Académique Documents
Professionnel Documents
Culture Documents
5 0 LEE STREET EAST SUITE 1600 PO. BOX 553 CHARLESTON. WEST VIRGINIA 25322 TELEPHONE: 304-340-1 000 TELECOPIER: 304-340- I I30
jacksonkelly corn
w.
Enclosed for filing are an unbound original and twelve bound copies of the
“Application for Waiver of Siting Certificate Modification Requirements or, in the Alternative,
for a Modification to Siting Certificate and Related Requests for Relief’ (“Application”), which
are hereby submitted for filing by AES Laurel Mountain, LLC (“AES”). Also enclosed is a CD
containing copies of the documents that comprise the Application, each in PDF format. A notice
of intent to make this filing was previously submitted to the Commission on October 13, 2010,
and a copy of that notice is included as Exhibit 7 to the Application.
In the Application, AES outlines its proposal to install an energy storage device
(“ESD”) at the site of its certificated 125 MW Laurel Mountain Wind Power Project (“Project”)
that is currently under construction in Barbour and Randolph Counties, West Virginia. As
explained in the Application, the ESD will not constitute a material modification to the Project.
For that reason, AES requests that the Commission waive the requirement that it obtain a
modification or amendment to the siting certificate issued for the Project. In the alternative, if
the Commission should determine that a modification or amendment to the AES siting certificate
is nevertheless required, AES requests that the Commission grant such a modification or
amendment and waive certain filing requirements under the Commission’s Rules Governing
Siting Certijkatesf o r Exempt Wholesale Generators (“Siting Rules”).
(Cl912548. I}
Clluksburg, WV Mminsburg, WV Morgantown, WV Wheeling, WV
Denver, CO Lexington. KY Piasburgh. PA Washington, DC
Ms. Sandra Squire
November 29,201 0
Page 2
Siting Rule 6.5 specifies that any application for modification or amendment of a
siting certificate be accompanied by an application fee in an amount equal to the greater of
$1,000 or one tenth of one percent (.001) of the projected capital cost of the proposed
modifications, which would be $28,800 based on the $28.8 million estimated cost of the ESD. In
light of the fact that a filing fee in any amount will be required only if the Commission
determines that a waiver of the requirement to obtain a modification or amendment to the AES
siting certificate is unwarranted, a check payable to the Commission in the amount of the
minimum filing fee of $1,000 is enclosed in a sealed envelope attached to the original
Application. It is requested that the Commission hold the check in escrow and deposit the check
only if it does not grant AES’s request for a waiver of the requirement to obtain a modification or
amendment of its siting certificate. In that event, AES will promptly submit the balance of any
additional filing fee that may be required at that time.
Sincerely,
SNCIdmb
Enclosures
cc: Barry Sweitzer
Piers Lewis
{C1912548.1}
PUBLIC SERVICE COMMISSION
OF WEST VIRGINIA
CHARLESTON
AES Laurel Mountain, LLC (“AES”), by counsel, respectfully requests that the
Commission waive any requirement that AES obtiin a modification or amendment to its existing
siting certificate (“Certificate”) in connection with the planned installation of an energy storage
device (“ESD’) at its 125 Megawatt (“MW’) Laurel Mountain Wind Power Project (“Project”)
that is currently under construction in Barbour and Randolph Counties, West Virginia. AES
represents that the ESD will not constitute a material modification to the Project in that it will not
alter the design, change the footprint, or increase the transmission or generation of the Project,
nor will it materially affect the viewshed impacts, sound levels, emissions or other environmental
impacts of the Project. In the alternative, if the Commission determines that a modification or
amendment to AES’s Certificate is required, AES requests that the Commission grant the
necessary modification or amendment at its first opportunity and waive certain filing
requirements under the Commission’s Siting Rules as requested in Exhibit 6 hereto. AES also
requests that the Commission retain this Application for decision, and accord it expedited
(Cl918361.3)
consideration in accordance with the Commission’s applicable procedures. In support of these
1. Introduction
1. The name and address of the applicant, and the name, address, telephone number,
fax number and e-mail address of a responsible official of the applicant are as follows:
Responsible official:
Barry Sweitzer
86 Baltimore, Street
Suite 300
Cumberland, Maryland 2 1502
Telephone: (301) 777-9754
Fax: (301) 777-9756
E-mail: barry.sweitzer@AES.com
2. The names, mailing address, e-mail addresses and telephone and fax numbers of
(“Certificate Case”), the Commission granted AES the Certificate for the construction and
operation of the Project, The Project involves the construction of a $250 million, 125 MW wind
{e1918361.3)
2 1
eight-mile stretch of the Laurel Mountain ridgeline lying about three miles east of Belington in
Barbour County and three miles northwest of Elkins in Randolph County. The Project is
