Vous êtes sur la page 1sur 24

BRITISH STANDARD BS 8204-5:

1994

Screeds, bases and in


situ floorings —
Part 5: Code of practice for mastic
asphalt underlays and wearing surfaces

UDC 693.78.025.331:693.73
BS 8204-5:1994

Committees responsible for this


British Standard

The preparation of this British Standard was entrusted by Technical


Committee B/544 Plastering, rendering, dry lining, screeds and in-situ
flooring, to Subcommittee B/544/6 Screeds and in-situ floorings, upon which
the following bodies were represented:

Association of Lightweight Aggregate Manufacturers


British Aggregate Construction Materials Industries
British Resin Manufacturers’ Association
Building Employers Confederation
Chartered Institute of Building
Concrete Society
Contract Flooring Association
Department of the Environment (Building Research Establishment)
Department of the Environment (Property Services Agency)
Federation of Associations of Specialists and Subcontractors
Federation of Plastering and Drywall Contractors
Federation of Resin Formulators and Applicators (FeRFA)
Mastic Asphalt Council and Employers Federation
Mortar Producers Association
National Federation of Terrazzo-Marble and Mosaic Specialists
Scottish Master Plasterers’ Association
Society of Chemical Industry

This British Standard, having


been prepared under the
direction of Technical
Committee B/544, was
published under the authority
of the Standards Board and
comes into effect on Amendments issued since publication
15 December 1994

© BSI 03-1999
Amd. No. Date Comments

The following BSI references


relate to the work on this
standard:
Committee reference B/544/6
Draft for comment 93/106952 DC

ISBN 0 580 23079 1


BS 8204-5:1994

Contents

Page
Committees responsible Inside front cover
Foreword iii
1 Scope 1
2 References 1
2.1 Normative references 1
2.2 Informative references 1
3 Definitions 1
4 Exchange of information and time schedule 1
4.1 General 1
4.2 Exchange of information 1
4.3 Provision of utilities, facilities and materials 2
4.4 Time schedule 2
5 Materials and equipment 2
5.1 Mastic asphalt 2
5.2 Coarse aggregate 2
5.3 Separating membranes 2
5.4 Expanded metal lathing 2
5.5 Sand for rubbing 2
5.6 High bond primer 2
5.7 Float 3
5.8 Gauges 3
5.9 Mechanical asphalt mixer 3
5.10 Mastic asphalt cauldron 3
5.11 Heated dumper 3
5.12 Hot-charge transporter 3
6 Design 3
6.1 Selection parameters 3
6.2 Base to receive mastic asphalt 3
6.3 Mastic asphalt waterproofing 5
6.4 Drainage of floor areas (falls and channels to shed water) 5
6.5 Effects of temperature 5
6.6 Mastic asphalt 5
6.7 Special applications 7
6.8 Mastic asphalt details 7
6.9 Regulating courses 9
6.10 Tolerances on finished mastic asphalt flooring 9
6.11 Mastic asphalt underlay 9
6.12 Thermal and sound insulation 9
6.13 Movement joints 9
6.14 Slipperiness 9
7 Construction work on site 9
7.1 Work planning 9
7.2 Preparatory sitework prior to asphalting 10
8 Workmanship 10
8.1 Re-melting 10
8.2 Transport of molten material 10
8.3 Setting out 10
8.4 Placing the separating membrane 10

© BSI 03-1999 i
BS 8204-5:1994

Page
8.5 Laying the flooring 10
9 Protection 11
9.1 On completion of laying 11
9.2 Between completion of laying and hand-over 11
10 Inspection and testing of flooring 11
10.1 Inspection 11
10.2 Testing 11
11 Maintenance of mastic asphalt flooring 12
12 Repair of mastic asphalt flooring 12
Annex A (normative) Methods for the assessment of floor levels and
surface regularity 13
Annex B (normative) Determination of slip resistance value (SRV) 13
Annex C (informative) Characteristics of mastic asphalt 16
Figure 1 — Flooring and skirting for wet areas 6
Figure 2 — Drainage channel with light-duty grating 6
Figure A.1 — Slip gauges for checking surface regularity 13
Figure B.1 — Friction tester 14
Table 1 — Grades and thicknesses of mastic asphalt for underlays and
wearing surfaces for various uses 4
Table 2 — Treatments for vertical and sloping surfaces to receive
mastic asphalt 8
Table 3 — Classification of surface regularity for mastic asphalt
flooring and underlays 10
Table B.1 — Properties of the friction tester slider (soft rubber) 16
Table B.2 — Temperature corrections for SRV readings using soft
rubber slider 16
List of references Inside back cover

ii © BSI 03-1999
BS 8204-5:1994

Foreword

This Part of BS 8204 has been prepared under the direction of Technical
Committee B/544 Plastering, rendering, dry lining, screeds and in situ floorings.
It gives recommendations for mastic asphalt flooring in buildings applied, as an
underlay or as a wearing surface, to a concrete base or screed. Annex A and
Annex B give test methods for surface regularity and slip resistance respectively,
and Annex C gives some characteristics of mastic asphalt.
A well laid mastic asphalt floor of the correct grade provides a hard, durable
surface easily cleaned and not inherently slippery. It will carry heavy loads,
providing care is taken to avoid static or mobile loads which may cause
indentation. It is unaffected by water.
Mastic asphalt flooring is an adaptable material laid either as a wearing surface
or as an underlay for decorative floor finishes. When laid as a mastic asphalt
waterproofing membrane, it can be used in wet process areas or in areas where
washing down is a requirement.
BS 8204-5 is one of a series dealing with in situ floorings; the other Parts of
BS 8204 are as follows:
— Part 1:1987: Code of practice for concrete bases and screeds to receive in-situ
floorings;
— Part 2:1987: Code of practice for concrete wearing surfaces;
— Part 3:1993: Code of practice for polymer modified cementitious wearing
surfaces;
— Part 4:1993: Code of practice for terrazzo wearing surfaces.
An additional Part of BS 8204 dealing with cold setting resin wearing surfaces is
to be prepared.
BS 8204-5 supersedes section 4 (the last remaining section) of CP 204-2:1970.
Sections 5, 6 and 7 and Appendix A of CP 204-2:1970 have been deleted by
amendment and CP 204-2:1970 is withdrawn.
As a code of practice, this British Standard takes the form of guidance and
recommendations. It should not be quoted as if it were a specification and
particular care should be taken to ensure that claims of compliance are not
misleading.
A British Standard does not purport to include all the necessary provisions of a
contract. Users of British Standards are responsible for their correct application.
Compliance with a British Standard does not of itself confer immunity
from legal obligations.

Summary of pages
This document comprises a front cover, an inside front cover, pages i to iv,
pages 1 to 16, an inside back cover and a back cover.
This standard has been updated (see copyright date) and may have had
amendments incorporated. This will be indicated in the amendment table on
the inside front cover.

