Académique Documents
Professionnel Documents
Culture Documents
P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 1440 1880
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1200 1567
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 692 903
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 128 167
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 1850 2415
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 165 215
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 150 196
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 150 196
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2400 3133
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1423 1858
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 516 674
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 520 679
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 450 588
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 240 313
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 670 875
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 15100 19715
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 11167 14580
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 8930 11659
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 7150 9335
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1700 2220
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 840 1097
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 5590 7298
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 11760 15354
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 200 261
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 230 300
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1545 2017
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 650 849
Paver Finisher Hydrostatic with sensor control 100
P&M-034 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 1725 2252
TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 629 821
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 3525 4602
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 802 1047
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2690 3512
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 585 764
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 83 108
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 297 388
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 738 964
Transportation of soil, GSB, WMM, Hotmix
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 15.6 20
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 1.74 2
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 200 261
etc.
P&M-049 Transit Mixer 4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 600 783
P&M-050 Transit Mixer 4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 5.22 7
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 550 718
Page 1 of 378
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km 4.8 6
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 245 320
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 252 329
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 14.5 19
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 186 243
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 1.6 2
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 994 1298
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 777 1014
P&M-065 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 0
P&M-068 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 0
P&M-069 Cement concrete batch mix plant @ 75 cum per hour hour 0
P&M-077 Compressor with guniting equipment along with accessories hour 350 457
P&M-078 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 0
P&M-083 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour 0
P&M-084 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 0
P&M-086 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 0
P&M-088 Snow blower equipment 140 HP @ 600 cum per hour hour 0
P&M-093 Vibrating Pile driving hammer complete with power unit and accessories. hour 0
Page 2 of 378
(B) Labour
(C) Materials
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum
M-002 Stone Boulder of size 150 mm and below at Site cum 1,089.00
M-003 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum
M-004 Boulder with minimum size of 300 mm for Pitching at Site cum 1,105.00
M-010 Granular Material or hard murrum for GSB works at Site Cum 1,369.00
M-011 Granular Material or hard murrum for GSB works at Mixing Plant Cum 1,369.00
M-012 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 225.00
Page 3 of 378
Rate at Plant
Description Unit (HMP/Batching Rate at Site
)
M-014 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 982.00 982.00
M-036 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the
M-037 nos 25,662.25
process of vulcanisation,)
M-038 Bearing (Forged steel roller bearing of 250 tonne nos
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel
M-039 nos 30,794.71
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components
M-060 Credit for excavated rock found suitable for use cum
M-062 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 727.43
M-063 Earth Cost or compensation for earth taken from private land cum 16.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause
M-064 metre
915.1 of IRC: 83 (part II),
M-065 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos
M-066 Epoxy compound with accessories for preparing epoxy mortar kg 100.00
Page 4 of 378
M-067 Epoxy mortar kg
M-073 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm
M-090 HTS strand including 5% wastage and extra length for jacking tonne
M-092 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm
M-106 Pesticide kg
M-111 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 855.40
M-116 Primer kg
M-119 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre
M-120 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 6,196.66
M-121 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre
M-123 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre
M-124 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre
Page 5 of 378
M-125 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre
M-126 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre
M-127 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre
M-129 Sand bags (Cost of sand and Empty cement bag) nos
M-132 Seeds kg
M-134 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm
M-137 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 336.78
M-140 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each
M-141 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each
M-142 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos
M-143 Steel helmet and cushion block on top of pile head during driving. kg
M-147 Steel wire rope 40 mm, including 7.50% extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m kg
M-150 Super plastisizer admixture IS marked as per 9103-1999 @ 0.5% by weight of cement kg 154.92
M-151 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm
M-157 Tube anchorage set complete with bearing plate, permanent wedges etc nos
M-166 Wooden staff for fastening of flag 25 mm dia, one m long each
Page 6 of 378
Overheads for Road Works 08 %
Page 7 of 378
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm height
Item 8.3 Printing new letter and figures of any shade (ii) English Roman 0.20
per letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 57.00
Item 8.9 Painting angle iron post two coats sqm 16.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 3,803.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,177.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,313.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 3,322.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4,448.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,241.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,547.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,569.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 5,284.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3,850.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,790.00
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 5,622.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 4,105.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,815.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 4,131.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,817.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 4,133.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,830.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 4,148.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,897.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 4,352.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 5,744.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 4,225.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3,974.00
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) i cum 3,927.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4,134.00
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) ii cum 4,086.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4,160.00
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iii cum 4,114.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4,222.00
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 5,753.00
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iv cum 4,174.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 5,744.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 153.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 31.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,810.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 6,278.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 6,849.30
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 4,803.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 4,003.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 51,136.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 66,706.00
Item 5.17 Fog Seal sqm 30.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 60.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 73.00
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
Item 5.21 Case-IV sqm 96.00
above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 46.00
Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 47.00
Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 32.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 20.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 80.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 64.00
Page 8 of 378
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost RS
Input ref.
Spec.
1.1 Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 13 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 261.00 86.13 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 679.00 224.07 P&M-017
cum/hour
b) Overheads @ 08 % on (a) 24.82
c) Contractors profit @ 10 % on (a+b) 33.50
Cost for 5.5 cum = a+b+c 368.52
Rate per cum = (a+b+c)/ 5.5 67.00
Note Unloading will be by tipping. say 67.00
1.4 Cost of Haulage Excluding Loading and Unloading
Page 9 of 378
Cost for 100 t .km = a+b+c 257.36
Rate per t.Km = (a+b+c)/100 2.57
say 2.60
1.4(III) Case III Katcha Track and Track in river bed / nallah bed and
choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 261.00 261.00 P&M-048
Time taken for empty return trip hour 0.670 261.00 174.87 P&M-048
b) Overheads @ 08 % on (a) 34.87
c) Contractors profit @ 10 % on (a+b) 47.07
Cost for 100 t .km = a+b+c 517.81
Rate per t.Km = (a+b+c)/100 5.18
say 5.20
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 155.00 9.30 L-12
Mazdoor day 1.500 155.00 232.50 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 0.00 0.00 M-003
c) Overheads @ 08 % on (a+b) 19.34
d) Contractors profit @ 10 % on (a+b+c) 26.11
Rate per cum = a+b+c+d 287.26
say 287.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.
