Vous êtes sur la page 1sur 290

Operation Manual for Platforming Process Unit 0-0800

CCR Section JGC DOC NO. S-312-1230-001


SHEET 1 OF
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 2 OF

Contents

1. GENERAL DESCRIPTION................................................................................................
1.1 Plant Duty......................................................................................................................
1.2 Discussion of Process.....................................................................................................
1.2.1 Catalyst...................................................................................................................
1.2.2 Chemistry................................................................................................................
1.2.3 Catalyst regeneration circuit principles....................................................................
1.3 Design Basis for Feeds and Products..............................................................................
1.3.1 Feeds.......................................................................................................................
1.3.2 Products..................................................................................................................
1.4 Material Balance / B.L. Conditions................................................................................
1.5 Utilities and Chemical Requirements..............................................................................
1.5.1 Utilities requirements...............................................................................................
1.5.2 Chemical requirements............................................................................................
2. OPERATING CONDITIONS AND CONTROLS...............................................................
2.1 Discussion of Process Variables......................................................................................
2.1.1 Catalyst circulation rate...........................................................................................
2.1.2 Burn zone oxygen....................................................................................................
2.1.3 Spent catalyst coke..................................................................................................
2.1.4 Burn zone gas flow..................................................................................................
2.1.5 Burn zone bed/reheat zone bed temperature.............................................................
2.1.6 Regeneration tower pressure....................................................................................
2.1.7 Chlorination gas flow..............................................................................................
2.1.8 Regeneration catalyst chloride.................................................................................
2.1.9 Drying air flow........................................................................................................
2.1.10 Cooling air flow.....................................................................................................
2.1.11 Reduction gas flow................................................................................................
2.1.12 Zone inlet temperatures..........................................................................................
2.1.13 Lift gas flow..........................................................................................................
2.1.14 L-Valve assembly inlet differential pressure...........................................................
2.1.15 Elutriation gas flow...............................................................................................
2.2 Process Flow and Control...............................................................................................
2.2.1 Catalyst flow control...............................................................................................
2.2.1.1 Catalyst flow pushbutton..................................................................................
2.2.1.2 Catalyst circulation rate setpoint......................................................................
2.2.1.3 Spent catalyst lift rate limiter............................................................................
2.2.2 Lock hopper sequence..............................................................................................
2.2.2.1 Lock hopper cycle time.....................................................................................
2.2.2.2 Long cycle alarm..............................................................................................
2.2.2.3 Abnormal unload/load alarms...........................................................................
2.2.2.4 Lock hopper cycle counter................................................................................
2.2.2.5 Unload/load timers...........................................................................................
2.2.2.6 Lock hopper level switch malfunction alarm.....................................................
2.2.2.7 Lock hopper equalization valve alarm..............................................................
2.2.2.8 Initial cycle sequence........................................................................................
2.2.3 Makeup valve..........................................................................................................
2.2.4 Isolation systems (Figures 2.2-12, 2.2-13, and 2.2-14)............................................
2.2.5 Catalyst flow interrupt systems...............................................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 3 OF

2.2.6 Regenerated catalyst lift line valve...........................................................................


2.2.7 Regeneration systems (Figure 2.2-15)......................................................................
2.2.7.1 Regenerator run-stop pushbutton......................................................................
2.2.7.2 Nitrogen pushbutton.........................................................................................
2.2.7.3 Air pushbutton..................................................................................................
2.2.7.4 Lower air supply line pushbutton.....................................................................
2.2.7.5 Chloride pushbutton.........................................................................................
2.2.7.6 Electric heater pushbuttons...............................................................................
2.2.8 Valve verification system.........................................................................................
2.2.9 Bypass switches.......................................................................................................
2.3 Control Flow Plan..........................................................................................................
3. EMERGENCY EQUIPMENT.............................................................................................
3.1 Safety Valves and Their Set Pressure..............................................................................
3.1.1 Summary of safety valve.........................................................................................
3.2 Car Sealed Valves...........................................................................................................
3.3 Remote Operating Valves................................................................................................
3.4 Instrument Alarms..........................................................................................................
3.5 Instrument Trip Settings.................................................................................................
3.6 Procedure for Setting Protective Relays..........................................................................
4. PREPARING UNIT FOR PRE-COMMISSIONING...........................................................
4.1 Pre-commissioning.........................................................................................................
4.1.1 Preliminary regeneration section operations.............................................................
4.2 Commissioning of Utilities..............................................................................................
4.2.1 Steam lines..............................................................................................................
4.2.2 Cooling water lines..................................................................................................
4.2.3 Plant air system.......................................................................................................
4.2.4 Instrument air lines..................................................................................................
4.2.5 Raw water...............................................................................................................
4.2.6 Firewater and sprinkler systems...............................................................................
4.2.7 Fuel gas lines...........................................................................................................
4.2.8 Natural gas system..................................................................................................
4.2.9 Nitrogen system.......................................................................................................
4.3 Pressure Testing..............................................................................................................
4.4 Flushing Out...................................................................................................................
4.5 Inspection and Run-In of Pumps.....................................................................................
4.5.1 Pump inspection......................................................................................................
4.5.2 Pump run-in.............................................................................................................
4.6 Leak Testing...................................................................................................................
4.7 Loading Internal Materials.............................................................................................
4.7.1 Packing of vent gas wash tower...............................................................................
4.8 Loading Catalyst............................................................................................................
4.9 Purging and Gas Blanketing...........................................................................................
4.10 Pre-Commissioning Check List.....................................................................................
5. COMMISSIONING.............................................................................................................
5.1 General Overall Commissioning Plant............................................................................
5.1.1 Introduction.............................................................................................................
5.1.2 Prestart-up checks...................................................................................................
5.1.3 Outline of commissioning procedure........................................................................
5.2 Detailed Step-by-Step Start-up Procedure......................................................................
5.2.1 Air-free the regeneration section..............................................................................
5 . 22Start up the platforming process unit in accordance with UOP startup
procedures...............................................................................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 4 OF

5.2.3 Establish catalyst collector and reduction zone purge flows.....................................


5 . 42Pressure up the regeneration section hydrogen system with recycle gas
from the platforming reactor section........................................................................
5.2.5 Commission the booster gas line from the net gas compression section....................
5 . 62Start flow of reduction gas, lift gas to the regenerated catalyst L-valve
assembly, and makeup gas.......................................................................................
5.2.7 Pressure up the regeneration tower with nitrogen.....................................................
5 . 82Pressure the nitrogen lift system and establish the spent catalyst
nitrogen “bubble” below the reactor........................................................................
5 . 92Establish the nitrogen “bubble" between the regeneration tower and
the lock hopper........................................................................................................
5.2.10 Commission the lock hopper and establish control of catalyst levels......................
5.2.11 Establish catalyst circulation.................................................................................
5.2.12 Establish a carbon level in the regeneration tower..................................................
5.3 Special Procedures.........................................................................................................
5.3.1 Regenerator coke burn test procedure......................................................................
5.3.2 Catalyst fines survey procedure...............................................................................
5.3.2.1 Prior to the survey............................................................................................
5.3.2.2 During the survey.............................................................................................
5.3.2.3 At the conclusion of the survey.........................................................................
5.3.2.4 Interpretation of the data..................................................................................
5.3.3 Safeing procedures..................................................................................................
5.3.3.1 Safeing procedure for the reduction gas system................................................
5.3.3.2 Safeing procedure for the lock hopper system...................................................
5.3.3.3 Safeing procedure for the regenerated catalyst lift line......................................
5 . 3 4.Safeing procedure for regeneration section air system and
nitrogen lift system............................................................................................
5.3.4 Catalyst unloading and reloading procedures...........................................................
5.3.4.1 Regeneration tower catalyst unloading..............................................................
5.3.4.2 Catalyst reloading.............................................................................................
5.3.5 Catalyst changeout on the fly...................................................................................
5.3.6 Special maintenance precautions for the stainless steel regeneration tower..............
6. NORMAL START-UP & SHUTDOWN PROCEDURES...................................................
6.1 Black Catalyst Startup Procedure...................................................................................
6.2 White Catalyst Startup Procedure...................................................................................
6.3 Normal Operations.........................................................................................................
6.3.1 Preventive maintenance schedule.............................................................................
6.3.2 Dust collector cleaning............................................................................................
6.3.2.1 Reverse jet cleaning..........................................................................................
6.3.2.2 Unloading.........................................................................................................
6.3.3 Normal catalyst addition..........................................................................................
6.3.4 Catalyst addition for catalyst changeout on the fly...................................................
6.3.5 Filter cleaning..........................................................................................................
6.3.6 Vent gas scrubbing system.......................................................................................
6.3.6.1 Control parameters...........................................................................................
6.3.6.2 Overpressure protection....................................................................................
6.3.6.3 Diversion valves...............................................................................................
6.4 Routine Operations.........................................................................................................
6.4.1 Sampling.................................................................................................................
6.5 General Overall Shutdown Plan......................................................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 5 OF

6.6 Detailed Step-by Step Shutdown Procedure....................................................................


6.6.1 Automatic shutdown................................................................................................
6.6.1.1 Hot shutdown...................................................................................................
6.6.1.2 Cold shutdown..................................................................................................
6.6.1.3 Contaminated nitrogen shutdown......................................................................
6.6.2 Manual shutdown....................................................................................................
6.6.2.1 Hot shutdown...................................................................................................
6.6.2.2 Cold shutdown..................................................................................................
6.7 Blanking Off...................................................................................................................
6.8 Operating Equipment......................................................................................................
6.9 Special Precautions.........................................................................................................
6.9.1 General....................................................................................................................
6.9.2 Precautions for entering a contaminated or inert atmosphere...................................
7. EMERGENCY SHUTDOWN.............................................................................................
7.1 General Instruction.........................................................................................................
7.2 Instrument Air Failure....................................................................................................
7.3 Recycle Compressor Failure...........................................................................................
7.4 Lift Gas Blower Failure..................................................................................................
7.5 Cooling Water Failure.....................................................................................................
7.6 Explosion, Fire, Line Rupture, or Serious Leak..............................................................
7.7 CCR Nitrogen Failure....................................................................................................
7.8 Power failure..................................................................................................................
7.9 Steam Failure.................................................................................................................
8. MAJOR EQUIPMENT........................................................................................................
8.1 Summary Tables.............................................................................................................
8.2 Tower Summary.............................................................................................................
8.2.1 Vent gas wash tower (312-V9)(Figure 8-30)............................................................
8.3 Drum Summary..............................................................................................................
8.3.1 Nitrogen seal drum (312-V7)(Figure 8-4)................................................................
8.3.2 Lock hopper (312-V8)(Figure 8-5)..........................................................................
8.3.3 Disengaging hopper (312-V3)(Figure 8-11 and 8-12)..............................................
8 . 43Catalyst addition funnel and catalyst addition lock hopper
(312-V1/V5, 312-V2/V6)(Figure 8-25 and 8-26)....................................................
8.4 Reactor Summary...........................................................................................................
8.4.1 Regeneration tower (312-R1)(Figure 8-1, 8-2 and 8-3)...........................................
8.5 Fire Heater Summary.....................................................................................................
8.6 Exchanger Summary......................................................................................................
8 . 16Electric heaters (312-H1, 312-H2, 312-H3 and 312-H4)
(Figure 8-17 and 8-18)............................................................................................
8.6.2 Regeneration cooler (312-EA1)(Figure 8-16)..........................................................
8.7 Pump Summary..............................................................................................................
8.8 Compressor Summary....................................................................................................
8.8.1 Regeneration blower (312-C3)(Figure 8-15)............................................................
8.9 Special Equipment Summary..........................................................................................
8.9.1 L-valve assemblies(Figure 8-6)................................................................................
8.9.2 Lift lines(Figure 8-7, 8-8 and 8-9)...........................................................................
8.9.3 Reduction zone(Figure 8-10)...................................................................................
8.9.4 Dust collector (312-ME9)(Figure 8-13)...................................................................
8.9.5 Lift gas and fines removal circuit (Figure 8-14).......................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 6 OF

8.9.6 Valves......................................................................................................................
8.9.7 V valves (Figure 8-19).............................................................................................
8.9.8 B valves (Figure 8-20 and 8-21)..............................................................................
8.9.9 G valves (Figure 8-22 and 8-23)..............................................................................
8.9.10 Oxygen analyzer (Figure 8-24)..............................................................................
8.9.11 Hydrogen/hydrocarbon analyzer............................................................................
8.9.12 Air dryer (312-ME10)(Figure 8-27)......................................................................
8.9.13 Catalyst samples (Figure 8-28 and 8-29)...............................................................
8.9.14 Vent gas scrubber (312-ME3)................................................................................
8.10 List of Instrument.........................................................................................................
8.11 Summary of All Equipment’s Drivers...........................................................................
8.12 Control Valves..............................................................................................................
8.13 Fired Heaters................................................................................................................
8.14 Miscellaneous...............................................................................................................
9. FLOW PLANS AND PLOT PLAN.....................................................................................
9.1 PFDs MSD’s and P&IDs................................................................................................
9.2 Design Engineering , Utility and Safety Flow Plans........................................................
9.3 Plot Plan.........................................................................................................................
9.4 Safety Shutdown Function Charts..................................................................................
10. SAFTY...............................................................................................................................
10.1 Emergency Fire Plan.....................................................................................................
10.2 Fire Fighting and Protective Equipment........................................................................
10.2.1 Fire alarm system..................................................................................................
10.2.2 Fixed water monitors.............................................................................................
10.2.3 Fire hydrants.........................................................................................................
10.2.4 Live hose reel stations............................................................................................
10.3 Fire Protection..............................................................................................................
10.3.1 Fire protection.......................................................................................................
10.4 Maintenance of Equipment and Housekeeping..............................................................
10.5 Repair Work.................................................................................................................
10.6 Thermal Expansion in Exchangers................................................................................
10.7 Withdrawal of Samples.................................................................................................
10.8 Safe Handling of Volatile and Toxic Materials Including Catalyst................................
10.8.1 Respiratory protection...........................................................................................
10.8.2 Corrosive materials................................................................................................
10.8.3 Poisonous gas........................................................................................................
10.8.3.1 Hydrogen sulfide (H2S)...................................................................................
10.8.3.2 Nitrogen.........................................................................................................
10.8.4 Aromatic hydrocarbons..........................................................................................
10.8.5 Catalyst (UOP Type R-134)..................................................................................
10.9 Preparing for Entering Process Equipment...................................................................
10.10 Opening Equipment....................................................................................................
10.11 Working in Columns or Vessels...................................................................................
10.12 Entering Tanks, Drums or Other Vessels.....................................................................
10.13 Procedure for Removing Safety Valves.......................................................................
10.14 Work Permit Procedure and Work Permit Formats......................................................
10.15 Operating Notes Relating HAZOP review..................................................................
10.16 Material Safety Data Sheet (MSDS)..........................................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 7 OF

11. MISCELLANEOUS...........................................................................................................
11.1 Conversion Tables.........................................................................................................
11.2 Summary of Precommissioning and Commissioning Procedure....................................
11.3 Overall Start-up and Shutdown Outlines.......................................................................
11.4 Offsite Systems.............................................................................................................
11.5 Catalyst and Chemical Loading/ Unloading..................................................................
11.5.1 Catalyst Loading....................................................................................................
11.5.2 Catalyst Unloading and Reloading Procedures.......................................................
11.5.3 Chemical Loading..................................................................................................
11.6 Catalyst and Chemical Requirement.............................................................................
11.7 Analytical Plan..............................................................................................................
11.7.1 Sample schedules...................................................................................................
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 8 OF

1GENERAL DESCRIPTION

This operation manual contains the design basis, process description, process control
and the operating procedure of the Platforming Process Unit CCR Section, constructed
for PAK-ARAB REFINERY LTD., Mahmood Kot, Pakistan.

1.1Plant Duty

The processing capability of the cyclemax type CCR regenerator section is 1,000 lb/hr
(454 kg/hr) of Platforming catalyst regeneration.

The CCR regenerator section process

The Catalyst Regeneration Section of a UOP Platforming Unit gives refiners the
flexibility to operate the reaction section at high-severity conditions. At high-severity
conditions in the reaction section, reforming catalyst deactivates more rapidly because
coke lays down on the catalyst at a faster rate. Without a Catalyst Regeneration Section,
the reaction section would have to be shut down more often for regeneration to burn off
this coke and to restore the catalyst's activity and selectivity. With a Catalyst
Regeneration Section, however, the refiner is able to operate the Platforming reaction
section without having to shut down for catalyst regeneration. This is done by
regenerating the catalyst continuously in the Catalyst Regeneration Section while the
Platforming reaction section continues to operate.

The Catalyst Regeneration Section consists of a system of integrated equipment that is


separate from, but still connected to, the reaction section. It performs two principal
functions-catalyst circulation and catalyst regeneration-in a continuous circuit. First,
spent catalyst from the last Platforming reactor is circulated to the Catalyst
Regeneration Section. In the Catalyst Regeneration Section, the spent catalyst is
regenerated in four steps: 1) Coke Burning; 2) Oxychlorination-for dispersing the
catalyst metals and adjusting the catalyst chloride content; 3) Catalyst Drying; 4)
Reduction-for changing the catalyst metals to the reduced state. Finally, the regenerated
catalyst is circulated back to the first Platforming reactor. the logic and sequence of this
circuit are controlled by the Regenerator Control System.

In this manner, freshly-regenerated catalyst is continuously circulated through the


Platforming reactors. This ensures that the Platforming reactor section operates
economically with optimum catalyst performance at high-severity conditions and for
long on-stream periods of operation.

In this manual, all aspects of the operating procedures of a Catalyst Regeneration


Section are covered in some detail.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 9 OF

1.2Discussion of Process

1.2.1Catalyst

The UOP Platforming catalyst consists of metals impregnated on an alumina base. A


wide variety of metals can be used, but platinum is the chief metal. The alumina base
acts as a support for the metal. The alumina is also a support for chloride.

In the Platforming reactors, both the metal and the chloride base help catalyze desirable
reactions. In short, the catalyst has two functions. The metal catalyzes hydrogenation
and dehydrogenation reactions. The chlorided alumina acid function catalyzes
isomerization and cracking reactions.

Optimum catalyst performance requires a proper balance of these two catalytic


functions. Too much or too little of one or the other will upset the selectivity and activity
of the catalyst. As a result, the performance of the catalyst in the Platforming reactors
will suffer.

The operation of the Catalyst Regeneration Section has a great affect on the proper
balance of the metal and chloride functions. Each of the four steps of catalyst
regeneration must be done well to ensure the proper balance is maintained. Proper
operation of the Catalyst Regeneration Section will help ensure optimum performance
of the catalyst and long catalyst life.

In addition to its optimum catalytic properties, the catalyst also has strong physical
properties. It is specially made to be resistant to attrition. Proper construction and
operation of the Catalyst Regeneration Section will help preserve the good mechanical
strength of the catalyst and minimize attrition.

1.2.2Chemistry

The Catalyst Regeneration process is a four-step process where the desirable


regeneration reactions are completed on the catalyst. The operating conditions for each
step are designed to help certain chemical reactions. Each step is important in its own
right, and all four steps must be performed correctly. The goal is to restore the catalyst
to a condition that is as close to that of fresh catalyst as possible. The basic regeneration
chemistry is the same for all regeneration sections.

(1) Coke Burning

The first step burns coke off the catalyst. Coke burning takes place with oxygen by the
combustion reaction. It makes carbon dioxide and water and gives off heat (exothermic):

Coke + O2 CO2 + H2O + Heat

This reaction is necessary and desirable to remove coke, but it can easily damage the
catalyst. It results in a temperature rise on the catalyst, and high temperature greatly
increases the risk of a permanent type of damage to the catalyst. So the burning must be
controlled. This is done by controlling the oxygen content during the burn. High oxygen
makes the burn temperatures high. But low oxygen makes the burning too slow. During
normal operation, the oxygen content is kept between 0.5-0.8 mol-% oxygen. This is an
optimum range to maximize the coke burning rate while minimizing the coke burning
temperature.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 10 OF

(2) Oxychlorination

The second step adjusts the chloride content and oxidizes and disperses the metals (i.e.,
platinum) on the catalyst. These reactions take place by complex reactions with oxygen
and an organic chloride compound. These reactions need both oxygen and chloride, The
chloride adjustment reactions can be summed up as:

(a) Chloride Compound + O2 HCI + CO2 + H2O

(b) HCl + O2 Cl2 + H2O (Deacon Equilibrium)

(c) Base-OH + HCl Base-Cl + H2O

Chloride is needed on the catalyst to keep the proper activity of the acid function. But
too much or too little chloride will have undesirable effects in the Platforming reactors.
So the amount of chloride on the catalyst must be controlled. This is done by controlling
the injection rate of the chloride compound. During normal operation, the chloride
content of the oxidized catalyst is kept between 1.1-1.3 wt-% chloride, depending on the
catalyst series. This is an optimum range for the acid function of the catalyst.

The oxidation and redispersion reactions can be summarized as follows:

Metal + O2 Oxidized Metal (dispersed)

The more evenly distributed the metal is on the catalyst surface, the better the metal
function of the catalyst will be. The conditions that help oxidation and redispersion of
the metal are high oxygen concentration, long residence time, correct temperature, and
correct chloride concentration.

(3) Drying Cl
2
The third step dries excess moisture from the catalyst. Excess moisture is on the
catalyst from the coke burning step. Drying takes place when a hot, dry gas flows
across the catalyst. The drying step can be thought of as stripping water off the catalyst
base:

Base-H2O + Dry Gas Base + Gas + H2O

The drier the catalyst is before it re-enters the Platforming reactors, the better its overall
performance will be. This drying step is helped by high temperature, long drying time,
and drying gas flow rates adequate to ensure good gas distribution and sufficient
thermal mass.

(4) Reduction

The fourth step converts the metals from an oxidized state to a reduced state. This must
be done after the oxychlorination step to return the catalyst to a state that is catalytically
active in the Platforming reactors. The reduction reaction takes place with hydrogen by
the following reaction:
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 11 OF

Oxidized Metal + H2 Reduced Metal + H2O

The more complete the reduction, the better the metal will perform in the Platforming
reactors. The conditions that help this reaction are high hydrogen purity, reduction gas
flow rates adequate to ensure good gas distribution, and sufficient reduction zone
temperatures.

1.2.3Catalyst regeneration circuit principles

Figure 1.2-1 is a flow diagram of the UOP CycleMax Catalyst Regeneration Section,
The Catalyst Regeneration Section performs two functions: catalyst regeneration and
catalyst circulation.

1.2.3.1 Catalyst regeneration

Catalyst regeneration consists of four steps. The first three steps-coke burning,
oxychlorination, and drying-occur in the Regeneration Tower. The fourth step,
reduction, occurs in the Reduction Zone at the top of the Reactor Stack. A fifth step,
catalyst cooling, is not part of the regeneration but is required for proper catalyst
transfer. This step occurs in the Regeneration Tower.

(a) Burn Zone/Reheat Zone (Figure 1.2-2)

The burning of coke from the catalyst occurs in the Burn Zone at the top of the
Regeneration Tower. Catalyst enters and flows downward between a vertical,
cylindrical outerscreen and an inwardly tapered innerscreen. Hot regeneration
gas, containing a low concentration of oxygen, flows radially from the outside to
the inside of the catalyst bed. Coke burning occurs as the catalyst moves down in
the bed. The coke burning should be complete when the catalyst exits the Burn
Zone. The purpose of the tapered centerscreen is two-fold: (1) To minimize the
volume of catalyst behind the burn front. This catalyst is exposed to oxygen-
deficient gas which is high in temperature and moisture. These are the conditions
which promote catalyst surface area loss. (2) To concentrate the flow of
regeneration gas at the top of the bed where coke burning is oxygen supply
limited. In the lower section, where the coke burning is oxygen diffusion limited,
a slower flow of gas is acceptable and residence time is of greater importance.
The hot combustion gas mixes with the gas flowing up from the Chlorination
Zone. This oxygen-rich chlorination gas supplies the oxygen for burning coke.
The combined gases flow back to the Regeneration Blower. The Blower recycles
the gases through the Burn Zone piping loop. The Regeneration Cooler removes
the heat generated by the coke burning. The Regeneration Heater operates, if
heat loss in the piping is greater than the heat of combustion, to heat the gas to
the proper zone inlet temperature. The oxygen analyzer controls the oxygen
content at the Burn Zone inlet. The products of combustion are vented at the
Regeneration Tower inlet so as to provide a constant controlled temperature vent
gas to the downstream chloride scrubbing equipment.

After catalyst exits the Burn Zone it enters the Reheat Zone. In this zone the
catalyst is contacted radially with hot combustion gas from the Regeneration
Blower discharge. The purpose of this zone is to raise the temperature of the
catalyst to that required in the Chlorination Zone. The flow rate of the reheat gas
is typically 10 % of the total regeneration gas flow. The Reheat Zone also
provides additional residence time for oxygen diffusion limited coke combustion
in case of coke breakthrough.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 12 OF

(b) Chlorination Zone (Figure 1.2-3)

Oxidizing and dispersing the metals on the catalyst, and adjusting the chloride
content on the catalyst base occur in the Chlorination Zone. The Chlorination
Zone is located below the Burn Zone/Reheat Zone. Catalyst enters and flows
downward in a cylindrical bed defined by an annular baffle. Hot air from the
Drying Zone below flows upward into the region behind the annular baffle. At
this point, vaporized organic chloride is introduced to the gas through a
distributor. The resulting chlorination gas then flows upward through the catalyst
bed and exits into the Burn Zone.

(c) Drying Zone (Figure 1.2-4)

Catalyst drying occurs in the Drying Zone. The Drying Zone is below the
Chlorination Zone. Catalyst enters and flows downward in a cylindrical bed. Hot
drying gas flows upward through the catalyst bed. The drying gas is air from the
Cooling Zone below and the instrument air header. Both the above gases are
dried to a very low moisture content in the Air Dryer before entering the
Regeneration Tower. The Air Heater heats the gas to the proper inlet temperature.
The gas from the Cooling Zone is hot, as it has been preheated by exchange with
hot catalyst in that zone. This preheat reduces the net duty on the Air Heater.
From the Drying Zone the drying air splits into two streams, one entering the
Chlorination Zone behind the annular baffle and one exiting the Regeneration
Tower. The split depends on the amount of air needed for coke burning. The flow
rate of air that is needed for coke burning enters into the Chlorination Zone. Any
excess air vents directly from the Regeneration Tower on oxygen control. The air
in excess of the coke burning requirement is needed in the Drying Zone for more
complete moisture removal in that zone.

(d) Cooling Zone (Figure 1.2-5)

The Cooling Zone serves two functions, cooling the catalyst for downstream
handling, and preheating a portion of the air to the Drying Zone. Cooling the
catalyst reduces the metallurgy requirement for the downstream catalyst transfer;
equipment and facilitates catalyst transfer by permitting isothermal catalyst
lifting. Preheating the Drying Zone air lowers the duty required for the Air
Heater, thus saving on utilities. The Cooling Zone is below the Drying Zone.
Catalyst enters and flows downward in a cylindrical bed exiting the Regeneration
Tower. The cooling gas is air from the Air Dryer. The gas exits the zone and
mixes with instrument air from the Air Dryer then enters the Air Heater before
going to the Drying Zone. The split between air going to the Cooling Zone and
air going directly to the Drying Zone determines the temperature of the catalyst
exiting the Regeneration Tower.

(e) Reduction Zone (Figure 1.2-6)

Reducing the metals on the catalyst occurs in the Reduction Zone. The Reduction
Zone is at the top of the Reactor Stack. Oxidized catalyst enters the top of the
zone via the regenerated catalyst lift line. The catalyst flows downward through
two cylindrical beds with a gas disengaging area between them. The catalyst
exits the zone and enters the first Platforming reactor. Reduction gas of
intermediate temperature is supplied to the upper cylindrical bed and flows co-
current with the catalyst. Reduction gas of higher temperature is supplied to the
lower cylindrical bed and flows counter-current to the catalyst flow. Both gases
exit from the Reduction Zone via the gas disengaging area. The reduction gas is
hydrogen-rich gas from the Platforming Unit recontact section. The Reduction
Heaters heat the gas to the proper inlet temperatures for each bed in the zone.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 13 OF

The purpose of the dual zone reduction is to affect optimum and independently
controlled, reduction conditions for the proper performance of the catalyst. A low
temperature reduction is performed in the upper bed, with the water of reduction
being swept downward with the gas. The presence of moisture in this zone is not
detrimental to catalyst performance due to the low temperature. In the lower
zone, a high temperature reduction is performed under dry conditions. The
moisture of reduction is swept away from the high temperature reduction front by
the counter-current flow of gas. This is important, as the combination of high
temperature and high moisture can lead to the metal agglomeration and improper
metal reduction.

1.2.3.2 Catalyst circulation

Catalyst circulation consists of transferring catalyst from the Platforming reactors to the
Regeneration Section and back again.

(a) Spent Catalyst Transfer

The catalyst circulation control scheme is shown in Figure 1.2-7. Spent catalyst
flows by gravity from the bottom of the last reactor to the Catalyst Collector.
Catalyst flows downward into the Spent Catalyst L-Valve Assembly against an
upward flow of nitrogen. At the L-Valve Assembly, circulating nitrogen from the
Lift Gas Blower engages the catalyst and lifts it through the catalyst lift line to
the Disengaging Hopper. In the Disengaging Hopper, additional circulating
nitrogen from the Fines Removal Blower separates catalyst chips and fines from
the whole catalyst and carries them out the top with the gas. The chips and fines
are removed in the Dust Collector and the nitrogen circulates back to the suction
of the Fines Removal Blower and the Lift Gas Blower. The whole catalyst drops
to the bottom of the Disengaging Hopper, and flows by gravity into the
Regeneration Tower. The catalyst flows through and out of the Regeneration
Tower by gravity.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 14 OF

(b) Regenerated Catalyst Transfer

From the Regeneration Tower, the catalyst flows by gravity into the Nitrogen
Seal Drum against a flow of nitrogen. From the Nitrogen Seal Drum the catalyst
flows into the Lock Hopper. The Lock Hopper removes small batches of catalyst
from the vessels above and transfers catalyst continuously into the Regenerated
Catalyst L-Valve Assembly. At the L-Valve assembly, hydrogen-rich gas from the
recontact section of the Platforming Unit engages the catalyst and lifts it through
the catalyst lift line to the Reduction Zone above the first Platforming reactor.
The catalyst flows through the Reduction Zone to the top of the first reactor by
gravity. The catalyst flows through and out each reactor by gravity until it
reaches the catalyst collector. This completes the transfer circuit. Catalyst flows
between the reactors through equally spaced transfer lines designed to ensure
even catalyst flow from all sides of each reactor.

(c) Catalyst Circulation Control

The catalyst circulation is shown in Figure 1.2-7. The catalyst circulation rate
for the entire system is set by the Regenerator Control System (RCS) and its
direct control of the regenerated catalyst lift rate. The desired catalyst circulation
rate is entered into the RCS and it generates an output signal that adjusts the
catalyst circulation as described below. The lift line pressure drop is used as a
control parameter because it varies directly with catalyst flux (catalyst flow rate)
in the lift line. The rate of catalyst lifting, as performed by the L-Valve assembly,
is controlled by splitting a constant lift gas flow between the primary and
secondary addition points. In practice, this is achieved by keeping the total lift
gas flow constant and varying only the secondary lift gas rate. In addition to the
above, the rate of change of the catalyst lift rate must be slow and controlled to
maintain the stability of the process environment isolation systems utilized in the
CycleMax design. Large or rapid changes in catalyst lift rate could result in the
contamination of the oxygen atmosphere in the Regeneration Tower by hydrogen
gas, or interruption of catalyst flow to the L-Valve assemblies.

Regenerated (oxidized) catalyst flows from the Regeneration Tower through the
Nitrogen Seal Drum, into the Lock Hopper by gravity. In the Lock Hopper, small
batches are transferred from the Regeneration Tower to the Regenerated Catalyst
L-Valve Assembly. Hydrogen-rich gas engages the catalyst and lifts it through the
catalyst lift line to the Reduction Zone above the Platforming Reactors. The flow
rate of the regenerated catalyst, and thus the entire system is set by an output
signal from the RCS to the Regenerated Catalyst Lift Line PDRC. The RCS
output signal is determined from the desired catalyst flow setpoint (circulation
rate) entered. The RCS sets the PDRC setpoint to a value stored in the RCS
memory commensurate with the flow setpoint entered. The output signal from the
regenerated catalyst lift line PDRC resets the regenerated catalyst secondary lift
gas FRC (Flow Recorder Controller) setpoint directly. The flow of secondary lift
gas as set by the FRC controls the catalyst lifting via the L-Valve Assembly to
the Reduction Zone. As lifted catalyst is replaced by catalyst from the Lock
Hopper Surge Zone, the level in that zone falls. Once the low level setting on
level indictor is reached, the RCS initiates the transfer of one batch of catalyst
from the Regeneration Tower to the Surge Zone via cycling of the Lock Hopper
Zone. The Lock Hopper Zone load size is a known weight of catalyst, calibrated
during the initial startup of the unit. The actual circulation rate is determined
based on a running average of the frequency of Lock Hopper loads transferred.
The regenerated catalyst lift line PDRC setpoint is then ramped up or down by
the RCS to reach the point where the actual circulation matches the desired
circulation rate entered into RCS.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 15 OF

Spent catalyst flows by gravity from the bottom of the last reactor to the Catalyst
Collector. Catalyst flows downward, against a low, upward flow of nitrogen, into
the Spent Catalyst L-Valve Assembly. Circulating nitrogen from the Disengaging
Hopper engages the catalyst and lifts it., via the catalyst lift line, to the
Disengaging Hopper above the Regeneration Tower. Since regenerated catalyst is
being lifted to the reduction zone, spent catalyst is removed from the Platforming
Reactors so as to maintain a level in the upper bed of the Reduction Zone atop
the reactor stack. The LRC (Level Recorder Controller) at the Reduction Zone
sends a signal resetting the spent catalyst lift line PDRC (Pressure Differential
Recorder Controller) setpoint via a signal selector. The signal selector also
receives a signal from the Regenerator Control System. The output signal from
the spent catalyst lift line PDRC resets the spent catalyst secondary lift gas FRC
(Flow Recorder Controller) setpoint via a signal selector. The selector also
receives an output signal from the Reactor/Spent Catalyst Lift Line PDRC. The
flow of secondary lift gas as set by the FRC controls the catalyst lifting rate via
the L-Valve Assembly to the Disengaging Hopper.

The signal selectors, and the secondary inputs they incorporate, are required to
maintain the stability of the process environment isolation systems utilized in the
CycleMax design. A large or rapid increase in catalyst lift rate could interrupt
catalyst flow from the Reactor. The low signal selector receiving input from the
Reduction Zone LRC also receives a signal from the Regenerator Control
System. The latter signal is an adjustable ramping function designed to slowly
increase the catalyst flow rate from 0% to 100% of the design catalyst
circulation rate. This ramping is used by the Catalyst Flow Control in the RCS
only when catalyst circulation is restarted from zero. At some point during the
catalyst circulation ramp, the signal from the LRC will be less than that of the
ramp function. At that point, the low signal selector will use the LRC signal as
its output signal to the spent catalyst lift line PDRC.

The signal selector that receives input from the lift line PDRC also receives a
signal from the Reactor/Spent Catalyst Lift Line (R/SCLL) PDRC. The latter
signal serves to limit the magnitude and speed of catalyst lift rate changes for
system stability. If the catalyst lift rate increases rapidly. the differential pressure
between the lift pipe and the Reactor will increase (the bottom of the lift line
being maintained at a higher pressure than the reactor) and the high upward flow
of gas will impede catalyst flow downwards to the L assembly. Once the pressure
differential increases to near that which will impede catalyst flow, the R/SCLL
PDRC output will limit the catalyst lift rate by limiting the secondary lift gas
flow.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 16 OF

(d) Process Pressures and Environments

There are several inherent hazards to overcome in order to transfer catalyst


safely between the reaction section and the Regeneration Section of a continuous
Platforming unit. This is because the two sections operate at different pressures
and under different environments, as shown in Figures 1.2-8 and 1.2-9. First, the
low pressure equipment in the Regeneration Section must at all times be kept
safe from the high pressure equipment in the Platforming section. Second, the
hydrogen/hydrocarbon environment of the reaction section must at all times be
kept safe from the oxygen-containing environment of the Regeneration Section.
Through the design of the equipment and through the programmed sequences of
the Regenerator Control System, the Regeneration Section accomplishes these
tasks.

The hydrogen/hydrocarbon and oxygen atmospheres are separated by the use of


"nitrogen bubbles". A nitrogen bubble in its simplest form is a region between
hydrogen containing equipment and oxygen containing equipment maintained as
a pure N2 atmosphere. This is accomplished by keeping the pure N2 region at a
higher pressure than the equipment on either side of it. Nitrogen bubbles are
maintained in the Regeneration Section just below the Reactors, i.e., the spent
catalyst transfer system and the Disengaging Hopper; and just below the
Regeneration Tower, i.e., the Nitrogen Seal Drum. The Reactor and Regenerator
pressures are kept separate by allowing a pressure gradient to exist across a
standpipe of catalyst. The pressure drop is maintained by the flow of gas from
high to low pressure through the resistance of a catalyst bed. Such pressure
gradients are maintained between the Disengaging Hopper and the Regeneration
Tower, and between different zones within the Lock Hopper.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 17 OF

FIGURE 1.2-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 18 OF

FIGURE 1.2-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 19 OF

FIGURE 1.2-3
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 20 OF

FIGURE 1.2-4
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 21 OF

FIGURE 1.2-5
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 22 OF

FIGURE 1.2-6
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 23 OF

FIGURE 1.2-7
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 24 OF

FIGURE 1.2-8
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 25 OF

FIGURE 1.2-9
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 26 OF

1.3Design Basis for Feeds and Products

1.3.1Feeds

Spent Catalyst: 1,000 lb/hr (454 kg/hr)

1.3.2Products

Regenerated Catalyst: 1,000 lb/hr (454 kg/hr)

1.4Material Balance / B.L. Conditions

Material Balance

Not Applicable.

Battery Limit Conditions

B.L. condition are tabulated below:

Refer to P&ID (D-300-1225-111)

Origin / Temp Pressure


Destination o
C kg/cm2G
Booster Gas 312-ME8 41 12.11
25OBe Caustic from Unit-900 312-V10 58 2.5
Spent Caustic 312-V9 43 7.0

1.5Utilities and Chemical Requirements

1.5.1Utilities requirements

Utility consumed and generated in this unit are shown in S-312-1223-501 Utility
Summary for Unit 312 (Attachment 1-1)

1.5.2Chemical requirements

Chemical as well as catalyst requirement are summarized in attachment 1-2, S-312-


1223-502 Catalyst and Chemical Summary for Platforming Process unit CCR section.
Requirement particular to these chemical/catalyst are noted in the attachment.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 27 OF

2OPERATING CONDITIONS AND CONTROLS

2.1Discussion of Process Variables

Good operation of the Regeneration Section depends on the proper selection and control
of the processing conditions. The operating variables are of utmost importance to the
performance of the Regeneration Section. This section includes general operating
guidelines that should be followed to maintain the operating variables within acceptable
limits.

PRINCIPLE

The four most important operating variables of the Burn Zone are:

(1) Catalyst circulation rate


(2) Burn zone oxygen content
(3) Spent catalyst coke content
(4) Burn zone gas rate.

These four operating variables are interrelated. That means, each has limits on its
acceptable operating range that are set by the other three variables. The operator must
select all four variables with one goal in mind to ensure that essentially all coke burning
occurs in the Burn Zone. If coke burning occurs below the Burn Zone, such as in either
the Chlorination Zone or the Drying Zone, then there will be serious damage to both
catalyst and equipment.

There is a general operating guideline that helps the operator achieve this goal. It is
called the General Operating Curve (Figure 2.1-1). It shows how these four operating
variables are interrelated to ensure that essentially all coke burning occurs in the Burn
Zone. The operator should always operate the Regeneration Tower in accordance with
the General Operating Curve.

In practice, the operator has direct control over only two of the variables in Figure 2.1-
1: 1) the catalyst circulation rate, and 2) the Burn Zone oxygen. The other two - the
spent catalyst coke and the Burn Zone gas rate - are not under the operator’s direct
control. This fact does not limit the operator's options, and the operator will find the
General Operating Curve is useful in several ways, as examples that follow will show.

CAUTION

The operator should keep in mind that the General Operating Curve (Figure 2.1-1) is an
operating guideline. This chart is considered to be conservative. That means, for a given
spent catalyst coke, Burn Zone oxygen, and Burn Zone gas flow, the maximum
permissible catalyst rate shown by Figure 2.1-1 is probably less than the true maximum
catalyst rate. So, Figure 2.1-1 should provide a safety margin between an actual
operating point and the point where coke burning is not completed in the Burn Zone.

The operator should check that the Regeneration Tower operates in accordance with the
General Operating Curve (Figure 2.1-1) before using it as an operating guideline. This
should be done as soon as the Regeneration Tower is started. That means, the operator
should do this check during the initial Black Catalyst Startup while there is only upper
air injection. Then, depending on the spent catalyst coke and the Burn Zone gas flow at
the time, the operator should choose the catalyst circulation rate and the Burn Zone
oxygen that correspond to a point on the General Operating Curve. Under these
conditions, the regenerated catalyst leaving the Regeneration Tower should be 0.1 wt-%
coke or less, have coke-free centers, and contain essentially no whole black spheres.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 28 OF

If desirable, the refinery may make a specific General Operating Curve that represents
the full coke-burning potential of its specific Regeneration Tower. in order to do this, a
series of Coke Burn Tests must be done on the unit. The Coke Burn Test Procedure is
available from UOP.

2.1.1Catalyst circulation rate

The operator controls the catalyst circulation rate using the Catalyst Flow Setpoint of
the Regenerator Control System. This setpoint sets the regenerated catalyst lift rate
which in turn sets the catalyst circulation rate for the entire system.

The recommended operating range for the catalyst circulation rate is 10-100% of
design. The catalyst circulation rate should not be operated above 100% of design.

There are limits on the acceptable operating range of the catalyst circulation rate. These
limits are set by the Burn Zone oxygen content, the spent catalyst coke content, and the
Burn Zone gas rate. The maximum permissible catalyst circulation rate is determined
using the General Operating Curve as shown in the following example:

EXAMPLE

Maximum Permissible Catalyst Circulation Rate

If the current Regeneration Section operations is:

Spent catalyst coke content 5 wt%


Burn Zone flow 90% of design
Burn Zone inlet oxygen 0.6 mole%

then from Figure 2-1:

Maximum permissible catalyst rate

Using the General Operating Curve, start at 5 wt-% on the coke axis. Move vertically to
the 90% Burn Zone flow curve. Move horizontally to the left to the 0.6% oxygen line.
Then move vertically down to the circulation rate axis. Read 82% of design.

As a result, if the actual catalyst circulation rate is greater than 82% of design, then it
should be reduced. If the actual rate is less than 82% of design, then it can be increased
gradually.

NOTE: Certain combinations of values for spent catalyst coke, Burn Zone gas flow,
and Burn Zone oxygen may give a maximum permissible catalyst circulation rate from
Figure 2.1-1 that is greater than 100% of design. However, for various technical
reasons, the catalyst circulation rate should not be increased above 100% of design.
When a catalyst rate is obtained from Figure 2.1-1 that is greater than 100% of design,
it is usually because the chosen value of the Burn Zone inlet oxygen content is too high
for the spent catalyst coke level. In the interest at minimizing the oxygen concentration
without sacrificing complete combustion in the Burn Zone, the oxygen content should be
reduced in accordance with the General Operating Curve. However, the Burn Zone inlet
oxygen content should NOT be operated outside the range of 0.5-1.0 mole percent.

COMPUTATION

The operator computes the catalyst circulation rate using two methods: by the cycling of
the Lock Hopper and by the combustion air usage.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 29 OF

(1) Lock Hopper

To compute the catalyst circulation rate by the Lock Hopper, use the final calibration of
the Lock Hopper zone size.

(number of L.H. cycles) x (L H. Zone size, wt)


(time, hrs)

(2) Combustion Air Usage

To compute the catalyst circulation rate by air usage, use the following formula:

CCR (Kg/hr) = (0.488) x ( - 1 ) x AT x (0.21 - Y)

CCR=
( CCR (pph) = (0.0288) x ( - 1 ) x AT x (0.21 - Y) )

where:

X = spent catalyst coke content, wt-%

Carbon, wt-% (by lab)


0.95

CCR = catalyst circulation rate, Kg/hr (pounds per hour)


100
Y = Burn Zone inlet oxygenXconcentration, mole fraction

AT =
total combustion air, Nm 3
100/hr (SCFH)
X
NOTE: For white burn conditions (lower air injection only), use:

AT = AL - VL

=
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 30 OF

where:

AL = air to Drying Zone, Nm3/hr (SCFH)

VL = excess air vent, Nm3/hr (SCFH)

For black burn conditions (upper air injection only), use:

AT = AU

where:

AU = air to Burn Zone, Nm3/hr (SCFH)

This formula can be put in chart form for easier use. An example of a typical chart for a
3000 pph CycleMax Regeneration Tower is shown in Figure 2.1-2.

EXAMPLE

If the current Regeneration is:

Total combustion air = 670 Nm3/hr (25,000 SCFH)


Spent catalyst coke content = 5.0 wt-%

then from Figure 2.1-2

Catalyst circulation rate = 1,264 Kg/hr (2,784 pph)

2.1.2Burn zone oxygen

The operator controls the Burn Zone oxygen content using the oxygen analyzer. During
normal operation, the oxygen analyzer controls how much excess air is vented from the
Regeneration Tower: As less excess air is vented, more enters the Burn Zone, and the
oxygen content becomes higher.

The recommended range for the Burn Zone oxygen is 0.5-1.0 mole % oxygen. Higher
oxygen causes higher burn temperatures that could cause damage to the catalyst,
primarily in the form of surface area loss. Lower oxygen causes slower coke burning
that might not finish completely in the Burn Zone. If coke burning occurs in the
Chlorination Zone, extremely high temperatures will occur that will cause serious
damage to catalyst, i.e., alumina phase change and equipment in the Chlorination Zone.

In order to minimize the negative effects of high temperature burning on catalyst


performance, it is recommended that the Burn Zone oxygen be minimized, provided that
coke burning is completed in the Burn Zone.

There are limits on the acceptable operating range of the oxygen content. These limits
are set by the catalyst circulation rate, the spent catalyst coke content, and the Burn
Zone gas rate. The minimum allowable oxygen content is determined using the General
Operating Curve as shown in the following example:
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 31 OF

EXAMPLE

Minimum Allowable Burn Zone Inlet Oxygen Content

If the current Regeneration Section operation is:

Spent catalyst coke content 5.5 wt-%


Burn Zone flow 110% of design
Catalyst circulation rate 90% of design

then from Figure 2.1-1:

Minimum allowable Burn Zone oxygen 0.6 mole-%

Using the General Operating Curve, start at 5.5 wt-% on the coke axis. Move vertically
to the 110% Burn Zone flow curve. Move horizontally to the left to the vertical line
extending up from 90% on the circulation axis. Read 0.6 mole-% on the oxygen line.

As a result, the actual Burn Zone inlet oxygen content is greater than 0.6 mole-%, then
it could be gradually reduced. If the actual oxygen content is less than 0.6 mole-%, then
it should be gradually increased

2.1.3Spent catalyst coke

The operating conditions in the reaction section control the coke on the spent catalyst
from the last Platforming reactor. The coke content is a function of charge rate, product
octane, charge quality, reactor pressure, recycle rate, and catalyst circulation rate.

The recommended operating range for the spent catalyst coke is 3-7 wt-% coke. Within
this range, catalyst performance and catalyst life optimum.

There are limits on the acceptable operating range of the spent catalyst coke content.
These limits are set by the Burn Zone oxygen content, the catalyst circulation rate, and
the Burn Zone gas rate. The maximum allowable spent catalyst coke content is
determined using the General Operating Curve as shown in the following example;

EXAMPLE

Maximum Allowable Spent Catalyst Coke Content

If the current Regeneration Section operation is:

Catalyst circulation rate 100% of design


Burn Zone inlet oxygen 0.8 mole-%
Burn Zone flow 90% of design

then from Figure 2.1-1:

Maximum allowable spent catalyst coke 5.4 wt-%


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 32 OF

Using the General Operating Curve, start at 100% on the circulation rate axis. Move
vertically to the 0.8% oxygen line. Move horizontally to the right to the 90% Burn Zone
flow curve. Then move vertically down to the coke axis. Read 5.4 wt-%.
X=
1 + coke content is greater than 5.4 wt-%, then the
As a result, if the actual spent catalyst
current Regeneration Section operation should be adjusted. For example, the actual
spent catalyst coke content is 6 wt-%, then one possible adjustment would be to increase
the Burn Zone oxygen content. Burn Zone inlet oxygen of 0.85 would be sufficient to
combust all the coke in the Burn Zone.

