Académique Documents
Professionnel Documents
Culture Documents
CHAPTER 6
6.1 General
Retaining walls are structures, which support and retain earth in order to prevent failure of
sediments in the places where stability of slope can not be assured by ground condition itself or
by other slope protection works.
Along the N-M highway, a lot of retaining walls, which consist mainly of gravity type concrete
wall, block masonry wall and gabion wall, have been constructed. However, a large number of
structural deformation and failure on the retaining walls were visibly and clearly observable.
The main problems regarding to the retaining walls are listed as follows:
b) No or less foundation works were executed. Some retaining walls were placed on deposit
layers without foundation treatment, which is the main cause of retaining structure
damage.
c) In some cases, retaining walls are misused because of the failure masses or earth pressure
that may be the several time larger than the wedge of earth retained by these retaining
walls. To be effective, the wedge of earth supported by the wall should be similar or
larger in size to that of the failed or potential failure mass. If the potential failure mass is
much larger than the wedge of earth that the retaining wall can potentially retain, a
tieback system or some other method of stabilization should be used in combination.
d) In some cases, anti-proof sand treatment (geotextile and filter material) behind the walls
were not designed and executed. This may cause flow out of backfilling materials,
leading to soil subsidence behind the wall and subsequent deformation and collapse of
the retaining wall.
e) Drainage treatment behind retaining walls was hardly done. High water pressure behind
wall body was produced during and after heavy rainfall because of no drainage treatment,
and deformed the retaining structures together with earth pressure. In principle, all walls
should be provided with weep holes. The weep holes are placed horizontally at the lowest
points where free outlets for water may be obtained and should be spaced at not more
than 2.0 m center to center in a staggered manner. The length of the weep hole should not
be less than the thickness of the walls and should be at least 50 mm diameter PVC, and
must be provided with filter material covered with geotextile filter fabric.
In addition, as a new method, reinforced earth walls, which has the function of a retaining wall,
has been widely used in unstable sites in mountainous areas in recent years. It is a technically
attractive and cost-effective technique for increasing the stability of natural soil and
constructed fill slopes and for reducing earth pressures against retaining walls. The method is
ideal for very high or heavily loaded retaining walls because of its high load-carrying
capacity. The method is thus introduced in this technical guide, in consideration of its
applicability in Nepal in the future.
Retaining walls are generally classified into the following types in accordance with shapes,
characteristics, design criteria and applications.
As summarized in Table 6.2.1 below, selection of the type of retaining wall is generally based on
the topographical and geological conditions at the place of the wall construction, work conditions,
purpose of retaining wall, and height of wall.
Retaining walls are used to correct highway failures by increasing the forces tending to resist
failures. Generally, retaining wall is placed at the toe of the distressed area or potential slope
failure.
a) To maintain the stability of the foot part of a slope after being distressed (Figure 6.2.1),
b) To prevent small-scale shallow collapse and toe collapse of large-scale slope failures,
d) To function as a foundation for other slope protection works such as crib works,
e) To catch rock fall mater in order to protect vehicles from rock fall (Figure 6.2.2), and
Road Road
a) Slope foot protection by gabion wall b) Slope foot protection by retaining wall
Road Road
Figure 6.2.3 shows the design procedure of retaining wall works. The following sections will
give brief descriptions of design procedures for retaining walls.
As shown in Table 6.2.1 before, there are many types of structures for retaining walls and the
selection of type of structures are dependent mainly on the topographical and geological
conditions at the place of the wall construction, work conditions, purpose of retaining wall, and
height of walls.
The types of foundations for a retaining wall are principally classified into spread foundations
and pile foundations. The preferable type of foundations for a retaining wall are spread
foundation in view of their movement together with the bearing stratum and the filling material
at the back. In some cases, if surface layer is soft, spread foundations can also be used with
the replacement or improvement of the soft layer. Pile foundations are used when the
application of spread foundations are difficult.
The parameters for shear strength of soil are generally obtained from either unconfined
compression test or the triaxial compression test. The empirical relationship with N value can be
used to obtain parameters of soils as follows:
c = 6 N~10 N (kN/m2)
φ = 15 + 15 N ≤ 45° N>5
The unit weight of soil γ(kN/m3) used for the calculation of earth pressure is obtained from
laboratory of soil samples. If it is difficult to conduct soil test, the values shown in Table 6.2.2
can be used instead of soil test results.
Source: Manual for Retaining Wall, Published by Japan Road Association, March 1999
The allowable bearing capacity of ground is, in principle, determined by conducting an in-situ
test (standard penetration test). When it is difficult to conduct an in-situ test for retaining wall,
the values shown in Table 6.2.3 can be used.
Source: Manual for Retaining Wall, Published by Japan Road Association, March 1999
When the shear parameters c and φ of the bearing stratum are obtained by soil test, the
friction angle of the foundation baseφB is determined to beφB =φfor cast-in-place concrete
retaining wall andφB =2/3φ for precast concrete retaining wall.
If it is difficult to conduct a soil test, the values shown in Table 6.2.4 can be used.
Table 6.2.4 Friction Coefficient and Cohesion between Foundation Base and Ground
Condition of shearing plane Type of bearing ground Friction
Cohesion
coefficient
Bedrock 0.7 ―
Rock/Gravel and Concrete
Gravel layer 0.6 ―
In Japan, the effects of earthquakes need to be considered when designing retaining walls higher
than 8 meters. Accordingly, it is suggested that analysis of stability against earthquake should be
made for retaining wall of up to 8 m in height when the importance of retaining wall and the
difficulty of it restoration demand such analysis.
Generally, loads acting on a retaining wall include a) deadweight, b) surcharge, c) earth pressure,
d) buoyancy below the base of wall body, e) water pressure behind wall body, and f) earthquake
load.
However, for design purposes, loads acting on a retaining wall are normally considered as (a)
deadweight, (b) surcharge and (c) earth pressure.
Design calculations against earthquakes are generally not required for ordinary retaining walls
because the load increase due to the seismic force can be compensated by a slightly increased
factor of safety for the normal design calculations and by a resisting force which can not be
considered in the calculations.
In addition, as a retaining wall is a structure which is in contact with the earth, it is subject to
earth pressure to the wall. The earth pressure caused by about-to-collapse bank soil due to
forward movement of the wall, i.e. in the direction away from the embankment; it called the
active earth pressure. As the purpose of a retaining wall is to support an about-to-collapse soil
mass, it is generally designed based on the active earth pressure.
The active earth pressure acting on movable walls is calculated by the following Coulomb’s
formula:
2 3 4 5 3
1
W3
H α R3 φ
H
δ
P3 ω
P3
90°-(α+δ)
90°-(ω-φ-α-δ)
R3 W3
ω-φ
2) Calculate the weight of soil wedge, and consider the equilibrium of force
soil wedge including the surcharge on the soil wedge), R (Reactive force acting along slip
surface), and P (Resultant force of earth pressure acting retaining wall).
If the other external force acts on the soil wedge, consider the equilibrium of force including
the other external force.
P is given as a function of ω (angle of slip surface and horizontal plane). The maximum P
which is obtained by varying the slip surface is Pa (the resultant force of acting earth
pressure) which should be considered in design time.
