Extension of Time under the
c. The nature of the contract or of its subject matter, time must Malaysian Standard Forms of Contract are tabulated in the next
of the essence of. page***.
Further, the Court of Appeal in the case of Hock Huat Iron Time at Large Issues
Foundry v Naga Tembaga Sdn Bhd [1999] 1 MLJ 65, had
also identified an additional situation to ascertain from the real Time is said to be at large when the contractor is no longer
intention of the contracting parties. Where time is of essence in obliged to complete the construction works within the
the contract, by conduct of one party allowing the defaulting contractual completion period or the extended period, but to
party to continue carrying out the works after the contractual complete the works within a reasonable time, thus rendering
completion period, time would be rendered at large as it was the liquidated damages inoperative.
no longer considered time of essence. The same principle was According to Atkinson (2007), time is at large under four
also applied to earlier cases of Yeoh Kim Pong Realty Ltd v situations, as summarized below;
Ng Kim Pong [1962] MLJ 118 and Ganam d/o Rajamany v
a. No time for completion is fixed in the contract;
Somoo s/o Sinnah [1984] 2 MLJ 290.
b. Improper contract administration or non-application of
With the existence of provisions for extension of time and
extension of time provision in the contract;
liquidated damages in almost all construction contracts, time
can be said to be no longer of essence. The sanctions that c. Waiver of time obligation;
may be imposed on the defaulting contractor would entitles d. Interference in certification process.
the employer to impose liquidated damages on the defaulting
party, and if necessary to determine the contractor’s In addition to the above four situations, time for completion
employment or terminate the contract, as the contract may may be set at large when the Engineer/Architect/SO is not
provide. conferred with the power to extend the time for completion
under the extension of time provision by the employer’s
Extension of Time culpable delay event as held by the learned Judge in the case
of Thamesa Designs Sdn Bhd v. Kuching Hotels Sdn Bhd
Generally, most construction contracts usually provide for
[1993] 3 MLJ 25.
provision relating to the construction period which allows for
extension of time due to delay/s not attributable to the The consequences of time for completion being set at large, is
contractor, which is sometimes known as non culpable delay. that employer cannot impose liquidated damages on the
The effect of such provision is to maintain the contractor’s contractor, and the contractor is entitled to complete the
obligation to complete the construction works within an construction works within a reasonable time. However, what is
extended period. In failing which the contractor can be liable a reasonable time to complete the works, when time is being
to damages, either liquidated or general, depending upon the set at large?
standard form of contract used. In the absence of such
provision in the contract, time for completion can be put at Time at Large Implications
large, if the employer or its consultant/representative prevents Reasonable Completion Time
the contractor from its obligation to complete the construction
“Reasonable” as defined by the Concise Oxford Dictionary, is
works, accordingly. That being the case, the contractor is
what is fair, sensible, practicable and appropriate. When a
entitled at law to complete within a reasonable time, which is
construction contract does not expressly state the time for
question of fact and dependent upon the circumstances.
completion or the specified time has been lost, the Court may
Eggleston (1992) stated that the essential purposes for be prepared to infer that the parties intended the works to be
extension of time provision under a construction contract are: - completed within a reasonable time. Chow K.F (2004) stated
80 • MBJ110