Page 10 of 378
e) Contractors profit @ 10 % on (a+b+c+d) 12315.11
Cost for 600 cum = a+b+c+d+e 135466.21
Rate per cum = (a+b+c+d+e)*0.95/600 214.49
say 214.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Page 11 of 378
Mate day 0.760 155.00 117.80 L-12
Mazdoor Skilled day 2.000 176.00 352.00 L-14
Mazdoor day 17.000 155.00 2635.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 0.00 0.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 15354.00 92124.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 679.00 13580.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 261.00 5220.00 P&M-048
d) Overheads @ 08 % on (a+b+c) 9122.30
e) Contractors profit @ 10 % on (a+b+c+d) 12315.11
Cost for 750 cum = (a+b+c+d+e)x0.85 115146.28
Rate per cum = (a+b+c+d+e)x0.85/750 153.53
say 154.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
5.9 510 Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 155.00 68.20 L-12
Mazdoor day 9.000 155.00 1395.00 L-13
Mazdoor skilled day 2.000 196.00 392.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 300.00 2160.00 P&M-031
Air compressor 250 cfm hour 7.200 269.00 1936.80 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2220.00 13320.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 261.00 1566.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00 P&M-017
Bitumen pressure distributor hour 6.000 903.00 5418.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 388.00 2328.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 35472.00 383097.60 M-045
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1423.00 192105.00 M-025
cum per sqm
d) Overheads @ 08 % on (a+b+c) 48628.85
e) Contractors profit @ 10 % on (a+b+c+d) 65648.94
Page 12 of 378
Cost for 9000 sqm= a+b+c+d+e 722138.39
Rate per sqm = (a+b+c+d+e)/9000 80.24
say 80.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 155.00 68.20 L-12
Mazdoor day 9.000 155.00 1395.00 L-13
Mazdoor skilled day 2.000 196.00 392.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 300.00 2160.00 P&M-031
Air compressor 250 cfm hour 7.200 269.00 1936.80 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2220.00 13320.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 261.00 1566.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1298.00 7788.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 35472.00 319248.00 M-045
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1419.00 127710.00 M-024
cum per sqm
d) Overheads @ 08 % on (a+b+c) 38806.08
e) Contractors profit @ 10 % on (a+b+c+d) 52388.21
Cost for 9000 sqm= a+b+c+d+e 576270.29
Rate per sqm = (a+b+c+d+e)/9000 64.03
say 64.00
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
5.15 516 Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 155.00 37.20 L-12
Mazdoor day 6.000 155.00 930.00 L-13
b) Machinery
Page 13 of 378
Mechanical broom hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfm hour 6.000 269.00 1614.00 P&M-001
Mobile slurry seal equipment hour 6.000 849.00 5094.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1047.00 6282.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 261.00 522.00 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 26950.00 521752.00 M-048
Fine aggregate 4.75 mm and below 87 % of total cum 102.080 750.00 76560.00 M-006
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 4400.00 15488.00 M-158
Cost of water KL 12.000 100.00 1200.00 M-159
d) Overheads @ 08 % on (a+b+c) 50953.54
e) Contractors profit @ 10 % on (a+b+c+d) 68787.27
Cost for 16000 sqm= a+b+c+d+e 756660.01
Rate per sqm = (a+b+c+d+e)/16000 47.29
say 47.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 155.00 31.00 L-12
Mazdoor day 5.000 155.00 775.00 L-13
b) Machinery
Mechanical broom hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfm hour 6.000 269.00 1614.00 P&M-001
Mobile slurry seal equipment hour 6.000 849.00 5094.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 261.00 522.00 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 26950.00 462462.00 M-048
Fine aggregate 3 mm and below 85 % of total mix, 60x cum 74.800 750.00 56100.00 M-006
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 4400.00 11616.00 M-158
Cost of water KL 12.000 100.00 1200.00 M-159
d) Overheads @ 08 % on (a+b+c) 43748.32
e) Contractors profit @ 10 % on (a+b+c+d) 59060.23
Cost for 30000 sqm= a+b+c+d+e 649662.55
Rate per sqm = (a+b+c+d+e)/20000 32.48
say 32.00
Page 14 of 378
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 155.00 31.00 L-12
Mazdoor day 5.000 155.00 775.00 L-13
b) Machinery
Mechanical broom hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfm hour 6.000 269.00 1614.00 P&M-001
Mobile slurry seal equipment hour 6.000 849.00 5094.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 261.00 522.00 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 26950.00 341456.50 M-048
Fine aggregate 2.36 mm and below,82 % of total cum 43.300 982.00 42520.60 M-015
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 4400.00 6952.00 M-158
Cost of water KL 12.000 100.00 1200.00 M-159
d) Overheads @ 08 % on (a+b+c) 32608.41
e) Contractors profit @ 10 % on (a+b+c+d) 44021.35
Cost for 24000 sqm= a+b+c+d+e 484234.86
Rate per sqm = (a+b+c+d+e)/24000 20.18
say 20.00
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately
Page 15 of 378
Cost for 10500 sqm= a+b+c+d+e 263357.74
Rate per sqm = (a+b+c+d+e)/10500 25.08
say 25.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 155.00 24.80 L-12
Mazdoor for precoating of grit day 4.000 155.00 620.00 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 1074.00 28192.50 M-016
Bitumenemulsion for precoating grit @ 2 % of tonne 0.790 26950.00 21290.50 M-048
grit,39.38 x 0.02
50127.80
4.77
say 5.00
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20 L-12
Mazdoor day 6.000 155.00 930.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfm hour 6.000 269.00 1614.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00 P&M-004
Hydraulic Chip spreader hour 6.000 2220.00 13320.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00 P&M-044
c) Material
Modified binder tonne 9.450 41024.00 387676.80 M-049
Crushed stone aggregates 5.6 mm size cum 105.000 1074.00 112770.00 M-022
d) Overheads @ 08 % on (a+b+c) 42071.52
e) Contractors profit @ 10 % on (a+b+c+d) 56796.55
Cost for 10500 sqm= a+b+c+d+e 624762.07
Rate per sqm = (a+b+c+d+e)/10500 59.50
say 60.00
Page 16 of 378