The acting point of Pa is the center of gravity of earth pressure distribution. Generally, earth
pressure distribution is assumed as triangle distribution. In this case, the acting point is 1/3 of
H (distribution height) from the bottom of earth pressure distribution.
In wedge analysis, earth fill shape of back side of retaining wall is uniform, and there is no
cohesion of backfill soil. The earth pressure acting on wall per unit width is coincident with
Coulomb’s acting earth pressure which is given in the equation (6.2.3.1) and (6.2.3.2).
cos 2 (φ −α)
Ka = 2
(6.2.3.2)
⎡ sin(φ + δ ) sin(φ −β) ⎤
cos αcos(α+ δ ) ⎢1 +
2
⎥
⎣ cos(α+ δ ) cos(α-β) ⎦
where,
a) Stability on sliding between the base of the wall and its foundation ground
∑V × µ + c × B
Fs =
∑H
Where,
The resultant of all forces acting on the structure should fall within the middle third of the
structure base.
B ∑ Mr − ∑ Mo
e= −
2 ∑V
Where,
qu
q =≤ qa =
Fs
Where,
d) Overall stability, including the stability of the wall itself and the overall slope of which the
wall may be a part
In this technical guide, it is recommended that the above-mentioned a), b) and c) be examined
for ordinary retaining walls, and d) and e) be added up depending on the size (height) of wall
and soil condition.
Source: Manual for Retaining Wall, Published by Japan Road Association, March 1999
The following discusses several types of retaining walls that are in common use in Nepal.
Gabion walls are effective in situations where erosion control is important. A gabion wall is
gravity type of structure. Generally, gabion walls are economical up to a height of about 5.0 m.
At greater heights, other wall systems may be more economical.
Gabion walls are usually used to protect small size failure at the toe of a slope, especially where
spring water abundantly exists. Because this type can resist only small earth pressure it is
preferably used as one of the protection work rather than as a retaining wall.
Gabion wall is a flexible type of wall and can withstand some vertical and horizontal movement
and/or deformation without failing. Other advantages include:
b) Self-draining
c) Easy to be installed
Gabion walls are fabricated from gabion baskets that are typically 1 meter × 1 meter in
cross-section and from 2 to 4 meters in length. The rock fill for the gabion is graded from a
maximum of 250 mm diameter to 100 mm diameter in size. As stated above, gabion walls are
flexible and the nature of the gabion fill provides good drainage conditions in the vicinity of the
wall. Filtration protection between the gabion and the wall backfill should be provided (Figure
6.3.1).
Filter Cloth
Road
20 mm Ø Rebars, 2 to 3 m long,
longitudinal spacing 3 to 4 m
Stone (or concrete block) masonry retaining walls must be made of wet masonry. Wall stability,
especially the critical height, is examined (refer to the depth from the wall top edge to the critical
point 1/3 outside of the force line centre). The foundation is embedded by at least 60 centimeters.
One drain hole (generally φ100 mm) is installed every 2 to 3 m2, usually in a zigzag pattern,
because of the poor drainage in the walls.
The details of stone (or concrete block) masonry retaining walls are shown in Figure 6.3.2, while
their standard dimensions are given in Table 6.3.1.
Source: Modification from Highway Earthwork Series, MANUAL FOR RETAINING WALLS, Published by Japan
Road Association, March 1999.
.
a b
c
10mm
H
N1 Gravel Soil
Drain hole
H1 Well-graded Soil
Foundation
Note: Wall thickness a=35 cm, Concrete backfill thickness b=0 to 20 cm,
Top edge thickness of backfill c=30 to 40 cm,
Wall height H=1.5 to 7.0 m, Foundation height H1=25 to 40 cm,
Gradient N1=1V: 0.3H to 1V: 0.5H.
Backfilling materials aim to reduce pressure acting on the retaining wall by draining water and
Leaning retaining wall is also called supported type retaining wall. The retaining wall is
designed as a gravity type structure although it can not stand by itself, and therefore, should be
supported by the earth at the rear. This type can counter by its own dead load against earth
pressure while being supported.
Leaning retaining walls can be subdivided, in terms of function and slope geology, into two types,
as shown in Figure 6.3.3, while the standard dimensions for wall design are given in Table 6.3.2.
Type A: Type B:
Gravely soil Hard rock
or
Soft rock
As shown in Figure 6.3.3, Type A is generally used for the protection of small rock falls and
design calculations against earth pressure is not conducted. The height of the wall shall be
determined on the basis of the bearing ground, as shown in Table 6.3.3.
Moreover, the bedding depth for the wall is 1.0 m in principle, but may be reduced to 0.5 m
where there is a bearing layer of hard rock.
Crib retaining walls, which are usually fabricated from pre-cast reinforced concrete elements, are
flexible due to the segmental nature of the elements and are somewhat resistant to differential
settlement and deformation. This type is more versatile than rigid retaining walls because it can
withstand fairly large vertical and lateral movements and not lose stability.
Therefore, especially when the ground deforms considerably and there is a large amount of spring
water in the potential soil slope collapse areas, this type is greatly applicable and
recommendable.
Components of a crib wall consist of a series of interconnected cells. The cells usually
constructed of wood (for example, old railroad ties and treated timber), and precast reinforced
concrete struts. Backfill consists of granular materials (smaller than 30 cm in diameter).
Stability is calculated for the whole structure as well as for several horizontal sections. Slope
stability calculations should include the potential failure surface above the toe of the wall. Earth
pressure calculations for the walls are similar to those for the gravity type retaining walls (Figure
6.3.4).
Whenever, practical, the wall should be placed on firm rock, or when this cannot be achieved,
the wall should be placed on compacted fill or firm natural soil layer. It is desirable to construct
a granular platform at the start of the construction of the crib wall.
Source: Modification from DESIGN GUIDE -EARTHWORKS, Published by Japan Highway Public Corporation,
May 1998.
For gravity type retaining walls, design considerations involve the above-mentioned analyses of
the four states, namely, sliding, overturning, bearing capacity and overall stability. In determining
the dimensions of the wall, it is desirable that the width, B, of the bottom slab is about 0.5 to 0.7
times the height of the retaining wall and the thickness of the top edge is between 15cm and
40cm.
Because of foundation requirements and construction costs, this type may have limited
application in Nepal.
Another important point in the design of a retaining wall is drainage. When the water content of
the soil at the back increase with the infiltration of water, the earth pressure rises due to the
increased density and reduction of the internal friction angle and cohesion of the soil and, in the
case of clayey soil, swelling due to added moisture.
Various types of drainage, including weep holes, ditch drainage and continuous back drainage,
can be available for retaining walls. There are many combinations for actual applications,
however, weep holes should always be introduced. Weep holes are generally installed at the rate
of one weep hole per 2-4 m2 of retaining wall using a PVC pile of 40 mm or more in diameter.
The method consists of three parts, namely, 1) wall facing materials, 2) reinforcement materials
and 3) backfill materials. Wall facing materials include precast concrete blocks and concrete
panels, cast-in-place concrete and steel wire boxes. Reinforcement materials include steel belts
(strips), anchor plates or bars, welded wire sheets, geotextiles, geogrids, and fibers. Backfill
materials are non-cohesive granular soils.