currently under construction, with Project roads and civil work nearing completion and wind
turbines scheduled for installation beginning late this year and continuing through the second
quarter of 201 1. The Project substation is scheduled to be energized in April 201 1, with
transmission line that crosses Laurel Mountain at about the midpoint in the string of wind
turbines. An approved interconnection substation is being constructed at the point where the
I
Allegheny transmission line crosses the Project to permit the energy generated by the Project to
enter the transmission grid. Subject to the Commission’s determinations in this proceeding, AES
intends to construct the ESD on a fenced-in parcel of land either directly adjacent to the
interconnection substation or in close proximity thereto and will connect the ESD to the
I
Allegheny transmission line through the Project switchyard. An aerial photograph of the site of
the interconnection substation showing the locc!tion of the substation and the approximate
5. The ESD will have a combined nominal output of 32 MW, comprised of eight 4
I
MW modules consisting of lithium-ion batteries, inverters, transformers and cooling systems.
The lithium-ion batteries used in the ESD are about the size of a standard “D” cell flashlight
battery and are the same kind of batteries used worldwide in a variety of applications, including
cordless power tools and battery powered or hybrid vehicles. The batteries are grouped into
battery packs or modules that are loaded into trays and the trays are mounted in floor-to-ceiling
(C1918361.3) 3 1
racks inside a standard shipping container (53’ long, 8’ wide and 9-1/2’ tall). Photographs of
batteries, a battery pack and tray, racks and a shipping container similar to what will be installed
at the Project site are attached hereto as Exhibit 2. Each 4 MW module includes:
a single 20’ long shipping container that houses bidirectional inverters to convert
In addition, there will be a small control house, main transformer, and row of switchgear.
Photographs of an existing AES ESD installation in Chile are attached as Exhibits 4-1 and 4-2.
Exhibit 4-1 is an aerial photograph showing the containerized storage modules in a single row to
the left and an adjacent substation on the right. Exhibit 4-2 consists of two ground-level
photographs. One photograph shows a row of shipping containers in which batteries are housed,
with a chiller unit in the foreground. This photograph, as well as Exhibit 4-1 also shows what
resembles a sidewalk extending along the row of battery containers. This is actually the surface
of an underground raceway that carries power cables to the main power transformer. The other
photograph in Exhibit 4-2 shows, in the foreground, an isolation transformer, and in the
6. Installation of the ESD is expected to take approximately four months and AES is
seeking expedited review in this proceeding to enable construction to start by February 1, 201 1,
thereby permitting the ESD to come online at the same time that the Project is put into service.
The construction process will involve minimal initial site work due to the location of the ESD
{ a 9 18361.3) 4 1
adjacent to the site of the Project substation which is already under construction. Once the site is
prepared, foundations for the shipping containers and concrete pads for other components of the
ESD will be installed and the shipping containers and other components will then be trucked in
and offloaded onto the foundations. Conduits and wiring (mostly at grade or underground) will
be installed to connect the various components of the ESD and the ESD will be connected to the
substation via underground cables. The site will be enclosed by security fencing, with locked
gates. Security lighting and cameras will be installed. Fire suppression systems will be included
in each of the battery storage containers and secondary containment will be installed for the oil-
7. The purpose of the ESD is twofold: to regulate the “ramp rate” of the Project and
to provide automatic generation control (“AGC”). The Project will gain the capability to regulate
its own ramp rate, controlling the rate at which power output from the Project to the grid
changes. Additionally, the AGC capability will enable the Project to provide the ancillary
primarily by dispatchable generators with AGC capability, but may also be offered by flexible
loads or energy storage devices. Regulation helps PJM Interconnection, L.L.C. (“PJM”), the grid
operator, to match generation levels with short-term changes in electricity use in order to
maintain stable grid frequency at 60.0 Hz. The resources selected to provide Regulation in each
hour earn a payment based on the amount of flexible capacity being provided. The market-based
payment to each resource, known as the “regulation market clearing price,” is determined hourly
by PJM based on the set of resources offering and clearing in the market. The Project will earn
revenue through its participation in the PJM Regulation market. The Project’s participation in
(C1918361.3)
this market is authorized under the Project’s authorization by FERC to make sales at market-
based rates.