Case - II Stress Absorbing Membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20 L-12
Mazdoor day 6.000 155.00 930.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 269.00 1614.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00 P&M-004
Hydraulic Chip spreader hour 6.000 2220.00 13320.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00 P&M-044
c) Material
Modified binder tonne 11.550 41024.00 473827.20 M-049
Crushed stone chipping 11.2 mm size cum 105.000 1376.00 144480.00 M-023
d) Overheads @ 08 % on (a+b+c) 51500.35
e) Contractors profit @ 10 % on (a+b+c+d) 69525.48
Cost for 10500 sqm= a+b+c+d+e 764780.23
Rate per sqm = (a+b+c+d+e)/10500 72.84
say 73.00
Case III Stress Absorbing Membrane (SAM) crack width above
9 mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20 L-12
Mazdoor day 6.000 155.00 930.00 L-13
Mazdoor skilled day 2.000 196.00 392.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 269.00 1614.00 P&M-001
Page 17 of 378
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00 P&M-004
Hydraulic Chip spreader hour 6.000 2220.00 13320.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00 P&M-044
c) Material
Modified binder tonne 15.750 41024.00 646128.00 M-049
Crushed stone aggregates 11.2 mm size cum 126.000 1376.00 173376.00 M-023
d) Overheads @ 08 % on (a+b+c) 67627.46
e) Contractors profit @ 10 % on (a+b+c+d) 91297.07
Cost for 10500 sqm= a+b+c+d+e 1004267.72
Rate per sqm = (a+b+c+d+e)/10500 95.64
say 96.00
Case IV Case - IV : Bitumen Impregnated Geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 155.00 86.80 L-12
Mazdoor day 12.000 155.00 1860.00 L-13
Mazdoor skilled day 2.000 196.00 392.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 300.00 840.00 P&M-031
Air compressor 250 cfem capacity hour 2.800 269.00 753.20 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 903.00 1806.00 P&M-004
Pneumatic roller hour 2.000 1047.00 2094.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 34377.00 126507.36 M-046
kg per sqm
Geotextile including 10 % for overlaps sqm 3850.000 0.00 0.00 M-079
d) Overheads @ 08 % on (a+b+c) 10747.15
e) Contractors profit @ 10 % on (a+b+c+d) 14508.65
Cost for 10500 sqm= a+b+c+d+e 159595.16
Rate per sqm = (a+b+c+d+e)/3500 45.60
say 46.00
NOTE As bitumen overlay construction shallfollow closely the fabric
placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day
Page 18 of 378
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 155 10.85
Painter Ist class day 1.25 196 245.00
Mazdoor day 0.50 155 77.50
b) Material
Paint Litre 0.50 0 0.00
c) Overheads @ 08 % on (a+b) 26.67
d) Contractors profit @ 10 % on (a+b+c) 36.00
Cost for 1600 cm = a+b+c+d 396.02
Rate per cm height per letter = (a+b+c +d)/1600 0.25
say 0.20
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 155 18.60
Painter day 2.00 196 392.00
Mazdoor day 1.00 155 155.00
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.00 225 1350.00
Page 19 of 378
d) Contractors profit @ 10 % on (a+b+c) 14.21
Cost for 10 sqm = a+b+c+d 156.34
Rate per sqm = (a+b+c+d)/10 15.63
say 16.00
12.6 Sub- Cement mortar1:3 (1cement :3 sand)
analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.51 4400.00 2244.00
Sand cum 1.05 750.00 787.50
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.90 155.00 139.50
Total Material and Labour = (a+b) 3177.00
Page 20 of 378
Cement mortar 1:3 (Rate as in item 13.6 D) cum 1.55 2313.00 3585.15
b) Labour
Mate day 0.62 155.00 96.10
Mason day 6.00 196.00 1176.00
Mazdoor day 9.00 155.00 1395.00
c) Overheads @ 20% on (a+b) 2516.70
d) Contractors profit @ 10 % on (a+b+c) 1510.02
Cost for 5 cum = a+b+c+d 16610.19
Rate per cum (a+b+c+d)/5 3322.04
say 3322.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
Page 21 of 378
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,547.00
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 4400.00 22924.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,569.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 4400.00 183304.00
Coarse Sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 166.64 154.92 25815.87
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 km, L-lead in km T-km 300L 7.00 25200.00 L= 12
Concrete Pump hour 6 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,850.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 18475.95
labour and machinery
e) Overheads @ 20% on (a+b+c+d) 96074.92
f) Contractors profit @ 10 % on (a+b+c+d+e) 57644.95
Cost for 120 cum = a+b+c+d+e+f 634094.49
Rate per cum = ( a+b+c+d+e+f )/120 5284.12
say 5284.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Page 22 of 378
Cement MT 5.99 4400.00 26356.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,790.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 4400.00 210980.00
Coarse sand cum 54.00 750.00 40500.00
40 mm Aggregate cum 43.20 1379.00 59572.80
20 mm Aggregate cum 43.20 1423.00 61473.60
10 mm Aggregate cum 21.60 1376.00 29721.60
Admixer Kg 191.80 154.92 29713.66
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 7.00 25200.00 L= 12
1 Km, L - lead in Kilometer
Concrete Pump hour 6 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,105.00
d) Formwork @ 3.75% of cost of concrete i.e.cost of 18472.01
material, labour and machinery
e) Overheads @ 20% on (a+b+c+d) 102211.77
f) Contractors profit @ 10 % on (a+b+c+d+e) 61327.06
cost of 120 cum = a+b+c+d+e+f 674597.70
Rate per cum (a+b+c+d+e+f)/120 5621.65
say 5622.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 4400.00 26620.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Page 23 of 378
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,815.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 4400.00 212872.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 193.52 154.92 29980.12
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity 1 cum hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 7.00 25200.00 L= 12
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,131.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 4400.00 26752.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,817.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 4400.00 213840.00
Coarse sand cum 54.00 750.00 40500.00
40 mm Aggregate cum 43.20 1379.00 59572.80
20 mm Aggregate cum 43.20 1423.00 61473.60
10 mm Aggregate cum 21.60 1376.00 29721.60
Page 24 of 378
Admixer Kg 194.40 154.92 30116.45
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 7.00 25200.00 L= 12