Reinforced earth walls are used to prevent small-scale soil collapse and road slips on steep and
large slopes in lieu of retaining walls. The method is the best solution to situations such as
restricted right-of-way and steep road slips.
The method requires the inclusion of tensile resistant elements in a soil mass to improve its
overall shearing strength and thereby increase the capacity of the retaining wall. Figure 6.3.5
gives the conceptual mechanism of reinforced earth walls.
Sliding surface
Since the first reinforced earth wall (Terre Armee) was developed in the 1960s, many other
types of reinforced earth walls have been developed. Table 6.3.4 summarizes the methods and
the characteristics of the most typical reinforced earth walls. Figure 6.3.6 gives the images of
reinforced earth walls.
Steep belts
Anchor plate & bar Geotextiles
In principle, the design of reinforced earth walls includes (a) Internal stability analysis, (b)
External stability analysis, and (c) Overall stability analysis, as graphically shown in Figure
6.3.7. For (b), the stability analyses are similar to that for retaining walls, including sliding,
overturning and bearing capacity of the foundation.
Figure 6.3.8 gives the general design procedure for reinforced earth walls. Geotechnical
parameters relevant to reinforced earth wall design include unit weight, stress strength of the
backfill and ground, and bearing capacity of the ground. Detailed guidance on the selection of
such parameters is in the other chapters of this Guide.
Wall Facing
Connection
Sliding Break
Surface
Tension
Earth
Earth Press
Pressure
Consolidation
Settlement
Settlement
For each design situation, concentrated or distributed loads, which may result in forces acting
on the reinforced earth wall, are evaluated. The general types of direct loads are a) Deadweight,
b) Surcharge, c) Earth pressure, d) Water pressure and e) Seismic load.
No common method for stability analysis is applicable to all reinforced earth walls. Table 6.3.5
gives a comparison of stability analysis among the typical reinforced earth walls.
Sliding of wall ─ ○ ○
Overturning of wall ─ ○ ─
Bearing capacity of ground for walls ─ ○ ○
Note: ○ = Must be evaluated, ─ = No need to be evaluated.
Source: Modification from DESIGN AND CONSTRUCTION MANUAL FOR MULTISTAGE ANCHOR TYPE
REINFORCED EARTH WALL, Published by Public Works Research Institute, October 2002.
START
No
Is the planned factor of safety met?
Yes
No
Additional
Is the stability ensured? measures
Yes
7. Calculation and design of detailed structures
END
The retaining effect of reinforced earth walls depends primarily upon the tensile resistance
between the reinforcement materials and backfill materials. The effective tensile resistant force
(R/Fs) is calculated by using the following equation.
R 2(c + σ tan φ ) × LE
=
Fs Fs
Where,
Table 6.3.6 gives the effective tensile resistance forces of typical reinforcement materials in the
case of backfill materials having a frictional angle of 30 degrees.
Table 6.3.7 gives the applicability of backfill materials for different types of reinforced earth
walls.
In order to maintain the reinforcement effectiveness of the reinforced earth walls, backfill
drainage must be carefully considered and designed. Figure 6.3.9 gives an example of a road
slip restored using a Terre Armee Wall.
Road
Embackment Work
Bedrock
Figure 6.3.9 Example of a Road Slip Restored Using a Terre Armee Wall
Retaining walls should be carefully constructed because these structures are designed to retain
the extensive earth pressure and therefore the failure of these structures will result in the severe
damage not only to the road facilities but also to the road users.
a) The bearing ground should be excavated to a depth required for placing a footing if it is
bedrock, the excavated foundation surface of bedrock should be cleaned, and then the spread
footing should be placed.
b) If the bearing ground is earth or gravel, rubble stones should be laid over the excavated
surface and rolled fully and uniformly, leveling concrete should be poured over the rubble
stones, and then the spread foundation should be placed over it.
c) If the bearing ground is slanted, the portion at the valley side should be excavated in the form
of steps and the rock should be replaced with concrete to the bedrock line to form a
horizontal, uniform foundation. After this, the body of retaining walls or sabo dams should
be directly constructed over the foundation.
d) If the bearing ground is soft and compressible, a pile foundation should generally be applied.
In addition, if the soft ground (or stratum) is thin or if replacing material is easily available,
the soft ground should be replaced with good quality soils so that the retaining walls may be
built directly over the replaced material.
e) Timber piles, for example, 80 to 100 mm in diameter, 2.0 m to 3.0 m long, may be installed on
gabion walls at longitudinal spacing of 3.0 to 4.0 meters to prevent the deformation of the
gabion from the earth pressure of the back slope.
Backfilling should be not allowed until the retaining structure become stable and strong enough
to resist the earth pressure.
a) Only selected quality materials should be used to backfill the retaining wall.
c) Rain water should be completely prevented from flowing into the portion of backfilling.
d) Drainage facilities must be provided in order to drain the seepage water. Especially weep
holes must always be provided with a rate of one weep hole per 2-4 m2 of retaining wall.
In addition, in principle, anti-proof sand treatment behind the walls should be placed between
the walls and the back slope or backfilling to prevent the flow out of fine soil from the back slope,
and hence preventing from disturbing the stability of soil mass behind the walls.
CHAPTER 7
7.1 General
Rock fall, a rapid movement of individual rock blocks or small-scale rock mass on a steep rock
face, is one of the main road slope disaster along the N-M highway. As seen along the N-M
highway, lots of steep, high and long rock faces are close to the highway, and therefore, because
of its high speed can cause considerable damage to vehicles, death or injury to drivers and
passengers, and economic loss due to road closures.
Some road sections along the N-M highway require countermeasures against rock fall. However,
no any rockfall prevention works have been implemented yet. This is due partly to less or no
experience with rock fall prevention in Nepal.
For this reason, this chapter introduces several rockfall prevention works, including rock fall
prevention net and fence, and rock shed, which are considered to be most useful for minimizing
hazards to the traveling public at present and in the future.
Moreover, reference is made to Chapter 6 of this Technical Guide for the design of retaining walls,
which can be used as catch walls especially where there is space between the highway and the
rock face.
Countermeasures against rock fall shall be designed with the assumption that the external forces
are to be safely borne by each countermeasure and by using these as design external forces.
The motion of falling rocks on a steep slope is divided into three types, namely, sliding, rolling
and bouncing, as illustrated in Figure 7.2.1. These motion patterns change into other forms, as
shown in Figure 7.2.2.
In designing countermeasures for rock fall, the weight, speed, direction and position of the falling
rocks is determined on the basis of the survey and/or history of rock fall in the specific area.
Diagram
Rolling
Collision
Parabolic motion
Bouncing
Free fall
Source: Modification from MANUAL FOR COUNTERMEASURES AGAINST ROCK FALL, Published by Japan
Road Association, June 2000.
Among the three motion patterns, the velocity of falling rocks moving down a slope is highest
during the bouncing motion. The velocity of a falling and bouncing rock block along a slope is
less than that of the freely falling rock in the air from the same height.
