Académique Documents
Professionnel Documents
Culture Documents
I
;;". 11. ".,,;\;I\!101"\;!:^.:it> I, I. ill. ^. 1,111!
.
I. I II'.
.
". ,
I ,
@
Vincent POWell-SiniilT
1990
IsBN 0-409-99592-4
71 .
Preface
V
vi Pity'uce
.
Table of Contents
Page
V
Prey'ace
IX
Flowc/iai. Is
X
Table of Cases
ntro u c tio n . . . . . . . . . . . . . . . . . . - - - - - - - - - - . . . . . .
The conditions
Clause I Contractor s o blig atton s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clause 2 Archite c I S In sIruclion s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cl au s e 3 C o ntr ac t doc urn en ts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clause 4 Statutory obligations, notices, fees and charges ........................
Clause 5 Levels and s etting-out of the works . ..... .. ... .. ... .. ... ... .. ..... . .. .. .. .. ...
Clause 6 Materials, goods and workmanship to confomi
to description, testing and inspection ......................................
Clause 7 Royalties and p atent rights .... .. .................. ..... .. .... ..... .. .. . -. - -. .. . - - - - -
Clause 8 Foreman-In- c ar e . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clause 9 AC CGs s for architect to the works . .. . ...... .. ... ...... ..... .. .... ... . ... . .... . ..
Clause 10 Clerk of w orks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - - - - - - - - - - - - -
Clause I I Variations, provisional and prime cost sums .............................
Clause 12 ontract I s -------. ........"""""' '
Clause 13 o n tract s uin - - - . . . - - - - ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' '
Vll
vilI Table of Collieii!r
'aoe
Clause 23
Clause 24
Exten SIon of time .. . .. . ... .... ... .. . . . .. . .. . .. . . 87
Loss and expense caused by disturbance of reoular
Clause 25
progres s of the works . . ... . . . .... . . . . . . . . . . . . . . . . . . . . . .. . 99
Clause 26
Determination by, employer ................ ............ I 07
Clause 27
Deierrnination by contractor .............................. I 15
Clause 28
Nominated sub-contractors .............................. 122
Clause 29
Nominated s up pliers ............................... 136
Clause 30
Artists and tradesmen ................................ 139
Clause 31
Certificates and paymenIs .................................... 141
OUIbreak of hostilities .................................
...........------- 154
Clause 32 War damaoe. ............... ... ... .. ...
e -------------------------------------........... .......... .. . . . .. I 5 6
Clause 33
Clause 34
Antiq uities . . .. . ... . . .. . .. . .. . . ... . ... . ... . . .. . .. .. .. 158
Arbitration . . . .. .... . .... . . . . .. .... . .. . ... . ... ....... . . . . . ... 159
index ...................
.
Flowcharts
Page
Flowchart I Architect's instructions
( clau se 2 ) .................................................................. _
Flowchart 2 Extension of time : Contractor's duties
(cl anse 23 ) ................................................................ 9 7
Flowchart 3 Extension of time : Architect's duties
(clause 2 3 ) .................-------....."""""""""""""""""'
Flowchart 4 Loss and/or expense : Contractor's duties
(clause 24) .............................................................. I 05
Flowchart 5 Loss and/or expense : Architect's duties
(clause 24) .............................................................. I 06
Flowchart 6 Delenmination by employer ..... ........ ..................... .. . .. I 14
Flowchart 7 Detennination by contractor ..... .. ...... .. ................. ..... . 121
IX
Table of Cases
Page Page
AMF (international) Ltd v Magnet Convent I{OSpiial Ltd v Eberlin &
Bowling Lid 119681 2 All Pinrs
ER 798 . 65 (1988) 14 ConLR I 8
A1gre}, Contractors Ltd v Tenth CToudace Ltd v London Borough of
Moat Housing SOCiei\, Ltd Lambeth
(1972) I BLR 45 ............:.......... 84 (1986) 6 CollLR 70 5.9.102
Amalgamaied Building Contractors Cutter v POWe11 (1795) 6 TR
Ltd v Wallham Holy Cross Urban 320 ..--."' "' ..................... 2
District Council
D & F Estates Lid v Church
119521 2 All ER 452. ................ 91 Commissioners for En, ,land
Appleby v Myers (1866) 2 (1988) 15 ConLR 35 ....:............. 127
LR CP 651 ,....
3.73
..............
Davies v Collins 119451 I All
Argyropoulas & Pappa v Chain ER 247 .. 62
Coinpania Naviera SA (1990) Dawber Williamson Roofing Lid v
7 - C L D - 05 - 0 I . . . . . . . . . . . . . . . . - - - - - - - - - - 10 Humberside Count>. Couiicil
Ban Hong 100 Mines Lid v Cheii & (1979) 14 BLR 70 .................... 52 112
Yap Ltd 119691 2 A1LJ 83 117
I Depariineiit of the En\ ironnieni for
Bolton v Mahadeva 11972: I Northern Ireland \. Farrans
..................... .. 2 (Construction! Ltd
BOSkalis We SIminsier Construction (1981) 19 BLR I . 85
Lid v Liverpool City, Council Dodd v Churlon 11897j I QB
(1983) 24 BLR 83 ...... 93 562 .. 88
Brainall & Ogden Ltd v She theId Englesham v A1cMaster
City Council [1920] AllER Rep 174. ....... 10
(1983) I ConLR 30 ................... 58, 85 English Industrial Estates Corporalion
British V, 'agon Co v Lea v George Wimpey & Co Lid
(1880) 5 QBD 149 .... ............. 62 119731 I Lloyd's Rep 118 .....
Building & Estates Ltd v AM ETiksson v Whalley 1197/1
NSWLR 397 . 110
Connor 119581 MLJ 174. ............ 2.9
Carr v IA BeTriman Ply Ltd EUsof A1i v Nyonya 'Lee Gaik
Hook
(1953) 27 ALJR 273 ..... 41
Central Provident Fund Board v Ho [1953] MLJ 98 ...................... 61
Bock Kee FG Minter Ltd v Weish Health
(l 981) 17 BLR 21 .................. 110. 161 Technical Services Organisation
Central Provident Fund Board v Ho (1980) 13 BLR I ..................... 46,100
Bock Kee Fairclough Buildino Ltd v Rhuddlan
(1981) 2 MLJ 162. ........ Borough Council
77
(1985) 3 ConLR 38 131
Cheng Keng Hong v Govt of the
............
I'
.t.
J.
it
, .t
,. 11
I '
Table of Cases xi
I
Page Page , .
I;
Glenlion Construction Ltd v The James Archdale & Co Ltd v A,
Gumness Trust Coinservices Ltd ,;
(1987) 11 ConLR 126 81,103 119541 I WLR 459 .......... 65 IJ *
,
Gold v Patinan & Fotheringham Ltd John Jarvis Ltd v Rockdale Housing ,.
,,
Brick Co Ltd
(1982) 23 BLR 10 ................... . 43 ..
(1988) 39 BLR 106 .................... 89 Ltd (1976) 3 BLR 104 ................ 145
H Fairweather Ltd v Asden Kunchi Raman v Goh BTOS Sdn Bhd
Securties Ltd t1978/1MLJ89. .. 2
(1979) 12 BLR 40 84 Lebeaupin v Crispi
HW Nevill (Sunblest) Ltd v Win [ 1920] 2 KB 714 ........................ 92
Press & Son Ltd
Lee Kam Chun v Syarikat Kukuh
(1981) 20 BLR 78 ............... 54
Maiu Sdn Bhd
Han Hasnan v Tan an Klan 119631 [1988] I CU 52 ...................... 148,149
MU I 75 ..... ................................ 12
Leon Engineering & Construction
Haulck v Nelson Canton Co Ltd v Ka Duk Investment
Construction Co Ltd
[1964] NZLR 72 ......................... 119 [1989] TCLR 465 9
Henry Boot Construction Ltd v
Central Lancashire New Town
Letchumi Am mai v Nam Fong
Housing Sdn Bhd
Development Corporation 119821 2 MU 19 61
(1980) 15 BLR I ...................... 95,139
Hickman & Co v Roberts Litn Hong Shin v Leong Fong Yew
(1918) 2 FMSLR 187 50
1/9/31 AC 229 ....... 10
Higgins v Northampton Corporation Ling Heng Toh Co v Borneo
[1927] I Ch 128 49 Development Corporation Sdn
Hoenig v Isaacs [1952] 2 All Bhd [1973] I MU 23 .............. 118,144
ER 176 2 London .Borough of Camden v
Houand Harmen & Cubitt 040rthem) Thomas MCInemey & Sons Ltd
Ltd v WeIsh Health Techitical (1986) 9 ConLR 99 144
Services Organization London Borough of Hillingdon v
(1981) 18 BER 80 ...................... 2,31 Cutlet
Holme v Guppy (1838) 2 M [1967] 2 AllER 361, CA 20
& W 387 80 London Borough of Hounslow v
Hong Kong Fir Shipping Co Ltd v Twickenham Garden
Kawasaki Kisen Kaisha Ltd Developments Ltd
[1962] 2 QB 26. ............ ............. 4 [1970] 3 An ER 326 ................ 80,112
XII Tubl, ' of' C, JICA
Page Page
London BOTougli of Merio!I \. P & M Ka\e Ltd \' Hosicr &
Sinnlc\' Hugli Lcach Ltd Dickinsoii Ltd
(1985) 32 BLR 51 119721 I AllER 121 15.54.152
4.17.89.94.100.103 Pacific Associaies 111c v BaAler
U
Lubenhtiin F1deliiies & In\. esiiiteni (1989) 16 Con LR 9(I ,
Page Page
Sumpter v Hedges
118981 I QB 673 ......................... 2 Wells v Army & Navy Co-operative
Society (1902) 86 LT 764 .......... 80
Tan Hock Chan v Kho Teck Seng Westminster City Council v I iaivis
[1980] I MLJ 308 ....................... 12.78 & Sons Ltd
Tan Swee Hoe Co Ltd v A1i HUSsain
[1970] I All ER 943 ........ 54.95,98
BTOs [1980] 2 MLJ 16 ............... 127
Whitaker v Dunn (1886) 3
Ternloc Ltd v Errlll Properties Ltd TLR 602 ..... ............................. 3
(1987) 12 ConLR 109 83
Wimpey Construction UK Ltd v
Token Construction Co Ltd v
Scottish Special Housing
Charlton Estates Ltd Association
(1973) I BLR 48. ...................... 84 (1986) 9 ConLR 19 .................... 65
Townsends (Builders) Ltd v Cinema Woon Hoe Kan & Sons Sdn Bhd v
News & Properly Mariaoement Bandar Raya Development Bhd
Ltd
119731 I MLJ 60. ........................ 145
(1958) 20 BLR 118 27
...................
The PAM fomi is a contract for a lump sum, re the contractor under-
takes to complete the whole work for a stated and fixed amount of
money payable by the employer. This is so even thouoh it contains
provisions for the adjustment of the contract sum for such thinos as
variations (clause 11) and payments in respect of both prolongation and
disruption claims I (clause 24) : Kanchi' Roi?1017 v Goh Bi'OS Sth Bhd
[1978] I MLJ 89 where Gunn Chit Tuan I reviewed the law on this
subject comprehensiveIy.
A contract on PAM terms is an entire contract for a lump sum, but
the contractor becomes entitled to payments only on reaching the van-
ous interim stages and, so far as the retention amounts are concerned,
on completion of the Works.
An admirable summary of the law relatino to the Endlish ICT 63
contract, which is equally applicable to the PAM fomi, was provided
by, Judge John Newey QC in Holland Hoiine, I & Cubiti (Noi'tilei'n) Ltd
v Wetsh Healih Technicol Se, .vices 01.80nisot!'on ( 1980) 18 BLR 80 :
*
sti'uction PI'oressionals use EITglisli case law (and 111e s ecialisi E gl' h
textbooks) as an aid 10 boili internreiatioii and administration. ~
Tile PAM fomi itself I'efei's 10 its \, anous clauses as "c d't' " b
this is all jinpi'ecise use of legal tel'1111nolog},. Not all the Tenjis of Ih
contract are "conditions" in tile legal sense. Contractual telni
dinonallcl,
dinonally classified into conchi!b/is 'f'd' and M,"o11uiii!'CS.
erera- Tile ,
to be a third category known as 1/11/0171i'linte 1,177is : Hoi K F ' '
Slimp!', 78 Co Lid v KdM. OSakv' K!'sell Kmsho Lid 119621 2 QB 26.
A colldi'ifbii is a maioi' tentT of the contract. breach of wh'ch g' I
rise 10 a right to treat 111e conti'act as repudiated. A uru'1'0 A' '
or subsidiary tenn, breacli of whicli gives rise onI to a 'gl I d
ages and not to a right to I'escind. A sei'IOHs breacli of an
oi' 1111eiv?led^^re lei'}?I gives rise to a right to rescind, but o111erw' d
only in damages. Tile Contracts Act 1950 contains no Tov' ' d I-
ing specifically with tlie contents of a contract or the clas 'f' f
terms, but the Malaysiaii coui'is have adopted the tradit' I
law approach.
Similarly, tlTe coui'Is recognize the distinction between e. ' d
117y?fled rely?is and it is clear that the courts will jin I , te h
contract based on the presumed intention of the arties or ' d
make it coinniercially effective. Tenris may also be jin lied Ih b
of CUSIon} or ti'ads usage (see Cheiig Keiig Hong v Gol'I of' 1/1e Fedciu-
1101i of Maid}'0 119661 2 MLJ 33 for' an unsucc;ssful allem I I i. v k
trade usage ill a consti'uctioii contract context). Tel'ms in a , I ' I
implied by, statute, as under the Sale of Goods Ordinanc 1957.
in implying ternis into a \\, titlen contract, the courts w'11 \, '
Inc contract for the parties. Tern!s based o11 tlie artie '
tention will only be implied judicialIy if tiley are "necessar I o' I
transaction sucli business efficacy as the parties must hav d d":
see the leading English case ofLiixoi. (EQsibo!!!vie) Lid v Coo)e. 11941
AC 108, at 137 per Lord Wright.
The tenns to be implied into a JCT 63 contract (on which Ih PAM
fomi is based) were one of the many points allssue in the se I
decision of Vinelott J in the English case of Lolldoii Bolou h I M I'-
1011 v Simile), Hwg/I Ledc/I Lid (1985) 32 BLR 51.11 was lield Ih h
two implied ternis must be written into the contract ' d
e
workable. The implied terms were :
,
(1)
That the employer would not hinder or prevent the c I . f
carrying out its contractual obligations or from executing Ih W k ,
in a regular and orderly manner.
(2) That the employer would take all SIG s rea bl
enable the contractor to discharoe its oblioations und h
tract and to execute the Works in a reoular and ord I
it is suggested that such telms are also to be jin I' d '
. O h - Saly to give business efficac>, to the con-
.
Introduction 5
The Articles of Agreement are the fomial opening parts and recitals of
the standard form and must be fully and properly completed.
The recitals (which begin "whereas") are introductory to the opera-
tive clauses. Since they are not within the operative part of the docu-
merit they cannot generally be used as an aid to the interpretation of the
operative part. However, if the operative clauses are ambiguous, the
recitals may be looked at to see if they assist in detennining the true
construction of the contract because they introduce what the parties are
intendino to achieve by their contract.
in this standard fomi of contract the recitals may in fact be of the
very greatest importance, particularly as regards the description of the
Works" which the contractor is to carry out and as to the site ' since
it is only here that there is any provision for such descriptions.
The recitals include a brief description of the Works to be constructed
and indicate the documents which are to be included as the contract
documents. it is conceivable that the description of the Works in the
Articles of Agreement might, by a side wind as it were, be used to
impose some measure of design liability on the contractor, eg where a
"Project Description" containing a design element or performance speci-
tication is expressly incorporated into the Articles of Agreement. In
that event it is thought that clause 12(I), below, would not be effective
to exclude its incorporation into the contract.
The recitals also state that the employer has caused drawings and
bills of quantities "showing and describing the work to be done to be
prepared by or under the direction of" his named architect. They also
state that a fully priced copy of the bills has been supplied by the
contractor to the employer. Throughout the contract, this copy is called
"the Contract Billsl'. By clause 3(2)(c) the contractor is entitled to ask
for a copy of the Contract Bills.
This recital recognizes the standard procedure of examiintig the suc-
cessful tenderer's priced bills and this means that when the Articles of
Agreement are executed an employer (or his architect or quantity sur-
veyor) will have the priced bills in his possession. The consideration of
the priced bills of all tenderers is an important part of the investigation
process as to whether or not the employer should be recoilrrnended by
his professional advisers to contract with a particular contractor since
the priced bills enable the employer's quantity surveyor to deterrnine
whether it is likely that the proposed contractor has put in an economi-
cally viable tender.
Tenderers must exercise considerable skill in pricing the bills and it
often happens that an employer finds the lowest tender price beyond
his available means, although he is amious to go ahead with the pro-
ject. in that event, a reduction of the work done has to be negotiated
and this results in what is called a bill of reductions.
Tenderers often operate on the basis that in pricing the bills they
seek to identify the items which may be omitted and to put a lower
price against that item. The difference between the net cost to the
8 Tile @111'c/es of @81'ee"rel?I
contractor of such an item and the price put into the ri d b'11 '
transferred to and built into other rates. IdealI , fr h '
point of view, enhanced rates are entered for item h' h h
believes the quantities are likely to be increased a th
gresses. The English courts have held that there ' h'
this practice. '
in Convent Hospttql Lid v Ebe, .jin & Pilli. s (1988) 14 C LR ,
appeal (1990) 7-CLD-05-11) contractors or a suic'd H I '
against a bill item requiring a performance bond, b t h o
held that this was not improper conduct on thej e
"The representation they were making were in no f I
took the risk that financial loss would result t Ih f
priced below cost and the item was not omitted. P f
quired of the contractors was that the enhanced f
should not be too easily identified and challen ed". Th'
at issue in the Court of Appeal and the learned 'ud '
edly express the true position.