© BSI 03-1999 iii


iv blank
BS 8204-5:1994

1 Scope 4 Exchange of information and time


This Part of BS 8204 gives recommendations for the schedule
types and grades of materials, design and work on 4.1 General
site for in situ mastic asphalt for flooring applied as
Consultations and exchange of information between
a wearing surface or underlay, incorporating
all parties concerned with the building operations
waterproof membranes where required. The
should be arranged at an early date, so that each
standard is applicable to mastic asphalt applied hot
may have full knowledge of the particulars of the
to concrete bases and screeds and concrete
work and be able to cooperate in producing the
suspended floors. This Part of BS 8204 is intended
conditions required by the others to complete a
to be read in conjunction with BS 8204-1:1987.
satisfactory job.
2 References 4.2 Exchange of information
2.1 Normative references The designer should provide in good time all
relevant information to those responsible for laying
This Part of BS 8204 incorporates, by dated or
the flooring and to others whose work could be
undated reference, provisions from other
affected, including whichever of the following are
publications. These normative references are made
applicable:
at the appropriate places in the text and the cited
publications are listed on the inside back cover. For a) description, situation and address of site and
dated references, only the edition cited applies; any means of access;
subsequent amendments to or revisions of the cited b) those conditions of contract which could
publication apply to this British Standard only practically affect this particular work;
when incorporated in the reference by amendment c) location and area of floors to be covered;
or revision. For undated references, the latest
d) age and nature of the base and any preparatory
edition of the cited publication applies, together
treatment required;
with any amendments.
e) finished floor level and maximum permissible
2.2 Informative references
departure from datum;
This Part of BS 8204 refers to other publications
f) class(es) of surface regularity required for the
that provide information or guidance. Editions of
bases and the finished mastic asphalt flooring;
these publications current at the time of issue of this
standard are listed on the inside back cover, but g) type of damp-proofing;
reference should be made to the latest editions. h) type and thickness of screed, if any;
i) any work consequent upon services passing
3 Definitions through the flooring;
For the purposes of this Part of BS 8204, the j) treatment of skirtings;
definitions given in BS 6100-1.3.3:1987, k) treatment of junctions with adjacent floors and
BS 6100-2.4.1:1992 and BS 8204-1:1987 apply, floorings;
together with the following.
l) type of surface finish;
3.1
m) any special requirements related to underfloor
coat
heating;
single layer of mastic asphalt
n) date for the completion of preliminary work;
3.2 o) dates for the start and completion of various
rubbing sections of the floor;
process by which the last coat of mastic asphalt is p) details of any conformity testing required;
given a matt surface finish by the use of clean sand
q) requirements relating to samples of mastic
3.3 asphalt for testing purposes.
spreader
operative (craftsman) skilled in the laying and
finishing of mastic asphalt

© BSI 03-1999 1
BS 8204-5:1994

4.3 Provision of utilities, facilities and — grade II: light duty flooring;
materials — grade III: medium duty flooring;
To prevent misunderstanding, particularly at the — grade IV: heavy duty flooring.
tendering stage, and to avoid possible situations
Types F1076 and F1451 do not cover grades of
detrimental to installation, it should be made clear
mastic asphalt for special applications such as
who will be responsible for providing the following: chemical resistant, or spark free, flooring, for which
a) adequate clean, dry, lockable storage space, purposes proprietary variants are available, nor are
protected from frost (if necessary); they suitable for external applications such as
b) secure storage compound for gas bottles, loading bays, balconies and rooftop car parks for
having a fence not less than 2 m high; which paving grade mastic asphalt is specified in
c) adequate ventilation in confined areas; BS 1447:1988.
d) adequate artificial lighting, if required; For characteristics of mastic asphalt see Annex C.
e) provision of a suitable level site for the mixer or Mastic asphalt should be supplied cast into blocks
mixers, blocks of mastic asphalt, and where suitable for transporting and handling or delivered
relevant coarse aggregate, as close as practicable to the site ready for use in hot-charge transporters.
to the work; 5.2 Coarse aggregate
f) unloading and hoisting facilities, if required. Coarse aggregate for grade IV flooring should be
4.4 Time schedule clean igneous or calcareous rock or siliceous
material conforming to the limits given in Table 5 of
In considering the schedule, in addition to the usual BS 6925:1988.
intervals between commencement and completion of
work by the various trades involved, additional Coarse aggregate for paving grades should be
allowances should be made for the following: crushed rock conforming to the limits given in
Table 3 of BS 1447:1988.
a) installation of all doors and windows and
heating within the building, which is especially 5.3 Separating membranes
relevant to laying grade I flooring (see 5.1); The separating membrane should be one of the
b) laying of underfloor services; preferably this following:
should be completed before the base is formed, as a) glass fibre tissue of mass 50 g/m2 to 70 g/m2;
there is a risk of subsequent cracking if services b) black sheathing felt comprising a batt of jute
are embedded in the flooring; fibre impregnated with bitumen.
c) curing and drying of the base concrete before
5.4 Expanded metal lathing
the flooring is laid, where appropriate;
Expanded metal lathing should be one of the
d) cooling and hardening of the flooring;
following:
e) period of protection of the completed floor from
a) bitumen coated plain expanded metal lathing
damage by other trades, including restriction of
with an aperture size of not less than 10 mm in
access;
the short way of mesh direction and not
f) siting of plant. less than 0.46 mm thick;
b) zinc coated steel, grade G 275 expanded metal
5 Materials and equipment
lathing conforming to reference number L 2 of
5.1 Mastic asphalt BS 1369-1:1987, suitably primed;
The mastic asphalt should be one of the following: c) stainless steel, grade 304 S15 expanded metal
a) mastic asphalt for flooring conforming to lathing conforming to reference number SL 1 of
type F1076 of BS 6925:1988; BS 1369-1:1987.
b) coloured mastic asphalt for flooring conforming 5.5 Sand for rubbing
to type F1451 of BS 6925:1988; Rubbing sand should be clean sand from natural
c) mastic asphalt for paving conforming to deposits, predominantly passing a 600 4m test sieve
BS 1447:1988; and retained on a 212 4m test sieve, both
d) mastic asphalt for waterproofing conforming to conforming to BS 410.
type R988 or type T1097 of BS 6925-1988. 5.6 High bond primer
Types F1076 and F1451 mastic asphalt for flooring A high bond primer, which is a modified synthetic
are graded according to usage as follows: rubber latex emulsion, should be used for
— grade I: special hard flooring; application to vertical surfaces to provide a key.