Empirically, the following relationship is used to calculate the velocity of a falling and bouncing
stone.
V = α × 2 gh
µ
α = 1−
tan θ
Where, V= Velocity of a falling and bouncing stone (m/s)
Table 7.2.1 gives the recommended coefficient of friction based on experiments for different
kinds of slopes.
Table 7.2.1 Kinds of Slopes and Values of the Equivalent Coefficient of Friction
When designing countermeasures for rock falls, it is necessary to calculate the kinetic energy of
the falling rocks by means of energy calculations.
Kinetic energy of falling rocks is expressed by the sum of the linear velocity energy and rolling
energy, as follows:
E = Ev + Er
µ
E = (1 + β ) × (1 − )× m× g × H
tan θ
Where,
µ
β= Rolling energy ratio (=Er/Ev) and (1 + β ) × (1 − ) ≤ 1.0
tan θ
In the above equation, the value of β is generally in the range of 0.1 to 0.4, and 0.1 shall be used
most frequently for design calculations.
From the results of experiments conducted, the height of the bounce of the falling rocks increases
as the height of freefall becomes larger, but does not exceed 2 meters in most cases. Therefore, a
bounce height of 2 meters is frequently used as the acting position of the design external force for
countermeasure design.
Rock fall protection works shall be designed by converting the impact force of falling rock to a
static force and by using the allowable stress method instead of the energy calculation method.
Since the impact force of falling rocks is considerably large, it is advantageous to use
shock-absorbing materials to economically design these countermeasures, such as sand mats.
If the shock absorbing material is assumed to be an elastic body with a semi-infinite thickness and
the specific gravity of the falling rock is assumed to be 2.6, then the maximum impact force Pmax
of the falling rock can be expressed by the following equation:
2 2 3
Pmax = 2.108 × ( m × g ) 3 × λ 5 × H 5
Where,
Countermeasures for rock falls are classified into rock fall prevention works and rock fall
protection works. Rock fall prevention works involve the rock fall source, such as removal of the
rocks and crib work, while rock fall protection works aim at protecting the relevant objects from
the damage of rock fall. Table 7.3.1 includes the most common countermeasures divided into
these two categories.
Adequate and effective measures for preventing rock fall are selected in consideration of
topographical and geological conditions, falling causes, vegetation, rock fall history, and effects
of the countermeasure by predicting the size and height of the rock fall.
a) If there is a danger of rock fall, in principle, the rock fall source should be removed.
When these methods are difficult to be implemented, other methods should be adopted.
c) It is necessary to combine various kinds of works together because the function of the
various types of countermeasures for rock falls is limited, as shown in Figure 7.3.1.
Road Road
d) Countermeasures for rock falls are designed by assuming the external forces to be safely
borne by each work and by using this as design external forces.
For designing rock fall protection works, the following objectives must be considered:
b) Effectiveness in changing the direction of falling rocks to direct them to fall in areas
where they will inflict no or minimal damage, and
c) Effectiveness in reducing the impact force and to halt the motion of the rocks.
In selecting the proper countermeasures, their effectiveness and capability to resist the energy of
falling rocks are to be carefully considered. In general, the effectiveness of the protection works
in absorbing the energy of falling rocks are in the following order from least to greatest: rock fall
catch nets, rock fall catch fences, rock fall catch walls and rock sheds.
On the other hand, in selecting rock fall prevention works, care must be taken to ensure an
appropriate combination of protection works. Effective combinations of countermeasures against
rock falls are often determined by the function, durability, construction ease, construction cost
and maintenance requirements of each type of countermeasure, as well as the conditions of the
roads and slopes.
It is subdivided into removal and Recutting. Removal is one of the basic methods and should be
adopted prior to execution of any slope protection work such as installation of anchoring and
crib works. This work is frequently used when the fixing work is not applicable.
Recutting is applied for overhang slope or when the gradient of a slope is very steep.
For suspicious slopes of rock fall due to surface water, drainage work such as top slope ditch
and berm ditch should be applied. However, where slopes are composed of hard rocks, this
work may not be required because hard rocks may not be eroded and scoured due to surface
water.
This work is applied for slopes where big and support-less rock blocks exist and the removal of
those blocks are considered to be costly and difficult.
For slopes composed of materials that are easily eroded, scoured and weathered, slope
protection works are more recommendable.
Rock fall generally occur from slopes composed of hard rocks with developed cracks and joints,
even though there is no erosion, scouring and weathering. For these slopes, fixing work may be
adopted, especially if the gradient of slopes is very steep and re-cutting is not practical.
This work is also used when proper countermeasures can not be applied due to limitation within
the area of the slope
This work is adopted for slope where rock fall are very large in size and other countermeasures
are considered to be impractical and costly. This work is usually used for large-scale rock fall.
Rock fall catch nets (or rock fall prevention net) consist of nets and wire rope and include two
major types: cover type and pocket type. The cover type rock fall catch net is able to restrain loose
rocks by means of the net tension and friction between the rocks and the ground. The pocket type
rock fall catch net is installed with the upper end of the net separate from the surface of the slope.
Falling rocks from the upper slope are caught in the gap between the net and slope.
(1) Purpose
Rock fall catch nets are used to cover slopes that have a potential for rock falls in order to
protect road traffic from damage.
Figure 7.4.1 shows the design procedure. Figure 7.4.2 gives an example of pocket type rock fall
catch nets. When designing the pocket type rock fall catch net, the assumed point of collision of
the falling rocks is at the center of the two posts and at the center between the top and second
horizontal ropes.
b) Energy absorbable by the net in such a manner that it will be able to withstand the energy
of the falling rocks
c) Strength and stability of anchor on the assumption that the breaking of the rope will act to
the anchor.
START START
Determine the load of falling rocks and Calculate the energy of falling stones
the deadweight of net to be used for the design
Yes
Review the strength and stability of anchor Review the strength and stability of anchor
END END
a) Cover type rock fall catch net b) Pocket type rock fall catch net
Wire/Net
(>10.0m )
Anchor
5.0m
2.0m 2.0m
ROAD
1.5m
Rock fall catch fences consist of fences made of net and wire rope attached to steel pipes or
H-section posts. This type of fence has the capacity to absorb the energy of falling rocks.
(1) Purpose
Rock fall catch fences are intended to protect road traffic from rock fall damage, but differ from
rock fall catch nets in that they are installed near the road.
Figure 7.4.3 gives the design flowchart for rock fall catch fences. The design of a rock fall catch
fence involves consideration of the energy of the falling rock and the energy absorbable by the
fence, as given in equation below and involves the following steps.
ET = E R + E P + E N
Where,
ET= Energy that can be absorbed by the rock fall catch fence
a) Determine the yield tension Ty corresponding to the diameter of the wire ropes.
b) Find the force R acting on the posts from Ty of the wire ropes. The two wire ropes
are assumed to be capable of resisting the force of the falling rocks.
c) Find the force Fy required to form a plastic hinge at the bottom of the intermediate
post.
d) Compare forces R and Fy and calculate the energy that can be absorbed by the
fence.