The drawings on which the contractor has tend d "
Contract Drawings" throughout the contract. B clause 4(2 b h
tractor is entitled to receive two copies of the Co I D
Both the Contract Bills and the Contract Dr ,' 0 ' '
by or on behalf of the 61nployer and the contract . I '
desirable that tlie quantity surveyor. should also sig th C ' '-
ings as evidence that tiley were the drawinos
Weretakenoff. 6 from
q wh' hh'
iies
Article I
Article 2
MLJ 312; 81/11ding & Estates Ltd v AM Connoi' [1958] MLJ 174; Sa-
phiotooiz v Liin SI^w H" [1963] MLJ 305; yong Mok Hih v United
Malay States Sugai. Indusn. I'es Lid 119671 2 MLJ 10.
Article 3
This requires the name and address of the architect to be inserted. The
person named must be an architect registered under the Architects Act
1967 : see GIInwng Boy!, Sdit Bhd v Syai'ikot Pemhinaan Pel'I^^ Sdn
Bhd 119871 2 MLJ 332 for discussion of the question whether a gradu-
ate architect who has not registered is entitled to sign certificates under
the contract. it is clearly permissible for the name of an architectural
practice to be inserted, and this is commonly done, although this may
cause evidential. difficulties if disputes arise in which the architect's
opinion is called into question.
The article goes on to provide that, in the event of the named
architect's death or his ceasino to act, the architect shall mean such
other person as the employer nominates. it is submitted that the Gin-
ployer is bound to nominate a successor within a reasonable time of the
death or cessation to act, as was held by the English Court of Appeal
in C"ouchce Ltd v London 80ro"gh of Lambeth (1986) 6 ConLR 70.
The functions of the architect are essential to the operation of the
contract and an employer's failure to nominate a successor would be a
breach of an implied terni of the contract, and breach would entitle the
contractor to damages in respect of any proven resultant loss.
The contractor has a right to object to the subsequent nominee for
reasons thought to be sufficient by an arbitrator appointed in accor-
dance with clause 34. The successor architect is not entitled to dis-
regard or overrule any certificate, opimon, approval or instruction given
by his predecessor.
Until recently, the view widely held by construction lawyers in Coin-
monwealth jurisdictions was that the architect owed duties in tort to the
contractor parallel to those remedies available to the contractor against
the employer under the contract, with the practical result that if the
architect negligently or unfairly under-certified, the contractor not only
had the right to have the certificate reviewed in arbitration, but might
also recover damages for economic loss against the architect, at least in
so far as he failed to recover from the employer.
The English Court of Appeal apparently put paid to that view by its
decision in Pacific Associates Inc v BCxter (1989) 16 ConLR 90, which
concerned a contract based on the F101C fonn and which contained a
number of clauses not usually found in construction contracts. The
clauses included an express disclaimer of liability extending to the
negligence and default of the engineer.
Subsequent to that decision, in Leon Engineering & Construction Co
Lid v Kg D"k Investment Co Ltd [1989] TCLR 465, the High Court of
Hong Kong considered the potential liability of an architect under a
I O Tile @1ncles of ag, 'eel?leii!
building contract in tenns similar to the PAM form and reached a like
conclusion. After careful consideration of the authorities, Bokhary I
stated the principle in this way :
Where, first, there is adequate machinery under the contract between the
employer and a contractor to enforce the contractor's rinhts thereunder and,
secondly, there is no good reason at tender stage to suppose that such ri hts
and machinery would not tooether provide the contractor with an ade uate
remedy, then in general, a certify ino architect . . . does not owe the contractor
a duty in tort coterminous with the obligation in contract owed to the
contractor by the employer.
it is believed that the Malaysian courts will ado t the same a roa h
which is part of the trend to relieve professionals from nabilit to ames
with whom they are not in a direct contractual relationshi .
Nonetheless, it is important to appreciate that the architect must act
impartialIy in performing many of his duties under the contract, and in
particular those relating to certification of sums due, the rantin of
extensions of time, and the ascertainment of loss and/or expense. As
architect he should never allow the employer jin ro erl to innuen
his decisions nor should the employer prevent the inde endent exercise
of the architect's powers as certifier: Hickmo, I & Co v Robei. ts 1/9/31
AC 229. in such a case the need for a certificate in a , be d' d
with, and the contractor could recover sums due in its absence b w
of an action for daniages. Improper conduct of this sort renders the.
architect's acts invalid : see Engiesh@in v Mt. Masie, . 119201 All ER
RepJ74. ' ~
indeed, it has been recently held in England that the architect '
entitled to detennine his engagement if the emplo 'er interferes with h'
granting or prevents him from granting extensions of time : A1' 7'0 o1, -
ms & Papp@ v Chain Coinpoizio Noviei. a SA (1990) 7-CLD-05-01.
Article 4
Contractor's obligations
(1) The Contractor shall upon and subject to these Conditions carry
out and complete the Works shown upon the Contract Drawings and
described by or referred to in the Contract Bills and in these Conditions
in every respect to reasonable satisfaction of the Architect.
^~.
2
(1) The Contractor shall (subject to sub-clauses (2) and (3) of th'
Condition) forthwith comply with all instructions issued to him b th
Architect in regard to any matter in respect of which the A h'
expressly empowered by these Conditions to issue instructions. If 'Ih'
seven days after receipt of a wrttten notice from the Architect '
compliance with an instruction the Contractor does not coin I th
with, then the Employer may employ and pay other ersons to
any work whatsoever which may be necessary to give effect to such
instruction and all costs incurred in connection with such I
shall be recoverable from the Contractor by the Em 10 er as d b
may be deducted by him from any monies due or to become d I h
Contractor under this Contract.
(b) That if neither the Contractor nor the Architect shall confinn such
an oral instruction in the manner and at the time aforesaid but the
Contractor shall nevertheless comply with the same, then the
Architect may confirm the same in writing at any time prior to the
issue of the Final Certificate, and the said instruction shall there-
upon be deemed to have taken effect on the date on which it was
issued.
(4) The Contractor shall upon signing this Contract notify the Archi-
Iect in writing of an address whereat notices and Architect's instruc-
lions under this Contract may be served upon him. in the event of the
Contractor failing to notify the Architect of such an address or failing
to notify the Architect of any chanoe in such address, notices and
Architect's instructions shall be deemed served upon the Contractor if
sent by registered post to his address stated in this Contract, or if left at
his office on the site and a receipt is obtained from the Contractor's
foreman-in-charge.
I(2) Discrepancies
4(I) Statutory obligations
5 Setting-out
6(3) Opening up and testing
6(4) Removal of defective work
6(5) Dismissal of persons employed on Works
11(I) Variations
11(3) Expenditure of PC Sums, &c
15(3) Defects during defects liability period
201Cl(c)(ii) Damage by fire, &c
21(2) Postponement of work
27(a)(b) PC Sums for nominated sub-contractors
28 PC Sums for nominated suppliers
31(2) Protective work duting hostilities
32(I)(b) War damage
. ..
, ,
I44 I, ,, *,,
41
..
-
11. .::
\.: \\
\\ \
1:1*
^ A1'cmtec!'s 1'11sr!Tieri'o113 21
... ,
,.'. *
^ .
Oral instructions have no immediate effect and must be confirmed in
writino. Oral instructions must be confirmed by the contractor in writ-
Ina to the architect within seven days of receipt and if within a further
.
seven days from receipt of the contractor's notice the architect has not
dissented in writing, the instruction takes effect from the date on which
\
the architect receives the contractor's notice. If the contractor madver-
tently fails to confirm the Instruction but nevertheless complies with it
\
he will be at risk since the architect only rimy subsequently confinm it.
in theory, a contractor should not carry out an oral instruction from
the architect but should wait until it is reduced to writino. in practice,
this is unrealistic because oral instructions are often Diven in an Giner-
gency. The sub-clause deals with this situation inadequately. Sinctly, if
the architect issues an oral instruction in an emergency situation, it is
"of no immediate effect" and the complex provisions of the clause should
be observed.
However, there is no requirement that the instruction be in a specific
to mm; it is merely to be "in writino". The practical solution is therefore
for the architect to write the instruction in the contractor's site record
book immediately and thus comply with the provisions of clause 2(3).
The provisos are important. Proviso (0) says that where within seven
days of issuing an oral instruction the architect issues a written confir-
mation, the oral instruction is valid and effective from the date of con-
finnation. The contractor is then relieved of his obiioation to confinn
the instruction in writing. The original oral instruction is therefore
validated retrospective Iy only to a limited extent.
PI'oviso (b) allows for the retrospective confirmation of oral instruc-
tions, but does not appear to deal adequately with the situation where
the contractor has already acted upon an oral instruction without going
through the confinnation procedure. If neither the contractor nor the
architect collfinms the oral instruction in writing, but the contractor acts
upon it, then the architect may (not must) confinn it in writing at any
time up to the issue of the final certificate. If the architect does this, the
Instruction is validated retrospectiveIy to the date of its issue. The op-
eration of this cumbersome procedure causes considerable difficulties
In practice.
Clause 2(4) is an interesting and necessary provision requiring the
contractor to notify the architect in writing of his address for service of
any notices or receipt of any instructions under the contract. He must
do this "upon signing the contract" 16 when executing the fonnal contract
documents. Should the contractor fail to so notify the architect (or to
infonn him of any subsequent change in such address) notices and
architect's instructions are deemed to have been validly served if sent
by registered post to the address stated in the testimonium "or if left at
his office on site and a receipt is obtained from" the foreman-in-charge
whom, under the ternis of clause 8, the contractor must "constantl
keep upon the Works". This is an eminently sensible provision not found
in the parent un fomi.
Flowchart I illustrates the operation of clause 2.
22 Clot, se 2
Flowchart I
Architect's instructions (clause 2)
START
A1 No
Empowered
in writing by, conditions
No Yes
if contractor complies,
architect may confirm Contractor
at any lime up 10 final complies
certificate 2(3)(b)
I\;o
Architect No
dissents
Yes
STOP
Clause 3
Contract documents
( I) The Contract Drawings and the Contract Bills shall remain in the
custody of the Architect or of the Quantity Surveyor so as to be avail-
able at all reasonable times for the inspection of the Employer or of the
Contractor.
(2) Immediately after the execution of this Contract the Architect with-
out charge to the Contractor shall furnish him (unless he shall have
been previously furnished) with:
(a) one copy certified on behalf of the Employer of the Articles of
Agreement and of these Conditions,
(b) two copies of the Contract Drawings, and
(c) two copies of the unpriced Bills of Quantities, and (if requested
by the Contractor) one copy of the Contract Bills.
(3) So soon as is possible after the execution of this Contract the Archi-
tect without charge to the Contractor shall furnish him (unless he shall
have been previously furnished) with two copies of the specification,
descriptive schedules or other like document necessary for use in
carrying out the Works. Provided that nothing contained in the said
specification, descriptive schedules or other documents shall impose any
obligation beyond those imposed by the Contract documents, namely,
by the Contract Drawings, the Contract Bills, the Articles of Agreement
and these Conditions.
(4) As and when from time to time may be necessary the Architect
without charge to the Contractor shall funtish him with two copies of
such drawings or details as are reasonably necessary either to explain
and amplify the Contract Drawings or to enable the Contractor to carry
out and complete the Works in accordance with these Conditions.
(5) The Contractor shall keep one copy of the Contract Drawings, one
copy of the unpriced Bills of Quantities, one copy of the specification,
descriptive schedules or other like document referred to in sub-clause
(3) of this Condition, and one copy of the drawings and details referred
to in sub-clause (4) of this Condition upon the Works so as to be
available to the Architect or his representative at an reasonable times.
(6) Upon final payment under clause 30(6) of these Conditions the
Contractor shall if so requested by the Architect, forthwith return to the
Architect all drawings, detads, specifications, descriptive schedules and
other documents of a like nature which bear his name.
24 Clawse 3
., <3ky4, ^, ", ,
Clause 3(I) deals with the 4145/9d of Ih C D ,
Contract Bills referred to in the recitals to the Articles of Agreeme I.
These are to remain in the custody of~The architect or the uantit sur-
veyor, but must be available for inspection by either the Gin 10 ,er or
the contractor at any reasonable time, Ie_ dunno normal office hours,
By clot, se 3(2) 1177medraieb, after the '6\^^till6fi';)f the contract, Ih
contractor must be given, without charge, a certified co of the
^:L^^Q^!!. t and the Conditions, two co ies of the Contract
Drawin s, and two co ies of the un riced Bills. The contractor in a
also ask for a co of the Contract ills.
Clawse 36) obliges the architect to provide the contractor - unless
he has previously done so - "as soon as possible after the execution of
this contract" with two copies of the specification (Which is not a contract
document) and of the "descriptive schedules or other like document
necessary for Lise in carr}, ing out 111e Works". This is again to be done
without cliarge. 11 is subniitted that 11ns obligation would be met b , 11
provision of an 3130.91^,!g, d Bill. The reference to the specification is
curious because the Bills contain the only IGOally bindin s ecification
of the work, to the detailed description of the methods and ual't f
work and materials : see clause 6.
indeed, this is emphasized by the proviso to the sub-clause wh' h
sa s that :
4 (1) The Contractor shall comply with and give all notices required by
any written law applicable to the territory or territories of Malaysia in
which the works are to be carried out, any instrument, rule or order
made under any written law applicable to the territory or territories of
Malaysia in which the works are to be carried out, or any redulation or
byelaw of ally local authority or of any statutory undertaker which has
any jurisdiction with regard to the Works or with whose systems the
same are or will be connected. The Contractor before making any
variation from the Contract Drawings or the Contract Bills necessitated
by such compliance shall give to the Architect a winten notice specify-
ing and giving the reason for such variation and the Architect may issue
instructions in regard thereto. If within seven days of having given the
said \\, mien notice the Contractor does not receive any instructions in
regard to the matters therein specified, he shall proceed with the work
confonning to the written law applicable 10 the territory or territories of
Malaysia in which the works are to be carried out, instrument, rule,
order, regulation or byelaw in question and any variation thereby neces-
sitated shall be deemed to be a variation required by the Architect.
(2) The Contractor shall pay and indemnify the Employer against Iia-
bility in respect of any fees or charges (including any rates of taxes)
legally demandable under any written law applicable to the territory or
territories of Malaysia in which the works are to be carried out, any in-
strument, rule or order made under any written law applicable to the
territory or territories of Malaysia in which the works are to be carried
out, or any regulation or byelaw of any local authotity or of any SIatu-
tory undertaker in respect of the Works. Provided that the amount of
any such fees or charges (including any rates or taxes) shall be added
to the Contract Sum unless they
(a) arise in respect of works executed or materials or goods supplied
by a local authority or statutory undertaker for which a prime cost
sum is included in the Contract Bills or for which a prime cost
sum has arisen as a result of Architect's instructions oiven under
clause 11(3) of these Conditions, or
(b) are priced or stated by way of a provisional sum in the Contract
Bills.
*.,,,,**.""" "" "' "
I. *\;; . I ..:...;:'-
~,,,,,,
***. . ., .,._ * ,
-,. -: ...,.
,
\
-........
... .
\
\ , Skilli!OJT ob!!^allo, is. norices. fees and CAOiges 27
..... \
, ,
*
Clause 4(I) is a short but important provision which is sometimes
... ..
:....
:,
* misunderstood. At one time it was suggested that the contractor's obli-
:
,,
**,...^. ;'*
-
galion was restricted to complying with or giving statutory notices. De-
o.
*~**;;* spite the punctuation of the first sentence. it is clear that the contractor
**^"
I
is bound to comply with any applicable written law, to statutory provi-
** . *-'. '*
sions, in the territories of Malaysia where the works are belno carried
out. This written law includes delegated legislation such as building by-
\.,
\
laws. indeed the contractor's obligation to so comply is made plain by
\
the final sentence. Even if that statement were not present, the position
*
* ,
would be the same, and the matter was considered by the English Court
of Appeal in Townsends (Builders) Lid v Cinema News & PI. opei'Iy
\
Managemeni Ltd (1958) 20 BLR 118.1n that case Lord Evershed MR,
while critical of the draftsmanship of the equivalent English provision,
had no difficulty in discernino that the contractor was under an oblioa-
lion to comply with the by-laws, etc as well as to o1ve any required
notices-.
5 The Architect shall dererrnine any levels which may be required for the
execution of the Works, and shall furnish to the Contractor by way of
accurately dimensioned drawinos such infomiation as shall enable the
Contractor to set out the Works at ground level. Unless the Architect
shall otherwise, instruct, in which case the contract sum shall be ad-
justed accordingly, the Contractor shall be responsible for and shall
entirely at his own cost amend any errors arising from his own in-
accurate setting out.
The architect has two duties under this clause. First, he must detennine
any levels required for the execution of the Works. Second, he must
provide the contractor with accurately dimensioned drawings to enable
him to set the Works out at ground level.
All setting-out above ground level is a matter for the contractor, but
he may need to be provided by the architect with working drawings to
enable him to set out where the contract drawings are insufficiently
detailed. The contractor is, of course, responsible for any maccurate
setting-out due to his own fault and must amend any errors resulting
from his maccurate setting-out at his ouni cost "unless the architect
shall otherwise instruct, in which case the Contract Sum shall be ad-
justed accordingly". On one reading of this provision, it would appear
that the architect is empowered to add the costs of erroneous setting-
out to the Contract Sum so that the employer would have to pay for the
contractor's error. On any purposive interpretation of the clause this
camot be the case. it is thought that the only sensible interpretation of
this ineptly-worded provision is that if the work can be accepted by the
employer as incorrectly set-out, then the Contract Sum may be red"ced
to take account of the error.
Clause 6
(5) The Architect may (but not unreasonably or vexatiously) issue in-
sumctions requiting the dismissal from the Works of any person em-
ployed thereon.
it is submitted that this must bear a narrow meaning and the clause is
in need of amendment, for example, by providing expressly for the re-
execution of any defective work and extending the architect's powers
to deal effectiveIy with defective work during the progress of the Works
: see clause 15(2) as to the contractor's liability for defects during the
defects liability period.