2 © BSI 03-1999
BS 8204-5:1994

5.7 Float g) the use of any wheeled conveyances,


A float, which is a flat-faced wooden tool with a e.g. fork-lift trucks, trolleys, their loading, rates
handle, should be used for spreading and finishing of travel, type and width of tyre;
the surface of the mastic asphalt. h) the weights of standing loads, their bearing
5.8 Gauges area and any point loading;
i) the anticipated ambient temperature within
Gauges, comprising wood or metal strips of required
the building;
thickness, should be used as temporary boundaries
to bays or elsewhere, to assist the spreader in laying j) maximum and minimum temperatures, and
the mastic asphalt. any other conditions likely to affect the
performance of the flooring either during laying
5.9 Mechanical asphalt mixer or in service;
A mechanical asphalt mixer, which is a mobile k) any exposure of the mastic asphalt to acids,
container, fitted with heating and powered stirrers oils, greases or other substances and their
to provide mechanical agitation, should be used for concentration and temperature;
the purpose of remelting mastic asphalt prior to
l) details of mastic asphalt flooring surface
laying.
required, e.g. slip resistance or need for ease of
5.10 Mastic asphalt cauldron cleaning;
As an alternative to a mechanical asphalt mixer, a m) details of floor finishes to be applied to a
mastic asphalt cauldron, which is a cylindrical steel mastic asphalt underlay and the adhesive to be
vessel fitted with a fire-box, may be used at the site used.
for the purpose of remelting mastic asphalt prior to The effects of some of these factors are interrelated,
laying. Generally, a mastic asphalt cauldron is not e.g. loads and temperatures. For specific conditions,
mechanically agitated. advice should be sought from the mastic asphalt
5.11 Heated dumper manufacturer.
A heated dumper truck with an insulated container A guide to the selection of the appropriate grade of
and mechanical agitation should be used for the flooring and recommended thicknesses is given
transportation of molten mastic asphalt to the point in Table 1.
of laying. 6.2 Base to receive mastic asphalt
5.12 Hot-charge transporter 6.2.1 General
A hot-charge transporter fitted with a heater and Surfaces to which mastic asphalt is to be applied
mechanical agitation should be used for delivery of should be installed or prepared so as to have a true
ready-for-use mastic asphalt to site. and even surface substantially free from
irregularities such as abrupt changes in levels,
6 Design hollows, ridges, dips, fins and concrete, mortar or
6.1 Selection parameters plaster droppings. The building design should,
therefore, enable the mastic asphalt to be applied to
Factors influencing the selection of grades of mastic
a uniform thickness.
asphalt flooring should be considered at an early
stage in the design and should include the following: 6.2.2 Concrete bases
a) the constructional form of the base on which Concrete bases to receive mastic asphalt directly
the flooring is to be laid, e.g. ground supported should be designed and constructed following the
slab, suspended floor, or screed; recommendations in BS 8204-1:1987. The surface
b) any falls or drainage facilities required; should be provided with a float finish, and a surface
regularity of SR2. Any falls required should be
c) the means of providing a transition from one
formed in the base.
level to another particularly at thresholds;
Any damp-proof membrane and/or thermal
d) features such as details of finishing against
insulation should be placed below the concrete base
other materials or floor finishes laid to falls; slab.
e) the type and intensity of traffic anticipated; Adequate end and side restraint should be provided
f) details of any fixtures or fittings, particularly to precast concrete beams and similar units in order
where these are fixed into the base and penetrate to reduce their structural movement to a minimum.
the asphalt;

© BSI 03-1999 3
BS 8204-5:1994

6.2.3 Screeds The surface should be provided with a float finish,


Cement: sand and fine concrete screeds should be and a surface regularity of SR2. Any falls required
designed and laid following the recommendations should be formed in the base supporting the screed.
given in BS 8204-1:1987. The soundness of the
screed should be at least category B when tested by
the method given in Appendix B of BS 8204-1:1987.
Table 1 — Grades and thicknesses of mastic asphalt for underlays and wearing
surfaces for various uses
Application Grade (and range of thickness)
I II III IV Paving to
BS 1447:1988
15 mm to 20 mm 15 mm to 20 mm 20 mm to 30 mm 30 mm to 50 mm 25 mm to 50 mm

Underlays
For resilient floorings X
For hard floorings X
Wearing surfaces
Hospital wards X
School classrooms X
Corridors
light traffic X
heavy traffic X
Shop flooring
to take moveable racks X
to take fixed racks X
Offices X
Factory flooring
light-duty X
medium-duty X
heavy-duty X
Loading sheds
internal X
external X
Breweries X
Railway platforms
internal X
external X
Domestic flooring X
Flooring subject to heavy
foot traffic
internal X
external X
Unheated warehouses X
and sports halls
NOTE 1 Grade I flooring should not be laid at temperatures below 10 °C, see 6.6.2.
NOTE 2 For special requirements such as suspended floors where wet processes are used see 6.3.

4 © BSI 03-1999
BS 8204-5:1994

6.3 Mastic asphalt waterproofing Usually the mastic asphalt should be laid in one
On ground-supported and suspended concrete coat, but multi-coat work should be used where a
bases, where wet processes are to be used, mastic waterproofing membrane is specified (see 6.3).
asphalt should be laid in two coats, the first coat Multi-coat work should be used for regulating
being an underlay of waterproofing mastic asphalt courses (see 6.9).
as given in 5.1 d). This system should be used in 6.6.2 Grade I. Special hard flooring
toilet and shower compartments on suspended
concrete slabs over accommodation areas, wet Grade I flooring should be laid in one coat within the
process areas and in breweries and food factories range of 15 mm to 20 mm thick. It can be used in
(see Figure 1 for typical details). hospital wards, schools, shop floors to take
moveable racks, offices and domestic floors. Grade I
6.4 Drainage of floor areas (falls and channels flooring can also be used as an underlay for other
to shed water) floor finishes.
Where wet processes or regular cleaning of the floor Grade I floorings are designed for situations with
is a user requirement it is essential that careful relatively high ambient temperatures, i.e. 25 °C
consideration be given to the provision of adequate to 30 °C.
falls to channels and gullies to prevent ponding. Grade I flooring should be planned so that the
Falls are essential where acid and chemical mastic asphalt is not restrained in any way during
resistant mastic asphalt is laid, in order to facilitate the cooling period, and that no large adjacent bay
washing down. In shower rooms similar provisions areas are laid at the same time where excessive
are essential. cooling shrinkage could occur. Care should be taken
The arrangement of falls and the location of to avoid restraint at door thresholds, at internal and
drainage outlets are interdependent and should be external angles of walls or partitions and around
considered carefully at the design stage as stanchions, pipes, machine bases, etc. Appropriately
adjustment of finished levels will be difficult at a positioned battens, set slightly away from the
later stage. vertical surface involved, will allow free movement
Where channels are needed, they should be formed of the mastic asphalt at these points, the asphalt
in the base and lined with appropriate material. It coat being completed after removal of the battens.
is recommended that falls of not less than 1 in 60 Grade I flooring should not be laid when the
should be provided both over the general floor area ambient temperature is below 10 °C, nor should it
and in channels (see Figure 2). be laid in areas where it is likely to be subjected in
Where mastic asphalt is an underlay to ceramic service to ambient temperatures below 10 °C. In
tiling or similar pavings, and surface drainage is such situations grade II or grade III flooring should
required, it is essential that the gullies are located be used.
at the level of the mastic asphalt waterproofing. An 6.6.3 Grade II. Light duty flooring
adequate number of outlets should be provided, of a Grade II flooring should be laid in one coat within
type suitable for use in conjunction with mastic the range of 15 mm to 20 mm thick. It is suitable for
asphalt. a wide range of floor conditions where point loading
6.5 Effects of temperature will not occur or where shallow indentations are
Mastic asphalt is a thermoplastic material. Its acceptable. It is suitable for shop floors to take fixed
resistance to indentation will be reduced with racks, light assembly factory floors for foot traffic
increase in temperature. As they are liable to be only or domestic floors with no point loading.
damaged at very low temperatures, flooring grades Grade II flooring can also be used as an underlay for
should never be laid externally or in unheated other floor finishes.
buildings. For these locations a paving grade 6.6.4 Grade III. Medium-duty flooring
asphalt should be used. Grade III flooring should be laid in one coat within
6.6 Mastic asphalt the range of 20 mm to 30 mm thick. It is a general
6.6.1 General purpose flooring suitable for medium duty
industrial floors, floors subjected to heavy foot
All grades of mastic asphalt are available coloured traffic, hospital corridors and heated sports halls.
red or black.
The total thickness of the mastic asphalt flooring
should be appropriate to the traffic conditions.