The height of the point of impact is generally considered to be two-thirds of the height of the
fence, and falling rocks are assumed to collide with the wire ropes between posts for the
design.
In designing the foundation (retaining wall or direct foundation) for the fence, loads due to
falling rocks should be considered in addition to the earth pressure and dead load.
START
END
(h1secθ - h1)cotθ
l: Width of flat area
l
ET: Absorbable energy by fence
l
g: Gravity acceleration
Height Post
of Wire Rope Wire Net
Fence Sectional Interval
Size and Type
(m) Coefficient (cm3) (m)
1.5 3×7G/0, φ18
2.0 H-200×100×5.5 Sectional area:
2.5
×8
181 A = 129 mm2 diamond
3.0 Elastic coefficient shape
3.5
3.0 Ew = 105 N/mm2
4.0 Fracture strength φ 3.2 × 50
4.5
H-200×100×8× Tb = 157 kN ×50
5.0 472 Yield strength
12
5.5 Ty = 118 kN
6.0
Source: Modification from MANUAL FOR COUNTERMEASURES AGAINST ROCK FALL, Published by Japan
Road Association, June 2000
Rock sheds are reinforced concrete or steel structures covering a road and can be subdivided into
four types from the structural viewpoint; portal (gate) type, retaining wall type, arch type and
pocket type (Figure 7.4.4).
This method is very costly and would only be planned and designed in areas of extreme rock fall
hazard.
Deposited mass
Absorption materials
Jointed Rock
Jointed Rock
ROAD ROAD
(1) Purpose
This method is applied to reduce road disasters due to rock fall or rock mass failure by absorbing
the impact force of a falling rock mass or changing the direction of the movement of rock mass
failure and rock falls.
The most important design consideration should be the calculation of the impact force of the
falling rock mass. Rock sheds are designed after converting the impact force into a static force
according to the allowable stresses design method. For the purpose of simplifying the calculations,
the area on which the impact load is calculated is assumed to be rectangular rather than circular.
The design procedure generally involves the following steps shown in Figure 7.4.5. The kinds and
combination of loads to be considered in the design of the rock shed are shown in Table 7.4.2.
ST A RT
EN D
Furthermore, in the conventional design method, the dispersion of loads on the roof slab of the
rock shed is simplified, as shown in Figure 7.4.6.
Deposited material
Water pressure
Earth pressure
Impact by car
Earthquake
Coefficient
Dead load
Weight of
Rock fall
of increase
in
allowable
unit stress
P
Falling Rock
Impact Absorbing
h 45 o 45 o Materials
Roof Slab
A = π h 2 /4
√π×h/2
√π×h/2
Source: Modification from MANUAL FOR COUNTERMEASURES AGAINST ROCK FALL, Published by Japan
Road Association, June 2000
CHAPTER 8
8.1 General
Most of road slope structures, such as retaining walls, drainage ditches, and vegetation, will
gradually deteriorate and weaken naturally and/or artificially after their construction. Because of
progressive deterioration and deformation, these structures (or works) may lose their originally
expected functions and result in road slope disasters in the worst cases.
On the other hand, the road slopes, including cut slopes and natural slopes, are mostly the main
sites of sediment disasters such as landslides, slope failures and rock falls because road
excavation disturbs the initial stability of the slopes and facilitates erosion, scouring and
weathering of the slopes.
The purpose of the maintenance of road slopes is to identify and determine the potential road
disaster sites that have the possibility to cause road disasters and associated traffic problems, to
take prompt and corrective action to return the road slopes to usable and stable conditions, and
to minimize hazards to the traveling public.
Further, as mentioned above, the road facility involves natural slopes and slopes with structures.
The maintenance of road slope will discuss on the following three categories in this chapter:
Basically, the first maintenance work is to inspect the abnormal situations of natural slopes. If
there are any signs of deformation and movement, and a road disaster are judged to be likely to
occur, monitoring and related emergency measures are required.
The second maintenance work, on the other hand, may be to a) inspect the present conditions of
structures, b) maintain the functions of structures, and c) implement structural measures in case
of emergency.
The third maintenance work, similar to the second work, deals with streams and related sabo
facilities.
a) Inspection on natural and cut slopes, road structure, road-related streams and sabo
facilities
8.2 Inspection
Regular inspection and monitoring herein involve mainly slopes and the structures fulfilled by
the preventive works, particularly focusing on those abnormal situations and signs of
deformation occurring in the road slopes and structures.
a) To aid in identifying potential landslide area and damaged structures to need repair
c) To provide vital information for establishing a priority program for allocating monies and
repair
d) To provide vital and historical data for technical staff for review
As we know, heavy rainfall has been regarded as the most important factor inducing road slope
disasters in this project area. Road slope disasters have occurred almost during and immediately
after heavy rainfall.
It is thus recommended that, as a minimum, inspections most be carried out twice a year before
and after rainfall in consideration of the occurrence frequency of road disasters and the
deterioration degree of the existing structures. It may be adjusted depending on slope conditions,
ongoing status of the ground and structure deformation, earthquake and meteorological change. It
is recommended, for instance, an additional inspection in case of heavy rain of 200 mm/day or
after earthquake.
In addition, a technical staff and/or a geological engineer should do regular inspection if possible.
The inspection is at present proposed to be carried out in the following locations and elsewhere
any sign of abnormal condition is recognized.
b) All locations with preventive structures including sabo facilities along the N-M
highway
c) Sta. 27km + 50
Sta. 27km + 50 and Sta. 26km + 700 are two small-scale landslides cross the highway, which
were identified during the Study. Their details are described in another Section of this chapter.
Later, as time and budget permit, the inspection could be expanded to include:
In addition, a technical staff and/or a geological engineer should do regular inspection if possible.
Inspection shall be made basically by visual observation to the sites; natural and artificial slopes,
including bio-engineering work (vegetation), stone masonry wall, gabion wall, drainage ditch,
horizontal drain hole, gabion sabo dam, natural slope, cut slope and road surface. The results of
inspection shall be recorded and filed as database which is shown in Table 8.2.1 and Appendix
8-1 to 8-4.
The points to inspection and records are listed, in terms of every works and slopes, as follows.
b) Poor growth corresponding to the local geological conditions (clayey soil, sandy soil,
bedrock, etc.)
c) Swamp around the structures due to leakage of water from these structures
d) Gap between the structures and the ground, due to surface water erosion and landslide
movement
b) Collapse of outlet
c) Amount of collected water from each hole before and after rainfall
c) Loose anchor
c) Conditions of drainage
a) Gap between the road surface and the settled embankment area
d) Conditions of rust of head device, pressure bearing plate and anchor bar
b) Scour of surface
(15) Stream
After inspection and monitoring, if some structures are partially weakened and locally damaged,
or signs of a landslide movement are observed, maintenance and/or repair should be
immediately made to these facilities and areas.