As presently worded the architect's power under clause 6(4) is Iim-
ited to ordering removal of the offending work, materials or goods, and
he camot merely condemn it without ordentig removal. This was so
held by an English judge of great experience in construction law in
Holland Hannen & CMb^^t (Northern) Ltd v We!sh Health Technical
32 Clawse 6
7 All royalties or other sums payable in respect of the supply and use in
carrying out the Works as described by or referred to in the Contract
Bills of any patented articles, processes or inventions shall be deemed
to have been included in the Contract Sum, and the Contractor shall in-
demnify the Employer from and against all claims. proceedings, dam-
ages, costs and expenses which may be brought or made against the
Employer or to which he may be put by reason of the Contractor in-
fringing or being held to have infringed any patent rights in relation to
any such articles, processes and inventions. Provided that where in
compliance with Architect's instructions the Contractor shall supply and
use in carrying out the Works any patented articles, processes or inven-
tions, the Contractor shall not be liable in respect of any infringement
or alleged infringement . of any patent rights in relation to any such
articles, processes and inventions and all royalties damages or other
monies which the Contractor may be liable to pay to the persons en-
titled to such patent rights shall be added to the Contract Sum.
The principle of this clause is that if royalties or other sums are pay-
able for any patented articles, processes or inventions used in carrying
out the Works as described in the Contract Bills, these are the
contractor's responsibility. This responsibility extends to any proceed-
ings arising out of breach of patent rights, and the contractor gives the
employer an indemnity against any such liability.
However, the contractor is relieved of liability if he supplies and
uses patented articles, processes, or inventions "in compliance with
architect's instructions". in that case, the responsibility is that of the
employer and the Contract Sum is to be adjusted accordingly. it must
be said that the wording of the proviso is inept and obscure, but pre-
sumably the architect's instructions referred to must mean instructions
to supply or use patented articles, etc which the contractor would not
otherwise have used.
Clause 8
The Contractor shall constantly keep upon the Works a competent fore-
man-in-charge who shall be capable of receivino verbal instructions in
Malay or English and any instructions diven to him by the Architect
shall be deemed to have been issued to the Contractor.
... 44 I Clause 9
*." ~ '.
..
....
.*
***
***
*, Access for architect to the works
' '..*
**
** ,
^^9
I;
*
**
9 The Architect and his representatives shall at all reasonable times have
**
* *,
access to the Works and to the workshops or other places of the Con-
44
, tractor where work is being prepared for the Contract. and when work
,
is to be so prepared in workshops or other places of a sub-contractor
(whether or not a nominated sub-contractor as defined in clause 27 of
,.',; these Conditions) the Contractor shall by a tenn in the sub-contract so
{
*
far as possible secure a similar right of access to those workshops or
places for the Architect and his representatives and shall do all things
reasonably necessary to make such right effective.
This provision confers express power on the architect and his represen-
tatives to have access to the Works, and to the workshops or other
places of the contractor where work is being prepared in compliance
with the contract. The right of access is one "at all reasonable times",
which must mean during working hours'
Where, as is usually the case, work is to be prepared in the premises
of a sub-contractor, the contractor undertakes "so far as possible" to
ensure a similar right of access to those premises by means of a terni
in the sub-contract. He also undertakes to "do all things reasonably
necessary to make such right effective". This seems to be purely pre-
catory. However, it is important that this provision should be stepped-
down in any sub-contract. in the case of nominated sub-contracts, clause
27(a)(Ix) provides that it shall be a term of the sub-contract that the
architect and his representatives be allowed necessary access to the
nominated sub-contractor's premises.
35
Clause I O
Clerk or s
The two sentences of 111is clause niight in o1'e conveniently have been
divided into sub-clauses as they deal with diffei'ent aspects of tlie same
subject, whicli is largely important in practice. in tile narui'e of thinos,
the architect \, is its the site only periodically. in contracts of any, in ao-
nitude it is necessaiy for the employ, a' to have a full-time represent-
ative on site to assist the architect in his duties of supervising of the
work and in particular to ensure compliance with the contract provi-
sions with regard to standards of materials and workmanship.
The first sentence Ginpowers the employer to appoint a clerk of works
and clearly labels him an illspecioi', to someone who examines closely
the contract Works as they proceed, His authority is very limited; he is
to act solely as an inspector" and can originate nothino. The contrac-
tor is bound to afford the clerk of works "every reasonable facility" for
the performance of his duties.
The clerk of works is employed and paid by the employer even though
in some cases he will have been recommended by the architect. There
is English case law authority which says that where an employer
appoiiits a clerk of works, the employer is vicariously responsible for
any negligence by him in the perfomiance of his duties. in appropriate
cases this could reduce the negiioent architect's financial liability to
the employer, eg where the arcliitect has been Guilty of neonoent
supervision.
The case in question is Kensii?gioii & Che/sea & WeSIminsiei' A, 'e@
Heo11h Awn?o1'1'ty v Wetiei7? Con?pornes Lid (1984) I ConLR 114, where
Cle, 'k of ", 0"As 37
(2) The term "variation" as used in these Conditions means the altera-
tion or modification of the design, quality or quantity of the Works as
shown upon the Contract Drawings and described by or referred to in
the Contract Bills, and includes the addition, omission or substitution of
any \\, ork, the alteration of the kind or standard of ally of the niaterials
or goods to be used in the Works, and the reinoval from the site of any
work Inaterials or goods executed or brought thereon by, the Contractor
for the purposes of the works oilier than work materials or goods which
are not in accordance with 111is Contract.
(c) Where work cannot properly be measured and valued the Con-
tractor shall be allowed day-work-rates on the prices prevailing
when such work is carried out (unless otherwise provided in the
Contract Bills):
(i) at the rates, if any, inserted by the Contractor in the Contract
Bills or in the Form of Tender; or
(ii) when no such rates have been inserted, at the actual prime
cost to the Contractor of his material, transport and labour for
the work concerned, plus fifteen per cent, which percentage
shall include for the use of all ordinary plant, tools and scaf-
folding, and for supervision, overheads and profit;
Provided that in either case vouchers specifying the time daily
spent upon the work (and if required by the Architect the
workmen's names) and the materials employed shall be delivered
for verification to the Architect or his authorised representative
not later than the end of the week following that in which the
work has been executed;
(d) The prices in the Contract Bills shall detennine the valuation of
items omitted; provided that if omissions substantially vary the
conditions under which any remaining items of work are carried
out the prices for such remaining items shall be valued under rule
(b) of this sub-clause.
(5) Effect shall be given to the measurement and valuation of vari-
ajions under sub-clause (4) of this Condition in Interim Certificates and
by adjustment of the Contract Sum; and effect shall be given to the
measurement and valuation of work for which a provisional sum is
included in the Contract Bills under the said sub-clause in Interim
Certificate and by adjustment of the Contract Sum in accordance with
clause 30(5)(c) of these Conditions.
(6) If upon written application being made to him by the Contractor,
the Architect is of the opinion that a variation or the execution by the
Contractor of work for which a provisional sum is included in the
Contract Bills (other than work for which a tender made under clause
27 (g) of these Conditions has been accepted) has involved the Con-
tractor in direct loss and/or expense for which he would not be reim-
bursed by payment in respect of a valuation made in accordance wit
the rules contained in sub-clause (4) of this Condition and if the said
application is made within a reasonable time of the loss or expense
having being incurred, then the Architect shall either himself ascertain
or shall instruct the Quantity Surveyor to ascertain the amount of such
loss or expense. Ally amount from time to time so ascertained shall e
added to the Contract Sum, and if an Interim Certificate is issued after
the date of ascentirunent any such amount shall be added to the amount
which would otherwise be stated as due in such Certificate.
Clause 11(3) requires the architect to issue instructions for the ex-
penditure of any prime cost (PC) and provisional sums included in the
Contract Bills and of prime cost sums which arise as a result of ' t
lions for the expenditure of provisional sums. 11 seems clear froni the
use of the word "shall" (and the use of the same word in clause 27(a)(b))
that the architect is bound to issue instructions on the ex enditu f
PC sums. to to exercise the power to nominate s ecialists. Indeed,
will be seen, if a first nomination fails before the work done und
PC sum instruction is completed, there is a duty on the Gin 10 er
(through the architect) to nominate another sub-contractor to succeed
the first : TA Bickeito, I & Co Ltd v Noi. th-WeSI Men. 0 o17 H I
Boor. d 119701 I All ER 1039 HL. The effect of nomination b wa of
a PC sum instruction is considered under clauses 27 and 28.
Not unexpectedly, the contract contains no definition of eith
prime cost or provisional sums, and definitions based on SMM in a be
useful ,
(1) A provisional sum is one provided for work or for costs which
cannot be entirely foreseen, defined or detailed at the time th
tendering documents are issued.
(2) A prime cost sum is one provided for work or services to be
executed by a nominated sub-contractor, a statuto authority o
public undertaking or for materials or o00ds to be obtained f
a nominated supplier.
Provisional sums can only be \, andly expended aoainst instructions d
clause I I(3). Such instructions may, for example, give some of the wor'
to the contractor and the remainder to a specialist sub-cont a I
instruct that some goods are to be obtained from a su lier nominat d
by the architect.
The contractor's work ordered under such an instruction falls I b
valued under clause I I (4) and clause I I (6) (if appropriate), while that
of the nominees will be dealt with under the relevant sub-c t
supply contract. The possibility that the expenditure of Tovisio I
may involve a nomination and therefore the substitution of a PC
for all or part of the provisional sum is covered b the last h
clause 11(3).
Clause 11(4) provides for the measurement and valuation of:
(1) variations as defined in clause 11(2);
(2) any contractor's work ordered by the architect when is sum 'n-
SITUctions on the expenditure of provisional sums.
The rules for valuation are only applicable to these two ite , d h
rules apply ""litess otheit-I, ise agi'eed" between the e I d h
contractor. it is sometimes SUGgested that the words " I h
agreed" in clause 11(4) mean "agreed by or with the uantit surve "
but this view was decisively rejected b the E o1' h H' h C
Vari'orlons. pro\. is Ibna/ and prime cosr sums 43
John Laing Construction Ltd v County and District Properties Ltd (1982)
23 BLR 10 for reasons which are entirely convincing. The words mean
"agreed between the contracting parties" although of course the em-
ployer may give the quantity surveyor express authority to make such
an agreement.
The role of the quantity surveyor under a contract identical in tenns
10 the PAM fomi was fully considered in the Laing case. it was held
that his "function and authority under the contract are confined to
measuring and quantifying. The contract gives him authotity, at least in
certain Instances, to decide quantum . . . it does not in any instance
give him authority to detennine any liability, or liability to make any
payment or allowance . . .".
There are, in fact, few express references to the quantity surveyor in
the contract. He is identified in Article 4 of the Articles of Agreement;
by clause I I (6) he is given the express duty of measuring and valuing
variations; by clause I I (6) he is given the duty of ascertaining loss and
expense involved in a variation if so instructed by the architect; by
clause 24(I) he is given a sintilar duty in respect of loss or expense
caused by disturbance of regular progress of the Works.
The quantity surveyor's position appears to be as stated by Lord Rad-
cliffe in the well-known English case of RB Burden Ltd v Swanse@
Corporati'on 119571 3 All ER 243, HL, where he said :
Generally speaking, I regard the quantity surveyor as the person charged
with the duty of valuing the contractor's work and advising the architect
as to the allowance of his claims for payment. But I do not see anything
in the contract which suggests that the architect is bound to accept the
quantity surveyor's opinions or valuations when he exercises his own
function of certifying sums for payment. At that point the architect
remains master in his own field.
Contract bills
12 (1) The quality and quantity of the work included in the Contract Sum
shall be deemed to be that which is set out in the Contract Bills which
Bills unless otherwise expressly stated in respect of any specified item
or items shall be deemed to have been prepared in accordance with the
principles of the Standard Method of Measurement of Building Works
last before issued by the Federation of Malaya and Singapore Branches
of the Royal Institution of Chartered Surveyors but save as aforesaid
nothing contained in the Contract Bills shall override, modify, or affect
in any way whatsoever the application or interpretation of that which is
contained in these Conditions.
Clause 12 defines the work for which the Contract Sum is payable and
also provides for the correction of errors in items (not prices) in the
Contract Bills.
Clause 12(I) makes clear that the quality and quantity of work for
which the Contract Sum is payable is that given in the Contract Bills.
Unless otherwise expressly stated in respect of any specified item or
items, the Contract Bills are deemed to have been prepared "in accor-
dance with the principles" of the Standard Method of Measurement
referred to ("SMM").
The reference to the Contract Bills having been prepared "in accor-
dance with the principles" of the SMM is ambiguous and obscure and
it would have been better by far to have stated that the Contract Bills
are deemed to have been prepared in accordance with the current edi-
tion of the SMM. it is suggested that the only sensible way to interpret
this ambiguous phrase is that it should be read in this way and, while
the SMM provides a unifonn basis for me asuting building works and
embodies the essentials of good practice, it is clear that more detailed
infonnation than is required by Sunl must be given where necessary
in order to define the precise nature and extent of the required work.
This opens up a wide area of potential contractor's claims.
it the Bills are drawn up in any way other than "in accordance with
the principles" of the SMM, the contractor must be infomied. it he is
not so infonned it is thought that the contractor is entitled to assume
48 C/diffe 12
that 1116 Contract Bills are drawn up in accoi'dance with the relevant
SMM.
,
..
I*
*
It
,
Clause 13
Contract sum
13 The Contract Sum shall not be adjusted or altered in any way whatso-
ever otherwise than in accordance with the express provisions of these
Conditions, and subject to clause 12(2) of these Conditions any error
whether of arithmetic or not in the computation of the Contract Sum
shall be deemed to have been accepted by the parties bereto.
14
Unfixed materials and goods intended for, delivered to, and laced on
or adjacent to the Works shall not be removed except for use upon the
Works unless the Architect has consented in writing to such removal
which consent shall not be unreasonably withheld. Where the value of
any such materials or goods has in accordance with clause 30(2) of
these Conditions been included in any interim Certificate under which
the Contractor has received payment, sucii materials and goods shall
become the property of the Employer, but subject to clause 20[B] or
clause 201Cl of these Conditions (if applicable), the Contractor shall
remain responsible for loss or damage to the same.
Cmuse 14 is a vesting clause and deals with 111!fixed materials and goods
intended to be fixed into the works. Under the general law, once the
are built into the works they become the property of the emplo^;CT. in
the absence of r v' ' , ""
the absence of provision to the contrary, the contractor's own;goods
and materials which he brings on site remain his properI until the
are built into the works : see the decision of the House of L6;as in
Reynolds v Ashby [1904] AC 406.
Considerable problems arise in the construction industry in eneral
and under the PAM form in particular because of the revalence of
retention of title clauses in the contracts of merchants and suppliers.
Many supply contracts contain a clause whereby the seller retains title
in the goods until he has been paid for them.
The right to retain title is recognized by section 25(I) of the Sale of
Goods Ordinance 1957 which provides :
Where there is a contract for the sale of specific goods or where goods
are subsequently appropriated to the contract the seller may by the ternis
of the contract or appropriation reserve the right of disposal of the goods
until certain conditions are fulfilled. in such case, notwithstanding the
delivery of the goods to the buyer . . . the property in the goods does
not pass to the buyer until the conditions imposed by the seller are
fulfilled.
**
>,
* Clause 15
,
*
I
Practical completion and
I
defects liability
,\
*
*
A
15 (1) When in the opinion of the Architect the Works are practically
. ,....
completed, he shall forthwith issue a certificate to that effect and Prac-
^*,
\*
tical Completion of the Works shall be deemed for all the purposes of
this Contract to have taken place on the day named in such certificate
*;. 11 *
;;*, (2) Ally defects, shankages or other faults which shall appear within
$ . .... : . the Defects Liability Period stated in the appendix to these Conditions
*\-'-'
*;*\ ' I, and which are due to materials or workmanship not in accordance with
*- - - this Contract shall be specified by the Architect in a Schedule of De-
*-
*-- , rects which he shall deliver to the Contractor not later than 14 days
*----
I
- after the expiration of the said Defects Liability Period, and within a
44.1' '
****' reasonable time after receipt of such Schedule the defects, shrinkages
4$*- ' and other faults therein specified shall be made good by the Contractor
*;.. and (unless the Architect shall otherwise instruct, in which case the
Contract Sum shall be adjusted accordingly) entirely at his own cost.
$1':::.
;;;, (3) Notwithstanding sub-clause (2) of this Condition the Architect may
I;*; whenever he considers it necessary so to do, issue instructions requiring
J, ,... any defect, shrinkage or other fault which shall appear within the Defects
{;^,"
\** Liability Period named in the appendix to these Conditions and which
is due to materials or workmanship not in accordance with this Contract
I\ --
to be made good, and the Contractor shall within a reasonable time
after receipt of such instructions comply with the same and (unless the
Architect shall otherwise instruct, in which case the Contract Sum shall
be adjusted accordingly) entirely at his own cost. Provided that no such
instructions shall be issued after delivery of a Schedule of Defects or
** .-
*;:: -" after 14 days from the expiration of the said Defects Liability Period.
**** '
(4) When in the opinion of the Architect any defects, sharkages or
4'<: * other faults which he may have required to be made Good under sub-
,*^ ..
clauses (2) and (3) of this Condition shall have been made good he
shall issue a certificate to that effect, and completion of making o00d
defects shall be deemed for all the purposes of this Contract to have
taken place on the day named in such certificate.
*. .:.
I'.
I\,,
Clause 15(I) provides that "when in the opinion of the architect the
\
*** *. Works are practically completed, he shall forthwith issue a certificate
* *** to that effect and practical completion of the Works shall be deemed
.- for all the purposes of this contract to have taken place on the day
named in such certificate".
*
. .-
**
**
53
<1,
.;:- .
54 Clanse 15
Sectional completion
. . . shall issue a ceitificaie stating his estimate o1' the approximate total
value of the said part. and for all the purposes of this Condition (but 110
other) the value so stated shall be deemed to be the total value of the said
part.