© BSI 03-1999 5
BS 8204-5:1994

6.6.5 Grade IV. Heavy-duty flooring In areas of heavy traffic, and areas where heavy
Grade IV flooring should be laid in one coat within static loads are anticipated, such as aprons in front
the range of 30 mm to 50 mm thick. It is intended of loading bays, a proprietary metal grillage should
for situations where the floor is subjected to be laid over a first coat of flooring grade mastic
mechanical trucks, trolleys, severe abrasion, heavy asphalt and its interstices filled with a suitable
static loads or impact. paving or flooring grade mastic asphalt. The use of
such grillages will serve to limit the degree of
indentation of the mastic asphalt.

Figure 1 — Flooring and skirting for wet areas

Figure 2 — Drainage channel with light-duty grating

6 © BSI 03-1999
BS 8204-5:1994

In the case of grade IV material, the percentage of 6.7.5 Postal sorting office flooring
coarse aggregate to be added may be varied within A proprietary grade of mastic asphalt flooring
the limits given in Table 5 of BS 6925:1988, in should be used for the traffic conditions and
proportion to the thickness to be laid. requirements of postal sorting office floors. Where
6.6.6 Paving grade flooring such flooring is required, a mastic asphalt
Paving grade flooring should be laid in one coat manufacturer should be consulted for guidance.
within the range of 25 mm to 50 mm thick. It may 6.7.6 Tank room flooring
be laid externally or in unheated areas. In areas of Where water storage is located in a tank room at or
heavy traffic or areas where heavy loads are near roof level the flooring is essentially a
anticipated, reference should be made to the mastic waterproof lining serving a similar function to that
asphalt manufacturer for guidance. of the mastic asphalt roofing. The amount of usage
In the case of a paving grade material, the may be no more than that on an average roof and
percentage of coarse aggregate to be added may be will involve occasional light maintenance traffic. In
varied within the limits given in Table 3 of this situation roofing grade mastic asphalt should
BS 1447:1988, in proportion to the thickness to be be used unless special traffic or environmental
laid. conditions have to be considered, when the mastic
6.7 Special applications asphalt manufacturer should be consulted.
6.7.1 General 6.7.7 Oil-resistant flooring
Where particular conditions have to be met and Oil-resistant mastic asphalts are no longer
where mastic asphalt conforming to type F1076 or to available and so a suitable oil-resistant coating
type F1451 of BS 6925:1988 does not fulfil certain should be applied over the mastic asphalt. The
specific requirements, special proprietary grades of oil-resistant coating should be applied as soon as
mastic asphalt should be used. possible after installation of the flooring and prior to
any traffic or the floor being put into service.
6.7.2 Chemical and acid resistant flooring
6.8 Mastic asphalt details
Grades of mastic asphalt manufactured with
limestone aggregate will be readily attacked by 6.8.1 Surface finishes
acids. Each situation should be considered Grades I, II and III floorings can be finished by sand
individually and the fullest technical information rubbing or with a natural float finish. Paving grade
obtained, including the nature and concentration of and grade IV floorings should always be sand
the liquors, the degree of spillage expected and the rubbed.
temperatures involved. Mastic asphalt underlays should receive a
The majority of industrial solvents will attack sand-rubbed or natural float finish, in accordance
mastic asphalt. with the requirements of the manufacturer of the
6.7.3 Gritless flooring floor covering.
In certain circumstances, as in some types of 6.8.2 Skirtings and angle fillets
munition factories, special grades of mastic asphalt Skirtings and fillets should be executed in a
should be used in order to minimize the risks of fire waterproofing mastic asphalt as given in 5.1 d). On
or of explosion from sparking. Where gritless new brickwork or concrete, skirting up to 300 mm
flooring is required, a mastic asphalt manufacturer high should be applied in two coats to a nominal
should be consulted for guidance. thickness of 13 mm. The height of the skirting will
6.7.4 Flooring for unheated buildings be dictated by design considerations related to wall
finishes, etc., but in areas subject to wet processes
In unheated buildings, such as warehouses, and in and wash down, the height should be not
buildings with intermittent heating, such as sports less than 150 mm. Skirtings should be tucked into a
halls, which can be subject to considerable seasonal chase or groove at the top edge. Skirtings
temperature variations, the mastic asphalt used over 300 mm are regarded as vertical work and
should be of a suitable proprietary grade or paving should be applied in three coats to a nominal
grade conforming to BS 1447:1988. thickness of 20 mm.
In unheated sports halls, the flooring should be laid On old or irregular brickwork it is usually necessary
to a thickness not less than 25 mm on a glass fibre for the skirtings to be applied in three coats; the first
tissue separating membrane. Where vibration or coat being a dubbing out coat to correct
impact is expected the flooring should be laid irregularities in the wall followed by the standard
directly on the base. two coat work. The nominal thickness should
be 20 mm.