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,133.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.10 4400.00 26840.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,830.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 4400.00 214720.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 195.20 154.92 30240.38
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 7.00 25200.00 L= 12
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,148.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Page 25 of 378
Taking output = 15 cum
a) Material
Cement MT 6.33 4400.00 27852.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,897.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 50.64 4400.00 222816.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 202.56 154.92 31380.60
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 7.00 25200.00 L= 12
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,225.00
d) Formwork @ 3% on cost of concrete i.e.cost of material, 15209.26
labour and machinery
e) Overheads @ 20% on (a+b+c+d) 104436.93
f) Contractors profit @ 10 % on (a+b+c+d+e) 62662.16
cost of 120 cum = a+b+c+d+e+f 689283.75
Rate per cum (a+b+c+d+e+f)/120 5744.03
say 5744.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 4352.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.
C Bottom Plug
Concrete to be placed using tremie pipe
Page 26 of 378
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 4400.00 24420.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixer Kg 18.60 154.92 2881.51
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 300.00 1800.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3974.00
Note 10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 4400.00 195360.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 148.80 154.92 23052.10
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 7.00 25200.00 L= 12
lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3927.00
Page 27 of 378
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixer Kg 21.60 154.92 3346.27
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 300.00 1800.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4134.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 4400.00 210672.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 172.80 154.92 26770.18
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 7.00 25200.00 L= 12
lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4086.00
Page 28 of 378
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 300.00 1800.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4160.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.64 4400.00 214016.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 172.80 154.92 26770.18
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 7.00 25200.00 L= 12
lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4114.00
(iv) PCC Grade M35
Page 29 of 378
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 172.80 154.92 26770.18
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 7.00 25200.00 L= 12
lead in Kilometer
Concrete Pump hour 6.00 215.00 1290.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4174.00
Add 5% of cost of material and labour towards cost of 22183.51
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 4400.00 222816.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 202.56 154.92 31380.60
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader(capacity 1 cum) hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 7.00 25200.00 L= 12
Concrete Pump hour 6.00 215.00 1290.00
Formwork @ 3% of (a+b+c) 15209.26
d) Overheads @ 20% on (a+b+c) 104436.93
e) Contractors profit @ 10 % on (a+b+c+d) 62662.16
cost of 120 cum = a+b+c+d+e 689283.75
Rate per cum (a+b+c+d+e)/120 5744.03
Say 5744.00
Page 30 of 378
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.
B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 155 49.60
Mazdoor day 8.00 155 1240.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1097 6582.00
c) Overheads @ 08 % on (a+b) 629.73
d) Contractors profit @ 10 % on (a+b+c) 850.13
Cost for 300 cum = a+b+c+d 9351.46
Rate per cum = (a+b+c+d)/300 31.17
say 31.00
Note Cost of dewatering upto 5% of (a+b) may be added, where
required. Assessment for dewatering shall be made as per
site conditions..
Page 31 of 378
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage MT 1.05 46300.00 48615.00
Binding wire kg 6.00 78.00 468.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 155.00 52.70
Blacksmith day 2.00 196.00 392.00
Mazdoor day 6.50 155.00 1007.50
c) Overheads @ 20% on (a+b) 10107.04
d) Contractors profit @ 10 % on (a+b+c) 6064.22
Rate for per MT (a+b+c+d) 66706.46
say 66706.00
14.1 1500 Furnishing and Placing Reinforced/Prestressed
&1600 cement concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 4400.00 180048.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 163.68 154.92 25357.31
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 7200.00 L= 12
Concrete Pump hour 6.00 215.00 1290.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
Page 32 of 378
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 4400.00 210980.00
Coarse sand cum 54.20 750.00 40650.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixer Kg 191.80 154.92 29713.66
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 7200.00 L= 12
Concrete Pump hour 6.00 215.00 1290.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 475623.00
120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 95124.60
e) Overheads @ 20% on (a+b+c+d) 114149.52
f) Contractors profit @ 10 % on (a+b+c+d+e) 68489.71
Cost for 15 cum= a+b+c+d+e+f 753386.83
Rate per cum (a+b+c+d+e+f)/120 6278.22
say 6278.00
C RCC Grade M 30
Page 33 of 378
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 7200.00 L= 12
Concrete Pump hour 6.00 215.00 1290.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:
Page 34 of 378
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 2.00 7200.00 L= 12
Concrete Pump hour 6.00 215.00 1290.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 527681.00
120 cum
d) Formwork and staging 18 % of (a+b+c) 18.00 94982.58
e) Overheads @ 20% on (a+b+c+d) 124532.72
f) Contractors profit @ 10 % on (a+b+c+d+e) 74719.63
Cost for 15 cum= a+b+c+d+e+f 821915.93
Rate per cum (a+b+c+d+e+f)/120 6849.30
say 6849.00
Note 1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.