NOTE: The operator should keep the spent catalyst coke content under control. The
spent catalyst coke is laid down on the catalyst in the Platforming reactors. The reactor
conditions that increase the laydown rate are:

Increasing charge rate


Increasing product octane
Increasing charge endpoint
Decreasing charge naphthenes
Decreasing charge aromatics
Decreasing reactor pressure
Decreasing recycle rate

The spent catalyst coke is burned off in the Regeneration Tower. The regeneration
conditions that increase the burnoff rate are:

Increasing Burn Zone oxygen


Increasing Burn Zone gas rate

To keep the spent catalyst coke content under control, the operator should always
balance the coke laydown rate and the coke burnoff rate. That means, if a change in
reactor conditions increases (or decreases) the coke laydown rate, then the operator
must compensate with a change in regeneration conditions that increases (or decreases)
the coke burn off rate. But the change in the regeneration conditions may not need to be
made immediately. It may take several days for a change in reactor conditions to show
its effect on the spent catalyst coke content. The important point is that the reactor
section change eventually shows its effect and then the operator must adjust the
regeneration conditions in accordance with the General Operating Curve.

COMPUTATION

The operator computes the spent catalyst coke content using two methods: by
combustion air usage and by laboratory analysis. The two results should not be different
by more than 0.1-0.2 wt-% coke.

(1) Combustion Air Usage

To compute the coke content by air usage, use the following formula:

100
CCR(kg/hr)
0.488 x AT x (0.21 - Y)

X=
1+
100
CCR(pph)
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 33 OF

0.0288 x AT x (0.21 - Y)

where:
X = spent catalyst coke content, wt-%
CCR = catalyst circulation rate, Kg/hr (pounds per hour)
Y = Burn Zone inlet oxygen concentration, mole fraction
AT = total combustion air, Nm3/hr (SCFH)

NOTE: For white burn conditions (lower air injection only), use:

AT = AL - VL

where:

AL = air to Drying Zone, Nm3/hr (SCFH)


VL = excess air vent, Nm3/hr (SCFH)

For black burn conditions (upper air injection only); use:

AT = AU

where:

AU = air to Burn Zone, Nm3/hr (SCFH)

This formula can be put in chart form for easier use. An example of a typical chart for a
3,000 pph Pressurized Regeneration Tower is shown in Figure 2.1-2.

EXAMPLE

If the current Regeneration Section operation is:

Total combustion air 670 Nm3/hr (25,000 SCFH)


Catalyst circulation rate 1,361 kg/hr (3,000 pph)

then from Figure 2-2

Spent catalyst coke content 4.7 wt-%

(2) Laboratory Analysis

To compute the coke content from the spent catalyst carbon analysis, use the following
formula:

Carbon, wt-% (by lab)


0.95

NOTE: Coke is about 95% carbon.

Coke, wt-% =
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 34 OF

2.1.4Burn zone gas flow

The flow of Burn Zone gas is not controlled. The flow rate is the maximum flow rate
capable by the Regeneration Blower. The rate is a function of the capacity of the Blower
and the pressure drop through the Burn Zone loop.

The recommended Burn Zone gas flow rate is 100% of design. Gradually over
successive regenerations, the Burn Zone screen plugs with catalyst chips. This decreases
the Burn Zone gas flow and the coke burning potential of the Burn Zone. When the
Burn Zone gas flow drops to 90% of the rate when the Burn Zone screen is clean, then
the screen should be cleaned.

There are limits on the acceptable operating range of the Burn Zone gas rate. These
limits are set by the catalyst circulation rate, the Burn Zone oxygen content, and the
spent catalyst coke content. The minimum allowable Burn Zone gas rate is determined
using the General Operating Curve as shown in the following example:

EXAMPLE

Minimum Allowable Burn Zone Gas Rate

If the current Regeneration Section operation is:

Catalyst circulation rate 95% of design


Burn Zone inlet oxygen 0.6 mole %
Spent catalyst coke content 4.5 wt-%

then from Figure 2-1:

Minimum allowable Burn Zone gas rate 93% of design

Using the General Operating Curve, start at 95% on the circulation rate axis. Move
vertically to the 0.6% oxygen line. Move horizontally to the right to the vertical line
extending up from 4.5% on the coke axis. Read 93% on the Burn Zone flow curves.

As a result, if the actual Burn Zone gas rate is less than 93% of design, then the current
Regeneration Section operation should be adjusted. For example, if the actual Burn
Zone gas rate is 90% of design, then one possible adjustment would be to decrease the
catalyst circulation rate to the maximum permissible circulation rate than corresponds
to 4.5 wt-% coke, 90% of design Burn Zone flow, and 0.6 mole-% oxygen. This
maximum permissible circulation rate is 92% of design. So, the catalyst circulation rate
could be decreased from 95% to 92% of design.

COMPUTATION

The operator computes the Burn Zone gas flow rate using two methods: by pressure
drop across the Regeneration Cooler and by oxygen measurements.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 35 OF

(1) Regeneration Cooler

The Regeneration Cooler causes a pressure drop when Burn Zone gas flows through it.
A differential pressure instrument measures this pressure drop. The higher the pressure
drop, the greater is the Burn Zone gas flow rate.

From the dimensions of the Cooler on the vendor’s drawings, a calibration chart is made
for computing the flow rate of Burn Zone gas through the Cooler from the measured
pressure drop. This chart will be prepared prior to the startup of the unit. A chart for a
typical Regeneration Cooler is shown in Figure 2.1-3. The actual Burn Zone gas flow
rate can then be calculated using this flow and the following formula:

Burn Zone Gas, Nm3/hr = Cooler Flow - Vent Gas Flow - Seal Gas Flow

where:

Cooler Flow = by direct measurement of Cooler pressure drop and


calibration curve,Nm3/hr (SCFH)

Vent Gas Flow = approximated by Chlorination Gas Flow, Nm3/hr (SCFH)

Seal Gas Flow = related to CCR size and Burn Zone Flow as given, below,
Nm3/hr (SCFH)

Seal Gas
CCR Size Flow, S
(Kg/hr) (pph) (Fraction of Burn Zone Gas Flow)

318 (700) 0.090


454 (1,000) 0.071
681 (1,500) 0.054
908 (2,000) 0.044
1,362 (3,000) 0.034
2,043 (4,500) 0.026

With the above substitution the Burn Zone gas flow formula becomes:

[ Cooler Flow - Vent Gas Flow ]


[1+S]

BurnMeasurements
(2) Oxygen Zone Gas =

To compute the Burn Zone gas flow by oxygen measurements, use the following
formula:

21 - Z
Y- Z

where:
Y Burn
= Zone
measured
Gas, Burn Zone
Nm3/hr inlet oxygen
(SCFH) = content, mole-%
x AU
Z = measured Burn Zone outlet oxygen content, mole-%
Au = upper combustion air,Nm3/hr (SCFH)
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 36 OF

NOTE: The Regeneration Tower must be in the black burn condition (upper air
injection only).

2.1.5Burn zone bed/reheat zone bed temperature

The operating conditions in the regeneration section affect the "bed” temperatures in the
Burn Zone. The "bed" temperatures give a very good indication of the coke burning in
the Burn Zone and should be recorded regularly. From top to bottom in the Burn Zone,
the “bed” temperatures form a profile. There are three rules concerning the bed profile.
First, the peak temperature should be located about 40% down from the top of the Burn
Zone, where the rate of coke burning is greatest. Second, the two Reheat Zone “bed"
temperatures should be the same (i.e., a "flat” profile) because coke burning is
essentially complete at the bottom of the Burn Zone. Third, a change in profile alerts the
operator to a change in Regeneration Tower operating parameters.

The “bed" temperatures are a function of the Burn Zone inlet oxygen concentration the
catalyst circulation rate, the spent catalyst coke, and the regeneration gas rate. The
temperatures in the bed rise whenever or wherever the rate of coke burning increases.
The recommended maximum peak “bed” temperature in the Burn Zone is 593 ºC
(1,100 ºF). Higher temperatures could cause damage to catalyst and equipment in the
Burn Zone.

The operating conditions that increase the temperature of the peak are:

Increasing Burn Zone oxygen concentration

The operating conditions that lower the location of the peak or increase the temperatures
at the bottom of the bed are:

Increasing catalyst circulation rate


Decreasing Burn Zone oxygen concentration
Increasing spent catalyst coke
Decreasing Burn Zone gas rate (by screen plugging)

In order to decrease the rate of surface area decline, it is recommended that the Burn
Zone "bed" temperatures be minimized, provided that coke burning is completed in the
Burn Zone.

A WORD OF CAUTION

Although the "bed” temperature are useful, they are not a substitute for the Burn Zone
oxygen analyzer. When the oxygen analyzer is out-of-service or not calibrated properly,
the operator should initiate a Hot Shutdown immediately. The operator should not
attempt to resume coke burning until the analyzer is working properly again.

The “bed” temperatures are also not a substitute for the General Operating Curve. The
operator should operate the Regeneration Tower in accordance with the General
Operating Curve,

DO NOT CONTROL THE REGENERATION TOWER USING THE “BED”


TEMPERATURES ALONE.

2.1.6Regeneration tower pressure

The operator controls the Regeneration Tower pressure using the pressure controller of
the Separator (300-V2), depending on the design. It is the vessel where the gases vent
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 37 OF

from the Look Hopper Disengaging Zone. A differential pressure controller keeps the
Regeneration Tower at the same pressure as the Lock Hopper Disengaging Zone.

The recommended operating pressure for the Regeneration Tower is 2.5 kg/cm 2g (35
psig). Low pressure decreases the coke burning capacity of the Burn Zone. High
pressure decreases the water removal of the Drying Zone.

2.1.7Chlorination gas flow

The oxygen analyzer controls the chlorination gas flow indirectly by controlling the
excess air vent flow from the Drying Zone. The remainder of the air from the Drying
Zone becomes the chlorination gas. The chlorination gas promotes the
chlorination/oxidation step, but it is also the air required for coke burning. This means
the chlorination gas flow rate depends on the catalyst circulation rate and the spent
catalyst coke. The greater the rate of coke burning, the higher the chlorination gas flow
will be.

The recommended operating range for the chlorination gas flow is 25-150 % of design.

The chlorination gas flow rate is not measured directly. Instead it is calculated by a
function block in the DCS. The block subtracts the excess air flow rate from the drying
air rate. It displays this value as the chlorination gas flow rate.

2.1.8Regeneration catalyst chloride

The operator controls the regenerated catalyst chloride content using the Organic
Chloride Injection Pump. The pump injects an organic chloride compound into the
Chlorination Zone. The greater the injection rate, the higher the regenerated catalyst
chloride will be.

The recommended operating range for the regenerated catalyst chloride is 1.1-1.3 wt-%
chloride, depending on the catalyst type. Within this range, the catalyst’s activity and
selectivity are optimum.

The organic chloride injection rate can be measured by two methods: by the chloride
flow meter and by the injection sight glass. The flow meter only indicates the presence
of chloride injection on the control panel, this is due to the pulsating nature of the flow
from the injection pump. The injection rate should be double-checked daily at the pump
using the sight glass on the organic chloride drum for an accurate flow measurement.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 38 OF

To determine the required organic chloride injection rate, calculate as in the following
example:

EXAMPLE

Chloride Makeup Rate

If the current Regeneration Section operation is:

Actual spent catalyst chloride 0.95 wt-%


Desired oxidized catalyst chloride 1.20 wt-%

then the required chloride makeup rate is:

Chloride Desired oxidized Actual spent


Makeup = catalyst chloride - catalyst chloride
Rate (weight %) (weight %)
(weight %)
= 1.20 - 0.95 = 0.25 wt-%

Organic Chloride Injection Rate

If the current Regeneration Section operation is:

Catalyst circulation rate 1,134 kg/hr (2,500 pph)

then the chloride injection rate is:

1,134 Kg/hr x 0.0025 = 2.835 Kg/hr chloride


(2,500 pph x 0.0025 = 6.25 pph chloride)

If the organic chloride compound that is being used is 1,1,1 trichloroethane (1,1,1
TCE), then the rate of injection of the organic chloride compound is:

2.835 kg chloride kg 1,1,1 TCE 754.8 cc 1,1,1 TCE


hour 0.7978 kg chloride kg 1,1,1 TCE

6.25 pounds chloride pound 1,1,1 TCE x 342.3 cc 1,1,1 TCE


x
hour 0.7978 pounds chloride pound 1,1,1 TCE

2,682 cc 1,1,1 TCE


hour x x

This =example can be put in chart form for easier use. An example of a typical chart for
a 3,000 pph Pressurized Regeneration Section using 1,1,1 TCE is shown in Figure 2.1-
4. To repeat this example using Figure 2-4, start at 2,500 pph on the circulation rate
axis. Move vertically to the 0.25 % makeup line. Move horizontally to the left to the
injection rate axis. Read 2,682 cc/hr.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 39 OF

Note: As the catalyst ages and experiences surface area decline, the chloride injection
required to maintain the chloride level on the catalyst will increase. The calculational
method indicated above, while valid, is best understood as a minimum chloride injection
rate, and used as a starting point for setting the injection rate.

2.1.9Drying air flow

The operator controls the total drying air rate on flow control using the drying air
control valve. Dry air strips water off the catalyst base. The drier the catalyst is before
it re-enters the Platforming reactors, the better its overall performance will be.

The recommended drying air rate is 100% of the design rate. The drying air should be
kept constant at this rate at all times.

The drying air itself must be dry in order to dry the catalyst. The moisture content of the
dried air must be checked regularly. There is a sample tap on the Air Dryer outlet for
connecting a moisture analyzer or a dew point analyzer, the recommended moisture
content of the air is 5 ppmv.

2.1.10Cooling air flow

A portion of the air flow from the Air Dryer is split off to the Cooling Zone. The
operator controls the cooling gas flow rate on flow control using the cooling gas control
valve.

The recommended cooling air rate is that which is required to maintain the catalyst in
the Nitrogen Seal Drum at the design temperature, typically, 150 ºC (300 ºF). This
temperature should equal the temperature of the booster gas supplied to the Lock
Hopper and the L-Valve Assembly.

2.1.11Reduction gas flow

The operator controls the reduction gas flow rates (upper and lower reduction gas) by
adjusting hand operated control valves for each flow. The total and lower reduction gas
flows are measured directly with the upper reduction gas flow determined by
subtraction. Hydrogen in the booster gas from the Platforming unit reduces the
catalyst’s metals, e.g., platinum.

The recommended reduction gas rate is 100% of the design rate. The reduction gas
should be kept constant at this rate at all times.

2.1.12Zone inlet temperatures

The operator controls the zone inlet temperatures using temperature controllers.

The recommended zone inlet temperatures are:

Burn Zone 477 ºC (890 ºF)


Chlorination Zone 510 ºC (950 ºF)
Drying Zone 565 ºC (1,050 ºF)
Upper Reduction Zone 377 ºC (710 ºF)
Lower Reduction Zone 550 ºC (1,020 ºF)
Lock Hopper Surge Zone 150 ºC (300 ºF)
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 40 OF

2.1.13Lift gas flow

The operator controls the total lift gas rate to each L-Valve Assembly on flow control
using the primary lift gas control valve.

The recommended total lift gas rate is 100% of the design rate. The lift gas rate should
be kept constant at this rate regardless of the catalyst circulation rate. High total lift gas
rate causes pipe erosion and makes catalyst fines. Low total lift gas rate may stop lifting
and plug the lift line.

The total lift gas flow splits into two streams - a primary stream and a secondary
stream. The primary lift gas stream enters at the bottom of the L-Valve Assembly and
the secondary lift gas stream enters through the side of the catalyst transfer pipe leading
to the lift line.

PRIMARY LIFT GAS

The total lift gas flow controller controls the primary lift gas control valve to keep the
total lift gas flow constant. The controller automatically adjusts the primary lift gas
when the secondary lift gas changes.

SECONDARY LIFT GAS

The pressure drop in the lift line above the L-Valve Assembly controls the secondary lift
gas flow on cascade using the secondary lift gas control valve. The recommended
operating range of the secondary lift gas flow is 0-20% of the design total lift gas flow.
The secondary lift gas controls the catalyst lifting rate. When the secondary lift gas rate
increases, then the rate of catalyst lifting increases. When it decreases, lifting decreases.

2.1.14L-Valve assembly inlet differential pressure

A differential pressure controller controls the pressure drop across the catalyst inlet line
into each L-Valve Assembly. The pressure drop into each L-Valve Assembly inlet should
be the design pressure drop.

SPENT CATALYST L-VALVE ASSEMBLY

The control valve on the nitrogen supply line to the Disengaging Hopper controls the
pressure drop from the Spent Catalyst L-Valve Assembly to the Catalyst Collector. The
L-Valve is maintained at a pressure higher than the Catalyst Collector. The upward flow
of nitrogen that this provides purges hydrogen gas from the catalyst as it leaves the
Catalyst Collector. Too high of a pressure drop slows the flow of catalyst into the L-
Valve Assembly. Too low of a pressure drop may insufficiently purge the catalyst and
allow hydrogen gas into the circulating nitrogen.

REGENERATED CATALYST L-VALVE ASSEMBLY

The control valve on the makeup gas line into the Lock Hopper Surge Zone controls the
pressure drop between the Surge Zone and the Regenerated Catalyst L-Valve Assembly.
The pressure drop is maintained near zero. Positive pressure drop (Surge Zone higher
pressure) leaks gas into the L-Valve Assembly and lifts the catalyst too quickly.
Negative pressure drop (L-Valve higher pressure) slows the flow of catalyst into the L-
Valve. The operator should occasionally check this control valve during an entire Lock
Hopper cycle. If the control valve goes wide open or completely shut (i.e., out of range),
then the maintenance personnel should check the Makeup Valve. The Makeup Valve's
programmed ramping should keep the control valve in range.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 41 OF

2.1.15Elutriation gas flow

The operator controls the elutriation gas flow using the flow control valve. The
elutriation gas flow should be 100% of the design rate. Elutriation gas removes chips of
catalyst and fines from the circulating catalyst. Low gas flow allows chips and fines to
enter the Regeneration Tower and plug the screens. Fines also cause lifting problems.
High gas flow carries out too many whole pills with the chips and fines.

Catalyst Fines Surveys should be done regularly. Catalyst Fines Surveys test the
efficiency of fines removal and optimize the elutriation gas flow. The Catalyst Fines
Survey Procedure is in the Special Procedures section (Section 6.9).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 42 OF

FIGURE2.1-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 43 OF

FIGURE2.1-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 44 OF

FIGURE2.1-3
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 45 OF

FIGURE2.1-4
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 46 OF

2.2Process Flow and Control

CCR tower structure is located south of the Naphtha Hydrotreating Process Unit, Uint-
200, Platforming Process Unit, Unit-300 and Platforming Process CCR Section, Unit-
312 area and faces Reactors, 300-R1/300-R2/300-R3 to minimize catalyst transfer
lines. To ease catalyst transfer by lift gas. CCR catalyst handling vessels are stacked in
nearly vertical line in the structure. Figure 1.2-1 shows a simplified flow diagram of the
Continuous Catalyst Regeneration (CCR) section. The CCR section performs two
functions; Catalyst regeneration and catalyst circulation.

This section outlines the logic requirements for the operation of the Lock Hopper
Sequence, the Makeup Valve, the Isolation Systems, the Catalyst Flow Interrupt
Systems, the Regeneration Systems, the Valve Verification System, and the Bypass
Switches. This explanation has been simplified to include only those items that the
operator can check for proper operation. For a complete explanation of the logic, refer
to the manual for the UOP PPS&E Regenerator Control System (RCS).

2.2.1Catalyst flow control

The Catalyst Flow Control in the Regenerator Control System (RCS) controls the
catalyst circulation rate throughout the entire Reactor and Regenerator system. A
description of the catalyst flow control functionality is given in Section 1.2.3.2.

2.2.1.1Catalyst flow pushbutton

The Catalyst Flow Pushbutton starts and stops the transfer of regenerated catalyst from
the Lock Hopper to the Reactors.

The Catalyst Flow Pushbutton has only two positions: ON and OFF. An indicator on the
control panel shows the position of the pushbutton.

ON

To start transferring catalyst, the following condition must be met:

(1) The Regenerator is not in a Hot Shutdown.

Then, when the operator depresses the Catalyst Flow Pushbutton, the catalyst transfer
starts. The indicator changes from OFF to ON.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 47 OF

OFF

The Lock Hopper stops automatically when a Hot Shutdown occurs.

The operator can manually stop the catalyst transfer at any time in order to begin the
Hot Shutdown Procedure. If the Catalyst Flow Pushbutton is depressed while catalyst is
transferring, then the transfer stops. The indicator changes from ON to OFF.

2.2.1.2Catalyst circulation rate setpoint

The Catalyst Circulation Rate Setpoint is used by the Regenerator Control System to
control the catalyst circulation rate. The operator sets the setpoint in three steps.

First, the operator decides on the desired catalyst circulation rate as required by the
Reactor Section and Regeneration Section operating conditions. This catalyst
circulation rate should not be above the design catalyst circulation rate.

Next, the operator computes the Catalyst Circulation Rate Setpoint using the formula
below:

Desired Catalyst Circulation Rate


Catalyst Circulation Rate, % = (pounds/hour)
Design Catalyst Circulation Rate
(pounds/hour)

The result should be a number between 0 and 100%. The higher the desired catalyst
circulation rate, the higher the computed Catalyst Flow Setpoint will be.

Finally, the operator enters the Catalyst Circulation Rate Setpoint into the Regenerator
Control System (RCS). The operator enters the setpoint at the control panel. Even
though the setpoint can be adjusted up to 100%, the operator should not enter a setpoint
that results in a catalyst circulation rate above the allowable catalyst circulation rate.
The General Operating Curve (see Figure 2.1-1) may limit the circulation rate to less
than 100%. And even though the desired setpoint may be less than 10% the setpoint can
only be adjusted down to a minimum of 10%.

The RCS utilizes the Catalyst Circulation Rate Setpoint to generate the setpoint for the
Regenerated Catalyst Lift Line Differential Pressure Controller. By adjusting the lift line
DP controller setpoint the catalyst circulation rate is adjusted. The RCS then compares
the Catalyst Circulation Rate Setpoint to the actual Averaged Catalyst Circulation Rate
as determined by the Lock Hopper cycle time (see Section 2.2.2.1), and adjusts the lift
line DP controller setpoint up or down until the setpoint and actual catalyst circulation
are in agreement.

When catalyst circulation is started from zero, the lift line controller setpoint is ramped
upward from 0% at a rate determined by the Regenerated Catalyst Lift Line Differential
Ramp Rate. This ramp rate is set so as to gradually increase the Reduction Zone
catalyst level, and thus gradually increase the spent catalyst lift rate. The rate of
increase of the spent catalyst lift rate must be slow so that the spent catalyst lift line DP
generated does not cause the DP between the L-valve assembly and the Catalyst
Collector to fall out of its control range. This ramp rate is also used during normal
operations when the actual catalyst circulation rate differs by more than 10% from the
setpoint. For initial operation of the unit this ramp rate should be set slow, 2-5%/min,
then adjusted higher with greater operating experience.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 48 OF

When the actual catalyst circulation rate and the catalyst circulation setpoint are within
10% of each other, the RCS will make incremental changes in the lift line DP setpoint
based on the error in percent toward the desired circulation rate every time a Lock
Hopper cycle is completed. The size of the lift line DP setpoint changes will depend on
the Catalyst Flow Rate Gain Constant.

2.2.1.3Spent catalyst lift rate limiter

Whenever catalyst circulation is started, the RCS slowly ramps up the spent catalyst lift
rate from 0% to 100% at a rate given by the Spent Catalyst Lift Line Differential Ramp
Rate. The ramp occurs at a rate set slow enough so that the lift line DP generated does
not cause the DP between the L-valve assembly and the Catalyst Collector to become
too high. At some point during the ramp, the signal from the Reduction Zone level
controller will take control and reset the lift line DP controller. The ramp rate for both
the regenerated and the spent lift lines should be set the same. For initial operation of
the unit this ramp rate should be set slow, 2-5%/min, then adjusted higher with greater
operating experience.

2.2.2Lock hopper sequence

The Lock Hopper transfers catalyst from the Regeneration Tower into the Regenerated
Catalyst L-Valve Assembly. The catalyst is moved through the Lock Hopper Zone of the
Lock Hopper in small batches. The Regenerator Control System controls the sequencing
of this batch operation.

The cycle time of this batch operation indicates the catalyst circulation rate. The more
often the Lock Hopper Zone cycles, the faster the catalyst circulation rate. In this way,
the flow of catalyst through the Lock Hopper monitors the catalyst circulation rate
throughout the entire Reactor and Regenerator system.

The Lock Hopper cycles through five basic steps in a sequence. Two of the steps,
PRESSURE and DEPRESSURE, have two sub-steps. The five basic steps in one cycle
of the Lock Hopper are:

BASIC OPERATION

READY Lock Hopper Zone, full of catalyst and at Disengaging Zone


pressure, waits for signal to start the cycle.

PRESSURE Lock Hopper Zone is pressured up in a programmed pattern to


equalize the pressure between it and the Surge Zone.

UNLOAD Catalyst is unloaded from the Lock Hopper Zone to the Surge
Zone.

DEPRESSURE Lock Hopper Zone is depressured in a programmed pattern to


equalize the pressure between it and the Disengaging Zone.

LOAD Catalyst is loaded into the Lock Hopper Zone from the
Disengaging Zone.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 49 OF

At the end of the LOAD step, the Lock Hopper returns to the READY step. When this
cycle repeats over and over again, catalyst moves through the Lock Hopper.

Three logic-operated valves control the pressuring and depressuring of the Lock Hopper
Zone: two Equalization Valves and one Makeup Valve. Valve (XV-25) is the Upper
Equalization Valve between the Lock Hopper Zone and the Disengaging Zone. XV-26 is
the Lower Equalization Valve between the Lock Hopper Zone and the Surge Zone. At no
time during the cycle should both Equalization Valves be open at the same time. Valve
XV-27 is the Makeup Valve to the Surge Zone for pressuring up the Lock Hopper Zone
with booster gas. Excess gas from depressuring the Lock Hopper Zone is vented from
the Disengaging Zone.

The Upper (XV-25) and Lower (XV-26) Equalization Valves, along with the Makeup
Valve (XV-27) change position during the PRESSURE and DEPRESSURE steps.
During the PRESSURE step, the Upper Valve closes completely, the Lower Valve opens
fully, and the Makeup Valve opens slightly more and then closes partially. During the
DEPRESSURE step, the Lower Valve closes completely, the Upper Valve opens fully,
and the Makeup Valve closes slightly and then reopens partially. The opening and
closing of these three valves is controlled by the Lock Hopper Control System in the
Regenerator Control System.

For the Upper (XV-25) and Lower (XV-26) Equalization Valves, their programmed
patterns for opening and closing are always the same. These patterns are programmed in
the RCS and never change.

For the Makeup Valve (XV-27), however, its programmed pattern for opening and
closing can change. The Makeup Valve can operate in any one of three different modes.
All three modes have one goal: to supply makeup gas for pressuring the Lock Hopper
Zone while keeping the differential pressure between the Lock Hopper and the
Regenerated Catalyst L-Valve Assembly stable. The correct Makeup Valve mode at any
one time depends on several conditions, including 1) whether or not the Lock Hopper is
cycling normally, 2) how many times the Lock Hopper has cycled after it was last
started, and 3) whether or not the operator chooses to change the programmed pattern
for the Makeup Valve. The three modes of the Makeup Valve (XV-27) are described in
more detail later in this section.

2.2.2.1Lock hopper cycle time

The Lock Hopper Cycle Time is the time from the start (i.e., pressure step) of one
Lock Hopper cycle until the start of the next cycle. The start of the cycle is initiated by
a low level in the Lock Hopper Surge Zone. The RCS computes the actual catalyst
circulation rate from the measured Lock Hopper Cycle Time.

Calibrated Lock Hopper Load Size


(lbs)
Actual Catalyst Circulation (%) = ´
Design Actual L.H. 360,000
Catalyst ´ Cycle Time
Circulation (sec)
Where : (lb/hr)

The Calibrated Lock Hopper Load Size is measured according to the Startup
Preparation and the Startup Procedures.

The actual catalyst circulation rate is reported as two values. The first is the
instantaneous rate, updated at the end of each Lock Hopper cycle, equal to Actual
Catalyst Circulation as shown above. The second is a running average of the last “n"
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 50 OF

(this number is adjustable) instantaneous rate calculations called the Averaged Catalyst
Circulation Rate. The value for “n” is determined from the Number of Lock Hopper
cycles for Average Catalyst Flow Rate.

2.2.2.2Long cycle alarm

The Long Cycle Alarm alerts the operator of a slow Lock Hopper cycle. A slow Lock
Hopper cycle is defined as when the cycle is so long that the Lock Hopper cannot keep
up with the required catalyst circulation rate. That is, catalyst is being withdrawn from
the Surge Zone faster than it can be supplied by the Lock Hopper Zone. This situation is
indicated by a low level alarm in the Surge Zone during the DEPRESSURE or LOAD
steps. So, if the Lock Hopper cycle is held up because of a malfunction, then the Surge
Zone level will go low and sound the Long Cycle Alarm. A Long Cycle Alarm will cause
a Hot Shutdown of the Regeneration Tower. The Hot Shutdown alarm condition will last
for one minute and then reset. At this time the Regeneration Tower can be restarted if so
desired, but if the conditions that caused the Long Cycle Alarm have not been rectified,
the alarm will soon sound again.

2.2.2.3Abnormal unload/load alarms

There are four alarms that alert the operator of a problem with the loading and
unloading of the Lock Hopper. If any alarm sounds during two consecutive Lock
Hopper cycles, then a Hot Shutdown occurs.

(a) Fast Unload Alarm

The Fast Unload Alarm alerts the operator that the Lock Hopper Zone is
unloading too quickly. The alarm is activated by the Fast Unload Timer. The Fast
Unload Timer starts to count down when entering the UNLOAD step. The alarm
will sound if the Lock Hopper Zone unloads to below the low-level instrument
before the Fast Unload Timer times out.

(b) Slow Unload Alarm

The Slow Unload Alarm alerts the operator that the Lock Hopper Zone is
unloading too slowly. The alarm is activated by the Slow Unload Timer. The
Slow Unload Timer starts to count down when the Fast Unload Timer times out.
The alarm will sound if the Lock Hopper Zone does not unload to below the low-
level instrument before the Slow Unload Timer times out.

(c) Fast Load Alarm

The Fast Load Alarm alerts the operator that the Lock Hopper Zone is loading
too quickly. The alarm is activated by the Fast Load Timer. The Fast Load Timer
starts to count down when entering the LOAD step. The alarm will sound if the
Lock Hopper Zone loads up to the high-level instrument before the Fast Load
Timer times out.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 51 OF

(d) Slow Load Alarm

The Slow Load Alarm alerts the operator that the Lock Hopper Zone is loading
too slowly. The alarm is activated by the Slow Load Timer. The Slow Load
Timer starts to count down when the Fast Load Timer times out. The alarm will
sound if the Lock Hopper Zone does not load up to the high-level instrument
before the Slow Load Timer times out.

2.2.2.4Lock hopper cycle counter

The Lock Hopper Cycle Counter counts the total number of times the Lock Hopper
Zone unloads a full load of catalyst. The counter advances one digit when the Lock
Hopper Zone unloads to below the low-level instrument following a cycle in which the
Lock Hopper Zone had loaded up to the high-level instrument. In this way, the Lock
Hopper Cycle Counter advances only when the Lock Hopper Zone transfers a full load
of catalyst.

2.2.2.5Unload/load timers

There are two timers that time how long it takes for the Lock Hopper Zone to unload
and load during each Lock Hopper cycle. The most recent unload time and the most
recent load time are displayed on the control panel for troubleshooting purposes.

The Unload Timer starts to time when the Upper Equalization Valve begins to close at
the start of the PRESSURE step. It stops timing and displays the elapsed time when any
of the following condition occur:

(1) The Catalyst Flow Pushbutton indicator changes from Run to STOP; or

(2) The Lock Hopper Zone unloads to below the low-level instrument; or

(3) The Long Unload Timer times out.

The Load Timer starts to time when the Lower Equalization Valve begins to close at the
start of the DEPRESSURE step. It stops timing and displays the elapsed time when any
of the following conditions occur:

(1) The Catalyst Flow Pushbutton indicator changes from RUN to STOP; or

(2) The Lock Hopper Zone loads up to the high-level instrument; or

(3) The Long Load Timer times out.

2.2.2.6Lock hopper level switch malfunction alarm

The Lock Hopper Level Switch Malfunction Alarm alerts the operator of a level
instrument malfunction. If the low-level instrument in the Lock Hopper Zone indicates a
low level and the high-level instrument indicates a high level for more than a prescribed
period of time (normally two seconds), then the Level Switch Malfunction Alarm will
sound. The alarm causes a Hot Shutdown.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 52 OF

2.2.2.7Lock hopper equalization valve alarm

The Lock Hopper Equalization Valve Alarm alerts the operator of a problem with the
positions of the Lock Hopper Equalization Valves. The closed position of the
Equalization Valves is indicated by position switches. The alarm is activated when both
Equalization Valves are open, or more precisely, “not closed,” at the same time for more
than a prescribed period of time (normally two seconds). When one Equalization Valve
is commanded closed, it must confirm closed before the other Equalization Valve is
commanded open. However, if the first Equalization Valves does not remain confirmed
closed when the second Equalization Valve is not confirmed closed, then if both
Equalization Valve position switches indicate “not closed” for more than two seconds,
the Lock Hopper Equalization Valve Alarm sounds. The alarm causes a Hot Shutdown.

2.2.2.8Initial cycle sequence

The Initial Cycle Sequence starts the Lock Hopper in a special way when the Lock
Hopper is first started. This sequence compensates for the unpredictable conditions of
pressure and catalyst level that exist in the Lock Hopper Zone, which depend on when
the Lock Hopper was stopped. For these reasons, the Initial Cycle Sequence starts the
Lock Hopper in the DEPRESSURE-2 step to depressure the Lock Hopper Zone.
Furthermore, the Fast Load and Slow Load Alarms are disabled for one cycle.

The following sheets (Figures 2.2-1 through 2.2-11) are an outline of the logic steps.
These sheets are in the order of a normal cycle sequence from the READY step until the
LOAD step. The sheets for a Initial Cycle Sequence – from the STOP step until the
LOAD step – precede the sheets for the normal cycle sequence.

2.2.3Makeup valve

The Makeup Valve (XV-27) supplies booster gas to the Surge Zone of the Lock Hopper
for pressuring the Lock Hopper Zone while keeping the differential pressure between the
Lock Hopper and the Regenerated Catalyst L-Valve Assembly stable. The Makeup
Valve can operate in three different modes, but at any time it can operate in only one
mode. The three modes of the Makeup Valve are:

MODE NO. 1: FEEDTHROUGH MODE (CLOSED LOOP CONTROL)

In Mode No. 1, the Makeup Valve (XV-27) operates like a differential pressure control
valve. It opens and closes depending on the signal from the differential pressure
instrument between the Lock Hopper and the Regenerated Catalyst L-Valve Assembly.
In this way, the differential pressure instrument controls not only its own control valve
but also the Makeup Valve. Both valves operate together in parallel.

Mode No. 1 is used when the Lock Hopper is stopped in order to compensate for the
unpredictable conditions that exist in the Lock Hopper from when it was stopped. Mode
No. 1 is also intended to be used during the first several cycles when the Lock Hopper is
restarted in order to compensate for the changing conditions that occur in the Lock
Hopper until process conditions are once again constant from cycle to cycle. The
Makeup Valve will operate in this mode until another mode is selected by the process
operator after the catalyst flow is started.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 53 OF

MODE NO. 2: RAMP TABLE MODE (PROGRAMMED RAMP)

Mode No. 2 is the normal operating mode. The Makeup Valve (XV-27) follows its
programmed pattern, and this programmed pattern remains the same from cycle to
cycle.

The programmed pattern for the Makeup Valve in Mode No. 2 is either the default
pattern or the learned pattern. The default pattern is permanently programmed in the
RCS and never changes. The learned pattern is a modified version of the default pattern
after it has been changed by operation in Mode No. 3. The RCS is capable of storing
different programmed patterns off-line which can be read into the RCS for future on-
line use.

Mode No. 2 is useful when the programmed pattern for the Makeup Valve keeps the
differential pressure between the Lock Hopper and the Regenerated Catalyst L-Valve
Assembly stable and the conditions in the Lock Hopper are constant from cycle to cycle.

MODE NO. 3: ADAPTION MODE

In Mode No. 3, as in Mode No. 2, the Makeup Valve (XV-27) follows its programmed
pattern. However, in Mode No. 3 the RCS changes the programmed pattern of the
Makeup Valve after each Lock Hopper cycle.

The Valve Ramping PLC “learns” what changes to make to the programmed pattern of
the Makeup Valve by monitoring both the indication and the output of the differential
pressure indicator/controller between the Lock Hopper and the Regenerated Catalyst L-
Valve Assembly. Then, the RCS will change the Makeup Valve’s programmed pattern
for the next Lock Hopper cycle using what it “learns" during the current Lock Hopper
cycle.

At each moment in the Makeup Valve’s current cycle, the RCS computes the changes in
the Makeup Valve's programmed pattern for the same moment in the next cycle using
the information below:

- Pressure differential between the Lock Hopper Surge Zone and the L-Valve
Assembly

- The controller output of the PDIC for the above

- Tuning constants

Mode No. 3 is useful when changes are needed to the programmed pattern for the
Makeup Valve. This may be necessary when there are significant differences between
the actual and design conditions in the Lock Hopper or when the process conditions in
the Lock Hopper are changing significantly from cycle to cycle.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 54 OF

The Makeup Valve (XV-27) has the following features;

(1) Feedthrough Counter

The operator uses the Feedthrough Counter to set the number of Lock Hopper
cycles that the Makeup Valve (XV-27) will operate in Mode No. 1 after either
Ramp Table or Adaptation mode is selected. This helps prevent the RCS from
using what it “learned” shortly after the cycle has been restarted. The counter is
adjustable from 0 to 5 cycles, usually it is set at 3 cycles.

(2) Adaption Cycles Counter

The operator uses the Adaptation Cycles Counter to set the number of Lock
Hopper cycles that the Makeup Valve (XV-27) will operate in Mode No. 3 when
the Adaptation mode is selected. This is useful when the operator wishes to
change the programmed pattern of the Makeup Valve, but only over a temporary
time period. The counter is adjustable from 1 to 20 cycles.

2.2.4Isolation systems (Figures 2.2-12, 2.2-13, and 2.2-14)

Isolation Systems keep the environment in the Regeneration Tower separate from the
environments in the rest of the Regeneration Section. The Regeneration Tower is an
oxygen-containing environment, while other areas of the Regeneration Section are
hydrogen/hydrocarbon-containing environments. The Isolation Systems prevent a
potentially hazardous mixture of those two environments.

There are two Isolation Systems. The Spent Catalyst Isolation System is on the catalyst
inlet to the Regeneration Tower, and it isolates the Regeneration Tower from the
Reactor. The Regenerated Catalyst isolation System is on the catalyst outlet from the
Regeneration Tower, and it isolates the Regeneration Tower from the Lock Hopper.

PRINCIPLE

Both Isolation Systems are alike. Each has a “High Pressure Zone”, two Isolation
Valves, a Pressure Valve, and a differential pressure control valve. There are two
differential pressure controllers. The top one is between the “High Pressure Zone” and
the vessel above it. The bottom one is between the “High Pressure Zone" and the vessel
below it.

The Spent Catalyst system does not have the lower differential pressure controller. It is
assumed in this case that the Disengaging Hopper will always be at a higher pressure
than the Regeneration Tower.

These two differential pressures are the key indications that the Isolation System is
keeping the environments above and below the Isolation System separate. Nitrogen
purges into the “High Pressure Zone” on differential pressure control. The “High
Pressure Zone” is at a slightly higher pressure than both the vessel above and below the
Isolation System. This “nitrogen bubble" prevents gases in the vessel above from
leaking downward and it prevents gases in the lower vessel from leaking upward. If
either the top or bottom differential pressure becomes too low, the "nitrogen bubble” in
the High Pressure Zone may be lost. On the other hand, if the top differential pressure
becomes too high, the flow of catalyst downward may be halted. So, it is very important
that these two differential pressures – top and bottom – are controlled, measured, and
monitored accurately.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 55 OF

First, each differential pressure, top and bottom, is controlled by one different pressure
indicator-controller. One control valve, the nitrogen purge to the High Pressure Zone,
controls both differential pressures by a signal selector.

Second, each differential pressure, top and bottom, is measured by two independent
differential pressure instruments. One of the instruments is the differential pressure
indicator/controller that controls the differential pressure. The other instrument is for
indication only. These instruments all operate simultaneously and provide two separate
measurements of the differential pressure.

And third, each differential pressure, top and bottom, is monitored by a two-of-two
voting circuit. This voting circuit is located in the Regenerator Control System. The two
independent differential pressure indications are inputs to this voting circuit. If one
indication is higher than the low-differential trip setting then the voting circuit is
satisfied. This is one of the requirements for opening the Isolation System. If both
indications are lower than the low-differential trip setting, then the voting circuit is not
satisfied. And if this condition persists for longer than a set period of time, the Isolation
System will close (if it was open). This voting circuit allows operation without the need
for a shutdown in case one of the differential pressure instruments must be serviced.

OPERATION

The Spent Catalyst Isolation Open Pushbutton opens the Spent Catalyst Isolation
System and the Regenerated Catalyst Isolation Open Pushbutton opens the Regenerated
Catalyst Isolation System. Both Isolation Systems must be open in order to circulate
and regenerate catalyst.

Both Isolation Systems have only two conditions OPEN and CLOSED. An indicator on
the control panel shows the condition of each Isolation System. Limit switches indicate
the positions of the Isolation Valves.

OPEN

Opening an Isolation System means opening its two Isolation Valves and closing its
Pressure Valve.

To open an Isolation System (either Upper or Lower), the following conditions must be
met:

(1) The Regenerator Run-Stop pushbutton is in “RUN," and

(2) One of the indicators for both the top and the bottom differential pressures are
higher than the low-differential trip settings (two-of-two voting system).

(3) (For Spent Catalyst Isolation only.) Reduction Zone above Low Level.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 56 OF

Then, when the operator depresses the Isolation Open Pushbutton, that Isolation System
opens. First, its Pressure Valve is commanded closed and confirms closed. Then, its
Isolation Valves are commanded open and confirm open. Its indicator changes from
CLOSED to OPEN.

CLOSED

Closing an Isolation System means closing its two Isolation Valves and opening its
Pressure Valve. This pressures the pipe between the two Isolation Valves to nitrogen
header pressure and prevents cross-mixing between the two vessels.

An Isolation System (either Upper or Lower) closes automatically when:

(1) A Cold Shutdown occurs (Regenerator Run/Stop to Stop), or

(2) One of the indicators for either the top or the bottom differential pressures are
lower than the low-differential trip settings (two-of-two voting system). The
indicators must be low for a time longer than 5 seconds.

(3) (For Spent Catalyst Isolation only.) Reduction Zone below Low Level.

When an Isolation System closes, first, its Isolation Valves are commanded closed and
confirm closed. Next, its Pressure Valve is commanded open and confirms open. Its
indicator changes from OPEN to CLOSED. If its Isolation Valves do not confirm closed
within the time period of its Purge Delay Timer (usually 10 seconds), a Cold Shutdown
occurs and its Pressure Valve is commanded open anyway. In this way, a limit switch
malfunction will not prevent the Pressure Valve from opening. If the Pressure Valve does
not confirm open, a Cold Shutdown occurs.

Any time either isolation system is tripped closed, a Hot Shutdown will occur. The
isolation system will continue to give this signal for one minute at the end of which the
Regeneration System can be restarted. An exception to the above is when the Spent
Catalyst Isolation is tripped by a low level in the Reduction Zone. In this case no Hot
Shutdown shall occur so the level can be reestablished.

An Isolation System closes automatically when a Contaminated Nitrogen Shutdown


occurs. Then, only the Upper Isolation System closes as described above. The Lower
Isolation System closes differently. Not only are its Isolation Valves commanded closed,
but so are its Pressure Valve and the control valve for the nitrogen purge to the Purge
Zone. In this way, contaminated nitrogen is prevented from entering the bottom of the
Regeneration Tower.

The operator can manually close both Isolation Systems at any time by depressing the
Isolation System close pushbutton, or if the operator depresses the Regenerator Run-
Stop Pushbutton, then a Cold Shutdown occurs. This closes the Isolation Systems.

REGENERATOR INVENTORY SWITCH

The Regenerator Inventory Switch bypasses the two logic requirements for opening the
Regenerated Catalyst Isolation System. This is useful before startup for loading catalyst
into the Regeneration Section.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 57 OF

The Regenerator Inventory Switch has only two positions: INVENTORY and
NORMAL. An indicator on the control panel indicates when the two logic requirements
are bypassed. The Regenerator Inventory Switch should be in the NORMAL position
during normal operation.

INVENTORY

To inventory the Regeneration Section, the following conditions must be met:

Item Condition
1. Emergency Stop Switch RUN position.
2. Regenerator Run-Stop Pushbutton STOP position.

Then, when the operator turns the Regenerator Inventory Switch to the INVENTORY
position, the two logic requirements for opening the Regenerated Catalyst Isolation
System is bypassed. The indicator labeled REGENERATOR INVENTORY
OPERATION on the control panel lights up. Then, when the operator depresses the
Isolation Pushbutton, the Regenerated Catalyst Isolation System will open.

NORMAL

NORMAL is the position of the Regenerator Inventory Switch during normal operation.
Either of the following conditions will end inventorying of the Regeneration Section:

Item Condition
1. Emergency Stop Switch STOP position.
2. Regenerator Inventory Switch NORMAL position.

Then, the two logic requirements for opening the Regenerator Catalyst Isolation System
are no longer bypassed. The Regenerated Catalyst Isolation System closes. The
indicator labeled REGENERATOR INVENTORY OPERATION on the control panel
turns off.

HAZOP recommendation

Ensure that spectacle blind is closed position when catalyst replacement line is not
in use.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 58 OF

2.2.5Catalyst flow interrupt systems

The catalyst flow from the Reactor and from the Lock Hopper Surge Zone can be
interrupted to prevent low levels in those vessels.

The Regenerator Control System controls the operation of these systems and catalyst
flow will be allowed or interrupted automatically when certain conditions exist.

During normal operation the interrupt systems have no effect on catalyst circulation.
However, during shutdowns, the systems prohibit catalyst transfer in order to maintain
catalyst inventory in the Reactor and the Lock Hopper.

SPENT CATALYST FLOW INTERRUPT

The catalyst flow from the Reactor will be interrupted in two ways depending on the
level at the top of the Reactor. If a low level is indicated by the Reduction Zone LRC
(Level Recorder Controller) the RCS resets the Spent Catalyst Lift Line DP controller to
zero via the low signal selector. In addition, the secondary lift gas control valve (fail
closed) is closed by de-energizing a solenoid in the instrument air line, shutting off the
instrument air supply.

If the Reduction Zone level continues to drop to below the low level indicator switch
point, the Spent Catalyst Isolation will trip. Tripping the isolation will cause the two
isolation valves to close and the nitrogen pressure valve to open.

CLOSED

The following condition will cause a Spent Catalyst Flow Interrupt:

(1) The catalyst level in the Reduction Zone is below the low low-level monitor
switch of the level controller.

Then, the indicator labeled SPENT CATALYST FLOW INTERRUPTED on the control
panel lights up.

OPEN

When the following condition is met, the Spent Catalyst Flow Interrupt will clear:

(1) The catalyst level in the Reduction Zone is above the low-level monitor switch of
the level controller.

Then, the indicator labeled SPENT CATALYST FLOW INTERRUPTED on the control
panel turns off. As during any commencement of catalyst circulation the RCS will ramp
the input signal (via the low signal selector) which resets the Spent Catalyst Lift Line
DP controller.

REGENERATED CATALYST FLOW INTERRUPT

The catalyst flow from the Lock Hopper Surge Zone will be interrupted if the catalyst
level in the Surge Zone falls to a low level. If a low-low level is indicated by the Surge
Zone LR (Level Recorder) the RCS resets the Regenerated Catalyst Lift Line DP
controller to zero catalyst flow. In addition, the secondary lift gas control valve (fail
closed) is closed by de-energizing a solenoid in the instrument air line, shutting off the
instrument air supply.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 59 OF

CLOSED

The following condition will cause a Regenerated Catalyst Flow Interrupt:

(1) The catalyst level in the Surge Zone is below the low low-level monitor switch of
the level indicator.

Then, the indicator labeled REGENERATED CATALYST FLOW INTERRUPTED on


the control panel lights up.

OPEN

When the following condition is met, the Regenerated Catalyst Flow Interrupt will clear.

(1) The catalyst level in the Surge Zone is above the low-level monitor switch of the
level indicator.

Then, the indicator labeled REGENERATED CATALYST FLOW INTERRUPTED on


the control panel turns off.

2.2.6Regenerated catalyst lift line valve

The valve in the regenerated catalyst lift line at the top of the reactor serves to isolate
the Platforming Process Unit reactors from the Regeneration Section under certain
circumstances. The valve may be closed by the process operator from the control center,
or it may be closed automatically by the RCS.