Assignment or sub-letting
17
(1) The Contractor shall not assign this contract or any part thereof or
the obligation to carry out and the right to receive payment for any art
of the Works to be carried out under this contract or the ri ht to receive
the whole or any part of the Contract Sum without the prior wrttten
consent of the Employer.
(2) The Contractor shall not sub-let the whole of the Works. Exce t
where otherwise provided by the Contract, the Contractor shall not sub-
let any part of the Works without the prior written consent of the
Architect (which shall not be unreasonably withheld) and such consent
if given shall not relieve the Contractor from any liability or obli ation
under the Contract and he shall be responsible for the acts, defaults and
neglects of any sub-contractor, his agent, servants or workmen as full
as if they were the acts, defaults or neglects of the Contractor, his a ents,
servants or workmen.
in' ry t. .. s. ns rid er y
e joyer's in. e nity
18 (1) The Contractor shall be liable for, and shall indemnify the Em-
ployer against, any expense, Iiabilit>,, loss. claim or proceedings what-
soever arising under any statute in respect of personal injury to or the
death of any person whomsoever an sino out of or in the course of or
caused by the carrying out of the Works, unless due to any, act or ne-
glect of the Employer or of any person for whom the Employer is
responsible.
(2) Except for such loss or damage as is at the risk of the Employer
under clause 20[Bj or clause 20[C] of these Conditions (if applicable)
the Contractor shall be liable for, and shall indemnify the Employer
against any expense, liability. loss, claim or proceedings in respect of
any injury or damage whatsoever 10 any property real or personal in so
far as such injury or damage arises out of or in the course of or by
reason of the carrying out of the works, and provided always that the
same is due to any negligence, omission or defauli of the Contractor,
his servants or agents or of any sub-contractor, his servants or agents.
19
(1) Without prejudice to his liability to indemnify the Employer under
clause 18 of these Conditions, the Contractor shall maintain and shall
cause any sub-contractor to maintain:
(a) Such insurances as are necessary to cover the liability of the
Contractor or, as the case may be, of such sub-contractor, in res ect
of personal injuries or deaths arising out of or in the course of or
caused by the carrying out of the Works; and
(b) Such insurances as may be specifically required by the Contract
Bills in respect of injury or damage to property real or personal
arising out of or in the course of or by reason of the carrying out
of the Works and caused by any neolitience, omission or default
of the Contractor, his servants or agents or, as the case may be, of
such sub-contractor, his servants or agents.
The Contractor shall produce or cause any sub-contractor to roduce for
inspection the relevant policy, or policies of insurance together with the
receipts in respect of premiums paid under such policy or policies as
and when required so to do by the Employer; Provided always that as
and when may be reasonably required by the Employer the production
by either the Contractor or any sub-contractor of a current certificate of
insurance from the company or finn which shall have issued the o1ic
or policies aforesaid shall be a good discharge of the Contractor's
obligation to produce or to cause the production of the policy or o1-
icies and the receipts in respect of premiums paid.
(2) (a) The Contractor shall maintain in the joint names of the Em-
ployer and Contractor such insurances as may be specificall stated b
way of provisional sum items in the Contract Bills in res ect of an
expense, liability, loss claim or proceedings which the Em 10 er in a
incur or sustain by reason of injury or damage to property real or personal
arising out of or in the course of or by reason of the carrying out of the
Works and caused otherwise than by the negligence, omission or d -
fault of the Contractor, his servants or agents or of an sub-contra I ,
his servants or agents.
(b) Any such insurance as is referred to in the immediateI re-
ceding paragraph shall be placed with insurers to be a roved b th
Architect, and the Contractor shall deposit with him the I' I-
icies and the receipts in respect of premiums paid.
his",'ance agains! milliy 10 persons and propel'!y 67
(3) Should the Contractor or any sub-contractor make default in in-
sunng or in continuing to insure as provided in sub-clauses (1) and (2)
of this Condition the Employer may himself insure against any risk with
respect to which the default shall have occurred and may deduct a sum
equivalent to the amount paid in respect of premiums from any monies
due or to become due to the Contractor.
Clause 19, together with clause 201Al, IBl or [C], contains the contrac-
tual requirements for insurance.
Clause 19 is concerned with claims against the contractor by third
parties. Both the contractor and his sub-contractors must insure aoainst
their liabilities for injury to third-party persons and property.
Clause 19(I) requires the contractor to insure (and cause his sub-
contractors to insure) against liability in respect of injury to persons
and property. He is bound to to take out and maintain :
(1) insurances necessary to cover his liability in respect of personal
injury or death arising out of or in the course of or caused by the
carrying out of the Works, to insurance against the liabilities which
he has accepted under clause 18(I). The wording follows that of
clause 18(I) when describing the classes of risk that must be
insured against. What is required is full insurance cover without
limit of the contractor's liability for claims for personal injuries
and death. The contractor must ensure that this provision is stepped-
down in any sub-contract. Under the indemnity provisions (clause
18(I)) the contractor is not liable to the employer if the injury is
due to the employer's act or neglect or the act or neglect of those
for whom the employer is responsible.
(2) insurance against property claims in respect of the liabilities which
he has assumed under clause 18(2). in this case, the requirement
is for the contractor to take out and maintain "such insurances as
may be specifically required by the Contract Bills" to cover this
area of risk. Once again it is important that the obligation is
stepped-down in any sub-contract.
it is important that contractors (and their sub-contractors) should main-
rain realistic cover; the in denimty which the contractor has given to the
employer under clause 18 is not limited to the amount of cover which
the contractor maintains under this provision.
The opening words of clause 19(I) are of great importance and are
not mere legalese. They make it clear that if a clann is made against
the employer, and under clause 18 the employer can claim to be indem-
litfied, he can claim from the contractor the total sum for which he is
liable. it would be no defence for the contractor to say that his irisur-
an CG cover was inadequate, and the advice of a competent insurance
broker should be obtained. Damages in personal injury cases can be
astronomical.
68 C/aM. ,e 19
20
*tA1 (1) The Contractor shall in tile joint names of the Employer and
Contractor insure against loss and daniage by fire, storm, tempest, light-
ning, flood, earthquake, aircraft or any, thing dropped therefrom, aerial
objects, riot and civil commotion for 111e full value thereof (plus the
percentage named in the appendix to these conditions to cover profes-
sional fees) all work executed and all unfixed materials and goods
intended for, delivered to, and placed on or adjacent to the Works, but
excluding temporary buildings, plant, tools and equipment owned or hired
by the Contractor or any sub-contractor, and shall keep such work. in a-
tenals and goods so insured until Practical Completion of the Works.
Such insurance shall be with insurers approved by, the Architect and the
Contractor shall deposit with him tile pollc} or policies and the recei is
in respect of premiums paid: and should the Contractor make default in
insuring or continuing to insure as aforesaid 111e Employer Ina), himself
insure against any, risk \\, ith respect of \\ hich Ihe default shall ha\. e
occurred and deduct a suni equivalent 10 the amount paid by him in
respect of premiums from any monies due or to become due to the
Contractor.
Provided always that if the Contractor shall independently of his obii-
gations under this Contract maintain a polic), of insurance which covers
conei. alto) the said work, materials and goods against the aforesaid
contingencies to the full value thereof (plus the aforesaid percentage,
if any), then the maintenance by the Contractor of such policy shall. if
the Employer's interest is endorsed thereon, be a discharge of the
Contractor's obligation to insure in the joint names of the Em 10 er
and Contractor; and the production by the Contractor as and when in a
reasonably be required by the Architect of a current certificate of irisur-
ance from the Company or finn which shall have issued the said o1ic
shall be a discharge of the Contractor's obligation to de OSit with the
Employer a policy or policies and the receipts in respect of reiniums
paid.
(2) Upon the settlement of any claim under the insurances aforesaid
the Contractor with due diligence shall restore work dama ed re lace o
repair any unfixed materials or o00ds which have been destro ed or
injured remove and dispose of any debris and proceed with the ca inc
out and completion of the Works. All monies received from such msur-
ances (less only the aforesaid percentaoe, if any) shall be paid to the
Contractor by instalments under certificates of the Architect issued t
Irisi, ,'Q, ice of Ihe 11.01'ks againsiji, 'e. erc 71
*tBj All works executed and all unfixed materials and goods intended
for, delivered to and placed on or adjacent to the Works (except tern-
POTary buildings, plant. tools and equipment owned or hired by the Con-
tractor or any sub-contractor) shall be at the sole risk of the Employer
as regards loss or damage by fire, storm, tempest, lightning, flood,
earthquake, aircraft or anything dropped therefrom, aerial objects, riot
and civil commotion. The Employer shall maintain a proper policy of
insurance against that risk. and such policy and the receipt for the last
premium paid for its renewal shall upon request be produced for irispec-
tion by the Contractor. If the Employer shall at any time fail upon the
request to produce any receipt showing such a policy as aforesaid to be
effective then the Contractor may in the name and on behalf of the
Employer insure all work executed and all unfixed materials and goods
as aforesaid against loss or damage occasioned by the said contingen-
cies and shall upon production of the receipt for any premium paid by
him be entitled to have its amount added to the Contract Sum. it any
loss or damage affecting the Works or any part thereof of any such
unfixed materials or goods is occasioned by any one or more of the said
contingencies, then
(a) The occurrence of such loss or damage shall be disregarded in
computing any amounts payable to the Contractor under or by virtue
of this Contract.
(b) The Contractor with due diligence shall restore work damaged,
replace or repair any unfixed materials or goods which have been
destroyed or injured, remove and dispose of any debris and proceed
with the carrying out and completion of the Works. The restoration
of work damaged, the replacement and repair of unfixed materials
and goods and the removal and disposal of debris shall be deemed
to be a variation required by the Architect.
*[C] The existing structures together with all the contents thereof and
the Works and all unfixed materials and goods intended for, delivered
to and placed on or adjacent to the Works (except temporary buildings,
plant, tools and equipment owned or hired by the Contractor or any
sub-contractor) shall be at the sole risk of the Employer as regards loss
or damage by fire, stonn, tempest, lightntng, flood, earthquake, aircraft
or anything dropped therefrom, aerial objects, riot and civil coriumotion,
and the Employer shall maintain a proper policy of insurance aganist
that risk, and such policy and the receipt for the last premium paid for
its renewal shall upon request produced for inspection by the Contrac-
tor. if the Employer shall at any time fail upon request to produce any
receipt showing such a policy as aforesaid to be effective then the
Contractor may in the name and on behalf of the Employer insure the
existing structures together with all the contents thereof the Works and
all unfixed materials and goods as aforesaid against loss and damage
occasioned by the said contingencies, and for that purpose shall have
72 CIO"se 20
This important clause must be read with clauses 18 and 19. There are
three alternatives and two of them must be deleted, as explained in the
first footnote. Each alternative is applicable to a particular situation.
instt, .OJTce of Ihe works agains! fire, e!c 73
Clause 201B/ is similar in its terms to clause 201Al, but provides for
the employer and not the contractor to take out the necessary insurance.
in this case, the matters for which the contractor is required to take out
insurance under clause 20[A] are at the sole risk of the employer. The
contractor is entitled to inspect the policy and premium receipts at any
time by simple request. if the employer fails to produce a receipt, the
contractor may insure against the specified perils in the employer's name.
He is then entitled to have the amount of any premium he pays added
to the Contract Sum on production of the receipt.
There is no express obligation on the contractor to give notice to the
employer should any loss or damage occur, but it is thought that such
an obligation is implied. Paragraph (a) emphasizes that if loss or damage
is caused by the specified risks, this in no way affects the computation
of any amounts due to the contractor under the contract up to the date
of the damage.
in simple tenns, the architect or quantity surveyor must take no
account of the damage when computing any amount nonnally payable
to the contractor under the contract in these circumstances.
in contrast to clause 20tA1, this clause tries to ensure that the con-
tractor suffers no loss of any sort if any of the work is damaged by the
insurance risks. This is emphasized again in paragraph (b) which sets
out the contractor's obligations as to reinstatement in ternis Corres ond-
ing to clause 20[A](2). The contractor must carry out restoration, re-
pair, and removal of debris and proceed with the Works in the nonnal
way. This is subject, of course, to his right to detemiine his own Gin-
ployment under clause 26(I)(c)(it) if appropriate and to his entitlement
to any extension of time for completion under clause 23(c) in respect
of any delay. The reinstatement work is to be regarded as a variation
and is to be valued accordingly under clause I I .
76 Clause 20
Paingraph (b) gives either party the right to detemiine the contractor's
employment under the contract "if it is just and equitable to do so"
The parties have only 28 days from the occurrence of the loss or damage
in which to serve notice of determination on the other party, who then
has only seven days from receipt of the notice within which to give the
other party a wrttten request to concur in the appointment of an arbitra-
tor under clause 34 to decide whether notice of delemiination would be
just and equitable. This last phrase is deplorably vague and the contract
lays down no criteria to aid in its interpretation.
The notice of detemnination is to be served by registered post or
recorded delivery, and it is submitted that these words are best inter-
preted as being mandatory : Cenirol Provident Fund Board v HO Bock
Kee 119811 2 MLJ 162, a decision of the Court of Appeal of Singapore.
When notice of detennination is given and not challenged (or is up held
by the arbitrator), the financial settlement of the contract up to the
detennination is to be canled out under clause 26(2). However, sensi-
bly and equitably, the contractor in these circumstances is not entitled
to be paid "any direct loss and/or damage" caused to him by the deter-
mination. As a result - and very sensibly - the contractor has no right
to recover, inter and, the loss of profit and overhead contribution which
he would have received had the contract proceeded to completion.
Paragraph (c) deals with what is to happen if no notice of detenni-
nation is given or, if given, is not upheld by the arbitrator. in that case,
the contractor must reinstate the Works and proceed to completion in
the nonnal way, obeying any architect's instructions for the removal
and disposal of debris. All reinstatement work, the making goods6f any
loss or damage, and compliance with architect's instructions for the
disposal and removal of debris is to be treated as a variation and valued
accordingly under clause I I.
Clause 21
This short clause is one of the most inTPOitant in the coniract, and -
perhaps not surprisingIy both of its constituent parts are \\, idcly niisun-
derstood in the construction industry.
Although failure by the employer to give effective possession of the
site does not of itself amount to a repudiation of the contract, it is a
breach of a covenant essential to the performance of the contract and,
as Chang Min Tat F1 pointed out in To, ? Hock Charr v Kilo Teck Sellg
119801 I MLJ 308, in such circumstances "the other party to the con-
tract may rescind the contract and he does so, ordinarily, by giving
notice of his intention to do so. His right to do so arises immediately
where time is or is made the essence and the time has passed .
Failure to give effective possessioi} of the site on the date specified
is thus a breach of contract which in principle entitles the contractor to
rescind. At the very least, the contractor will be entitled to damages for
any loss which he suffers as a result of the breach. Moreover, since
there is no provision in the contract for the architect to grant an exten-
sion of time for completion because of the delay caused by the
employer's breach, it means that the date for completion will be "at
large" and the employer will forfeit his right to liquidated damages.
The English Court of Appeal has considered the problems involved
in the operation of clause 21(I) in Tile Rapid Build^77g GJ'oup Ltd v
Eol^itg Family Housing Associoiion Ltd (1984) I ConLR I where, at
the time when, by clause 21, the defendants promised to give the plain-
tiffs possession of the site, they were unable to do so because its north
east corner was occupied by squatters in an area of some size behind a
-.:
.
.,
I
,
I
A
There is no doubt that the the PAM fomi needs similar amendment.
Until it is so amended, any failure by the employer to give possession
"
* of the site on the due dare is a breach Going to the root of the contract
*
and at the very least the contractor will be entitled to damages for any
loss he suffers by the breach.
"
, .*** Gin!, se 21(I) sets out the employer's obligation to give possession of
* . .- . .
*~* .
the site to the contractor. The contractor is then oblioed to begin the
Works, proceed "regularly and diligently" with them so as to complete
^* *.
\** .
the Works "on or befoi. e" the completion date set out in the Appendix.
The dates for possession of the site and for completion must be speci-
^. .. fled in the Appendix and, subject to the orant of any extension of time
j;;:***.-
;*- -
under clause 23 or clause 32(I)(c) (which peruiits an extension of time
for reinstatement of war damage) the contractor is bound to complete
the work by the specified completion date. it he fails to do so, he will
** *
*** be liable for liquidated damaoes to the employer under clause 22.
***^
",*.
This is subject to the exception that the employer is not entitled to
liquidated damages if by his acts or omissions he has prevented the
*-
,. . ^ ..
contractor from completing his work by the completion date unless an
*,-, extension of time is both Grantable and has been granted for any delay
caused by that act or omission : see the old Enolish cases of Ho/me v
;.* *.
It *..
** *
*, -:,
~..
{...
80 CIOuse 21
Guppy (1838) 2 M & W 387; Wells v A1'my & Na\, y CO-OPei'drive So-
ciei}, (1902) 86 LT 764.
Clause 21(I) says nothing about the degree of possession which must
be Given to the contractor but it has been held in Canada that the
contractor is entitled to a sufficient degree of possession to allow him
to execute the work unimpeded by others : The Queen ill Right of
Coiloda v Waite, ' Cabott Const, .MCIion Lid (1975) 69 DLR (3d) 542.