14.2 1600 A) Supplying ,fitting and placing HYSD bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage MT 1.05 46300.00 48615.00
Binding wire Kg 8.00 78.00 624.00
b) Labour for cutting, bending, tying and placing in position
Page 35 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-1
CARRIAGE OF MATERIALS
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading
1.1 point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip) cum 67.00
Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated
1.6 stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and cum 214.00
vibrating screens to obtain stone aggregates of 13 mm nominal size.)
Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
1.7 crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and cum 182.00
vibrating screens to obtain stone aggregates of 20 mm nominal size.)
Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
1.8 crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and cum 154.00
vibrating screens to obtain stone aggregates of 40 mm nominal size.)
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks,
2.1 branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth
filling in the depression/pit.)
Page 36 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
A Rubble stone masonry in lime mortar cum 170.00
B Rubble stone masonry in cement mortar. cum 193.00
C Rubble Stone Masonry in mud mortar. cum 155.00
D Dry rubble masonry cum 147.00
E Dismantling stone pitching/ dry stone spalls. cum 140.00
F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. cum 155.00
(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level cum 328.00
(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.
A Including dismembering tonne 799.00
B Excluding dismembering. tonne 600.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 6.00
(vi) Scraping of bricks dismantled from brick work including stacking.
In lime/Cement mortar 1000
A 670.00
numbers
In mud mortar 1000
B 239.00
numbers
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 269.00
B In Mud mortar cum 57.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 9.00
Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and
(ix) dismantling of masonry works.
A Up to 600 mm dia metre 99.00
B Above 600 mm to 900 mm dia metre 134.00
C Above 900 mm metre 230.00
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead
2.5 of 1000 metres, stacking serviceable and unserviceable materials separately)
I By Manual Means
A Bituminous courses cum 425.00
B Granular courses cum 311.00
II By Mechanical Means
A Bituminous course cum 202.00
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal
2.6 of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately) cum 667.00
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and
2.7 up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.) metre 47.00
Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and
2.8 up to a lead of 1000 metre) metre 10.00
Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material
2.9 with all lifts and up to a lead of 1000 metre) metre 15.00
Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of
2.10 dismantled material with all lifts and lead upto 1000 m and back filling of pit.)
A 5th KM stone each 217.00
B Ordinary KM Stone each 139.00
C Hectometre Stone each 26.00
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back
2.11 filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking metre 27.00
serviceable material and unserviceable material separately. )
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead
2.12 upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of metre 69.00
concerned department)
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia
under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking
2.13 of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.) metre 77.00
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and
2.14 dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to each 98.00
a lead of 1000 metres and stacking the serviceable and unserviceable material separately)
Page 37 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for
3.1 carrying of cut earth to embankment site with all lifts and lead upto1000 metres.) cum 96.00
Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a
3.2 truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres ) cum 136.00
Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means
3.3 including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), cum 126.00
including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by
deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres
3.4 ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross cum 212.00
sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements
3.5 of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres ) cum 187.00
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for
roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom
3.6 and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment cum 37.00
location within all lifts and lead upto 1000m)
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres.
(Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in
3.7 tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in cum 48.00
accordance with requirements of lines, grades and cross sections.)
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock
3.8 breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom
and side slopes in accordance with requirements of lines, grades and cross sections.)
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity
3.10 including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side cum 41.00
slopes in accordance with requirements of lines, grades and cross sections.)
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation,
3.11 loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per cum 37.00
clause 305.)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock
face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the
3.12 excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead sqm 80.00
upto 1000 m, all as specified in clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
3.13 dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally
for road work.)
Page 38 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
B Mechanical Means cum 74.00
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road
3.14 surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. ) sqm 16.00
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing
3.15 bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.) sqm 3.00
Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved
3.16 material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and cum 183.00
compacting to meet requirement of table 300-2)
Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with
3.17 approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures cum 100.00
graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved
3.18 material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and cum 215.00
compacted to meet requirement of table No. 300-2)
Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow
3.21 areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to cum 76.00
maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.)
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or
3.22 other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and sqm 31.00
watering)
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer,
3.23 mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including sqm 79.00
watering for 3 months all as per clause 308)
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to
3.24 specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates
3.28 conforming to table 300-4, excavated material to be utilised in roadway ) metre 140.00
Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined
3.29 with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads) metre 2662.00
Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud
3.30 and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, sqm 2.00
profile and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)
Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not
3.31 exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top cum 57.00
layer with granular material, rolled with vibratory road roller, all complete as per clause 313)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including
3.32 cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) cum 123.00
Page 39 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area
3.33 in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut cum 186.00
material with all lift and lead upto 1000 metres )
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by
3.34 mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.) cum 201.00
Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following
3.35 reasons:)
Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as
waste material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal
3.36 or lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at cum 155.00
OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.)
Page 40 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant
A at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding
the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and
4.5 compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub- cum 581.00
base/base.)
Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base
(Providing, laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread
4.6 Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)
Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse
4.8 sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc) cum 1147.00
Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in
4.9 stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and compacting to the required density.)
A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1870.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2324.98
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1881.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2151.00
Page 41 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(c) Using Screening Type-B (11.2mm Agg.) cum 2274.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 2196.00
(b) Using Screening Type-B (11.2mm Agg.) cum 2588.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1793.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2247.89
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1804.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2074.00
(c) Using Screening Type-B (11.2mm Agg.) cum 2197.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 2119.00
(b) Using Screening Type-B (11.2mm Agg.) cum 2511.00
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement
concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from
4.10 breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, cum 231.00
constructed as WBM to clause 404 except the use of screening or binding Material.)
