Vous êtes sur la page 1sur 11

SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.

00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 30-Apr-17 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements

Coating application procedure incorporates all the mandatory


SAES-H-201,
A1 requirements of SAES-H-201 and is approved by CSD
Section 1

FBE Powder material, Batch Number, Date of Manufacture, expiry SAES-H-201,


A2
date meets with the requirements of APCS-102A, 102B & 102C Para. 5.3 & 6.1

FBE Coating Repair Material is supplied or approved by the


SAES-H-201,
A3 manufacturer of the powder epoxy coating and conform to CSD
Para. 8.5.3
approved Coating Procedure.

SAES-H-002,
Internal coatings for potable water service are certified by FDA,
Para.
A4 NSF or equivalent.
5.2.14
Note: The certificate shall be renewed every 24 months.

The coating system has been selected for specific service from the SAES-H-002,
A5 various SAP Material Numbers specified in APCS-117 and Para.
approved by CSD/Coatings Team . (Refer to Attachment #1) 5.2.11

Robotic crawler (consisting of blasting and coating equipment, dry


film thickness gauge and holiday detector) are used for onshore
SAES-H-002,
application for internal field girth welds of pipe strings with
A6 Para. 5.2.4
diameters ranging from 8 to 36".
Note: If isotope is used as the girth weld locator, it should be
backed up with a video camera for real time inspection.

For pipe diameters larger than 36", the coating application is done SAES-H-002,
A7 manually by qualified contractors with the approval of Para. 5.2.4
CSD/Coatings Team.

A semi-robotic system is used for offshore applications of specialty


SAES-H-002,
A8 liquid coating on internal girth welds with diameters ranging from 8"
Para. 5.2.5
and above qualified and experienced contractors shall be utilized.

Crawler Equipment for internal coating is verified for correct


SAES-H-201,
functioning and calibration on a test spool.
A9 Para. 7.1.6
Note: The Length & diameter of the test spool shall be decided &
agreed by contractor, CSD & SA inspector before work begins.

Coating personnel hold a valid certification as follows :


SAEP-316
B) Equipment operator (trained & certified by Coating Contractor)
A10 Para 1.1 & Para.
C) Crew supervisor (trained & certified by Coating Contractor)
1.3

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 30-Apr-17 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

B In-Process Inspection of Internal FBE Coating

Coating operations are only allowed to proceed in bad weather


SAES-H-201,
B1 conditions (rain, high winds, etc.)if protective canopies approved
Para. 7.3.6
by SA Inspector are used.
Coating is applied with in 4 hrs, of blast cleaning before any rust
blooming of the prepared metal surface occurs.. SAES-H-201,
Para. 7.3.2
B2
Any flash rusting observed shall be re-blasted prior to coating. SAES-H-002
Refer to the surface preparation and coating application APCS-Sheets
requirements given in APCS Data sheets

Application of phenolic primer prior to the application of FBE is


carried out using a machine to ensure that the travel of application
is constant and that the DFT will not exceed 25 microns (One mil) SAES-H-002,
B3
in all areas. Para. 5.2.3
Note : One mil thickness is exceeded if the “peaks” of steel
substrate are no longer visible.

Substrate Pre-Heat Temperature meets the temperature specified Approved


in the procedure. * Required Pre-heat Temp = ___________ Procedure
SAES-H-201,
B4
1 . Preheating shall be accomplished by induction heating coils. Para. 7.3.1
2. Preheating temperatures shall be measured with contact &
pyrometers. Temperature crayons shall not be used. Para. 7.3.4

The powder application is started immediately after correct metal SAES-H-201,


B5
temp is reached. Para. 7.3.5

Coating Machine applies the powder uniformly to correct width SAES-H-201,


B6 centered on girth weld to achieve a target dry film thickness of 325 Para.
to 625 microns in least number of passes possible. 7.3.5.1

SAES-H-201,
Coated areas are protected from contamination of dirt or
B7 Para.
deleterious materials during application & curing.
7.3.5.2
C Final Inspection Visual Check or Video Camera:

Internally coated pipeline with diameters from 10" to 20" shall be SAES-H-201,
C1
inspected by the cameras fitted on the crawling machine. Para 8.2.5

SAES-H-201,
Finished coating has a uniform, glossy appearance free of defects
C2 Para 8.2.4
such as holidays, fish eyes, lumps, dry spray, sags, and runs.