© BSI 03-1999 7
BS 8204-5:1994

Fillets should be formed either with a cove or an Where surface contamination is evident, reference
angle, in two coats with a minimum width of 40 mm should be made to the mastic asphalt manufacturer
on the face. for guidance.
6.8.3 Chases 6.8.5 Preparation of vertical and sloping
Chases should be provided in brickwork and concrete surfaces to provide a key
concrete and should be 25 mm × 25 mm. Where smooth concrete formwork has been used,
After asphalting, the chase should be pointed using the laitance, or any release agent from the
a cement: sand mortar containing a polymer formwork, should be removed by needle gun, wire
admixture such as a styrene butadiene rubber or brushing or other suitable mechanical means. Prior
acrylic type. to asphalting, the prepared surface should be
treated with an application of a suitable proprietary
6.8.4 Separating membranes high bond primer applied in accordance with the
Grades I, II and III flooring should be laid on a manufacturer’s instructions.
separating membrane. Alternatively, expanded metal lathing may be fixed
A glass fibre tissue separating membrane should to the concrete to provide the necessary key.
always be used when it is known or suspected that On lightweight aggregate concrete and lightweight
there is no adequate damp proof membrane below concrete blockwork, mechanically fixed expanded
the concrete ground slab or where a suspended metal lathing, on sheathing felt, should be used to
concrete slab is located over areas where wet provide the necessary key (see Table 2).
processes could permit moisture vapour to
penetrate the concrete. The use of a separating 6.8.6 Preparation of brickwork to provide a key
membrane between waterproofing and flooring The horizontal joints in the brickwork should be
grades of mastic asphalt is not recommended. flush pointed and the brickwork treated with an
application of a suitable proprietary high bond
Grade IV flooring should preferably be laid directly
on the concrete base; however, a separating primer applied in accordance with the
membrane is essential in the following manufacturer’s instructions.
circumstances: Engineering bricks do not provide an adequate key
for mastic asphalt and should only be used in
a) where the base is of a porous or open texture
association with an application of a suitable
such as no fines concrete or lightweight concrete;
or proprietary high bond primer, applied in accordance
with the manufacturer’s instructions, and
b) where the concrete surface contains fine
mechanically fixed expanded metal lathing
cracks.
(see Table 2).
Table 2 — Treatments for vertical and sloping surfaces to receive mastic asphalt
Substrate High bond primea Expanded metal Expanded metal
lathing lathing on sheathing
felt

Smooth concrete (alternative treatments) Xb Xc


Textured concrete (coarse aggregate) X
Lightweight aggregate concrete X
Lightweight concrete blockwork X
Facing bricks d
X
Engineering brickse X X
Timber X
Metal (alternative treatments) X X
a
Suitable primer applied in accordance with the manufacturer’s instructions.
b
Applied to concrete with a mechanically prepared surface.
c
Fixed to concrete with an unprepared surface (not a preferred option).
d With flush pointed joints (see 6.8.6).
e Brickwork should be primed prior to fixing expanded metal lathing (see 6.8.6).

8 © BSI 03-1999
BS 8204-5:1994

6.9 Regulating courses 6.12 Thermal and sound insulation


On old and uneven floors a mastic asphalt Interposing thermal or sound insulation between
regulating course may be used provided the total the structural base and the mastic asphalt flooring
thickness permits. The mastic asphalt is not advisable. The majority of materials used for
manufacturer should be consulted prior to the this purpose do not provide adequate support for the
commencement of work regarding the feasibility of mastic asphalt.
providing a regulating course, and the grade and 6.13 Movement joints
build up of mastic asphalt to be used.
Allowance should be made for movement joints in
6.10 Tolerances on finished mastic asphalt mastic asphalt flooring where such joints are
flooring incorporated in the base on which the asphalt is
6.10.1 General applied.
Floor level is defined as the mean height of the floor Where floors will be cleaned by washing down, or
surface measured in relation to the height of a fixed are in wet process areas, movement joints should
datum. Some variation in level can be allowed not be located at low points of falls or near to gullies
without detriment to the satisfactory use of the or channels.
floor. If a proprietary movement joint system is used it is
Surface regularity or flatness is a measure of the essential to ensure that it is capable of accepting the
waviness of the surface of the floor. For convenience expected type of traffic and degree of movement,
in checking, tolerances on surface regularity are that the materials of which it is made are
normally expressed in terms of the permissible compatible with mastic asphalt and that a secure
departure from the underside of a 3 m straightedge and watertight joint can be made between the
laid in contact with the floor. movement joint and the combined mastic asphalt
6.10.2 Departure from datum waterproofing and flooring.
Where joints in the concrete base or screed are liable
The designer should specify the maximum
to move, they should be carried through the base
permissible departure of the finished surface of the
and/or screed and the mastic asphalt to the floor
flooring from datum, taking into account the area of
surface by means of a proprietary movement joint
the floor and its intended use. For large areas a
profile. These vary in depth and thickness.
tolerance of ± 15 mm from datum is usually
Movement joint profiles should also be used
satisfactory.
between mastic asphalt and other types of flooring,
6.10.3 Surface regularity and centrally over supporting beams and walls of
For normal commercial floors, the maximum suspended floors.
departure of the surface from a 3 m straightedge 6.14 Slipperiness
should be 5 mm. A departure of 10 mm may be
Mastic asphalt is not inherently slippery.
acceptable for floors where the surface regularity is
Slip-resistance is improved by initial sand rubbing.
not critical. In special circumstances (such as a
However, frequent polishing will reduce the slip
television studio floor) a closer tolerance, e.g. a
resistance of the surface.
maximum departure of 3 mm under a 3 m
straightedge, may be necessary (see Table 3).
7 Construction work on site
The specification of close tolerances can incur
increased costs. 7.1 Work planning
The classification of surface regularity for mastic Where mastic asphalt waterproofing is to be
asphalt flooring and underlays is given in Table 3. overlaid with mastic asphalt flooring the work
Details of the method of checking surface regularity should be arranged so that the overlaying is
are given in Annex A. undertaken as a continuous operation and
precautions should be taken to prevent
There should be no noticeable change in level across
contamination of the surface of the waterproofing
any joints in the mastic asphalt flooring.
prior to laying the flooring.
6.11 Mastic asphalt underlay
Where mastic asphalt is to be used as an underlay it
should be laid to the surface regularity selected by
the specifier from Table 3.
The surface finish of the mastic asphalt underlay
should be as specified by the manufacturer of the
flooring to be applied.

© BSI 03-1999 9
BS 8204-5:1994

Table 3 — Classification of surface regularity for mastic asphalt flooring and underlays
Classa Maximum permissible Application Mastic asphalt grade
departure from a 3 m
straightedge laid in
contact with the floor
mm
SR1 3 High standard floors Grades I and II
Special floors
SR2 5 Normal standard floors Grades I, II and III
SR3 10 Utility standard floors Grades III and IV and
Other floors, the surface paving grade
regularity of which is not critical
a As given in Table 2 of BS 8204-1:1987.