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface
of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key
4.11 aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8) sqm 28.00
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper
4.12 to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with cum 2170.00
vibratory roller to achieve the desired density.)
Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above
4.13 road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other cum 125.00
structures, spread, graded and compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above
4.14 road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407) cum 204.00
Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles,
4.17 spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of
sub-base/Base)
Page 42 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
5.1 clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.) sqm 21.00
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of
B 0.25 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. sqm 9.30
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to
5.3 site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
5.6 hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)
Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates
5.9 of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel
roller)
Page 43 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required
5.10 line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)
Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less
(i) than 75 tonnes/hour . sqm 126.00
(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 50.00
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity
not less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using
5.11 penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously sqm 146.00
prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade. )
Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and
5.12 cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 58.00
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75
(ii) tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.) sqm 44.00
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to
the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection,
transportation, stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained.
5.13 Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of cum
aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of
carriage may be added to these rates to arrive at the cost at site.)
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
5.14 size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, sqm 455.00
pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous
5.15 emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying
and compacting to provide even riding surface)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 8048.00
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 8026.00
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 2498.00
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 2457.00
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and
5.19 bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings cum 6800.00
including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb
rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP:
53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified
5.20 binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure tonne
uniform dispersion.)
Page 44 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone
(i) aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates sqm 60.00
and surface finished to conform to clause 902.)
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed
(ii) stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished sqm 73.00
to conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and
laying a single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and
cracked area above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521,
(iii) sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sqm 96.00
sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.)
Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after
(iv) cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm 46.00
sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type
5.22 cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with
a smooth steel wheel roller, all as per clause 519.3)
Page 45 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade
with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate
cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less
6.1 than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be cum 2883.00
less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and curing.)
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a
prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation
6.2 including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant cum 4885.00
primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and
grades as per drawing )
Rolled Cement Concrete Base (Construction of rolled cement concrete base course with coarse and fine aggregate
conforming to IS:383, the size of coarse aggregate not exceeding 25 mm with minimum, aggregate cement ratio15:1 and
minimum cement content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, mixing in batching
6.3 plant at optimum moisture content, transporting to site, laying with a paver with electronic sensor, compacting with 8-10 cum 3145.00
tonnes smooth wheeled vibratory roller to achieve, the designed flexural strength, finishing and curing.)
Transition section between rigid and flexible pavement (Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage at the butting
joint. After provision of an expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10 cm
6.4 over a length of 3 m towards the flexible pavement. The deficiency of thickness caused due to tapering of the slab should be
made up by the asphaltic layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction of Base/sub-base using
cement, sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water content ratio,
slump and compressive strength as defined in the said table, mix prepared in a batching and mixing plant and compacted
6.5 with a vibratory roller 8-10 tonnes capacity within the time limit laid down vide clause 7.6.3 of IRC: 74-1979, construction cum 2703.00
joints properly formed at the end of day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel jointed, plain cement concrete
pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size
of coarse aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and sand by 10%, mixed in a
batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread,
6.6 compacted and finished in a continuous operation including provision of contraction, expansion, construction and cum 4750.00
longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing to lines and grades as per drawing )
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using geotextiles treated with
carbon black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite
7.1 structure, joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including metre 158.00
excavation and backfilling)
Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of porous or perforated
7.2 pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed metre 158.00
as per clause 702.3 and 309.3.5 including excavation and backfilling)
Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with physical requirements as
per table 704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over
thoroughly cleaned and repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to
7.3 be free of wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface with pneumatic sqm 44.00
roller to maximise paving fabric contact with pavement surface)
Page 46 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of geogrid crated apron 1 m x
5 m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of
suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to
avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less
7.4 than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping ground and laid over a layer of cum 402.00
geotextile to prevent migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.)
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as under: a) Excavation
for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia
7.5 material). b) Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing
elements. d) Earthfill with granular material which is to be retained by the wall.)
Page 47 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165
mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm
8.1 projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as
per clause 408)
Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction
and place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide
clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron
8.6 post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade sqm 13799.00
cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2
8.7 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles
and trusses of sections and type as per structural design requirements and approved plans)
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after
8.9 through cleaning of surface to give an even shade) sqm 16.00
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface
8.10 after through cleaning of surface to give an even shade) sqm 17.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on
8.11 roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
Page 48 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(ii) Up to 10 cm in width sqm 74.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on
8.12 roads in two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in
8.14 position including painting and printing etc)
(i) 5th kilometre stone (precast) each 2763.00
(ii) Ordinary Kilometer stone (Precast) each 1693.00
(iii) Hectometer stone (Precast) each 483.00
Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100
cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm
8.15 dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.) each 957.00
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in
8.16 position including finishing and lettering but excluding painting) each 452.00
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle
iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6
metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end
8.17 post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI metre 235.00
staples, turn buckles etc complete as per clause 807 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle
iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6
metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end
8.18 post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI metre 393.00
staples, turn buckles etc complete as per clause 807 )
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle
iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete,
8.19 corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x metre 268.00
25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and
8.20 erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 metre 943.00
mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50
8.21 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with metre 518.00
3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of
the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
8.22 board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)
Page 49 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Reinforced Cement Concrete Crash Barrie with M-40 grade concrete (Provision of an Reinforced cement concrete
8.22 © crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-40 grade concrete
Addl. with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-
Analysis for moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to
Bridge MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at
works locations directed by the Engineer, all as specified)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel
B parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to metre 2451.00
be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)
Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by
8.24 specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in
this field and ISI certified for the approved design and drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts
of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m
below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50
m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post
to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist
8.25 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation metre 1699.00
concrete as per approved design and drawing, rate excluding excavation and cement concrete.)
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and
erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre
length and 1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle,
B made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation metre 575.00
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.)