The sub-clause in fact contemplates that the contractor is to haveexclu-
sive possession of the site, subject to the employer s power under clause
29 to brino others on the site to work concurrently with the contractor.
in such a case the contractor is entitled to an extension of time for any
consequent delay (clause 23(h)) and to recover any direct loss and/or
expense which he suffers or incurs as a result of the exercise of that
power (clause 24(I)(d)).
in principle, then, "the contract necessarily requires the building owner
to give the contractor such possession, occupation or use as Is neces-
sary to enable him to perfonn the contract" : London Bo, 'oug/I of
Houjislow v Twickenhanz Go, den Developments Ltd [1970] 3 All ER
326. This is a fundamental obligation on the part of the employer.
The contractor's primary obligation is to complete the Works by the
contractual date for completion. His secondary obligation is to proceed
with the Works "regularly and diligently ' so as to achieve that objec-
live "on or before" the date for completion stated in the Appendix. '
in the TM^kenhai?I Golden Developme, lis Lid case the meaning of
the phrase "I'egularly and diligently" was discussed. Tile judge said :
These are elusive words on which the dictionaries help very little. The
words convey a sense of activity, of orderly progress, and of industry and
perseverance; but such language provides little help on the question of
how much activity, progress and so on is to be expected. They are words
used in a standard fomi of building contract and in those circumstances 11
may be that there is evidence that could be given, whether of usage
among architects, builders and building owners or otherwise, that would
be helpful in construing the words. At present, all I can say is that I
remain somewhat uncertain as to the concept enshrined in those words. ,
Failure to proceed regularly and diligently with the Works is one of the
grounds in clause 25(I) which may give rise to delennination of the
contractor's employment by the employer.
The obligation to complete "on o1' b<fore" the completion date should
be noted. The contractor may programme for early completion and he
is entitled to complete the Works on a date earlier than the date of
completion stated in the Appendix. He is further entitled to carry out
the Works in such a way as to enable him to achieve an earlier coin-
PIGtion date whether or not the Works were programmed.
However, there is no corresponding obligation on the employer or
his architect to co-operate with the contractor so as to enable early
completion to be achieved, eg by supplying infonnation at times to
enable the contractor to complete by the earlier date he had in mind.
This is so even if the Bills have required the submission of a pro-
Possession, coinple!ion and POS!ponemen! 81
gramme to the architect and the programme submitted shows a dare for
completion ahead of the contract date.
These points were a matter of direct decision in England in Glenfton
Consti'wction Ltd v The Gumness T, .ust (1987) 11 ConLR 126. The
contractor is entitled, but not oblioed, to complete by an earlier coin-
PIetion date shown in his programme, and it is clear that the contrac-
tor has no claim for damages (or for "direct loss and/or expense" under
clause 24) for the architect's failure to issue information and instruc-
lions at times necessary to comply with the progranune. The fact that
the Contract Bills have required a programme to be submitted by the
contractor does not in itself make the position different.
in practical terms, it is important that the contractor should prepare
a competent programme before commencing work, and that he updates
this programme as the work proceeds and that he prepares forward plans.
Potential causes of delay are then revealed in time to allow preventive
action to be taken. Too many contractors proceed in the hope that they
can make up time which appears to be lost, and discover too late that
this is physically impossible due to the overlapping of trade operations
which must eventually result. Any programme produced by the
contractor is merely a management document; it has no contractual
effect and is not a contract document. This is so even if, as in the
Glention case, the programme is required by a provision in the Bills of
Quantities.
The date for completion should not be confused with the date of
practical completion (clause 15(I)). This may or may not coincide with
the date for completion stated in the Appendix. The date so stated is
the date by which the Works must be completed, subject of course to
the fact that the date may be altered by the grant of extensions of time
under clause 23 or 32(I)(c). Only if the Works are not completed by
that date is the contractor in breach of his obligation to complete and
becomes liable to liquidated damages. The contractor camot be required
to finish earlier than the completion date stated in the Appendix.
Clause 21(2) Ginpowers the architect to issue instructions requiring
the postponement of any work to be executed under the contract, and
neither this sub-clause nor any other terni of the contract empowers
him to defer the giving of possession of the site. in England it has been
held that an instruction to postpone win be implied if the architect issues
an instruction to the contractor which necessarily entails postponement
of the work, even though the instruction is not issued under clause 21 (2)
and does not specifically instruct postponement : M Hornson & Co
(Leech) Lad v Leeds City Council (1980) 14 BLR 118.
If instructions to postpone the execution of work are given they may :
(1) provide grounds for claiming an extension of time (see clause
23(e)); and/or
(2) give grounds for a claim for direct loss and/or expense (see clause
24(I)(e)); and/or
(3) give grounds for the contractor to detennine his employment under
the contract (see clause 26(I)(c)(iv)).
Clause 22
22 if the Contractor fails to complete the Works by the Date for Coinple-
lion stated in the appendix to these Conditions or within any extended
time fixed under clause 23 or clause 32(I)(c) of these Conditions and
the Architect certifies in writing that in his opinion the same ought Tea-
sonably so to have been completed, then the Contractor shall pay or
allow to the Employer a sum calculated at the rate stated in the said
appendix as Liquidated and Ascertained Damaoes for the period during
which the Works shall so remain or have remained incomplete, and the
Employer may deduct such sum from any monies due or to become due
to the Contractor under this Contract.
This clause provides the machinery whereby tile parties can agree in
advance the damages 10 be payable by the contractor if he fails to
complete the \\'orks by the completion date stated in the Appendix, of
within any, extended period authorized by the architect under clause 23
or clause 32(I )(c). 11 also provides a contractual mechanism for their
recovery. When liquidated damages are agreed, the employer's only
remedy for late completion is a sum not exceeding the specified amount.
He does not have the option of claiming unliquidated damages.
Should no date for completion be inserted in the Appendix, then no
liquidated damages will be payable since there is then no date from
which liquidated damages can run, There must be a definite date to act
as a starling point and if for some reason the completion date has gone,
the employer's right to liquidated damages will be lost : Slim Chio HMOt
v Wong red Fui [1983] I MLJ 151.
This is a very real possibility under the PAM form because, as will
be seen, the extension of time clause is defective, and if no extension
of time is grantable and granted under the contract for acts of hindrance
or prevention by the employer which cause delay to completion, this
will have the effect of putting time for completion "at large". in other
words, the provision for liquidated damaoes will be Tendered unenforce-
able by any delay caused by the employer and not covered by the
extension of time clause : Peak Consti. "ciion (Live, pool) Ltd v MCKin-
ney Foundations Ltd (1976) I BLR 111, which is the leading modem
English case, also holding that a provision for liquidated damages must
be consumed conti. a PI'ofei'entem.
Damages 101' non-completion 83
breach. TITe amount of loss or damaoe which has actually occurred must be
a major factor in deciding whether the amount provided for was an honest
pie-estimate of the likely loss or damaoe. if 111e actual loss or damaoe suffered
is very much less than the sum agreed, the court will refuse to enforce the
agreement to pay at specified sum by way, of liquidated damages.
Section 75 apparently perniits the recovery of liquidated damages
"whether or not actual damage or loss is proved to have been caused"
by the breach of late completion, but Professor Sinnadurai says, "the
cases seem to suggest that the plaintiff cannot recover sinipficilei. the
suni fixed in the contract, whether as a penalty or liquidated damaoes.
The plaintiff is required to prove the actual damages he has suffered" :
Low of Colliinci in Malaysio ond Singoj?oi'e . Coses und Coi??,?lei?100',
2nd edition, 1987, Butterworths, page 671. Later (page 703) he adds
that in every case "the court has to be satisfied that every sum of money
payable by way of liquidated damages is reasonable. Upon the
court being satisfied that the said sum is a genuine pre-estimate and
that it represents a reasonable sum for the loss suffered, it may order
the said sum to be paid as damages".
in practical tenns, therefore, the architect must make an actual cal-
CUIation of the likely loss to the employer and any temptation to in-
crease the figure should be avoided as otherwise it may well be found
not 10 be "reasonable compensation". The amount of damages oldered
by the court in these circumstances cannot exceed the specified amount, ,
and so the figure inserted in the Appendix is a limitation on the anIOUnt
for which the contractor is liable.
Cmuse 22 deals only \\, ith damaoes for' late completion and confers
on the employer a right to deduct liquidated daniaoes "from any moneys
due or to become due to the Contractor under this Contract", re from
interim certificates or from retention moneys.
For this provision to operate it is necessary for the architect to CGr-
tify "in writing that in his opinion [the Works] ouoht reasonably" to
have been completed by the Date for Completion. it follows that a
certificate can only be given under clause 22 after the Date for Coin-
PIetion (or any extended Date for Completion) has passed. The issue of
the clause 22 certificate of delay (clause 3(8) applies to its issue) is a
coltdrtion PI'ecedeiit to the employer's noht to liquidated damaoes ; this
has been so decided in England in A1gi'ey Collti'actoi's Ltd v Tenth Moot
Housing Society Lid ( 1972) I BLR 45 and Token Coltsti'MCIioii Co Lid
v Chin'Ito11 Estates Lid (1973) I BLR 48.
The architect can issue his clause 22 certificate at any time prior to
the issue of the final certificate. Once he has issued the final certificate
under clause 30(6) then, if no notice of arbitration has been given by
either party in accordance with clause 30(7), the architect becomes
functus offICio and is thereafter precluded from issuing any valid CGr-
tmcate under clause 22 : see the Briolish case of H Foiiv, earl^i. Lid v
Asden Sec",. mes Ltd (1979) 12 BLR 40.
Daniages 101' non-completion 85
Extension of time
This important clause is the main provision under WITich any alteration
to the completion date is made. (Clause 32(I)(c) requires the architect
to grant the contractor an extension of time in respect of reinstatement
after war damage. )
Clause 23 provides for the architect to grant an extension of time on
specified grounds and an extension of time is orantable on those grounds
and no other. The architect has no inherent power to extend the period
for completion and in the absence of an express provision such as clause
23 he would have no power to do so. Failure by the architect properI
to exercise the power to extend lime, where any, dela}, to completion is
caused by the employer or those for whom he is responsible in law,
relieves the contractor from his Iiabilit\, to pay or allow liquidated
damages (Dodd v C/I"lion 118971 I QB 562) and the time for cample-
lion becomes "at large", to the contractor's oblioation is then to coin-
PIete "within a reasonable time".
The 'operation of clause 23 modifies the liability of the contractor to
complete the Works by the date for completion specified in the Appen-
dix (clause 21) and to pay or allow liquidated damages for the breach
of late completion. (dause 22). 11 imposes a duo, on the architect to
grant "a fair and. reasonable extension of time for completion of the
Works" in specified circumstances. One effect of extendin the eriod
for completion is to prevent the architect from issuing his clause 22
certificate of delay. He cannot certify late completion under clause 22
until the revised completion date has passed.
Clause 23 is gravely defective in many important respects and is in
need of urgent amendment. The grounds on which an extension in^, be
granted are very limited and do not cover many common delaying events,
eg failure by the employer to supply materials to the contractor, failure
to give agreed access and failure to give possession of the site on the
due date. it such events occur and cause delay to completion the an'chi-
tect has no power to grant an extension of time with the result that time
will be "at large" and the employer will lose his noht to liquidated
damages. This is made clear by the leading English case of Peak
Consti. "ctioiz (Dyeipoo/) Ltd v MCKiitney Fowldotio, us Lid (1970) I BLR
I I and it is somewhat surprising that clause 23 should continue to be
used in its present fomi.
ET!ensi'on of tinie 89
must then "make in writing a fair and reasonable extension of time for
completion of the Works". The contract says that he must do this "as
soon as he is able to estimate the length of the delay" and no time limit
is specified.
it is submitted, however, that the views of Roper I in the New Zealand
case of Fernbrook TrQding Co Lid v Taggai't I 19791 I NZLR 556 are
of assistance. The learned judge said :
I think that it must be implicit in the normal extension of time clause that
the contractor is to be infomied of his new completion date as soon as
reasonably practicable. it the sole cause is the ordering of extra work, then
in the nomial course extensions should be given at the time of ordering, so
that the contractor has a target for which to aim. Where the cause of delay
lies beyond the employer, and particularly where its duration is uncertain,
then the extension may be delayed, although even then it would be a reason-
able inference to draw from the ordinary extension clause that the extension
should be given a reasonable time after the factors which will govern the
exercise of the larchitect'sl discretion have been established. Where there
are multiple causes of delay, there may be no alternative but to leave the
final decision until just before the issue of the final certificate.
A rider should be added to this statement since where the event
causing delay is the employer's responsibility, the architect should grant
an extension before the current completion date has passed. it he fails
to do so, it is thought that time will become "at large" and the em-
ployer will forfeit his right to liquidated damages : see the English
decision of Miller v London County Council (1934) 151 LT 425.
The position is different where the event causing delay is outside the
control of the employer or the architect. in that case, the architect may
grant an extension of time even after completion of the Works as appears
from the English case of Amalgamoted Build^^g Contractors Ltd v
Wattham Holy Cross Urban District Council 119521 2 All ER 452.
The effect of the cause of delay on completion is to be assessed at
the time when the Works are actually being carried out and not when
they were programmed to be carried out. This has been so decided in
England in Waiter Lawrence & Son Ltd v Commercial Union Proper-
ties (UK) Ltd (1986) 4 ConLR 37 which involved a contract on all
fours with the PAM fomi. in that case it was held to be so even though
the contractor was in CUIpable delay.
The contractor's entitlement is to "a fair and reasonable extension of
time" and the length of the extension of time must relate to the effect
of the delaying event on contract progress.
The dual prowso to the clause is important, and deals with matters
which the architect will take into account in consideting the grant of an
extension of time. The architect's decision as to whether or not the
contractor has used "constantl his best endeavours to revent dela is
subject
j yto review
., by____.
an, arbitrator in case of dispute,
. I and the better view
is that compliance witri~the proviso does not require the contractor to
expend substantial sums of money.
,
92 Clause 23
Other necessary instructions which are received late from the architect
may, of course, give rise to a claim under paragraph (f).
Delay on this ground is very common, and the contractor must be able
to show that he has taken all practicable steps to avoid or reduce the
delay if he is to be entitled to an extension of time for completion.
Ex!ension of time 95
What these steps are is not specified but they may well include some
reprogramming. in fact, the paragraph has a limited meaning because
of the decision of the English House of Lords in Westminster Corpora-
tion v I loryis & Sons Ltd 119701 I All ER 943, where it was laid
down that "delay on the parr of nominated sub-contractors" was con-
fined to delay in completing the sub-contract works.
Thus, if as in that case a nominated sub-contractor ostensibly coin-
PIetes his sub-contract, but is later found to be in breach and has to
realm to site to remedy the breach. that is not "delay on the part of"
the nominated sub-contractor. in those circumstances, therefore, the
contractor is not entitled to an extension of time. By analogy the same
ruling applies to such delays by nominated suppliers.
The House of Lords said :
execution of their work and does not extend to delay caused by their
returning to carry out remedial work after purported completion : see
Wesri?liftsiei' Coipoi. ajio, ? v I Jolt, is & Soils Lid 119701 I All ER 943.
Examine relevant
START Progress delayed events
No
Yes Exceptionally
inclement weather
Use best endeavours 10
minimise delav No
Yes Clause 20
contingencies
No
Do all reasonably
required Yes Civil
commotion etc
No
Yes
AIS
No
Yes Late
information
No
Nominated
sub-contractor
No
Artists &
tradesmen
No
inspection
and testing
No
Unforeseen
shortages*
No
Notify architect of
delay in wiring
* May be omitted
\
98 Clause 23
Flowchart 3
Extension of time : architect's duties (clause 23)
No No No
Force majeure
No
Works
Excepiionally No
delayed beyond
inclemeni wealher
coinpleiion
dale
No Yes
Clause 16
No Contractor used
contingenc, CS
be SI endeavours
No
\'CS
Civil
commotion
No Contract
done all reasonably
No d
q
AIS Yes
Any \'es
No more claims
Late Requested
information in writing in No
time
Go To
No No NEXT
ITEM
Nominated Yes
subcontractor Took steps
to reduce
No No
No
No
Unforeseen Yes STOP
shortages*
No
No
Any Yes
more claims
*OPTIONAL
Reject claim
Refer to Conditions
Clause 24
(2) The provisions of this Condition are without prejudice to any other
rights and remedies which the Contractor may possess.
99
100 CIOiise 24
The objective of clause 24 is to reimburse the contractor for dii. ect loss
and/or expense which he has suffered or incurred as the direct result of
certain specified events and for whicli he is not reimbursed by payment
made under "any other provision" of the contract. it provides a
mechanism for the settlement of the more common contractor's monetary
claims.
A claim can only be made under the provision if "regular progress
of the Works or any part thereof" has been nioiei'iany dyected by one
or more of the stated events, to a claim can only arise as a ITect con-
sequence of one of the five specified matters.
Some, but not all, of the matters listed in clause 24(I) amount to
breaches of contract for which the employer is responsible. In that case,
clause 24( I ) provides an alternative means of recovery to a claim for
damages at common law, such common law claims being expressly
preserved by clause 24(2). The benefit to the contractor of a claim under
clause 24(I) is that he receives payment under the contractual
mechanism. A written application to the architect by the contractor at
the right time is a condition precedent to a successful claim under clause
24(I ).
The term "direct loss and/or expense" is a convenient shorthand which
means that what is recoverable is the equivalent of damages at common
law according to the ordinary principles in section 74 of the Contracts
Act 1950, to "compensation for any loss or damaoe caused to him . . .
which naturally arose in the usual course of things from the breach, or
which the parties knew. when they made the contract, to be likely to
result from the breach of it . . . . Such compensation is not to be given
for any remote and indirect loss or damaoe sustained . " : see the
English cases of Winight Ltd v pH & T (Holdings) Ltd (1968) 13 BLR
26 and FG Miniei. Ltd v Wets/? Health Technical Services 01,801tisaiion
(1980) 13 BLR I, which are decisive on the meanino of "direct loss
and/or expense" being equivalent to a claim for damages at common
law.
A claim under clause 24( I) is not a means of turning a loss-making
contract into a profitable one, The only purpose of the clause is to
ensure that the contractor is not out of pocket as a result of the speci-
fled events materialIy affecting "regular progress of the Works". The
word dii. ect is important; the loss and/or expense must have been caused
directly by the event relied on.