There are two conditions which will signal the RCS to close the lift line valve:

(1) The temperature of regenerated catalyst lift line, as measured by the lift line skin
TC, is above the high-temperature monitor switch of the temperature indicator.
This indicates a back flow of Reduction Zone gas or Reactor gas as a result of a
lift line rupture.

(2) The flow of gas to the Reduction Gas Heater No. 1 AND regenerated catalyst lift
gas are below the low-level monitor switches of both flow indicators.

2.2.7Regeneration systems (Figure 2.2-15)

The Regeneration Systems control the catalyst regeneration. The goal of catalyst
regeneration is to restore the catalyst to a condition that is as close as possible to fresh
catalyst in a way that is safe. The Regeneration Systems follow the logical requirements
to achieve this goal.

The operator starts and stops the Regeneration Systems using pushbuttons and
switches. These pushbuttons and switches must be operated correctly to ensure the
catalyst regeneration is done properly and safely. The Regeneration Systems help ensure
that all of the process requirements are satisfied when a system is started or stopped.
Depending on the actual conditions present, the Regeneration Systems can prevent a
system from starting or it can automatically cause a system to stop.

The operator controls the Regeneration Systems using the following: the Regenerator
Run-Stop Pushbutton, the Nitrogen Pushbutton, the Air Pushbutton, the Chloride
Pushbutton, the Lower Air Supply Line Pushbutton, the Electric Heater Pushbuttons,
and the Emergency Stop Switch.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 60 OF

2.2.7.1Regenerator run-stop pushbutton

The Regenerator Run-Stop Pushbutton starts and stops the Regenerator. The
Regenerator must first be started in order to start any of the other Regeneration
Systems.

The Regenerator Run-Stop Pushbutton has only two positions: RUN and STOP. An
indicator on the control panel shows the position of the pushbutton.

RUN

To start the Regenerator, the following conditions must be met:

Item Condition
1. Spent Catalyst Isolation System Valves XV-5 and XV-7 confirm
closed.
Valve XV-6 confirms open.
2. Regenerated Catalyst Isolation System Valves XV-24 and XV-22 confirm
closed.
Valve XV-23 confirms open.
3. CCR Nitrogen Header Pressure not low.
4. CCR Nitrogen Analyzer Contaminants not high.
5. Regenerator Inventory Switch NORMAL position.
6. Emergency Stop Switch RUN position.

Then, when the operator depresses the Regenerator Run-Stop Pushbutton, the
Regenerator starts. The indicator changes from STOP to RUN.

Once the Regenerator starts, the Regenerator Run-Stop indicator changes from STOP to
RUN. All of the Regenerator conditions remain the same. Starting the Regenerator
simply allows other Regeneration Systems to be started. It allows the Spent Catalyst
and Regenerated Catalyst Isolation Systems to be opened, catalyst circulation to be
started, and the Electric Heaters to be turned on. However, to start any of these systems,
other conditions must be met and their respective pushbuttons must be depressed.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 61 OF

STOP

The Regenerator stops automatically when any of the following conditions occur:

Item Condition
1. Spent Catalyst Isolation System Either Valve XV-5 or XV-7 does
not confirm closed when they
should be closed OR Valve XV-6
does not confirm open when it
should be open.
2. Regenerated Catalyst Isolation System Either Valve XV-24 or XV-22 does
not confirm closed when they
should be closed OR Valve XV-23
does not confirm open when it
should be open.
3. CCR Nitrogen Header Low pressure.
4. CCR Nitrogen Header High contaminants.
5. Regenerator Run-Stop Pushbutton “STOP” by manual operation.
6. Emergency Stop Switch “STOP” by manual operation.

Then, the Regenerator Run-Stop indicator changes from RUN to STOP. If the condition
is high contaminants in the CCR nitrogen header, a Contaminated Nitrogen Shutdown
occurs. With any of the other conditions above, a Cold Shutdown occurs.

The operator can manually stop the Regenerator at any time in order to begin the Cold
Shutdown Procedure. If the Regenerator Run-Stop Pushbutton is depressed while the
Regenerator is running, then the Regenerator stops. The indicator changes from RUN to
STOP and a Cold Shutdown occurs.

2.2.7.2Nitrogen pushbutton

The Nitrogen Pushbutton opens and closes the Nitrogen Valve (XV-15). The Nitrogen
Valve is a fail-open valve that starts and stops the flow of nitrogen to the Cooling Zone
and Drying Zone of the Regeneration Tower. Nitrogen flow must first be started in order
to begin the Startup Procedures.

The Nitrogen Pushbutton has only two positions: ON and OFF. In the ON position, the
Nitrogen Valve (XV-15) is open. In the OFF position, the Nitrogen Valve is closed. An
indicator on the control panel shows the position of the pushbutton. Limit switches
indicate the position of the valve.

ON

The Nitrogen Valve (XV-15) opens automatically when a Hot Shutdown or a Cold
Shutdown occurs. This keeps the Regeneration Tower under a nitrogen environment
when catalyst circulation and catalyst regeneration are stopped.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 62 OF

The operator can manually open the Nitrogen Valve (XV-15) without any preconditions
when doing the Hot Shutdown Procedure. If the Nitrogen Pushbutton is depressed while
the Nitrogen Valve is closed, then the Nitrogen Valve opens. The indicator changes from
OFF to ON.

If the Nitrogen Pushbutton is depressed during a Contaminated Nitrogen Shutdown, the


Nitrogen Valve does not open. In this way, contaminated nitrogen is prevented from
entering the bottom of the Regeneration Tower.

OFF

Closing the Nitrogen Valve (XV-15) manually is an important step in the Startup
Procedures. In the Shutdown Procedures, the Nitrogen Valve is open and it must remain
open until the Startup Procedures are underway. This keeps the Regeneration Tower
under a nitrogen environment. Even in the Startup Procedures, the Nitrogen Valve must
continue to remain open until it is allowable, according to the Startup Procedures, to
open the Lower Air Supply Line Valve (XV-14). The important point is that opening the
Lower Air Supply Line Valve too early can cause serious damage to equipment and
catalyst inside the Regeneration Tower.

When it is allowable, according to the Startup Procedures, to close the Nitrogen Valve,
the operator depresses the Nitrogen Pushbutton. The Nitrogen Valve closes and the
indicator changes from ON to OFF.

The Nitrogen Valve (XV-15) closes automatically when a Contaminated Nitrogen


Shutdown occurs. In this way, contaminated nitrogen is prevented from entering the
bottom of the Regeneration Tower.

2.2.7.3Air pushbutton

The Air Pushbutton opens and closes the Air Valve (XV-13). The Air Valve is a fail-
close valve that starts and stops the flow of air to the Regeneration Tower. Air flow
must be started during the Startup Procedures in order to begin coke burning.

The Air Pushbutton has only two positions: ON and OFF. In the ON position, the Air
Valve (XV-13) is open. In the OFF position, the Air Valve is closed. An indicator on the
control panel shows the position of the pushbutton. Limit switches indicate the position
of the valve.

ON

Opening the Air Valve (XV-13) is an important step in the Startup Procedures that
should not be taken lightly. In the Shutdown Procedures, the Air Valve is closed and it
must remain closed until the Startup Procedures are underway. This keeps the
Regeneration Tower under a nitrogen environment. Even in the Startup Procedures, the
Air Valve must remain closed until it is allowable, according to the Startup Procedures,
to begin coke burning. The important point is that opening the Air Valve too early can
cause serious damage to equipment and catalyst inside the Regeneration Tower.

When it is allowable, according to the Startup Procedures, to open the Air Valve (XV-
13), the operator depresses the Air Pushbutton. The Air Valve opens and the indicator
changes from OFF to ON.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 63 OF

OFF

The Air Valve (XV-13) closes automatically when a Hot Shutdown, a Cold Shutdown,
or a Contaminated Nitrogen Shutdown occurs. This keeps air out of the Regeneration
Tower when catalyst circulation and catalyst regeneration are stopped during these
shutdowns.

The operator can manually close the Air Valve (XV-13) without any preconditions when
doing the Hot Shutdown Procedure. If the Air Pushbutton is depressed while the Air
Valve is open, then the Air Valve closes. The indicator changes from ON to OFF.

2.2.7.4Lower air supply line pushbutton

The Lower Air Supply Line Pushbutton opens and closes the Lower Air Supply Line
Valve (XV-14). The Lower Air Supply Line Valve is a fail-closed valve that starts and
stops the flow of air to the Cooling Zone and Drying Zone of the Regeneration Tower.
Air flow must be started to the Cooling Zone and Drying Zone during the Startup
Procedures in order to begin oxidizing and chloriding the catalyst.

The Lower Air Supply Line Pushbutton has only two positions: ON and OFF. In the ON
position, the Lower Air Supply Line Valve (XV-14) is open. In the OFF position, the
Lower Air Supply Line Valve in closed. An indicator on the control panel shows the
position of the pushbutton. Limit switches indicate the position of the valve.

ON

Opening the Lower Air Supply Line Valve (XV-14) is an important step in the Startup
Procedure that should not be taken lightly. In the Shutdown Procedures, the Lower Air
Supply Line Valve is closed and it must remain closed until the Startup Procedures are
underway. This keeps the Cooling Zone and Drying Zone under a nitrogen environment.
Even in the Startup Procedures, the Lower Air Supply Line Valve must remain closed
until it is allowable, according to the Startup Procedures, to begin oxidizing and
chloriding the catalyst. The important point is that opening the Lower Air Supply Line
Valve when there is coke below the Burn Zone can cause serious damage to equipment
and catalyst inside the Regeneration Tower.

When it is allowable, according to the Startup Procedures, to open the Lower Air
Supply Line Valve (XV-14), the operator depresses the Lower Air Supply Line
Pushbutton. The Lower Air Supply Line Valve opens and the indicator changes from
OFF to ON.

OFF

The Lower Air Supply LineValve (XV-14) closes automatically when a Hot Shutdown,
a Cold Shutdown occurs, or a Contaminated Nitrogen Shutdown occurs. This keeps air
out of the Drying Zone when catalyst circulation and catalyst regeneration are stopped
during these shutdowns.

The operator can manually close the Lower Air Supply Line Valve (XV-14) without any
preconditions when doing the Hot Shutdown Procedure. If the Lower Air Supply Line
Pushbutton is depressed while the Lower Air Supply Line Valve is open, then the Lower
Air Supply Line Valve closes. The indicator changes from ON to OFF.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 64 OF

2.2.7.5Chloride pushbutton

The Chloride Pushbutton opens and closes the Chloride valve (XV-16). The Chloride
Valve is a fail-close valve that opens and closes to supply an organic chloride into the
Chlorination Zone. Chloride injection must be started during the Startup Procedures in
order to begin redispersing the metals and chloriding the catalyst.

The Chloride Pushbutton has only two positions: ON and OFF. In the ON position, the
Chloride Valve (XV-16) is open. In the OFF position, the Chloride Valve is closed. An
indicator on the control panel shows the position of the pushbutton. Limit switches
indicate the position of the valve.

ON

Opening the Chloride Valve (XV-16) can be done only after normal catalyst circulation
and catalyst regeneration have been started. That means, gas flow rates to each zone are
normal, operating temperatures of each zone are normal, and the gas flowing to the
Cooling Zone and Drying Zone is air. These conditions help ensure that the organic
chloride will decompose when it is injected. The Chloride Valve cannot be opened during
a Hot Shutdown, Cold Shutdown, or a Contaminated Nitrogen Shutdown. To open the
Chloride Valve (XV-16), the following conditions must be met:

Item Condition
1. Nitrogen Valve XV-15 is commanded
closed and confirms closed.
2. Regeneration Gas Heater Outlet Temperature Not low.
3. Air Heater Outlet Temperature Not low.

When the operator depresses the Chloride Pushbutton, the Chloride Valve opens.
The indicator changes from OFF to ON.

For the Organic Chloride Injection Pump to start, the following conditions must be met:

Item Condition
1. Chloride Valve XV-16 confirms opened.
2. Chloride Injection Pump Handswitch (local) AUTO position.

Then, the Organic Chloride Injection Pump will start automatically.

The operator can adjust the organic chloride injection rate by using the stroke
adjustment on the injection Pump. A flow meter indicates the injection rate. If the flow
rate is too low for a time longer than the Chloride Flow Alarm Timer (usually 15
seconds), then an alarm sounds and the Chloride valve closes. The operator should
check the injection rate regularly using the sight glass on the organic chloride drum.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 65 OF

The operator can manually start the Organic Chloride Injection Pump in order to
inventory the injection line. If the operator turns the local Pump Handswitch to the
HAND position while the Emergency Stop Switch is in the RUN position, then the
Injection Pump starts. The line should be inventoried up to the Chloride Valve (XV-16)
before beginning the Startup Procedures. After inventorying, the local Pump
Handswitch should be in the AUTO position for normal operation.

OFF

The Chloride Valve (XV-16) closes automatically when a Hot Shutdown. Cold
Shutdown, or a Contaminated Nitrogen Shutdown occurs. And the Chloride Valve closes
automatically if any condition required to open the Chloride Valve and start the Injection
Pump is not met while the Chloride Valve is open, that is:

Item Condition
1. Nitrogen Valve XV-15 is not confirmed
closed.
2. Regeneration Gas Heater Outlet Temperature Low.
3. Air Heater Outlet Temperature Low.
4. Chloride Valve XV-16 is not confirmed
open.

Then, the indicator changes from ON to OFF. If the Pump Handswitch is in the AUTO
position, then the Injection Pump stops automatically too.

The operator can manually close the Chloride Valve (XV-16). If the Chloride
Pushbutton is depressed when the Chlorid Valve is open, then the Chloride Valve closes.
If the Injection Pump is running and the Pump Handswitch is in the AUTO position,
then the Injection Pump stops.

The operator can also manually stop the Injection Pump by turning the Pump
Handswitch to the OFF position.

2.2.7.6Electric heater pushbuttons

There are four electric heaters – Regeneration Gas, Air, Reduction Gas No. 1, and
Reduction Gas No. 2. Each heater has an Electric Heater Pushbutton that starts and
stops its electrical power. Each Electric Heater Pushbutton has only two positions: ON
and OFF. An indicator on the control panel shows the position of the pushbutton.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 66 OF

ON

To start each of the electric heaters, the following conditions must be met:

Item Condition
1. Regenerator Run-Stop Pushbutton RUN position.
2. Process Gas Flow Not low.
3. Heater Element Skin Temperature Not high.
4. Ground Fault None.

When the operator depresses the Electric Heater Pushbutton, then that electric heater
starts. Its indicator changes from OFF to ON.

The operator controls each heater’s output with its temperature controller on the DCS.

OFF

The Regeneration Gas and Air electric heaters stop automatically when a Cold
Shutdown or a Contaminated Nitrogen Shutdown occurs.

Each of the electric heaters can individually stop automatically. If any condition
required to start the heater is not met while the heater is on, then that heater alone stops.
If the heater stops because of low process gas flow, high heater element skin
temperature, or ground fault, the indicator changes from ON to display neither ON nor
OFF.

The operator can manually stop each of the electric heaters. If the Electric Heater
Pushbutton is depressed when the heater is on, then that electric heater stops. Its
indicator changes from ON to OFF.

2.2.7.7. Emergency stop switch

The Emergency Stop Switch controls power to all logic-operated valves and electric
heaters in the Regeneration Section. The Emergency Stop Switch has two positions:
RUN and STOP.

RUN

RUN is the position of the Emergency Stop Switch during normal operation. The
Emergency Stop Switch must be in the RUN position in order for the operator to control
RCS instrumentation. The Emergency Stop Switch must be in the RUN position or else
no other system, including the Regenerator, can be in the RUN condition.

When the Emergency Stop Switch is turned to the RUN position, the three Controller
Failure Alarms clear. This confirms that the Emergency Stop Switch is functioning
normally.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 67 OF

STOP

If the Emergency Stop Switch is turned to the STOP position, a Cold Shutdown occurs
and each logic-operated valve immediately moves to its fail-safe position. In addition,
the three Controller Failure Alarms sound, and the Valve I/O Failure Alarm, if present,
clears. Turning the Emergency Stop Switch to the STOP position may be required as a
last resort. But in normal operations this is not recommended. This is because all of the
valves move at once and neither the operator nor the Regenerator Control System
controls the sequence of the movement.

2.2.8Valve verification system

Every valve in on-off service has two limit switches for indicating the valve’s actual
position, either open or closed. Each valve also has a Valve Verification Alarm that
alerts the operator of a problem with a valve’s position. Indicators on the control panel
show the commanded and actual positions of each valve. If the commanded and actual
positions for a valve are not the same, the alarm sounds. Time (usually 15 seconds) is
allowed for the valve to change position whenever the commanded position changes.

The on-off valves and their failure positions are listed below:

Tag Description Failure Position


XV-1 Catalyst Addition Lock Hopper No. 1 Load Closed
XV-2 Catalyst Addition Lock Hopper No. 1 Pressure Closed
XV-3 Catalyst Addition Lock Hopper No. 1 Vent Closed
XV-4 Catalyst Addition Lock Hopper No. 1 Unload Closed
XV-5 Spent Isolation Top Closed
XV-6 Spent Isolation Pressure Open
XV-7 Spent Isolation Bottom Closed
XV-9 Fines Collection Pot Load Closed
XV-10 Fines Collection Pot Pressure Closed
XV-11 Fines Collection Pot Vent Closed
XV-12 Fines Collection Pot Unload Closed
XV-13 Air Closed
XV-14 Lower Air Supply Line Closed
XV-15 Nitrogen Open
XV-16 Chloride Closed
XV-17 Catalyst Addition Lock Hopper No. 2 Load Closed
XV-18 Catalyst Addition Lock Hopper No. 2 Pressure Closed
XV-19 Catalyst Addition Lock Hopper No. 2 Vent Closed
XV-20 Catalyst Addition Lock Hopper No. 2 Unload Closed
XV-22 Regenerated Isolation Top Closed
XV-23 Regenerated Isolation Pressure Open
XV-24 Regenerated Isolation Bottom Closed
XV-29 Regenerated Catalyst Lift Line Closed
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 68 OF

2.2.9Bypass switches

There are five bypass switches. Each switch bypasses a condition that causes a
shutdown during normal operation. Each switch has only two positions: NORMAL and
BYPASS. Each switch is locked and a key must be inserted into the switch in order to
turn it. An indicator on the control panel shows the position of the switch.

The bypass switches and the condition each bypasses are:

Item Condition
1. CCR Nitrogen Header High contaminants
2. Oxygen Analyzer Sample Low flow
3. Burn Zone Oxygen Content High O2 content
4. Burn Zone Gas Low flow
5. Air to Air Heater Low flow

BYPASS

The operator may turn the CCR Nitrogen Header switch to BYPASS at any time. This
action bypasses the shutdown due to high contaminants detected by the CCR Nitrogen
Header Analyzer. This allows the CCR Nitrogen Header Analyzer to be calibrated
without shutting down the Regeneration Section.

The operator may turn the Oxygen Analyzer Sample to BYPASS at any time. This
action bypasses the shutdown due to low flow detected by the Oxygen Analyzer Sample
Flow Switch. This allows the Regeneration Section to continue in operation in the event
of a very brief malfunction of the analyzer’s sample flow switch. This bypass switch is
also useful during the Final Startup Preparation when it allows the catalyst to be
circulated and a carbon level to be established on the catalyst before the Regeneration
Blower is started prior to the Black Catalyst Startup Procedure.

Although the operator may turn the switches for the Burn Zone Oxygen Content, Burn
Zone Gas, and Air to Air Heater to BYPASS at any time, these switches will only
bypass their respective shutdowns when the Air Valve (XV-13) is confirmed closed and
the Nitrogen Valve (XV-15) is confirmed open. This allows the Oxygen Analyzer and
the flow meters for the Burn Zone gas, and Air to Air Heater to be calibrated, but only
when there is nitrogen but no air entering the Regeneration Tower. And, in the case of
the flow meters, this also allows the catalyst to be circulated and a carbon level to be
established on the catalyst before normal flow rates of Burn Zone gas, and Air to Air
Heater are set prior to the Black Catalyst Startup Procedure.

NORMAL

EXCEPT FOR THE SITUATIONS DESCRIBED UNDER “BYPASS” AND


ALWAYS DURING NORMAL OPERATIONS, THE BYPASS SWITCHES
SHOULD BE KEPT IN THE NORMAL POSITION.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 69 OF

FIGURE 2.2-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 70 OF

FIGURE 2.2-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 71 OF

FIGURE 2.2-3
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 72 OF

FIGURE 2.2-4
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 73 OF

FIGURE 2.2-5
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 74 OF

FIGURE 2.2-6
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 75 OF

FIGURE 2.2-7
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 76 OF

FIGURE 2.2-8
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 77 OF

FIGURE 2.2-9
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 78 OF

FIGURE 2.2-10
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 79 OF

FIGURE 2.2-11
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 80 OF

FIGURE 2.2-12
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 81 OF

FIGURE 2.2-13
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 82 OF

FIGURE 2.2-14
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 83 OF

FIGURE 2.2-15
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 84 OF

2.3Control Flow Plan


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 85 OF
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 86 OF
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 87 OF
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 88 OF
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 89 OF

3EMERGENCY EQUIPMENT

3.1Safety Valves and Their Set Pressure

3.1.1Summary of safety valve

Summary of the safety valves provided for the Platforming Process Unit CCR Section
is shown below. Refer to “Data Sheet for Safety Relief Valve” (S-312-1374-301).

Tag No. Set Size & Service Location Governing


Press. Type Relief Case
Kg/cm2
G
312-PSV-001A/B 10.5 1E 2 312-ME9 Collector outlet Valve Close
312-PSV-002 10.5 1D2 312-V4 Top mounted Fire
312-PSV-003A/B 12.3 3/4 x 3/4 312-P2A/B Discharge Valve Close
312-PSV-004A/B 4.2 1.1/2 F 2 312-R1 Cooling zone outlet Valve Close
312-PSV-006A/B 13.8 1.1/2 F 2 312-ME8 Coalescer outlet valve Open
312-PSV-007A/B 13.8 1D2 312-V8 Pressure gas inlet Fire
312-PSV-008 10.5 1D2 312-V2 Top mounted Fire
312-PSV-009A/B 12.3 3/4 x 3/4 312-P3A/B Discharge Valve Close
312-PSV-010A/B 12.3 1D2 312-P4A/B Discharge Valve Close
312-PSV-051 8.2 3/4 x 1 312-E3 Tube side inlet Thermal
Expansion

3.2Car Sealed Valves

For safer operation, several valves are car sealed open or closed to prevent them from
being accidentally closed or open. A list of these valves is shown below:

CSO/CSC Srevice Line No. Size, inch P&ID No.


CSO Recycle gas to 312-R1 300-PG-2103-B1A1 2” 116
CSO Recycle gas to 312-R1 PG-1602-PR07 1.1/2” 116
CSO CN2 supply line CN2-1705-PR30 1.1/2” 117
CSO CN2 supply line CN2-1701-PR08 1” 117
CSO 312-PSV-004A inlet PG-2310-PR24 1.1/2” 123
CSO 312-PSV-004A outlet PG-2307-PR30 2” 123
CSC 312-PSV-004B inlet PG-2310-PR24 1.1/2” 123
CSO 312-PSV-004B outlet PG-2307-PR30 2” 123
CSO 312-PSV-007A inlet PG-2514-PR07 1” 125
CSO 312-PSV-007A outlet FL-2502-PR30 3” 125
CSC 312-PSV-007B inlet PG-2514-PR07 1” 125
CSO 312-PSV-007B outlet FL-2502-PR30 3” 125
CSO 312-PSV-006A inlet PG-2516-PR23 1.1/2” 126
CSO 312-PSV-006A outlet FL-2502-PR30 3” 126
CSC 312-PSV-006B inlet PG-2516-PR23 1.1/2” 126
CSO 312-PSV-006B outlet FL-2502-PR30 3” 126
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 90 OF

3.3Remote Operating Valves

Platforming Process Unit CCR section has no ROV.

3.4Instrument Alarms

Set value of each alarm is shown in Alarm and Trip Schedule (S-312-1371-102). Refer
to Attachment 3-1

3.5Instrument Trip Settings

Instrument are provided to facilitate automatic shutdown of equipment/unit during


emergency conditions. These instruments and their trip settings are listed Below and
also refer to Attachment 3-1

Tag No. Service Set Point P&ID No.


LALL-078 Reactor No.1 surge zone LL,SD Top TL-4,140 mm 117
LSHH-215 Vent gas wash tower EL+107,400 mm 129

3.6Procedure for Setting Protective Relays

Access control to various manipulations on DCS for this project is shown below and
details of operating procedures is shown in the DCS vendor's operating manual :

Operator Supervisor Engineer


Controller SP x x x
Alarm SP/Flow Meter Range x x
PID Turning Constants x
Other Parameters (e.g. dir/rev) x

Access control to various manipulations on ESD PLC for this project is shown below
and details of operating procedures is shown in the DCS vendor's operating manual:

Operator Supervisor Engineer


Trip SP x
Other Parameters (e.g. Timer) x
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 91 OF

4PREPARING UNIT FOR PRE-COMMISSIONING

Prior to the commissioning of the plant there are several operations that must be
conducted to prepare the plant for the actual start-up; these are:

- Plant inspection.
- Commissioning of utilities.
- Final inspection of vessels.
- Pressure test of equipment.
- Wash out lines and equipment and break-in pumps.
- Service and calibrate instruments.
- Purge and gas blanketing.

It is important that these operations be carried out as thoroughly and as well as


possible to help achieve a smooth and trouble-free start-up and later a steady normal
operation.

4.1Pre-commissioning

4.1.1Preliminary regeneration section operations

The following basic steps are covered in this preliminary operations subsection:

(1) Conduct Pneumatic Pressure Tests


(2) Service Utility Systems
(3) Inspect Equipment
(4) Check Regenerator Logic Wiring
(5) Verify Valve Assembly
(6) Bench Test Relief Valves
(7) Clean Lines
(8) Run In Blowers
(9) Prepare the Electric Heaters
(10) Install Metering Orifices
(11) Install Filter Elements
(12) Install Control Valves
(13) Install Regeneration Tower Thermocouples
(14) Install Reduction Zone Thermocouples
(15) Install Reduction Zone Catalyst Sampler
(16) Calibrate Instrumentation
(17) Prepare the Air Dryer
(18) Pressure Test the Regeneration Section
(19) Check the Logic of the Lock Hopper Control System
(20) Dryout the Regeneration Section
(21) Load Catalyst
(22) Calibrate the Lock Hopper
(23) Check Lock Hopper Surge Zone Level Instrument
(24) Check Catalyst Lifting Rates

A suggested sequence for these preliminary operations is shown in Figure 5.2-1.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 92 OF

It is essential that the items summarized below be completed before the Regeneration
Section can be considered ready for initial startup. Later startups will not require this
detailed preparation. The UOP Chief Technical Advisor will usually provide detailed
procedures for this preliminary preparation.

(1) Conduct pneumatic pressure tests of pertinent equipment. This is generally


handled by the construction contractor.

NOTE: Gas-tight ball valves must never be installed before the final assembly
of the unit. Free water and/or humidity in the air can cause damage to the
sealing surface. The construction should provide pipe spools to fill the flange-
to-flange height of the ball valves to obtain proper piping fit-up.

Refer to section 4.3 for the hydrostatic pressure test that is applied to water
systems such as cooling water, condensate and caustic.

(2) Clean and service utility systems.

Refer to section 4.2 for details.

(3) Inspect pertinent piping, instrumentation, and equipment for fabrication and
installation in accordance with the UOP Project Specifications.

(4) Check regenerator logic wiring. Ensure that all electrical connections from the
logic cabinets to the field and to the control board are correct.

(5) Verify the mechanics and the assembly of all automatic valves, manual ball
valves, and control valves. Inspect clearances of valve internals. Bench test
valves that require leak testing.

Bench-calibrate the positioners and actuators of the two Equalization Valves


and the two gas makeup valves of the Lock Hopper, Stroke each valve
manually.

For the two Equalization Valves, measure the angle at which the port of the ball
valve just begins to open up to the flow (“dead angle”). Refer to Figure 4.1-1.

(6) Bench test all relief valves associated with the Regeneration Section.

(7) Blow down all lines associated with the Regeneration Section with air to
remove trash, scale, and water. A thorough purge of all lines will minimize
valve problems and ensure a smooth startup. The blowdown is accomplished by
dividing the Regeneration Section system into loops, such as:

a. Nitrogen header to all Regeneration Section users.


b. Recycle gas header to all Regeneration Section users.
c. Booster gas header to all Regeneration Section users.
d. Nitrogen Lift System.
e. Regenerated Catalyst Lift System.
f. Combustion air system.
g. Organic chloride injection system.
h. Vent gas line from Reduction Zone and Lock Hopper.
i. Ejector line to Regeneration Section users.
j. Regeneration Tower associated piping.
k. Lock Hopper associated piping.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 93 OF

NOTE: Clearing each piping loop must be carefully planned to avoid blowing
trash, scale, and water into an area of piping that has already been cleared.
Likewise for vessels, trash, scale, and water should not be blown into vessels
that have already been cleaned.

After line blowing, check visually for trash and scale in the catalyst lines
between vessels of the Regeneration Section. Clean as required in preparation
for installation of the automatic valves and the manual ball valves.

Refer to section 4.4 for the flushing out of water systems such as cooling water,
condensate and caustic.

(8) Run in the Regeneration Blower and the Regeneration Cooler Blower.
Commission the nitrogen seal purge to the Regeneration Blower. Start the
blowers in accordance with the manufacturer’s instructions.

Refer to section 4.5 for the run-in of pumps.

Regeneration Blower run-in will also serve to blow down the large-diameter
suction and discharge lines. If possible, a screen should be placed at the suction
of the Regeneration Blower to prevent any trash from being pulled into the
Blower. In addition, at the Regeneration Tower, the flanged connections should
be unbolted and spread apart with a blind installed on the Regeneration Tower
nozzles. These steps provide suction flow to the Regeneration Blower and
prevent trash from being blown into the Regeneration Tower.

(9) Prepare the Electric Heaters. Check the continuity of the electrical wiring of the
Regeneration Heater, Air Heater, and Reduction Gas Heaters. Dry out the
insulation surrounding the electric elements in the heaters in accordance with
the manufacturer's procedures.

(10) Install all metering orifices, restriction orifices, and any other flow-measuring
elements. Before installation, measure and check all orifice diameters against
the UOP Project Specifications and the contractor's calculations.

(11) Install all filter elements, this includes: in-line filters; screen inserts inside the
Reduction Zone gas outlet, L-Valve Assemblies, Fines Collection Pot, Lock
Hopper; and the elements inside the Dust Collector, the Booster Gas Coalescer,
and Reduction Gas Filters.

(12) Install all control valves, automatic valves, and manual ball valves.

Install the two Equalization Valves and the two gas makeup valves of the Lock
Hopper. Calibrate each valve’s transducer in the field. Stroke each valve after
installation via an input signal to the transducer to check the linearity of the
control of the valve position.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 94 OF

(13) Install the long Regeneration Tower thermocouples that extend from the top
head of the Regeneration Tower down inside the Burn Zone, Reheat Zone, and
Chlorination Zone.

(14) Install the long Reduction Zone thermocouple assembly that extends from the
top head of the Reduction Zone down into the Lower Reduction Zone.

(15) Install the Reduction zone catalyst sampler. Follow vendor instruction regarding
installation.

(16) Calibrate all instrumentation. For record purposes, measure with a Geiger
counter and record the radiation strength at the detector tubes of all nuclear
level instruments, including the Reduction Zone (2 instruments), the
Disengaging Hopper (2 instruments), and the Lock Hopper (3 instruments}.

(17) Prepare the Air Dryer, Load the Air Dryer with the drying medium provided by
the manufacturer. Pressure test the Air Dryer with the Combustion Air System
at the normal operating air pressure. Cycle the logic sequence. Verify that the
product air moisture content meets project specification at the design drying air
flow rate.

(18) Pressure test the Regeneration Section in the following loops. Include in the
pressure test all instrumentation associated with the equipment and piping of
each pressure test loop.

a. The steam side of the Booster Gas Heater and the Organic Chloride
Injection Line Steam Jacket, the cooling water pad of the Regeneration
Blower (if applicable), and the cooling water side of the Lift Gas Blower
Gas Cooler (if applicable) should be tested at their normal operating
pressures.

b. The following equipment and associated piping are pressure-tested with


the Platforming reactor circuit:

Reduction Zone
Reduction Gas Heaters
Reduction Gas Exchanger

c. The following equipment and associated piping are pressure-tested at the


Platforming reactor circuit test pressure:

Spent Catalyst Lift System


Disengaging Hopper
Dust Collector
Lock Hopper
Regenerated Catalyst Lift System

d. The Booster Gas Coalescer, the Booster Gas Heater and the associated
piping are pressure-tested with the Platforming net gas booster
compression section.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 95 OF

e. The following equipment and associated piping are pressure-tested at the


Regeneration Tower normal operating pressure:

Regeneration Tower
Regeneration Blower
Regeneration Cooler
Regeneration Heater
Air Heater
Catalyst Addition Lock Hopper No.2
Nitrogen Seal Drum
Organic Chloride Injection System

Blind off the Regeneration Blower from the rest of this loop and pressure-
test it separately. When pressuring-up the Regeneration Blower, maintain
the seal purge at the design differential pressure above the suction
pressure at all times. The Regeneration Blower itself will not be gas-tight
because its seals will leak. Check the housing and the flanges at the
suction and discharge of the blower for leaks using a dilute soap solution.

f. The Combustion Air System, including the Air Dryer and the associated
piping, are pressure-tested at the normal operating air pressure.

g. The Nitrogen Header and its distribution piping to the Regeneration


Section users are pressure-tested at the normal operating nitrogen
pressure.

Refer to section 4.7 for the generalized procedure of leak testing.

(19) Check the logic of the PIC Regenerator Control System.

a. Hand stroke all the manual and automatic ball valves to check ease of
operation. Stroke all logic-controlled valves using the logic system. Stroke
all control valves using the control board station.

b. Set and test the setpoints of all limit, logic, and alarm switches.

c. Set and cheek all timer settings in the logic and alarm systems.

d. Perform a dry-run cycling of all the various systems of the Regenerator


Control System.

(20) Dry out the Regeneration Section.

Dry out the Regeneration Tower and associated equipment before loading
catalyst. The Regenerator Section dryout will be done at the same time as the
Platforming reactor section dryout.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 96 OF

The Regeneration Tower will be dried out by heating nitrogen with the
Regeneration and Air Heaters and by circulating it with the Regeneration
Blower. The reactor section will be dried out by heating nitrogen with the
charge heater and the interheaters and by circulating it with the Recycle
Compressor. The Spent Catalyst Lift System, Disengaging Hopper, and Dust
Collector will be dried out by circulating nitrogen with the Lift Gas and Fines
Removal Blowers. The Catalyst Addition Lock Hopper will be dried with
nitrogen vented from the Spent Catalyst Lift System. The Lock Hopper and
Regenerated Catalyst Lift System will be dried out by circulating nitrogen with
the Recycle Compressor. The Reduction Gas Heaters and associated piping will
be dried with nitrogen vented from the Regenerated Catalyst Lift System.

The following procedure outlines a general procedure for carrying out this
drying operation:

a. Prepare the Regeneration Section for Dryout.

To prepare the Regeneration Section for dryout, the Regeneration Section


is divided into five loops:

Nitrogen Header
Equipment that is included with the Platforming reactor circuit
Nitrogen Lift System
Regeneration Section Air System
Hydrogen System

The nitrogen header and the hydrogen system of the Regeneration Section
must be purged with nitrogen to remove any oxygen prior to starting the
dryout. Nitrogen should be purged through all vents, drains, and
instrument taps to ensure that no air pockets are missed. Care should be
taken not to back-purge into a system that has previously been purged. In
the case of unavoidable dead ends in piping systems, an effective nitrogen
purge can only be achieved by repeated pressuring and venting to
atmosphere.

(a) Nitrogen header.

Purge all piping from the independent nitrogen source through the
nitrogen header to the various nitrogen users in the regeneration
section. Commission the nitrogen header.

(b) Equipment that is included with the Platforming Unit reactor


circuit.

The following equipment and its associated piping is evacuated and


purged simultaneously with the Platforming Unit reactor circuit:
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 97 OF

Reactor Catalyst Collector purge line


Reduction Zone
Reduction Gas Exchanger and outlet line to Platforming Unit

Before this purging, prepare the Regeneration Section as follows:

(i) Close the blind in the catalyst line between the bottom of the
reactors and the Spent Catalyst Isolation Valve. Keep this
blind closed until the end of the Platforming reactor section
and Regeneration Section dryouts.

(ii) Connect the temporary dryout line from the upstream side of
the valve in the Reduction Zone Purge line from the Recycle
Gas Compressor to the inlet nozzle of the Booster Gas
Coalescer. Close the valve in this line.

(iii) Close the valve at the top of the Reactor stack.

(c) Regeneration Section Air System.

This system includes the Regeneration Tower, Nitrogen Seal Drum,


and associated piping. Prepare this system as follows:

(i) Ensure that the Regenerated Catalyst Isolation System is


closed.

(ii) Install temporary blinds in the catalyst lines between the


Disengaging Hopper and the top of the Regeneration Tower.
Keep these blinds closed until the end of the Platforming
reactor section and Regeneration Section dryouts.

(iii) Switch control of nitrogen addition control valve downstream


of the Fines Removal Blower to the pressure transmitter at
that location.

(iv) Install a temporary blind in the catalyst line between the


Nitrogen Seal Drum and the top valve of the Lower Isolation
System. Keep this blind closed until the end of the
Platforming reactor section and Regeneration section dryouts.

(v) Close the spectacle blind at the Cooling Zone outlet nozzle of
the Regeneration Tower downstream of the pressure relief
valve.

(d) Nitrogen Lift System. This system includes the Spent Catalyst L-
Valve Assembly, Spent Catalyst Lift Pipe, Disengaging Hopper,
Dust Collector, Lift Gas Blower, Lift Gas Blower Cooler, Fines
Removal Blower, Catalyst Addition Lock Hopper, and the
associated piping.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 98 OF

(e) Regeneration Section hydrogen system. This system includes the


Lock Hopper, Reduction Gas Heaters, Regenerated Catalyst L-
Valve Assembly, Regenerated Catalyst Lift Pipe,. Booster Gas
Coalescer, and Booster Gas Heater. Air-free this system as follows:

(i) Isolate the hydrogen system from the Regeneration Section air
system and from the reactor section, and the net gas section in
the Platforming Unit.

(ii) Close the manual valves in the catalyst line at the bottom of
the Lock Hopper. Keep these valves closed until the end of the
Platforming reactor section and Regeneration Section dryouts.

(iii) Evacuate the Regeneration Section hydrogen system and


pressure with nitrogen:

i) Unblock valves in the Hydrogen System so that the


pressure throughout the system is equalized.

ii) Connect the ejector manifold to the outlet of the Booster


Gas Heater.

iii) Commission the ejector and evacuate the hydrogen


system to at least 600 mm Hg (24 in Hg) vacuum. Hold
for one hour to determine system tightness. Break the
vacuum and pressure up the system to 0.35 kg/cm2g (5
psig) with nitrogen.

iv) Evacuate the hydrogen system again to at least 600 mm


Hg (24 in Hg) vacuum. Break the vacuum and pressure
up the system again to 0.35 kg/cm2g (5 psig) with
nitrogen. Repeat until oxygen measurements are less
than 0.1 vol-%. In the case of dead ends in piping, purge
by repeated pressuring with nitrogen and venting.

v) Pressure up the system with nitrogen to about 2.1


kg/cm2g (30 psig). Hold the pressure for one hour to
determine system tightness. Keep the system under
nitrogen pressure in preparation for the dryout.

b. Air-free the Platforming Process Unit reactor section in accordance with


UOP startup procedures. These steps are summarized as follows:

(a) Isolate the reactor section from the net gas compression section, the
fractionation section, and the fuel gas section.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 99 OF

(b) Route the vent line from the Product Separator pressure control
valve to atmosphere.

(c) Air-free the reactor section by evacuating and purging the system
with nitrogen until the oxygen level is below 0.1%.

(d) Purge the Recycle Compressor with nitrogen.

c. Pressure up the Platforming Unit reactor circuit with nitrogen and start
the Recycle Compressor. These steps are summarized as follows:

(a) Commission all instrumentation associated with the Platforming


reactor circuit and the Recycle Compressor.

(b) Pressure up the reactor section with nitrogen into the Recycle
Compressor discharge to a Product Separator pressure of about
2.43 kg/cm2a (34 psia), with the Recycle Compressor blocked in.
Hold the pressure for an hour to determine system tightness.

(c) Establish normal operation of the Reactor Products Condenser(s)


and the Reactor Products Trim Cooler(s).

(d) Commission the pressure controller of the Product Separator and


set the Product Separator pressure at 2.43 kg/cm2a (34 psia),
provided this is consistent with the mechanical limitations of the
Recycle Compressor. Valve the Recycle Compressor into the
reactor section.

(e) Start the Recycle Compressor. Establish nitrogen circulation


through the system at a rate compatible with the compressor
discharge temperature and pressure differential. Control the
pressure of the Production Separators venting with its pressure
controller and by adding makeup nitrogen at the discharge of the
Recycle Compressor.
(f) Drain all free water from any low points in the system.

d. Establish Catalyst Collector and Reduction Gas Outlet flows.

(a) Start the Reduction Zone Gas Outlet flow through the Reduction
Gas Exchanger.

(b) Start the Catalyst Collector and Reduction Zone recycle gas purge
flows when the Platforming Recycle Compressor is placed on
stream. Raise the Catalyst Collector purge flow to design.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 100 OF

e. Start the dryout of the Platforming reactor section in accordance with


UOP startup procedures and any requirements of vendors for the
Platforming Heater dryout and the Platforming Heater convection section
boilout. These steps are summarized as follows:

(a) Commission all instrumentation associated with the Platforming


Heaters.

(b) Establish flows and operating conditions in the convection section


in accordance with the bailout instructions.

(c) Establish a draft through the heater in accordance with the heater
vendor’s instructions. Purge the heater. Light the pilots.

(d) Light a few burners in each Platforming heater.

(e) Raise the temperatures of the reactor inlets at the specified heat-up
rate. Rotate burners in accordance with the heater dryout
procedures.

(f) (If applicable.) Raise the temperature of the Catalyst Collector


Purge along with the reactor inlets up to its normal operating
temperature.

(g) Hold the reactor inlet temperatures at the specified hold


temperatures for the specified time periods.

(h) Drain water from the Product Separator and plant low points until
the total drainage rate from the Product Separator and all other low
points is less than 100 ml per hour.

(i) Inspect closely the entire reactor section and Regeneration Section
for thermal expansion throughout the dryout.

(j) After the reactor section dryout, heater dryout, and convection
section bailout are judged complete, cooldown the Platforming Unit
reactor section in accordance with the dryout procedures. These
steps are summarized below:

Reduce reactor inlet temperatures.

Shutdown Platforming heaters.

Continue recycle nitrogen circulation until all reactor temperatures


have cooled at least below 66ºC (150ºF). In addition, continue
operation of the Recycle Compressor until the dryout of the
Regeneration Section is complete.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 101 OF

f. Commission the vent gas lines from the Regeneration Section.

(a) Ensure that the Regeneration Section hydrogen system is pressured


up with nitrogen to about 1.4 kg/cm2g (20 psig).

(b) The offgas lines from the Lock Hopper are normally routed to the
Product Condenser, then open the valves in the line to the suction
of the Recycle Compressor.

g. Start circulation of elutriation gas, lift gas to Spent Catalyst L-Valve


Assembly and to the Dust Collector:

(a) Open the Unload and Vent lines of the Catalyst Addition Lock
Hopper.

(b) Pressure up the spent catalyst lift system with nitrogen via the
normal addition point to the normal operating pressure. Adjust
nitrogen addition to balance venting through the Catalyst Addition
Lock Hopper. If possible switch control of the nitrogen addition to
the Fines Removal Blower discharge pressure indicator.

(c) Commission the Lift Gas Blower Cooler.

(d) Commission the Lift Gas Blower and the Fines Removal Blower.
Establish design flows to the Dust Collector and Spent Catalyst L-
Valve assembly.

h. Start flow of lift gas to the Regenerated Catalyst L-Valve Assembly and
makeup gas to the Lock Hopper:

(a) Open the valve in the temporary line from the Recycle Gas inlet
line to the inlet line of the Booster Gas Coalescer. Recycle nitrogen
will pressure up the Booster Gas Coalescer and Booster Gas
Heater to the discharge pressure of the Recycle Compressor.

(b) Open the Booster Gas Coalescer drain.

(c) Commission the Booster Gas Heater.

(d) Open the ball valve in the regenerated catalyst lift line at the top of
the Platforming reactors. Recycle gas will pressure up the lift line
to about the discharge pressure of the Recycle Compressor.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 102 OF

(e) Establish the primary and secondary lift gas to the L-Valve
Assembly.

(f) Establish makeup gas to the Surge Zone of the Lock Hopper
through both the logic-ramped control valve and the differential
pressure control valve.

i. Pressure up the Regeneration Tower with nitrogen.

(a) Close the vent control valve from the Burn Zone and the excess air
control valve from the Drying Zone.

(b) Slowly open the drying air control valve and pressure up the
Regeneration Tower with nitrogen to 2.5 kg/cm2g (35 psig).
Monitor the Regeneration Tower pressure closely in order to avoid
over-pressuring the system. Also, during pressure-up of the system
including the Regeneration Blower, maintain the blower’s seal
purge at the design differential pressure above the suction pressure
to avoid over-pressuring the seal.

(c) Hold the pressure and determine the tightness of the system by
checking for leaks at all flanges with soapy water. The system will
not hold pressure because of leakage through the seals of the
Regeneration Blower.

(d) Set and control the differential pressure between the Regeneration
Tower and the Nitrogen Seal Drum at 0 mm H2O (0 in. H2O).

j. Commission the Vent Gas Scrubber System

(a) Prior to this time Vent Gas Wash Tower internals, including the
tower packing material, should have been installed. Note: that the
tower should be filled with water before loading packing material.

(b) Commission all instrumentation associated with the Vent Gas


Scrubber System, including nitrogen purges to impulse lines.

(c) Inventory the wash tower with caustic at the design strength via the
normal condensate and caustic injection lines.

(d) Commission cooling water to the Caustic Cooler.

(e) Commission caustic circulation to the wash tower inlets above and
below the packed bed.

(f) Commission caustic circulation to the Venturi Scrubber. Set flow to


maintain the pressure in upstream piping design
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 103 OF

k. Establish the following flows and conditions:

(a) Nitrogen purge to the Regeneration Tower Cooling Zone: 30% of


flow meter maximum.

(b) Nitrogen purge to the Nitrogen Seal Drum: design flow rate.

(c) Nitrogen purge to Regeneration Blower seal: design differential


pressure.

(d) Nitrogen purges to the regeneration gas and reheat gas flow meters:
design flow rates.

l. Vent the nitrogen bled through the excess air control valve and the
Catalyst Addition Lock Hopper valves. Start the nitrogen flow to the Air
Heater to maintain the apparent Chlorination Zone flow at design flow.

m. Start the Regeneration Blower and the Regeneration Cooler Blower. Start
the regeneration blower with low speed.

n. Calibrate and set up the analyzers for normal operation:

Nitrogen header hydrogen/hydrocarbon analyzer


Regeneration gas oxygen analyzer

o. Set the Emergency Stop Switch to RUN. Depress the Regenerator


Run/Stop button to RUN.

p. Start the Air Heater and heat up the Regeneration Tower:

(a) Set the temperature controller for the Drying Zone inlet in manual
at zero output to the heater.

(b) Depress the electric heater pushbutton to start the heater.

(c) Raise the zone inlet temperature at 55ºC per hour (100'F per hour)
to 150ºC (300ºF). Hold for four hours. Drain all low points.

(d) Inspect the entire Regeneration Section for problems associated


with thermal expansion.

q. Start the Regeneration Heater and heat up the Regeneration Tower.

(a) Set the temperature controller for the Burn Zone inlet in manual at
zero output to the heater.

NOTE: The inlet temperature controller for the Burn Zone is split-
ranged to the Regeneration Heater (50-100%) and the Regeneration
Cooler (50-0%). Set its output at 50% for zero output to the
Regeneration Heater.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 104 OF

(b) Depress the electric heater pushbutton to start the heater.

(c) Raise the zone inlet temperature at 55ºC per hour (100ºF per hour)
to 150ºC (300ºF).

r. Raise the zone inlet temperatures at 55°C per hour (100°F per hour)
to150°C (300°F) to design temperature:

Burn Zone inlet 477°C (890°F)


Drying Zone inlet 565°C (1,050°F)

Hold for four hours. Again, inspect the entire Regeneration Section for
problems associated with thermal expansion.

Motor of the regeneration blower must be changed from low speed to high
speed when regeneration gas temperature will reach at 250°C - 300°C.

s. Shut down the electric heaters and cool down to 200°C (400ºF), or to as
low as the Regeneration Blower will allow.

t. Shut down the Regeneration Blower and the Regeneration Cooler Blower.