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with
rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an
angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level,
C vertical post firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on metre 800.00
exposed faces, all complete as per approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
8.27 street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the
road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls
at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a
0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to
8.29 minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher
than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)
Page 50 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(ii) Double Row for two utility services metre 1780.00
(iii) Triple Row for three utility services metre 2566.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. )
8.30
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/
subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign
8.31 etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)
Traffic Control System and Communication system (Providing a traffic control centre and communication system
including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer
system These are specialised item of telecommunication system and are the commercial products. The designer is required
8.32 to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.)
Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board
8.33 electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or
galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of
B flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 sqm 424.00
mm steel wire rope as per approved design and drawings)
With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic
C tubes on impact over a pre-determined time, thus absorbing the energy)) sqm 325.00
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
8.35 hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part each 4.00
4:1973)
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE)
8.36 material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as each 2.00
per BS 873)
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the
B quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.)
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where
8.39 necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel each
pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)
High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power
tools for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and
8.40 fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a
specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this work is required to be worked
out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded
as the contractors for road and bridge works generally donot undertake such jobs.)
Page 51 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under
8.41 based on the approved design and drawings:-)
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition
zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road
8.42 level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-2001)
Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5
m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2
8.43 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, each 2469.00
complete as per IRC:SP:55-2001 )
With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high
from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post,
B painted with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 ) each 344.00
With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long,
C 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips) each 22105.00
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter,
8.45 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted each 108.00
with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely
8.46 fastened to a staff 1 m in length for guiding the traffic) each 192.00
CHAPTER-9
PIPE CULVERTS
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size
9.1 mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 3721.00
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row .
(Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular
9.2 material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets . )
Page 52 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-10
MAINTENANCE OF ROADS
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose
10.1 soil, benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate cum 90.00
compactor or power rammers to restore the original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/ irregularities on shoulder to the
10.2 design level by adding fresh approved soil and compacting it with appropriate equipment.) sqm 27.00
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder surface to achieve the
10.3 approved level and compacting with plate compactor) sqm 8.00
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of all failed material,
trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and
base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 511, compacting,
10.4 trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2) sqm 130.00
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. ( Removal of all failed material, trimming
of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of
10.5 excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting,
trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2)
10.7 Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has occurred.) sqm 2.19
10.8 A Fog Seal (ref item 5.17) sqm 30.00
B Crack Prevention courses. (ref item 5.21)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 60.00
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 73.00
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % sqm 96.00
(iv) Bitumen Impregnated Geotextile sqm 46.00
C Slurry Seal (ref item 5.15)
(i) 5 mm thickness sqm 47.00
(ii) 3 mm thickness sqm 32.00
(iii) 1.5 mm thickness sqm 20.00
D Surface Dressing for maintance works. (ref item 5.9)
(i) 19 mm nominal chipping size sqm 80.00
(ii) 13 mm nominal size chipping sqm 64.00
Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints, longitudinal joints and
10.9 expansion joints in concrete pavements using epoxy mortar or epoxy concrete) metre 141.00
Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction, longitudinal or expansion joints
10.10 in concrete pavement with fresh sealant material) metre 12.00
Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on the valley side manually)
10.11 metre 20.00
Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and
10.12 disposal of the same on the valley side) cum 64.00
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock requiring blasting for 50% of
10.13 the boulders and disposal of the same on the valley side.) cum 75.00
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165 Hp and disposing it on
10.14 the valley side) cum 4.00
Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow blower and disposing on
10.15 the valley side.) cum 0.00
Page 53 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard manure or/ and good
11.1 earth in required thickness (cost of sludge, farm- yard manure or/and good earth to be paid for separately)) cum 13.00
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance of the lawn for 30 days
11.2 or more till the grass forms a thick lawn free from weeds and fit for moving including supplying good earth if needed)
Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough grassing) for a period
11.4 of one year including watering etc) sqm 172.00
Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine grassing including
11.5 ploughing, dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots at 10 cm sqm 9.00
apart, including supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 152.00
a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges including digging of
11.7 trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at the rate of metre 52.00
4.65 cum per 100 metres and supplying and planting hedge plants at 30 cm apart)
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil (Renovation lawns
including, weeding, forking the ground, top dressing with forked soil, watering and maintenance the lawns, for 30 days or
11.10 more, till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as directed, including sqm 11.00
supplying good earth, if needed but excluding the cost of well decayed farm yard manure)
Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard manure, from any
11.11 available source, approved by the engineer in charge including screening and stacking) cum
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem cake duly packed in
11.12 used gunny bags) quintal
11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd class brick, internal diametre 1.25
metres, and height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid dry, and top three
11.14 courses in cement mortar 1:6 ( 1 cement 6 sand) and the intermediate courses being in dry honey comb masonry, as each 2816.00
per design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry lengthwise, including
11.15 excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of metre 59.00
50 metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making tree guard 53 cm
dia and 1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the department
11.16 at stock issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect) each 87.00
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums (Making tree guard 53
cm dia and 2 metres high as per design from empty bitumen drums, slit suitably to permit sun and air, ( supplied by the
department at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard
11.17 and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects) each 198.00
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using angles, square bars,
tees and channel grills, grating frames, gates and tree guards of any size and design etc. including cost of screens and
11.18 welding rods or bolts and nuts complete fixed in position but without the cost of excavation and concrete for fixing which will quintal 6977.00
be paid separately)
Page 54 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground level formed
of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted each tree
11.19 together with 8 mm dia and 30 mm long bolts including painting two coats with paint of approved brand over a coat of 1740.00
guard
priming, complete in all respects.)