Clause 24(I) does not oblige the contractor to make a written appli-
cation. it merely governs the steps to be taken if an application is made.
in London Boi'ough of MeI. ton v Sinnley Hugh Ledch Ltd (1985) 32
BLR 51, the English High Court emphasized that the machinery of the
clause is not exhaustive of the contractor's remedies and referred to the
express wording of clause 24(2). Accordingly, the contractor is entitled
to pursue a claim for damages as an alternative if he so desires pro-
vided, of course, that the event relied on amounts to a breach of con-
tract for which the employer is responsible. The contractor can only
recover his loss once. Per Vinelott J in London Bo, 'ough of Me I'ton v
Loss and expense callsed by di^1111'bance of leg"!or progress of the works 101
Sinn/ey Hugh Leoch Ltd (1985) 32 BLR 51:
Under clause 24 the contractor can call on the architect to ascertain the
direct loss and/or expense suffered and to add the loss when ascertained to
the contract sum. The contractor will then receive reimbursement promptly
and without the expense and delay of a claim for damages. But the contrac-
tor is not bound to make an application under clause 24(I). He may prefer
to wait until completion of the work and join the claim for damages for
breach of the obligation to provide instructions, drawings and the like in
o00d time with other claims for damages for breach of obligations under the
contract . . . .
(1) Be made in time. it not in time then, whatever its merits, the
architect may reject it. However, architects should be careful in
this regard since the employer may, by his conduct, be estopped
from objecting to a late claim: Rees & Kii. by Ltd v Swanseo City
Council (1985) 5 ConLR 34.
(2) Show that the regular progress of the Works or part of them has
been affected by one or more of the matters specified.
(3) Be supported by relevant information and details of the loss and/
or expense incurred to the date of the application.
(4) Be of such a nature that the sum claimed is not recoverable, if
recoverable at all, under any other clause in the contract.
Loss and expense caused by disrt, ,. borice of I'eg!1101' PI'ogress of Ihe wo, 'ks 103
The following five events are specified as giving rise to a claim by the
contractor.
START
Direct
Regular Yes Examine matters
progress materialIy loss and/or
listed
affected expense
No No
No
No
Yes
Inspection
and testing
Apply in writing to
architect within
reasonable time of it No
becoming apparent
progress has been Yes
affected 24(I) Discrepancy
or
divergence
No
Yes
Artists &
tradesmen
No
Yes A1
postponement
of work
No
STOP
106 Clause 24
Flowchart 5
Loss and/or expense : architect's duties (clause 24)
START
No No No No
Yes
Examine in a ers
No No No
Work
Irispeciion in accordance ". iih
and legung contraci
Archiiect or qu"1111y
No No surveyor must
ageeri. In claim
Discrepancy Yes
or
divergence
No
No No
Reject claim
AIS
Yes
postponement of
work
No
Refer 10 conditions
Clause 25
Determination by employer
25 (1) If the Contractor shall make default in any one or more of the fol-
lowing respects, that is to say:
(a) If he without reasonable cause wholly suspends the carrying out of
the Works before completion thereof or
(b) If he fails to proceed regularly and diligently with the Works, or
(c) it he refuses or persistently neglects to comply with a written
notice from the Architect requirlng hint to remove defective work
or improper materials or goods and by such refusal or neglect the
Works are materialIy affected, or
(d) If he fails to comply with the provisions of clause 17 of these
Conditions,
then the Architect may give to him a notice by registered post or re-
corded delivery specifying the default, and if the Contractor either shall
continue such default for fourteen days after receipt of such notice or
shall at any time thereafter repeat such default (whether previously
repeated or not), then the Employer without prejudice to any other rights
or remedies, may within ten days after such continuance or repetition
by notice by registered post or recorded delivery forthwith detennine
the Employment of the Contractor under this Contract provided that
such notice shall not be given unreasonably or vexatiously.
(2) in the event of the Contractor becoming bankrupt or making a
composition or arrangement with his creditors or having a winding up
order made or (except for purposes of reconstruction) a resolution for
voluntary winding up passed or a receiver or manager of his business or
undertaking duly appointed, or possession taken by, or on behalf of the
holders of any debentures secured by a floating charge, of any properly
comprised in or subject to the floating charge, the employment of the
Contractor under this Contract shall be forthwith automatically deter-
mined but the said employment may be reinstated and continued if the
Employer and the Contractor his trustee in bankruptcy liquidator re-
ceiver or manager as the case may be shall so agree.
(3) in the event of the employment of the Contractor being detennined
as aforesaid and so long as it has not been reinstated and continued, the
following shall be the respective rights and duties of the Employer and
Contractor:
(a) The Employer may employ and pay other persons to carry out and
complete the Works and he or they may enter upon the Works and
use all temporary buildings, plant, tools, equipment, goods and
107
108 Clause 25
Flowchart 6
Determination by employer
START
Notice of
Con. rustor No
Wholly delenninaiion by
Architeci may serve
suspends work slops dejauli within
without reasonable default nullce 25(11 7 davs employer 25(I)
cause
Yes
No
No further aciion
Falls 10 Yes buy employer can
proceed regularly and delennine without
diligently further notice 11
default repealed
No 25(I)
F. 115 10
Yes
comply with A1 and
works material Iy
riflec, ed
No
F"13 Yes
10 comply with
clause h
No
No
Take legal .dvice
employer may
General Yes delennine .her 28
mobilisation days unless works
31 pr. c, ICally completed
or was damaged
No
Arbirraior decides if
just and equi"ble
31
Yes
Determination by contractor
26 (1) Without prejudice to any other rights and remedies which the Con-
tractor may possess, if
(a) The Employer does not pay to the Contractor the amount due on
any certificate within the Period for Honouring Certificates named
in the appendix to these Conditions and continues such default for
seven days after receipt by registered post or recorded delivery of
a notice from the Contractor staring that notice of detemiination
under this Condition will be served if payment is not made within
seven days from receipt thereof; or
(b) The Employer interferes with or obstructs the issue of any certifi-
cate due under this Contract; or
(c) The carrying out of the whole substantially the whole of the un-
completed Works (other than the execution of work required under
clause 15 of these Conditions) is suspended for a continuous period
of the length named in the appendix to these Conditions by reason
of:
co 10, ce male", e, or
(ii) loss or damage occasioned by any one or more of the contin-
gencies referred to in clause 20(A) or clause 20tBl of these
Conditions (if applicable), or
(in) civil coriumotion, or
(iv) Architect's instructions issued under clauses I(2), 11(I) or
21(2) of these Conditions, or
(v) the Contractor not having receiv?d in due time necessary in-
structions, drawings, details or levels from the Architect for
which he specifically applied in writing on a date which hav-
ing regard to the Date of Completion stated in the appendix
to these Conditions or to any extension of time then fixed
under clause 23 or clause 32(I)(c) of these Conditions was
neither unreasonably distant from nor unreasonably close to
the date on which it was necessary for him to receive the
same, or
(vi) delay on the part of artists, tradesmen or others engaged by
the Employer in executing work not fomiing part of this
Contract, or
(vii) the opening up for inspection of any work covered up or of
the testing of any of the work materials or goods in accor-
dance with clause 6(3) of these Conditions (including making
good in consequence of such opening up or testing), unless
116 Cirruse 26
(a) The Contractor shall with all reasonable dispatch and in such manner
and with such precautions as will prevent injury, death or damaoe
of the classes in respect of which before the date of determination
he was liable to indemnify the Employer under clause 18 of these
Conditions remove from the site all his temporary buildings, plant,
tools, equipment, goods and materials and shall give facilities for
his sub-contractors to do the same, but subject always to the provi-
sions of sub-paragraph (iv) of paragraph (b) of this sub-clause.
(b) After taking into account amounts previously paid under this Con-
tract the Contractor shall be paid by the Employer:
a) The total value of work completed at the date of detennination.
(ii) The total value of work begun and executed but not completed
at the date of detennination, the value being ascertained in
accordance vJith clause I I(4) of these Conditions as if such
work were a variation by the Architect.
(iii) Any sum ascertained in respect of direct loss and/or expense
under clauses 11(6), 24 and 33(2) of these Conditions (whether
ascertained before or after the date of detennination).
(iv) The cost of materials or goods properly ordered for the Works
for which the Contractor shall have paid or for which the
Contractor is legally bound to pay, and on such payment by
the Employer and materials or goods so paid for shall become
the property of the Employer.
(v) The reasonable cost of removal under paragraph (a) of this
sub-clause.
(vi) Any direct loss and/or damage caused to the Contractor by
the detemiination.
Dele, 'minori'o11 by conir@CIOr I 17
Provided that in addition to all other remedies the Contractor upon such
delerrnination may take possession of and shall have a lien upon all
unfixed goods and materials, which may have become the property of
the Employer under clause 14 of these Conditions until payment of all
monies due to the Contractor from the Employer.
Clause 26 (1) sets out the grounds on which the contractor can deter-
mine his employment under the contract. The right of delennination is
also expressed to be "without prejudice to any other rights or remedies
which the Contractor may possess", thus preserving the contractor's
rights under any other provision of the contract and at coriumon law.
Most of the events referred to in the clause are not breaches of contract
by the employer and those that are are not necessarily repudiatory in
their effect. it the employer wrongfully prevents completion of the
contract, this is a repudiatory breach. Thus, in Smith Constr"ciion Co
Ltd v Phit Kin\, atrid [1955] MLJ 8, the employer's refusal to issue a
promised architect's certificate was held to amount to repudiation of
the contract. However, it is often a difficult question of both law and
fact whether a particular breach is repudiatory in character.
C!@14se 26(I) confers on the contractor a right to determine his
employment under the contract - not a right to treat the contract as at
an end - by serving notice on the employer or the architect by regis-
Iered post or recorded delivery. No particular fomi of notice is speci-
fled but it is suggested that it should be drafted with care and refer to
the cause of detennination in precise tenns. The detemiination takes
effect "forthwith", to upon service of the notice.
The right of detennination is once again subject to the proviso that
it must not be effected "unreasonably or vexatiously" and the coriumen-
tary on that phrase and on the service of notices generally under the
preceding clause is equally relevant : see page 78.
The grounds which give rise to a right in the contractor to detennine
his employment - some of which are not even breaches of contract -
are set out in the sub-clause. They are the following.
alleged that the employers had obstructed or intermeddled with the issue
of an interim certificate by wrtting them a letter suggesting that they
should make a further claim for another progress payment. Close con-
SUItation between architect and employer is to be expected in a contract
of this nature : see the New Zealand case of Han'ick v Nelson Cm'lion
Cons!1.11ciioii 119641 NZLR 72.
right is subject to the proviso that notice shall not be served unreasona-
bly or vexatiously : see the discussion on page 78.
CIOi!se 26(2) sets out the rights and duties of the parties after a valid
notice of determination has been given by the contractor under clause
26(I). The phrase "without prejudice to the accrued rights or remedies
of either party" is obscure but refers to, eg the contractor's right to
accept a repudiatory breach of contract by the employer in appropriate
circumstances.
Flowchart 7
Determination by contractor
START
Yes
Notice of
Yes Contrac. or may Employer
Employer serve dejauli notice slops dejaul, in
delermina, 10n bv
falls 10 pay 2611/1ai 7 d"vs coni, acior 26/11
No
Inlederes or Yes
ob, umeis certificate
No
Yes
Force
majeure
No
Ye*
201AjtBl
contingencies
No
Civil Yes
commotion
No
No No
Laie Yes
infomaiion
No
No
^
Yes
his recuon and
testing
No
Yes
Employer
bankrupt
No
Yes
Genenl
mobitisation
Arbtua. or deades
No
it just and
equi"ble
Yes
No in ated sub-contractors
27 The following provisions of this Condition shall apply where prime cost
sums are included in the Contract Bills or arise as a result of Architect's
instructions given in regard to the expenditure of provisional sums in
respect of persons to be nominated by the Architect to supply and fix
materials or goods or to execute work.
(a) Such sums shall be expended in favour of such persons as the
Architect shall instruct, and all specialists or others who are nomi-
nated by the Architect are hereby declared to be sub-contractors
employed by the Contractor and are referred to in these Conditions
as 'nominated sub-contractors'. Provided that the Architect shall not
nominate any person as a sub-contractor against whom the Con-
tractor shall make reasonable objection, or (save where the Archi-
rect and Contractor shall other otherwise agree) who will not enter ,
122
Nominated $14b-con!Factors 123
(b) The Architect shall direct the Contractor as to the total value of the
work, materials or goods executed or supplied by a nominated sub-
contractor included in the calculation of the amount stated as due
in any certificate issued under clause 30 of these Conditions and
shall forthwith infonn the nominated sub-contractor in writing of
the amount of the said total value. The sum. representing such total
value shall be paid by the Contractor to the nominated sub-contrac-
tor within 14 days of receiving from the Architect the certificate
less only a) any retention money which the Contractor may be
entitled to deduct under the tentis of the sub-contract, and (ii) any
sum to which the Contractor may be entitled in respect of del^, in
the completion of the sub-contract Works or any section thereof.
(C) Before issuing any certificate under clause 30 of these Conditions
the Architect may request the Contractor to furnish to him reason-
able proof that all amounts included in the calculation of the amount
stated as due in previous certificate in respect of the total value of
the work, materials or goods executed or supplied by any nomi-
nated sub-contractor have been duly discharged, and if the Contrac-
tor fails to comply with any such request the Architect shall issue
a certificate to that effect and thereupon the Employer may himself
pay such amounts to any nominated sub-contractor concerned and
deduct the same from any, sums due or to become due to the
Contractor.
(d) (i) The Contractor shall not grant to any nominated sub-contrac-
tor any extension of the period within which the sub-contract
Works or (where the sub-contract Works are to be completed
in sections) any section thereof is to be completed without
the wrttten consent of the Architect provided always that the
Contractor shall inforrn the Architect of any representations
made by the nominated sub-contractors as to the cause of any
delay in the progress or completion of the sub-contract Works
or of any section thereof, and that the consent of the Archi-
rect shall not be unreasonably withheld.
(ii) If any nominated sub-contractor fails to complete the sub-
contract Works or (where the sub-contract Works are to be
completed in sections) any section thereof within the period
specified in the sub-contract or within any extended time
granted by the Contractor with the wrttten consent of the
Architect, then if the same ought reasonably so to have been
completed the Architect shall certify in wrtting accordingly;
immediately upon issue the Architect shall send a duplicate
of any such certificate to the nominated sub-contractor.
I. , ,
the amount so certified. Upon such final payment, the amount named
in the appendix to these Conditions as Limit of Retention Fund
shall be reduced by the sum which bears the same ratio to the said
amount as does such sub-contractor's sub-contract price to the
Contract Sum, and save for latent defects the Contractor shall be
discharged from all liability for the work materials or goods executed
or supplied by such sub-contractor under the sub-contract to which
the payment relates.
I
(f ) Neither the existence nor the exercise of the foregoing powers nor
anything else contained in these Conditions shall render the Bin-
ployer in any way liable to any nominated sub-contractor.
(g) (i) Where the Contractor in the ordinary course of his business
directly carries out works for which prime cost sums are in-
cluded in the Contract Bills and where items of such works
are set out in the appendix to these Conditions and the Archi-
tect is prepared to receive tenders from the Contractor for
such items, then the Contractor shall be pennitted to tender
for the same or any of them but without prejudice to the
Employer's right to reject the lowest or any tender. it the
Contractor's tender is accepted, he shall not sub-let the work
or any part thereof without the consent of the Architect:
Provided that where a prime cost sum arises under Architect's
instructions issued under clause 11(3) of these Conditions it
shall be deemed for the purposes of this paragraph to have
been included in the Contract Bills and the item of work to
which it relates shall likewise be deemed to have been set out
in the appendix to these Conditions.
(ii) It shall be a conditiQ_n of any tender accepted under this
paragraph that clause I I of these Conditions shall apply in
respect of the items of work included in the tender as if for
the reference therein to the Contract Drawings and the Con-
tract Bills there were references to the equivalent documents
included in or referred to in the tender.
Where . . . the sub-contractor has entered into a direct contract and ex-
pressly undertaken a direct but limited contractual responsibility 10 the
building owner, I regard the direct contract as being inconsistent with any
assumption of responsibility that has been expressly undertaken. This does
not affect the sub-contractor's nomial liability in tort (!^101' pel'sonol injury
o1' physicol damage - author's note) but does negative the existence of the
exceptional circumstances needed for liability for economic loss.
Great care, therefore, is needed in drafting any collateral contract or
warranty agreement. Even where one exists, this does not provide an
exception to the docttine of prtvity of contract but is rather an applica-
tion of it. The rule is that each party has contractual rights only against
the party above or below him in the contractual chain. This is so even
where, as with most standard form sub-contracts, some tenns of the
main contract are incorporated by reference.
11 has also been correctly held in England that the existence of a col-
lateral contract does not affect the rights of the main contractor against
the employer. Thus, a claim under the collateral contract between the
employer and a nominated sub-contractor could not give rise to any
set-off or counterclaim against a main contractor's claim under the main
contract : George E Toyloi' & Co Ltd v G Pel'cy 71'enthom Ltd (1986)
16 BLR 15.
In the UK the use of direct warranty agreements between the Gin-
ployer and nominated sub-contractors is standard practice and an earlier
version of the current standard form was considered in the Gi'eate, ' Not-
-
Nom!'nared sub-con!Factors 129
Clause 27
The position under clause 27 may now be considered in detail, and this
is best done by breaking the clause down into an introduction and three
parts. ~
The Inti. od"ction is contained in the first six lines down to the pro-
viso in clause 271a). Pa, .t I is contained in clause 27 (b) to (f); port 2
is set out in the proviso to clause 27(a) and paragraphs co to (ix); part
3 is contained in clause 27 (g).
introduction
The clause only applies where there are prime cost (PC) sums. These
can arise in three ways :
Paragraph (i) provides that the contractor "shall not grant" any ex-
tension of time to a nominated sub-contractor without the written consent
of the architect, which must not be unreasonably withheld. That con-
sent is a condition precedent 10 the granting of an extension of lime;
and this requirement must be stepped-down in the sub-contract. The
contractor must infomi the architect of any representations which the
sub-contractor has made to him about the cause of any delay. Exact
observance of these provisions is essential.
