Please refer to the following data for exact cooling tower installation:
1. Installation Manual
2. Delivery Order
3. Assembly Drawing
4. Photograph
5. Parts Number and Screw List
Tools Required
1. Scaffolding
2. Spanner size 17&18 (16 pcs) and 22 & 24 (6 pcs)
3. Pipe Wrench 20” ( 2 pcs)
4. Electric Drill 13 MM (Double direction) (2 pcs)
5. Drill Bit 11,13 ( 2 pcs)
6. Grinder 4” (2 pcs)
7. Socket Spanner 17 & 19 (2 pcs)
1. FRAME ASS’Y
a. Concrete foundation bases should be located perfect level and
clean
b. Assemble Tower Frame Ass’y Fix assembled frame on the
foundations.
c. After checking the Frame for being level, securely tighten bolts.
d. Do not fasten the bolts mentioned above, until the assembly of
water basin and sump is completed.
4. Casing
a. Rest casing on the stiffener ring. Corresponding set marks
clamp casing with bolts (For LDT 300 Upwards)
b. Clamp casing rim and stiffener ring with bolts. (For LDT 300
Upwards)
c. Rest casing on the casing supporter (For LDT 150 – 250)
d. After ensuring assembled condition, securely tighten bolts with
even torque.
e. If casing has two parts, it shall be assembled according to the
following procedures, cylinder (additional casing) and diffuser
(Upper casing/ Fan stack) (for LDT 400 & upwards)
Liang Hoo Cooling Tower
5. Stand Pipe
Insert stand pipe base to the water sump, and applied F.R.P. to
join two of connection pipe.
6. Filling Supporter.
a. After placing column assemble filling supporter.
b. After checking and correcting any irregularity secure each bolt.
Liang Hoo Cooling Tower
Filling Support B
Filling Support A
Ring Support
Filling
Support Louver
Filling Support
Filler Support
LDT 225 - 350
Filling Support C
Filling Support B
Filling Support A
Filling Support
Ring Support
Filling
Support
Ring Base Atas
7. Ladder
a. Fix the ladder upper sec. && lower sec. with bolts. Then
assemble bracket.
b. Set the top end of ladder on the upper flange of casing.
c. Set bracket on water basin rim.
Liang Hoo Cooling Tower
8. Filling
a. The form filling has 2 layers, which must be kept in level
condition when assembled.
b. Bring the form filling inside the cooling tower as shown figured
below.
Material Precautions:
1. Matt has to keep clean and dry
2. PE Resin should be stored in the shadow place, and lower
temperature (32 0C max)
3. Catalyst must keep away from fire and high temperature.
Liang Hoo Cooling Tower
13.Final Examination
a. Inspect that all bolts are in good condition
b. Clean the surface of casing and water basin
c. I the events that damage, scoring of scratching has occurred
during transit, it may be necessary to touch up the paint on the
metal parts.
8b QTY
8a LDT
Item 400 UNIT
No DESCRIPTION
19
30 29
APPROVED BY : - PROJECT