Routine maintenance and repair (RMR) activities are mainly, with simple, fast, cost-effective
methods, as follows:
Some practical maintenance and repair methods in response to different structures and road
disasters are suggested below:
Vegetation becomes only after the growth of the plants, and their effects can be continued for
many years and only if they are properly maintained.
b) To re-vegetate with wicker for broken covers, collapsed area due to erosion or slope
failure
c) To place gabion or sandbag on the toe part of vegetated slopes to minimize the runoff
erosion
Because water is the main cause of landslide and slope failure, the extra precaution should be
taken for the drainage facilities. For drainage ditch, the following maintenance and repair should
be done to keep its function:
c) To repair cracks, gap and joints in ditch and culvert with mortar
d) To fill gap and cracks between ditch/culvert and the ground with clay
c) To extend the drain pipe with PVC pipe. If the drainage pipe is terminated too short, this
may allow water to discharge onto the slope again.
a) To install wooden pile (φ100 to 150, L=2 to 3.0 meters) on the valley side of gabion work,
when subject to deformation
b) To fully fill the gap or subsidence between the wall and the ground to minimize the
flowing of surface water into the ground behind the wall
c) To install stone masonry to reinforce its foundation when subject to foundation scouring.
Also to direct surface water away from the damaged area by installing stone pitching
ditch or similar structures
a) To repair the damaged or broken wall with stones and mortar. Also to install weep holes
(PVC, φ40-50, L= L=2 to 3.0 meters) when the damage is considered to be due to
spring erosion
b) To fully fill the gap or subsidence between the wall and the ground to minimize the
flowing of surface water into the ground behind the wall
a) To place plain concrete of about 3 to 5 cm think on the crest part of a gabion sabo dam to
prevent damage of wire mesh box from massive debris flow sediments
c) To install wooden pile (φ100 to 150, L=2 to 3.0 meters) on the valley side of gabion work,
if possible, when subject to deformation or inclination
The main maintenance activity relating to sabo dam, including gabion and concrete sabo dams,
is to remove the sediments deposited behind the dam in order to maintain their functions.
A number of sabo dams have been constructed along the mountain streams, especially on the
mountain side of the road. These sabo dams were constructed mainly to catch the overall or
partial deposits due to debris flow, and hence to prevent the road from hit of debris flow. In
general, the functional recovery of an existing sabo dam by removing deposits is thus one of the
most important and cost-effective methods. Figure 8.3.1 conceptually shows the functional
recovery of existing sabo dams.
B
Sabo dam
Original streambed line
The sabo dams to be required for removal of deposit are recommended to be those sabo dams
within about 100 m far from the road, in consideration of the easy access and a larger capacity
of deposit catch after removal. on the other hand, sabo dams in the upstream are suggested to be
excluded because they also have the same function as embankment to protect the toe failure of
valley slope in addition of deposition of sediment.
Refer to the Drift Final Main Report prepared in this Study to know the sabo dams which are
required for removal of deposits.
It is suggested that the removal of deposits be preferably completed before the rainy season. In
addition, for the time being the removal of deposits should be conducted by manpower with
some simple equipment, such as trolley, wooden channel, plastic hose etc. The wooden channel
functions as flume to flow the deposits and is tentatively called Debris Flow Flume (DFF). The
Debris Flow Flume should be reinforced with thin steel sheet inside to facilitate the flow of
deposits. Figure 8.3.2 gives the schematic diagram for removal of deposit using DFF and the
structural detail of the flume will be considered in the next stage.
Sabo dam
ROAD
a) A monorail car easily runs on a narrow valley and steep slope with a speed of about 30
m/min to 40 m/min,
When a small landslide or slope failure has occurred, maintenance and repair should be done to
prevent the landslide from becoming worse, or to slow or stop slide movement. These are as
follows:
b) To fill open cracks on its head portion and on both sides with clay
c) To direct the surface water away from the landslide area using pipe or stone pitching
ditch
d) To cover the cracked port of the slope in order to prevent the infiltration of rainwater and
to prevent progressive failure
A road shoulder slip may be due to undercutting or erosion by overflow from hill slope. In the
worst case, the right of way would be completely lost.
c) To place gabion wall on the valley side to prevent road shoulder from erosion of runoff or
undercutting
If any sign of large landslide or failure is found or any imminent event is identified, emergency
measures should be immediately performed together with reevaluation of slope stability and
study of preventive measures.
In this Technical Guide, emergency measures as temporary works are, when an emergency
event is identified or found, those works which can be implemented simply and fast in order to
avoid large slope failure and subsequent damage before the required permanent works are
commenced.
The following introduces several emergency works for road slope disasters. These emergency
measures can generally be applied in combination.
8.4.1 Drainage
Surface and subsurface drainage is always one of the main emergency measures. Because many
open cracks are always associated landslide movement (Figure 8.4.1a), top slope ditch by
open-cut with plastic sheet or by rock pitching are more desirable to cut off flowing into from
surrounding slopes.
If the landslide is moving, horizontal drain holes (PVC pipe) should be performed. It is notes
that several drain holes (lateral boring) should be drilled across the open cracks approximately
10 to 20 m at 5 to 10 m intervals in the direction of cracks as shown in Figure 8.4.1.
5 ~ 10 m Crack
Lateral
Landslide
Lateral Boring
Block
Boring
Road Groundwater
Level
Retaining Structure C/L
(Gabion Mat)
River
Road
10 ~ 20 m
Sliding
River Surface
a) Plan Image b) Longitudinal Image
It is an effective measure in many cases to perform horizontal cutting of the soil mass by several
meters at the head of a landslide as shown in Figure 8.4.2. However, this removal should not be
performed if the upper slope of the cutting may become unstable, or if it is located at the tail of
a secondary landslide area behind the proposed cut that may be predicted to slip
If the toe of the landslide is likely to collapse or if a failure is likely to enlarge, earth retaining
works should be installed with cylinders or mat gabions at the toe.
Earth Removal
Original
Slope Line
If any signs of slope failures or open cracks are found on the upper slope or a slope failure has
occurred, the scale and range of the failure or potential failure should be examined at first.
In case the slope failure has occurred only locally and there is no immediate danger of
occurrence of other large-scale failures, then it is the simplest to take emergency measures by
using wicker works. Besides the said situation, if the scale of the failure is large, it becomes
necessary to secure the long-term stability by re-shaping the slope and providing a gentler
gradient as shown in Figure 8.4.3.
If the slope failure is only local or partial on the lower portion of hill slopes, the failure surface
should be protected by piling sand bags as an emergency work. If spring water is found flowing
out from the failed portion, gabion mats should be recommendable and the appropriate surface
water treatment also should be provided, as illustrated in Figure 8.4.4
Cracks
Covering with
Vinyl Sheet
C/L
Failure
Surface
Figure 8.4.3 Example of Emergency Measures and Restoration after Cracks and
Failure on the Upper Slope
Failure
Collapse
Soil
C/L
Emergency Countermeasure
Spring Water
Stopping Pile
Fixing Pile
On the other hand, if a larger scale failure may occur due to further infiltration of rain water,
then the failed slope should be stabilized by providing a counterweight embankment until
implementing permanent restoration. Furthermore, it should be noted that an underground water
drainage facility should be provided in order to avoid filling the embankment body with water
In most cases, slope failures on the valley slope of the road are due mainly to erosion of runoff
and overflow from the ditch. If the slope failures of road shoulder collapse, which are generally
about 5 m or less in width, are small in size, they can be treated by using wicker and sand mats,
as shown in Figure 8.4.5. Also installation of gabion mats at the toe of the slope is effective
when spring water is observed issuing from the failure surface
Failure
Bench Cut
Emergency
Countermeasure
Wicker by
Wooden Pile
Countermeasure against Spring Water
Sand Bag
Spring Water
Failure Surface
Gabion Mat
Figure 8.4.5 Example of Emergency Measures by Sand Bags or Gabion Mats for Valley
Slope
In addition to locations described in Section 8.2, on the basis of the detailed field
reconnaissance along the highway, the following locations are proposed for regular inspection in
order to secure the safety of road traffic and to maintain the present road situation.
c) Cracks and settlement cross the road around Sta. 26km + 700
Also, the above-mentioned locations, as actual examples, inspection points and conceivable
emergency works are described.