7.2 Preparatory sitework prior to asphalting 8.3 Setting out


Before laying of the mastic asphalt flooring is The setting out of the floor into bays should be
commenced, checks should be made to ensure that: decided by the asphalt contractor. The arrangement
a) the base has been properly laid to the specified of the bays will normally depend on the design of the
falls, tolerances and finishes; the equivalent of a floor and the number of spreaders engaged, so that
wood float finish is essential on horizontal the laying and finishing processes can both be easily
concrete screeds or slabs; controlled by the spreaders, in order to achieve the
specified surface regularity.
b) all chases have been properly cut;
c) all outlets have been installed, located and 8.4 Placing the separating membrane
fixed at the correct height relative to the base; The separating membrane, when required, should
d) vertical surfaces have been correctly prepared; be laid loose with lapped joints at least 50 mm wide.
e) movement joints have been correctly installed. 8.5 Laying the flooring
8.5.1 General
8 Workmanship Laying the flooring should be carried out in
8.1 Re-melting accordance with accepted practice as given in 8.5.2
Re-melting of mastic asphalt should be carried out to 8.5.5. However, discretion should be allowed to
in mechanically agitated mixers; cauldrons should the asphalt contractor if, in his judgement, the
only be used in exceptional circumstances, such as circumstances in any particular case call for some
those governed by site conditions and the areas of modification.
flooring to be laid. 8.5.2 Horizontal work
The heating should be controlled to avoid the Mastic asphalt flooring should be laid in bays
material becoming overheated to an extent which generally in one coat. It should be spread to the
might affect its properties. The temperature should specified thickness, timber or metal gauges being
not exceed 240 °C. used to ensure accuracy. The mastic asphalt should
8.2 Transport of molten material be floated to a uniformly level surface and should be
free from roughness or imperfections. If blowing
When the material is sufficiently molten to be occurs, the bubbles should be stabbed and the area
workable, it should be carried in buckets, affected carefully made good while the mastic
wheelbarrows, or heated dumpers to the point of asphalt is still hot.
laying. To prevent the molten material from
sticking to the buckets, wheelbarrows, etc. these Multi-coat work should be treated in a manner
should be sprinkled inside with a small quantity of similar to that for single-coat work, but care should
inorganic dust such as limestone dust. For acid be taken to arrange that the joints in successive
resistant mastic asphalt a silica or similar acid layers are not coincident (see 8.5.3).
resistant dust should be used. 8.5.3 Junctions
The edges of previously laid bays should be warmed
and cleaned by the application of hot mastic asphalt
before the joint with the new material is made.

10 © BSI 03-1999
BS 8204-5:1994

In the case of two-coat work the junction between Concrete, mortar, cement grout or plaster should
adjacent bays of mastic asphalt should be not not be mixed directly on the flooring.
less than 75 mm from the corresponding junction in
the preceding coat. This procedure should also be 10 Inspection and testing of flooring
adopted at junctions between the floor finish and 10.1 Inspection
skirtings, coves or fillets.
The work should be inspected before asphalting is
8.5.4 Skirtings commenced, while it is in progress, and after
Skirtings should be executed in not less than two completion, special attention being paid to the
coats, particular care being taken to ensure proper following:
adhesion of the first coat to the base. Special care a) general condition of the base;
should be taken at external angles to ensure the full
thickness of the material. b) correct laying of the separating membrane,
when used;
8.5.5 Cove or angle fillets
c) cleanliness of plant for re-melting;
At the intersection of the two planes forming an
d) correct temperature of the mastic asphalt prior
internal angle and after the mastic asphalt has been
to laying;
laid on horizontal, sloping or vertical surfaces, a
solid angle or coved fillet of mastic asphalt, not e) use of the correct kind of dust to assist removal
less than 40 mm wide on the face, should be formed of mastic asphalt from the buckets,
in two coats, immediately after first warming and wheelbarrows, etc.;
cleaning the intersection by the temporary f) making good of all blows;
application of hot mastic asphalt, before the fillets g) correct thickness of the coats of mastic asphalt;
are formed.
h) correct treatment of junctions and skirtings;
8.5.6 Sand rubbed finish i) removal of all mastic asphalt tailings;
While the mastic asphalt is still warm, horizontal j) correctness of the finished level and that the
surfaces should be well rubbed with a wooden float, finish is to specification.
using clean sand. Special attention should be given
to the junctions between bays. All surplus material 10.2 Testing
should be removed after rubbing is completed. 10.2.1 Floor levels and surface regularity
8.5.7 Natural float finish At the appropriate time after laying, when the
The surface should be finished with a float in a flooring is tested by the methods described in
manner similar to that used for a sand rubbed finish Annex A the departure from datum and the surface
but without the use of sand. regularity should be within the limits specified
(see 6.10 and Table 3).
9 Protection The number of measurements required to check
floor levels and surface regularity should be agreed
9.1 On completion of laying
at the outset between the parties concerned bearing
The flooring should not be subjected to traffic until in mind the standard required and the likely time
the mastic asphalt has cooled to ambient and costs involved [see 4.2 f)].
temperature.
10.2.2 Slip resistance
9.2 Between completion of laying and
At the appropriate time after laying, the floor
hand-over
should be tested by the method described in
Between completion of laying and hand-over it is Annex B.
essential that mastic asphalt flooring is fully The slip resistance value (SRV) should be greater
protected from: than 39 in both the wet and the dry state.
a) mechanical and impact damage, including
10.2.3 Sampling of mastic asphalt
damage from contractors’ plant, equipment and
materials; When samples of mastic asphalt are required for
testing, the sampling procedure adopted should be
b) careless handling of scaffolding or other
in accordance with BS 5284:1993.
builder’s accessories;
The requirements regarding samples for testing
c) traffic by following trades;
should be agreed between the parties concerned at
d) contamination by spillage of solvents, diesel the exchange of information stage [see 4.2 q)].
fuel or paints.

© BSI 03-1999 11
BS 8204-5:1994

11 Maintenance of mastic asphalt 12 Repair of mastic asphalt flooring


flooring Areas of mastic asphalt flooring subjected to heavy
A mastic asphalt flooring requires periodic, routine traffic may require repairing in order to maintain
attention to obtain the maximum service and to the flooring in good condition. All repair work to a
maintain the best decorative effects. The user mastic asphalt surface should be performed by a
should be guided by the advice of the asphalt specialist mastic asphalt contractor. If it is
manufacturer or a reliable flooring contractor in the necessary to remove an area of mastic asphalt, the
selection of suitable cleaning agents and polishes for line of the cuts should be covered with molten
the maintenance of the floor finish. Polishes should mastic asphalt until the underlying material has
be of the emulsion type, free from solvents. Polishes softened. The asphalt should not be removed until
in which wax is prepared in a paste form with a this has taken place. In no circumstances should a
solvent should not be used. hammer and chisel be used to cut cold mastic
Superficial dirt can normally be removed by asphalt. Alternatively a disc cutter may be used to
washing or scrubbing with warm water and suitable remove mastic asphalt. A gas torch with controlled
detergents. Where there is much dirt on the gradual heating may be used in carrying out
flooring, the addition of a small quantity of washing repairs.
soda to the warm water may be desirable. After the Where mastic asphalt has previously been laid in a
dirt has been removed the floor should be mopped single coat the cut edge of the existing mastic
with clean water. It is essential that all oils, fats and asphalt should be warmed using molten mastic
greases be removed as soon as possible. asphalt so that a proper joint with the re-laid mastic
When hosing down, a constant water temperature asphalt can then be formed.
should be maintained with the water temperature On multi-coat work where a waterproofing coat and
not exceeding 40 °C. a flooring coat have been laid, the cut edge of the
existing mastic asphalt should be softened using
molten mastic asphalt and the flooring coat removed
over a width of approximately 75 mm. A lapped
joint with the relaid waterproofing and flooring
grade mastic asphalt should then be formed.