Motor of the regeneration blower must by changed at 250°C - 300°C.

u. Maintain nitrogen purges to the Regeneration Tower Drying Zone and the
Nitrogen Seal Drum to cool the Regeneration Tower to 38°C (100°F).

v. After the completion of the reactor section dryout, heater dryout, and
convection section boilout, cooldown the Platforming Unit reactors by
continuing recycle nitrogen until the reactors are below 66ºC (150°F).

w. Prior to shutting down the Recycle Compressor, block in all flows


between the reactor section and the Regeneration Section hydrogen
system, including the vent gas flow from the Lock Hopper.

x. Stop the Lift Gas and Fines Removal Blower and depressure the Spent
catalyst lift system.

y. Isolate the Regeneration Section hydrogen system from the reactor


section. Depressure the hydrogen system and maintain under a slight
positive pressure of nitrogen.

z. Shut down the Recycle Compressor. Depressure the reactor section and
maintain under a slight positive pressure of nitrogen. Isolate the reactors
from the rest of the Platforming reactor section with blinds. Purge the
Platforming reactors with dry instrument air. Open the manways of the
reactors and inspect the reactor internals.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 105 OF

aa. Depressure the Regeneration Tower and the Regeneration Section air
system. Purge the Regeneration Tower with dry instrument air. Open the
manway of the Regeneration Tower and inspect the internals.

bb. Disconnect and blank off the temporary dryout piping, remove or open the
dryout blinds.

(21) Load Catalyst.

a. Maintain the dry instrument air purges established following the reactor
section and the Regeneration Section dryouts.

b. Follow the catalyst handling guidelines in section 10.8.5.

c. Load catalyst into each Platforming reactor in the reactor stack according
to the procedures in the operation manual for Platforming Process Unit
(S-300-1230-001).

NOTE: The Spent catalyst L-Valve Assembly will not be filled with
catalyst at this time. The manual V-ball and B-valve below the catalyst
collector should remain closed throughout the loading.

d. Load catalyst into the Reduction Zone at the top of the Platforming
reactors through the top head or the manway of the Reduction Zone.

The quantity of catalyst loaded above the Reduction Zone low-level alarm
instrument should at least be sufficient to satisfy the net thermal and
mechanical slump of the catalyst in the Platforming reactor stack.

NOTE: Two percent of the catalyst loaded into all of the Platforming
reactors is normally provided for net thermal and mechanical slump
requirements.

However, for the purpose of checking the response and linearity of the
Reduction Zone's level controller, the quantity of catalyst to loaded in
Reduction Zone should be up to near the top (around 80-90%) of the level
controller.

During loading of the Reduction Zone, gauge the level in the Reduction
Zone using a measuring tape as it is being filled and compare it with the
level indication of the Zone’s level controller. Gauge the level after
loading, say, each 2 or 3 drums of catalyst or at each 5 or 10% change in
the level indication, in order to check the response and the linearity of the
level instrument.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 106 OF

e. Load the Lock Hopper, Regeneration Tower, and Disengaging Hopper


through the top nozzle of the Disengaging Hopper.

For the purpose of checking the response and linearity of the Disengaging
Hopper’s level recorder, load the Disengaging Hopper to the top of the
Disengaging Hopper’s level recorder while the Upper Isolation System is
closed. During loading of the Disengaging Hopper, gauge the level in the
Hopper using a measuring tape as it is being filled. Compare the
measurements with the level indication of the Disengaging Hopper level
recorder. Gauge the level after loading, 2 or 3 drums of catalyst or at each
5 or 10% change in the level indication in order to check the response and
the linearity of the level instrument.

Then, open the Regenerated Catalyst Isolation System by turning the


Regenerator Inventory Switch and depressing the Isolation Open
Pushbutton. The catalyst in the Disengaging Hopper will fall by gravity
and fill the Lock Hopper and part of the Regeneration Tower. Continue
loading catalyst into the Disengaging Hopper with the Isolation System
open.

NOTE: While unloading from the Disengaging Hopper recheck the


Disengaging Hopper level instrument calibration (after linearization) and
perform the initial calibration of the Lock Hopper Surge Zone level
instrument.

NOTE: The Regenerated Catalyst L-Valve Assembly will not be filled


with catalyst at this time. The manual V-ball and B-valve below the Lock
Hopper should remain closed throughout the loading.

The quantity of catalyst loaded above the Disengaging Hopper low-level


alarm instrument should be sufficient to satisfy the net thermal and
mechanical slump of the catalyst in the Regeneration Tower and the Lock
Hopper.

NOTE: Two percent of the catalyst loaded into the Regeneration Tower
and the Lock Hopper should be provided for net thermal and mechanical
slump requirements.

f. For record purposes, keep complete and accurate records of the number of
catalyst drums loaded into each of the Platforming reactors and the
Regeneration Section.

g. Be careful to avoid spilling any of the catalyst during loading because


platinum reforming catalyst is relatively expensive. If any catalyst does
spill, sweep it up and return it with catalyst fines for metals recovery.

NOTE: Do not discard empty catalyst drums. Store them with their lids
and clamp rings in a dry location. Normal practice is to use the empty
catalyst drums for return of catalyst fines or spent catalyst and for
handling catalyst during unloading.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 107 OF

(22) Calibrate the Lock Hopper.

The Lock Hopper must be calibrated in order to get an initial estimate of the
Lock Hopper load size, i.e., the amount of catalyst transferred during each
cycle of the Lock Hopper. Accurate measurement of the Lock Hopper load size
is important because it is the basis for calculating the catalyst circulation rate.

Using this calibration method, the Lock Hopper load size should be set equal to
the design Lock Hopper load size or up to 5% larger. The Lock Hopper load
size is set by adjusting the volume of catalyst that is transferred during each
cycle of the Lock Hopper. This volume of catalyst is at the top of the Lock
Hopper Zone of the Lock Hopper. It is the volume that is between the bottom of
the standpipe at the inlet of the Lock Hopper Zone and the position of the Lock
Hopper Zone low-level nuclear instrument source and detector.

The Lock Hopper should be calibrated after loading catalyst into the
Regeneration Tower and the Lock Hopper. The following discussion outlines a
satisfactory procedure for calibrating the Lock Hopper:

a. Set the initial positions of the source and detector for the high-level and
low-level nuclear level instruments in the Lock Hopper Zone of the Lock
Hopper at their design positions, according to the UOP Project
Specifications.

The switch point for the high-level nuclear level instrument should pass
just below the bottom of the catalyst standpipe above the Lock Hopper
Zone. The high-level should be lost 10-15 seconds after the Lock Hopper
Zone begins to empty.

b. Remove the spoolpiece below the two manual ball valves below the Lock
Hopper. Install a canvas sock below the valves leading to a convenient
location to collect catalyst. Open the lower ball valve keeping the upper
(V-ball) valve closed.

c. Remove the cover of the inspection nozzle of the Lock Hopper Zone to
gain access to the bottom of the Lock Hopper Zone standpipe. The Lock
Hopper Zone should be full of catalyst to bottom of the standpipe at this
time and both level instruments should indicate a catalyst level.

d. Place an empty, tared drum under the sock attached to the manual ball
valve.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 108 OF

e. Install a slide valve under the bottom of the Lock Hopper Zone standpipe
through the inspection nozzle of the Lock Hopper Zone. See Figure 4.1-2
for a typical design of a slide valve. Move the slide valve so it stops
catalyst flow out the bottom of the Lock Hopper Zone standpipe. This
will prevent any catalyst in the Disengaging Zone from refilling the Lock
Hopper Zone when the Lock Hopper Zone begins emptying. Open the
manual V-ball valve completely and allow the catalyst to drain out of the
Lock Hopper Zone of the Lock Hopper, through the sock and into the
tared drum. As the catalyst level in the Lock Hopper Zone drops, first
the high-level nuclear level instrument will indicate the absence of a
catalyst level, then the low-level instrument will, too. Immediately when
the low-level instrument indicates the absence of a level, close the
manual valve. Record the actual time required to empty the Lock Hopper
Zone from the standpipe down to the high-level nuclear level instrument
and down to the low-level nuclear level instrument. Weigh the catalyst
that drained into the drum.

NOTE: After the manual valve closes, the catalyst level in the Lock
Hopper Zone may continue to fall. This is due to refilling of the Surge
Zone, which may have not remained full while catalyst was draining
from it. Step (g) will prevent this from happening so that the catalyst
weighed in the drum will be equal to the amount of catalyst between the
bottom of the standpipe and the low-level instrument in the Lock Hopper
Zone only.

f. Move the slide valve so it starts catalyst flow out the bottom of the Lock
Hopper Zone standpipe. This will allow catalyst in the Disengaging Zone
to refill the Lock Hopper Zone up to the bottom of the standpipe. Record
the actual time required to fill the Lock Hopper Zone up to the low-level
nuclear level instrument and up to the high-level nuclear level
instrument.

Verify that the high-level nuclear level instrument is positioned so that


the high level is reached 5-10 seconds before the catalyst fills up to the
standpipe.

g. Repeat Step e, but do not open the manual valve completely. This will
slow down the rate of emptying of the Lock Hopper Zone for the
purpose of keeping the Surge Zone of the Lock Hopper full during the
emptying and throughout the calibration. Open the valve only enough so
that the time required to empty the Lock Hopper Zone from the
standpipe down to the low-level nuclear level instrument will be longer
by 20-40 seconds than the time measured in Step f to refill the Lock
Hopper Zone from the low-level instrument up to the standpipe. Then
repeat Step f. Repeat Steps f and g as needed until the required opening
of the manual ball is determined and the valve can be opened to that
position reproducibly.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 109 OF

h. Repeat Steps f and g ten more times, while, during each emptying of the
Lock Hopper Zone, opening the manual valve only as far as determined
in Step g. Compute the average load size transferred by the Lock Hopper
Zone from the weights unloaded. If necessary, adjust the position of the
low-level nuclear level source and detector to obtain the design Lock
Hopper load size (+5/-0%).

i. When the average load size based on ten weighings is correct, calculate
the average Lock Hopper load size with the low-level nuclear source and
detector at the final position.

NOTE: The Lock Hopper load size determined by this calibration


method will most likely be an underestimate of the actual Lock Hopper
load size during normal operation. This is because of the nature of the
Lock Hopper cycle and the hydraulics of catalyst flow through the Lock
Hopper during a cycle at normal operating pressures and temperatures.

(23) Check the Lock Hopper's Surge Zone Level Instrument.

a. In order to check the response and linearity of the level instrument in the
Lock Hopper's Surge Zone, keep the slide valve (Figure 4.2-2) in the
inspection nozzle of the Lock Hopper Zone. Position the slide valve so it
stops catalyst flow into the Lock Hopper Zone. This will prevent any
catalyst in the Disengaging Zone from refilling the Surge Zone when the
Surge Zone begins emptying. Open the manual valve and allow some
catalyst to drain out of the Surge Zone of the Lock Hopper, through the
canvas sock and into a drum until 90% catalyst level is reached.

Then, close the manual V-ball valve. Empty the Surge Zone in 5%
intervals and weigh the catalyst removed in each interval. Repeat until
the Surge Zone is empty. Gauge the catalyst level in the Surge Zone
using a measuring tape as it is being emptied and compare it with the
indication of the Zone’s level controller.

b. Refill the Surge Zone by closing the manual valve and miring the
position of the slide valve so it starts catalyst flow into the Lock Hopper
Zone.

c. Remove the slide valve. Remove the sock and replace the spool piece.
Close the nozzle in the Lock Hopper.

NOTE: If the initial level linearity check was done when filling the
Surge Zone only one recheck is required, if not this procedure must be
repeated after linearizing.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 110 OF

(24) Check Catalyst Lifting Operations.

After loading catalyst but prior to closing any of the vessels, check the
operation of the Spent and Regenerated Catalyst L-Valve Assemblies. As a
result, operable catalyst lift systems will be available during the startup of the
Platforming Unit. This is especially important for the Regenerated Catalyst L-
Valve Assembly, which must be operating during the startup to satisfy reactor
thermal and mechanical slump, or else the catalyst level in the Reduction Zone
could be lost.

In each L-Valve the rate of catalyst lifting is set by the dimensions in the L-
Valve and the flow rate of secondary lift gas to the L-Valve.

The following discussion outlines a satisfactory procedure for checking the


catalyst lifting rates:

Spent Catalyst L-Valve Assembly

Establish nitrogen lift gas flow to the Disengaging Hopper via the Spent
Catalyst L-Valve Assembly.

a. Commission the Lift Gas Blower and the Fines Removal Blower.

b. Open the manual ball valves below the Reactor,

c. Open the control valve for the primary lift gas to the L-Valve Assembly to
provide an actual flowing velocity at 7.6 to 9.1 meters per second (25 to
30 feet per second) in the spent catalyst lift line to the Disengaging
Hopper. Keep the control valve for the secondary lift gas to the L-Valve
assembly closed. There should be no catalyst flow with the secondary lift
gas closed.

NOTE: Since the manway of the Disengaging Hopper is open, the


pressure in the spent catalyst lift line is only slightly above atmosphere.

d. Open the Spent Catalyst Isolation Valves.

e. Slowly increase the secondary gas flow to confirm the L-Valve's ability to
lift catalyst, and record the secondary gas flow that initiates catalyst
lifting.

Regenerated Catalyst L-Valve Assembly

Establish nitrogen lift gas flow to the Reduction Zone via the Regenerated
Catalyst L-Valve Assembly.

a. Install a nitrogen hose at a convenient point on the lift gas line upstream
of the flow meter for the total lift gas to the L-Valve.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 111 OF

b. Open the valve in the nitrogen line, Nitrogen will pressure up the line to
the control valves for the primary and secondary lift gas.

c. Open the manual ball valve below the Lock Hopper.

d. Open the manual V-ball completely.

e. Open the control valve for the primary lift gas to L-Valve Assembly to
provide an actual flowing velocity of 9.1 to 10.6 meters per second (30 to
35 feet per second) in the regenerated catalyst lift line to the Reduction
Zone. The rate of nitrogen lift gas required to establish this velocity can be
measured by the flow meter for the total lift gas to the L-Valve Assembly
without changing the meter span or the orifice bore size. Keep the control
valve for the secondary lift gas to the L-Valve assembly closed. There
should be no catalyst flow in the lift line with the secondary lift gas
closed.

NQTE; Since the manway of Platforming Reactor No. 1 is open, the


pressure in the regenerated catalyst lift line is only slightly above
atmosphere.

g. Slowly increase the secondary gas flow to confirm the L-Valve’s ability to
lift catalyst, and record the secondary gas flow that initiates catalyst
lifting.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 112 OF

FIGURE 4.1-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 113 OF

FIGURE 4.1-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 114 OF

4.2Commissioning of Utilities

Fo1lowing construction, the various utilities such as steam, cooling water, air, etc.
must be put in service. Prior to commissioning, the various lines must be tested for
leakage and cleared of debris and construction trash. The latter may be done by water
circulation and steam or air blowing techniques, depending on the particular utility
service. Such techniques are generally described below for each type of utility system.

4.2.1Steam lines

Once steam is available in the refinery, the steam system can be warmed up and blown
free of all debris. Before putting steam into the system all steam traps, control valves,
turbines, heaters, instruments, vacuum ejectors and strainers should be removed or
blanked off from the system. The steam headers, one header at a time should be slowly
warmed up while expansion of the line is observed. Special attention should be given
pipe support shoes. Condensate must be drained manually as it forms to prevent steam
hammering.

When the headers are warm, the drain and vent valves should be opened and the lines
blown vigorously for a few moments blare reclosing the valves. This procedure should
be repeated 5 to 10 times to move material along the headers to the drains. On lines
leading to turbines special attention to detail is critical. All debris including scale must
be removed from these lines otherwise there will be damage to the turbine blades. Blow
these lines clean using high velocity steam and alternate the temperature of the lines so
scale on the pipe walls is removed. Usually a lead or aluminum impingement plate is
installed at the opening where the steam is being vented. When no indents are noted on
the plate the line is clean.

Also care must be taken that debris or scale is not blown into a line that has already
been cleaned. Condensate lines may be cleaned in the same manner as steam lines, but
close observation of the pressure on the condensate line is necessary since the working
pressure and temperature of the condensate lines is generally lower than that of the
steam headers.

When blowdown of the steam system is complete, traps and other equipment that were
removed prior to the blowdown may be reconnected. Steam turbine alignment should
be rechecked. The system can then be reheated and placed in service.

4.2.2Cooling water lines

Cooling water lines should be flushed with makeup water. Cooling water tanks or pits
should be thoroughly cleaned by hose and by hand, if necessary, before they are filled
with clean water. Suction strainers of 30 mesh should be installed in the pump suctions.
This screening can generally be fitted around a 6 mesh permanent pump suction screen.
All coolers, condensers, sample coolers, lube oil coolers at pumps and cooling water to
case jackets of rotational equipment should be disconnected from the system. The inlet
lines should be flushed, one at a time, using flow from the cooling water pumps. When
all inlet lines are flushed, reconnect the lines. Disconnect the cooling water outlet line
from the user. Flush through the users; then reconnect the outlet lines. When all outlet
lines are connected, flush the return line.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 115 OF

4.2.3Plant air system

Clean out the plant air blower(s) suction lines. Disconnect the blower discharge(s) line
from any downstream equipment; i.e., driers, oil separator, exchangers. Start the
blower(s) and verify it works correctly. At the same time the discharge line is blown
clean. Shutdown the blower(s) and reconnect the lines. Restart the blower(s), pressure
up the entire blocked in plant air header and start blowing down each header one at a
time starting with the main header. Then do each branch header individually. Do not
blowdown any lines through instruments or equipment. Always disconnect and make
sure the line is clean to that point before moving on.

4.2.4Instrument air lines

Disconnect the air line from the instrument air regulators. Remove any other regulators
from the line. Blow down each individual air line, then make up the line.

4.2.5Raw water

Raw water lines to safety eyewashes, showers, drinking fountains should be flustered
then left running to remove and dilute any harmful substance. Analyses of the water
should be made at points of human consumption to ascertain whether the water is fit
for human consumption.

4.2.6Firewater and sprinkler systems

After removing all nozzles, each fire hydrant and turret should be flushed. Since this
may be the first time the firewater pump has operated, the pump’s operation should be
observed carefully. Replace all turret nozzles when flushing is complete. Before
flushing sprinkler systems remove all sprinkler heads; then flush the entire system.
When clean, replace heads. Inspect each head before installation to make sure it is
clean. Try each piece of equipment with its head installed.

4.2.7Fuel gas lines

The fuel gas lines may be blown clear with steam. All regulators and control valves
should be rolled out of the lines prior to such blowing. All gas burners piping should be
opened. Once the main fuel gas system has been steam blown (start from the knockout
drum and work out). Steaming may then be resumed up through the burners to check
their orientation and confirm that all nozzles are free and clear. The entire system
should then be air dried before replacing regulators and control valves. Care must be
taken during both the steam blowing and the air drying not to exceed the relief valve
settings.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 116 OF

4.2.8Natural gas system

The natural gas lines may be blown clear with steam or air. All regulators and control
valves should be rolled out of the lines prior to such blowing. And all natural gas users
should be isolated. Once the main natural gas system has been steam (or air) blown,
the entire system should then be air dried before placing regulators and control valves.
Care must be taken during both the steam or air blowing and the air drying not to
exceed the relief valve settings. After air drying the natural gas system is purged by
nitrogen for air freeing. Then, the system is ready for the natural gas introducing.

4.2.9Nitrogen system

Nitrogen supply package is provided by others. Refer to their operating manual for the
nitrogen plant startup and operation. When the nitrogen plant is ready for supply, the
nitrogen supply headers and branch lines are to be air blown as follows:

Disconnect the nitrogen line from the users. Remove any other regulators from the line.
Blow down each individual nitrogen line, then make up the line.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 117 OF

4.3Pressure Testing

The hydrostatic pressure test is made by completely water filling the facility to be
tested and increasing the pressure to 1-1/2 times the design pressure of the lowest
pressure-rated piece of equipment in the circuit being tested. For a successful test, the
system loss should not exceed 2% of the test pressure per hour. If the system fails the
test, i.e. has a greater loss than 2% evidence of water at flanges, welds, pipes, etc. will
indicate the leaking areas to be repaired.

NOTE: Hydrostatic pressure testing should not be confused with the less severe
“tightness test” that will be conducted generally by operations personal during leak
checking.

It is not necessary to do hydrostatic pressure testing for a stop fabricated equipment,


since this test has been done at a stop.

Hydrostatic pressure testing the entire unit and all of its equipment simultaneously is
normally not practical. Generally, therefore, the unit will be divided into sections as
governed by the location of the various items of equipment and the test pressures to
which each items will be subjected. Suitable blinds must be made up for insertion on
nozzles and between flanges to isolate the various sections of equipment as required.
During pressure testing, all safety valves must be blinded off, since normal relieving
pressure will be exceeded.

Platforming reactor sections utilizing stacked reactors should not be field


hydrostatically tested because of structural support considerations and the probability
of internal reactor system damage. The reactor vessels should have been shop tested
hydrostatically by the manufacturer. Since the Platforming reactors are housed in the
same vessel shell, if field hydrostatic testing is desired, precautions must be taken to
prevent overstressing or rupture of the intermediate heads and expansion joints, which
are designed only for a maximum differential pressure of 1.1 kg/cm2g (16 psig),

General guidelines for hydrostatic testing are:

a. An air pressure test may be placed on the sections of the plant prior to
hydrostatic pressure testing so that any open lines or flanges may he located and
repaired before the test.

b. All equipment in the section of the plant to be tested should be rated for the test
pressure.

c. The test pressure gauge should be installed at the bottom of any vessel to
include any liquid head effects.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 118 OF

d. Differential test pressure between the tube and shell side of all heat exchangers,
coolers, condensers and combined feed exchangers must be taken into
consideration and proper testing procedures used. Generally, both the tube and
shell side are raised to the lowest test pressure at the same time. Then while
maintaining the lower test pressure on its respective side the higher test pressure
is developed and maintained on its respective side. Any equalization of pressure
indicates a leak.

e. Safety valves, relief valves, and rupture disks must be isolated or removed from
the tested system, since their normal relieving pressure will be exceeded.

If the safety and relief valves are removed, the time during the hydrostatic test
period can be utilized to bench test and set the valves.

f. The sections of the plant to be pressure tested must be isolated from the
remainder of the unit by blinds inserted between flanges. Blinds must be rated
for the test pressure.

g. All spring hangers should be in the pinned position. Piping should be checked to
ascertain if there is sufficient support to withstand the weight of water.

h. All vessel foundations to be hydrostatic pressure tested must be checked to


ensure their ability to support the vessel when full of water.

i. Hydrostatic pressure testing should not be carried out at vessel wall


temperatures below 15ºC (60ºF), to prevent metal embrittlement. If necessary,
the testing medium should be warmed to attain this temperature.

j. The water used must be clean and contain less than 50 wt-ppm chloride.

k. Never include compressors or pumps in the hydrostatic pressure test.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 119 OF

4.4Flushing Out

Upon completion of final mechanical inspection of the unit for variations form design
specifications, the unit is handed over to the operations group. One of the first tasks
they have to do beside familiarizing themselves with the unit is flushing. During
flushing all piping and equipment not previously cleaned is flushed with clean water
(typically). All reactors, vessels and heaters have already been cleaned as part of the
final mechanical inspection. While it is all right and even desirable to flush through
these pieces of equipment special care should be taken that no trash is flushed into
them. Always flush away from vessels.

if desired the pumps that can operate on water can be run-in after most of the trash has
been removed from the piping.

Just like during hydrostatic testing the water used must be clean an contain less than
50 wt-ppm chloride.

NOTE: No water flushing should be carried out in the compressors. The compressors
should be blinded off at the suction and at the discharge before line flushing is started.

The following guidelines are generally observed for flushing operations:

(1) All possible lines should be used during the flushing operation to facilitate
complete system cleanout.

(2) The fire water system should be flushed first and can be used to supply-water
for flushing the rest of the plant.

(3) Flush pump suction and discharge lines while disconnected from the pump
casing.

(4) Screens should be placed in the suction lines of all pumps before any liquid it
allowed to pass through them. If this is not done, scale, weld metal or slag,
stones, etc., may freeze or damage centrifugal pump impellers. The screens also
act to trap such dirt in a place where it can be conveniently removed. The
screens should be placed in a flange between the suction valve and the pump so
that the screen may be removed without depressuring any vessels. The flow
through the screen should preferably be downward, or horizontal. Precautions
should be taken to place the screen in a location where the dirt particles will not
drop into an inaccessible place in the line when the flow through the pumps is
stopped. If this should happen, it would not be possible to remove the dirt upon
removal of the screen.

(5) When practical, lines should always be flushed away from a vessel rather than
into a vessel. Any vessel flushed into, should be opened and manually cleaned
following flushing.

(6) Always flush from highest elevation to lowest elevation.

(7) Vessels and systems must be vented when filling or emptying. This is especially
true for towers not rated for vacuum or high pressure.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 120 OF

(8) All lines not flushed by vessel drainage or pump circulation must be flushed
independently.

(9) In flushing, maximum volume and velocity should always be used to insure
thorough cleaning. Regulate rate of flushing medium at the source.

(10) Control valves and thermowells must be removed from the piping system during
flushing to prevent damage.

(11) Orifice plates should only be installed after flushing is completed.

(12) Instruments, i.e. pressure gauges and transmitters, differential flow meter
transmitters, moisture and other in-line analyzers, etc., must be isolated from
the system during flushing.

(13) Flush through all drains and vents to check for blockage.

(14) Where possible, flush through open end lines. Do not restrict flow.

(15) Flush lines in the following sequences where possible; first, the main header;
second, each lateral header; and third, each branch line.

(16) Always flush through a bypass to an open end before flushing through
equipment.

(17) Do not flush lines into exchangers. Spread the inlet flange, cover the exchanger
nozzle and flush the line clean. If flushing through an exchanger is necessary,
open the exchanger and clean when flushing is complete.

(18) Continue flushing each line or piece of equipment until the exiting water is
clear.

(19) Use a unit piping flow diagram as a cleaning checkoff record to ensure that all
lines are flushed including lines to and from tankage. This helps ensure that a
line that has already been cleaned is not contaminated by later flushing a dirty
line into it.

(20) Avoid flushing from a large pipe to a smaller one. At the completion of the
flushing operations, keep the water in the unit to facilitate pump run-in if this
was not done during the flushing operation. If pump run-in has been completed
or is not to follow the flushing operation immediately drain all water from the
unit. When necessary, break flanges at low spots to facilitate drainage and air
blow as required to remove as much water as possible. All orifice plates should
be installed in the lines at the end of this step or after run-in of pumps and fans
as is convenient. They must all be installed prior to leak checking.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 121 OF

4.5Inspection and Run-In of Pumps

Prior to unit startup, all pumps must be thoroughly checked and properly run-in to
insure trouble free performance once the plant is in operation. This may be
accomplished in connection with flushing, if convenient.

Refer to the pump operating manuals.

4.5.1Pump inspection

All centrifugal pumps should be inspected and run-in by techriiques similar to the
following guidelines.

a. Check to see that all necessary water piping has been made to stuffing boxes,
bearing jackets, pedestals and quench glands. Ensure that all necessary lube oil
piping is installed, and that this piping is not mistakenly connected to the water
system.

b. Check arrangements to vent the pump for priming, if the pump is not self-
venting. See that special connections such as bleeds and drains are properly
installed.

c. Check strainers in pump suction lines. Strainers must be installed before


aligning pumps. A 6 mesh strainer is provided for each pump suction line
during startup. To avoid pump damage during flushing with water, the strainers
should temporarily be lined with 30 mesh screen., arms specified by the pump
manufacturer. Remove this screen after water flushing is completed. All
strainers should be flagged, and a list similar to the blind list should be kept, so
as to prevent a “lost" screen from plugging and upsetting unit operation.

NOTE: On new units, the fine mesh strainer screens are sometimes left in
service for the first run on all locations where spare pumps are provided.

d. Check that power or steam is available for running in the pump. Check that
pressure gauges and any special instrumentation are in working order.

e. Before lubricating oil-lubricated bearings, check bearing chamber in pumps to


see that no slushing compound or shipping grease is left in the chamber.
Mechanical seals should be flushed with water prior to pump operation.

f. It is extremely important that the proper type and viscosity oil and proper grade
of grease is used to lubricate the equipment. Refer to manufacturer’s
instructions and refinery lubricating schedule for this information.

g. See that the driver rotates the pump in the direction indicated by the arrow on
the pump casing. Rotate the pump by hand to see that it is clear before starting.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 122 OF

h. After lines and vessels have been flushed with water, pumps shouted be run k
on water, if practical. Couple up and align the pumps, then check for cooling
water availability and start flow of cooling water to the pumps requiring
external cooling, before they are run in.

NOTE: Multistage, LPG service and double mechanical sealed centrifugal


pumps should not be run in with water to prevent equipment damage.

4.5.2Pump run-in

a. Open pump suction valve and close discharge valve (crack discharge valve for
high capacity, high head pumps).

b. Flush pump through casing drain and vent to remove any particulate and ensure
that the pump is liquid full.

c. Warm up the turbine of turbine driven pumps without shaft rotation. Turbines
may be warmed up by opening the exhaust valve wide and bleeding a small
amount of steam through the turbine case. Be sure to condensate-free the steam
line first and to drain any condensate from the turbine case prior to startup,

d. Start pump. If motor driven, pump will come up to speed; if turbine driven,
pump must be brought up to speed as quickly as possible. Immediately check
discharge pressure gauge. If no pressure is shown, stop the pump and find the
cause. If discharge pressure is satisfactory, slowly open the discharge valve la
give the desired flow rate. Do not run pump with discharge block valve closed,
except for a very short time. Note any unusual vibration or operating condition.

NOTE: Water circulation with motor driven hydrocarbon pumps designed for
light hydrocarbons can result in motor overload. For equipment of this type,
pump capacity must be reduced by throttling the discharge to restrict flow. An
ammeter can be used to determine the required throttling.

e. Check bearings of pumps and drivers for signs of heating. Recheck all oil
levels. Check stuffing box for heating. Loosen or tighten packing gland as
required. It is desirable to allow considerable leakage in the stuffing box at the
beginning, to permit packing to run-in. Heating of pump casing may be
attributed to internal rubbing.

f. Run pump for approximately one hour, then shut off to make any adjustment
necessary and check parts for tightness. Since it is robot possible to run pump
at operating temperature, final check of alignment must be made during normal
operation by switching to spare pump.

g. Start pump and run for at least four hours. Shut down and pull strainers. Clean
strainers and replace in line.

h. Replace temporary packing (if used) with normal service packing.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 123 OF

4.6Leak Testing

Leak testing is performed typically with air or nitrogen. It is usually performed on


sections of the unit rather than the whole unit at one time. When leak checking it is
important the personnel involved stay organized and document leaks found. The easiest
way to accomplish this is by flagging any leaks noted and have a repair team follow
closely behind the leak checkers.

(1) The following is a list of guidelines to keep in mind when preparing for and leak
checking.

a. Have on hand a large quantity of soap, squirt bottles and colored tagging
tape. Also needed are a couple of five gallon buckets.

b. Break the unit up into sections to be tested. This way when a leak is found
that cannot be fixed while still under pressure only that section needs to be
depressured. Leak checking on other areas can continue.

c. STAY ORGANIZED. Start at one end of a section and work your way
through to the other end, checking all flanges, valves, fittings, instruments,
etc.

d. Tag each leak found. Also log the location of the leak on a list to make it
easier for maintenance and the next shift to find if. Maintenance crews
should work along with the leak checking teams as much as possible.

e. Check pumps and compressors independently. Because they have packing


leaks which could interfere with the pressure gauge check on the rest of the
unit.

f. Use large quantities of soapy wafer when testing.

g. It is preferable that leak checking be done shortly before startup. This


minimize the change of new leaks developing through additional
maintenance.

(2) The following is a generalized procedure to be used when leak checking:

a. Isolate the section of the unit from the rest of the unit to be tested. Do not
add additional blinds to do this. Block valves should' sufficient.

b. Slowly pressure the section to 1.8 kg/cm2g (25 psig) with nitrogen or air,
Listen for large leaks or open valves. Walk through the entire section.

c. Hold at here for 1 hour while monitoring a low range pressure gauge. If the
leaks are minor less than 1 psig should be lost, then continue. If the leak
rate is greater than 1 psig check the block valves and blinds isolating this
section from others. Also, start leak checking.

d. Slowly pressure the section to be tested to 7 kg/cm2g (100 psig) or design


pressure if less.

e. Monitor an appropriate range pressure gauge for a loss in pressure.

f. Start systematically, leak checking the unit with plenty of soapy water.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 124 OF

g. After all leaks have been repaired and the pressure gauge holds within 2%
of the test pressure for one hour the test is complete.

h. As was mentioned earlier leak check the compressor and pumps separately.
Typically, many small leaks are found on new reciprocating compressors.

i. Depressure the section rapidly through low point valves to maximize water
removal from the unit.

NOTE: It is very important that a good tightness check be performed. Otherwise


during normal operation hydrogen which leaks out of the unit could result in an almost
invisible flame. Also at a given pressure a hydrogen leak will be greater than an air or
nitrogen leak. Since hydrogen is an important product from the Platforming Unit any
leaks represent a loss in valuable product.

4.7Loading Internal Materials

4.7.1Packing of vent gas wash tower

Random packing (carbon raschig ring) shall be loaded through the top manway
according to the packing vendor’s instruction. The tower should be filled with water
before loading packing.

After the loading the height of packing shall be checked.

Refer to engineering drawing of vent gas wash tower (312-V9), D-312-1351-201.

4.8Loading Catalyst

Refer to Section 11.5 for Catalyst Loading.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 125 OF

4.9Purging and Gas Blanketing

It must be remembered that oil or flammable gas should never be charged into process
lines or vessels indiscriminately. The unit must be purged before admitting
hydrocarbons. There are many ways to purge the unit and ambient conditions may
dictate the procedure to be followed: nitrogen or inert gas purging, displacement of air
by liquid filling followed by gas blanketing, or steaming followed by gas blanketing.

When the steam purging followed by fuel gas blanketing is done the following steps
will briefly outline the method.

Potential problems or hazards could develop during the steam purge are as follows:

(1) Collapse due to vacuum: some of the vessels are not designed for vacuum. This
equipment must not be allowed to stand blocked in with steam since the
condensation of the steam will develop a vacuum. Thus, the vessel must be
vented during steaming and immediately followed up with fuel gas purge at the
conclusion of the steam out.

(2) Flange and gasket leaks: thermal expansion and stress during warm-up of
equipment along with dirty flange faces can cause small leaks at flanges and
gasket joints. These must be corrected at this time.

(3) Water hammering: care must be taken to prevent “water hammering” when steam
purging the unit. Severe equipment damage can result from water hammering.

Block in the cooling water to all coolers and condensers.

Shut down fans on fin-fan coolers and condensers. Open high point vents and low
point drains on the vessels to be steam purged.

Start introducing steam into the bottom of the columns, towers, and at low points of
the various vessels. It may be necessary to make-up additional steam connections to
properly purge some piping which may be “dead-ended”.

Thoroughly purge all equipment and associated piping of air. Be sure to open
sufficient drains to drain condensate which will accumulate in low spots and receivers.

When purging is completed, close all vents and drains. Start introducing fuel gas into
all vessels and cut back the steam flow until it is stopped completely when the systems
are pressured. Regulate the fuel gas flow and the reduction of steam so that a vacuum
due to condensing steam is not created in any vessel or that the refinery fuel gas
system pressure is not appreciably reduced.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 126 OF

4.10Pre-Commissioning Check List

This procedure describes in general terms the steps to be followed for placing the unit
on stream. The exact sequence of events depends on the flow scheme of the particular
unit. However, the following steps must be completed before charging oil to
Pratforming Process Unit (Unit-300).

(1) All unnecessary blinds are removed,

(2) All relief valves are tested and installed.

(3) The flare header is purged and in service.

(4) The sewers are in service.

(5) All instruments and control systems are ready for service.

(6) All utilities are in service.

(7) All drains and vents are closed.

(8) Control valves and bypasses are blocked in.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 127 OF

5COMMISSIONING

5.1General Overall Commissioning Plant

5.1.1Introduction

Operators should adhere to the general commissioning plan as far as possible.

It is important that all equipment, lines, pumps, etc., be adequately steamed, air blown,
water washed, and/or flushed during phases of pre-commissioning. The operator shall
maintain a master set of P&ID’s indicating the status of each procedure as it
progresses. Each line, equipment, instrument, etc., should be color coded (i.e. yellow
lined) by the controlling operator as the line, etc., is completed in the procedure.

It is assumed that pre-commissioning activities have been carried out. For subsequent
start-ups, the procedure can be modified to eliminate those parts unique to the initial
start-up and also incorporate any changes which experience with the initial start-up
may show to be desirable.

Following is the suggested sequence of operations for the initial start-up of the plant.

Remember, the operator is, at all times, responsible for the condition of the unit and is
expected to take whatever action is necessary to safeguard the plant and carry out the
start-up in a satisfactory manner.

5.1.2Prestart-up checks

Prestart-up checks are reviewed to prevent inadvertent delays in start-up.

To avoid repetition in the write-up, certain procedures will be standard in all systems,
These procedures are listed below:

All pump suction, discharge, and minimum flow valves will be closed and the drain
valves ahead of the suction and discharge valves will be opened.

All pump case drains will be opened.

All control valves will be left in the closed position, the bypass and drain valves will
be opened.

The inlet, outlet, and drain valves on all exchangers, reboilers, and fin fans will be
opened during the steam purge.

Water cooled exchangers will have the cooling water supply and return valves closed
and the tube side vent and drain open.

Use the P&ID drawings and mark off each line with a colored pen as it is lined up and
steam purge is completed.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 128 OF

When leak testing check the systems using the following procedure:

If any leaks are found, repair them if possible. If the leaks cannot be repaired, make a
repair list and if possible, isolate the line or vessel and depressure to make repairs. If
the entire system must be depressured, do so. Make the repairs and depressure the
system to check the repairs.

All unit hydrotests are to be completed when individual equipment has been opened for
repairs such as exchangers ,furnaces, steam generators, and etc.

5.1.3Outline of commissioning procedure

The detailed startup procedure outlined below is divided into 11 sections. The timing of
some sections and steps is a matter of convenience, while others may fall into a
necessary sequence. Some of the sections and steps can or must be carried out
simultaneously.

(1) Air-free the Regeneration Section.

(2) Start up the Platforming Process Unit in accordance with UOP start-up
procedures.

(3) Establish catalyst collector and reduction zone purge flows.

(4) Pressure up the Regeneration Section Hydrogen System with recycle gas from
the Platforming reactor section.

(5) Commission the booster gas line from the net gas compression section.

(6) Start flow of reduction gas, lift gas to the Regenerated Catalyst L-Valve
Assembly, and makeup gas.

(7) Pressure up the Regeneration Tower with nitrogen.

(8) Pressure the Nitrogen Lift System and establish the Spent Catalyst nitrogen
“bubble” below the Reactor.

(9) Establish the nitrogen “bubble" between the Regeneration Tower and the Lock
Hopper.

(10) Commission the Lock Hopper and establish control of catalyst levels.

(11) Establish catalyst circulation.

(12) Establish a Carbon Level in the Regeneration Tower.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 129 OF

5.2Detailed Step-by-Step Start-up Procedure

BASIS: This section is written with the assumption that all of the Regeneration
Section’s CCR Preliminary Operations have been completed. For the initial startup of
the Regeneration Section, it is essential that each step of this Final Startup Preparation
be completed prior to starting coke burning operations. For subsequent startup; of the
Regeneration Section, however, some variation in the Final Startup Preparation is
possible, depending on how completely the Regeneration Section was shutdown. In
fact, for most subsequent startups, the startup sequence can begin with the Black
Catalyst Startup Procedure or the White Catalyst Startup Procedure, whichever
applies.

IMPORTANT: Before beginning the Final Startup Preparation, ensure that all
shutdown bypass switches are in the NORMAL position.

5.2.1Air-free the regeneration section

The Regeneration Section must be purged with nitrogen to remove any oxygen prior
to admitting combustible gases into any part of the system. To accomplish this, the
Regeneration Section is divided into five loops:

Nitrogen Header
Equipment that is included with the Platforming reactor circuit
Regeneration Section Air System and nitrogen Lift System
Regeneration Section hydrogen System

Nitrogen should be purged through all vents, drains, and instrument taps to ensure
that no air pockets are missed. Care should be taken not to back-purge into a system
that has previously been purged. In the case of unavoidable dead ends in piping
systems, an effective nitrogen purge can only be achieved by repeated pressuring and
venting to atmosphere.

a. Nitrogen Header

Purge all piping from the independent nitrogen source through the nitrogen
header to the various nitrogen users in the Regeneration Section. Commission
the nitrogen header.

b. Equipment that is included with the Platforming reactor circuit.

The following equipment and its associated piping is evacuated and purged
simultaneously with the Platforming Unit reactor circuit:

Reactor Purge Exchanger


Reactor Catalyst Collector purge line
Reduction Zone
Reduction Gas Exchanger and outlet line to Platforming Unit
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 130 OF

c. Regeneration Section Air System and Nitrogen Lift System.

This system includes the Regeneration Tower, Nitrogen Seal Drum, and
associated piping. It also includes the Spent Catalyst L-Valve Assembly, Spent
Catalyst Lift Pipe, Disengaging Hopper, Dust Collector, Lift Gas Blower, Fines
Removal Blower, Catalyst Addition Lock Hopper, and the associated piping.

Prepare this system as follows:

(1) Ensure that the Spent Catalyst and Regenerated Catalyst Isolation
Systems are closed.

NOTE: The nitrogen purge line between the two V-ball valves of each isolation
system should be open and the manual valves in these lines should be locked
open.

(2) Purge the system using nitrogen through the Air Heater into the Cooling
Zone and through the Regeneration Tower. Vent from the Burn Zone vent
to atmosphere.

(3) Purge the system using nitrogen from the Nitrogen Seal Drum normal
addition point. Vent into the Regeneration Tower.

(4) Purge the Burn Zone circuit and the Reheat Zone circuit using the
Regeneration Blower.

(5) Purge the system using nitrogen from the normal addition point down
stream of the fines removal blower.

(6) Purge the Fines Removal circuit and the Lift Gas circuit using the Fines
Removal and Lift Gas Blowers.

(7) Maintain the purge flows. Keep the Regeneration Section Air System
under a slight positive pressure of nitrogen for the startup.

d. Regeneration Section Hydrogen System.

This system includes the Lock Hopper, Reduction Gas Heaters, Regenerated
Catalyst L-Valve Assembly, Regenerated Catalyst Lift Pipe, Booster Gas
Coalescer, and Booster Gas Heater. Air-free this system as follows:

(1) Isolate the Hydrogen System from:

Regeneration Section Air System – At the Regenerated Catalyst Isolation


System.

Reactor Section – At the booster gas coalescer drain, downstream of the


Reduction Gas Heaters, the Lock Hopper offgas line, and at the ball valve
at the top of the Regenerated Catalyst lift pipe.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 131 OF

Net Gas Section – Immediately upstream of the booster gas coalescer.

Fuel Gas Section – At the Lock Hopper offgas line (if applicable).

(2) Evacuate the Regeneration Section Hydrogen System and pressure with
nitrogen:

(a) Unblock valves in the Hydrogen System so that the pressure


throughout the system is equalized.

(b) Isolate pressure instruments during evacuation.

(c) Connect the ejector manifold to the outlet of the Booster Gas
Heater.

(d) Commission the ejector and evacuate the Hydrogen System to at


least 600 mm Hg (24 in Hg) vacuum. Hold for one hour to
determine system tightness. Break the vacuum and pressure up the
system to 0.35 kg/cm2g (5 psig) with nitrogen. Hold the pressure
for one hour to determine system tightness.

(e) Evacuate the Hydrogen System again to at least 600 mm Hg (24 in


Hg) vacuum. Break the vacuum and pressure up the system again
to 0.35 kg/cm2g (5 psig) with nitrogen. Repeat until oxygen
measurements are less than 0.1 vol-%. In the case of dead ends in
piping, purge by repeated pressuring with nitrogen and venting.

(f) Purge instrument taps and commission instruments.

(g) Keep the system under a slight positive pressure of nitrogen for the
startup.

5.2.2Start up the platforming process unit in accordance with UOP startup procedures

a. Commission the fuel gas system.

b. Start up the reactor section, net gas compression section, and the fractionation
section of the platforming process unit in accordance with UOP startup
procedures. Line out at normal operating conditions, especially the normal
Reactor pressures.

5.2.3Establish catalyst collector and reduction zone purge flows

It is imperative that the recycle gas purge flow to the Catalyst Collector and
Reduction Zone be started when the Platforming Recycle Compressor is first placed
on stream.

a. Raise the flow of the Catalyst Collector stream up to design rates as soon as
possible.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 132 OF

b. Raise the temperature of the Catalyst Collector purge along with the reactor
inlets up to its normal operating temperature.

c. Establish recycle gas purge flow to the Reduction Zone to maintain the pressure
in that zone above that of the reactor.

5.2.4Pressure up the regeneration section hydrogen system with recycle gas from the
platforming reactor section

a. Pressure up the system to 0.35 kg/cm2g (5 psig) with nitrogen.

b. Evacuate the hydrogen system again to at least 600 mm Hg (24 in Hg) vacuum.
Break the vacuum and pressure up the section to 0.35 kg/cm 2g (5 psig) with
recycle gas.

c. Pressure up the system with recycle gas to about 2.5 kg/cm2g (35 psig). Hold
the pressure for one hour to determine system tightness.

5.2.5Commission the booster gas line from the net gas compression section

a. Close the booster gas valve in the line to the Reduction Zone, and the control
valves for the total and secondary lift gas to the Spent Catalyst L-Valve
Assembly.

b. Open the Booster Gas Coalescer drain.

c. Open the valves upstream of the Booster Gas Coalescer. Booster gas will
pressure up the Booster Gas Coalescer and heater to the pressure of the High
Pressure Separator.

d. Commission the Booster Gas Heater.

5.2.6Start flow of reduction gas, lift gas to the regenerated catalyst L-valve assembly,
and makeup gas

a. Reset the solenoid in instrument air line of the PDV in the Reduction Gas Outlet
line. The Reduction Zone/Reactor pressure differential control valve should be
closed and on auto control.

b. Establish the booster gas flow to the Reduction Zones at their design flows. The
flow rates are adjusted by hand operated control valves. With the introduction
of booster gas the Reduction Zone/Reactor No. 1 pressure differential will come
into its control range. When the pressure differential is established, the recycle
gas purge gas valve will close.

c. Open the ball valve in the regenerated catalyst lift line at the top of the
Platforming reactors. Recycle gas will pressure up the L-Valve Assembly to
about the inlet pressure of the first reactor.

d. Establish total lift gas to the L-Valve assembly.

e. Open the manual valves below the Lock Hopper, B-valve first.

f. Make sure that the Lock Hopper is in the STOP step.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 133 OF

g. Start makeup gas to the Surge Zone of the Lock Hopper. Open the Surge
Zone/L-Valve differential pressure control valve in manual. Booster gas will
pressure up the Surge Zone. Unblock the logic-ramped Makeup Valve, which is
in Mode No. 1 because the Lock Hopper is stopped. Booster gas will continue
to pressure up the Surge Zone to about the pressure of Platforming Reactor No.
1. When the differential pressure controller comes into range, control in
automatic the pressure of the Surge Zone of the Lock Hopper at the design
differential pressure.

5.2.7Pressure up the regeneration tower with nitrogen

a. Close the Burn Zone vent control valve. The lower nitrogen purge to the cooling
zone will pressure up the Regenerator. Slowly increase the pressure of the
Regeneration Tower to about 2.5 kg/cm2g (35 psig). Hold the pressure for one
hour to determine system tightness by checking for leaks at all flanges. The
system will not hold pressure because of leakage through the seals of the
Regeneration Blower.

b. Restart the lower N2 purge and control the differential pressure between the
Lock Hopper and the Regeneration Tower at 0 mm H2O (0 in. H2O).

5.2.8Pressure the nitrogen lift system and establish the spent catalyst nitrogen “bubble”
below the reactor

a. Depress the Regenerator Run/Stop Pushbutton to RUN.

b. Open the nitrogen valve to the Nitrogen Lift System. Increase the lift system
pressure to 500 mm H2O (20 in. H2O) higher than the Catalyst Collector purge
line according to the differential pressure indicator.

c. Commission the Lift Gas Blower and Fines Removal Blower. Establish design
flows to the Disengaging Hopper and total lift gas to the Spent Catalyst L-Valve
Assembly.

d. Open the manual valves below the Catalyst Collector.

e. Depress the Spent Catalyst Isolation Pushbutton to OPEN.

f. Adjust the differential pressure controller to control the Nitrogen Lift System
pressure 500 mm H2O (20 in. H2O) higher than the Catalyst Collector purge
line.

5.2.9Establish the nitrogen “bubble" between the regeneration tower and the lock
hopper

a. Open the nitrogen valve to the Nitrogen Seal Drum. Increase the Seal Drum
pressure to 250 mm H2O (10 in. H2O) higher than both the Regeneration
Tower and the Lock Hopper.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 134 OF

b. Depress the Regenerated Catalyst Isolation Pushbutton to OPEN.

c. Adjust the two differential pressure controllers – one between the Regeneration
Tower Cooling Zone and the Nitrogen Seal Drum and the other between the
Nitrogen Seal Drum and the Lock Hopper – to control the Nitrogen Seal Drum
pressure 250 mm H2O (10 in. H2O) higher than both the Cooling Zone and the
Lock Hopper.