Paragraph (ii) is badly phrased and the nature of the architect's
certificate under this clause is widely misunderstood. it requires the
architect to certify his opinion that the sub-contractor ought reasonably
to have completed his work or the relevant section within whatever
period was stated in the sub-contract or is applicable following the grant
of any extension of time by the main contractor. it should not state
what that period is, nor should it state the date by which, in the
architect's opinion, the work should have been completed. A duplicate
of the clause 27(d)(ii) certificate must be sent to the sub-contractor.
This certificate is a condition precedent to the contractor deducting "any
sum to which [he] may be entitled in respect of delay in completion"
under clause 27(b).
CIQuse 27(e) provides the machinery whereby the architect can se-
cure early final payment to a nominated sub-contractor. Early final
payment is not mandatory. If the architect wishes to ensure final pay-
merit to a nominated sub-contractor before issuing the final certificate
he may include its amount in an interim certificate, but only "if such
sub-contractor has satisfactorily indemnified the Contractor against any
latent defects" in the sub-contract works, for which the contractor remains
Normina!ed sub-contractors 133
from nominating "any person . . . who will not enter into a su -con-
tract" which includes the tentis set out in paragraphs (i) to (ix). The. re-
sponsibility for ensuring that the eventual sub-contract is coinpati e
with the provisions of this sub-clause is that of the contractor who niust
see that the actual sub-contract accords with this part of the proviso.
Pal. agi'ap/I (i) is so framed as to place' the sub-contractor under a
similar obligation to that undertaken by the contractor under clause I(I. ).
The sub-contract must, therefore, provide that the sub-contractor wi
carry out and complete the sub-contract works to the satisfaction o
both the contractor and the architect (although in practice this dual
requirement may have no significance) and in conformity with all
reasonable directions and requirements of the contractor under the su -
contract.
Poi. agi'ap/? (17) is intended to ensure that the relevant main contract
provisions are incorporated into the sub-contract, save for clause 201Al
Of applicable). it clause 20[A] applies then the contractor must Insure
the full value of all work and materials - including those of any
nominated sub-contractor - against loss or damage by the stated ris s.
Pal'o81'@pit (in) is intended to ensure that the sub-contract mirrors
the indemnities given by the contractor and for the same liabilities (see
clauses 7 and 18), while paragraph (Iv) is to make clear that the
nominated sub-contractor accepts liability for claims caused by the sub-
contractor's negligence, omission or default and against 'any misuse,
. . . of any scaffolding or other plant", backed up by corresponding in-'
surance and an express indemnity.
The contents of poiugi. dpi? (i\,) are self-explanatory and tie in with
the contractor's obligations, including the provisions of clause 27(d). it
is essential that any supporting sub-contract should define the causes o
delay entitling the sub-contractor to an extension of time to cover delay
caused by the main contractor or those for whom he is responsible and
those events in clause 23 which entitle the contractor to an extension of
time.
Fomgi. aph (vi) is to ensure that the sub-contract mirrors the provi-
sions of clause 27(b) and (d)(Ii), and it envisages that the sub-contract
will (unusually) provide either for liquidated damages or for the recov-
ery of general damages. Where the sub-contract stipulates liquidated
damages they will almost invariably operate as a limitation on the
nominated sub-contractor's liability.
Paing, .aph (vii) ensures that the sub-contract reflects the method of
payment prescribed in the main contract, while pal'ag, 'aph (vin) is
intended to deal with retention money on the sub-contract works and
the relation of that retention to the main contract provisions. The net
result is that there is only one retention held by the employer but there
are several interests therein, to those of the contractor and the various
nominated sub-contractors.
Under clause 9, the architect and his representatives are given a rights
of access to the site and workshops and other places of the contractor.
Noin?mored sub-conr, actoi. s 135
it the item is not in the Contract Bills as a PC sum, but the architect
wishes to nominate a sub-contractor to carry out work which is the
subject of a provisional sum, the effect of the proviso is that the archi-
Iect must allow the contractor the benefit of clause 27(g)(I). The con-
tractor thus has the opportunity of competing for such work.
it the contractor is successful in his tender, he must not sub-let the
work without the architect's consent and there is no provision that such
consent should not be unreasonably withheld.
CIOuse 27(g)(ii) tries to make it clear how variations, etc on works
for which the contractor's tender has been successful are to be valued.
Clause I I is made applicable, but the references in that clause to the
Contract Drawings and Contract Bills are to be read as "references to
the equivalent documents included or referred to in the tender".
Clause 28
N minate supplie s
136
.
Clause 28 deals with nominated suppliers and, in its own way, is just
as complex as clause 27.1t also opens with an introduction which states
that its provisions only apply where a PC sum occurs in respect of any
matei'ials o1' goods to be fixed by the contractor.
This will be the case where (1) PC sums are included in the Contract
Bills; of (2) where they arise as a result of an architect's instruction on
provisional sum expenditure under clause 11(3); or (3) as a result of a
variation instruction. in the last two cases the instruction will fall to be
valued under clause 11.
Although not expressly stated, nominated suppliers have no contrac-
Iual relationship with the employer; the contract of sale is with the
contractor : see clause 28(b).
Clause 28(@) defines prime cost for purposes of this clause as "the
net cost to be deftayed as a prime cost after deducting any trade or
other discount and shall include the cost of packing, carriage and
delivery". The proviso is important. Where, in the opinion of the archi-
tect, the contractor has incwrred expenses for special packing or
cadage, these are to be allowed as part of the sums actually paid by
the contractor.
Clause 28(b) imposes a duty on the architect to nominate a supplier.
it is clear from the use of the word "shall" in this sub-clause that the
architect is obliged to issue instructions on expending PC sums, etc.
Indeed, by analogy with the case law on nominated sub-contractors
already discussed (and in particular the case of TA Bickerton & Son Ltd
v North-west Metropolitan Regional Hospi!o1 Board 119701 I All ER
1039) if a first nomination fails before the nominated supply work is
completed, there is a duty on the architect to Tenominate and the con-
sequences of his failure to do so are the same.
All specialists, tradesmen or others so nominated by the architect are
"nominated suppliers" and are expressly stated to be ' suppliers to the
contractor .
The proviso limits the architect's powers to nominate as suppliers to
those who will enter into a supply contract with the contractor which
includes the ternis set out in paragraphs (i) to (in), unless the architect
and the contractor agree otherwise. The ternis set out are not to be the
only tenns of the contract which will, of course, be subject to the Sale
of Goods Ordinance 1957. The practical effect of this provision is that
if a supplier whom the architect wishes to nominate refuses to accept
any or all of the ternis set out, the contractor camiot be forced to accept
the nomination. The contractor has no right to make reasonable objec-
tion to a proposed noriimated supplier as he does in the case of pro-
posed nominated sub-contractors.
138 Clause 28
29 The Contractor shall pennit the execution of work not fomiing part of
this Contract by artists, tradesmen or others engaged by the Employer.
Every such person shall for the purposes of clause 18 of these Condi-
tions be deemed to be a person for whom the Employer is responsible
and not to be a sub-contractor.
139
140 Clause 29
Delays caused by these artists, tradesmen and others may give rise to
a claim for extension of time under clause 23(h) and to a claim for
direct loss and/or expense for any disturbance of regular progress of the
Works under clause 24(I)(d). Lengthy delay caused by them may be a
ground for determination by the contractor under clause 26(I)(c)(vi).
Clause 30
141
142 Clause 30
(a) The sum of the amount paid to the Contractor under Interim
Certificate and the amount named in the said appendix as Limit of
Retention Fund, and
(b) The Contract Sum adjusted as necessary in accordance with the
teams of these Conditions,
and the difference (if any) between the two sums shall be expressed in
the said certificate as a balance due to the Contractor from the Em-
ployer or to the Employer from the Contractor as the case may be.
Subject to any deductions authorised by these Conditions, the said balance
as from the fourteenth day after presentation of the Final Certificate by
the Contractor to the Employer shall be a debt payable by the Employer
to the Contractor or as the case may be as from the fourteenth day after
issue of the Final Certificate shall be a debt payable by the Contractor
to the Employer.
(7) Unless written request to concur in the appointment of an arbitrator
shall have been given under clause 34 of these Conditions by either
party before the Final Certificate has been issued or by the Contractor
within 14 days after such issue, the said certificate shall be conclusive
evidence in any proceedings arising out of this Contract (whether by
arbitration under clause 34 of these Conditions or otherwise) that the
Works have been properly carried out and completed in accordance with
the tentis of this Contract and that any necessary effect has been given
to all the tentis of this Contract which require an adjusttnent to be made
to the Contract Sum, except and in so far as any sum mentioned in the
said certificate is erroneous by reason of:
(a) Fraud, dishonesty or fraudulent concealment relating to the Works,
or any part thereof, or to any matter dealt with in the said centfi-
cate; or
(b) Any defect (including any omission) in the Works, or any part
thereof which reasonable inspection or examination at any reason-
able time during the carrying out of the Works or before the issue
of the said certificate would not have disclosed; or
(c) Ally accidental inclusion or exclusion or any work, materials goods
or figure in any computation or, any arithmetical error in any
computation.
(8) Save as aforesaid no certificate of the Architect shall of itself be con-
clusive evidence that any works materials or goods to which it relates
are in accordance with this Contract.
CIO"se 30 regulates payment under the contract. it sets out the way in
which the Contract Sum, as adjusted by the various provisions in the
contract, is to be paid over to the contractor.
144 Clause 30
Clause 30(I) provides for the issue of interim certificates by the archi-
^ct. both, ^;^^:4'I^:^^~" ,:'^;;!,':rt',:;;:',^;"
If no period is stated there, they must be issued at intervals of a calen-
dar month. The architect's failure to issue interim certificates is a breach
of contract for which the employer is liable. in England it has been
held that the mere signature by the architect of a certificate does not
amount to its issue since the dictionary meaning of the transitive verb
"to issue" means, inte, ' offa, "to send forth; to give or send out authori-
tatively or officially; to put into circulation".
This was so held by the English High Court in London Bo, ough of
Camden v Thomas MCInei. ney & Sons Ltd (1986) 9 ConLR 99 where
the contract was in ternis identical to FAM fomi. The architect signed
certificates but they were never sent out because a subsequent mspec-
tion revealed defective work. On the facts, the signing of the final
certificate did not constitute giving of the opinion under clause 30(7)
that the Works had been "properly caded out and completed in accor-
dance with the tenns of this contract". Since it was not issued, it was
of no effect. A final or other certificate only Fomes to life as a docu-,
merit which is legally enforceable as a certificate when the architect
issues it as required by clause 3(8).
The issue of an interim certificate to the contractor (see clause 3(8))
does not of itself entitle him to payment, but it is a condition precedent
to payment : Ling Heng Toh Co v Borneo Development Coino, .ajion
Sdn Bhd [1973] I MLJ 23. The period for bonouting the certificate
dates from its PI'esentotion to the employer, which presumably means
its actual receipt by him. The contractor is then entitled to payment
within the period named in the Appendix, which will be 14 days from
presentation unless a different period is specified.
Clause 30(I ) refers to the contractor being "entitled to payment there-
for" within the named period, to payment of the amount certified by the
architect as due to him. in L"benhom Fide!^71^s & Investment Co Lid v
South Feinbrokeshire District Council (1986) 6 ConLR 85, the English
Court of Appeal held that this means the contractor is entitled to pay-
merit of the sum actually stated in the interim certificate to be due to
the contractor from the employer, even if the certificate contains a latent
or patent error. (The clause of the contract in issue was in identical
terms to clause 30. ) in that case, a negligent architect made invalid
deductions on the face of interim certificates and the employer refused
to pay sums in excess of the amounts actually shown as due. This was
held not to be a breach of contract.
Clause 30(I) merely requires the employer to pay the sum stated in
the certificate as being due to the contractor and by doing fulfils his
Cer!ofic@!es and payments 145
contracttial obligation. Where a certificate is erroneous, the contractor's
remedy is to request the architect to make an adjustment in another
certificate; or if he declines to do so, to take the dispute to arbitration.
in their nature, interim certificates are only an approximate valuation
of the work done and the amount of any interim certificate is subject to
adjustment in subsequent certificates. By issuing an interim certificate
for payment the architect is not thereby expressing a final view of the
state of the Works. He is entitled to take a fresh view each time he
issues an interim certificate and his opinion does not become conclu-
SIve until he issues the final certificate.
11 was also emphasized that the issue of an interim certificate is a
condition precedent to payment under the contract and so the contrac-
tors were not entitled to recover the full amount which they alleged as
properly due to .them either on the basis of an implied term that the
employer would properly secure the architect's performance of his duties
under the contract or otherwise,
The employer's obligation, then, is to pay the amount stated as due
within (usually) 14 days from rece!77t of the interim certificate, to he
has a period of grace. The contractor's entitlement to payment is sub-
ject to the employer's contractual rights of deduction, eg liquidated
damages under clause 22, and any tight of set-off. Mere non-payment
of a certificate does not of itself entitle the contractor to treat the contract
as at an end and if he does so by abandoning the contract he will be
treated as himself being guilty of repudiatory breach : Yong Mok Hin v
United Malay Sugar Industries Ltd 119661 21v^it, I 286.
The English case of KITby & Gay/'ord Ltd v Sel^hco"rt Ltd (1976) 3
BLR 104 is of interest in connection with the issue of interim certifi-
cates under clause 30(I). There, a contract for alteration works was in
ternis identical to the PAK^I fomi and the employer challenged the sixth
interim certificate, contending that no written variation orders had been
given. He withheld payment. The Court of Appeal found for the
contractor, holding that in the absence of proper evidence that the
variations were not properly ordered, the interim certificate must be
honoured, pending practical completion.
"So long as a certificate is good on the face of it and is within the
authority given by the contract [to the architect] then it is in accordance
with the conditions. it must be honoured" said Lord Denning MR. This
does not mean that a certificate is as good as cash, and if an employer
raises a bona lide arguable contention that an interim certificate may
have been over-valued, he is entitled to have the issue arbitrated and
the contractor will not necessarily be entitled to sunrrnary judgment,
when he would be entitled to interest for late payment : see Contracts
Act 1950, section 74, illustration (n) and Woon Hoe Kon & Sons Sdn
Bhd v Bunchr Raya Development Bhd [1973] I MLJ 60.
To arrive at the amount due in interim certificates, interni valuations
are to be made by the quantity surveyor, whenever the architect consid-
ers them mecess@17. interim valuations are not, therefore, mandatory,
I46 Clause 30
but even where the architect dispenses with them he is still under the
duty laid down in clause 30(2) to include what that sub-clause says an
interim certificate must cover.
If the contractor feels that an interim certificate has not been prop-
erly prepared, he can request the architect to make an adjustment in the
next interim certificate, or give notice of arbitration under clause 34.
However, no interim certificate is final and conclusive (see clause 30(8))
ancl is subject to review in the final certificate. Consequently, it is
doubtful whether it is worthwhile to challenge an interim certificate b
giving notice of arbitration.
Clause 30(2) lays down what matters are to be covered by an in-
tenm certificate, and two items are to be included. The sub-clause is
stated to be "subject to any agreement between the parties as to stage
aments"andth'
payments , and this envisages thath
theh I
employer and the contractor may
agree that payments are not to be due until certain fixed stages of the
Works are completed. in that case, clause 30(2) would have to be read
subject to the agreement for stage payments.
Under clause 30(2) the two items to be included are :
Retention
The retention sum in this case is an existing debt and in fact an existing
indebted sum that involves the payment, notionally and irresistibly PUTSuant
to an interim certificate issued by the architect, by the garnishee to the
judgment-debtor and the latter's payment in turn back 10 the garnishee for
retention . . . with the garnishee holding the money as trustee for the judg-
merit-debtor.
designated bank account as has been held to his duty. That duty can
be enforced by injunction.
it is a moot point as to whether the contractor is entitled to interest
on the retention moneys; it is said that since the employer is not obliged
to invest the retention fund there is no obligation on him to pay inter-
est. However, it is a basic principle of equity that a trustee is not
permitted to benefit from trust moneys and in view of the silence of the
contract on this matter it is suggested that the contractor is entitled to
interest earned on retention moneys.
Although the retention is trust money, the employer is given certain
rights of recourse to it under the tenns of the contract. Clause 30(4)(a)
states that, notwithstanding the employer's fiduciary position, he is
entitled "to have recourse thereto from time 10 time for payment of any
amount which he is entitled under the provisions of this contract to
deduct from any sum due or to become due to the Contractor".
The employer's right of recourse under the ternis of the contract
appears to be confined to the following :
(1) His rights under clause 2(I) to reimburse himself for the con-
tractor's failure to carry out valid architect's instructions when he
has exercised his default powers to employ others'
(2) The recovery of liquidated and ascertained damages under clause
22.
(3) Deductions under clause 15(2) if he elects not to have defects
made good by the contractor.
(4) The recovery of insurance premiums paid under clause 19(3) and
clause 201Al(I) if the contractor fails to insure as required.
(5) Direct payments to nominated sub-contractors under clause 27(c).
in Lee Kam Ch"n v Sy@rikot KMk"h Mai" Sdn Bhd 119881 I CLI 52 the
court also expressed the view that there was "no doubt that for dam-
ages and loss to be quantified by a court or an arbitrator later, for alleged
breach of contract on the parr of the [contractor, the employer] would
have the right to dip into such retention money for satisfaction" assum-
ing, of course, that the retention had not been paid over.
Paragraph (b) provides that one inoiety, to half of the retention
percentage is payable on the issue of the practical completion certifi-
cate under clause 15. This payment is against the architect's certificate
and is on the same tenns as for interim certificates under clause 30(I).
Paregroph (c) deals with the release of the second half of the Teten-
tion percentage. Once the contractor's liability to remedy defects under
clause 15 is discharged, the second half of the percentage is released to
him. This occurs either when the defects liability period expires or when
the architect issues his Certificate of Completion of Making Good
Defects whichever is the later.