12 © BSI 03-1999
BS 8204-5:1994

Annex A (normative) Annex B (normative)


Methods for the assessment of floor Determination of slip resistance value
levels and surface regularity (SRV)
Check floor levels to datum using standard B.1 Principle
surveying methods. The floor surface is swept over a given area by a
Check surface regularity by using a slider at the end of a pendulum. The retardation
straightedge 3 m long laid in contact with the floor which is caused by the friction so generated is
surface and resting under its own weight. Measure measured by the extent to which the pendulum fails
the deviations of the surface from the underside of to reach its original release height. This
the straightedge by means of a slip gauge or other measurement, referred to as the slip resistance
suitable accurate measuring device. An example of value (SRV) is recorded on a scale and approximates
a suitable form of slip gauge is shown in Figure A.1. to 100È, where È is the dynamic coefficient of
friction.
B.2 Apparatus
B.2.1 TRL Pendulum slip resistance tester
B.2.1.1 The friction test shall be made with a tester
(see Figure B.1) manufactured to the design of the
Transport Research Laboratory (TRL). All bearings
and working parts of the instrument shall be
enclosed as far as possible, and all materials used
shall be treated to prevent corrosion under wet
conditions.

Figure A.1 — Slip gauges for checking surface regularity

© BSI 03-1999 13
BS 8204-5:1994

Figure B.1 — Friction tester


B.2.1.2 The tester shall have the following features: e) a pointer balanced about the axis of
a) a spring-loaded rubber slider of the mass, size suspension, indicating the position of the
and shape specified in B.2.1.4 to B.2.1.6. It shall pendulum arm throughout its forward swing and
be mounted on the end of a pendulum arm so that moving over the circular scale. The mass of the
the sliding edge is approximately 510 mm from pointer shall be not more than 85 g. The friction
the axis of suspension; in the point mechanism shall be adjustable so
that, with the pendulum arm swinging freely
b) means for setting the column of the instrument
from a horizontal position, the outward tip of a
vertical;
nominal 300 mm long pointer can be brought to
c) means for raising and lowering the axis of rest on the forward swing of the arm at a
suspension of the pendulum so that the slider point 10 mm below the horizontal;
can:
f) a main scale as detailed in TRL drawings for a
1) swing clear of the surface of the floor; and sliding length of 126 mm.
2) be set to slide over a fixed length of flat B.2.1.3 The mass of the swinging arm, including the
surface of 126.0 mm ± 1.0 mm, as near as is slider, shall be 1.50 kg ± 0.03 kg. The centre of
visually possible; gravity shall lie on the axis of the arm at a distance
d) means of holding and releasing the pendulum of 410 mm ± 5 mm from the centre of suspension.
arm so that it falls freely from a horizontal
position;

14 © BSI 03-1999
BS 8204-5:1994

B.2.1.4 For wet floors the slider shall consist of a B.4 Setting up procedure
rubber pad the properties of which shall be as given B.4.1 Measure and record the temperature of the
in Table B.1. The pad shall be 76 mm ± 1.0 mm floor surface.
wide and 25.4 mm ± 1.00 mm long (in the direction
B.4.2 Level the base, using the spirit level and the
of swing) and 6.35 mm ± 0.50 mm thick. It shall be
three levelling screws on the base-frame. Raise the
held on a rigid base with a central pivoting axis and
head so that the pendulum arm swings clear of the
the combined mass of slider and base shall
surface.
be 35 g ± 5 g. The slider assembly shall be mounted
on the end of the swinging arm in such a way that, NOTE Movement of the head of the friction tester, carrying the
swinging arm, graduated scale, pointer and release mechanism,
when the arm is at the lowest point of its swing with is controlled by a rack and pinion on the rear of the vertical
the trailing edge of the slider in contact with the test column. After unclamping the locking knob at the rear of the
surface, the plane of the slider is angled at (26 ± 2)° column, raise or lower the head as required by turning either of
the vertical movement control knobs. When the required height
to the horizontal. In this configuration the slider can is obtained, it is essential to lock the head unit in position again
turn about its axis without obstruction to follow by clamping the locking knob at the rear of the column.
unevenness of the surface as the pendulum swings. B.4.3 Check the zero setting as follows.
For dry floors a more appropriate result will be a) Raise the swinging arm to the horizontal
obtained using a 76 mm ± 1.0 mm wide shoe release position on the right-hand side of the
sole/heel leather slider and/or a 25 mm ± 1.0 mm apparatus, so that it is locked automatically in
wide hard rubber slider. This latter should have a the release catch.
hardness of (85 ± 5) IRHD. Alternatively
b) Bring the pointer round to its stop in line with
a 76 mm ± 1.0 mm RAPRA (Rubber and Plastics
the pendulum arm.
Research Association) 4S rubber slider may be used.
c) Release the pendulum arm by pressing the
B.2.1.5 The slider shall be spring-loaded against the
test surface. The nominal static force on the slider release button.
as set by the procedure defined in the equipment’s NOTE The pointer is carried with the pendulum arm on the
forward swing only.
calibration instructions shall be 22.2 N ± 0.5 N in
its median position; the change in the static force on d) Catch the pendulum arm on its return swing,
the slider shall be not greater than 0.2 N per and note the pointer reading.
millimetre deflection of the slider. The resilience e) Return the arm to the release position.
and hardness of the sliders shall conform to f) Correct the zero setting as necessary by
Table B.1. adjustment of the friction rings. If the pointer has
B.2.1.6 The working edges of the slider shall be swung past the zero position, screw the rings up
prepared by several swings over fine grade a little more tightly. If it has not reached zero,
sandpaper when the pendulum is set up as given unscrew the rings a little.
in B.4. Before testing, the bevel formed by wear on g) With the pendulum arm free and hanging
the working edge shall be measured and if greater vertically, place the spacer, which is attached to a
than 2.0 mm the slider shall be replaced. The chain on the base of the vertical column, under
rubber shall be free from contamination, by, for the lifting-handle setting screw in order to raise
example, abrasive or oil and in sheet or slider form the slider. Lower the head of the tester so that the
shall be stored in the dark at a temperature slider just touches the test surface and clamp in
of 20 °C ± 4 °C. position. Remove the spacer.
B.2.2 Thermometer, capable of measuring surface h) Check the sliding length of the rubber slider
temperatures. (the distance between two points where the slider
B.2.3 Potable water, at 20 °C and brush for wetting edge of the rubber touches the test surface) by
floor surface. gently lowering the pendulum arm until the
B.2.4 150 mm scale, for setting the swept length. slider just touches the surface, first on one side
and then on the other side of the vertical. To
B.3 Selection of test area prevent undue wear of the slider when moving
Test areas can be selected in either a strict grid the pendulum arm through the arc of the contact,
patten, or on a random basis. Normally a minimum raise the slider off the test surface by means of
of four tests would be required but in large areas one the lifting handle.
test per 250 m2 would be appropriate. On very large Adjust the sliding length to between 125 mm
areas the sampling rate may be decreased if it is and 127 mm by raising or lowering the head as
found that there is a consistency between results, necessary.
conversely, in smaller areas this sampling rate may
NOTE On the scale provided, the outer marks are 127 mm
be increased if there are wide variations in results. apart and the inner ones each indicate the tolerance allowed.
i) Place the pendulum arm in its release position.