5.2.10Commission the lock hopper and establish control of catalyst levels.

a. Cascade the secondary lift gas for the Spent Catalyst L-Valve Assembly to the
Spent Catalyst Lift Line Pressure Differential Controller, which in turn is reset
by the level controller for the Reduction Zone.

b. Cascade the secondary lift gas for the Regenerated Catalyst L-Valve Assembly
to the Regenerated Catalyst Lift Line Pressure Differential Controller.

c. Turn the shutdown bypass switches for the Burn Zone Gas flow, Drying Zone
Air flow, and Oxygen Analyzer Sample flow to the BYPASS position. When the
fourth switch is turned, catalyst circulation for both L-Valve Assemblies will be
enabled.

Allow the differential pressure controller between the Surge Zone of the Lock
Hopper and Regenerated Catalyst L-Valve Assembly to reestablish the pressure
in the Surge Zone at the design differential higher than the pressure of L-Valve
Assembly.

d. Adjust the level for the Reduction Zone to normal.

5.2.11Establish catalyst circulation

Establish catalyst circulation as follows:

a. Set the Catalyst Flow Setpoint at 50% of the design catalyst circulation rate.

b. Depress the Catalyst Flow Pushbutton to start transfer of catalyst from the
Lock Hopper to the Reduction Zone. This action will initiate the ramping of
secondary gas to the Regenerated Catalyst L-Valve Assembly.

c. Increase the catalyst circulation rate stepwise to the desired rate but no higher
than the design catalyst circulation rate.

d. Monitor the catalyst level in the Disengaging Hopper.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 135 OF

5.2.12Establish a carbon level in the regeneration tower

The reactor section of the Platforming Process Unit is in operation, and so the coke
content of the catalyst in the reactors will increase.

a. Continue catalyst circulation at the desired catalyst circulation rate, but no


higher than the design catalyst circulation rate.

b. Analyse daily the spent catalyst for carbon. Take a sample at the sample point
between the Disengaging Hopper and the Regeneration Tower.

c. Stop catalyst circulation when the carbon content of the spent catalyst is about
3.0 wt-%. Proceed with the Black Catalyst Startup Procedure.

CAUTION NOTES FOR THE CYCLEMAX CCR UNIT

CAUTION:
All equipment containing hydrogen shall be evacuated and purged with nitrogen before
opening and admitting air and after closing before admitting hydrogen.

CAUTION:
Care must be exercised when venting and draining equipment to prevent personnel exposure
to toxic aromatics.

CAUTION:
All upstream and equipment must be purged with inert gas before isolating the relief gas
header from the line to the knockout drum and flare.

Same start-up procedures as Normal start-up after prolonged shut down described in
Section 6.1 should be followed for the initial start-up for this unit.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 136 OF

FIGURE 5.2-1

Sequence for Preliminary Regeneration


Section Preparation

Check the Logic Wiring Set Logic


Trips, Timers
Check Valve Install Hand Service and Cycle Load
Clearances and Travel Valves Stroke Calibrate Logic Dry Out Catalyst
Valves Instruments Regenerator in Lock Hopper, Calibrate Test
Regenerator Lock Circulate
& Disengaging Hopper Catalyst
Hopper
Re Bench Pressure Test Service Prepare
ge Test
Relief
Blower Casing,
Steam Heaters,
& Run-In
Blowers
Electric
Heaters
Pressure Test Regenerator,
Lock Hopper Systems
ne Valves Water Coolers
Load
rat Vessel Inspection Install and
or & Punch list Complete TI
Assemblies
Cycle
Air
Dryers
Blower Down Lines,
Install R.O.’s, Filters, Etc.

Pl
atf Vessel Inspection Dryout Catalyst Loading Feed in
&Punch list Complete
or
me
r
Note: Hydrostatic Pressure Testing by Contractor and Commissioning of Utilities Should
Be Complete Prior to the Above Timing.

UOP 1538-70
PLT-R00-71
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 137 OF

5.3Special Procedures

5.3.1Regenerator coke burn test procedure

Regenerator Coke Burn Tests quantify the maximum coke burning potential of the
Regeneration Tower. The result of the tests is a specific operating guideline chart,
similar to the General Operating Curve, but representing the full coke-burning
potential of the as-built Regeneration Tower.

A Regenerator Coke Burn Test consists of first circulating catalyst with a high coke
content through the Burn Zone and then testing to determine how much of the coke is
burned away. The testing is done at several different Burn Zone conditions. However,
all of the testing is done with the Regeneration Tower in black burn conditions (i.e.,
upper air injection only, nitrogen to the Air Heater).

Black burn conditions are required for Coke Burn Tests for two reasons. First, under
certain Coke Burn Test conditions, a significant amount of the coke being circulated
through the Burn Zone may not be burned away. With an all-nitrogen atmosphere in
the Chlorination and Drying Zones, any residual coke (above 0.1 wt-% coke) on the
catalyst exiting the Burn Zone will not cause overheating and damage to catalyst and
equipment. Second, black burn conditions permit measurement of an important
variable: the Burn Zone oxygen utilization. The Burn Zone oxygen utilization is
calculated using the Burn Zone outlet oxygen concentration of the Regeneration Gas,
and this is representative of the Regeneration Gas exiting the Burn Zone bed only
during black burn conditions.

An operating guideline chart representing the full coke burning potential of the
Regeneration Tower can be constructed based on the results of the Coke Burn Tests. To
be conservative, this chart should be based on an oxygen utilization factor lower than
the utilization factor actually measured. In spite of this conservatism, such a chart will
generally establish greater coke burning potential for the Regeneration Tower than that
afforded by the General Operating Curve.

Aside from evaluating the maximum coke burning potential of the Regeneration Tower,
the Regenerator Coke Burn Tests offer an excellent opportunity to characterize
operating temperature profiles exhibited by the Burn Zone catalyst bed thermocouples
for known coke burning rates and residual coke contents. Profiles such as these will
provide a basis for comparing profiles observed during normal operation.

For further information and the current coke burn test procedure contact the UOP
Platforming Technical Service Department.

5.3.2Catalyst fines survey procedure

In order to achieve optimum performance of both the reactor and regeneration sections
of the Continuous Platforming Process Unit, it is essential that catalyst fines be
efficiently removed from the circulating catalyst inventory. In this regard, a fines
survey should be conducted monthly to check the performance of the elutriation
system. Based on the results of these surveys, elutriator velocity should be set, by
adjustment of the elutriation gas flow, to maximize the removal of material under 0.040
inches and at the same time limit whole sphere carryover to the Dust Collector to a
tolerable level, typically 20-30 wt%. The duration of a fines survey is generally eight
hours.

A recommended catalyst fines survey procedure along with example calculations is


found below.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 138 OF

5.3.2.1Prior to the survey

a. Thoroughly blow down the Dust Collector and Fines Collection Pot.

b. Install an empty, tared 55-gallon drum to collect fines beneath the Fines
Collection Pot.

c. Set the elutriation gas flow at the desired rate. Set the total nitrogen lift gas
flow to the Spent Catalyst L-Valve Assembly at the design rate based on lifting
catalyst.

d. Line out the catalyst levels in the Reduction Zone and the Disengaging Hopper.

e. Record the number of transfer cycles on the Lock Hopper cycle counter.

5.3.2.2During the survey

a. Maintain elutriation gas flow and lift gas flows steady to provide constant
elutriator velocity.

b. Maintain steady Reactor Surge Zone and Disengaging Hopper catalyst levels.

c. Collect a 500 cc composite sample of Disengaging Hopper product catalyst.

5.3.2.3At the conclusion of the survey

a. Record the number of transfer cycles on the Lock Hopper cycle counter.

b. Thoroughly blow down the Dust Collector and Fines Hopper.

c. Determine the net weight of fines collected during the survey.

d. Collect a 500 cc sample of the fines drum material.

e. Determine the size distribution of the Disengaging Hopper product catalyst and
fines drum material using laboratory analysis method UOP-333.

NOTE: The apparatus section of UOP 333 should be modified as explained in


Laboratory Test Schedule in Section IX.

f. Compute the percent removal of the various particle sizes as follows:

(1) Based on the number of transfer cycles of the Lock Hopper cycle counter
compute the total weigh of catalyst fed to the Disengaging Hopper during
the survey.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 139 OF

(2) Compute the total weight of Disengaging Hopper product by subtracting


the total fines weight from the total Disengaging Hopper catalyst feed
weight.

(3) Compute the weight of the various size ranges making up the Disengaging
Hopper product and fines streams by multiplying the UOP-333 results by
the respective total stream weights.

(4) Compute the weight of the various size ranges making up the Disengaging
Hopper feed by adding the weight breakdowns on the Disengaging
Hopper product and fines streams.

(5) Compute removal of the various size ranges by dividing the weights of
each size range contained in the fines stream by the corresponding weights
contained in the Disengaging Hopper feed stream. Convert fractions to
percent.

g. On five-cycle semi-log graph paper, plot percent removal on the log scale
versus average particle size on the linear scale.

An example of typical fines survey calculations is presented below:

FINES SURVEY CALCULATION EXAMPLE

Given the following plant data:

Lock Hopper transfers during fines survey 96


Lock Hopper load size 251.5 lbs
Total fines and whole pills collected during fines survey 5.9 lbs
Total fines collected during fines survey 4.1

Fines and D.H. sample size breakdown as follows:

SIZE BREAKDOWN
Size Fines D.H. Product
(U.S. Sieve No.) (wt-%) (wt-%)
14 19.06 99.98
16 10.89 0.016
18 18.47 0.0037
20 4.12 0.0001
30 8.56 0.0001
Pan 38.9 0.0001

Compute the fines removal efficiency during the survey as follows:

(1) Total catalyst circulated during survey period (MT)


MT = (96) (251.5) = 24144 lbs

(2) Total D.H. Product (MD)


MD = 24144 - 5.9 = 24138.1 lbs
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 140 OF

(3) Calculated spent catalyst size breakdown


For each size range:
Fines + D.H. Product = Spent Catalyst

i.e., for 14 mesh:


(19.06) ´ (0.01) ´ (5.9) + (99.98) ´ (0.01) ´ (24138.1) = 24134.40

Etc.

SIZE BREAKDOWN BY ANALYSIS


Spent
Size Fines D.H. Product Catalyst
U.S.
Sieve No. Wt-% lbs wt-% lbs lbs
14 19.06 1.125 99.98 24,133.27 24,134.40
16 10.89 0.643 0.016 3.862 4.505
18 18.47 1.090 0.0037 0.893 1.983
20 4.12 0.243 0.0001 0.024 0.267
30 8.56 0.505 0.0001 0.024 0.529
Pan 38.9 2.295 0.0001 0.024 2.319
TOTAL 5.9 24,138.1 24,144.0

(4) Fines removal efficiency

For each size range:

Fines
´ 100% = wt-% Removal
Spent Catalyst

i.e., For 14 mesh:


1.125
´ 100% = 0.0047%
24134.40

Etc.

Size Avg. Particle Size


(U.S. Sieve No.) (In.) Wt-% Removed
14 0.055 0.0047
16 0.0505 14.3
18 0.0425 55.0
20 0.036 91.0
30 0.028 95.4
PAN 0.023 99.0
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 141 OF

(5) Graph results (Figure 5.3-1).

5.3.2.4Interpretation of the data

Figure 5.3-1 shows a typical case of fines removal efficiency. Every unit should be
capable of achieving this level of fines removal.

In order to choose the “best” elutriation gas velocity, fines surveys should be
performed over a 0.6 m/sec (2 ft/sec) span in elutriation gas velocity at 0.1 m/sec
(0.25 ft/sec) increments. As the elutriation gas velocity increases, more total catalyst
fines are removed. At some point, the amount of fines (defined as catalyst on U.S.
Sieve No. 18 and smaller) removed remains constant with increasing elutriation gas
velocity. At gas velocities above this point, the increase in catalyst and fines removed
is solely due to an increase in the catalyst removed (U.S. Sieve No. 16 and larger).
Therefore, the optimum gas velocity would be at this point of maximum fines removal
without excessive catalyst removal. Refiners who choose to operate below this
optimum gas velocity for the sake of minimizing whole catalyst removal do so at the
expense of more frequent Regenerator centerscreen cleaning. Note that catalyst and
fines are on a volatile-free basis.

5.3.3Safeing procedures

The following safeing procedures are general in nature and are not meant to apply to
any one particular unit. The purpose in presenting these general procedure outlines is
to assist the refiner in developing more detailed procedures for his particular unit.

5.3.3.1Safeing procedure for the reduction gas system

The Reduction Gas System includes the Booster Gas Coalescer, Booster Gas Heater,
Reduction Gas Heaters No. 1 and No. 2, and the Reduction Gas outlet line including
the Reduction Gas Exchanger and filters. To perform maintenance on any equipment in
this system, the whole system must be isolated, depressured and inerted.

The following procedure outlines a general procedure for carrying out this operation.
This outline is written with the assumption that the Regeneration Section has been
operating under normal conditions.

a. Shut down the Regeneration Section manually in accordance with the Cold
Shutdown procedure.

NOTE: It is not necessary to cool the Regeneration Tower down to 200ºC


(400ºF) in order to continue isolation of the Reduction Gas System.

b. Stop Regenerated Catalyst lift gas flow by closing the primary and secondary
lift gas control valves on manual.

c. Stop steam flow to the Booster Gas Heater by closing the steam condensate
control valve on manual.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 142 OF

d. Stop the Booster Gas supply to the system by closing the Booster Gas inlet
valves to the Booster Gas Coalescer. Close the coalescer drain valves.

The loss of reduction gas and lift gas flow should signal the Regenerated
Catalyst lift line valve to close, and for the Reduction Zone recycle gas purge
valve to open.

e. Isolate the Reduction Gas system from the reactor section, net gas section, and
the Lock Hopper. Use double-block and bleed valve assemblies where they are
provided.

(1) Close the double-block and bleed assembly at both the primary and
secondary lift gas control valves.

(2) Close the double-block and bleed assembly at both the makeup gas control
valves.

(3) Close the double-block and bleed assembly on the Reduction Gas outlet
line located at the reactor vessel.

(4) Close double-block and bleed assembly at the pressure differential control
valve on the Reduction Gas outlet line.

(5) Close the single-block valve at the outlet of both Reduction Gas Heater
No. 1 and No. 2. A single-block valve is used in these locations due to
heat loss considerations in the piping downstream of the heaters. Blinds
should be inserted at these points once the system is depressured.

f. Depressure the Reduction Gas System to flare using the relief valve bypass on
the reduction gas supply line take off at the Booster Gas Coalescer.

g. Close the blinds at each block valve described in step e.(5).

h. Depressure the reduction outlet line between the reactor and the pressure
differential control valve using the vent provided at the filters.

i. Evacuate the Reduction Gas System and pressure with nitrogen.

(1) Connect the ejector manifold to the Booster Gas line downstream of the
coalescer.

(2) Commission the ejector and evacuate the system to at least 600 mm Hg
(24 in Hg) vacuum. Break the vacuum and pressure up the system to 0.35
kg/cm2g (5 psig) with nitrogen from purge points at the outlet of
Reduction Gas Heater No. 2, makeup gas control valves, and lift gas flow
control valves.

(3) Repeat evacuation and purging until combustibles measurements are less
than 0.1 vol%.

(4) Keep the system under a slight positive pressure for the maintenance.

j. Purge the Reduction Gas outlet line with nitrogen from the purge point located
at the double-block and bleed assembly to the relief header via the vents at the
filters.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 143 OF

k. After the maintenance has been completed, the equipment has been reinstalled,
and the blinds removed from the lines, the system can be air freed by the
evacuation and purging procedure given above.

l. Pressure the system back up to operating pressure by slowly opening the


isolation valves in the Booster Gas supply line to the coalescer and the
coalescer drain valves.

m. Un-isolate the system by opening the double-block and bleed assemblies closed
in step e. of this procedure.

n. Commission the steam to the Booster Gas Heater as well as lift gas and
reduction gas flows.

o. Restart the Regeneration Section in accordance with either the Black Catalyst
Startup procedure or the White Catalyst Startup procedure, whichever applies.

5.3.3.2Safeing procedure for the lock hopper system

The Lock Hopper system includes the Lock Hopper and its associated piping along
with the Regenerated Catalyst lift line. To perform maintenance on the Lock Hopper,
the whole system must be isolated, depressured and inerted.

The following procedure outlines a general procedure for carrying out this operation.
This outline is written with the assumption that the Regeneration Section has been
operating under normal conditions.

a. Shut down the Regeneration Section manually in accordance with the Hot
Shutdown procedure.

b. Isolate the Lock Hopper System from the reactor section, net gas section, and
the Regeneration Tower. Use double-block and bleed valve assemblies where
they are provided.

(1) Close the double-block and bleed assembly at both the primary and
secondary lift gas control valves.

(2) Close the double-block and bleed assembly at both the makeup gas
control valves.

(3) Close the double-block and bleed assembly at the Lock Hopper outlet line.

(4) Close the Regenerated Catalyst lift line isolation valve by pressing the
Regenerated Catalyst Lift Line Valve Pushbutton.

(5) Close the Regenerated Catalyst Isolation system by pressing the


Regeneration Catalyst Isolation Close Pushbutton.

c. Depressure the Lock Hopper system to flare using the vent line at the top
equalization valve line.

d. Blind off the lines at the Regenerated Catalyst Lift Line Valve and below the
Regenerated Catalyst Isolation system.

f. Evacuate the Lock Hopper system and pressure with nitrogen.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 144 OF

(1) Connect the ejector manifold to the secondary lift gas line downstream of
the control valve.

(2) Commission the ejector and evacuate the system to at least 600 mm Hg
(24 in Hg) vacuum. Break the vacuum and pressure up the system to 0.35
kg/cm2g (5 psig) with nitrogen from the hard piped addition line on the
Lock Hopper gas outlet line.

(3) Repeat evacuation and purging until combustibles measurements are less
than 0.1 vol%.

(4) Keep the system under a slight positive pressure for the maintenance.

g. After the maintenance has been completed, the equipment has been reinstalled,
and the blinds removed from the lines, the system, can be air freed by the
evacuation and purging procedure given above.

h. Pressure the system back to operating pressure by opening the control valve
then slowly opening the isolation valve on the secondary lift gas line.

i. Un-isolate the system by opening the double-block and bleed assemblies and
isolation valves closed in step (b) of this procedure.

j. Restart the Regeneration Section in accordance with either the Black Catalyst
Startup procedure or the White Catalyst Startup procedure, whichever applies.

5.3.3.3Safeing procedure for the regenerated catalyst lift line

The Regenerated Catalyst lift line includes the lift line from the reactor to the lift gas
control valves. To perform maintenance on any equipment in this system, the whole
system must be isolated, depressured, and inerted.

The following procedure outlines a general procedure for carrying out this operation.
This outline is written with the assumption that the Regeneration Section has been
operating under normal conditions.

a. Shut down the Regeneration Section manually in accordance with the Hot
Shutdown procedure.

b. Close the manual V-port valve and then the manual ball valve below the Lock
Hopper to allow the lift line to clear of catalyst.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 145 OF

c. Isolate the lift line from the reactor, Lock Hopper, and Booster Gas system. Use
double-block and bleed assemblies where they are provided.

(1) Close the double-block and bleed assembly at both the primary and
secondary lift gas control valves.

(2) Close the Regenerated Catalyst lift line isolation valve by pressing the
Regenerated Catalyst Lift Line Valve Pushbutton.

d. Depressure the lift line to flare using the vent line at the secondary lift gas line.

e. Blind off the lines at the Regenerated Catalyst lift line valve and below the
manual valves under the Lock Hopper.

f. Evacuate the lift line and pressure with nitrogen.

(1) Connect the ejector manifold to the secondary lift gas line downstream of
the control valve.

(2) Commission the ejector and evacuate the system to at least 600 mm Hg
(24 in Hg) vacuum. Break the vacuum and pressure up the system to 0.35
kg/cm2g (5 psig) with nitrogen from the purge point downstream of the
primary lift gas control valve.

(3) Repeat the evacuation and purging until combustibles measurements are
less than 0.1 vol%.

(4) Keep the system under a slight positive pressure for the maintenance.

g. After 1he maintenance has been completed, the equipment has been reinstalled,
and the blinds removed from the lines, the system can be air freed by the
evacuation and purging procedure given above.

h. Pressure the system back to operating pressure by opening the control valve
then slowly opening the isolation valve on the secondary lift gas line.

i. Un-isolate the system by opening the double-block and bleed assemblies and
isolation valves closed in step (b) of this procedure.

j. Restart the Regeneration Section in accordance with either the Black Catalyst
Startup procedure or the White Catalyst Startup procedure, whichever applies.

5.3.3.4Safeing procedure for regeneration section air system and nitrogen lift system

The Regeneration Section air and nitrogen systems include the Regeneration Tower
and its associated piping, and the nitrogen lift circuit. To perform maintenance on any
equipment in this system, the system must be isolated, depressured, and inerted. This
system should not be evacuated using the ejector. To perform any maintenance
requiring the catalyst in the Regeneration Tower to be unloaded, follow the Catalyst
Unloading and Reloading Procedure in Part D of this section. In most other cases, the
following procedure outlines a general procedure for preparing the Regeneration
Section air system for maintenance:

a. Shutdown the Regeneration Section manually in accordance with the Cold


Shutdown procedure. This closes the Spent Catalyst and Regenerated Catalyst
Isolation Systems, isolating the Regeneration Section air system from the
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 146 OF

Regeneration Section hydrogen system. If maintenance is required on the


isolation system valves, this system can be isolated by closing the manual
valves below the reactors and closing the blind below the valves.

b. Depressure the Regeneration Tower through the Burn Zone vent valve. Keep the
system under a slight positive nitrogen pressure.

c. At this point, maintenance procedures can be performed on the equipment in the


air system. The maintenance procedures will vary depending on the particular
piece of equipment involved. In any case, the procedures should minimize the
ingress of ambient air and any moisture into the air system.

d. After the maintenance has been completed, the equipment has been reinstalled,
and the flanges in the air system have been closed, the Regeneration Section can
be prepared for restarting in accordance with the Final Startup Preparation
Procedure.

e. Restart the Regeneration, Section in accordance with either the Black Catalyst
Startup Procedure or the White Catalyst Startup Procedure, whichever applies.

5.3.4Catalyst unloading and reloading procedures

The following procedures for unloading and reloading the Regeneration Tower are
general in nature and are not meant to apply to any one particular unit. The purpose in
presenting these general procedure outlines is to assist the refiner in developing more
detailed procedures for his particular unit.

Some maintenance procedures require that the catalyst be unloaded from the
Regeneration Section while the Platforming reactor section remains in operation.
Cleaning the screens in the Regeneration Tower is an example of such a procedure.
The catalyst is first unloaded from the Regeneration Tower into catalyst drums at
grade, and then reloaded via the Catalyst Addition Lock Hopper No. 1, while the
reactor section remains in operation.

5.3.4.1Regeneration tower catalyst unloading

The following outlines a general procedure for unloading catalyst from the
Regeneration Tower. This procedure is written with the assumption that the
Regeneration Tower is operating under normal white burn conditions (lower air only):

a. Stop catalyst circulation by depressing the Catalyst Flow Off Pushbutton. Let
the Reduction Zone and the Disengaging Hopper levels stabilize.

b. Close the manual V-ball, only, below the Catalyst Collector.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 147 OF

c. Place the secondary gas flow control to the Spent Catalyst L-Valve Assembly
off cascade from the lift pipe pressure differential controller. Slowly start
secondary gas flow to clear catalyst from the catalyst transfer line below the
closed V-ball valve and the lift pipe.

d. Close the manual B-valve below the Catalyst Collector.

e. Press the Regeneration Stop Button. This will perform the following:

- Close both isolation systems.


- Shut the power off to the Regeneration Gas Heater, and the Air Heater.
- Close both catalyst flow interrupt systems.
- Stop catalyst addition.
- Start nitrogen addition to the Regeneration Tower.
- Stop air addition to the Regeneration Tower.
- Stop chloride injection to the Regeneration Tower.

f. Switch the control element for the Spent Catalyst Lift Pipe pressure differential
control valve from the pressure differential transmitter to the pressure
transmitter on the Fines Removal Blower discharge line.

g. Lower the nitrogen lift gas system pressure to just below that of the
Regeneration Tower. This should serve to close the nitrogen addition to this
system.

h. Stop the Fines Removal Blower and the Lift Gas Blower.

i. Continue Regeneration Gas Blower operation to cool catalyst in the Burn Zone
down to approximately 200ºC (400ºF).

j. Stop the Regeneration Gas Blower and the Cooler Blower.

k. Connect the catalyst withdrawal line at the outlet of the Regeneration Tower.

l. Locate sufficient catalyst drums to contain the catalyst from the Disengaging
Hopper and Regeneration Tower. Catalyst will be unloaded at grade from the
exit of the catalyst withdrawal line.

m. Open the valve at the bottom of the catalyst withdrawal line and unload catalyst
into drums.

n. When approximately 80% of the catalyst in the Disengaging Hopper and the
Regeneration Tower has been unloaded, reduce the Regeneration Tower
pressure to below 0.35 kg/cm2g (5 psig). This will prevent high pressure
nitrogen from exiting the tower when the catalyst level drops.

o. Close the valves in the catalyst withdrawal line when the line clears of catalyst.

p. Cool the Regeneration Tower with the design nitrogen purge to the Drying Zone
until all temperatures are below 38°C (100°F).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 148 OF

q. Reduce nitrogen flow to the Regeneration Tower to the minimum required to


maintain pressure control.

r. Maintain the Regeneration Tower under a slight positive pressure with nitrogen.

5.3.4.2Catalyst reloading

The following outlines a general procedure for reloading catalyst into the Regeneration
Tower. This procedure is written with the assumption that the Regeneration Section
hydrogen system and the Regeneration Section air system are isolated and depressured.

a. Air-free the Regeneration Section in accordance with Step 1 of the Final


Startup Preparation.

b. With the Regeneration Tower and spent catalyst under slight nitrogen pressure,
commission the Lift Gas Blower and Lift Gas Blower Cooler.

c. Establish the total lift gas rate such that the actual gas velocity is 8-10 m/s (25-
30 ft/s). Direct all lift gas to the primary gas inlet to the Spent Catalyst L-Valve
Assembly.

d. Commission the Fines Removal Blower and establish an elutriation gas rate
such that the actual gas velocity in the elutriation tube is 4.5 m/s (15 ft/s).

e. Place the Emergency Stop Switch to the RUN position.

f. Commission all instrumentation around the Catalyst Addition Lock Hopper No.
1 if not already done.

g. Load a drum of Platforming catalyst into the Catalyst Addition Funnel No. 1.

h. Commission the Catalyst Addition Lock Hopper No. 1 operation as described in


the Normal Operations section of this manual. Cycle the Lock Hopper.

i. Increase the secondary lift gas to the rate which corresponds roughly to that
required to maintain design catalyst circulation. Measure the time required to
lift the drum of catalyst as indicated by the lift pipe pressure differential.

j. Calculate the catalyst flux in the lift pipe, that is, kg/cm2/sec (lb/in2/hr).
Compare this value to 38 kg/cm2/sec (550 lb/in2/hr).

k. Continue loading catalyst into the addition funnel and cycling the Lock Hopper.
Adjust the secondary lift gas rate until the catalyst lift pipe flux approaches the
target of 38 kg/cm2/sec (550 lb/in2/hr).

l. Continue loading catalyst drums into the Regeneration Tower and Disengaging
Hopper until a level is observed in the Disengaging Hopper.

m. Stop the Fines Removal Blower and Lift Gas Blower.

n. Proceed with Final Startup Preparations at Step 2.

5.3.5Catalyst changeout on the fly

The following procedure, nicknamed “changeout on the fly,” allows for a total catalyst
replacement while maintaining Platforming Unit operations. This procedure is
particularly useful when a refiner finds the need to replace old CCR Platforming
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 149 OF

catalyst with a new load between scheduled unit turnarounds. The basic principle of
the changeout procedure is that while the Platforming Unit and CCR Section continues
normal operation old catalyst is continuously withdrawn and replaced with fresh
catalyst. The old catalyst is removed below the Regeneration Tower where the coke
can be combusted before unloading. The fresh catalyst is added just below the
withdrawal point, at the Nitrogen Seal Drum, via the Catalyst Addition Lock Hopper
No. 2. At the Nitrogen Seal Drum a special valve and piping arrangement is used to
allow for the catalyst replacement while maintaining normal gas communication
between the Regeneration Tower and the Nitrogen Seal Drum. This arrangement is
given in Figure 5.3-2.

The following procedure outlines a general procedure for carrying out this operation.
This outline is written with the assumption that the Regeneration Section has been
operating under normal conditions.

a. Install and commission necessary changeout on the fly equipment and piping
around the Nitrogen Seal Drum. This includes the Catalyst Addition Funnel No.
2, Catalyst Addition Lock Hopper No. 2 and associated piping, catalyst
withdrawal line, gas communication line at the Nitrogen Seal Drum, and the
level indicator on the Nitrogen Seal Drum.

b. Reduce the catalyst circulation to a maximum of 1500 pph, or to the maximum


rate that catalyst drums can be supplied to the Catalyst Additional Funnel No.
2. The Platforming Unit severity may need to be reduced such that the coke
production is consistent with the new catalyst circulation rate. To prevent a loss
of performance in the Platforming Unit the catalyst coke level should be kept
below 7%.

c. Switch operation of the Regeneration Tower from White Burn mode to Black
Burn mode.

d. Stop the Air Heater firing, while maintaining the Regeneration Gas Heater
firing, to maximize catalyst cooling as it leaves the tower.

e. In order to minimize nuisance shutdowns, increase the setpoints for the pressure
differential controllers to the meter maximum. This will reduce the chance of
low pressure differential causing a shutdown and will aid in purging air from
the fresh catalyst loaded into the unit.

f. Load a drum of fresh Platforming catalyst into the addition funnel and
commence the Catalyst Addition Lock Hopper sequencing.

g. At the same time as step (f), open the manual valve below XV-20, open the gas
communication valve above the Nitrogen Seal Drum, and close the manual
block valve in the catalyst inlet line just above the Nitrogen Seal Drum.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 150 OF

h. Continue loading fresh catalyst into the Nitrogen Seal Drum via the Catalyst
Addition Funnel and Catalyst Addition Lock Hopper No. 2. The logic for this
system’s operation is given in the Normal Operations Section of this manual.

i. Once catalyst addition is progressing smoothly, begin catalyst removal via the
catalyst withdrawal line. Open fully the block valve at the top of the withdrawal
line. Open the valve at the bottom of the withdrawal line to set a catalyst
withdrawal rate consistent with the catalyst addition rate.

j. The old catalyst should be loaded directly into catalyst drums at grade. The
unloaded catalyst should be free of coke, as the Regeneration Tower is still in a
modified Black Burn mode, and cooled to such a point as to permit easy
handling.

k. Continue the catalyst addition and withdrawal until the entire catalyst inventory
has been replaced.

l. Once catalyst addition is completed, close the block valve at the top of the
catalyst withdrawal line and allow the line to drain.

m. Close the block valve in the catalyst addition line just below XV-20.

n. Open the manual block valve in the catalyst inlet line just above the Nitrogen
Seal Drum. Close the gas communication valve above the Nitrogen Seal Drum.

o. Disconnect and blankoff changeout on the fly equipment and piping.

p. Restore normal pressure differential setpoints on the pressure differential


controllers around the Nitrogen Seal Drum.

q. Resume desired catalyst circulation rate and Platforming Unit severity.

5.3.6Special maintenance precautions for the stainless steel regeneration tower

The Regeneration Tower and associated piping are constructed out of 300 series
stainless steel. The use of this material is compatible with all process conditions found
in the vessel during normal operations and normal startup and shutdown. There is one
concern with stainless steel in this service that warrants special consideration, that is
stress corrosion cracking. Stress corrosion cracking is a intergranular attack of the
metal that can lead to vessel failure without having the typical outward signs of
corrosion, i.e., metal loss at the affected site. The conditions required for this type of
corrosion are as follows:

- The presence of water in the liquid state.


- The presence of HCI in the liquid water.
- The liquid water must be at a temperature above 60°C (140°F).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 151 OF

During the normal operation (including startup and shutdown) of the unit the above
conditions can not be present for a number of reasons. As a general statement the
operating procedures precludes the presence of at least one of the above mentioned
conditions at all times. Some pertinent examples are as follows:

- Normal operating temperatures in the tower are high enough to preclude the
presence of liquid water in flowing lines.

- All low flow or dead legs are heat traced to prevent the presence of liquid water.

- Instrument taps are purged with dry nitrogen to preclude the presence of water
and chloride.

- During any significant upset condition in the unit the Regeneration Tower will
undergo a “Hot Shutdown” where regeneration of the catalyst ceases, but the
tower remains at operating temperatures and gas flows remain in commission. A
consequence of a Hot Shutdown is that the air is removed from the tower to
stop combustion, thus removing the source of water from the system. When the
air is removed it is replaced with a dry nitrogen flow to purge out the tower of
any oxygen and moisture remaining. When the nitrogen is introduced to the
tower chloride addition is automatically stopped to preclude the presence of
HCI.

- During any cooldown of the tower, i.e., low Regeneration Gas or Drying Zone
gas temperature, the chloride injection to the tower is stopped to preclude the
presence of HCI in the tower.

- Any cooling down of the tower will also cool down the catalyst, and the natural
properties of the catalyst are such that as it cools down it has a greater affinity
and holding capacity for both chloride and water. Thus the catalyst acts as a
desiccant to remove any free chloride and water left in the tower.

- During any heatup of the tower, chloride injection is prohibited by the logic
system until the Regeneration Gas and Drying Zone Gas temperatures are near
their design values. This precludes the presence of HCI in the tower before all
liquid water is evaporated by the hot process gas.

- The design of the Regeneration Tower is such that all catalyst free areas are
free draining to catalyst full areas, actually the entire tower is free draining to
the bottom of the tower. The catalyst will be able to absorb any free water in the
system thus precluding its presence in the tower.

- While the tower is shutdown, either hot or cold, catalyst full or unloaded,
procedures call for the tower to be kept under slight pressure with a nitrogen
purge.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 152 OF

Given the above there are still two conditions which are out of the scope of the
operating procedures, that is any time the Regeneration Tower is open to the
atmosphere for screen cleaning or other maintenance, and when the Regeneration
Blower fails for an extended period. During these situations it is important for the unit
operating staff to be conscious of the conditions that lead to stress corrosion cracking.
In order to facilitate this effort find the following suggestions:

Regeneration Tower open.

- Keep any opening to the Regeneration Tower or associated piping


covered to preclude the presence of any liquid water, i.e., rain or cooling
tower mist.

The free draining design of the tower should keep the accumulation of
water to a minimum, but the metal may still become wetted,

- Keep an instrument air purge on the Regeneration Tower to preclude the


presence moist air in the tower.

- If for some reason the Regeneration Tower has been exposed to liquid
water conduct a tower dryout similar to that outlined in the
Commissioning Section of this manual.

Blower failure.

- Depressure the Regeneration Tower via the normal tower vent line to
near atmospheric pressure to affect a purge of the piping while it is still
hot enough to prevent condensation.

- Close the tower vent valve to re-pressure the tower with nitrogen and
depressure again after reaching design pressure.

- Repeat the pressuring and depressuring two more times to reduce the
moisture and chloride concentration in the tower atmosphere to below
that required for condensation.

CAUTION:

The regeneration tower gas include HCl. Therefore, the regeneration tower system
shall be maintain at dry condition. At the wet condition, the stainless steel happen
corrosion. In the shutdown operation, the system purge shall be use nitrogen gas for
prevent the system corrosion.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 153 OF

FIGURE 5.3-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 154 OF

FIGURE 5.3-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 155 OF

CAUTION NOTES FOR THE CYCLEMAX CCR UNIT

CAUTION:

All equipment containing hydrogen shall be evacuated and purged with nitrogen before
opening and admitting air and after closing before admitting hydrogen.

CAUTION:

Care must be exercised when venting and draining equipment to prevent personnel exposure
to toxic aromatics.

CAUTION:

All upstream piping and equipment must be purged with inert gas before isolating the relief
gas header from the line to the knockout drum and flare.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 156 OF

6NORMAL START-UP & SHUTDOWN PROCEDURES

There are two procedures used to startup the Regeneration section. The Black Catalyst
Startup Procedure MUST be used for the initial startup of the Regeneration Section.
For subsequent startups, the Black Catalyst Startup Procedure must also be used if
there is ANY possibility that carbonized catalyst is present in the Regeneration Tower
below the Burn Zone. Otherwise, the White Catalyst Startup Procedure may be used.

6.1Black Catalyst Startup Procedure

(1) Establish the following flows and conditions:

a. Nitrogen purge to the Regeneration Tower Cooling Zone: Minimum flow


required to maintain flow control.

b. Nitrogen purge to the Regeneration Tower Drying Zone: design flow of


nitrogen for startup. (NOTE: This rate is lower than the design flow rate
of drying air for normal operations.) This flow corresponds to the design
rate of Chlorination Zone flow for normal operations.

c. Excess air vent: no flow. Close excess air vent hand-control valve in
manual.

d. Chlorination Zone flow: equal to Nitrogen purge to the Regeneration


Tower Drying Zone and Cooling Zone.

e. Spent Catalyst nitrogen “Bubble”: design differential pressures.

f. Regenerated Catalyst nitrogen “Bubble”: design differential pressures.

g. Spent Catalyst Isolation System: open.

h. Regenerated Catalyst Isolation System: open.

i. Nitrogen purge to Regeneration Blower seal: design differential pressure.

j. Nitrogen purges to Regeneration Gas and Reheat Gas flowmeters: design


flow rates.

k. Cooling water flow to the Regeneration Blower water pad.

l. Normal Disengaging Hopper catalyst level.

m. Total lift gas to Spent Catalyst L-Valve Assembly: design flow.

n. Total lift gas to Regenerated Catalyst L-Valve Assembly: design flow.

o. Regeneration Tower Pressure: design pressure.

p. Reduction Gas Heater booster gas: design flows.

q. Purge Gas to Catalyst Collector: design flow.

r. Air Drier activated in accordance with the manufacturer’s procedures.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 157 OF

(2) Start the Regeneration Blower and the Regeneration Cooler Blower. If
Regeneration Blower has a two speed electric driver, start on Low speed.

(3) Calibrate and set up the analyzers for normal operation:

Nitrogen header hydrogen/hydrocarbon analyzer


Burn Zone gas oxygen analyzer

NOTE: The oxygen concentration in the Regeneration Tower should be nil


before commissioning the electric heaters. The analyzer must be at the design
pressure when calibrating or the analyzer will not read correctly at normal
operating conditions.

(4) Ensure that all shutdown bypass switches are in the NORMAL position.

(5) Start the four electric heaters and heat up the Regeneration Tower and the
Reduction Zone:

a. Set the temperature controller for each zone inlet - Burn Zone inlet,
Drying Zone inlet, and Reduction Zone inlets - in manual at zero output to
its heater.

NOTE: The inlet temperature controller for Burn Zone is split-ranged to


the Regeneration Heater (50-100%) and the Regeneration Cooler (50-0%).
Set its output at 50% for zero output to the Regeneration Heater.

b. Depress the four electric heater pushbuttons to start the heaters.

c. Raise the zone inlet temperatures at 55°C per hour (100°F per hour) to
design temperatures:

Burn Zone inlet 477°C (890°F)


Drying Zone inlet 565°C (1,050°F)
Upper Reduction Zone inlet 377°C (710°F)
Lower Reduction Zone inlet 550°C (1,020°F)

(6) Determine the maximum permissible catalyst circulation rate from the General
Operating Curve (Figure 6.1-1). Use the coke content determined from the
actual laboratory carbon analysis and an oxygen concentration within the
recommended range of Burn Zone inlet oxygen concentrations (0.5-1.0 mole
percent). Refer to the CCR Process Variables Section.

(7) Stop catalyst circulation (if is not stopped already) by setting the catalyst flow
pushbutton to stop.

(8) Start upper combustion air and begin an in-situ burn of the coked catalyst in the
Burn Zone. (Refer to Figure 6.1-2.)

a. Confirm that the Tie Line Valve (XV-14 on Figure 6.1-2) is CLOSED.

b. Confirm that the control valve for the upper combustion air is closed.
Open the manual valve in this line at the injection point.

c. Record the Burn Zone temperature profile.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 158 OF

d. Open the Air Valve (XV-13) by depressing the Air On Pushbutton. Inject
upper combustion air through the startup line into the Burn Zone loop as
required to establish the oxygen concentration that was selected in Step 7
above.

e. Stabilize the oxygen concentration and the upper combustion air flow.
Then, cascade the upper combustion air flow controller to the oxygen
analyzer controller.

f. Maintain the desired oxygen concentration while the in-situ burn


continues. The amount of coke in the Burn Zone will gradually decrease.
Eventually, some of the oxygen entering the catalyst bed will begin
breaking through the bed and will be recycled to the Regeneration Blower
and back to the Burn Zone inlet. This will significantly decrease the upper
combustion air required to maintain the desired inlet oxygen
concentration.

(9) Start catalyst circulation when the upper combustion air rate decreases to about
one-half of its original rate (in Step 8e):

a. Set the Catalyst Flow Setpoint at or below the maximum permissible


catalyst circulation rate from the General Operating Curve (Figure 6.1-l).

b. Depress the Catalyst Flow On Pushbutton to start catalyst circulation.

(10) Maintain the coke burn at the following conditions:

Burn Zone inlet 477 °C (890 °F)


Burn Zone outlet (max) 565 °C (1,050 °F)
Burn Zone delta T (max) 88 °C (160 °F)
Burn Zone bed (max) 593 °C (1,100 °F)
Burn Zone inlet oxygen Per Gen. Op. Curve:
(1.0 mole-% maximum)

Drying Zone inlet 565 °C (1,050 °F)


Drying Zone inlet 2.5 kg/cm2g (35 psig)
Nitrogen to Drying Zone Design for startup

Nitrogen to Cooling Zone To maintain150 °C (300 °F)


in Nitrogen Seal Drum

Upper Reduction Zone inlet 377 °C (710°F)


Lower Reduction Zone inlet 550 °C (1,020°F)

Catalyst circulation rate Per Gen. Op. Curve:


(not greater than design)

Reduction Gas Exchanger


Shell Side Outlet 65 °C (150 °F)
Booster Gas to Lock Hopper 150 °C (300 °F)

(11) Sample the regenerated catalyst:

After one turnover of the catalyst in the Regeneration Tower has been
completed, begin sampling the regenerated catalyst every two hours below the
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 159 OF

Nitrogen seal drum for carbon analysis. Consecutive samples should show the
catalyst to meet all of the following criteria:

a The coke content should be 0.2 wt-% or less.

b The catalyst pills should have coke-free centers. (Break open several
pills.)

c There should be essentially no whole black spheres.

When two consecutive samples of regenerated catalyst meet the above three
criteria, establish dual air injection.

(12) Start air injection to the Drying Zone and Cooling Zone and establish dual air
injection as follows:

a. During this step, monitor the Regeneration Blower suction temperature,


the Burn Zone, Reheat Zone and Chlorination Zone bed temperatures, and
the Cooling Zone outlet temperature while establishing dual air operation.
If any significant temperature increase occurs, start nitrogen flow and stop
air flow to the Air Heater IMMEDIATELY.

b. Ensure that the nitrogen flow to the Drying Zone is at the design rate for
startup. Ensure that the excess air vent control valve is closed in manual.

c. Confirm that the current flow of upper combustion air is sufficient to


permit continued cascade control of the upper air when lower air flow to
the Drying Zone is started. Confirm that the current flow of upper
combustion air is also sufficient to maintain the apparent flow of
chlorination gas at the current rate when lower air to the Drying Zone is
started.

NOTE: After the lower air flow to the Drying Zone is started, the upper
air flow to the Burn Zone will have to be reduced to compensate for the
effect of the lower air on the Regeneration Tower’s oxygen balance. The
upper air flow rate will have to be reduced by an amount that is roughly
equal to the lower air flow rate. Therefore, the upper air flow rate must be
sufficient so that, after it is reduced, the remaining upper air flow still
permits control of the Burn Zone oxygen content by the upper air control
valve.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 160 OF

EXAMPLE

If the current Regeneration Section operation is:

Upper Air Flow Rate 400 Nm3Hr (15,000 SCFH)


Lower Nitrogen Flow Rate 267 Nm3Hr (10,000 SCFH)

then, after lower air is started, the operating conditions will roughly be:

Upper Air Flow Rate 133 Nm3/Hr (5,000 SCFH)


Lower Air Flow Rate 267 Nm3/Hr (10,000 SCFH)

So, prior to starting lower air, ensure that 133 Nm3/Hr (5,000 SCFH) is
sufficient for the upper air control valve to control the Burn Zone oxygen
content. Generally, the upper air flow is sufficient for control if it is >20%
of the lower air flow.

d. Place the upper combustion air in local-automatic control.

e. Depress the Tie Line Pushbutton to open the Tie Line Valve (XV-14).

f. As soon as the Tie Line Valve is opened, depress the Nitrogen Pushbutton
to close the Nitrogen Valve (XV-15).

g. Twenty to thirty seconds after the Nitrogen Valve is closed, reduce the
upper air flow to compensate for the effect of the lower air on the Tower’s
oxygen balance. In the example above, the upper air flow would be
reduced from 400 Nm3/hr to about 133 Nm3/hr, while carefully watching
the oxygen analyzer.

h. Stabilize the oxygen concentration and the upper combustion air flow.
Then cascade the upper combustion air flow controller back to the oxygen
analyzer controller.

(13) Establish excess drying air flow and stop upper combustion air flow:

a. As soon as the oxygen concentration has stabilized, increase the lower air
injection in local-automatic to the design air rate for regeneration. At the
same time, increase the flow of air through the excess air vent a
corresponding amount by opening the hand-control valve in local-manual.
Maintain the apparent chlorination gas flow at the current rate.

b. Confirm that the current excess air vent flow is sufficient to permit control
of the burn zone oxygen concentration when upper combustion air is
stopped.

NOTE: Before the upper air flow to the Burn Zone is stopped, the excess
air vent from the Drying Zone will have to be reduced to compensate for
the effect of the upper air on the Regeneration Tower’s oxygen balance.
The excess air vent rate will have to be reduced by an amount that is
roughly equal to the upper air flow rate. Therefore, the excess air vent rate
must be sufficient so that, after it is reduced, the remaining excess air vent
rate will permit control by the excess air control valve of the Burn Zone
oxygen content.

EXAMPLE
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 161 OF

If the current Regeneration Section operation is:

Upper Air Flow Rate 133 Nm3/Hr (5,000 SCFH)


Excess Air Vent Rate 267 Nm3/Hr (10,000 SCFH)
Lower Air Flow Rate 534 Nm3/Hr (20,000 SCFH)

then, after upper air is stopped, the operating conditions will roughly be:

Upper Air Flow Rate 0 Nm3/Hr (0 SCFH)


Excess Air Vent Rate 133 Nm3/Hr (5,000 SCFH)
Lower Air Flow Rate 534 Nm3/Hr (20,000 SCFH)

So, prior to stopping upper air, ensure that 133 Nm3/Hr (5,000 SCFH) is
sufficient for the excess air control valve to control the Burn Zone oxygen
content.

c. Place the upper combustion air in local-automatic control.

d. Reduce the excess air vent flow by the amount of upper combustion air
flow.

e. Twenty to thirty seconds after the excess air vent flow has been reduced,
close the upper combustion air control valve to anticipate and compensate
for the effect of the lower air on the Tower’s oxygen balance.

f. Stabilize the oxygen concentration and the excess air vent flow. Switch the
oxygen analyzer-controller to control the excess air vent control valve.

g. Block in the upper combustion air line at the Burn Zone.

(14) Establish the desired injection rate of organic chloride to the Chlorination Zone
by setting the Chloride pushbutton to “ON” and adjusting the pump stroke of
the injection pump.

(15) Sample the regenerated catalyst:

a. After the catalyst inventory in the Chlorination Zone, Drying Zone, and
Cooling Zone of the Regeneration Tower has been turned over at lined-out
conditions, sample the regenerated catalyst for chloride below the
Nitrogen seal drum.

b. Adjust the chloride injection rate to provide the target chloride level on the
regenerated catalyst.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 162 OF

(16) Continue to monitor the coke burn. The operating conditions are as follows:

Burn Zone inlet 477 °C (890°F)


Burn Zone outlet (max) 565 °C (1,050°F)
Burn Zone delta T (max) 88 °C (160°F)
Burn Zone bed (max) 593 °C (1,100°F)
Burn Zone inlet oxygen Per Gen. Op. Curve:
(1.0 mole-% maximum)

Drying Zone inlet 565 °C (1,050°F)


Drying Zone inlet 2.5 kg/cm2g (35 psig)
Air to Drying Zone Design for regeneration
Air to Cooling Zone To maintain 150°C (300°F)
in Nitrogen Seal Drum

Upper Reduction Zone inlet 377 °C (710°F)


Lower Reduction Zone inlet 550 °C (1,020°F)

Catalyst circulation rate Per Gen. Op. Curve:


(Design CCR maximum)

Reduction Gas Exchanger


Shell Side Outlet 65 °C (150°F)
Booster Gas to Lock Hopper 150 °C (300°F)

(17) Maintain normal Regeneration Section operations.