At the 2003 flooding road shoulders were partially washed out due to bank erosion along the
Trishuli River. As restoration works, the washed away road shoulder was filled by embankment
and the embankment was stabilized by combination of concrete retaining wall and anchors.
At the time of field visit, the settlement and gap of the road surface due to embankment
settlement behind the retaining wall and the inclination of retaining wall toward the river side
were numerously observed, as shown in Figure 8.5.1.
When the deformation and settlement of retaining wall is in fast progress, the road shoulder as
well as retaining wall and anchors is likely to collapse at the same time. Accordingly, this will
have a considerable hazard to the safety of road traffic.
In this reason, regular inspection and monitoring at the anchor installation locations are required
to avert risk and minimize losses.
The points to observation and monitoring are listed, focusing on those abnormal situations and
signs of deformation occurring in the road surface, ground surface and structures, as follows
(Figure 8.5.1).
a) Gap between the road surface and the settled embankment area
If any sign of large collapse failure is found or any imminent event is identified, emergency works
should be immediately performed together with reevaluation of slope stability and study of
preventive measures.
In the anchor installation locations, conceivable emergency works and repair methods are as
follows:
a) To remove surface water out of the target area by using drain ditch,
b) To protect shallow collapses on the valley slopes with gabion mats, if necessary, to install
timber piles (80 to 100 mm, 2.0 m to 3.0 m long).
c) To fill cracks and gaps on the road surface with clay or mortal.
d) To cover the failed and cracked slopes and road surface with plastic or vinyl sheets.
Around Sta. 27km + 50, a crack obliquely cross the road, about 5 m long, was observed at the
time of field visit. The crack resulted presumably from the movement of a small-scale landslide,
about 15 wide, as shown in Figure 8.5.2.
The landslide is in close proximity to the small stream that flows cross the road. Two gabion
sabo dams were constructed in the stream on the valley side of the road. The initialization of the
small landslide was considered to be due to foundation excavation of the gabion sabo dams.
The small landslide was considered, based on the field visit, to be less likely to reactivate and
quickly slide down. However, once sliding down, the right of way would be completely lost. As
restoration works, highly costly combination of anchor, retaining wall and embankment would
be required.
Mountain side
Road
Sabo dam
Therefore, ongoing status of the crack should be regularly inspected and monitored for securing
the safety of road traffic.
The frequency of regular inspection is the same as that for the anchor installation locations, as
described above.
In addition, in the case of emergency, conceivable urgent measures and repair methods are as
follows:
b) To fill the cracks and gaps on the road surface with clay or mortar,
Around Sta. 26km + 700, a road surface gap of about 2 cm was observed at the time of field
visit. In addition, some opening cracks were observed on the side masonry ditch and masonry
wall on the hillside.
Similar to the small-scale landslide at Sta. 27km + 50, the landslide movement would make the
right of way completely lost. Therefore, the ongoing status of the gap and crack on the road
surface and masonry wall should be regularly inspected and monitored for securing the safety of
road traffic.
50 m
Mountain side
Road
50 m River side
2-cm gap
Settlement
Further, in case where unusual conditions or ongoing conditions of the deformed structures are
observed, e.g. significant settlement on the road surface and obvious opening of cracks on the
masonry wall observed, advice for emergency measures should immediately be sought from a
geologist or landslide expert.
a) To remove surface water out of the landslide area by installing a drain ditch above the
upslope end of the landslide area,
b) To fill the cracks and gaps on the road surface with clay or mortar,
c) To construct retaining concrete wall with anchors on the valley slope of the road.
Photographs
General View
General Description
Appendix 8-2 Asset Inventory Sheet 2: Evaluation of Existing Countermeasure
Road Name Narayangharh-Mugling Highway
Station from km m S.No.
Location (Distance from Road Center) km m
3-1 Front view/ Plane view sketches
Comprehensive Evaluation
Appendix 8-3 Asset Inventory Sheet 3: Rehabilitation Plan
Road Name Narayangharh-Mugling Highway
Station from km m S.No.
Name of planner
DESIGN EXAMPLES
1 Sabo Dam
This section provides an example of sabo dam design, which is based on the following
guidelines:
a) Technical Guideline for Debris Flow Control Measures (Tentative), July 2000, Prepared
by Sediment Control Division, Sediment Control Department, River Bureau, Ministry of
Construction.
b) Technical Standard for the Measures against Debris Flow and Driftwood, August 2007,
Prepared by Sediment Control Division, Sediment Control Department, River Bureau,
Ministry of Construction.
The design data and conditions are determined on the basis of site investigation and common
engineering practice as shown in Table 1.1.
The peak discharge, Qp, of clear water due to rainfall is calculated as follows:
1
Qp = × f ×r a × A
3.6
ra : Average rainfall intensity (mm)
In case of no average rainfall intensity available in the project area, the peak discharge, Qp, can
be calculated as follow:
1 1
Qp = ×r e × A = × 129.5 × 0.12 = 4.32 m2/s
3.6 3.6
re : Effective rainfall intensity (mm), which is obtained using the following method:
P24 1.21 24 × f 2
re = ( ) × ( )0.606
24 kp / 60 × A 0.22
The design discharge of a dam is determined by considering the sediment content ratio, using
the return period of about 1:100 years of daily rainfall or previous maximum rainfall, whichever
is larger.
50% sediment mix is generally added to the peak discharge (Qp) in Japan, the Q, is calculated as
follows:
ρ w × tan θ
Cd =
( ρ g − ρ w ) × (tan φ − tan θ )
The amount of possible debris flow in assumed debris flow area is obtained by estimating the
amount of possible debris flows in each branch at upstream of the planning point as shown in
Table 1.2.
As shown in the table above, the assumed debris flow area 1 has the biggest amount of possible
debris flow.
10 3 × P24 × A C
Vdy 2 = × ( d ) ×K f 2
1− Kv 1 − Cd
As calculated above, the amount of possibly transported debris flow at one debris flow event is
larger than that of possible debris flow in assumed debris flow area, as follows:
27,200m3 >2,520 m3
Accordingly, the amount of assumed debris flow at one debris flow event is set as Vdqp=2,520m3.