8. PJM has concluded an Interconnection Feasibility Study for the ESD, a copy of
which is attached as Exhibit 6-1, and is in the process of performing a System Impact Study,
which is expected to be completed in the first calendar quarter of 201 1 . Given that no facilities
issues were noted in the feasibility study, it is reasonable to expect that PJM will determine that
no facilities study will be required after the System Impact Study is completed. Following
completion of the System Impact Study, AES and PJM will revise the Project Interconnection
9. The estimated cost of the ESD is $28.8 million, which will be hnded entirely by
AES.
10. The impact of the ESD on the Project is not material. Specifically:
(a) The ESD does not change the engineering design plans or generating
No additional property is required for the ESD, which will fall within the
existing footprint of the Project. The ESD will occupy approximately 1.25
Project substation and within the limits of disturbance established for the
Project will be necessary for access to the ESD site. Due to the short
(C1918361.3)
6 1
installation schedule for the ESD, the volume and frequency of any
The viewshed of the Project will be virtually unchanged. The total height
determined that the ESD will have negligible effects on total Project sound
levels, with increases in total modeled Ldn sound levels at the closest
residences being less than 0.5 decibel. The projected sound impact of the
ESD was modeled under a worst case scenario with both the wind turbines
and the ESD operating at full load conditions, with all chillers and
The ESD generates no emissions and will have no impact on air or ground
the NPDES permit issued for the Project will not need to be modified
because the construction of the ESD is not expected to exceed the existing
{C1918361.3)
7l
Nothing in the size, composition, location, operation or nature of the ESD
suggests that it will have any adverse impact on the environment, any
are required either for the ESD or for the Project as a result of the ESD.
AES intends to use local electrical and mechanical contractors for the
local area.
7
IV. Waiver Warranted Under Circumstances
11. s
Considering the totality of circum tances, the installation and operation of the
ESD should not be considered a “material” modification to the Project. Installation of the ESD
will not alter the design, change the footprint, or increase the transmission or generation of the
Projcct, nor will it materially affect the existing viewshed, sound levels, emissions or other
environmental impacts of the Project. In that regard, the relative impact of the ESD on the
Project is quite similar to the impact that a so-called “black start generator” installed by Big
Sandy Peaker Plant, LLC at its Wayne County, West Virginia gas-fired generating plant was
found to have on that facility. In Case No. 06-1912-E-CS-PW, Bin Sandy Peaker Plant, LLC,
the Commission concluded that the construction of the generator was not material because it
would neither modify the footprint of Big Sandy’s generation facility, nor increase the
transmission or generation of the facility, nor require any modification to the facility with a
potential environmental impact. The Commission further found that the generator would not
materially affect the viewshed impacts, noise levels, emissions or other environmental impacts of
{C1918361.3} 8
the Big Sandy power plant.’ Similarly, in Case No. 05-1467-E-CN, Longview Power, LLC, the
Commission found that a proposed increase in the generating capacity of a coal-fired plant from
600 MW to 695 MW was not a material modification to Longview Power’s siting certificate,
subject to a number of conditions, including that there be no change in the footprint or layout of
the facility, the switchyard or transmission line, and stack height, as well as no need for
compliance with operational noise levels set forth in Longview’s siting certificate.2 Again, the
factors considered by the Commission in Longview, when applied to the facts of this application,
clearly support the issuance of a waiver of the requirement that AES obtain a modification or
12. If the Commission should determine that the installation of an ESD requires AES
I
to obtain a modification or amendment to the Certificate, AES requests that the Commission
grant the modification or amendment for the reasAns set forth above and in the attached Exhibit
6.
I
13. Attached as Exhibit 5 hereto is an qpplication for Modification to or Amendment
of a Siting Certificate in the form of Form No. 3 attached to the Commission’s Rules Governing
Siting; Certificates For Exempt Wholesale Generators (1 50CSR30) (“Siting Rules”). Also
attached as Exhibit 6 is a table setting forth (i) the filing requirements of Siting Rules 3.1.a.
through 3.l.p. and (ii) either the corresponding required information, a notation that the
particular information is not applicable under the circumstances, or a request for a waiver of the
I
Case No. 06-1912-E-CS-PW, Big Sandy Peaker Plant, LLC (Commission Order entered on January 30,
2007)
2
Case No. 05- 1467-E-CN, Longview Power. LLC (Commission Order entered on February 16,2007).