(18) Stop injection of water into the feed (if being injected) to the CCR Platforming
Unit after one turnover of the catalyst in the Regeneration Tower, Lock Hopper,
and Reduction Zone has been completed following Step (7) This would be
approximately 10 hours at 100% of design catalyst circulation rate.

(19) Stop injection of chloride compound into the feed to the CCR Platforming Unit
after one turnover of the catalyst in the Regeneration Tower, Lock Hopper, and
Reduction Zone has been completed following Step (13) This would be
approximately 10 hours at 100% of design catalyst circulation rate.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 163 OF

6.2White Catalyst Startup Procedure

The White Catalyst Startup Procedure are used for subsequent startups of the
Regeneration Section, but only under certain conditions. Namely, IF the Regeneration
Section was shut down in accordance with the Hot Shutdown or Cold Shutdown
procedure AND no catalyst was transferred from the Regeneration Tower during or
after these shutdowns, then carbonized catalyst in the Regeneration Tower will be
present only in the Burn Zone. Then the White Catalyst Startup Procedure may be used.

(1) Establish the following flows and conditions:

a. Nitrogen purge to the Regeneration Tower Cooling Zone: Minimum flow


required to maintain flow control.

b. Nitrogen purge to the Regeneration Tower Drying Zone: design flow of


nitrogen for startup. (NOTE: This rate is lower than the design flow rate
of drying air for normal operations.) This flow corresponds to the design
rate of Chlorination Zone flow for normal operations.

c. Excess air vent: no flow. Close excess air vent hand-control valve in
manual.

d. Chlorination Zone flow: equal to Nitrogen purge to the Regeneration


Tower Drying Zone and Cooling Zone.

e. Spent Catalyst nitrogen “Bubble”: design differential pressures.

f. Regenerated Catalyst nitrogen “Bubble”: design differential pressures.

g. Spent Catalyst Isolation System: open.

h. Regenerated Catalyst Isolation System: open.

i. Nitrogen purge to Regeneration Blower seal: design differential pressure.

j. Nitrogen purges to Regeneration Gas and Reheat Gas flowmeters: design


flow rates.

k. Cooling water flow to the Regeneration Blower water pad (if applicable).

l. Normal Disengaging Hopper catalyst level.

m. Total lift gas to Spent Catalyst L-Valve Assembly: design flow.

n. Total lift gas to Regenerated Catalyst L-Valve Assembly: design flow.

o. Regeneration Tower Pressure: design pressure.

p. Reduction Gas Heater booster gas: design flows.

q. Purge Gas to Catalyst Collector: design flow.

r. Air Drier activated in accordance with the manufacturer’s procedures.

(2) Start the Regeneration Blower and the Regeneration Cooler Blower. If
Regeneration Blower has a two speed electric driver, start on Low speed.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 164 OF

(3) Calibrate and set up the analyzers for normal operation:

Nitrogen header hydrogen/hydrocarbon analyzer


Burn Zone gas oxygen analyzer

NOTE: The oxygen concentration in the Regeneration Tower should be nil


before commissioning the electric heaters. The analyzer must be at the design
pressure when calibrating or the analyzer will not read correctly at normal
operating conditions.

(4) Ensure that all shutdown bypass switches are in the NORMAL position.

(5) Start the four electric heaters and heat up the Regeneration Tower and the
Reduction Zone:

a. Set the temperature controller for each zone inlet – Burn Zone inlet,
Drying Zone inlet, and Reduction Zone inlets – in manual at zero output
to its heater.

NOTE: The inlet temperature controller for the Burn Zone is split-ranged
to the Regeneration Heater (50-100%) and the Regeneration Cooler (50-
0%). Set its output at 50% for zero output to the Regeneration Heater.

b. Depress the four electric heater pushbuttons to start the heaters.

c. Raise the zone inlet temperatures at 55°C per hour (100°F per hour) to
design temperatures:

Burn Zone inlet 477 °C (890°F)


Drying Zone inlet 565 °C (1,050°F)
Upper Reduction Zone inlet 377 °C (710°F)
Lower Reduction Zone inlet 550 °C (1,020°F)

(6) Determine the maximum permissible catalyst circulation rate from the General
Operating Curve, Figure 6.1-1. Use the coke content determined from the actual
laboratory carbon analysis and an oxygen concentration within the
recommended range of Burn Zone inlet oxygen concentrations (0.5-1.0 mole
percent). Refer to the CCR Process Variables Section.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 165 OF

(7) Start upper combustion air. (Refer to Figure 6.1-2):

a. Confirm that the Tie Line Valve (XV-14) is CLOSED.

b. Confirm that the control valve for the upper combustion air is closed.
Open the manual valve in this line at the injection point.

c. Record the Burn Zone bed temperature profile.

d. Open the Air Valve (XV-13) by depressing the Air On Pushbutton. Inject
upper combustion air through the startup line into the Burm Zone loop as
required to establish the oxygen concentration that was selected in Step 7,
above.

e. Stabilize the oxygen concentration and the upper combustion air flow.
Then, cascade the upper combustion air flow controller combustion to the
oxygen analyzer-controller.

(8) Start catalyst circulation:

a. Set the Catalyst Flow Setpoint at or below the maximum permissible


catalyst circulation rate from the General Operating Curve.

b. Depress the Catalyst Flow On Pushbutton to start catalyst circulation.

(9) Start air injection to the Drying Zone and Cooling Zone and establish dual air
injection as follows:

a. During this step, monitor the Regeneration Blower suction temperature,


the Burn Zone, Reheat Zone and Chlorination Zone bed temperatures, and
the Cooling Zone outlet temperature while establishing dual air operation.
If any significant temperature increase occurs, start nitrogen flow and stop
air flow to the Air Heater IMMEDIATELY.

b. Ensure that the nitrogen flow to the Drying Zone is at the design rate for
startup. Ensure that the excess air vent control valve is closed in manual.

c. Confirm that the current flow of upper combustion air is sufficient to


permit continued cascade control of the upper air when lower air flow to
the Drying Zone is started. Confirm that the current flow of upper
combustion air is also sufficient to maintain the apparent flow of
chlorination gas at the current rate when lower air to the Drying Zone is
started.

NOTE: After the lower air flow to the Drying Zone is started, the upper
air flow to the Burn Zone will have to be reduced to compensate for the
effect of the lower air on the Regeneration Tower’s oxygen balance. The
upper air flow rate will have to be reduced by an amount that is roughly
equal to the lower air flow rate. Therefore, the upper air flow rate must be
sufficient so that, after it is reduced, the remaining upper air flow still
permits control of the Burn Zone oxygen content by the upper air control
valve.

EXAMPLE

If the current Regeneration Section operation is:


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 166 OF

Upper Air Flow Rate 400 Nm3/Hr (15,000 SCFH)


Lower Nitrogen Flow Rate 267 Nm3/Hr (10,000 SCFH)

then, after lower air is started, the operating conditions will roughly be:

Upper Air Flow Rate 133 Nm3/Hr (5,000 SCFH)


Lower Nitrogen Flow Rate 267 Nm3/Hr (10,000 SCFH)

So, prior to starting lower air, ensure that 133 Nm3/Hr (5,000 SCFH) is
sufficient for the upper air control valve to control the Burn Zone oxygen
content. Generally, the upper air flow is sufficient for control if it is >20%
of the lower air flow.

d. Place the upper combustion air in local-automatic control.

e. Depress the Tie Line Pushbutton to open the Tie Line Valve (XV-14).

f. As soon as the Tie Line Valve is opened, depress the Nitrogen Pushbutton
to close the Nitrogen Valve (XV-15).

g. Twenty to thirty seconds after the Nitrogen Valve is closed, reduce the
upper air flow to compensate for the effect of the lower air on the Tower’s
oxygen balance, In the example above, the upper air flow would be
reduced from 400 Nm3/Hr to above 133 Nm3/Hr, while carefully watching
the oxygen analyzer.

h. Stabilize the oxygen concentration and the upper combustion air flow.
Then cascade the upper combustion air flow controller back to the oxygen
analyzer-controller.

(10) Establish excess drying air flow and stop upper combustion air flow:

a. As soon as the oxygen concentration has stabilized, increase the lower air
injection in local-automatic to the design rate for regeneration. At the same
time, increase the flow of air through the excess air vent a corresponding
amount by opening the hand-control valve in local-manual. Maintain the
apparent chlorination gas flow at the current rate.

b. Confirm that the current excess air vent flow is sufficient to permit control
of the burn zone oxygen concentration when upper combustion air is
stopped.

NOTE: Before the upper air flow to the Burn Zone is stopped, the excess
air vent from the Drying Zone will have to be reduced to compensate for
the effect of the upper air on the Regeneration Tower’s oxygen balance.
The excess air vent rate will have to be reduced by an amount that is
roughly equal to the upper air flow rate. Therefore, the excess air vent rate
must be sufficient so that, after it is reduced, the remaining excess air vent
rate will permit control by the excess air control valve of the Burn Zone
oxygen content.

EXAMPLE

If the current Regeneration Section operation is:

Upper Air Flow Rate 133 Nm3/Hr (5,000 SCFH)


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 167 OF

Excess Air Vent Rate 267 Nm3/Hr (10,000 SCFH)


Lower Air Flow Rate 534 Nm3/Hr (20,000 SCFH)

then, after upper air is stopped, the operating conditions will roughly be:

Upper Air Flow Rate 0 Nm3/Hr (0 SCFH)


Excess Air Vent Rate 133 Nm3/Hr (5,000 SCFH)
Lower Air Flow Rate 534 Nm3/Hr (20,000 SCFH)

So, prior to stopping upper air, ensure that 133 Nm3/Hr (5,000 SCFH) is
sufficient for the excess air control valve to control the Burn Zone oxygen
content.

c. Place the upper combustion air in local-automatic control.

d. Reduce the excess air vent flow by the amount of upper combustion air
flow.

e. Twenty to thirty seconds after the excess air vent flow has been reduced,
close the upper combustion air control valve to anticipate and compensate
for the effect of the lower air on the Tower’s oxygen balance.

f. Stabilize the oxygen concentration and the excess air vent flow.
Switch the oxygen analyzer-controller to control the excess air vent
control valve.

g. Block in the upper combustion air line at the Burn Zone.

(11) Establish the desired injection rate of organic chloride to the Chlorination Zone
by setting the Chloride pushbutton to “ON” and adjusting the pump stroke of
the injection pump.

(12) Sample the regenerated catalyst:

a. After the catalyst inventory in the Chlorination Zone, Drying Zone, and
Cooling Zone of the Regeneration Tower has been turned over at lined-out
conditions, sample the regenerated catalyst for chloride below the
Nitrogen seal drum.

b. Adjust the chloride injection rate to provide the target chloride level on the
regenerated catalyst.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 168 OF

(13) Continue to monitor the coke burn. The operating conditions are as follows:

Burn Zone inlet 477 °C (890°F)


Burn Zone outlet (max) 565 °C (1050°F)
Burn Zone delta T (max) 88 °C (160°F)
Burn Zone bed (max) 593 °C (1100°F)
Burn Zone inlet oxygen Per Gen. Op. Curve:
(1.0 mole-% maximum)

Drying Zone inlet 565 °C (1050°F)


Drying Zone inlet 2.5 kg/cm2g (35 psig)

Air to Drying Zone Design for regeneration


Air to Cooling Zone To maintain 150° (300°F)
in Nitrogen Seal Drum

Upper Reduction Zone inlet 377 °C (710°F)


Lower Reduction Zone inlet 550 °C (1020°F)

Catalyst circulation rate Per Gen. Op. Curve:


(Design CCR maximum)

Reduction Gas Exchanger


Shell Side Outlet 65 °C (150°F)
Booster Gas to Lock Hopper 150 °C (300°F)

(14) Maintain normal Regeneration Section operations.

(15) Stop injection of chloride compound and water into the feed to the CCR
Platforming Unit after one turnover of the catalyst in the Regeneration Tower,
Lock Hopper, and Reactor Surge Zone has been completed following Step (11)
This would be approximately 10 hours at 100% of design catalyst circulation
rate.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 169 OF

FIGURE 6.1-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 170 OF

FIGURE 6.1-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 171 OF

6.3Normal Operations

This section outlines normal operating procedures that are done on a day-to-day basis
when the Regeneration Section is in operation. This section includes: Preventive
Maintenance Schedule, Dust Collector Cleaning, Catalyst Addition, Filter Cleaning,
and Vent Gas Rerouting.

6.3.1Preventive maintenance schedule

This is a suggested schedule for preventative maintenance during normal operation. It


is a general schedule that is intended to help the refinery prepare a specific schedule
for a particular unit.

Each Shift

(1) Check the position of the shutdown bypass switches. (All bypass switches
should be in the NORMAL position, not the BYPASS position.)

(2) Check that the operation of the Regeneration Tower is in accordance with the
General Operating Curve.

(3) Check for burned out indicators on the control panel and replace as necessary.

(4) Check oil levels in Regeneration Blower and Regeneration Cooler Blower.

(5) Check for proper cooling water flow and nitrogen purge flow to the seals of the
Regeneration Blower.

Daily

(1) Visually check that the sample flow rate and pressure are correct for all
analyzers.

(2) Clean the Dust Collector by depressing the reverse jet pushbutton.

(3) Check the nitrogen purges to the regeneration gas and reheat gas flow meters.

Weekly

(1) Check the “zero” and “span” of all analyzers with bottled gas.

NOTE: Do not forget to use the shutdown bypass switches as needed when
calibrating the CCR Nitrogen Header Analyzer and the Burn Zone Oxygen
Analyzer. Do not forget to turn the bypass switches back to the NORMAL
position after the analyzer calibration. (Refer to the Process Flow and Control
Section.)

(2) Check the air dryer outlet moisture content.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 172 OF

(3) Unload the Dust Collector and record the weekly fines collected. Visually
inspect for % whole spheres in the fines (20% to 30% whole spheres is the
normal range). Send fines sample to lab for size distribution test. Note: Units
with a design CCR of 4,500 lbs/hr (2,040 kg/hr) or higher may need to unload
the Dust Collector two times per week.

(4) Check the pressure drop across the off gas filters. Replace or clean the filter
elements as needed.

(5) Check the bundle element temperatures of the electric heaters. (Maintain a
record.)

Monthly

(1) Check the “zero” on all flow, pressure, and differential pressure transmitters.

NOTE: Do not forget to use the shutdown bypass switches as needed when
calibrating the Burn Zone Gas and Drying Zone Air flow transmitters. Do not
forget to turn the bypass switches back to the NORMAL position after the
transmitter calibration. (Refer to the Process Flow and Control Section.)

(2) Stop catalyst circulation and check the “zero” and “span” settings on all the
radiation level detectors (amplifier cards).

(3) Check the V-ball valve packing integrity and add lubrication as necessary.

Quarterly

(1) Check the “zero” and “span” of all flow, pressure, and differential pressure
transmitters.

(2) Check sample line filters to CCR Nitrogen Header H2/HC analyzer.

(3) Calibrate the regeneration gas and reheat gas flow meters.

(4) Check Regeneration Blower and Regeneration Cooler Blower for vibration and
for bearing temperature.

(5) Check trip settings of automatic shutdowns. (Maintain a record.)

(6) Perform a Catalyst Fines Survey.

Semi-annually

(1) Replace filters in the organic chloride injection line.

(2) Replace the air dryer after-filter and pilot air filters.

(3) Check the regeneration gas flow rate. Clean the Regeneration Tower screens
when the regeneration gas flow rate drops 10% below the rate when the
Regeneration Tower screens were clean.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 173 OF

Annually

(1) Replace the air dryer pre-filter and desiccant.

(2) Replace the filter elements in the booster gas coalescer.

6.3.2Dust collector cleaning

6.3.2.1Reverse jet cleaning

The operator cleans the filter elements in the Dust Collector using the reverse jet
pushbutton. An alarm sounds when the pressure drop across the Dust Collector is high
– about 125 mm H2O (5 in H2O) – and cleaning is required. The operator may then
depress the pushbutton while the Dust Collector is in normal operation.

When the operator depresses the pushbutton, a cleaning sequence occurs


automatically. The sequence blows nitrogen backwards through all the elements and
dislodges the fines. The fines drop to the bottom of the Dust Collector. The fines stay
in the bottom head until they are unloaded into the Fines Collection Pot (usually once
per week).

Reverse jet cleaning should be done as soon as the pressure drop alarm sounds. If the
pressure drop across the Dust Collector becomes too high, the reverse jet sequence
may not be able to clean the filter elements. And if the pressure drop changes very
significantly before and after cleaning, then the spent catalyst lifting and the fines
removal may suffer.

After cleaning, the pressure drop across the Dust Collector should drop down to the
normal.

At initial start-up, reverse jet cleaning should be done to make permanent cake on the
filter elements in accordance with the manufacturer’s recommendation. Refer to the
manufacturer’s instructions (V-2155-503-A-501) for additional information.

6.3.2.2Unloading

Periodically (usually once per week), the operator must unload the Dust Collector
fines into an empty catalyst drum. Fines are transported from the Dust Collector to the
Fines Collection Pot. This vessel and its associated piping (Figure 6.3-1) are required
to safely remove the fines from the elevated pressure of collector, which must remain
in service at all times. This operation is carried out by cycling the Fines Collection Pot
through a programmed sequence controlled by the Regenerator Control System.

The operator must keep in mind that the catalyst fines may be pyrophoric. Care must
be taken to minimize their exposure to air during unloading.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 174 OF

This section outlines the logic requirements for the operation of the Dust Collector
Fines Collection Pot System. This explanation has been simplified to include only
those items that the operator can check for proper operation. For a complete
explanation of the logic refer to the manual for the PPS&E Regenerator Control
System.

The Dust Collector unloading operation consists of cycling the Fines Collection Pot
through a sequence of LOAD and UNLOAD steps. The operator starts these steps by
turning a handswitch. The steps are monitored and controlled by the PPS&E
Regenerator Control System.

The two basic steps of the fines unloading are:

STEP OPERATION
UNLOAD Fines Collection Pot, full of fines, is depressured to atmosphere and
unloaded into a catalyst drum.
LOAD Fines Collection Pot, empty of fines, is pressured and loaded with
fines from the Dust Collector.

At the end of the UNLOAD step, the cycle can be repeated if more fines unloading is
desired.

The Catalyst Addition System has the following feature:

Fines Collection Pot Switch: The Fines Collection Pot Switch is a field-
mounted, three-position handswitch. The three positions of the switch are
labeled as “LOAD,” “OFF” (mid-position), and “UNLOAD.” The switch must
be turned through the “OFF” position when switching from “LOAD” to
“UNLOAD” or back.

“LOAD”

In the “LOAD” position, the PPS&E Regenerator Control System prepares the
Fines Collection Pot and loads fines from the dust collector.

“OFF”

In the “OFF” position, the PPS&E Regenerator Control System closes the
Fines Collection Pot. Fines cannot be loaded or unloaded.

“UNLOAD”

In the “UNLOAD” position, the PPS&E Regenerator Control System prepares


the Fines Collection Pot and unloads fines into a catalyst drum.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 175 OF

UNLOAD SEQUENCE

STEP OPERATION
OFF Collection Pot, full of fines at Dust Collector pressure, waits for
signal to start sequence. All valves (XV-9,10,11,12) closed.
To proceed to the next step: Turn the Fines Collection Pot Switch to
the UNLOAD position. All valves verified closed.
DEPRESSURE The Vent valve (XV-11) opens and depressures the Collection Pot to
atmosphere through a restriction orifice. The restriction orifice limits
the rate of depressuring so as not to fluidize the dust in the vessel.
To proceed to the next step: The pressure in the Collection Pot must
be lower than the high switch point for the pressure transmitter (PT),
near atmosphere pressure. The pressure differential between the
Collection Pot and Dust Collector is above the high-high switch point
for the pressure differential transmitter (PDT). XV-11 verified open,
all other valves verified closed.
UNLOAD The Unload valve (XV-12) opens and fines flow into the catalyst
drum below.
To proceed to the next step: Turn the Fines Collector Pot Switch to
the OFF position.
OFF All valves close (XV-11, 12) or remain closed (XV-9, 10). The
Collection Pot is empty.

HAZOP Recommendation

The catalyst drum shall be provided electrical grounding when in catalyst unloading
operating work.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 176 OF

LOAD SEQUENCE

STEP OPERATION
OFF Collection Pot, empty of fines at atmospheric pressure, waits for
signal to start sequence. All valves (XV-9, 10, 11, 12) closed.
To proceed to the next step: Turn the Fines Collection Pot Switch to
the LOAD position. All valves verify closed.
PRESSURE-1 The Pressure valve (XV-10) opens and pressures the Collection Pot
to Dust Collector pressure through a restriction orifice. The
pressuring flow also serves to blow back the in-line screen at the
vessel.
To proceed to the next step: The pressure differential between the
Collection Pot and the Dust Collector is lower than the high switch
point for the PDT, the pressure differential is near zero. XV-10
verified open, all other valves verified closed.
PRESSURE-2 The Pressure valve (XV-10) closes.
To proceed to the next step: The pressure in the Collection Pot must
be higher than the high-high switch point for the pressure transmitter.
All valves verified closed.
LOAD The Load valve (XV-9) opens and fines flow into the Collection Pot
from the Dust Collector.
To proceed to the next step: Turn the Fines Collection Pot Switch to
the OFF position.
OFF All valves close (XV-9) or remain closed (XV-10,11,12). The
(After Load) Collection Pot is full of fines.

Every time the Dust Collector is unloaded into the catalyst drum via the Fines
Collection Pot record the following:

- Date
- Time
- Lock Hopper Counts
- Weight of Fines Collected

In this way a continuous record of fines collected as a function of catalyst circulated


can be kept.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 177 OF

6.3.3 Normal catalyst addition

This section outlines the logic requirements for the operation of the Catalyst Addition
System No. 1. This explanation has been simplified to include only those items that the
operator can check for proper operation. For a complete explanation of the logic, refer
to the manual for the PPS&E Regenerator Control System.

The operator must add fresh catalyst periodically to the Regeneration Section to
replenish catalyst removed as fines. Over time, as more and more fines are removed,
the catalyst level in the Disengaging Hopper decreases. To keep the normal operating
level in the Disengaging Hopper, the operator adds fresh catalyst into the Disengaging
Hopper via the Spent Catalyst Lift System using the Catalyst Addition System.

The Catalyst Addition System (Figure 6.3-2) consists of a Catalyst Addition Funnel
No. 1, Catalyst Addition Lock Hopper No. 1, and four valves. The Catalyst Addition
Funnel is open to the atmosphere and can be filled with catalyst from drums. The
Catalyst Addition Lock Hopper fills with catalyst and can be pressured up to transfer
the catalyst into the Catalyst Transfer System. The four logic-operated valves that
allow the Catalyst Addition Lock Hopper to be depressured, loaded, pressured up, and
unloaded during the addition of catalyst are listed below:

VALVE TAG
Load Valve XV-1
Pressure Valve XV-2
Vent Valve XV-3
Unload Valve XV-4

The open and closed positions of these valves are indicated by position switches.

There are several inherent hazards to overcome in order to add catalyst safely from
drums into the Catalyst Transfer System. First, since the Catalyst Transfer System
operates under a nitrogen pressure equal to the reactor pressure, it cannot be opened
directly to the atmosphere. Second, since the fresh catalyst has no coke (and the spent
catalyst obviously does) it must be added slowly enough to avoid an upset in the coke
burning operation of the Regeneration Tower. Third, since the Catalyst Addition Lock
Hopper should be filled only when it is completely empty (to avoid overfilling and thus
closing valves on catalyst), the time allowed for unloading the Catalyst Addition Lock
Hopper must be coordinated with the cycling of the Lock Hopper. By the addition
procedures and through the controlled sequence of the PPS&E Regenerator Control
System, the Catalyst Addition System accomplishes these tasks. In addition to fresh
catalyst, whole catalyst pills screened from the fines collected in the Dust Collector
can be added using the Catalyst Addition System. This is possible because the coke
content of the whole pills and the spent catalyst will be roughly the same, and any
leftover fines will be removed in the Disengaging Hopper.

A second function provided by the Catalyst Addition System is reloading of the


Regeneration Tower. Whenever the Regeneration Tower is unloaded for maintenance,
the catalyst can be reloaded by using the addition system in conjunction with the Spent
Catalyst Lift System.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 178 OF

The catalyst addition operation consists of cycling the Catalyst Addition Lock Hopper
through a sequence of LOAD and UNLOAD steps. The operator starts these steps by
turning a handswitch. The steps are monitored and controlled by the PPS&E
Regenerator Control System.

The two basic steps of the catalyst addition are:

STEP OPERATION
LOAD Catalyst Addition Lock Hopper, empty of catalyst, is depressured
and loaded with catalyst from the Addition Funnel.
UNLOAD Catalyst Addition Lock Hopper, full of catalyst, is pressured up
with nitrogen and unloaded into the Spent Catalyst Lift System.

At the end of the UNLOAD step, the cycle can be repeated if more catalyst addition is
desired.

The Catalyst Addition System has the following features:

a. Catalyst Addition Switch: The Catalyst Addition Switch is a field-mounted,


three-position handswitch. The three positions of the switch are labeled as
“LOAD,” “OFF” (mid-position), and “UNLOAD.” The switch must be turned
through the “OFF” position when switching from “LOAD” to “UNLOAD” or
back.

“LOAD”

In the “LOAD” position, the PPS&E Regenerator Control System prepares the
Catalyst Addition Lock Hopper so the operator can load it with catalyst.

“OFF”

In the “OFF” position, the PPS&E Regenerator Control System closes the
Catalyst Addition Lock Hopper. Catalyst cannot be loaded or unloaded.

“UNLOAD”

In the “UNLOAD” position, the PPS&E Regenerator Control System prepares


the Catalyst Addition Lock Hopper and unloads catalyst into the Spent Catalyst
Lift System.

b. Lock Hopper Cycle Counter: The Lock Hopper Cycle Counter counts the
number of times the Lock Hopper loads while the Unload Valve of the Catalyst
Addition Lock Hopper is confirmed open. Each time the Lock Hopper loads,
some catalyst is unloaded from the Catalyst Addition Lock Hopper. In order to
empty the Catalyst Addition Lock Hopper, the Lock Hopper must load a set
number of times. When the Lock Hopper has cycled the set number of times,
the Catalyst Addition Lock Hopper is considered to be empty. NOTE: This can
be confirmed by tapping lightly on the side of the Catalyst Addition Lock
Hopper.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 179 OF

c. Spent Catalyst Lift Line Pressure Differential: The lift line differential
pressure is monitored during the UNLOAD step. When the addition hopper is
being used to reload the Regeneration Tower, that is when the Lock Hopper is
not cycling, the absence of a lift line pressure differential is used as an
indication that the addition Hopper is empty.

d. Status Lamps: The status lamps aid the operator in loading and unloading the
Catalyst Addition Lock Hopper. There are two field-mounted lamps:
CATALYST ADDITION LOCK HOPPER LOAD and CATALYST
ADDITION LOCK HOPPER NOT EMPTY. Both status lamps cannot be lit at
the same time.

CATALYST ADDITION LOCK HOPPER LOAD

This lamp lights when the PPS&E Regenerator Control System has unloaded
the Catalyst Addition Lock Hopper and prepared it so the operator can load it
with catalyst. The operator may load catalyst only when this lamp is lit and the
Catalyst Addition Switch is in the “LOAD” position.

CATALYST ADDITION LOCK HOPPER NOT EMPTY

This lamp lights when PPS&E Regenerator Control System has not fully
unloaded the Catalyst Addition Lock Hopper. The operator is prevented from
loading catalyst into the Catalyst Addition Lock Hopper because it needs to be
unloaded.

e. Automatic Shutdown Sequence: All four logic-operated valves close


automatically when a Cold Shutdown, or Contaminated Nitrogen Shutdown
occurs. Any of the four valves that are open when the shutdown occurs close,
regardless of the step the Catalyst Addition Lock Hopper is in. After any
automatic shutdown the operator must restart operation in the UNLOAD
sequence to ensure that the addition hopper has fully unloaded before
proceeding.

f. Valve Interlocks: The valve interlock system prevents certain valve position
combinations which could cause a hazardous situation.

If the Pressure Valve or the Unload Valve is not confirmed closed, then the Vent
Valve and the Load Valve cannot be opened. This temporarily halts the LOAD
step. When the Pressure Valve and the Unload Valve confirm closed, the
catalyst addition sequence resumes.

The Vent Valve or the Load Valve is not confirmed closed, then the Pressure
Valve and the Unload Valve cannot be opened. This temporarily halts the
UNLOAD step. When the Vent Valve and the Load Valve confirm closed, the
catalyst addition sequence resumes.

The Figure6.3-2 ~ 6.3-9 are an outline of the logic steps for catalyst addition.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 180 OF

6.3.4Catalyst addition for catalyst changeout on the fly

This section outlines the logic requirements for the operation of the Catalyst Addition
System. This explanation has been simplified to include only those items that the
operator can check for proper operation. For a complete explanation of the logic, refer
to the manual for the PPS&E Regenerator Control System.

To effect an on-line catalyst changeout, the operator must add fresh catalyst to the
Nitrogen Seal Drum to replenish catalyst removed from the Regeneration Tower. To
keep the normal operating level in the Disengaging Hopper, the operator adds fresh
catalyst into the Nitrogen Seal Drum using the Catalyst Addition System No. 2 for
Catalyst Changeout on the Fly.

The Catalyst Addition System No. 2 (Figure 6.3-10) consists of a Catalyst Addition
Funnel, Catalyst Addition Lock Hopper, and four valves. The Catalyst Addition
Funnel is open to the atmosphere and can be filled with catalyst from drums. The
Catalyst Addition Lock Hopper fills with catalyst and can be pressured up to transfer
the catalyst into the Catalyst Transfer System. The four logic-operated valves that
allow the Catalyst Addition Lock Hopper to be depressured, loaded, pressured up, and
unloaded during the addition of catalyst are listed below:

VALVE TAG
Load Valve XV-17
Pressure Valve XV-18
Vent Valve XV-19
Unload Valve XV-20

The open and closed positions of these valves are indicated by position switches.

There are several inherent hazards to overcome in order to add catalyst safely from
drums into the Nitrogen Seal Drum. First, since the Seal Drum operates under a
nitrogen pressure of about 2.5 kg/cm2g (35 psig), it cannot be opened directly to the
atmosphere. Second, since the Addition Lock Hopper should be filled only when it is
completely empty (to avoid overfilling and thus closing valves on catalyst), the time
allowed for unloading of the Catalyst Addition Lock Hopper must be coordinated with
the catalyst circulation. By the addition procedures and through the controlled
sequence of the Regenerator Control System, the Catalyst Addition System
accomplishes these tasks.

The catalyst addition operation consists of cycling the Catalyst Addition Lock Hopper
No. 2 through a sequence of LOAD and UNLOAD steps. The operator starts these
steps by turning a handswitch. The steps are monitored and controlled by the PPS&E
Regenerator Control System.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 181 OF

The two basic steps of the catalyst addition are:

STEP OPERATION
LOAD Catalyst Addition Lock Hopper, empty of catalyst, is depressured and
loaded with catalyst from the Addition Funnel.
UNLOAD Catalyst Addition Lock Hopper, full of catalyst, is pressured up with
nitrogen and unloaded into the Nitrogen Seal Drum.

At the end of the UNLOAD step, the cycle can be repeated if more catalyst addition is
desired.

The Catalyst Addition System has the following features:

a. Catalyst Addition Switch: The Catalyst Addition Switch is a field-mounted,


three-position handswitch. The three positions of the switch are labeled as
“LOAD,” “OFF” (mid-position), and “UNLOAD.” The switch must be turned
through the “OFF” position when switching from “LOAD” to “UNLOAD” or
back.

“LOAD”

In the “LOAD” position, the PPS&E Regenerator Control System prepares the
Catalyst Addition Lock Hopper so the operator can load it with catalyst.

“OFF”

In the “OFF” position, the PPS&E Regenerator Control System closes the
Catalyst Addition Lock Hopper. Catalyst cannot be loaded or unloaded.

“UNLOAD”

In the “UNLOAD” position, the PPS&E Regenerator Control System prepares


the Catalyst Addition Lock Hopper and unloads catalyst into the Nitrogen Seal
Drum.

b. Nitrogen Seal Drum Level Indicator: The level in the Seal Drum is monitored
during the UNLOAD step. A low level in the Seal Drum indicates that it can
accept a drum of catalyst without overfilling. If the Seal Drum overfilled, then
the Unload valve would close on catalyst.

c. Status Lamps: The status lamps aid the operator in loading and unloading the
Catalyst Addition Lock Hopper. There are two field-mounted lamps:
CATALYST ADDITION LOCK HOPPER LOAD and CATALYST
ADDITION LOCK HOPPER NOT EMPTY. Both status lamps cannot be lit at
the same time.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 182 OF

CATALYST ADDITION LOCK HOPPER LOAD

This lamp lights when the PPS&E Regenerator Control System has unloaded
the Catalyst Addition Lock Hopper and prepared it so the operator can load it
with catalyst. The operator may load catalyst only when this lamp is lit and the
Catalyst Addition Switch is in the “LOAD” position.

CATALYST ADDITION LOCK HOPPER NOT EMPTY

This lamp lights when the PPS&E Regenerator Control System has not fully
unloaded the Catalyst Addition Lock Hopper. The operator is prevented from
loading catalyst into the Catalyst Addition Lock Hopper because it needs to be
unloaded.

d. Automatic Shutdown Sequence: All four logic-operated valves close


automatically when a Cold Shutdown or Contaminated Nitrogen Shutdown
occurs. Any of the four valves that are open when the shutdown occurs will
close, regardless of the step the Catalyst Addition Lock Hopper is in. After any
automatic shutdown the operator must restart operation in the UNLOAD
sequence to ensure that the addition hopper has fully unloaded before
proceeding.

e. Valve Interlocks: The valve interlock system prevents certain valve position
combinations which could cause a hazardous situation.

If the Pressure Valve or the Unload Valve is not confirmed closed, then the Vent
Valve and the Load Valve cannot be opened. This temporarily halts the LOAD
step. When the Pressure Valve and the Unload Valve confirm closed, the
catalyst addition sequence resumes.

If the Vent Valve or the Load Valve is not confirmed closed, then the Pressure
Valve and the Unload Valve cannot be opened. This temporarily halts the
UNLOAD step. When the Vent Valve and the Load Valve confirm closed, the
catalyst addition sequence resumes.

The Figure6.3-10 ~ 6.3-17 are an outline of the logic steps for catalyst addition.

6.3.5Filter cleaning

Very fine dust which may be carried out with the gas from the Reduction Zone collects
in one of the Filters (312-ME2A/B).

Periodically, the operator must take a Filter out of service for a short period of time in
order to clean the filter elements. During this operation, the Filter is bypassed and
normal catalyst circulation continues.

The operator must keep in mind several important factors and precautions when
cleaning or replacing the elements in a Filter. First, since the Filter operates under a
pressured, hydrogen-rich environment, it must be depressured and inerted before it is
opened. And since the catalyst fines may be pyrophoric, care must be taken to
minimize their exposure to air during the cleaning and replacement of the elements.

The following procedure for replacing an element in a Filter is general in nature and is
not meant to apply to any one particular unit. The purpose in presenting this general
procedure outline is to assist the refiner in developing a more detailed procedure for his
particular unit.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 183 OF

FILTER CLEANING

(1) Open the bypass valve to bypass the Filter.

(2) Block in the inlet and outlet valves of the Filter.

(3) Depressure the Filter to flare or other safe location.

(4) Inert the Filter by purging with nitrogen.

(5) Open the Filter and carefully remove the element. Install a new element and
close the Filter.

(6) Inert the Filter by purging with nitrogen.

(7) Open the inlet valve slowly and pressure up the Filter. Open the outlet valve to
recommission the Filter. Close the bypass valve.

6.3.6Vent gas scrubbing system

A by-product of the regeneration process is the release of HCI and chlorine. Treating
the vent gas for HCI and chlorine eliminates environmental and structural corrosion
concerns. UOP utilizes a two-stage treating unit. The first stage is a Venturi Scrubber
which educts regeneration vent gas from the regeneration gas outlet line. Circulating
caustic, with a controlled pH, is the educting fluid. As the caustic and regeneration
vent gas pass through the scrubber, essentially all of the HCI and the majority of the
chlorine are removed. The combined stream of caustic and regeneration gas then flows
to the second stage of treating, the Vent Gas Wash Tower.

A two-stage treating system reduces HCI and chlorine to lower levels than can be
achieved by a single-stage system. The combined stream enters the Wash Tower near
the bottom. The vent gas passes through a shower of circulating caustic and a packed
bed washed with caustic. The scrubbed gas exits the top of the wash tower and is
vented to atmosphere. The caustic flows out of the bottom of the wash tower for
disposal, or pH adjustment and recirculation.

6.3.6.1Control parameters

(a) Caustic Flow to the Venturi

The caustic flow to the Venturi is controlled by a flow control valve. The flow
rate is set at its design rate. Decreasing the caustic flow, thus increasing the
vent gas pressure, will cause the regeneration tower pressure control valve to
open in order to maintain the same tower pressure.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 184 OF

(b) Caustic Flow to the Tower Packing

The caustic flow to the tower packing is controlled by a hand-operated globe


valve. The flow rate is set at its design rate to effect the chloride removal in the
packed bed. No adjustment to this flow is required other than to maintain the
design rate.

(c) Caustic Flow to the Spray Nozzle Below the Packed Bed

The caustic flow to below the packed bed is controlled by a hand-operated


globe valve. The flow rate is set at its design rate to keep the bottom of the
packing and the tower walls wetted with caustic. No adjustment to this flow is
required other than to maintain the design rate.

(d) Condensate Flow to the Spray Nozzle Below the Mesh Blanket

The condensate flow is intermittent and controlled by a hand-operated globe


valve. The flow rate and time in operation is set by what is required to dissolve
any salt buildup on the Mesh Blanket. When the pressure differential across the
mesh blanket reaches the high alarm setpoint, open the globe valve for 15
minutes to spray the deposit with condensate. Stop flow and check the pressure
differential. Repeat the washing procedure until the pressure differential returns
to its clean mesh value.

(e) Condensate Injection to the Circulating Caustic

The condensate flow is controlled by the liquid level in the Wash Tower. The
liquid level is maintained by condensate injection to replace the moisture lost
due to humidification of the vent gas and through the spent caustic drain.

(f) Caustic Injection to the Circulating Caustic

The caustic flow is controlled by manually adjusting the pumpstroke of the


injection pump. The flow of caustic is adjusted to maintain the total alkalinity
of the circulating caustic at 0.35%, which should correspond to a pH level of
between 7.5 and 8.5. The pH is monitored continuously by an on-line pH meter.
The total alkalinity (NaOH equivalent) is monitored by lab analysis of a daily
circulating caustic sample. Increasing the caustic injection will increase the
total alkalinity of the circulating caustic.

(g) Spent Caustic Withdrawn from the Circulating Caustic

The spent caustic withdrawal is controlled by a hand-operated globe valve in


the withdrawal line. The flow of spent caustic is adjusted to maintain the total
solids of the circulating caustic at 1%. The total solids level of the circulating
caustic is monitored by lab analysis of a daily sample. Increasing the spent
caustic withdrawal will decrease the total solids of the circulating caustic as
more makeup condensate will be required to maintain liquid level in the wash
tower.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 185 OF

6.3.6.2Overpressure protection

To protect the wash tower from overpressurization caused by a flooded bed, failure of
the level instrument, or a restricted vent line, a liquid leg and tower gas bypass line are
provided. The liquid leg is located such that if the wash tower pressure builds, a high
level alarm in the line will sound and shut down the circulating caustic pumps, caustic
injection pumps, and water injection pumps. As the tower pressure builds and pushes
the caustic into the liquid leg, the tower gas bypass line distributor will be exposed and
allow gas to bypass the tower. A siphon breaking vent is provided in the liquid leg to
prevent the entire caustic inventory of the tower from being educted out the liquid leg.

6.3.6.3Diversion valves

To protect the wash tower packing from high temperature and possible combustion,
the vent gas is bypassed around the tower if the circulating caustic flow is lost. The
circulating caustic to the Venturi scrubber cools the vent gas before entering the wash
tower. If this flow is lost, a valve in the vent line upstream of the Venturi is closed, and
the valve in the tower bypass opens.

CAUTION NOTES FOR THE CYCLEMAX CCR UNIT

CAUTION:
All equipment containing hydrogen shall be evacuated and purged with nitrogen before
opening and admitting air and after closing before admitting hydrogen.

CAUTION:
Care must be exercised when venting and draining equipment to prevent personnel
exposure to toxic aromatics.

CAUTION:
All upstream piping and equipment must be purged with inert gas before isolating the
relief gas header from the line to the knockout drum and flare.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 186 OF

Normal operating variables

Operation parameters used for the design and specification of the Platforming Process
Unit CCR Section at full throughput on Lean Feed Case and Rich Feed Case are given
below for easy reference. Further information is available on the Process Flow
Diagram in the attachment 9-1.

These figures should be used only as a guide. Actual operating parameters will be
determined during operation at different throughputs.

(1) Reactor section at Unit-300


Lean Feed Rich Feed
Reactor outlet reduction gas temperature (oC) 249.3 249.4
Reduction gas temperature to Unit-300 (oC) 65.6 65.6
Reduction gas heater No.1 outlet temp. (oC) 398.8 399.1
Reduction gas heater No.2 outlet temp. (oC) 573.1 573.1

(2) Vent gas wash tower


Lean Feed Rich Feed
Bottom temperature (oC) 43.0 43.0
Bottom flow rate (kg/hr) 25,982 25,982

(3) Regeneration tower


Lean Feed Rich Feed
Overhead temperature (oC) 509.0 509.0
Regeneration cooler outlet temperature (oC) 481.5 481.5
Regeneration heater outlet temperature (oC) 476.7 476.7
Air heater outlet temperature (oC) 584.6 584.6
Chloride injection temperature (oC) 148.9 148.9

(4) Lift gas blower


Lean Feed Rich Feed
Lift gas blower outlet flow rate (kg/hr) 171.9 171.9
Lift gas blower outlet temperature (oC) 161.0 161.0
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 187 OF

FIGURE 6.3-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 188 OF

FIGURE 6.3-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 189 OF

FIGURE 6.3-3
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 190 OF

FIGURE 6.3-4
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 191 OF

FIGURE 6.3-5
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 192 OF

FIGURE 6.3-6
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 193 OF

FIGURE 6.3-7
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 194 OF

FIGURE 6.3-8
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 195 OF

FIGURE 6.3-9
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 196 OF

FIGURE 6.3-10
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 197 OF

FIGURE 6.3-11
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 198 OF

FIGURE 6.3-12
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 199 OF

FIGURE 6.3-13
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 200 OF

FIGURE 6.3-14
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 201 OF

FIGURE 6.3-15
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 202 OF

FIGURE 6.3-16
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 203 OF

FIGURE 6.3-17
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 204 OF

6.4Routine Operations

In order to keep the plant in good and safe working conditions, several routine
operations need to be conducted.

6.4.1Sampling

Regular sampling especially of the products should be done to ensure that these
products meet specification. Regular sampling can also indicate possible leaks in the
equipment.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 205 OF

6.5General Overall Shutdown Plan

The following shutdown procedure covers a normal planned complete shutdown such
as would be required for a catalyst change and/or the periodic cleaning and inspection
of vessels.

The operations described in these sections must overlap to some extent. The extent to
which these operations may be conducted simultaneously will depend upon the
availability of operating personnel.

The shutdown instructions which follow are divided into sections for convenience.
Below is a list of the various sections to be discussed:

(1) Automatic Shutdown


a. Hot Shutdown
b. Cold Shutdown
c. Contaminated Shutdown

(2) Manual Shutdown


a. Hot Shutdown
b. Cold Shutdown
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 206 OF

6.6Detailed Step-by Step Shutdown Procedure

6.6.1Automatic shutdown

The PPS&E Regenerator Control System prevents improper or unsafe conditions by


executing an automatic shutdown. There are three automatic shutdowns: a Hot
Shutdown, a Cold Shutdown, and a Contaminated Nitrogen Shutdown. Each shutdown
has its own specific usage, causes, and results.

6.6.1.1Hot shutdown

A Hot Shutdown occurs when the conditions in the Regeneration Section require that
catalyst regeneration be stopped but not that the Regeneration Section be cooled, nor
that the Isolation Systems be closed. This avoids delays in reheating the Regenerator
Section prior to restarting. It also minimizes valve wear and catalyst attrition.

When any of the Hot Shutdown alarms sound, the Regenerator Control System will
initiate the following actions in the Regeneration Section:

Action Item
(1) Starts nitrogen purge. XV-15 opens.
(2) Stops air addition. XV-13 closes.
(3) Closes Lower Air Supply Line. XV-14 closes.
(4) Stops chloride addition. XV-16 closes and Chloride Injection Pump
shuts down.
(5) Stops catalyst flow. Lock Hopper stops cycling, equalization
valves close.
(6) Stops catalyst lifting. Regenerated Catalyst Lift Pipe DP setpoint is
set to zero.
(7) Stops catalyst addition. Catalyst Addition Lock Hopper will stay in
the unload step, if operating.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 207 OF

Any of following items and conditions will cause a Hot Shutdown. The conditions that
clear a Hot Shutdown are also listed.

Item Condition that Causes Condition that


a Hot Shutdown Clears
a Hot Shutdown
(1) Spent Catalyst Isolation System Closed Open
(2) Regenerated Catalyst Isolation Closed Open
System
(3) Air Flow to Air Heater Low Not low
(4) Bypass for Air Flow to Air - Bypassed
Heater
(5) Burn Zone Gas Flow Low Not low
(6) Bypass for Burn Zone Gas Flow - Bypassed
(7) Burn Zone Inlet Temperature High Not high
(8) Burn Zone Outlet Temperature High Not high
(9) Disengaging Hopper Level Low Not low
(10) Disengaging Hopper Level High Not high
(11) Total Spent Catalyst Lift Gas Low Not low for 10
Flow minutes.
(12) Total Regenerated Catalyst Lift Low Not low for 10
Gas Flow minutes.
(13) Oxygen Analyzer Sample Flow Low Not low
(14) Bypass for Oxygen Analyzer - Bypassed
Sample Flow
(15) Burn Zone Inlet Oxygen Content High Not high
(16) Bypass for Burn Zone Inlet - Bypassed
Oxygen Content
(17) Regenerated Catalyst Lift Line High Not high
Temperature
(18) Lock Hopper Abnormal Cycle Alarm No alarm
Alarm
(19) Recycle Gas Flow to Catalyst Low Not low for 10
Collector minutes.
(20) Recycle Gas Temperature to High Not high
Catalyst Collector
(21) Circulating Caustic to Vent Gas Low Not low
Wash Tower Flow
(22) Lock Hopper Level Switch Alarm No alarm
Malfunction Alarm
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 208 OF

6.6.1.2Cold shutdown

A Cold Shutdown occurs when the conditions in the Regeneration Section require that
catalyst regeneration be stopped, the Regeneration Section be cooled, and the Isolation
System be closed. This reduces the temperatures in the Regeneration Section and
prevents cross-mixing of the hydrogen/hydrocarbon environment of the reaction
section and the oxygen-containing environment of the Regeneration Section.

When any of the Cold Shutdown alarms sound or when the Regenerator Run/Stop
Pushbutton is pushed or when the Emergency Stop Switch is turned, the Regenerator
Control System initiates the following actions in the Regeneration Section:

Action Item
(1) Starts nitrogen purge. XV-15 opens.
(2) Stops air addition. XV-13 closes.
(3) Closes Lower Air Supply Line Valve. XV-14 closes.
(4) Stops chloride addition. XV-16 closes and Chloride Injection
Pump shuts down.
(5) Stops catalyst flow. Lock Hopper stops cycling,
equalization valves close.
(6) Stops catalyst lifting. Regenerated Catalyst Lift Pipe DP
setpoint is set to zero. Secondary lift
gas control valve closed on both L-
Valve Assemblies.
(7) Stops catalyst addition. XV-1, XV-2, XV-3, and XV-4 close.
(8) Closes Spent Catalyst Isolation System. XV-5 and XV-7 close, then XV-6
opens.
(9) Closes Regenerated Catalyst Isolation XV-22 and XV-24 close, then XV-23
System. opens.
(10) Shuts down Regeneration Gas and Air Stops voltage to each heater’s power
Heaters. controller.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 209 OF

Any of the following conditions will cause a Cold Shutdown:

Item Condition
(1) Regenerator Run/Stop Pushbutton. “STOP” by manual operation.
(2) Emergency Stop Switch. “STOP” by manual operation.
(3) Spent Catalyst Isolation Valves. Either Valve XV-5 or XV-7 does not
confirm closed when they should be
closed OR does not confirm open when
they should be open.
(4) Regenerated Catalyst Isolation Valves. Either Valve XV-22 or XV-24 does not
confirm closed when they should be
closed OR does not confirm open when
they should be open.
(5) CCR Nitrogen Header. Low pressure.