***The tabulation of Relevant Events concerning Extension of Time under the Malaysian Standard Forms of Contract

that before the Court arrives at such conclusion, the contract completion of the works, Diplock J ruled that reasonable time
as a whole and the circumstances surrounding the contract not only dependent on the contractor’s convenience and
must be considered. If the contract specifically provided a financial interest, but also his interest to have “every detail cut
date for completion, the contractor cannot claim that he is and dried on the day the contract is signed”, but such attempt
entitled to complete the works within a reasonable period after could not have been contemplated at the time of contract. The
the date has been agreed and formed part of the conditions of learned judge held that a reasonable time was a question of
contract. fact to be determined by considering all the circumstances of
the case, including;
But, what is a reasonable time for completion? According to
Wallace (1995), when determining the reasonable time in the a. Consideration of the employer’s engineer and his staff;
ordinary circumstances, before considering the actual
b. The order by which the works were to be carried out and
post-contract circumstances, there are other matters which
approved by the engineer;
needed to be taken into consideration e.g. whether is there any
particular factor in mind, either expressly or impliedly c. The contractor’s request for particular details;
contracted by the parties, such as the parties’ other d. The relevancy of the details requested relate to variations;
commitment. Chow K.F (2004) stated that, the test of
‘reasonableness’ can sometimes be construed as being e. The contract duration.
equivalent to the convenience and economic interest of the The aforesaid list of questions or test of reasonableness in
contractor. respect of timing of instructions, additional drawings and
In the case of Neodox Ltd v Swinton and Pendlebury information to be given, is not exhaustive. According to Bailey
Borough Council [1958] 5 BLR 34, where the contractor (2011), reasonable time is a matter to be judged in the
alleged that there was an implied obligation on the employer to circumstances as they exist at the time of the prevention event
provide all necessary instructions and details in timely manner or conduct.
to prevent the contractor being delayed the execution and
MBJ110 • 81

Further, Gill (1969) stated that, in establishing or computing 3. The time in which a reasonably diligent contractor of same
reasonable time, all circumstances of the case should be taken class would take (from the case of Hydraulic Engineering Co
into consideration. Such circumstances may include (RY Ong, Ltd v McHaffie, Goslett & Co. [1878] 4 QBD 670).
2007);
Right to Impose Liquidated Damages
1. Nature of the works and time required to do it, as well as the
It is common for construction contracts to provide a provision
contractor’s ability to do so (from the case of Attwood v
for the deduction/imposition of liquidated damages by the
Emery [1856] 1 CB (NS) 110;26 LJCP 73);
employer if the contractor fails to complete the work within the
2. Proper use of customary appliances (from the case of Lyle contractual completion period or date. The relevant provisions
Shopping Co. v Cardiff Corporation [1900] 2 QB 638); under Malaysian Standard Forms of Contract are, as follows :

Item Contract Clause Description

i) PAM 2006 Cl. 22.1 If the Contractor fails to complete the Works by the Date for Completion or within any extended
time fixed under Clause 23.0 (extension of time)………. LAD for the period from the Date for
Completion or any extended date where applicable to the date of Practical Completion……

ii) JKR 203A (2010) Cl. 40.1 If the Contractor fails to complete the Works by the Date for Completion or within any extended
time granted pursuant to Clause 43 (Delay and Extension of Time) ……….

iii) IEM CE 2011 Cl. 40 If the Contractor fails to complete the Works by the Date for Completion or ….. or within any
extended time under Clause 43 (Delay and Extension of Time)…………..

iv) CIDB 2000 Cl. 26.1(a) If the Works have not been completed within the Time for Completion or any extended time
granted pursuant to Clause 24 (Delay and Extension of Time)…………..

v) PWD DB/T Cl. 45.1 If the Contractor fails to complete the Works by the Date for Completion or within any extended
time granted pursuant to Clause 49 (Delay and Extension of Time) ……….