(C1918361.3)
VI. Pre-Filing and Notice Requirements
14. Siting Rules 2.1 and 2.2 require that the Commission be given at east 30 days
advance notice of an intended application for a siting certificate and that, upon filing of the
application, a notice of the filing on Form No. 2 be published. However, Siting Rules 6.1
not contain any pre- or post-filing notice or publication requirements. Nevertheless, on October
13, 2010, Counsel for AES filed a letter with the Commission advising it of the intent of AES to
file this application. A copy of this letter is attached hereto as Exhibit 7. In addition, AES
representatives and counsel previously met with the Commission Staff to describe the ESD and
15. Siting Rule 6.5 specifies that any application for modification or amendment of a
$1,000 or one tenth of one percent (.001) of the projected capital cost of the proposed
modifications ($28,800 in this case). In light of the alternative relief requested herein, a check
payable to the Commission in the amount of $1,000 in payment of the minimum application fee
is being submitted with the filing of this application. It is requested that the Commission hold
the check in escrow and deposit the check only if it does not grant AES’s request for a waiver of
WHEREFORE, AES prays that the Commission (i) waive any requirement to obtain a
modification or amendment to its Certificate to install and operate the ESD; and (ii) hold in
escrow the application fee for the reasons identified in paragraph 15 above. In the alternative,
AES prays that the Commission (i) grant the waivers of certain filing requirements as specified
((2191 8361.3)
in Exhibit 6 hereto; and (ii) grant a modification or amendment to the Certificate to permit the
installation and operation of the ESD at the Project. In either case, AES requests that the
Commission grant such other and further relief as it may deem appropriate and that it retain this
applicable procedures.
{C1918361.3)
I
11
VERIFICATION
STATE OF MARYLAND,
Bany Sweitzer, Vice President of AES Laurel Mountain, LLC, being duly sworn,
says that the facts and allegations contained in the foregoing Application are true, except so far
as they are therein stated to be on information, and that, so far as they are therein stated to be on
information, he believes them to be true.
KRISTEN MABEE
Notary Public
Allegany County
Maryland
Taken, sworn to, and subscribed before me this is day of November, 2010.
My commission expires Q - L . 2 7 aor.
,
[C1909592.1)
Index of Exhibits
(C1918361.3) 12
Exhibit 1
Approximate Location of
Energy Storage Device
e Project Substation
I
0 2010 The AES Corporation, All rights reserved.
Exhibit 2
I--
w
Racks
4 MW Modile Layout
Two Modules Shown Side by Side
8 total for 32 MW Device
3'-0
BATTERY
lpf CONTAINER
DISTRIBUTION\
POWER PANF'
I 5 U L A T I ON
TRANSFDR MER
1
BATTERY
lrl'
CONTAINER
FENCE1-
I lllll llllll I1
Exhibit 4-1
T
Exhibit 4-2
Exhibit 5
[Form No. 3)
STATE OF WEST VIRGINIA
PUBLIC SERVICE COMMISSION
CHARLESTON
Comes now the above-named AES Laurel Mountain, LLC, the applicant herein,
by counsel, and respectfully shows the Commission as follows:
1.
I
That the name and address of the applicant is AES Laurel Mountain, LLC,
4300 Wilson Boulevard, Arlington, Virginia 22203.
{C1905371.1}
AES LAUREL MOUNTAIN, LLC
By Counsel
$150-30-3. Application
1, A general purpose statement; The purpose of the ESD is to regulate the ramp rate
of the Project and to supply ancillary services to the
wholesale energy market.
2. Reasons for selection of the proposed site including the principal Not applicable. The ESD will be located on the site
environmental and socio-economic considerations of the proposed site; of the Project constructed and operated pursuant to
the prior authorization of the Commission granted
in the Certificate Case.
3. A description of the proposed facility; The ESD will have a combined nominal output of
32 M W , comprised of eight 4 MW modules
consisting of lithium-ion batteries, inverters,
transformers and cooling systems. Each 4 MW
module consists of two standard shipping containers
housing battery packs, a single 20’ long shipping
container housing inverters, a chiller to cool the
battery containers, and a transformer to change the
alternating current for the inverter. In addition there
will be a small control house, main transformer, and
row of switchgear. The ESD will be located on
approximately 1.25 acres of property adjacent to the
(C1905369.2)
1
Exhibit 6
{C 1905369.2)
2
Exhibit 6
1. Where applicable, for each generationunit,describe thetype o f Gencrally Not Applicable. See response to 3.1 .a.3
unit, estimated net demonstrated capability, heat rate, expected annual above.
capacity factor and expected hours of annual generation for each year
of the first five years of operation.
