METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 1 of 8

METHOD STATEMENT / TECHNICAL PROPOSAL FOR WATER


PROOFING OF CATALYST AT GIKI

PROJECT ‘’Water Proofing Of Catalyst at GIKI – Topi ’’.

CLIENT GIKI

CONTRACTOR FIDA CONSTRUCTION


Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 2 of 8

INTRODUCTION

This method statement represents the proposed Construction/Work plan for the ‘waterproofing
of the catalyst’’ under this Project.

SCOPE OF WORK
This method statement covers the following:
1. Mobilization/Early Preparation.
2. Preparation of Roof for the new layer of Bitumen membrane sheet.
3. Tack/Primer Coat of Bitumen 1 mm thick.
4. Laying of 3mm Thick membrane sheet over the roof surface with gas torch.
5. Filling of the joints with hot bitumen with gas torch.
6. Revisiting all the joints for any leakages.
RESPONSIBILITIES

1. It is the overall responsibility of the Site Incharge, to ensure that the site preparation activities
and safety plans are conducted according to the project specifications and approved safety
plan.
2. Cleaning and Protection
3. Smooth work flow

To execute the water proofing work the Site Incharge will be accompanied by team that will includes
Site foreman, Welders and Various number of Skilled/Unskilled Labours as per plan requirement.
Below is the organization chart to carry out the work

Site Incharge
(Naqash Ali Khan) HSE/Safety
Inspector (Rashid
Khan)

Site Foreman
(Shafiq Hayat)

Gas Torch Semi Skilled


Unskilled Labour/Material
Operator (2) Labour (3) Handler (5)
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 3 of 8

Site Organization Chart Fig 1


MANPOWER AND EQUIPMENTS

Overall Machinery List

S.No Equipment Item Qty


1 VAN 1
2 Welding Plant 2
3 Rivet Gun 3 Sets
4 Pick-up 1
5 Material Handling Tools 2 Sets
6 Cutters, Grinders and Misc Tools 4 Sets
7 Welding Rods 50 Kg
8 Welding Mask 3 Pairs
9 Welding Gloves 6 Pairs
10 Safety Belt 4 sets

Overall Manpower Category

1 Site Incharge 1
2 Site Foreman 1
6 Welder 3
7 Semi Skilled Labour 3
8 Unskilled Labour 5

1. PROCEDURE
1.1. PRIOR ACTIVITIES
1. Manual Survey will be carried out for the area required water proofing.
2. Old surface of the roof will be cleaned with brushes before putting of the tack coat.

1.2. Installation of Angle iron Steel Frame over the old roof
Required no. of 50mm x 50mm x 5mm angle iron will be cut in various sizes to make steel frame
over the old roof. The steel frame will be installed with Rawal Bolts on old roof. Various boxes and
sections will be made from angle iron so that the GI Sheet could be installed on the frame.
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 4 of 8

1.3. Laying of Bituminous Membrane sheets

Bituminous membrane waterproofing is a popular method used for low-sloped roofs due to
their good proven performance. Bituminous waterproofing membrane has a torch on a
membrane and self-adhesive membrane. After Tack/Primer Coat Membrane sheet will be
laid with the help of gas torch so that it can permanently stick with surface.
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 5 of 8

1.4. Finalising Water Proofing


After laying of membrane sheets and joints filling. The team will re visit the roof for any
defects and will request the Client site representative to help notify any defects which would
be addressed in timely manner.

1.5. Inspection and Handing Over


We will officially request to client for 3rd party inspection to successfully handover the site.

1.6. Clearance of Site and Project Completion


Site will be handed over back to the client after the leftover material/Debris from the work are
removed.

2.0. HEALTH, SAFETY AND ENVIRONMENT

HSE General Precautions & General Mitigation Measures/Controls

Activity to be adequately supervised by competent staff (both Construction & HSE)


All Personnel/Workforce involved in the activity to be inducted, and received the required
training/competencies BEFORE commencing the activity

1. Engineer/Supervisor/Foremen In-Charge to prepare and the JSTI (Job Safety Task Instructions)
form, and discuss it with the workforce BEFORE commencing the activity (form and discussion
to be in the language understood by the workforce)
2. Required Permits/NOCs (including Permits To Work, as applicable) to be obtained ahead of
time (BEFORE commencing the activity)
3. All Plants/Machines/Vehicles/Equipment used in the activity to be pre-inspected and approved
by the competent authorized personnel
4. HSE Procedures relevant/applicable to the activity to be reviewed by the Engineer/Supervisor
In-Charge, and specific precautions to be conveyed to the Foreman/Charge-Hand and
Workforce.
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 6 of 8

5. All Personnel/Workforce involved in the activity to fully comply with PPE requirement (Personal
Protective Equipment)
6. Use adequate and visible HSE signage, posters and board to promote awareness
7. Ensure adequate rest areas (welfare facilities) are accessible
8. Engineer/Supervisor/Foreman/Charge-Hand to be familiarized with Emergency Response Plan
& Contact Numbers. Emergency contact numbers to be posted on site.
9. Supply toilets and cool drinking water at the immediate area of the activities prior to
commencement of works.

3.0. PROJECT TIMELINES

In order to ensure timely completion of the Project, We are proposing Project Timeline so that all the
activities are simplified for better understanding. The required No. of days for successful completion
of the water proofing work are 19 days.
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 7 of 8

Timeline 1

Timeline 2

4.0. WARRANTY/GUARANTEE FOR THE WATER PROOFING WORK

Fida Construction would give guarantee for the water proofing work of Bituminous Membrane sheets
of 3 years, Including one year period for the withholding of 5% retention amount from the date of
handing over.

5.0. SIMILAR NATURE OF WORK DONE IN LAST FIVE YEARS

We have carried out numerous work of similar nature but the one which is near to the GIKI is Base
workshop in T4 Extension Project, Tarbela Dam, Swabi.

Project Name: Mechanical Workshop Rehabilitation


Project Location: Base Workshop, T4 Extension Project, Tarbela Dam
Project Value: 44 Million PKR
Client: Sino Hydro Bureau 8 Co Ltd.
Doc. No.
Water Proofing Of Catalyst at GIKI – Topi GIKI/1022
(Rev No.)
Issue
METHOD STATEMENT 05 10 2019
Date
Water Proofing (water proof Bituminous Rev. Date NA
membrane sheet for Incubation Centre GIKI) Pages 8 of 8