However, as discussed in the foregoing, an employer loses its In so far as Malaysia is concern, the Court in the case of
entitlement to liquidated damages if the time for completion is Maniam v the State of Perak [1975] MLJ 75 and Linggi
set at large, as the employer cannot insist on compliance of Plantations Ltd v Jagatheesan [1972] 1 MLJ 89 held that,
the condition if he himself has defaulted it, in the first place. In there is no difference between penalty and liquidated
Peak Construction (Liverpool) Ltd v McKinney damages. Section 75 of the Contract Act 1950 dealt with the
Foundations Ltd [1971] 1 BLR 111, the Court held that if the effect of a sum named in the contract which is payable to the
party is being prevented by the refusal of the other innocent party in the event of breach. In order to be entitled for
contracting party from completing the contract within the such sum, the innocent party is required to prove actual loss
stipulated time, he cannot be liable in law for that default. incurred (Selvakumar Murugiah v Thiagarajah a/l Retnasamy
[1995] 2 MLJ 817).
In the case of Wells v Army & Navy Co-operative Society Ltd
(1902) 86 LT 764, the learned Judge, Lord Wright J concluded However, it is noted that in the event if the employer has lost its
that there is no appropriate date for liquidated damages right to claim for the liquidated damages, subject to the
computation due to the act of prevention by the Society, by contract stated otherwise, the employer can still recover
expounding as follows: general damages, as long as he is able to prove, but not
exceeding the amount indicated in the contract provision as in
“On the whole, I think that the conclusion must be that the
accordance to Section 75 of the Contract Acts 1950.
defaults of the Society were such that in their cumulative effect
they were inconsistent with their claim to insist on completion Employer’s Determination of Contractor’s Employment or
within the stipulated time. The defaults were, in my opinion, Termination of Contract
sufficiently substantial to cast upon the Society the burden of
The other remedy for an employer when its contractor fails to
showing that the defaults did not excuse the delay. It is true
complete the works within the contractual completion period
that, apart from their defaults, Wells had, by the default of
or date is to determine the contractor’s employment or
sub-contractors, been delayed to an extent which might of
terminate the contract, which is allowed under Section 56(1) of
itself have involved them in penalties, but in the absence of the
the Contract Act 1950.
further defaults by the Society it is impossible to say to what
extent the liability to penalties might not have been reduced”
82 • MBJ110

Under the Malaysian Standard Form of Contracts, the following are the relevant events in which the employer can proceed with
the determination or termination;

Item Contract Clause PAM JKR 203A IEM CE 2011 CIDB 2000 PWD /DB
2006 (2010)
Contractor’s Default
i) Fails to commence Works in Cl 25.1(a) Cl 51.1(a)(i) - Cl 44.1(a)(i) Cl 60.1(a)(i)
accordance with the Contract
ii) Fails to provide Performance - - - Cl 44.1(a)(ii) -
Security Deposit
iii) Suspension of Works Cl 25.1(b) Cl 51.1(a)(ii) Cl 51(a)(i) Cl Cl 60.1(a)(ii)
44.1(a)(iii)
iv) Fails to proceed regularly and Cl 25.1(c) Cl 51.1(a)(iii) Cl 51(a)(ii) Cl Cl 60.1(a)(iii)
diligently 44.1(a)(iv)
v) Fails to execute Works in - Cl 51.1(a)(iv), Cl 51(a)(iii) - Cl 60.1(a)(iv),
accordance with the Contract (v) & (viii) (v), (vii) &
(ix)
vi) Fails to remove defective work Cl 51(a)(iv) Cl 54.1(d) Cl 51 (a)(iv) Cl 44.1(a)(v)

vii) Assignment or Sub-letting Cl 25.1(e) Cl 51(a)(v) Cl 54.1(e) Cl 51(a)(v) Cl 44.1(a)(vi)


without consent
viii) Abandoned the Contract Cl 25.1(f) Cl 61(h)

ix) Failure to comply with Cl 25.1(d) Cl 61(f) Cl 44.1(a)(vii)


Architect/S.O’s Instructions
x) Contractor’s bankruptcy Cl 25.1 Cl Cl54.2(a),(b), Cl 61.2 Cl 44.2
51(b)(i),(ii),(iii) (c),(d) (a),(b),(c)&(d)
&(iv)