2. Provide total facility land area requirement. The ESD will occupy approximately 1.25 acres 01
land owned by AES and entirely within the
footprint of the Project.
3. Where applicable, provide fuel quantity. Indicate the maximum Not Applicable.
amount of fuel expected to be consumed in one hour and the expected
amount of fuel consumed per year.
{C1905369.2)
3
Exhibit 6
6. Fuel Storage. Indicate how much, if any, fuel will be stored on Not Applicable.
and off site. Discuss the details of such storage arrangements including
the expected number of days of fuel to be stored.
7. Provide a list of expected air andwater emissions and,for each- Not Applicable.
emission, the name of the federal and/or state regulatory authority from
which a permit must be obtained, or, a statement that no permits from
other federal and/or state regulatory authorities are required for that
emission. If permits from other authorities are not required, state the
expected impact of such emissions.
9. Provide a summary description of other major equipment, All of the significant equipment is described in
including any significant safety equipment, e.g., fire fighting 3.1.a.3 above and in paragraph 5 of the Application.
equipment. Each shipping container will be equipped with a fire
suppression unit.
3.1.d Submit all interconnection studies necessary for facility. The PJM Feasibility Study Report for the ESD is
attached as Exhibit 6-1. A System Impact Study is
currently being conducted and is expected to be
completed in the first calendar quarter of 2011.
When it is available, the System Impact Study will
be submitted to the Commission. Given that no
facilities issues were noted in the feasibility study, it
is anticipated that no facilities study will be required
by PJM following completion of the System Impact
Study. However, if a facilities study is required, it
will be promptly submitted to the Commission
when available.
(C1905369.2)
4
Exhibit 6
3.1.e Provide proposed project schedule in a Gantt Chart, including the See attached Exhibit 5-2.
critical path and covering all applicable major activities and milestones,
including:
1. Acquisition of land and/or land rights; Not applicable. ESD to be located on site of the
Project.
2. Submittal of the application and receipt of a Public Service Application filed on November 29, 2010. Waiver,
Commission Siting certificate; or modification to or amendment of siting
certificate, requested in time to permit installation to
begin on or about FebruaIy 1,2011.
3. Submittal and receipt of all required approvals andor permits See response to 3.1.a.4.
from other governmental (state, local, federal) agencies (See Rule
5.l.a.). Include a statement of the current status of such submissions
and receipts including copies of any correspondence from agencies
addressing the status of such applications or permits;
4. Preparation of the final design; Final design of ESD expected to be Completed prior
to the end of 2010.
5. Construction of the facility; and Installation of ESD expected to begin on or about
February I, 2011, and be completed on or about
June 1,201 1.
6. Placement of the facility in service. ESD expected to be put in service on or about June,
2011.
3.1.f Describe the impact of delays on the eventual in-service date. Delays in putting the ESD in service will deprive
the grid operated by PJM and the generating
facilities connected thereto of the benefits of the
frequency regulation capabilities of the ESD.
3.1 .g Technical data:
1. Site. Information on the location, major features, and the Not applicablelwaiver requested. The ESD is to
topographic, geologic, and hydrological suitability of the selected site. be located on the site of the Project. Installation of
the ESD will have no geologic or hydrological
impact on the site.
{C1905369.2}
5
Exhibit 6
2. An aerial photograph for a one-mile radius from the facility. Not applicable/waiver requested. The ESD is to
be located on the site of the Project.
3. Design and construction. Provide plan and elevation view Interim waiver requested. The final siting and
engineering drawings based on information on the proposed layout on design of the ESD are in progress and engineering
the most current engineering design plans for the facility, depicting the drawings are expected to be available by the end of
major structures and installations. 2010 and will be filed with the Commission when
~~
available.
4. Site activities. Describe the proposed site preparation and Only minimal site preparation will be required as
reclamation operations, including: test boring; removal of vegetation; the ESD is being located in close proximity to the
grading and drainage provisions; access roads; removal and disposal of Project’s interconnection substation on land that is
debris; and post-construction reclamation. being cleared and graded for or in connection with
the substation.