Coating overlap shall be within the thickness specified in SAES-H- SAES-H-201,


C3 200 and / or as per the applicator's procedure approved. Para 8.2.4

Cure Test is performed on first five joints coated and twice each
SAES-H-201,
C4 day there after, and found acceptable the results are recorded
Para 8.2.3
using SATR-H-2009.

Adhesion Test is conducted as per the frequency specified in


SAES-H-201 found acceptable and test result recorded on SATR-
SAES-H-201,
C5 H-2010.
Section 8.4
Note: Coatings failing the adhesion test criteria shall be completely
removed and areas recoated.

D Dry Film Thickness (DFT) measurement & Holiday Testing

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 30-Apr-17 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Thickness measurements made on each coated weld joint using


an
SAES-H-201,
approved, correctly calibrated dry film thickness gauge (per SSPC
Para. 8.2.2
D1 PA-2). A minimum of 6 readings shall be taken on each field joint
&
including weld seam.
Para. 7.3.5.1
Refer to attachment # 1 for Coating thickness specified for
Various Coating Systems.
Holiday test applied on 100% of the joints coated, at test voltage of SAES-H-201,
125 volts DC per 25 microns of maximum coating thickness. Para. 8.3
D2
(Surface temp of pipe shall not exceed 88). 09-SAMSS-091
Test results are recorded on SATR-H-2008 Para 10.6.3

All holidays, imperfections, and damaged areas are carefully SAES-H-201,


D3
identified as required by the procedure. (Joint ID Number) Para 8.3.2

E Repairs

Girth welds with more than 3 holidays are completely blasted off SAES-H-201,
E1
and the area recoated Para 8.5.1

Pipe surface to be repaired are cleaned of all dirt and damaged or


disbonded coating using abrasive blasting or other suitable means.
SAES-H-201,
E2 The edges of the original coatings are "feathered out"
Para 8.5.2
approximately 50 mm around the specific area to be coated, and
all dust wiped off before applying the patch coating.

Approved
Patch-up coating is applied using materials & methods specified in
E3 Coating
the approved Repair Procedure.
Procedure

Patch Repair areas are 100% holiday tested applying procedures


SAES-H-201,
E4 used for original coating (Refer to D2 above) and found
Para 8.5.4
acceptable, results recorded on SATR-H-008

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating
SAIC-H-2060 30-Apr-17 COAT-
Application on Field Girth Welds
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Remarks:
ATTACHMENTS # 1
REFERENCE DOCUMENTS:
1. SAES-H-201: General Specification for Over-the-Ditch External and Internal FBE Coating of Field Girth Welds (16 November 2011)
2. SAES-H-001, Coating Selection and Application Requirements for Industrial Plants and Equipment (10 April 2011)
3. SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping (2 June 2012)
4. 09-SAMSS-091, Shop-Applied Internal FBE Coatings (15 October 2011)
5. SAEP-316 Performance Qualification of Coating Personnel (11 MAR. 2015)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and
Name, Initials and Date:
Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Comp of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015) Rev. 2015.03.00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process & Final Inspection of Internal coating SAIC-H-
30-Apr-13 COAT-
Application on Field Girth Welds 2060
PROJECT TITLE WBS / BI / JO NUM CONTRACTOR / SUBCONTRACTOR

Attachment- 1
REQUIREMENTS- SAUDI ARAMCO APPROVED PROTECTIVE COATING SYSTEMS for INTERNAL COATINGS

S.R. No APCS
Coating Specific Requirements for Coating Application
Type/Service Total DFT #1 #2
Specialty Liquid Coating Systems 1- Ceramic/Alloy Filled Epoxy 2- Glass Flakes Filled
for Pumps, Valves, Piping, Fitting Coatings Coatings
and Exchanger Boxes. Filler Coatings: Filler Coatings:
Service Temp: Up to 105C. Belzonas 1311/1111 Corroglass 100, 200,
Purchase Specifications: 09- Barrier Coatings: 600, Polyglass VEF
SAMSS-067
1 APCS-28 750 – 1500 microns Belzonas 1341/1321/ 1391S/1391T / Barrier Coatings &
SAMS Stock Numbers: N/A 5891 Top Coat:
Fluiglide and/or Veil
cote