Vdqp × C 0
Qsp = 0.01 × ∑ Q = 0.01 ×
Cd
2,520 × 0.6
= 0.01 × = 36.9 (m3/s)
0.41
1.4 Design Depth for Design Discharge
The design depth of a dam is determined by considering 1) design depth for design discharge, 2)
design depth for peak discharge of debris flow and 3) design depth for maximum grain size of
debris gravel, whichever is biggest.
The width of crest opening is, in principle, over 3.0 m. The width is set to be same as the width
of existing streambed, as follows:
Here the inclination (m2) of opening is 0.5, the discharge of opening is shown in the following
figure and calculated as follows:
B2
h2
1:m2
Hc
h1
B1
1
3/ 2
Q = (0.71 × h1 + 1.77 × B1 ) × h1
h1 = 0.79m ≅ 0.8m
The design depth of debris flow, h, is calculated using the following equation:
3
Qsp ⎧ n × Qsp ⎫ 5
h= =⎨ 0.5 ⎬
=1.43 m =1.5m
B × Vdf ⎩ B × (sin θ ) ⎭
Qsp 36.9
Vdf = = =5.16 m/s
B×h 5 × 1.43
The design depth of opening is determined to be 1.5 m on the basis of the calculation above, as
listed below:
The freeboard depends on the design flood discharge, as shown in Table 1.3.
The sabo dam is designed pass through debris flow, and the height of crest opening, Hc, is thus
determined to be the sum of design depth, h, of debris flow and freeboard, ∆H, as follows
The section of crest opening is, on the basis of the above calculation results, set and shown in
Figure 1.2.
7.3 m
0.8 m
1:0.5
1.5 m 2.3 m
1:0.5
5.0 m
Load combination for stability analysis is dependent mainly on the height of dam body and
given in Table 1.5.
n:1 W2
H=9m m:1 PH2
W3 W1 Basic point
PH1
of calculation
1) Dead weight
W = Wc × V
Where:
2) Hydrostatic pressure
P = ρ w × hw
Where:
3) Load combination
fr × V 0.6 × 1234.57
Fs = = =1.32>1.2, Therefore OK.
H 561.43
2) Analysis against overturning
M 6028.01
X = = = 4.88
V 1234.57
B=2.25+3.00+2.25=7.50, Then, (B/3=2.5) <(X=4.88) < (2B/3=5.00), Therefore OK.
1 1
e= X − B = 4.88 − × 7.50 = 1.13
2 2
V ⎧ e ⎫
q= × ⎨1 ± (6 × )⎬
B ⎩ B ⎭
1234.57 ⎧ 1.13 ⎫
q max = × ⎨1 + (6 × 2 2
⎬ =313.42kN/m <qa=600kN/m , Therefore OK.
7.50 ⎩ 7.50 ⎭
1234.57 ⎧ 1.13 ⎫
q min = × ⎨1 − (6 × 2 2
⎬ =15.80kN/m >0 kN/m , Therefore OK.
7.50 ⎩ 7.50 ⎭
b1
m:1 PV1
W2
n :1 PeH2
H PH2 H
W3 W1
PeH1 PH1
σ1 nH b1 mH σ2
1) Dead weight
W = Wc × V
Where:
γd 2 17.4
F= h × Vdf = × 1.11 × 5.16 2 = 52.5 kN/m2
g 9.8
Where:
Where:
Pe = We × he
Where:
4) Load combination
Table 1.9 Summary of Calculation Results for Debris Flow (n=0.25, m=0.25)
Vertical Horizontal Arm length Arm
Design Symb Calculation Moment
force force calculation length
load ol (a) (kNm)/m
(V) (H) (b) (L) (m)
1/2×22.56×0.25
W1 228.42 2/3×0.25×9 1.50 342.63
×92
Dead
W2 22.56×3.0×9 609.12 0.25×9 +1/2×3 3.75 2284.20
weight
f × V 0.6 × 1262.45
Fs = = =1.23>1.2, Therefore OK.
H 613.62
M 6218.12
X = = = 4.91
V 1262.45
B=2.25+3.00+2.25=7.50, Then, (B/3=2.4)<(X=4.91)<(2B/3=5.00), Therefore OK.
1 1
e= X − B = 4.91 − × 7.50 = 1.16
2 2
V ⎧ e ⎫
q= × ⎨1 ± (6 × )⎬
B ⎩ B ⎭
1262.45 ⎧ 1.16 ⎫
q max = × ⎨1 + (6 × 2 2
⎬ =324.53kN/m <qa=600kN/m , Therefore OK.
7.50 ⎩ 7.50 ⎭
1262.45 ⎧ 1.16 ⎫
q min = × ⎨1 − (6 × 2 2
⎬ =12.12 kN/m >0 kN/m , Therefore OK.
7.50 ⎩ 7.50 ⎭
The design data and conditions are determined on the basis of site investigation and common
engineering practice as shown Table 2.1
q=10kN/m2
B1=0.40m
H1=3.0m
H0=2.0m
β =33.69 o
Gravely soil
H=3.0m o
φ=35
Wall body weight, Wc, and weight centre, Xc, are calculated below:
H 3.00
Wc = × (b + B) × γ c = × (0.40 + 2.20) × 23 = 89.7 kN/m2
2 2
B H 2b + B
Xc = + × ( m − n)
2 6 b+B
2.20 3.00 2 × 0.40 + 2.20
= + × (0.40 − 0.20) = 0.98 m
2 2 0.40 + 2.20
(2) Earth Pressure
' q 10
Ho = Ho + = 2.00 + = 2.50 m
γ 20
Ratio of embankment height to wall height is calculated below:
'
Ho 2.50
= = 0.883
H 3.00
Therefore, according to chart of active earth pressure coefficient, active earth pressure
coefficient is estimated below:
At H0/H=0.8, Ka = 0.890
At H0/H=0.9, Ka = 0.919
0.919 − 0.890
Therefore, at H0/H=0.833, K a = 0.890 + × (0.833 − 0.8) = 0.900
0.1
2) Active earth pressure, PA
1 1
PA = K AγH 2 = × 0.90 × 20 × 3.00 2 = 81.0 kN/m2
2 2
The vertical earth pressure, PAV, Horizontal earth pressure, PAH, are respectively calculated
below:
Where:
H 3.00
YA = = = 1.00 m
3 3
X A = B − n × Y A = 2.20 − 0.40 × 1.00 = 1.80 m
∑ V × µ 147.1 × 0.6
Fs = = = 1.55 >1.5, Therefore, OK.
∑H 57.1
∑ V × x − ∑ H × y 191.2 − 57.1
d= = = 0.91 m
∑V 147.1
B 2.20 B
e= −d = − 0.91 = 0.19 ≤ = 0.36 , Therefore, OK.
2 2 6
∑V 6e
q= (1 ± )
2B B
∑V 6e 147.1 6 × 0.19
q max = (1 + ) = (1 + )
2B B 2.20 2.20
=102kN/m2 < qa=300 kN/m2, Therefore, OK.
∑V 6e 147.1 6 × 0.19
q min = (1 − ) = (1 − )
2B B 2.20 2.20
=32kN/m2 > 0 kN/m2, Therefore, OK.