6.6.1.3Contaminated nitrogen shutdown

A Contaminated Nitrogen Shutdown occurs when the independent nitrogen header is


contaminated, requiring that catalyst regeneration be stopped, the Regeneration
Section be cooled, and the Isolation Systems be closed. In addition, the Contaminated
Nitrogen Shutdown prevents contaminated nitrogen from entering the lower section of
the Regeneration Tower by closing the Nitrogen Valve (XV-15), the Pressure Valve of
the Regenerated Catalyst Isolation System (XV-23), and the control valve for the
nitrogen purge to the Nitrogen Seal Drum.

When a contaminated Nitrogen Shutdown occurs, the UOP PIC Regenerator Control
System initiates the following actions in the Regeneration Section:

Action Item
(1) Prevents nitrogen purge. XV-15 closes.
(2) Stops air addition. XV-13 closes.
(3) Closes Lower Air Supply Line Valve. XV-14 closes.
(4) Stops chloride addition. XV-16 closes and Chloride Injection
Pump shuts down.
(5) Stops catalyst flow. Lock Hopper stops cycling,
equalization valves close.
(6) Stops catalyst lifting. Regenerated Catalyst Lift Pipe DP
setpoint is set to zero. Secondary lift
gas control valve closed on both L-
Valve Assemblies.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 210 OF

(7) Stops catalyst addition. XV-1, XV-2, XV-3, and XV-4 close.
(8) Closes Spent Catalyst Isolation System. XV-5 and XV-7 close, then XV-6
opens.
(9) Closes Regenerated Catalyst Isolation XV-22, XV-24 close, and XV-23
System. remains closed.
(10) Closes nitrogen purge to Nitrogen Seal Control valve closes.
Drum.
(11) Shuts down Regeneration. Stops voltage to each heater’s power
controller.

The condition that will cause a Contaminated Nitrogen Shutdown is:

Item Condition
(1) CCR Nitrogen Header. High contaminants.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 211 OF

6.6.2Manual shutdown

The manual shutdown procedures may be used for a planned shutdown or for a
shutdown necessitated by an event like one of the following:

(1) Sudden rise in the temperature of the bed thermocouples in the Burn Zone and
the Reheat Zone, at the Burn Zone outlet, or the Drying Zone outlet.

(2) Malfunctioning oxygen analyzer.

(3) Loss of the electric heaters.

(4) Cooling water failure.

(5) Platforming reactor section shutdown.

Obviously, the events listed above do not cover all of the possibilities for a manual
shutdown, but most other failures result in an immediate automatic shutdown.

Information regarding instrument air failure, serious leaks, etc. is contained in


Emergency Procedures.

6.6.2.1Hot shutdown

The shutdown is only going to be for a short duration (no more than 36 hours),
maintain the heat input to the Regeneration Section. Proceed as follows:

(a) Stop catalyst flow by depressing the Catalyst Flow Off Pushbutton.

NOTE: The Lock Hopper stops cycling.

(b) Start a nitrogen purge to the Regeneration Tower by depressing the Nitrogen On
Pushbutton.

NOTE: Chloride injection to the Chlorination Zone stops automatically:


XV-16 closes; the Chloride Injection Pump shuts down.

(c) Stop air addition to the Regeneration Tower by depressing the Air Off
Pushbutton.

(d) Set the Catalyst Flow Setpoint at 0% (or as low as possible) to prevent the
carbon profile in the Burn Zone of the Regeneration Tower from being
accidentally disturbed during the shutdown.

(e) Close the excess air vent hand-control valve in manual. Set the nitrogen flow to
the Air Heater at the design rate of nitrogen for startup.

(f) Close the Lower Air Supply Line Valve by depressing the Lower Air Supply
Line pushbutton to closed. Block in the manual valve in the air line upstream of
the Air Valve (XV-13).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 212 OF

(g) Block in the organic chloride drum, pump discharge, and manual valve
downstream of the Chloride Valve (XV-16).

6.6.2.2Cold shutdown

If the Regeneration Section shutdown is to last for a long period (or if vessels or lines
are to be opened), proceed as follows:

a. Depress the Regenerator Run/Stop push button to STOP.

b. Set the Catalyst Flow Set point at 0% (or as low as possible) to prevent the
carbon profile in the burn zone of the tower from being accidentally disturbed
during the shutdown.

c. Set the two temperature controllers for the electric heaters on manual at zero
output (Regeneration Heater and Air Heater).

NOTE: The inlet temperature controller for the Burn Zone is split-ranged to the
Regeneration Heater (50-100%) and the Regeneration Cooler (50%). Set its
output at 50% for zero output to the Regeneration Heater.

d. Close the excess air vent hand-control valve in manual. Set the nitrogen purge
to the Air Heater at the design rate of nitrogen for startup.

e. Close the Lower Air Supply Valve by depressing the Lower Air Supply
Pushbutton to OFF (XV-14). Block in the manual valve in the air line upstream
of the Air Valve (XV-13).

f. Block in the organic chloride drum, pump discharge, and manual valve
downstream of the Chloride Valve (XV-16).

g. Continue to cool the tower until all temperatures are down to 205ºC (400ºF) (or
as low as the Regeneration Blower will allow.) Then shut down the
Regeneration Blower and Cooler Blower.

h. Continue the design rate of nitrogen purge for startup through the Air Heater
until all temperatures are down to 95ºC (200ºF).

i. Reduce the nitrogen purge via the Air Heater to as low a rate as possible while
maintaining Regeneration Tower pressure control. Maintain the Spent Catalyst
and Regenerated Catalyst Isolation Systems closed. The purges to the Air
Heater and the Nitrogen Seal Drum should keep the Regeneration Tower air-
free.

j. During the period the regeneration section is not in operation, start addition of
chloride compound and water into the feed to the CCR Platforming Unit. For all
UOP R-30 and R-130 series Platforming catalyst, typical addition rates are 0.5
wt-ppm Cl and 4 wt-ppm H2O on a fresh feed basis.

On a regular basis, transfer enough catalyst out of the bottom of the last reactor
until a “fresh” sample of spent catalyst from the last reactor reaches the spent
catalyst sample location. Sample the spent catalyst to monitor not only the
chloride content but also the increasing coke level. Adjust the chloride addition
rate as needed to maintain the desired Cl level on the spent catalyst. Note: Black
Catalyst Startup to be used when restarting.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 213 OF

CAUTION NOTES FOR THE CYCLEMAX CCR UNIT

CAUTION:
All equipment containing hydrogen shall be evacuated and purged with nitrogen before
opening and admitting air and after closing before admitting hydrogen.

CAUTION:
Care must be exercised when venting and draining equipment to prevent personnel exposure
to toxic aromatics.

CAUTION:
All upstream piping and equipment must be purged with inert gas before isolating the relief
gas header from the line to the knockout drum and flare.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 214 OF

6.7Blanking Off

Every line connecting to a nozzle of the vessel to be entered must be blinded. This
includes drains connecting to a closed sewer, utility connections and all process lines.
The location of each blind should be marked on a master piping and instrumentation
diagram (P&ID), each blind should be tagged with a number and a list of all blinds
and their locations should be maintained. One person should be given responsibility
for all the blinds in the unit to avoid errors.

The area around the vessel manways should also be surveyed for possible sources of
dangerous gases which might enter the vessel while personnel are inside. Examples
include acetylene cylinders for welding and process vent or drain connections in the
same or adjoining units. Any hazards found in the survey should be isolated or
removed.

Furthermore, additional blinds should be installed at the battery limits for safety.

6.8Operating Equipment

In turnaround inspections, the possibility that vessels will contain dangerous gases is
much higher. Equipment which has been in service must be thoroughly drained and
purged before entry. The vessel should have been steamed out, unless steam present; a
hazard to the internals, and then fresh air circulated through it until all traces of
hydrocarbons are gone. If liquid hydrocarbon remains or if odors persist afterwards,
repeat the purging procedure until the vessel is clean. The service history of the vessel
must also be investigated before entry so that appropriate precautions may be taken.

In a turnaround inspection, every vessel nozzle must be blinded with absolutely no


exceptions. There will always be residual process material at the low and high points
in the lines connecting to the vessel because it is not possible to purge them completely
clean. The blinds must all be in place at the vessel nozzles before the vessel is purged.

Another factor to be cautious of, especially if entering a vessel immediately after the
unit has been shut down, is heat. The internals of the vessels can still be very hot from
the steam-out procedure or from operations prior to the shutdown. If that is the case,
the period of time spent working inside of the hot vessel should be limited and frequent
breaks should be taken outside of the vessel.

Also refer to Section 10.10 and 10.12 for additional information.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 215 OF

6.9Special Precautions

6.9.1General

The following precautions, recommended during the HAZOP Study, for the
Platforming Process Unit should be especially observed.

6.9.2Precautions for entering a contaminated or inert atmosphere

Nitrogen is non-toxic. Seventy-nine mol% of the air we breathe is nitrogen, 21 mol% is


oxygen. However, in vessels or areas where there is a high concentration of nitrogen,
there is also a deficiency of oxygen for breathing. Breathing an atmosphere deficient in
oxygen (i.e.: an inert atmosphere) will rapidly result in dizziness, unconsciousness, or
death depending on the length of exposure. Do not enter or even place your head into a
vessel which has a high concentration of nitrogen. Do not stand close to a valve where
nitrogen is being vented from equipment at a high rate which might temporarily cause
a deficiency in oxygen close to the valve.

UOP policy is not to allow any UOP technical advisors to perform work in a vessel
which is known to be contaminated or under an inert atmosphere. UOP does not permit
its technical advisors to perform “inert entry” work inside any vessel.

Refinery personnel who do have to enter a contaminated or inert atmosphere should


follow all prescribed standard safety precautions and regulations which apply for the
refinery. OSHA regulations concerning the use of respirators (29 CFR Subpart 1,
Section 1910.134) should be read and thoroughly understood.

It is also important to emphasize that if a person has entered a vessel and becomes
unconscious, no individual should go in to help him without first putting on a fresh air
mask, confirming that the air supply is safe, donning a safety harness, and enlisting the
aid of a minimum of two other people to remain immediately outside of the vessel to
assist him. This may seem to be an obvious warning, but people do forget this in the
trauma of an emergency situation. Often the first thought is to save the person in
distress and people enter the vessel without proper protection only to succumb to the
same hazard without anyone else being present to save them.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 216 OF

7EMERGENCY SHUTDOWN

7.1General Instruction

The following situations necessitate immediate shutdown of the Regeneration Section


as described below. These items supplement the conditions that would require a
manual shutdown.

In any of the following situations: air addition to the Regeneration Tower must be
stopped IMMEDIATFI.Y When an automatic Hot Shutdown, Cold Shutdown, or
Contaminated Nitrogen Shutdown is initiated, the Control System should stop this air
addition automatically by closing the Air Valve (XV-13). In any case, to help ensure
that no air addition does occur, close the manual block valve in the air line upstream of
the Air Valve (XV-13) IMMEDIATELY

7.2Instrument Air Failure

(1) Upon instrument air failure, all control valves in the Regeneration Section move
to the fail-safe positions. In most cases, the fail-safe position is the closed
position. However, the two Regeneration Tower vent control valves (i.e., the
Burn Zone vent and the excess air vent) stay in the positions they were in at the
time of the instrument air failure in order to maintain Tower pressure control.
And the control valves for nitrogen to the Air Heater and the recycle gas purge
to the Catalyst Collector at the bottom of the Platforming Reactor and to the
Reduction Zone will open to maintain purge flows.

All logic-operated valves in the Regeneration Section will also move to the fail-
safe positions upon instrument air failure. For both isolation sums., the two
isolation valves in the catalyst line will close and the nitrogen purge valve will
open to isolate the Regeneration Tower. These actions will initiate a Hot
Shutdown. The Air Valve (XV-13) will close and the Nitrogen Valve (XV-15)
will open to purge the Regeneration Tower with nitrogen,

Complete the shutdown of the Regeneration Section in accordance with the


manual Hot Shutdown Procedure.

(2) Upon instrument air failure, the combustion air flow to the Air Heater will be
also lost suddenly. This will initiate an automatic Hot Shutdown. Complete the
shutdown of the unit in accordance with the manual Hot Shutdown Procedure.

NOTE: The nitrogen header is tied in with the instrument air header as a
standby system. So, if the instrument air supply pressure is low, then nitrogen
may be put into the instrument air header. If this happens, it would be indicated
by a sudden loss of oxygen concentration and Burn Zone temperatures. A
manual Hot Shutdown should be initiated immediately.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 217 OF

7.3Recycle Compressor Failure

Restart the Recycle Compressor as soon as possible. Upon Recycle Compressor


failure, recycle gas flow to the Reduction Zone at the top of the Platforming reactor
and to the Catalyst L-Valve Assembly at the bottom of the Platforming reactor will
also be lost. These purges keep these areas free of naphtha and should be restarted as
soon as possible.

If the Recycle Compressor cannot be restarted, shutdown the Platforming reactor


section in accordance with UOP shutdown procedures.

Complete the shutdown of the Regeneration Section in accordance with the manual
Hot Shutdown procedure.

7.4Lift Gas Blower Failure

Upon Lift gas blower failure, booster gas flow to Regenerated Catalyst L-Valve
Assembly will be lost suddenly. This will initiate an automatic Hot Shutdown. Also,
net gas flow will be lost to the Reduction Gas Heaters, causing them to shutdown.
Standby recycle gas to the reduction zone should begin automatically.

Maintain recycle gas flow to the Reduction Zone at the top of the Platforming reactors
and to the Catalyst Collector at the bottom of the Platforming reactors.

Complete the shutdown of the Regeneration Section in accordance with the manual
Hot Shutdown Procedure. Because of the loss of flow, however, the Reduction Gas
Heater will not be in operation.

7.5Cooling Water Failure

Upon cooling water failure, cooling to the Lift Gas Blower and to the Circulating
Caustic Cooler will be lost suddenly. Shut down the Regeneration Section in
accordance with the Cold Shutdown Procedure.

7.6Explosion, Fire, Line Rupture, or Serious Leak

Do the following if possible:

a. Turn the Emergency Stop switch to the Stop position.

b. Isolate the affected area of the unit. Block in the high pressure hydrogen system
(net gas) as required to accomplish this.

Maintain the booster gas supply as lift gas to the Reduction Zone via the
Regenerated Catalyst L-Valve Assembly. Maintain recycle gas flow to the
Reduction Zone atop the Platforming reactors and to the Catalyst Collector at
the bottom of the Platforming reactors.

c. Complete the shutdown of the Regeneration Section in accordance with the


manual Cold Shutdown procedure when time permits.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 218 OF

7.7CCR Nitrogen Failure

Loss of nitrogen (CN2) to the Regeneration Section is a serious emergency. The


Regeneration Section cannot be safely operated without a constant supply of nitrogen
at the design pressure and purity. Restart nitrogen to the Regeneration Section as soon
as possible.

Upon nitrogen failure, the nitrogen header pressure to the Regeneration Section will be
lost suddenly. This will initiate an automatic Cold Shutdown. Also, all of the nitrogen
purge gas flows to the Regeneration Section will be lost.

Close the manual valve in the air supply line to the Regeneration Section upstream of
the Air Valve (XV-13).

Complete the shutdown of the Regeneration Section in accordance with the manual
Cold Shutdown procedure. However, there will be no nitrogen purge to the Air Heater
to cool the Regeneration Tower, and the Regeneration Tower will cool more slowly.

Maintain operation of the Regeneration Blower. The Regeneration Tower will


gradually depressure through the seals of the Regeneration Blower.

After a loss of nitrogen, ensure that the nitrogen header is purged free of any
contaminants before resuming the nitrogen supply to the Regeneration Tower.

CAUTION NOTES FOR THE CYCLEMAX CCR UNIT

CAUTION:
All equipment containing hydrogen shall be evacuated and purged with nitrogen before
opening and admitting air and after closing before admitting hydrogen.

CAUTION:
Care must be exercised when venting and draining equipment to prevent personnel
exposure to toxic aromatics.

CAUTI ON:
All upstream piping and equipment must be purged with inert gas before isolating the
relief gas header from the line to the knockout drum and flare.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 219 OF

7.8Power failure

When power failure occurs, all of the motor driven rotary machines and electric
heaters are tripped. And the Platforming process unit CCR section emergency
shutdown sequence will be activated automatically (cold shutdown: see Section 6.6).

When the electrical power failure occurs, the operating condition for this unit will be
as follows:

(1) The booster gas flow to regenerated catalyst L-Valve Assembly will lost suddenly
by the net gas compressor (300-C2A/B) stop.

(2) Due to primary lift gas flow low low caused by trip of motor driven lift gas
blower (312-C2). The reactor catalyst L-Valve Assembly will lost suddenly.

(3) Circulating caustic flow will stopped since the motor driven caustic circulation
pumps (312-P1A/B) are stopped at the electrical power failure.

After that, follow the shutdown procedure shown in the Section 6 if the power failure
is long term. When the electrical power is restored and feed is available, start-up the
section in accordance with the applicable steps in the Section 6.

7.9Steam Failure

Generally a steam failure is of long term duration. Due to a loss of driving force for
the net gas compressor at the Platforming Process Unit and loss of steam trace
temperature the Platforming Process Unit and CCR section emergency shutdown
sequence will be activated automatically. The following is a guideline for shutting
down the Platforming Process Unit and CCR section.

(1) The booster gas flow to regenerated catalyst L-Valve Assembly will lost suddenly
by the net gas compressor (300-C2A/B) failure, CCR section will cold shutdown
automatically. Because the recycle gas pressure decrease, CCR section pressure
balance among catalyst circulating drums could not be maintained, and this will
trigger cold shutdown. Closure of catalyst transfer line isolation valves and
nitrogen purge to regeneration tower (312-R1) will be performed automatically.

(2) Stop chloride injection pumps (312-P2A/B) to avoid liquid of chloride entry to
regenerator tower (312-R1).

(3) Stop the caustic and condensate injection flow to the vent gas wash tower.

When the steam supply is restored, startup the unit in accordance with the applicable
steps in the section 6, normal start-up procedure.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 220 OF

8MAJOR EQUIPMENT

8.1Summary Tables

Equipment in the Platforming Process Unit CCR Section is summarized below. Refer
to “Equipment List for Platforming Process Unit CCR Section” (S-312-1224-101).

Item No ID TL DP DT (OP) OT
(mm) (mm) (kg/cm2G) (oC) (kg/cm2G) (oC)

312-R1 1,680 19,000 4.2 580 2.5 565


1,070
312-V1 900 730 ATM 120 ATM 38
312-V2 600 1,230 10.5 120 3.76 38
312-V3 1,600 3,400 10.5 120 3.56 91
312-V4 500 650 10.5 120 3.56 57
312-V5 900 730 ATM 120 ATM 38
312-V6 600 1,230 10.5 120 3.76 38
312-V7 900 2,300 10.5 177 2.46 149
312-V8 600 8,534 13.8/F.V. 177/149 2.71 149
400
500
312-V9 750 9,300 .36 507 0.01 46
312-V10 400 1,500 ATM 120 ATM 40
312-V11 400 1,500 ATM 120 ATM 65
312-V50 1,000 2,850 ATM 120 ATM 38
312-E1 381 3,807 13.8/13.8 412/234 6.3/12.0 249/66
787 39/207
312-E2 254 2,675 13.0/13.8 285/205 10.2/12.0 184/184
495 41/177
312-E3 450 3,625 12.3/8.2 120/120 6.8/4.5 43/41
34.5/40
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 221 OF

8.2Tower Summary

8.2.1Vent gas wash tower (312-V9)(Figure 8-30)


The Vent Gas Wash Tower is a cylindrical tower, with a packed bed of 19 mm (3/4
inch) diameter carbon Raschig rings, to remove HCI and chloride from the
regeneration vent gas. The tower is constructed of carbon steel. A combined stream of
caustic and regeneration vent gas enters through a nozzle near the bottom of the tower.
A distributor located above the packed bed insures that the packed bed remains wetted
with caustic. A spray nozzle, located below the packed bed, insures that the bottom of
the packing is wetted, and provides a shower of caustic for the regeneration gas to pass
through. The caustic, after contacting the regeneration gas collects in the bottom of the
tower where it exits to the Caustic Circulation Pump. After the pump a drag stream of
spent caustic is removed and fresh caustic and condensate is injected. The circulating
caustic then returns to the Venturi Scrubber and the two caustic inlets to the Wash
Tower. The strength of the circulating caustic is monitored by an in-line pH meter.

The regeneration gas passes through the packed bed where it is scrubbed of HCI and
chlorine. The scrubbed gas then passes through a mesh blanket, located at the top of
the tower, which serves as a demister pad. The gas exits the tower through a nozzle in
the top head and is vented to atmosphere. A spray nozzle, located below the mesh
blanket, provides for intermittent washing of the mesh with clean steam condensate. A
pressure differential indicator across the mesh blanket indicates the build up of caustic
salt on the mesh, and signals the need for condensate washing to dissolve the salt.

Tower over pressure protection is provided via a gas bypass outlet nozzle. If pressure
in the tower builds up too high the liquid inventory in the bottom will be pressured out
to a safe location, and the gas bypass outlet will be uncovered. This bypass allows for
the regeneration gas to bypass the packed bed and exit directly to the atmospheric
vent.

Access to the tower for inspection, internals installation, and rashig ring loading is
provided by a manway in the top head of the tower. A rashig ring unloading nozzle is
provided in the tower wall located near the bottom of the packed bed. An additional
manway is provided at the tower bottom for access to the region below the packed bed.

8.3Drum Summary

8.3.1Nitrogen seal drum (312-V7)(Figure 8-4)

The Nitrogen Seal Drum and its internals are made of Carbon Steel. Catalyst enters at
the top of the Seal Drum into a gas disengaging zone (used primarily for Catalyst
Change-out on the Fly). The catalyst then passes through a standpipe into a purge zone
and then out of the vessel. Nitrogen enters the purge zone and flows upward through
the standpipe and the catalyst bed in the disengaging zone then out the catalyst inlet.
Nitrogen also flows downward through the catalyst bed in the purge zone and out of
the catalyst outlet. The normal function of this vessel is to provide a Nitrogen addition
point clear of catalyst for the Regenerated Catalyst Isolation System (Nitrogen
Bubble), but serves an additional purpose for the optional Catalyst Change-out on the
Fly. During Catalyst Change-out on the Fly, the Nitrogen Seal Drum serves to receive
and purge air from fresh catalyst loaded into the unit. Fresh catalyst enters the seal
drum catalyst inlet via a Catalyst Addition Hopper and passes through the drum as
during normal operation. The difference is that the catalyst is added batchwise rather
than continuously. To facilitate the catalyst addition a catalyst level indicator is
provided to signal when the drum is ready to accept a load of fresh catalyst. The
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 222 OF

nitrogen flow path is also similar to normal operation except gas exits the vessel from
the top via the gas bypass nozzle rather than the catalyst inlet. The reason for this is
that during catalyst change-out the gas communication between the seal drum and the
Regeneration Tower is provided through this bypass line.

8.3.2Lock hopper (312-V8)(Figure 8-5)

The Lock Hopper and its internals are made of Killed Carbon Steel. The Lock Hopper
contains three separate zones – the Disengaging Zone, Lock Hopper Zone, and Surge
Zone.

Catalyst enters at the top of the Lock Hopper via a Restriction Orifice. This orifice
serves to limit the instantaneous catalyst withdrawal from the Regeneration Tower to
an acceptable rate. This allows for maintenance of a steady burn profile as the
catalyst is circulated through the unit. Below the Restriction Orifice are the three
catalyst zones. The top zone is called the Disengaging Zone, the middle zone is called
the Lock Hopper Zone, and the bottom zone is called the Surge Zone. The zones are
designed to operate together to transfer catalyst in small batches and to raise the
pressure surrounding the catalyst. All three zones operate under an environment of
Platforming booster gas, but at two different pressures. The Disengaging Zone
operates at nearly Regeneration Tower pressure, the Surge Zone operates at nearly
Regenerated Catalyst L-Valve Assembly (Reactor No. 1) pressure, and the Lock
Hopper Zone cycles between these two pressures. A pressure instrument indicates the
pressuring and depressuring of the Lock Hopper Zone.

The Disengaging Zone has two gas nozzles – an equalization nozzle for gases from the
Lock Hopper Zone and a vent nozzle equipped with a screen for venting excess gases.
The Lock Hopper Zone has one gas nozzle – an equalization nozzle equipped with a
screen that is for gases from the Surge Zone and to the Disengaging Zone. And the
Surge Zone has two gas nozzles – an equalization nozzle equipped with a screen for
gases to the Lock Hopper Zone and a nozzle for the makeup gas to the Lock Hopper.

Two nuclear level instruments – a high-level switch and a low-level switch – are
mounted on brackets outside the Lock Hopper Zone to control the unloading and
loading of the Lock Hopper Zone. Another nuclear level instrument is mounted on
brackets outside the Surge Zone to indicate the catalyst level in the Surge Zone.

For inspection purposes, there is one manway in the Surge Zone. Also, there are
inspection handholes to the bottom of the standpipe in each zone. The three sections of
the Lock Hopper are connected with dropleg flanges which can be opened as needed
for access.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 223 OF

8.3.3Disengaging hopper (312-V3)(Figure 8-11 and 8-12)

The Disengaging Hopper and its internals are made of killed carbon steel. The
Disengaging Hopper is a cylindrical zone with a elutriation pipe down the center at the
top. The spent catalyst lift line enters the side of the elutriation pipe, bends downward,
and ends as an open pipe. Catalyst and lift gas enter through the lift line and flow
down into the center of the elutriation pipe. Elutriation gas enters through a nozzle in
the side of the Disengaging Hopper and flows upward through the elutriation pipe.
Chips of catalyst and fines are carried with the gas out the top of the elutriation pipe.
The whole catalyst drops to the bottom of the Disengaging Hopper where it is a surge
inventory of spent catalyst for the Regeneration Tower. The whole catalyst pills exit
the Disengaging Hopper via eight outlet nozzles and associated transfer piping.

The Disengaging Hopper is sized to hold the excess catalyst from the reactors during
start-up. This excess is due to the catalyst bed density change with the commencement
of catalyst circulation. A nuclear level instrument is mounted on the outside of the
vessel to indicate the catalyst level. A gauging nozzle is provided for initial calibration,
and subsequent recalibration, of the nuclear level instrument. For inspection purposes,
there is one manway in the Disengaging Hopper.

8.3.4Catalyst addition funnel and catalyst addition lock hopper (312-V1/V5, 312-V2/V6)
(Figure 8-25 and 8-26)

The Catalyst Addition Funnel and Catalyst Addition Lock Hopper are designed for
adding fresh catalyst from drums into the Regeneration Section. This addition must be
done on an occasional basis to replace catalyst that is removed as fines from the
Regeneration Section by the Disengaging Hopper. The Funnel and the Lock Hopper
are fabricated from Type 304 stainless steel to prevent rusting. The screen inside the
funnel and the cover on top are intended to prevent any foreign objects from being
loaded into the Regeneration Section.

An addition funnel and lock hopper are specified for the optional Catalyst Change-out
on the Fly system. The specification for this equipment is the same as that for the
regular catalyst addition system.

8.4Reactor Summary

8.4.1Regeneration tower (312-R1)(Figure 8-1, 8-2 and 8-3)

The Regeneration Tower and its internals are made of Stainless Steel. The
Regeneration Tower contains five separate zones – the Burn Zone, Reheat Zone,
Chlorination Zone, Drying Zone, and Cooling Zone.

Catalyst enters the top of the Regeneration Tower via a number of symmetrical pipes.
The catalyst flows by gravity into the Burn Zone. The system is designed for uniform
catalyst flow into the Burn Zone.

The Burn Zone is an annular catalyst bed between a truly vertical outer screen and an
inwardly sloping inner screen. The outer screen is welded at the bottom to the vessel
wall of the Regeneration tower and it is connected at the top to the vessel wall by a
wire mesh. At the bottom of the outer screen where it is attached, there are a number of
horizontal slots to allow for free drainage of the area behind the outer screen. The wire
mesh atop the outer screen allows for some of the burn zone gas to enter the catalyst
bed from the top. This provides a seal gas flow to prevent catalyst fluidization. The
inner screen is attached at the top to the top head of the Regeneration Tower. At the
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 224 OF

bottom, the inner screen fits around guide vanes that prevent sideways movement. The
screens are designed for uniform gas flow and coke burning all around the Burn Zone.
Gas enters the Burn Zone through the inlet nozzle outside of the outer screen and it
exits through the outlet pipe at the top of the inner screen. Both screens are specially
made with smooth, vertical screen bars to minimize catalyst breakage and plugging.
But periodically these screens must be cleaned to ensure good gas flow through them.

The Reheat Zone is directly below the Burn Zone, and catalyst flows by gravity into it.
Like the Burn Zone except smaller, the Reheat Zone is a annular catalyst bed between
the outer screen and the inner screen. The zone is designed to preheat the catalyst
entering the Chlorination Zone with the hot outlet gases from the Burn Zone. It is
separated from the Burn Zone by a baffle located outside of and near the bottom of the
outer screen. The baffle is perforated by a number of small holes to allow for free
drainage of the area above the baffle. Gas enters the Reheat Zone through the inlet
nozzle outside of the outer screen and it exits upward inside the inner screen and into
the Burn Zone.

Inside the inner screen are special thermocouples to measure the temperature of the
regeneration gas at various points down the catalyst bed. These thermocouples are
inside thermowells that extend down from nozzles in the top head of the Regeneration
Tower. Except for the two thermocouples that measure the temperature in the Reheat
Zone, all the rest measure temperatures in the Burn Zone. These “bed” temperatures
give a very good indication of changes in the coke burning in the Burn Zone and
should be recorded on a regular basis. In addition to the above there is a single
thermocouple located at the catalyst exit of the Reheat Zone. This is referred to as the
Chlorination Zone thermocouple as it indicates the temperature at the gas outlet of the
zone. This temperature gives a good indication if there is any coke combustion in the
Chlorination Zone.

The Chlorination Zone is below the screens, and guide vanes direct the catalyst by
gravity flow into it. The Chlorination Zone is a cylindrical catalyst bed inside an
annular baffle that is attached to the wall of the Regeneration Tower. Gas enters the
Chlorination Zone from the Drying Zone through perforations in the plate separating
the two zones. The gas first enters an annular region defined by the vessel wall and an
annular baffle. At this point organic chloride is introduced to the gas via two chloride
distributors set 180º apart. The gas then enters the bottom of the cylindrical catalyst
bed where the chlorination of the catalyst occurs. The annular baffle is specially
designed to provide uniform gas flow down the outside of the baffle and up through the
catalyst bed. Gas exits the zone upward into the inside of the inner screen at the
Reheat Zone.

The Drying Zone is below the Chlorination Zone, and catalyst flows by gravity into it
through a conical funnel and a distributor. Like the Chlorination Zone, the Drying
Zone is a cylindrical catalyst bed inside an annular baffle. Gas enters the Drying Zone
through the inlet nozzle in the wall of the Regeneration Tower. The annular baffle is
specially designed for drying to provide uniform gas flow, down the outside of the
baffle and up through the catalyst bed. Gas exits the zone through the drying air outlet
nozzle in the wall of the Regeneration Tower above the catalyst bed, and the
aforementioned perforations in the plate separating the Drying Zone from the
Chlorination Zone. One air outlet is the inlet to the Chlorination Zone, where an
organic chloride agent is injected into the air, and enters the Chlorination Zone. The
other air outlet nozzle is a vent that exhausts excess drying air from the Regeneration
Tower through a control valve.

The cylindrical distributor leading to the Drying Zone is pierced in four locations by
vapor tunnels. These tunnels allow for vapor communication between the area
enclosed by the distributor and the area outside the distributor. This communication is
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 225 OF

important to ensure even gas distribution across the cylindrical bed of the Drying
Zone.

The Cooling Zone is below the Drying Zone, and catalyst flows by gravity into it
through a conical funnel and a distributor. Like the Drying Zone, the Cooling Zone is a
cylindrical catalyst bed inside an annular baffle. Gas enters the Cooling Zone through
the inlet nozzle in the wall of the Regeneration Tower. The annular baffle is specially
designed for cooling to provide uniform gas flow down the outside of the baffle and up
through the catalyst bed. Gas exits the zone through a cooling air outlet nozzle in the
wall of the Regeneration Tower above the catalyst bed. The air exiting the nozzle is
routed, along with air from the Air Dryer, to the Air Heater to supply the Drying Zone.

As above, the cylindrical distributor leading to the Cooling Zone is pierced in four
locations by vapor tunnels. These tunnels allow for vapor communication between the
area enclosed by the distributor and the area outside the distributor. This
communication is important to ensure even gas distribution across the cylindrical bed
of the Cooling Zone.

For inspection purposes, access to the various zones is gained through the top of the
vessel via the Burn Zone gas outlet nozzle. The inside of the inner screen is accessible
immediately through the outlet nozzle. At the bottom of the inner screen, where the
catalyst guide vanes attach to a cylindrical support, there is a manway for further
access to the lower zones of the tower. Access to the Drying Zone and Cooling Zones
is achieved by the use of a removable cone in the center of the conical funnels.

8.5Fire Heater Summary

Not Applicable

8.6Exchanger Summary

8.6.1Electric heaters (312-H1, 312-H2, 312-H3 and 312-H4)(Figure 8-17 and 8-18)

Electric Heaters are used to heat up three gas streams: regeneration gas, drying air,
and reduction gas. These heaters are immersion type. The gas flows around the outside
of the heater bundle, which fills the process piping. The bundle sheaths contain
electrical elements. The bundle sheath temperatures are monitored by thermocouples
that shut down the heater on high temperature. Gas must be flowing across the bundle
during normal operation, or else the elements may overheat and burn up. The elements
have an unheated length that includes the portion of the bundle that does not see gas
flow. The terminal box is located a specified distance from the heater flange, and a
cooling baffle is added between the two, to minimize heat conduction to the box.

The Regeneration Heater is a single-bundle design. For the Air Heater and the
Reduction Gas Heaters, multiple bundles in series may be required because of duty
requirements.

8.6.2Regeneration cooler (312-EA1)(Figure 8-16)

The Regeneration Cooler cools the hot regeneration gas by removing the heat of coke
combustion. It is a single-pass, shell-and-tube exchanger. Hot regeneration gas flows
through the inside of the tubes of the Cooler and air is blown over the outside of the
tubes. The Regeneration Cooler Blower blows the air through the Cooler. The flow of
cooling air is controlled by a butterfly valve at the discharge of the Cooler Blower.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 226 OF

8.7Pump Summary

Centrifugal pumps are used to supply caustic to the vent gas washing. Proportioning
pumps are used to makeup condensate and caustic.

8.8Compressor Summary

8.8.1Regeneration blower (312-C3)(Figure 8-15)

The Regeneration Blower recycles the hot regeneration gas through the Regeneration
Tower. The Blower plug unit is a paddle-wheel fan inside an internally-insulated
housing. The seals are the multiple carbon-ring type and continuous nitrogen purging
is required and is controlled by a differential pressure regulator. The bearings are
lubricated by gravity-feed oilers that must be kept clean, free-flowing, and filled with
the manufacturer’s recommended lubricant at all times.

Motor of the Regeneration Blower is pole change type.

Low speed: 1500 rpm


High speed: 3000 rpm

Change over temperature from low speed to high speed is 250ºC - 300ºC.

When the regeneration gas temperature will reach 250ºC - 300ºC, change speed of
motor by the following procedure.

(1) Press the stop button on local switch board to make sure that ammeter is zero.

(2) Press the high button (low to high)

Press the low button (low to high)


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 227 OF

8.9Special Equipment Summary

8.9.1L-valve assemblies(Figure 8-6)

There are two L-Valve Assemblies, one at the base of each catalyst lift line, that
fluidize and transport catalyst using lift gas. The Spent Catalyst L-Valve Assembly
transports spent catalyst from the bottom of the Platforming reactor stack to the top of
the regeneration section. The Regenerated Catalyst L-Valve Assembly transports
regenerated catalyst from the bottom of the regeneration section back to the top of the
Platforming reactor stack.

Both L-Valve Assemblies are identical in most essential respects, including metallurgy
and geometry. Both assemblies are made of the same material as the catalyst lift pipe,
that is carbon steel. Catalyst enters the assembly via a vertical pipe and then reaches a
horizontal section. The horizontal section continues until it intersects the catalyst lift
line proper. The length of the horizontal section is such that the catalyst slope that
forms will not reach the lift line. Lift gas is supplied to the assembly at two locations.
The primary lift gas is introduced at the bottom of the lift pipe, and the secondary lift
gas is introduced at the side of the vertical pipe upstream of the horizontal section. At
both of the gas inlets, a screen is provided to prevent the catalyst from backing up into
the lift gas supply line. At the bottom of the lift pipe, a removable spool piece is
provided in order to facilitate clearing the lift pipe if catalyst slumps and can not be
lifted by the lift gas flow. The catalyst lift line temperature is measured with a skin
thermocouple.

The rate of catalyst lifting is set by the flow rate of secondary lift gas. As the rate of
secondary gas increases so does the catalyst lift rate. The secondary lift gas, in effect,
pushes the catalyst in the horizontal section into the primary lift gas flow and together
both lift gas flows transport the catalyst upward. For this reason, the dimensions and
orientation of the piping associated with the L-Valve Assembly are critical and must be
maintained as specified.

The L-Valve Assembly must be kept clean of debris, hydrocarbon liquid, or foreign
materials, because these can stop lifting. The removable spool piece allows the L-
Valve Assembly to be cleaned if needed.

8.9.2Lift lines(Figure 8-7, 8-8 and 8-9)

There are two lift lines that transport catalyst using lift gas. One transports spent
catalyst from the Spent Catalyst L-Valve Assembly to the top of the regeneration
section. The other transports regenerated catalyst from the Regenerated Catalyst L-
Valve Assembly to the top of the Platforming reactor stack.

To minimize catalyst attrition and minimize fluctuations in lift line pressure drop, the
construction of both lift lines is rigorous: directional changes are made with special
elbows; the number of elbows in the lift lines is minimized; the number of line joints is
minimized; only downward sloping runs are allowed; and the total length of the lift line
is minimized.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 228 OF

Lift line joints are of special construction. Except for one flange at the top of the
reactor stack, flanges are not allowed. Instead, pipe sections are joined together by one
of two fabrication methods. The preferred method employs a Dur-O-Lok coupling
assembly. The two Dur-O-Lok hubs are a machined pair. They match at the joint with
minimal gap and offset. The seal is self-energizing using an internal O-ring and an
external split coupler, held in position with set screws. Experience has shown a
significant reduction in catalyst attrition in regeneration units using this type of lift
pipe joint.

8.9.3Reduction zone(Figure 8-10)

Catalyst enters at the top of the Reduction Zone via the regenerated catalyst lift line.
The Reduction Zone vessel sits atop the reactor stack, and catalyst exits to the first
Platforming reactor directly below it via catalyst transfer lines. The Reduction Zone
actually consists of two zones, an Upper and Lower Reduction zone. Both zones are
cylindrical catalyst beds inside annular baffles that are attached to the wall of the
vessel.

Gas enters the Reduction Zone through two inlet nozzles in the wall of the vessel. The
upper reduction zone gas enters above the catalyst bed of the Upper Reduction Zone,
flows through the bed, and exits the vessel through a nozzle behind the annular baffle
of the Upper Reduction Zone. The annular baffle is specially designed for proper
disengagement of the reduction gas from the catalyst to prevent entrainment. The lower
reduction zone gas enters the vessel behind the annular baffle of the Lower Reduction
Zone. The annular baffle is specially designed for uniform gas flow down the outside
of the baffle and up through the catalyst bed. Gas exits the vessel through the same
nozzle as the upper reduction zone gas. The gas outlet nozzle, and the immediate
downstream piping, are set at an upward slope as an additional safeguard to prohibit
any entrained catalyst from leaving the vessel.

A nuclear level instrument is mounted on brackets outside the Reduction Surge Zone to
control the catalyst level of the entire Reactor stack, inclusive of the Reduction Zone.
This control is effected by indirectly controlling the rate of catalyst withdrawal from
the Reactor stack. Special thermocouples extend down from a nozzle in the top head of
the Reduction Zone and measure the temperature at various points in the catalyst bed
of the Lower Reduction Zone. Access to the Reduction Zone is provided by a manway
located in the Reduction Surge Zone.

8.9.4Dust collector (312-ME9)(Figure 8-13)

The Dust Collector removes catalyst chips and fines from the elutriation gas. The
elutriation gas enters the side of the Dust Collector, flows through filter elements
which is made by sintered stainless steel powder, and exits out the top. The catalyst
chips and fines collect on the elements and in the bottom head.

As the dust loading on the elements increases, the pressure drop across the elements
increases. When a differential pressure alarm sounds, the elements must be cleaned.
This is done while the Dust Collector is in service by reverse jet cleaning using
Nitrogen gas.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 229 OF

8.9.5Lift gas and fines removal circuit (Figure 8-14)

The Spent Catalyst L-Valve Assembly, the Disengaging Hopper, the Dust Collector,
the Fines Removal Blower, and the Lift Gas Blower make up the lift gas and fines
removal circuit.

This circuit begins at the outlet of the Dust Collector where a stream of filtered
nitrogen gas is routed to both the Fines Removal Blower, and the Lift Gas Blower.
Nitrogen from the Lift Gas Blower flows as lift gas to the Spent Catalyst L-Valve
Assembly to fluidize the catalyst and carry it up the lift line. Nitrogen from the Fines
Removal Blower flows as elutriation gas to the Disengaging Hopper, via the elutriation
gas flow control valve, to separate the fines from the whole catalyst in the elutriation
pipe. The whole catalyst drops into the bottom of the Disengaging Hopper, while lift
gas, elutriation gas, and fines leave the vessel through the upper end of the elutriation
pipe.

The circulating nitrogen gas stream leaving the Disengaging Hopper flows to the Dust
Collector for removal of the catalyst fines. The fines settle to the bottom of the Dust
Collector. From the bottom of the Dust Collector the catalyst fines and chips are
unloaded into a drum via the Fines Collection Pot. The Fines collection pot serves as a
lock hopper to transfer the fines from the Dust Collector pressure to atmospheric
pressure. Once filtered, the nitrogen gas flows out and the gas circuit is completed at
the suction of the blowers.

8.9.6Valves

There are four types of valves in the Regeneration Section: “V” valves, two types of
“B” valves, and “G” valves. Some of these are in automatic services, in which the
valve is equipped with an actuator that is controlled by the PPS&E Regenerator
Control System. Others are in manual services, and the valve is opened and closed by
hand.

Proper valve handling and maintenance is an important part of the operation of the
Regeneration Section. Leaking or poor-performing valves can lead to hazardous
situations and possibly cause a shutdown of the unit. It is very important that valves
be properly assembled before installing them in the unit. Valves must be properly
maintained and when valves start to leak, they should be repaired promptly and
correctly. Some valves require leak testing before installation in the field. Valves
should be protected from dirt and the elements when they are in the field and between
the field and the maintenance shop.

8.9.7V valves (Figure 8-19)

Whenever catalyst flow must be stopped, a special ball valve called a V-ball valve is
used. This valve is designed so that the shearing action between the ball and seat stops
catalyst flow without breaking many catalyst pills and without clogging. Although the
valve stops catalyst flow, it does not seal against gas flow.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 230 OF

This type of valve is used in several automatic services in the Regeneration Section for
on-off control. The valve body is Type 316 stainless steel, and the ball and seat are
Type 317 stainless steel with stellite facing.

Both the top and bottom valves in both Isolation Systems are V-ball valves. So is the
reactor isolation valve, which is located above the regular manual ball valve in the
catalyst transfer line from the reactors. The regular manual ball valves do provide a
gas-tight seal but are not intended to close on catalyst. So, when these lines must be
closed and blocked in, the V-ball valve is closed first to stop catalyst flow. Then, when
the line below is empty of catalyst, the regular manual ball valve is closed to stop gas
flow, if necessary.

A V-ball valve is also used as the first of two manual valves at two catalyst sample
connections, one at the outlet of the Disengaging Hopper and the other at the outlet of
the Nitrogen Seal Drum. Use of the catalyst samplers will be described in a later
chapter.

8.9.8B valves (Figure 8-20 and 8-21)

Regular ball valves or “B” valves are used to provide a gas tight seal. These valves are
not intended to close on catalyst. There are two types of “B” valves specified for the
Regeneration Section. One is the Neles-Jamesbury ball valve. This is a full bore ball
valve, with no reduction in flow area through the valve body and ball. So it can be
used in gas streams that contain catalyst dust, as well as in clean gas streams. A
Kamyr-Neles valve model is used for the two pressure equalization valves between the
zones of the Lock Hopper, where it is designed to exclude catalyst dust from the
sealing surfaces. For these two valves, the balls are Type 316 stainless steel with an
abrasion-resistant coating and the seats are stellite.

The other type of “B” valve is the McCanna ball valve. This is not a full bore valve
and it, or a Neles-Jamesbury valve, can be used in clean streams that do not contain
much catalyst dust. These services include the Chloride Valve, and, because fresh
catalyst contains few fines, the inlet and outlet valves of the Catalyst Addition hopper.
In these services, the valve seats are Teflon and the valve balls are stainless steel,
inconel, or chrome-plated, depending on the service.

Manual ball valves are used in several locations in the Regeneration Section.
Depending on the service, the specified valve may be Neles-Jamesbury or McCanna.
Likewise, the valve construction and metallurgy depends on the service.

8.9.9G valves (Figure 8-22 and 8-23)

A special Masoneilan “G” valve is used for gas-tight seals in vent services handling
nitrogen and possibly catalyst dust. The “G” valve is a globe valve with two seats, a
hard seat and a soft seat. When the “G” valve closes, the hard seat closes first, and a
short moment later the soft seat closes to complete the seal. Because of the impact-
resistance of the hard seat, these “G” valves are durable and leak-resistant during
normal operation. “G” valves are used for the vent valves at the Catalyst Addition
Lock Hoppers, and at the Fines Collection Pot.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 231 OF

8.9.10Oxygen analyzer (Figure 8-24)

The oxygen analyzer measures the oxygen concentration at the inlet of the Burn Zone.
The sample enters the analyzer through a probe, flows through the analyzer, and
returns to the Burn Zone in a closed loop. The analyzer must always have adequate
sample flow. A flow switch inside the analyzer will alarm if the sample flow is too low.
Without any sample flow, the analyzer will still display an oxygen concentration, but
the reading will have no relation to the actual oxygen concentration in the Burn Zone.

The calibration of the “zero” and “span” of the analyzer should be checked regularly.
The detector in the analyzer is a zirconium oxide cell and it measures the partial
pressure of oxygen in the sample. When the analyzer is calibrated, the cell must be at
its normal operating pressure.

8.9.11Hydrogen/hydrocarbon analyzer

The hydrogen/hydrocarbon analyzer detects contaminants in the CCR Nitrogen Header


to the Regeneration Section. If the sample of the CCR Nitrogen Header is
contaminated by either hydrogen or hydrocarbon, the high or low analyzer reading will
cause a contaminated nitrogen shutdown. Contamination of the CCR Nitrogen Header
is a serious hazard that should be corrected immediately. The analyzer piping is also
equipped with “quick disconnect” connections to allow periodic checking of the
circulating lift gas nitrogen purity.

The analyzer is calibrated to measure both hydrogen and hydrocarbon. When the
sample is pure nitrogen, the analyzer displays 50%. When the nitrogen is contaminated
with hydrogen, the analyzer indication increases – up to 100%. when the sample is
99% nitrogen and 1% hydrogen. When the nitrogen is contaminated with hydrocarbon,
the analyzer indication decreases – down to 0% when the sample is 85% nitrogen and
15% hydrocarbon.

For safety reasons, nitrogen to the CCR Nitrogen Header should come from an
independent source which is not connected to any other users.

8.9.12Air dryer (312-ME10)(Figure 8-27)

The Air Dryer is used to dry the air for the Cooling Zone and Drying Zone. It is a
packaged unit which uses a desiccant that absorbs moisture from wet air. There are
two desiccant chambers. Only one is in service while the other is reactivated using a
purge stream of the dry air product. During normal operation, a timing device switches
the chambers in and out of service.

The moisture content of the dried air must be checked regularly. There is a dew point
analyzer on the Air Dryer outlet. If the moisture content is above specification (5
vppm) (-49ºC), then the reactivation purge rate, the cycling sequence, and the
condition of the desiccant should be checked in accordance with the manufacturer’s
recommendations. Refer to the manufacturer’s instructions for additional information.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 232 OF

8.9.13Catalyst samples (Figure 8-28 and 8-29)

Catalyst sampler systems are used for sampling catalyst from the inlet line of the
Regeneration Tower, the outlet line of N2 Seal Drum, and the outlet of the Reduction
Zone.