The architect must then issue a certificate releasing the residue and
the contractor is entitled to payment on the same conditions as for interim
certificates under clause 30( I). Thus, on the assumption that all defects
150 Clause 30
are remedied before the expiry of the defects liability period, six months
from the date of practical coinpletion is the niaximum time that can
elapse before payment becomes due, unless a longer defects 11a i ity
period has been specified in the Appendix.
Each of these amounts must be ascertained and set against the appro-
prtaie PC or Provisional Sum and the Contract Sum is adjusted accord-
ingly. The sub-clause specifically refers to the contractor s normal right
to insert a profit percentage in respect of PC Sums, but is not a coin-
prehensive code.
The proviso that "no deduction shall be made in respect of any
damages paid or allowed to the Contractor by any sub-contractor or
supplier" is self-explanatory since such settlements are not relevant to
the adjustment of the Contract Sum.
Clot, se 30(6) provides a timetable for the issue of the final certificate
which is the last certificate issued by the architect in connection with
the contract. On its issue, the architect becomes functus offICio, to his
authotity under the contract is at an end unless notice of arbitration has
been given within the permitted time under clause 30(7), and he is
precluded from issuing any further valid certificates.
The final certificate should be issued "as soon as practicable", re so
soon as the necessary calculations have been carried out but in any
event the final certificate must be issued not later than three months
after the occurrence of whichever of the following three events occurs
last :
given under clause 34 by either party before its issue or by the contrac-
tor within 14 days after its issue, the final certificate "shall be conclu-
sive evidence in any proceedings arising out of this Contract . . . that
the Works have been properly carried out and completed in accordance
with the tenns of this Contract and that any, necessary effect has been
given to all the terms of this Contract which require an adjustment to
be made to the Contract Sum . . .".
The effect of the final certificate is not, therefore, merely financial
and the meaning of the words "conclusive evidence in any proceedings
arising out of this contract" was considered by the House of Lords in
P & M Ko\'e Lid v Hosiei' & DJtkiitso, ? Ltd 119721 2 All ER 121 where
their lordships held, by a maiotity, that these words prevented any further
legal action, including legal proceedings started long before the centfi-
cate was issued.
This decision has been followed in Malaysia on many occasions, eg
in Shell Yuan PCi v Doro Wee Hood Teck 119761 I MLJ 16, which is
also authority for the view that it is for the architect to delennine the
form and nature of the final certificate as he thinks fit.
'i'he final certificate is "conclusive evidence" not only of the adjust-
merit of the Contract Sum, but also "that the Works have been properly
carried out and completed in accordance with the terms of this Con-
tract" which is, to say the least, hardly in the employer's interest since
effectiveIy it excuses the contractor from liability for what could be *
serious breaches of contract. although the exceptions discussed below-'
may in fact be of some assistance.
in fact, in the light of clause 30 (7)(b) it is clear that the contractor's
liability for latent defects is preserved and, so far as defective work is
concerned, the final certificate will only relieve the contractor of nabil-
ity in respect of patent defects, to those which reasonable inspection
ought to have revealed.
The final certificate incorporates the value of all interim certificates.
it seems that even if the quantification of the balance due under it is
mistakenly based on sums certified rather than sums certified and paid,
the certificate is nonetheless not reviewable by the arbitrator under clause
34 because it is "conclusive evidence that any necessary effect has been
given to. all the terms of this Contract which require an adjustment to
the Contract Sum".
As between the employer and the contractor, therefore, the final
certificate becomes conclusive evidence of the matters specified in clause
30(7) unless arbitration proceedings have been commenced as speci-
fled. To avoid its conclusive ness the employer must make a request to
concur in the appoininient of an arbitrator prior to its issue.
The exceptions relate only to financial matters - "except and in so
far as any sum mentioned in the said certificate is erroneous by reason
of" :
(2) any defect in the whole or part of the Works which reasonable
inspection ought to have revealed;
(3) any accidental inclusion or exclusion of any work, materials, goods
or figure in any computation or any arithmetical error in any
computation.
Clanse 30(8) provides that apart from the conclusive nature ascribed to
the final certificate by clause 30(7), no other certificate (interim centfi-
cate, certificate of practical completion, certificate of making good
defects, etc) is considered conclusive evidence that any work, materials
or goods are in accordance with the contract. This emphasizes the
different nature and crucial importance of the final certificate.
Clause 31
O tbrea f hostilities
(2) The Architect may within 14 da}, s after a notice under this Con:
dition shall have been given or received by the Employer issue instruc-
tions to the Contractor requiring tile execution of such protective work
as shall be specified therein and/or the continuation of the Works up to
points of stoppage to be specified therein, and the Contractor shall comply
with such instructions as if the notice of determination had not been
given.
Provided that if the Contractor shall for reasons beyond his control be
prevented from completing the work to which the said instructions relate
within 3 months from the date on which the instructions were issued, he
may abondon such work.
(3) Upon the expiration of 14 days from the date on which a notice of
determination shall have been given or received by the Employer under
this Condition or where works are required by the Architect under the
preceding sub-clause upon completion or abandonment as the case may
be of such works, the provisions of sub-clause (2) (except sub-para-
graph (vi) of paragraph (b)) of clause 26 of these Conditions shall apply,
and the Contractor shall also be paid by the Employer the value of any
work executed PUTSuant to instructions given under sub-clause (2) of
this clause, the value being ascertained in accordance with clause I I'(4)
of these Conditions as if such work were a variation required b the
Architect.
*'Footnote - Tile pal. lies he I. eio ill Ihe eveni of Ihe owlbi'eok of hos!ithi^s
in@), at oily tin?e by ogi'eeme, ?I betH, een Ihem rimke such Iui'Ihei' o1' o1hei'
ai'I'd 118enients OS lirey Ihink fir 10 meei 1/1e cii'cwmsioiices.
154
0111bituk o1' fros!Jinits 155
War da age
32 (1) in the event of the Works or any part thereof or any unfixed ina-
tenals or goods intended for, delivered to and placed on or adjacent to
the Works sustaining war damage then notwithstanding anything ex-
pressed or implied elsewhere in this Contract:
(a) The occurrence of such war damage shall be disregarded in coin-
puting any amounts payable to the Contractor under or by virtue of
this Contract.
(b) The Architect in^, issue instructions requiring the Contractor to
remove and/or dispose of any debris and/or damaged work and/or
to execute such protective work as shall be specified.
(c) The Contractor shall reinstate or make good such war damage and
shall proceed with the carrying out and completion of the Works,
and the Architect shall grant to the Contractor a fair and reasonable
extension of time for completion of the Works.
(d) The renioval and disposal of debris or damaged work, the execu-
lion of protective works and the reinstatement and making good of
such war damage shall be deemed to be a variation required by the
Architect.
(2) If at any time after the occurrence of war damage as aforesaid either
party serves notice of determination under clause 31 of these Condi-
tions, the expression 'protective work' as used in the said clause shall
in such case be deemed to include any matters in respect of which the
Architect can issue instructions under paragraph (b) sub-clause (1) of
this Condition and any instructions issued under the said paragraph prior
to the date on which notice of detennination is given or received by the
Employer and which shall not then have been completely complied with
shall be deemed to have been given under clause 31(2) of these Condi-
tions.
156
W(11 dunioge 157
Anti uities
33 (1) All fossils, antiquities and other objects of interest or value which
may be found on the site or in excavating the sanie during the progress
of the work shall become the properly of the Employer. The Contractor
shall carefully take out and preserve all such objects and shall jinmedi-
alely or as soon as conveniently may be after the discovery of such
articles deliver the same into the possession of the Architect or of the
clerk of works uncleaned and as excavated.
158
Clause 34
Arbitration
This clause provides for the settlement of disputes under the contract
by arbitration. in the 1985 reprint of the form, it consists of two sub-
clauses, but in the reprint of 1986 three sub-clauses have been omitted,
and sub-clause (I ) stands alone. This commentary covers the clause in
its complete fomi and the wrtter has been advised that the omissions in
the 1986 reprint were unintended.
Clause 34(I) is the arbitration agreement and is wide in its scope.
Under its provisions there is referred to arbitration "any dispute or
difference between the employer or architect on his behalf and the
Contractor" which arises during the progress or after the completion or
abandonment of the works "as to any matter or thing of whatsoever
nature arising thereunder or in connection therewith' . The arbitrator's.
jurisdiction is broad and specifically extends to matters left to the:
architect's discretion, the withholding by the architect of ally certificate
to which the contractor alleges he is entitled, the measurement and
valuation of the Works as mentioned in clause 30(5)(a), and the rights
and liabilities of the parties on detemnination (clauses 25 and 26),
outbreak of hostilities (clause 31 ) or occurrence of war damage (clause
32).
The second paragraph of the sub-clause contains the machinery for
commencing arbitration. When a dispute or difference arises, either party
may serve written notice on the other that the dispute or difference be
referred to the arbitration of a person to be agreed. This is the notice to
concur in the appointment of an arbitrator, and while no special fomi
is required it is usual for the person making the request to submit to the
other party a list of at least three qualified persons proposed as arbitra-
tor, from which one may be selected. Failing agreement, or in the
absence of a reply or reluctance to act by the other party, after 14 days
from the dote of the notice to concur in the appointment of an arbitta-
tor, the person seeking arbitration can apply to the President or Vice-
President of Pertubuhan A1citek Malaysia (the Malaysian Association of
Architects) to appoint an arbitrator. Properly used, this provision pre-
vents its objective being frustrated.
Upon appointment - whether by agreement or in default by the
appointor - the arbitrator is to commence the arbitration proceedings
"with despatch" in accordance with the provisions of the Arbitration
Act 1952, as revised in 1972. The final sentence is important since the
parties agree that the arbitrator may proceed ex pal'Ie, to in the absence
A1'bitr@!ion 161
of the other party, should either party fail to attend any meeting or
hearing after due notice.
Clause 34(2) (which, as noted above, is omitted in the 1986 reprint
of the fomi) is important if it is applicable since it places a limitation
on the commencement of the arbitration proceedings. Subject to the
exceptions discussed below, the arbitration reference camot be opened
"until after practical completion or alleged practical completion of the
Works or teamination or alleged termination of the contractor's em-
ployment ~ or abandonment of the Works' unless both parties consent
in writing. it should be noted that the architect is empowered to give
such consent on the employer s behalf.
Immediate arbitration is available in the following cases :
(1) The appointment of another architect or quantity surveyor under
Articles 3 or 4 on the death or ceasing to act of the named archi-
rect or quantity surveyor.
(2) Whether or not the issue of an architect's instruction is Ginpow-
ered by the contract, to the correctness of the architect s reply
when the contractor invokes clause 2(2).
(3) The alleged improper withholding of any certificate. Immediate
arbitration is appropriate, for example, if the contractor does not
receive an interim certificate.
(4) The alleged improper content of any certificate or, to quote the
contract wording "whether a certificate is not in accordance with
these Conditions". For example, if an interim certificate is alleged
to be undervalued and the architect has refused to adjust it.
(5) Ally matter arising under clause 31 (outbreak of hostilities) or
clause 32 (war damage).
The coriumon thread running through these matters is that such disputes
must, of their very nature, be settled rapidly.
Clause 34(3) - which is also omitted from the 1986 reprint - is
significant, since it enhances the powers of the arbitrator and, in effect,
enables him to substitute his own opinions and decisions for those of
the architect (or quantity surveyor) acting under the contract and con-
fors on him powers to "open up, review and revise any certificate,
opinion, decision, requirement or notice which would not extend to
the courts if the much-discussed English case of Northern Regional
Health Authority v Derek Crouch Construction Ltd (1986) 26 BLR I is
correct. See also the Singapore case of Central Provident Fund Board
v HO Bock Kee (1981) 17 BLR 21.
The arbitrator camot, however, go behind the final certificate which
is, by clause 30(7), made final and conclusive, nor can he review the
validity of an instruction acted upon by the contractor in reliance on
the architect's reply under clause 2(2) since in those circumstances the
instruction is "deemed for all the purposes of this Contract to have
been Ginpowered by" the clause named by the architect.
Clawse 30(4) - which is again ontitted in the 1986 reprint of the
forrn - states that the arbitrator's award is final and binding, which
162 Clause 34
would in any event otherwise be the case under the provisions of the
Arbitration Act 1952.
A grave practical defect in clause 30 is its failure to incorporate any
procedural rules governing the conduct of the arbitration, and this is a
matter with which the appointed arbitrator should deal as a condition of
his acceptance of the appointment.
Index
Architect (cont'd)
entitlements of,
Abandonment access to work, to, 35
determination of engagement, as to,
effect on payment. 2
10
non-payment, for, 145 79
outbreak of hostilities, upon, 154 possession, to defer giving,
pertomiance, of, 2 func!"s Qincio, when, 84, 151
Access instructions of,
clause on, 35 authorised under contract, to be, 20
site, to, see POSSESSION challenging validity of, 20
sub-contractor's premises, to, 35 clause on issuance of, 18
works, to, 35 completion of work, to postpone, 81
Agent compliance to be "forthwith", 20
foreman as, 34 dismissal of person from site, as to,
Antiquities 31,32
clause on, 158 expenditure of PC sums, as to, 42
contractor's obligations as to, 158 failure to comply with, 19-20
loss and/or expense for removing, 158 inspection of materials and goods,
ownership of, 158 as to, 30--31
Arbitration insure, to, 68
agreement, 160 late, extension of time for, 94
arbitrator, oral,
confimiation of, 21
appointtnent of, 160
effect of, 21
jurisdiction of, 160
powers of, to review, 161 restrospective validity of, 21
award of, binding effect of, 161-162 protective works, as to, 155, 156
clause on, 159 remedy defects, to, 55
commencement of, limits on tune removal of defective materials and
for, 161 goods, as to, 31-32
"with despatch", 160 review of, by arbitration, 161
notice of, 160 substitution of materials and goods
settlement of disputes by, 159 as to, 31
subjects of, 161 variations, as to, see VARIATIONS
time for commencement of, 160--161 writing, in, 20
Architect interim certificates, dispensing with,
clerk of work's directions, confirma- 145-146
lion by, 37 invalid deductions by, effect of, 144
death, 9 name and address in article 3.9
extension of time by, see errsNsioN notice to, see NoncE (architect, to)
OF TIME obligations of,
discrepancies in contract documents, act impartialy, to, 10
correct, to, 17 ascertain loss andor expense, to,
notice to, 17 101-102
163
164 111de. \
Employer (cont'd)
licensees of,
delay by, 95.98, 104, 140 Final certificate
responsibility for, 139 conclusive ness of, 15
obligations of, challenging, 152-153
completion of "relevant part", as to effect of, 152
payment of, 59^10 liquidated damages, on, effect of,
interest on retention money, to pay, 84-85
149 review of, by arbitration, 161
royalties, as to payment of, 33 signing and issuance of, importance of,
144
prtvity between sub-contractor and,
127-128 statements in, 151
successor architect, failure to nominate, time for issuing, 151
9 Force majeure, 92,156
unfixed materials and goods, owner- Foreman-in-charge
ship of, 51-52 agent of contractor, 34
vicarious liability for clerk of works, clause on, 34
36-37 "competent", to be, 34
warranties by sub-contractor to, 127 removal of, 34
Entire contract, see also PERFORMANCE
meaning, 2
performance,
abandonment of, 2 implied terms
payment for, 2-3 completion of work, as to postpone-
prevention of, 3 merit of, 81
quantum menut, 3 custom, by, 4
substantial, 2 materials, goods and wormanship, a
Express term, 4 to, 30
Extension of time PAMjlSM 69, in, see pan/ISM 69
cause of delay, contractor to give, 90 (implied tenns in)
clause on, 87 reasonable diligence by architect, as t
completion of works, after, 91 24
decision as to, review of, 91 statute, by, 4
effect of, 88 Injury to persons or property
events justifying, clause on, 64
employer's licensees, delay by, 95, indemnity by contractor,
98, 140 extent of, 67
exceptionany inclement weather, hails of, 64
92-93 limitation period, 65
force majeure, 92, 156 negligence of employer, resulting fro
insurance contingencies, 93 6465
labour and materials, inability to "property real or personal", 65
obtain, 98 Innominate term
late infomiation by architect, 25 meaning, 4
late instructions by architect, 94 Institution of Surveyors of Malaysia
nominated sub-contractor, delay by, ("ISM"), I
95, 129 insurance
Tenomination of sub-contractor, clauses on, 66, 70
delay in, 130 contingencies, extortsion of time for,
stokes, 93 contractor's liability,
tests and inspection showing confor- date for cessation of, 54
inity with contract, 31, 98 extent of, 67
inherent power of architect as to, 88 "full value", importance of, 74, 7
' interference with grant of, 10 now arising, 68
1681ndex
W
Terms of contract (cont'd)
innominate, 4
War
interpretation of, 48 compensation for damage by, 156
warranty, 4 extension of time because of, 93,157
war damage,
V clause on, 156
meaning, 156-157
Variations variations resulting from, 156
addition, omission or substitution of Warranty
works, by, 31,41 meaning, 4
Weather
clause on, 38
extension of time because of, 92-93
contractor's method of working, 40
Work
corrections of contract bills, 48
cost of, included in interim certificates acceleration of progress of, 92
44, 147 access to, 35
discrepancies in contract documents, completion of,
17 late, liquidated damages for, 82
- effect on contract, 40 "on or before" completion date,
80-81
extent and nature of, limits. of, 40-41
loss and/or expense arising from, 45' postponement of, 81
meaning, 40 "regularly and diligently", 80
measurement and valuation, failure as to, 111
defective, failure to remove, I I I
quantity surveyor, by, 43
rules for, 44 description, uses of, 7
measurement and valuation, time for
number of, 41
reinstatement work, completion of, 150
fire, resulting from, 75.77 sectional completion of, see SECnoNAL
COMPLETION
war damage, resulting from, 156
removal of work, materials and goods, suspension of,
by, 41 contractor, by, 110
wrtting, in, 40,41 employer, by, 119
Vouchers war damage to,
day-work, 44 compensation for, 156
materials and goods, as to, 30-31 "war damage", meaning, 156-157