Shop-Applied Fusion Bonded APCS-102A shall not be used on the SAP M/N: (Refer to
Epoxy for Internal Coating of girth welds of any pipe and fittings SAES-H-002V)
Treated Seawater and Potable coated with either APCS-28, APCS- Purchase Spec: 09-
Water Pipelines (Service Temp: 375-625 117 or APCS-118. SAMSS-091.
2 APCS-102A
Min. 0°C Max. 90°C ) microns

Shop-Applied Fusion Bonded APCS-102B shall not be used on SAP M/N: (Refer to
Epoxy for Internal Coating of the girth welds of any pipe and SAES-H-002V)
Formation Water and Wet Crude fittings coated with either APCS-28, Purchase Spec: 09-
Pipelines (Service Temp: Min. 0°C 375-625 APCS-117 or APCS-118. SAMSS-091.
3 APCS-102B Max. 95°C ) microns

Shop-Applied Fusion Bonded Field Girth Weld Area: Crawler- Purchase Spec:
Epoxy for Internal Coating of applied FBE or liquid coating APCS- (Refer to CSD. The
Sour/Sweet Gas Pipelines. 120 for internal girth welds of pipe coating shall be
Pipe 625 – 750
(Primarily used for sour and strings. tested against the
microns
4 APCS-102C sweet gas pipelines excluding operating conditions.)
Girth Welds: As per
girth welds. Temp: Min. 0°C
Coating Data sheets
Max. 95°C)

Internal coating for water, oil or The coating system for specific
gas service. For spools, valves, service shall be selected from the
elbows, tees, wyes, nozzles, various SAP Material Numbers
flanges and other associated specified in APCS-117. SAP M/N:
pieces of piping systems. When In this regard, CSD/Coatings Team 1000180021,
the coating is glass fiber/flake shall be contacted 1000180023,
reinforced, a final coat of flow 1000180276,
5 APCS-117 500 to 1500 microns
coating should be used to ensure 1000180279,
a good flow property. 1000180328 and
(Service Temp: depends on 100018033
coating product) Purchase Spec: N/A

Saudi Aramco: Company General Use


Internal coating for oil, water and SAP M/N: N/A
gas service. Applied on internal Purchase
of spools, elbows, tees, wyes, Specification: N/A
APCS-118 nozzles, flanges and other
1,500 to 3,000
(This Coating System associated pieces of piping The coating system for specific
systems. This coating type microns
6 is removed from service shall be recommended by
(depending on
SAES-H-002 Revised creates a “pipe within a pipe” CSD/Coatings Team.
concept. (Service Temp: Min. product specification)
on 8-May-2011)
-20°C Max. 105°C or depends on
coating product)

Internal coating to prevent black Field and/or Shop Girth Weld Areas: SAP M/N: N/A
APCS-119 (This powder and/or enhance flow of Coating is not required Purchase
Coating System is sales gas in pipelines and piping Specification: API 5L2
7 removed from SAES- systems. (Service Temp: Min. 0°C 75 to 125 microns or ISO 15741
H-002 Revised on 8- Max. 90°C)
May-2011)

Internal coating for water, oil or SAP M/N: N/A


gas service in the girth weld area Purchase Spec: N/A
applied by special semi-robotic 500 to 1,000 microns
8 APCS-120 machines.(Service Temp: (depending on
depends on coating product) product specification)

Saudi Aramco: Company General Use


31-Mar-15
BER

NGS

ing Application
#2
2- Glass Flakes Filled
Coatings
Filler Coatings:
Corroglass 100, 200,
600, Polyglass VEF
Barrier Coatings &
Top Coat:
Fluiglide and/or Veil
cote

SAP M/N: (Refer to


SAES-H-002V)
Purchase Spec: 09-
SAMSS-091.

SAP M/N: (Refer to


SAES-H-002V)
Purchase Spec: 09-
SAMSS-091.

Purchase Spec:
Refer to CSD. The
coating shall be
ested against the
operating conditions.)

SAP M/N:
1000180021,
1000180023,
1000180276,
1000180279,
1000180328 and
100018033
Purchase Spec: N/A

Saudi Aramco: Company General Use


SAP M/N: N/A
Purchase
Specification: N/A

SAP M/N: N/A


Purchase
Specification: API 5L2
or ISO 15741

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015)

Saudi Aramco: Company General Use


Rev. 2015.03.00

4/30/2017

Saudi Aramco: Company General Use


3/31/2015

Saudi Aramco: Company General Use

Vous aimerez peut-être aussi