© BSI 03-1999 15
BS 8204-5:1994

Table B.1 — Properties of the friction tester slider (soft rubber)


Property Temperature

°C

0 10 20 30 40

Resilience (%)a 43 to 49 58 to 65 66 to 73 71 to 77 74 to 79
Hardness (IRHD)b 55 ± 5 55 ± 5 55 ± 5 55 ± 5 55 ± 5
a Lüpke rebound test in accordance with BS 903-A8:1990.
b International rubber hardness degrees in accordance with BS 903-A26:1969.

B.5 Test procedure B.6 Test report


B.5.1 For wet tests, wet the slider and the surface to The test report shall include the following:
be tested over the whole area which will be in a) the number, date (and clause reference) of this
contact with the slider with potable water British Standard, i.e. BS 8204-5:1994 (Annex B);
at 20 °C ± 4 °C.
b) the location of the site and a drawing showing
For dry tests, unless conducting “as found” tests, the position of the tests;
thoroughly clean and dry the surface.
c) a description of the flooring and its age;
NOTE If this test is carried out after the wet test, the action of
testing in the wet is normally sufficient to clean the surface and d) whether tested in dry or wet test conditions;
it is only then necessary to thoroughly dry the surface before e) the slip resistance value at each position tested
conducting the dry test.
and the mean of all results.
B.5.2 Bring the pointer round to its stop. Release
the pendulum arm by pressing the release button Annex C (informative)
and catch it on the return swing before the slider
strikes the test surface. Return the arm and pointer
Characteristics of mastic asphalt
to the release position, keeping the slider clear of the C.1 Control of water vapour
surface by means of the lifting handle. The vapour resistivity of mastic asphalt can be
B.5.3 Repeat B.5.2, spreading water over the assumed to be not less than 100 000 MN·s/(g·m). For
contact area with a brush between each swing. condensation control calculations a vapour diffusion
B.5.4 Record five successive readings, provided they resistance factor (È) of 20 000 may be taken. (See
do not differ by more than three units. If the range also BS 6229:1982.)
is greater than this, repeat the test until a set of five C.2 Compressive strength
successive readings are within 3 units. When When mastic asphalt is fully confined it has the
readings are above 75 this requirement can be same compressive strength as the containing
relaxed to within 6 units. material. When not confined the compressive
B.5.5 Raise the head of the tester so that it swings strength is dependent upon a number of factors
clear of the surface and check the free swing for zero including temperature to which it may be subjected.
error. Advice on individual cases should be sought from
B.5.6 Calculate the slip resistance value as the the manufacturer.
mean of the five recorded readings. Temperature C.3 Combustibility
corrections for SRV readings using a soft rubber Mastic asphalt has low combustibility on account of
slider are given in Table B.2. its high mineral content.
Table B.2 — Temperature corrections for SRV C.4 Thermal conductivity
readings using soft rubber slider
Mastic asphalt has a thermal conductivity (2) value
Surface temperature Correction to SRV of between 0.43 W/m·K and 1.15 W/m·K. A 2 value
°C of 0.50 W/m·K may be assumed for design purposes.
8 to 11 –3 C.5 Toxicity
12 to 15 –2 Mastic asphalt is non-toxic and is generally suitable
16 to 18 –1 for use in contact with potable water.
19 to 22 0 C.6 Odour
23 to 28 +1 Mastic asphalt is odourless after laying.
29 to 35 +2

16 © BSI 03-1999
BS 8204-5:1994

List of references (see clause 2)

Normative references

BSI publications
BRITISH STANDARDS INSTITUTION, London

BS 410:1986, Specification for test sieves.


BS 903, Physical testing of rubber.
BS 903-A8:1990, Method for determination of rebound resilience.
BS 903-A26:1969, Determination of hardness.
BS 1369, Steel lathing for internal plastering and external rendering.
BS 1369-1:1987, Specification for expanded metal and ribbed lathing.
BS 1447:1988, Specification for mastic asphalt (limestone fine aggregate) for roads, footways and pavings
in building.
BS 5284:1993, Methods of sampling and testing mastic asphalt used in building and civil engineering.
BS 6100, Glossary of building and civil engineering terms.
BS 6100-1.3.3:1987, Floors and ceilings.
BS 6100-2.4.1:1992, Highway engineering.
BS 6925:1988, Specification for mastic asphalt for building and civil engineering (limestone aggregate).
BS 8204, In-situ floorings.
BS 8204-1:1987, Code of practice for concrete bases and screeds to receive in-situ floorings.

Informative references

BSI publications
BRITISH STANDARDS INSTITUTION, London

BS 6229:1982, Code of practice for flat roofs with continuously supported coverings.
BS 8204, In-situ floorings.
BS 8204-2:1987, Code of practice for concrete wearing surfaces1).
BS 8204-3:1993, Code of practice for polymer modified cementitious wearing surfaces1).
BS 8204-4:1993, Code of practice for terrazzo wearing surfaces1).

1)
Referred to in the foreword only.

© BSI 03-1999
BS 8204-5:
1994
BSI — British Standards Institution
BSI is the independent national body responsible for preparing
British Standards. It presents the UK view on standards in Europe and at the
international level. It is incorporated by Royal Charter.

Revisions

British Standards are updated by amendment or revision. Users of


British Standards should make sure that they possess the latest amendments or
editions.

It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using
this British Standard would inform the Secretary of the technical committee
responsible, the identity of which can be found on the inside front cover.
Tel: 020 8996 9000. Fax: 020 8996 7400.

BSI offers members an individual updating service called PLUS which ensures
that subscribers automatically receive the latest editions of standards.

Buying standards

Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.

In response to orders for international standards, it is BSI policy to supply the


BSI implementation of those that have been published as British Standards,
unless otherwise requested.

Information on standards

BSI provides a wide range of information on national, European and


international standards through its Library and its Technical Help to Exporters
Service. Various BSI electronic information services are also available which give
details on all its products and services. Contact the Information Centre.
Tel: 020 8996 7111. Fax: 020 8996 7048.

Subscribing members of BSI are kept up to date with standards developments


and receive substantial discounts on the purchase price of standards. For details
of these and other benefits contact Membership Administration.
Tel: 020 8996 7002. Fax: 020 8996 7001.

Copyright

Copyright subsists in all BSI publications. BSI also holds the copyright, in the
UK, of the publications of the internationalstandardization bodies. Except as
permitted under the Copyright, Designs and Patents Act 1988 no extract may be
reproduced, stored in a retrieval system or transmitted in any form or by any
means – electronic, photocopying, recording or otherwise – without prior written
permission from BSI.

This does not preclude the free use, in the course of implementing the standard,
of necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.

If permission is granted, the terms may include royalty payments or a licensing


agreement. Details and advice can be obtained from the Copyright Manager.
BSI Tel: 020 8996 7070.
389 Chiswick High Road
London
W4 4AL

Vous aimerez peut-être aussi