5. Plans for construction. Describe the proposed construction See Exhibit 6-2.
sequence based on engineering design plans filed pursuant to this
section.
6. Structures. Describe all major proposed structures, including The ESD will be comprised of eight 4 MW modules
estimated overall dimensions; construction materials; color and texture consisting of lithium-ion batteries, inverters,
of facing surfaces; any unusual features; transmission towers; and transformers and cooling systems. Each 4 M W
security facilities. module includes: (i) two standard 53’ long shipping
containers housing the battery packs; (ii) a single
20’ long shipping container that houses inverters to
change the battery power from direct current to
alternating current; (iii) a chiller to cool the battery
containers; and (iv) a transformer to change the
alternating current for the inverter. In addition there
will be a small control house, main transformer, and
row of switchgear. The shipping containers and
control houses are prefabricated metal structures.
These structures will contain fire suppression
systems and will be enclosed by a locked security
fence and protected by security cameras.
7. Future glans. Statement whether applicant intends to be the entity [t is currentlv the intent of AES to be the entitv that
(C 1905369.2)
6
Exhibit 6 ,
that will own and operate the facility into the future and a description of will own and operate the ESD into the future. No
any plans for future additions of generating units for the site, including additional storage capacity is currently anticipated
the type and timing; and the maximum generating capacity anticipated for this site. Post useful life demolition, removal,
for the site. The applicant shall describe post useful life demolition, disposal and restoration plans for the ESD have not
removal, disposal, and restoration plans for facilities. been developed. However, removal and disposal of
the self-contained ESD components would not be
difficult and would not require any significant
disturbance to the remainder of the site.
8. Equipment. See response to 3.1.g.6 above and paragraphs 5 and
A. Description of proposed major generating equipment. 7 of the Application.
B. Emission control and safety equipment. Description of all
proposed major flue gas emission control equipment, including
tabulations of expected efficiency, power consumption, and operating
costs for supplies and maintenance; the reliability of the equipment and
the reduction in efficiency for partial failure; the equipment proposed
for control of effluents discharged into water bodies and receiving
streams; and all proposed major public safety equipment.
C. Description of any other major equipment not discussed
above.
i.1.i [mpact. Identify and describe the impact of the facility on any public The ESD will have no impact on existing public
utilities, including but not limited to water utilities, sewer utilities, otilities or solid waste facilities. The ESD will have
5lectric utilities, commercial solid waste facilities, natural gas utilities, 2 positive impact on the electric grid operated by
md telephone utilities. The applicant shall further identifl and describe P J M Interconnection and the generating facilities
the impact of the facility on other generating facilities whether or not connected thereto that will benefit from the
utility-owned. frequency regulation capabilities of the ESD.
{C1905369.2)
Exhibit 6
1. The applicant shall provide still renderings from all scenic adjacent to the site of the interconnection substation
overlooks and project views that will be most evident to the public, and for the Project. Due to the relatively small size of
which are accessible to the applicant, from which the 24-2-1(c) the ESD and its low profile (12’-15’ in overall
generating facility will be visible after construction. height) in comparison to the wind turbines and the
2. Still renderings which show structures at ground level shall substation, it will not have any material impact on
include a scaled 6 foot tall figure in near proximity to such structures to Project views.
allow the viewer to clearly see the scale of the project structures.
2. Provide an analysis of the prospects of floods and high winds Waiver requested. The ESD will be located on the
for the area, including the probability of occurrences and likely site of the Project and will have no additional
consequences of various flood stages and wind velocities, and describe impact on hydrological resources.
plans to mitigate any likely adverse consequences;
3. Provide existing maps of aquifers which may be directly Waiver requested.The ESD will belocated on the
affected by the proposed facility; and site of the Project and will have no additional
impact on hydrological resources.
4. A study of how the project and the water use identified in Rule Waiver requested. The ESD will be located on the
3.1 .c.8. will affect the identified water sources. site of the Project and will have no additional
impact on hydrological resources.