In the event that the contractor is refused of its entitlement for circumstances, the owner may serve a notice to the contractor
extension of time due to act of prevention by employer, which which states that time is of the essence, and if the contractor
results in time for completion being set at large, the employer again fails to complete its works within a reasonable time, where
loses its right to determination or termination, and it follows that such time for completion is indicated expressly in the said notice,
no liquidated damages can be imposed under such the owner then may have the right to terminate the contract.
circumstances. This is supported by the English case of
McAlpine Humberoak Ltd v McDermott International Inc Summary/Conclusion
(1992) 58 BLR 1 at 21 in which Lloyd LJ stated that : Time for completion is one of the main objectives in
“The principle enunciated in Wells v Army & Navy Co-operative construction projects. Unlike the old days, in modern
Society was not new. It is as old as Holme v Guppy (1831) 3 M construction contracts, the difficulties and subjectivity on time
& LJ 387, where Baron Parke first used the phrase, often since issues, which promoted the arguments on time at large and
repeated, of the contractor being “left at large”. In recent times ensuing reasonable time have been substantially curtailed by
the principle has been applied in such cases as Peak extension of time provision in most standard forms of contract.
Construction (Liverpool) Ltd v McKinney Foundations Ltd The aim is to eliminate the situation of time becoming at large
(1970) 1 BLR 114, The Cape Hatteras [1982] 1 Lloyd’s Rep arising from act of prevention by the employer or its
518 and SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] consultant/s and failure or refusal to grant reasonable time
VR 391. In all these cases the employer was claiming liquidated extension, accordingly. Similar, the issue concerning time at
damages. In all of them it was held that the claim for liquidated large and reasonable time for completion also apply to
damages must fail since the employer could not rely on the subcontractors who undertake subcontract works for the
original date of completion, nor on a power to extend the date of contractor.
completion. In the absence of such a power, there could be no Any such act of prevention or default by the employer or its
fixed date from which the liquidated damages could run.” consultant/s, which had impacted and prevented the
In an archaic but still relevant case of Walker v London and contractor from completing the works within the contractual or
North-Western Railway Co [1876] 1 CPD 518, the Court held extended completion period or date, the employer loses his
that the owner will not be able to exercise a right to terminate the right to insist on the works to be completed within the said
contract for slow progress after the contractual date for period or date, as the completion time has been set at large, by
completion, because after the time for completion there is no such breach, thereby disentitling the employer to impose
further date against which progress can be determined. In such liquidated damages.
MBJ110 • 83

In view of the above and in order to avoid completion time


being set at large, it is crucial for employers and their
In the next issue of the MBAM Journal, BK Entrusty
consultants to properly assess and grant extension of time
entitlement to the contractor in accordance with the contract.
article will deal with another pertinent contractual
Otherwise, the employer concern loses its right to impose issue affecting the Malaysian construction industry,
liquidated damages and the contractor is entitled to complete on “S-Curves – Issues and Implications”
the works within reasonable time, which is in turn dependent on
the factual matrix and circumstances prevailing on the event/s
concern. 