The sampler systems around the Regeneration Tower consist of the sample pot, one V-
ball valve, two ball valves, and a needle valve. The sample pot is divided in two
sections by a restriction funnel. The top section includes the volume of the restriction
funnel and the transfer line. This volume fills with catalyst when the sample inlet
valves are opened. The bottom section is the collection area, and the catalyst drains
into this area before the sample pot is depressured and unloaded. The four valves in
the sampling system are intended to be opened and closed according to a specified
sampling procedure. The procedure helps ensure that a fresh catalyst sample is safely
obtained from the pressurized process line. The procedure also helps ensure that the
gas-tight ball below the V-ball valve is not damaged from opening and closing on
catalyst.

The reduced catalyst sampler system removes catalyst as it leaves the Lower
Reduction Zone. This system differs from the above in several mays. One important
difference is that it includes a sampling probe that extends into the flowing catalyst bed
to obtain a representative sample. Catalyst withdrawal is achieved with this system not
by gravity flow, but by a controlled depressurization of the sample probe. By opening
the sample probe up to the sample receiver, which is at a lower pressure than the
Reduction Zone, the probe pressure is lowered and catalyst is entrained with the gas
flowing to the receiver. The sampling procedure and the equipment are supplied by
UOP PIC.

8.9.14Vent gas scrubber (312-ME3)

The Venturi Scrubber is constructed of Hastelloy B-2 and is intended to educt the
regeneration vent gas and remove, by contacting with caustic, the small amount of
HCI and chlorine found in the gas. Caustic flows to the Venturi on a pressure control
signal from the regeneration gas line. The combined stream of caustic and regeneration
gas exit the Venturi Scrubber for further treatment in the Vent Gas Wash Tower.

8.10List of Instrument

Refer to “Instrument Schedule for Platforming Unit CCR Section” (S-312-1730-101)

8.11Summary of All Equipment’s Drivers

Summary of all the equipment drivers for this unit are also shown in Equipment List
(S-312-1224-101) under Rotary Machinery and Air Cooled Heat Exchanger.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 233 OF

8.12Control Valves

Summary of control valves are listed below. Refer to “SPECIFICATION FOR


CONTROL VALVE” (S-312-1374-101).

No. Service Action PID No.


FV-064 Lower Regeneration Gas to Reduction Gas Heater No.2 FC 115
FV-059 Upper Reduction Gas FC 115
PDV-066C Recycle Gas Purge to Reduction Zone FO 116
PDV-066B Reduction Zone Vent Gas Shutoff FC 116
PDV-066D Reduction Zone Vent Gas FC 116
FV-087 Spent Catalyst Secondary Lift Gas FC 119
FV-088 Spent Catalyst Primary Lift Gas FC 119
FV-110 Lift Gas Blower Spillback FO 119
PDV-089 Makeup Nitrogen FC 119
FV-102 Elutriation Gas FC 119
FV-119 Upper Combustion Air FC 120
FV-117 Air to Regeneration Tower Cooling Zone FO 120
FV-115 Regeneration Tower Cooling Zone Bypass FLO 120
TV-120 Air to Regeneration Cooler FO 120
PDCV-127 Regeneration Blower Seal Nitrogen Purge -- 121
PDV-160 Regeneration Tower Bum Zone Vent FLO 123
AV-144 Regeneration Tower Drying Zone Vent FLO 123
PDV-179 Nitrogen to Nitrogen Seal Drum FC 124
PDV-185 Booster Gas Lock Hopper Surge Zone FC 125
XV-027 Booster Gas to Lock Hopper Surge Zone FC 125
FV-195 Regenerated Catalyst Secondary Lift Gas FC 126
FV-196 Regenerated Catalyst Primary Lift Gas FC 126
FV-199 Condensate from Booster Gas Heater FC 126
PDV-066A Reduction Gas Shutoff FC 126
PV-202 Booster Gas to Booster Gas Coalescer FC 126
XV-204B Regeneration Tower Vent Gas Bypassing Vent Gas Wash FO 129
Tower
XV-204A Regeneration Tower Vent Gas to Vent Gas Wash Tower FC 129
FV-204 Circulating Caustic to Venturi Scrubber FO 129
LV-230 Condensate to Water Break Tank FO 127
XV-003 Catalyst Addition Hopper No.1 Vent FC 117
XV-011 Fines Collection Pot Vent FC 118
XV-019 Catalyst Addition Hopper No.2 Vent FC 124
XV-006 Nitrogen to Spent Catalyst Isolation Valves FO 117
XV-023 Nitrogen to Regenerated Catalyst Isolation Valves FO 125
XV-002 Catalyst Addition Hopper No.1 Pressure FC 117
XV-018 Catalyst Addition Hopper No.2 Pressure FC 124
XV-010 Elutriation Gas to Fines Collection Pot FC 118
XV-015 Nitrogen Purge to Regeneration Tower FO 120
XV-013 Air to Regeneration Tower FC 120
XV-014 Air Nitrogen Tie Line FC 120
PCV-354 Nitrogen to 312-V50 -- 121
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 234 OF

8.13Fired Heaters

Not Applicable

8.14Miscellaneous

Miscellaneous equipment for this unit are also listed in Equipment List (S-312-1224-
101).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 235 OF

FIGURE 8-1
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 236 OF

FIGURE 8-2
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 237 OF

FIGURE 8-3
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 238 OF

FIGURE 8-4
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 239 OF

FIGURE 8-5
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 240 OF

FIGURE 8-6
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 241 OF

FIGURE 8-7
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 242 OF

FIGURE 8-8
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 243 OF

FIGURE 8-9
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 244 OF

FIGURE 8-10
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 245 OF

FIGURE 8-11
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 246 OF

FIGURE 8-12
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 247 OF

FIGURE 8-13
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 248 OF

FIGURE 8-14
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 249 OF

FIGURE 8-15
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 250 OF

FIGURE 8-16
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 251 OF

FIGURE 8-17
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 252 OF

FIGURE 8-18
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 253 OF

FIGURE 8-19
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 254 OF

FIGURE 8-20
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 255 OF

FIGURE 8-21
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 256 OF

FIGURE 8-22
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 257 OF

FIGURE 8-23
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 258 OF

FIGURE 8-24
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 259 OF

FIGURE 8-25
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 260 OF

FIGURE 8-26
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 261 OF

FIGURE 8-27

AirDryer
Typical Arrangement

After Filter Prefilter

Drying Air Instrument


to Regenerator Air

Dew Point
Analyzer

Dessicant
Chambers
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 262 OF

FIGURE 8-28
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 263 OF

FIGURE 8-29
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 264 OF

FIGURE 8-30
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 265 OF

9FLOW PLANS AND PLOT PLAN

9.1PFDs MSD’s and P&IDs

Refer to the documents listed below.

“Process Flow Diagram”


( D-312-1223-101 ) Attachment 9.1
“Material Selection Diagram”
( D-312-1223-501 ) Attachment 9.2
“Piping and Instrument Diagrams”
( D-312-1225-101~103,115~129 ) Attachment 9.3

9.2Design Engineering , Utility and Safety Flow Plans

Refer to the documents listed below:

“Piping and Instrument Diagram” (Utility distribution)


( D-200-1225-141A~150 ) Attachment 9.4

“Area classification” ( D-200-1380-001 ) Attachment 9.5

“Fire Protection System Layout for Process Area”


( D-926-1225-003 ) Attachment 9.6

“Fire Extinguisher Layout for Process and Utility Area”


( D-926-1225-011 ) Attachment 9.7

“Arrangement of Gas Detectors for Process Area”


( D-926-1225-023 ) Attachment 9.8
“Arrangement of Fire Alarm System Equipment for Whole Refinery Area”
( D-926-1225-001 ) Attachment 9.9
“Layout for Whole Fire Protection System”
( D-926-1225-002 ) Attachment 9.10

9.3Plot Plan

Refer to the documents listed below:

“Plot Plant of Naphtha Hydrotreating Process Unit, Platforming Process Unit and
Platforming Process Unit CCR Section”
( D-200-1225-001 ) Attachment 9.11

9.4Safety Shutdown Function Charts

Refer to the documents listed below:

“The Cause and Effect Chart for Platforming Process Unit CCR Section”
( S-312-1371-401 ) Attachment 9.12
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 266 OF

10SAFTY

10.1Emergency Fire Plan

The fire protection system of the plant is designed to prevent fire occurrence, control
fire escalation, or extinguish fire within a short period of time, assuming there will be
no outside fire fighting assistance, with only one major fire at a time.

To prevent accidents it is of the utmost importance that all personnel be instructed


properly on the following subject;

- The tasks and responsibilities of the operators


- The methods to accomplish this in a safe manner.

The following safety regulations cover operations of particular concern to the


personnel responsible for the Naphtha Hydrotreating Process Unit. They are intended
to supplement any existing general refinery safety regulations which cover all units;
reference should be made to the latter for all points not mentioned below;. Mechanical
craftsmen working on a unit will be governed by their own departmental safety
regulations, but the operator should see that none of the following safety regulations
are violated by mechanical workers.

In addition to specifically defined rules and practices, the exercise of good judgment by
every person involved is essential to safe operation. An operator should be alert for
any situation which might present a personnel hazard. It should also be the
responsibility of each person familiar with the plant to warn other workers who enter
the plant of possible hazards they could encounter.

Refer to " Fire Protection System Layout for Process Area" ( D-926-1225-003 ) for
detail.

Also, Refer to " Fire Extinguisher Layout for Process & Utility Area " ( D-926-1225-
011 )

10.2Fire Fighting and Protective Equipment

Refer to “ FIRE PROTECTION SYSTEM LAYOUT FOR PROCESS AREA” ( D-


926-1225-003 ) for detail.

10.2.1 Fire alarm system

Refer to “ ARRANGEMENT OF FIRE ALARM SYSTEM EQUIPMENT FOR


WHOLE REFINERY AREA “ ( D-926-1225-021 ).

Also, Refer to “FIRE EXTINGUISHER LAYOUT FOR PROCESS & UTILITY


AREA” ( D-926-1225-011 )
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 267 OF

10.2.2Fixed water monitors

Provision for fixed water monitors shall be per “ LAYOUT FOR WHOLE FIRE
PROTECTION SYSTEM” ( D-926-1225-002). Fixed water monitors have an
effective nozzle range of at least 30 m and a discharge capacity of 1900 liter per
minutes. Monitors are arranged so that any equipment to be protected may be covered
by two fixed monitors with a radius of at least 30m. Monitors are located
approximately 15 m from the equipment being protected.

10.2.3Fire hydrants

The maximum distance between fire hydrants serving the process units shall be 50
meters or less as determined by the equipment served.

10.2.4Live hose reel stations

Heavy duty hose reels having 40 meters of 32 mm hard booster hose equipped with 28
mm couplings and contain straight stream/fog nozzle, shall be provided as means for
quick water application by one man.

10.2.5. Fixed water spray system

Fixed water deluge systems are provided around air cooled hydrocarbon exchangers
and hydrocarbon pumps. Application rate are 10.2 lpm/m2 for air fin exchanger and
20.4 lpm/m2 for pumps.

10.3Fire Protection

Refer to “ LAYOUT FOR WHOLE FIRE PROTECTION SYSTEM” ( D-926-1225-


002) for detail.

10.3.1Fire protection

Structure steel, Pipe racks, Equipment Supports, main supports of heater are
fireproofed .( Refer to S-000-13B0-001 )

10.4Maintenance of Equipment and Housekeeping

Operating equipment should be checked frequently for signs of leakage, overheating,


or corrosion, so that unsafe conditions may be corrected before they result in serious
consequences. Unusual conditions should be reported at once.

Guard around moving shafts, coupling belts, etc., which have been removed for repairs
to the equipment must be replaced when repair work is completed.

Tools, pieces of pipe etc., should never be left lying on platforms or railings of
operation equipment where they can be knocked off and injure someone below.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 268 OF

Access to ladders and fire escapes must be kept clear. Waste material and refuse must
be put in proper locations where they will not offer fire or stumbling hazards.

Liquid spills must be cleaned up immediately. Blanket gas leaks with steam and
immediately report leaks for repair.

In the event of electrical equipment malfunction, notify the electrical department and
stay clear of the equipment until the electrician arrives.

Gas cylinders should be stored so that they cannot fall over. Guard caps must remain
in place over the valves of cylinders which are not in use.

Care should be taken when installing scaffolding to ensure that the wooden boards do
not contact hot equipment and that no part is allowed to impair free access on
operational equipment e.g. ladders, stairways, walkways or valves. Scaffolding should
be removed immediately on completion of the work in hand.

Switch pumps regularly when spares are provided. This will assure that the spare
pump will be ready when needed.

10.5Repair Work

Mechanical work around the operating unit must be kept to a minimum, and minimum
number of men should be used.

No mechanical work on the equipment is to be done without a properly authorized


work permit.

Safety hats must be worn by all personnel in all areas at all times.

No burning, welding, open fires, or other hot work shall be allowed in the area unless
authorized by a work permit. Catch basins, manholes, and other sewer connections
must be properly sealed off to prevent leakage of gases which may ignite upon contact
with an open flame.

No personnel shall enter a vessel for any purpose whatsoever until it has been
adequately purged, blanked off, then tested to ensure freedom from noxious or
flammable gases and an entry permit issued.

When flushing equipment with a fire hose, the fire hose must be equipped with a check
valve to prevent backflow into the fire main.

Lines operating at low temperatures might fracture if unduly stressed; therefore, do not
physically strike these lines and avoid operating conditions which would cause water
hammer.

Do not use light distillates such as gasoline or naphtha to clean machinery or for any
other cleaning purposes.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 269 OF

Equipment should not be left open overnight. At the end of each day’s work, blanks or
spades should be installed to prevent entry of flammable materials due to valve let-by.

Welding cylinders should be placed in a designated safe area at the end of each
working day.

10.6Thermal Expansion in Exchangers

Because of serious accidents caused by thermal expansion of liquid trapped in


exchangers the following precautions is outlined in an effort to eliminate this hazard.

(1) When the cooler side of an exchanger is to be bypassed while hot material is
passing through the other side, the drain or vent should be checked before
bypassing to see that it is not plugged.

(2) When the exchanger is bypassed, the bleeder or vent should be arranged such
that the pressure can dissipate to a suitable place

(3) Warning signs should be installed on all exchangers where it is possible to block
in the cold side of an exchanger while hot liquid is going through the other side.

10.7Withdrawal of Samples

Samples shall be withdrawn from the unit by authorized personnel only.

Protective equipment, face masks or goggles, and suitable gloves must be worn for
sampling liquids or solids. A container must never be filled to the brim in order to
minimize risk of subsequent spillage.

When sampling any product liquids, gloves and goggles will be worn.

When sampling any material, gas or liquid, the sampling line must be flushed long
enough to remove dormant materials to insure that the sample obtained represents the
current stream. Pass enough gas through the sample vessel to insure the displacement
of the purge gas and to adjust the temperature of the sampler so that the composition is
not distorted by condensation or flashing, etc. Then the sample composition is
representative of the source material, undistorted by flash vaporization. Certain
classes of samples may require inert atmospheres , cooling or special carrying devices.
Wear approved personal safety equipment and exercise caution to avoid injuries.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 270 OF

The following operating instructions are general guideline for sampling system type 8-
133 and 8-134. Refer to “Specification for Closed Sampling System” (S-000-1360-
191) for drowing of 8-133 and 8-134.

(1) Sampling system type 8-133

a. Cylinder should be cleaned, passivated and filled with nitrogen to 2.1


kg/cm2g (30 psig). (alternately, cylinder can be partially emptied at
laboratory and returned to the same sample location for purging).

b. insure that valves A and C are closed.

c. Slowly open valves B and D. Both pressure gauges should indicate relief
header pressure. Warning: Do not disconnect hose if pressure is greater
than 3.5 kg/cm2g (50 psig).

d. Disconnect hose at quick connect on inlet manifold.

e. Place cylinder into cylinder support bracket and slip into the quick connect
on the inlet manifold.

f. Connect hose to the upper quick connect on the cylinder.

g. Close valves B and D.

h. Open valves E and F.

i. Slowly open valve A. Pressure gauge on inlet manifold should rise quickly
to operating pressure. Pressure gauge on outlet manifold should follow
quickly. If not, line is obstructed and should be safely repaired.

j. Slowly open valve C until pressure gauge on outlet manifold indicates a


slightly lower pressure than the inlet manifold pressure gauge. Let sample
flow through cylinder for a sufficient amount of time to obtain a
representative sample.

k. Close valve C.

l. Close valve A.

m. Close valves E and F.

n. Slowly open valves B and D. Both pressure gauges should indicate relief
header pressure. Warning: Do not disconnect cylinder if pressure is greater
than 3.5 kg/cm2g (50 psig).

o. Disconnect hose at upper quick connect on cylinder.


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 271 OF

p. Remove cylinder by disconnecting quick connect on the inlet manifold.

q. Connect hose to quick connect on inlet manifold.

r. Sample shall be taken to laboratory and emptied as soon as possible.


Extreme care must be exercised in transportation and storage of full
cylinders to avoid cylinder temperature increase which can result in a
hazardous high internal cylinder pressure.

CAUTION: When taking samples containing H2S or other toxic chemicals. An


air mask shall be worn at all times. Follow normal safety procedures when handling
H2S or other toxic chemicals.

(2) Sampling system type 8-134

a. Cylinder should be cleaned, passivated and filled with nitrogen to 2.1


kg/cm2g (30 psig). (alternately, cylinder can be partially emptied at
laboratory and returned to the same sample location for purging).

b. insure that valves A and C are closed.

c. Slowly open valve B. Both pressure gauges should indicate relief header
pressure. Warning: Do not disconnect hose if pressure is greater than 3.5
kg/cm2g (50 psig).

d. Disconnect hose at quick connect on inlet manifold.

e. Place cylinder into cylinder support bracket and slip into the quick connect
on the inlet manifold.

f. Connect hose to the upper quick connect on the cylinder.

g. Close valve B.

h. Open valves E and F.

i. Slowly open valve A. Pressure gauge on inlet manifold should rise quickly
to operating pressure. Pressure gauge on outlet manifold should follow
quickly. If not, line is obstructed and should be safely repaired.

j. Slowly open valve C until pressure gauge on outlet manifold indicates a


slightly lower pressure than the inlet manifold pressure gauge. Let sample
flow through cylinder for a sufficient amount of time to obtain a
representative sample.

k. Close valve C.

l. Close valve A.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 272 OF

m. Close valves E and F.

n. Slowly open valve B. Both pressure gauges should indicate relief header
pressure. Warning: Do not disconnect cylinder if pressure is greater than
3.5 kg/cm2g (50 psig).

o. Disconnect hose at upper quick connect on cylinder.

p. Remove cylinder by disconnecting quick connect on the inlet manifold.

q. Connect hose to quick connect on inlet manifold.

r. Sample shall be taken to laboratory and emptied as soon as possible.


Extreme care must be exercised in transportation and storage of full
cylinders to avoid cylinder temperature increase which can result in a
hazardous high internal cylinder pressure.

CAUTION: When taking samples containing H2S or other toxic chemicals. An


air mask shall be worn at all times. Follow normal safety procedures when handling
H2S or other toxic chemicals.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 273 OF

10.8Safe Handling of Volatile and Toxic Materials Including Catalyst

The safety rules given below are for the protection of life and limb, and the prevention
of property loss. It is expected that refinery people will exercise common sense,
alertness, and good judgment in carrying them out. If ever there is any doubt as to the
safety aspect of a particular operation, consult your supervisor immediately.

10.8.1Respiratory protection

Refer to “ ARRANGEMENT OF GAS DETECTORS FOR PROCESS AREA” ( D-


926-1225-023 ).

Most refinery gases, other than air, are harmful to human beings if inhaled in sufficient
concentration. Toxic gases may be classified as either asphyxiating or irritating.
Asphyxiating gases may cause death by replacing the air in the lungs or by reaction
with the oxygen carried in the blood; examples are hydrogen sulfide, carbon monoxide,
and smoke. Irritating gases may cause injury or death not only by asphyxiating but
also byinternal and external burnins. Examples are chlorine and sulfur dioxide.

To guard against the inhalation of harmful gases:

(1) Secure a gas test certificate showing the gas condition of the vessel is safe for
entry.

(2) Stand on the windward side of an operating unit from which gases escape.

(3) Provide proper ventilation.

All personnel should become familiar with the accepted method of artificial respiration
in order to render assistance to any one overcome by gas, electric shock, or drowning.

If anyone is overcome by gas, his rescuer should:

(1) Never attempt a rescue unless an assistant is standing by.

(2) Protect himself before attempting a rescue by wearing breathing apparatus.

(3) Get the victim to fresh air as soon as possible.

(4) Give artificial respiration and send his assistant to call for medical aid.

(5) When using a breathing apparatus, be sure that the mask fits the face properly.
Test it by the approved test method.

(6) Wear the correct type of breathing apparatus, suited to the situation encountered.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 274 OF

Breathing Apparatus (BA)

There are four types of breathing apparatus in general refinery service. They are the
canister type mask, the fresh air hose line BA. The compressed air self-contained BA
and the compressed air line trolley BA.

a. The canister type mask utilizes a filter element to absorb the poisonous gas from
the air and is used only by personnel working at the TEL/TML building off/on
loading.

Use this mask only in the open air or where the gas concentration is less than 2%,
not in a tank or other confined space. A canister type mask does not protect the
user against a deficiency of oxygen. A lifeline should be used in questionable
locations.

When a seal is removed from a canister, mark the date on the canister, and after
one year discard it regardless of how little it has been used.

A record of the amount of time that the canister has been used must be kept on a
tag attached to the canister. Do not exceed the permissible time limit for the
particular canister being used. Inform Safety Department when time limit is
near.

b. The fresh air hose line breathing apparatus has a length of air hose though which
the wear draws in the air required for respiration.

When a man must enter a tank, sewer, or other confined area where the
atmosphere is 20% or more of the lower explosive limit, or contains evidence of
hydrogen sulfide or other toxic materials, a fresh air breathing apparatus must be
used. It is to be used subject to the following conditions:

i. The free end of the air hose line must be placed where only fresh air can
enter it, but not more than 100m of hose should be used.

ii. A life belt and rope should always be used with the end fixed so that it will
not fall back into the tank or sewer.

iii. Be sure that the harness is buckled close to the wearer’s body so that it will
not slip over his shoulders if a rope rescue is necessary.

c. The compressed air self-contained breathing apparatus has a self-contained air


supply carried on the back of the user. It is one of two of the four types that is
completely independent of outside air.

It is used principally in emergencies.

After use, always notify the proper department so that they can recharge the
cylinders as soon as possible.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 275 OF

d. Compressed air line trolley breathing apparatus. This breathing apparatus is also
completely independent of outside air. It is principally used where the fresh air
line breathing apparatus would be unsuitable.

10.8.2Corrosive materials

Whenever containers of corrosive chemicals such as ammonia, chlorine, caustic soda,


sulfuric acid, etc., are to be opened or emptied, always have a connected water hose
handy to flush off and help absorb spilled material and to reduce spread of toxic
vapors.

10.8.3Poisonous gas

A matter of utmost concern for all operating personnel is the presence of H 2S in


streams.

Refer to “ ARRANGEMENT OF GAS DETECTORS FOR PROCESS AREA” ( D-


926-1225-023).

10.8.3.1Hydrogen sulfide (H2S)

H2S is a colorless gas slightly heavier than air (it accumulates in low spots- beware!).
It is highly flammable and a dangerous fire risk. Hydrogen sulfide is an explosive gas
which will explode in concentrations of 4.3% (3.4% at 300F) to 45% by volume in air.
Hydrogen sulfide explosions are most likely to occur in the vapor space over liquid
sulfur, because as liquid sulfur is cooled or agitated, it evolves H2S into the vapor
space above it. Such vapor exists above the liquid sulfur in the sulfur pit, which must
be swept with air to prevent a buildup of H 2S to explosive. H2S is easily identified in
very low, non-fatal concentrations (0.13 ppm) by the strong pungent odor of rotten
eggs. However, since H2S deadens your sense of smell, do not rely on its odor to warn
you of its presence in lethal concentrations.

NOTE: H2S is extremely poisonous, (more poisonous than the hydrogen cyanide
gas used in the “gas chambers”) and breathing any concentration must be avoided.
Symptoms of poisoning vary with the concentration and length of exposure.

H2S is present in the the stripper overhead system and in many lines and vessels in the
plant.

NOTE: H2S leaks should never be approached without self-contained breathing


gear and a stand-by man in position with the breathing gear.

H2S monitors have been provided to detect H2S leaks in particular areas of moderate
to high concentrations. Become familiar with the location of this safety equipment and
its operation.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 276 OF

Precautions to Avoid Danger from Hydrogen Sulfide Gas

Working in any concentration of hydrogen sulfide is not desirable. Where necessary,


work can be done for an eight-hour period with a concentration up to 10ppm (0.002%)
by volume in air, provided that continual checks are made by a qualified gas tester
using an approved H2S Gas Detector. Under no circumstances should anyone work in
concentration greater than 10 ppm without proper respiratory equipment and the
approval of a supervisor.

Because of the dangerous release of hydrogen sulfide gas, the following precautions
must be strictly observed:

(1) Do not work or permit anyone to work in an area suspected of containing a


concentration of hydrogen sulfide gas without first having the area tested by a
qualified gas tester, using an approved H2S detector.

(2) Report at once any leakage of gas or any gaseous areas as soon as discovered.

(3) Keep out of gaseous areas and keep others out.

(4) Stay on the windward side of the area as long as the condition exists.

(5) When necessary to vent equipment containing hydrogen sulfide or hydrogen


sulfide bearing material, use a vent or relief system, if provided. Avoid venting
this gas directly to the atmosphere.

(6) Maintain adequate ventilation of any enclosed space where leakage of gases
might occur.

(7) If it should be necessary, in an emergency, to enter an area where there is any


possibility of hydrogen sulfide gas being present, particularly in enclosed
locations where the gas could accumulate, use a Scott Air-Pak. Have a man
standing by in a safe location equipped with a breathing apparatus and, if
necessary, use a life line.

Principles for Emergency Action

If any emergency situation develops due to escaping hydrogen sulfide gas, observe the
following principles for safety:

First get out and warn all others to stay clear of the hazardous areas.

Do not attempt to rescue anyone unless you are wearing breathing gear. Your first duty
is to summon help before attempting a rescue.

Do not, under any circumstances, try to determine the concentration of hydrogen


sulfide as by it’s odor. If it’s presence is suspected, have the location tested with an
approved Hydrogen Sulfide Gas Detector.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 277 OF

In case a man is over come, summon help, get him into the fresh air at once, and begin
artificial respiration, using an inhalator if available. Summon a doctor as soon as
possible. But do not stop artificial respiration.

Any person overcome by gas must be kept warm, even during artificial respiration.
Use anything available which may be suitable for this purpose, such as emergency
blankets, coats etc. When the patient has recovered and can be safely moved, he must
be set to the hospital by ambulance and never allowed to stand until released by the
doctor.

10.8.3.2Nitrogen

N2 is neither poisonous nor flammable, but care must be exercised when working
inside equipment that has been N2 purged. Adequate ventilation must be provided and
appropriate breathing devices worn. To breathe an atmosphere high in N2, could result
in suffocation.

Before entering vessels that have been purged with N 2, a check must be made for
proper oxygen content prior to entry. Rapid vaporization of liquid nitrogen can cause
severe burns on contact with the skin.

10.8.4Aromatic hydrocarbons

(1) Benzene

Benzene is present in the Platforming process. Benzene is extremely toxic. A summary


of health effects which can occur from exposure to benzene appear in “Documentation
of the Threshold Limit Values (Benzene), 4th edition, 1980, ACGIH” included at the
end of this chapter.

Special Instruction: The clothing (including gloves, shoes) becomes contaminated with
benzene, the clothing should be removed immediately. Wash any skin area benzene
with soap and water. Take a complete bath if the body is wetted with benzene. Do not
wear clothing that has been wet with benzene until the garment has been
decontaminated by washing or dry cleaning. Wearing clothing that has been wet with
benzene almost assures that the person will inhale benzene vapors over a long period
of time, resulting in potential health hazards.

Avoid draining benzene to the concrete or into the sewers where it can vaporize and
create a health hazard. The benzene is accidentally spilled, flush it from the concrete
and sewer catch basin with large quantities of cold water. Do not use hot water or
steam which increases the vaporization of benzene. If you must enter an area of high
benzene vapor concentration, wear appropriate respiratory protection, such as self-
contained breathing apparatus or an air mask with an external air supply.

Though not specifically a health hazard, an environmental problem can result from
benzene entering the sewer since benzene is much more soluble in water than any other
hydrocarbon. This places an extra load on the effluent treating system.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 278 OF

(2) Toluene, Xylenes and Heavier Aromatics

These aromatic compounds are also present in the Platforming process. These
compounds are moderately toxic and are believed to not have the destructive effect on
the blood-forming organs as does benzene. If clothing (including gloves, shoes, etc.)
becomes wet with such aromatics, remove the clothing, bath and put on fresh clothing.
Avoid breathing aromatic vapors. The NIOSH Occupational Health Guidelines for
ethyl benzene, toluene and xylene are included at the end of this chapter.

(3) Toxicity information

Toxicity and safe handling information on most of the materials used in the unit can be
found in the following references:

(a) Dangerous Properties of Industrial Materials


N.Irving Sax
Van Nostrand Reinhold

(b) Patty’s Industrial Hygiene Toxicology


Craley and Craley, eds., 1979

( c) ASTM D-270, “Standard Method of Sampling Petroleum and Petroleum


Products.”

(d) Data Sheet D-204 "Xylene and Toluene.” Published by the National
Safety Council.

(e) Data Sheet D-308 “Benzene.” Published by the National Safety Council.

(4) Minimizing Exposure to Aromatics

Operating and laboratory personnel involved in obtaining samples should wear


chemical-type safely goggles or shield, protective apron or laboratory coat solvent-
resistant gloves, and approved respiratory protective equipment where ambient
concentrations exceed allowable limits. This protective equipment is hot, however, a
substitute for safe working conditions, proper ventilation, safe sampling practices, and
proper maintenance of both operating and safety equipment. In all cases, skin contact
(especially eyes) and inhalation must be minimized.

Sampling liquid hydrocarbons always requires some care to limit personal exposure
and release to the atmosphere. Even greater care is needed when the liquid to be
sampled contains aromatic hydrocarbons, especially benzene. UOP’s current design
calls for flow-through sampling points which utilize closed sample containers
whenever aromatics are present.

In order to minimize vaporization, hot hydrocarbon streams must be routed through a


cooler before drawing a sample. In all sampling situations, the personnel involved
should be instructed to remain at arm's length from the sample container and to situate
themselves upwind of the container if at all possible. These simple precautions will
greatly minimize exposure to the hydrocarbon vapors.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 279 OF

(5) Medical Attention

The US NIOSH/OSHA guidelines attached for ethyl benzene, toluene and xylene set
forth recommendations for medical monitoring of personnel working in environments
where exposure to these materials can occur. UOP recommends that the
NIOSH/OSHA guidelines for medical monitoring be considered in development and
implementation of an occupational heath monitoring program for employees who may
be exposed to toluene, xylene and/or ethylbenzene.

OSHA has recommended the following medical monitoring for employees who may be
exposed to benzene:

Preplacement and quarterly examinations. including a history which


includes past work exposures to benzene or any other hematologic toxins,
a family history of hematological neoplasms, a history of blood dyscrasias,
bleeding abnormalities, abnormal function of formed blood elements, a
history of renal or liver dysfunction, a history of drugs routinely taken,
alcoholic intake and systemic infections; complete blood count including a
differential white blood cell count; and additional tests, where, in the
opinion of the examining physician, alterations in the components of the
blood are related to benzene exposure. (42 Federal Register 22516, 1977.)

UOP recommends that these guidelines be considered in development and


implementation of an occupational health monitoring program for employees who may
be exposed to benzene.

All new or current employees should be alerted to the early signs and symptoms
resulting from exposure to aromatics, and any workers experiencing such symptoms
should seek professional medical attention. In addition to the above, all employees
should be advised of the hazards involved and precautions to be taken

OSHA has established stringent maximum exposure levels for various chemicals, some
of which may be found in UOP catalysts. These exposure limits can be found in the
Code of Federal Regulations, Title 29, Chapter 17, Subpart Z, Section 1910.1000.
This information is also contained in NIOSH/OSHA Pocket Guide to Chemical
Hazards, DHEW (NIOSH) Publication No. 78-210.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 280 OF

10.8.5Catalyst (UOP Type R-134)

It is during periods of opening and cleaning equipment or in sampling that bodily


exposure to UOP Platforming Catalyst can occur and caution must be exercised.
Material Safety Data Sheets should be obtained from UOP the time of catalyst
supply and should be available to the operating personnel.

The major constituent of the UOP Platforming catalyst is alumina, which is not
currently listed by OSHA as a hazardous substance. These catalysts do contain other
constituents, in lesser amounts, which might present hazards to human health and/or
the environment if handled or disposed of improperly. It is the purpose of this safety
section to provide information and recommendations which will allow safe handling
and proper disposal of these catalysts.

Only the following fresh catalysts (R-11, R-12, R-14, R-16, R-18, R-19, R-50, R-51,
R-55, R-60, R-62) contain hydrogen sulfide.

Spent Platforming catalyst may also contain additional hazardous chemicals, such as:
arsenic, carbon, hydrocarbons, iron pyrites, iron sulfide, lead, and vanadium. The
toxic properties and exposure limit of the most hazardous of these chemicals follow:

HYDROGEN SULFIDE: Hydrogen sulfide is both an irritant and an asphyxiant.


The current OSHA permissible exposure limits are 20 ppm ceiling concentration and
50 ppm peak concentration for a maximum 10 minute exposure.

ARSENlC: Arsenic is a recognized carcinogen and can cause acute and chronic
toxicity. Symptoms of acute toxicity are somewhat dependent upon the route of contact
and can include (for ingestion or inhalation): irritation of the stomach and intestines,
with nausea, vomiting and diarrhea; liver damage; kidney damage; blood disturbances;
and allergic reactions. The OSHA 8-hour time weighted average exposure limit to
inorganic arsenic compounds is 10 micrograms per cubic meter of air.

The greatest potential for human exposure to catalyst materials comes from catalyst
dust during reactor loading, and from dust, fumes, and vapors during catalyst
unloading operations. For the unprotected worker, hazardous dust, fumes, and vapors
may be inhaled, ingested, or contaminate the eyes and skin.

OSHA has established stringent maximum exposure levels for various chemicals, some
of which may be found in UOP catalysts. These exposure limits can be found in the
Code of Federal Regulations, Title 29, Chapter 17, Subpart Z, Senior, 1910.1000.
This information is also contained in NIOSH/OSHA Pocket Guide to Chemical
Hazards, DHEW (NIOSH) Publication No. 78-210.

Handling Catalyst Spills and Deposited Catalyst Dust

Always wear a NIOSH-approved self-contained breathing apparatus or the


combination of toxic dust respirator-rubber frame eye goggles, protective clothing, and
gloves. Avoid cleaning methods which raise dust. Dispose of all catalyst wastes
properly in containers, which should then be labeled as to the contents and hazards.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 281 OF

Do not dispose of catalyst wastes in a public water system or in the normal solid
waste. Return material to supplier for metal recovery.

Handling UOP Catalysts Safely

UOP believes that the OSHA exposure limits to catalyst chemicals will not be
exceeded if proper handling procedures and worker protective clothing/safety devices
are used. UOP recommends that the following minimum safety procedures be
established and adhered to:

(1) Handle catalysts only in a well ventilated area.

(2) In areas where natural ventilation is insufficient, use local mechanical exhaust
ventilation.

(3) Wear a NIOSH-approved toxic dust respirator with full face-piece, protective
clothing, and gloves for normal catalyst handling operations.

(4) Reactor loading and unloading operations present extraordinary health risks.,
especially to personnel working in the reactor. During loading operations, large
quantities of catalyst dust may be generated. During unloading, the hazards
may include insert (nitrogen) atmosphere, toxic feedstock, product, or purge
materials present with the catalyst, or toxic forms of catalyst chemicals.
Personnel working in reactors should wear a supplied air respirator with a hood
or helmet, operated in a pressure-demand or other positive-pressure mode, or in
a continuous flow mode (NIOSH Respirator Code SAFE: PD, PP, CF). This
respirator should have a primary, secondary, and emergency supply of air. In
addition, personnel in the reactor should be equipped with safety harnesses and
safety lines for rescue and a means for visual, voice or signal line
communication with standby personnel, who should be strategically located
with suitable rescue equipment. The OSHA regulations concerning use of
respirators (29 CFR, Subpart 1, Section 1910.134) should be read and
thoroughly understood before undertaking to place personnel in reactors during
catalyst loading and unloading operations.

Protective clothing and all safety devices should be thoroughly decontaminated


after each use. Worn-out, broken or defective safety equipment and clothing
should be removed from service and repaired or replaced. Good personal
hygiene after handling a catalyst or being exposed to catalyst dust is an
essential part of a responsible catalyst safety program. Do not eat, drink, or
smoke in areas where the catalyst is being handled or where exposure to
catalyst dust is likely.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 282 OF

10.9Preparing for Entering Process Equipment

Anyone entering a vessel which may contain an inert or contaminated atmosphere must
follow safety precautions and rules which apply. The vessels may contain H2S or
other toxic material in addition to hydrocarbons.

Therefore, the following precautions should be included in the standard procedure.

(1) The vessels should be isolated by positive action, such as blinding, to exclude all
sources of hydrocarbon, fuel gas, steam, air, etc.

(2) The refinery safety officer and supervisory personnel will give their permission
for vessel entry after they have made the appropriate tests.

(3) Install an air mover outside the vessel to sweep away any vapors.

(4) The man entering the vessel must be equipped with a fresh air mask in proper
working condition, with a fresh air supply.

(5) There should be available and ready for immediate use and transfer to the man in
the vessel, a separate air supply which is independent of electrical power.

(6) The man entering the vessel should wear a safety harness with properly attached
safety line.

(7) If the work involves a large distance above the floor of the vessel, scaffolding or
support flooring must be built to prevent dangerous falls.

(8) There should be a spare fresh air mask complete with its own separate air
supply, to allow a second man to enter the reactor quickly in case of an
emergency. This spare equipment must be compact enough to allow the second
man to enter through the manway of the equipment.

The API publication “Guide for Inspection of Refinery Equipment” or the NIOSH
publication No. 87-113; “A Guide to Safety in Confined Spaces” can be referred to for
additional information on safety procedures for vessel entry and accident prevention
measures.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 283 OF

10.10Opening Equipment

Every line connecting to a nozzle on the vessel to be entered must be blinded at the
vessel. This includes drains connecting to a closed sewer, utility connections and all
process lines. The location of each blind should be marked on a master piping and
instrumentation diagram ( P&ID ), each blind should be tagged with a number and a
list of all blinds and their locations should be maintained. One person should be given
responsibility for the all blinds in the unit to avoid errors.

The area around the vessel manways should also be surveyed for possible sources of
dangerous gases which might enter the vessel while the person is inside. Examples
include acetylene cylinders for welding and process vent or drain connections in the
same or adjoining units. Any hazards found in the survey should be isolated or
removed.

Safe access must be provided both to the exterior and interior of the vessel to be
entered. The exterior access should be a solid, permanent ladder and platform or
scaffolding strong enough to support the people and equipment who will be involved in
the work to be performed.

Access to the interior should also be strong and solid. Scaffolding is preferred when
the vessel is large enough to permit it to be used. The scaffolding base should rest
firmly on the bottom of the vessel and be solidly anchored. If the scaffolding is tall,
the scaffolding should be supported in several places to prevent sway. The platform
boards should be sturdy and capable of supporting several people and equipment at the
same time and also be firmly fastened down. Rungs should be provided on the
scaffolding spaced at a comfortable distance for climbing on the structure.

If scaffolding will not fit in the vessel a ladder can be used. A rigid ladder is always
preferred over a rope ladder and is essential to avoid fatigue during lengthy periods of
work inside a vessel. The bottom and top of the ladder should be solidly anchored. If
additional support is available, then the ladder should also be anchored at intermediate
locations. When possible, a solid support should pass through the ladder under a rung,
thereby providing support for the entire weight should the bottom support fail. Only
one person at a time should be allowed on the ladder.

When a rope ladder is used, the ropes should be thoroughly inspected prior to each
new job. All rungs should be tested for strength, whether they be made of metal or
wood. Each rope must be individually secured to an immovable support. If possible,
a solid support should pass through the ladder so that a rung can help support the
weight and the bottom of the ladder should be fastened to a support to prevent the
ladder from swinging. As with the rigid ladder, only one person should climb the
ladder at a time.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 284 OF

10.11Working in Columns or Vessels

It is recommended that any man working in a vessel which has an inert or


contaminated atmosphere not be permitted to move too far away or into any tight
areas, such as through a fractionator tray manway. The reason for this precaution is
that should the man develop some difficulty while below a tray, for example, to a point
where he could not function properly or lose consciousness, it would be extremely
difficult for the surveillance team outside the vessel to pull the man up through the
small tray manway by use of the safety line.

Any one working in the bottom of the column or vessel should be aware of the hazard
of falling objects. Hard hats should be worn , but these will not provide total
protection against heavy objects. The workmen should be warned to pay attention, to
look, and listen. The maintenance supervisor should be careful when scheduling work,
to avoid having people in the bottom of the vessel when there is heavy work going on
at the top of the column or vessels.

A communication system should be provided for the manway watch so that they can
quickly call for help in the event that the personnel inside of the vessel encounter
difficulty. A radio, telephone, or public address system is necessary for that purpose.

10.12Entering Tanks, Drums or Other Vessels

Before entering a vessel, the refinery’s safety precautions should be observed. These
usually include the following: sampling the vessel for toxic vapors and oxygen
concentration, wearing a safety harness, and having an attendant outside the vessel.

An unattended vessel should never be entered

10.13Procedure for Removing Safety Valves

In general, PSV removing work shall be done at shutdown period of related equipment
covered by the PSV. If the work is done at on-stream, work permit should be given
authorized supervisors, both safety and operation. And in the case that PSV to be
replaced, at first spare PSV to be prepared after which set pressure is properly
adjusted on the testing facility.

Release car seal of isolation valves by using the device. Close both inlet/outlet
isolation valves and release fluid stored between isolation valves and PSV safely by
opening vent or drain valves if the vent and drain valves are provided.

Release PSV inlet/outlet flange to remove the PSV.

In the case that PSV to be replaced, after replacing PSV to new one, inlet/outlet
isolation valves, drain and vent valves to be set as it was, including car seal position.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 285 OF

10.14Work Permit Procedure and Work Permit Formats

Before entering the vessel, a vessel entry permit must be obtained. A vessel entry
permit insures that all responsible parties know that work is being conducted inside of
a vessel and establishes a safe preparation procedure to follow in order to prevent
mistakes which could result in an accident. The permit is typically issued by the safety
engineer or by the shift supervisor.

The permit should be based on a safety checklist to be completed before it is issued.


The permit should also require the signatures of the safety engineer, the shift
supervisor, and the person that performed the oxygen, toxic and explosive gas check
on the vessel atmosphere. Four copies of the permit should be provided. One copy
goes to the safety engineer, one to the shift supervisor, one to the control room, and one
copy should be posted prominently on the manway through which the personnel will
enter the vessel.

The permit should be renewed before each shift and all copies of the permit should be
returned to the safety engineer when the work is complete. Additional requirements or
procedures may be imposed by the refiner, but the foregoing is considered the
minimum acceptable for good safety practice.

10.15Operating Notes Relating HAZOP review

Refer to “HAZOP STUDY REPORT” S-312-1220-101, and “HAZOP ACTION


FOLLOW-UP LIST” S-312-1220-102.

Action Recommendation Ope. manual


No. Section No.
2. Highlight the electrical grounding for the catalyst fines 6.3.2.2.
drum in the operating procedure.
3. Include the HAZOP recommendation (Ensure that spectacle 2.2.4.
blind is closed position when catalyst replacement line is not
in use) in the operating procedure.
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 286 OF

10.16Material Safety Data Sheet (MSDS)

The MSDS requirement falls primarily on chemical manufacturers, importers and


distributors. The OSHA standard requires them to develop and provide a MSDS for
each hazardous chemical they produce or handle. These manufacturers, importers and
distributors are required to provide the MSDS to the purchasers of the hazardous
chemical.

Although the format of the MSDS can vary, they should all include the following
information:

Chemical and common name


Ingredient information
Physical and chemical characteristics
Physical hazards - Potential for reactivity fire and/or explosion
Health hazards
Symptoms of exposure
Primary route of likely entry into the body upon exposure
OSHA permissible exposure levels
Precaution for use
Waste disposal
Protective measures ad equipment, including during spills and maintenance
Emergency and first-aid procedures
Date of MSDS preparation and last revision
Emergency contact of manufacture or distributor

The Material Safety Data Sheets for the unit are shown in Attachment 10-1 (Later).
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 287 OF

11MISCELLANEOUS

11.1Conversion Tables

English - Metric Conversions and Abbreviations


Multiplied
English Unit Abbrev. By . Metric Unit Abbrev.

length inch in 25.4 millimeter mm


foot ft 304.8 millimeter mm

area square foot ft2 0.09290 square meter m2

volume cubic foot ft3 0.02832 cubic meter m3


standard cubic SCF 0.02826 standard cubic std m3
feet of gas* meters of gas
gallon gal 0.003785 cubic meter m3
barrel bbl 0.1590 cubic meter m3
O O
temperature degrees Fahrenheit F C=5/9(OF-32) degrees Celcius O
C

pressure pound per square inch psi 6.895 kilopascal kPa


inch of mercury at 32ºF in Hg 0.1333 kilopascal kPa
inch of water at 4ºC in H2O 0.2491 kilopascal kPa
pound per square inch psi 0.07030 kilograms per kg/cm2
square centimeter

mass pound mass lb or lbm 0.4536 kilogram kg

energy British Thermal Unit Btu 1.055 kiloJoule kJ

power horsepower hp 0.746 kilowatt kW


British Thermal Btu/hr 0.2931 watt W
Units per hour

*UOP calculates standard cubic feet of gas at 60º F and 14.696 psia. UOP proposes to calculate standard cubic
meters of gas at 15º C and 101.325 kPa.

11.2Summary of Precommissioning and Commissioning Procedure

Refer to S-000-1720-001

11.3Overall Start-up and Shutdown Outlines

Refer to S-000-1730-001
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 288 OF

11.4Offsite Systems

Not Applicable.

11.5Catalyst and Chemical Loading/ Unloading

11.5.1Catalyst Loading

Refer to Section 4.1.1.(21) for Catalyst Loading.

11.5.2 Catalyst Unloading and Reloading Procedures

Refer to Section 5.3.4. for Catalyst Unloading and Reloading Procedures

11.5.3Chemical Loading

Chemicals used for this unit consist of the chloride is injection to the Regeneration
Tower, 312-R1. Conduct for utilizing these chemicals are described as follows:

The chloride will be injected to the Regeneration Tower by the Chloride Injection
Pump, 312-P2A/B from the Chloride Storage Vessel, 312-V50.

Refer to the Catalyst and Chemical Summary (S-312-1223-502)

11.6Catalyst and Chemical Requirement

Refer to the Catalyst and Chemical Summary (S-312-1223-502)


Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 289 OF

11.7Analytical Plan

11.7.1Sample schedules

Recommended sampling requirements are provided in the table below. Test frequency
shown is a rough figure and will be optimized with experience in plant operation.

(1) Regeneration tower drying air (312-SN-01) (air)

Test Method Normal Start-up


Moisture (Dew point) Online analyzer -- --

(2) Spent catalyst (Regenerator feed) (312-SN-02) (catalyst)

Test Method Normal Start-up


Carbon UOP 703 3/W As req.
Chloride UOP 291 3/W As req.
Loss on ignition (LOI) UOP 275 As req. As req.
Size distribution UOP 333 (1) As req. As req.

(3) Regenerated catalyst (312-SN-03) (catalyst)

Test Method Normal Start-up


Carbon UOP 703 3/W As req.
Chloride UOP 291 3/W As req.
Loss on ignition (LOI) UOP 275 As req. As req.
Size distribution UOP 333 (1) As req. As req.

(4) Vent gas from wash tower (312-SN-04) (off gas)

Test Method Normal Start-up


HCl Detector tube As req. As req.

(5) Spent caustic (312-SN-05) (caustic)

Test Method Normal Start-up


pH pH meter 1/D 1/D
Total alkalinity UOP 210 1/D 1/D
Operation Manual for Platforming Process Unit 0-0800
CCR Section JGC DOC NO. S-312-1230-001
SHEET 290 OF

(6) Lift gas nitrogen (312-SN-06) (N2)

Test Method Normal Start-up


Composition ASTM D-1945 As req. As req.

(7) Fines drum (312-SN-07) (catalyst)

Test Method Normal Start-up


Size distribution UOP 333 (1) 1/W 1/W

(8) Reduced catalyst (312-SN-08) (catalyst)

Test Method Normal Start-up


Chloride UOP 291 As req. As req.
Loss on ignition (LOI) UOP 275 As req. As req.

Note (1) The apparatus of UOP 333 should be modified. The following U.S.
standard sieve series screens are required:

U.S. No. 14 0.056 inch opening


U.S. No. 16 0.047 inch opening
U.S. No. 18 0.039 inch opening
U.S. No. 20 0.033 inch opening
U.S. No. 30 0.023 inch opening

Eight-inch diameter screens are sufficient.

Vous aimerez peut-être aussi