3.1.1 Financial and Economic data.
1. Debt and Equity Capital. AES will pay the entire estimated $28.8 million cost
A. Estimates of the amounts of debt and equity capital for the of the acquisition and installation of the ESD and no
project. These estimates shall include all capital that will support the separate financing (public or private) will be
construction of the project and all permanent sources of capital, if required. No construction or bridge financing is
{Cl905369.2}
8
Exhibit 6
2. Pro forma financial statements. Provide pro forma financial Waiver requested. The ESD will not have any
statements palance Sheet, Funds Statement and Income Statement) for adverse affect on the financial or operational
each year of the start-up phase (project development and construction) capabilities of either AES or its operation of the
~~
and for the first five years of operation of the proposed project. The Project.
financial statements must disclose all assumptions.
3. Local and State Economic Impact. Provide estimates of the Waiver requested for the detailed economic impact
effect of the project on the local and state economy as well as the model information set forth in this rule. Although not
used to derive the estimates. Such estimates shall cover the construction formally evaluated and quantified, AES’s
phase of the project and the ongoing impacts after construction. Such investment in construction and operation of the ESD
estimates shall include but not be limited to: (i) the impact on local is expected to have a positive economic impact on
employment (including the number of added man-hours, jobs and the state and local economy similar in nature, and
expected payroll value of added jobs), both directly and indirectly roughly proportional in amount, to the positive
related to the project; (ii) the impact on all local and state taxes economic impacts associated with AES’s
(including gross tax amounts and net amounts if any abatement investment in the Project itself.
agreements apply), both directly and indirectly related to the project;
(iii) the impact on local commercial business activity including
{C1905369.2)
9
Exhibit 6
tourism; (iv) the impact on area property values; (v) the impact on
existing infiastructure; (vi) the impact on per capita income in the local
area and the region; and (vii) the impact of lost opportunity(ies) as to
alternative use(s) of the land upon which the facility is proposed to be
built.
4. Regional development impact. The applicant shall describe the The ESD will not have any measurable impact on
impact of the proposed facility on regional development. regional development that is separate and apart fiom
the impact of the Project.
3.1.m Environmental data.
(C1905369.2)
10
Exhibit 6
PSC Rules.] sound levels at the closest residences being less than
C . Operation. Provide (with Application filing) a noise exposure 0.5 decibel. The projected sound impact of the ESD
map of the noise expected to be present during operation. Said map will was modeled under a worst case scenario with both
contain contour lines of equal noise at and up to one mile from the the wind turbines and the ESD operating at full load
facility’s property line. [Details for noise exposure map found in PSC conditions, with all chillers and isolation
Rules.] transformers running and the main transformer plus
the substation transformer running under second
stage auxiliary cooling. The results of the analysis
are summarized on the attached Exhibit 6-3.
3.1 .n Land Uses. In the application, estimate the impact of the proposed Waiver requested. The ESD will have no impact
facility on the land uses depicted on the map required in Rule 3.1.h.l., on the existing or foreseeable future uses of the site
identify stmctures that will be removed or relocated, describe formally or surrounding property.
adopted plans for future use of the site and surrounding lands for
anything other than the proposed facility, and describe plans for
concurrent or secondary uses of the site.
(C1905369.2)
11
Exhibit 6
3.1.0 Cultural impact. Waiver requested. Installation of the ESD will not
1. Landmarks. change the cultural impact, if any, of the Project.
2. Recreation areas.
3.l.p Public responsibility. Describe any program for public interaction Waiver requested. In light of the exceedingly
planned for the siting, construction, and operation of the proposed minor impact of the ESD in relation to the Project,
facility, i.e., public information programs; and describe any insurance no program for public interaction is proposed. AES
or other corporate programs for providing liability compensation for maintains adequate policies of insurance and loss
damages to the public resulting from construction or operation of the control programs to sufficiently protect the public
proposed facility. against the risk of any damage to property or person
arising from the installation or operation of the
ESD.
{C1905369.2)
12
Exhibit 6- 1
Generation Interconnection
Feasibiiity Study Report
For
October, 2010
Overview
Interconnection Customer (IC), AES Lauren Mountain, LLC, has submitted an Attachment N to
propose the interconnection of 32 MW ofbattery storage on a tract of land at the site of the PJM
Queue number P-59Belington 138kV (Leadsville) Project for the purpose of participation in the
PJM Regulation and energy markets via the Allegheny Power network This project was studied
as an injection into the same POI used by the P59 project. Since it was stated at the Feasibility
Kick-off meeting that the maximum amount ofwind at this site will be 91.5 MW, the addition of
32 MW of battery storage at this site therefore fell under the 125 MW energy and 25 M W of
Capacity stipulated under the existing P59 ISA. The Commercial Operation date for this project
was requested to be October 30,2010. The analysis was performed using a 2014 base year
Network Impacts
Queue project W2-057 was studied as a 32.0MW (0 M W of which was Capacity) injection into
the 34.5kV collector bus to be constructed by AES for the P59 Belington 138kV (Leadsville)
wind project. Project W2-057 was evaluated for compliance with reliability criteria fbr summer
peak conditions in 2014. Potential network impacts were as follows:
Generator Deliverability
(Single or N-1 contingencies for the Capacity portion only of the interconnection)
No problems identified.