References / Bibliography
1. Bailey, J. (2011), “Construction Law”. UK. Informa Law. 11. Rajah Tann (2011), “Delays in Completion : When Is Time Set At Large And When Do
2. Chow K.F. (2004). “Law and Practice of Construction Contract. 3rd ed”. Singapore. Sweet & Liquidated Damages Provisions Survive Termination Of Contract for Case Laws in Lim Chin
Maxwell Asia San Contractors Pte Ltd v LW Infrastructure Pte Ltd [2011] SGHC 162 & LW Infrastructure
3. Dato’ Jeffrey Tan, Hakim Mahkamah Persekutuan Malaysia, cited case law, Hock Huat Iron Pte Ltd v Lim Chin San Contractors Pte Ltd [2011] SGHC 163”;
Foundry v Naga Tembaga Sdn Bhd [1999] 1 MLJ 6 as stated in Rayuan Sivil No. 02-14 12. Thierry Linares, “Time at Large and Extension of Time Principles including cited Case Laws
Tahun 2012 between Sime Hok Sdn Bhd and Soh Poh Sheng, 17 January 2013; Bruno Zornow (Builders) v Beechcroft Developments [1990] 51 BLR 16, Peak Construction
4. Doyles, “Case Law – Wells v Army & Navy Co-operative Society Ltd (1902) 86 LT 764”. (Liverpool) Ltd v McKinney Foundations Ltd [1971] 1 BLR 111 & Home v Guppy [1938]
Retrieved from https://mosaicprojects.com.au/casewatch/1047%20Wells%20v%20 150 ER 1195, Expert Paper 2013-01 rev 0”. Retrieved from
Army%20 and%20Navy.pdf; www.ProjectValueDelivery.com;
5. Eggleston, B. (1992) “Liquidated Damages and Extension of Time in Construction 13. VIP Consultancy, “Extension of Time – Time of the Essence & Time at Large including Case
Contracts” Oxford. Blackwell Scientific Publications Law, Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973]”.
6. Gill, W.H. (1969) “Emden and Gill’s Building Contracts and Practice. 7th ed”. London. Retrieved from http://vipconsultancy.co.uk;
Butterworths 14. Wallace, D. (1995). “Hudson’s Building and Engineering Contracts. 11th ed”. London.
7. Marten Walsh Cherer Ltd., “Stenographic Notes on Case Law – Bluewater Energy Services Sweet & Maxwell
BV v Mercon Steel Structures BV & Mercon Holding BV & Mercon Groep BV, neutral citation 15. References were also made to several Malaysian Standard Forms of Contract, namely;
number : [2014] EWHC 2132 (TCC) Case No. : HT 10-355”. Retrieved from i. PAM Form of Building Contract 2006
http://www.bailii.org/ew/cases/EWHC/TCC/2014/2132.html; ii. JKR/PWD Form of Contract (203A – Rev 2010)
8. Ong, HT (2017), “Session Five of Practical Construction Contract iii. IEM Conditions of Contract for Works Mainly of Civil Engineering Construction (Rev
Administration/Management - Contractual Issues and Determination/Termination.” 2011)
Organised by MBAM, 6 July 2017. iv. CIDB Form of Contract for Building Works (2000 Edition)
9. Ong Rui Ying (2007), “Time at Large and Reasonable Time for Completion”, Universiti v. JKR PWD/Standard Form of Design & Build/Turkey Contract (PWD Form DB/T)(2002
Teknologi Malaysia. Edition)
10. Oon Chee Kheng, (2003), “Extension of Time and Liquidated Damages in Construction
Contracts”; paper presented on Construction Contracts and Arbitration organized by IEM,
18 October 2003.

Bhd (in association with Applied Facilitation & Training, BK Entrusty provides 30 minutes of free consultancy
Australia), International Master Trainers Sdn Bhd (in (with prior appointment) to MBAM members in the areas
BK Asia Pacific is group of companies incorporated in association with Master Trainer of New York), Agensi of project, commercial, contracts, risks, quality and
the Asia Pacific Region providing a comprehensive Pekerjaan Proforce Sdn Bhd and Entrusty International value management.
network of project management, commercial and contract Pte Ltd. The Group provides comprehensive
For enquiries, please contact Sr. HT Ong at BK Entrusty,
management services to the international construction consultancy, advisory and management services in
22-1 & 2 Jalan 2/109E, Desa Business Park, Taman
industry, with offices in China (Hong Kong, Macau and project, commercial, contracts, construction, facilities,
Desa, 58100 Kuala Lumpur, Malaysia.
Shanghai), Malaysia, Philippines, Singapore and Vietnam. risks, quality and value management, cost
For further details, visit www.bkasiapacific.com management, executive search/personnel recruitment Tel : 6(03)-7982 2123
and corporate training/seminars/workshops to various Fax : 6(03)-7982 3122
industries particularly in construction, petrochemical, Email : htong@entrusty.com.my or
manufacturing and IT, both locally and internationally. htong@bkasiapacific.com
For further details, visit www.entrusty.com
Entrusty Group is a multidisciplinary group of
companies which comprises Entrusty Consultancy Sdn
Bhd (formerly known as J.D. Kingsfield (M) Sdn Bhd),
BKAsiaPacific (Malaysia) Sdn Bhd (a member of BK Asia
Pacific Ltd, Hong Kong), Pro-Value Management Sdn

Vous aimerez peut-être aussi