No problems identified.
No problems identified.
0 PJM Interconnection 2010.All rights reserved.
Exhibit 6-1
None.
None.
Short Circuit
(Report Overdutied breakers here)
None.
Stabilitv Analvsis
No problems identified.
This portion of this Feasibility Study Report has been prepared for PJM queue project W1-057
by Allegheny Power. It addresses the required reinforcements, if any, found in the PJM analysis
of the Transmission System and provides the results of a similar analysis at the distribution leveL
including the attachment and direct connection facilities.
This project was studied as an injection into the 34.5kV collector bus to be constructed by IC for
the P59 (Leadsville) wind project. Therefore, no attachment facilities are to be constructed by AP
to support this installation.
Based on discussions with the developer of this project, it was assumed that the P59 wind
generation hcility will have a maximum output of 91.5 MW. Therefore, at the Leadsville bus,
there will be no net increase of generation capacity with the installation of W2-057. Thus, no
thermal violations were identified.
Union
Road
* Belington
r u
w5.MuchavrLa
4 Ailegheny power 8- oawmto
AHoma
E
m
nur
W2457pd
LEAOSVllLE SHllTCHllG STATfOH
PROVlDE IHTERCONWECnOH FAgLmES FOR
AESLAUREL MOUtrrAlM LLC
OCAU
NS
rnrmrrcrrnr
E
;D
-
Permit Review
Ezl
5 PSC Intent to File Letter 10/13
I__-
11 Site Preparation
13 Commissioning
+
'roject: Laurel Mountain Summary Sc
late: Mon 11/29/10
[
Task
Split
Progress - Milestone
Summary
Project Summary
Page 1
4-
4-
External Tasks
External Milestone
Deadline 9
Exhibit 6-3
JACKSONQLLY
ATTORNEYS AT LAW PLLC
5M3 LEE STREET EAST SUITE 1600 PO.BOX 553 CHARLESTON, WEST VIRGINIA 25322 TELEPHONE: 304-340- 1000 TELECOPIER: 304-340-1 I30
www.jacksonkolly.corn
DIRECT TELEPHONE: (304) 340-1214 DIRECT TELECOPIER: (304) 340-1 080
E-Mail: snchamb~~iacksonkelIv.com
State Bar No. 694
October 13,2010
Re: -
Prefiling notice AES Laurel Mountain, LLC
Application for Waiver of Siting Certificate
Modification Requirements or, in the Alternative,
for a Siting Certificate Modification for the
Installation of an Energy Storage Device at the
Site of the Laurel Mountain Wind Power Project
AES intends to install an energy storage device (“Storage Device”) at the site of
its certificated 125 MW Laurel Mountain Wind Power Project (“Project”) that is currently under
construction in Barbour and Randolph Counties, West Virginia. The Storage Device will have a
nominal output of 32 MW and will be comprised of eight, 4 MW modules consisting of lithium-
ion batteries, inverters, transformers, and cooling systems. The modules will be contained within
a fenced-in area less than 1% acres in size on open land directly adjacent to the Project’s
substation and transmission line and will be connected through the Project switchyard. The
purpose of the Storage Device is to regulate the ramp rate of the Project and to enable the Project
to supply ancillary services in the wholesale markets managed by PJM Interconnection. The
Storage Device will not increase the transmission or generation of the 125 MW Project, but will
improve the delivery of energy from the Project.
AES believes that, considering the totality of the circumstances surrounding the
Project, which extends over an area of approximately 14 miles in length, the construction of the
Storage Device is not material and will not materially affect the Project’s viewshed impacts,
noise levels, emissions or other environmental impacts. Accordingly, AES intends to seek a
((21891233.3)
Clarksburg. WV Martinsburg, WV Porgantown,WV Wheeling, W
Denver, CO Lexingron. KY Pittsburgh, PA Washington. DC