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre square, 2.00 metre high
fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm dia welded and fabricated as per each tree
11.20 2029.00
design in two halves bolted together) guard
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290 trees per hectare at a
spacing of 6 m by grubbing and leveling the ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing
11.21 farm yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering) hectare 74051.00
Page 55 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
12.1 specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 74.00
(ii) 3 m to 6 m depth cum 96.00
(iii) Above 6 m depth cum 128.00
B Mechanical Means
(i) Depth upto 3 m cum 43.00
(ii) Depth 3 m to 6 m cum 49.00
(iii) Depth above 6m cum 60.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 106.00
B Mechanical Means cum 55.00
III Hard rock ( requiring blasting )
A Manual Means cum 222.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 319.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 321.00
B Mechanical Means cum 83.00
VI Back Filling in Marshy Foundation Pits cum 241.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per
12.2 items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 1014.00
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
12.4 nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 4123.00
Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per
12.5 drawing and technical specifications cum 7923.00
Page 56 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
H RCC Grade M35
Case I Using Concrete Mixer cum 5298.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5744.00
Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.
12.9
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 27885.00
B Assuming depth of water 4.0 m and height of island 4.5 m. each 98684.00
Providing and constructing one span service road to reach island location from one pier location to another
C pier location metre 1488.00
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per
12.10 drawing and technical specification. tonne 80460.00
12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification
A Well curb
(i) RCC M20 Grade
Case I Using concrete mixer cum 5653.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6098.00
(ii) RCC M25 Grade
Case I Using concrete mixer cum 6043.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6544.00
(iii) RCC M35 Grade
Case I Using concrete mixer cum 6173.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6692.00
B Well steining
(I) PCC M15 Grade cum 4706.00
(ii) PCC M20 Grade cum 5150.00
(iii) RCC M20 Grade
Case I Using concrete mixer cum 5182.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5590.00
(iv) PCC M25 Grade
Case I Using concrete mixer cum 5503.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5960.00
(v) RCC M25 Grade
Case I Using concrete mixer cum 5539.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5998.00
(vi) PCC M30 Grade
Case I Using concrete mixer cum 5542.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6001.00
(vii) RCC M30 Grade
Case I Using concrete mixer cum 5561.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6023.00
(viii) RCC M35 Grade
Case I Using concrete mixer cum 5658.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6135.00
(ix) RCC M40 Grade 6192.00
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 5485.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5411.00
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 5707.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5631.00
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 5744.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5669.00
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 5829.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5753.00
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 5246.00
Page 57 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5184.00
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 5457.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5394.00
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 5491.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5430.00
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 4278.00
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 4682.00
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 5003.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5419.00
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 5038.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5456.00
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 4862.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5242.00
(ii) RCC Grade M25
Case I Using concrete Mixer cum 5224.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5658.00
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 5232.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5666.00
(iv) RCC Grade M35
Case I Using Concrete Mixer cum 5298.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5744.00
(v) RCC M40 Grade cum 5828.00
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.12 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 748.00
(ii) Beyond 3m upto 10m depth metre 935.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1236.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2319.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 2782.00
(v) Beyond 30m upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter 5508.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 6610.00
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 941.00
(ii) Beyond 3m upto 10m depth metre 1883.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2486.00
b Add for dewatering @ 5% of cost, if required. metre 2611.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4663.00
b Add 5% of cost for dewatering of the cost, if required metre 6121.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 5829.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11080.00
b Add 5% of cost for dewatering, if required metre 13961.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 13296.00
Page 58 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 6630.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8098.00
b Add for dewatering @ 5% of cost, if required. metre 8503.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12322.00
b Add for dewatering @ 5% of cost, if required. metre 12938.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 23112.00
b Add 5% of cost for dewatering on the cost, if required metre 30334.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 28889.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 54910.00
b Add 5% of cost for dewatering, if required metre 69186.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 65892.00
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 4483.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5474.00
b Add for dewatering @ 5% of cost, if required. metre 5747.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8328.00
b Add for dewatering @ 5% of cost, if required. metre 8745.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 15621.00
b Add 5% of cost for dewatering on the cost, if required metre 20503.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 19526.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 37115.00
b Add 5% of cost for dewatering, if required metre 46765.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 44538.00
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.13 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 1841.00
(ii) Beyond 3m upto 10m depth metre 1122.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1482.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2779.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 3335.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6602.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 7923.00
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 1122.00
(ii) Beyond 3m upto 10m depth metre 1500.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1982.00
b Add for dewatering @ 5% of cost, if required. metre 2081.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3718.00
b Add 5% of cost for dewatering on the cost, if required metre 4880.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 4648.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8835.00
b Add 5% of cost for dewatering, if required metre 11132.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 10602.00
Page 59 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 3854.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4706.00
b Add for dewatering @ 5% of cost, if required. metre 4942.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 7162.00
b Add for dewatering @ 5% of cost, if required. metre 7520.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13436.00
b Add 5% of cost for dewatering on the cost, if required metre 17634.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 16795.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 31922.00
b Add 5% of cost for dewatering, if required metre 40222.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 38306.00
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 5945.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 7260.00
b Add for dewatering @ 5% of cost, if required. metre 7623.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11045.00
b Add for dewatering @ 5% of cost, if required. metre 11598.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 20718.00
b Add 5% of cost for dewatering on the cost, if required metre 27192.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 25897.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 49223.00
b Add 5% of cost for dewatering, if required metre 62021.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 59068.00
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.14 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 1122.00
(ii) Beyond 3m upto 10m depth metre 1317.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1739.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3263.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 3915.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1147.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 1376.00
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 2228.00
(ii) Beyond 3m upto 10m depth metre 1758.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2322.00
b Add for dewatering @ 5% of cost, if required. metre 2438.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4356.00
b Add 5% of cost for dewatering on the cost, if required metre 5717.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 5445.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 10348.00
b Add 5% of cost for dewatering, if required metre 13039.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 12418.00
Page 60 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 4432.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5413.00
b Add for dewatering @ 5% of cost, if required. metre 5684.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8237.00
b Add for dewatering @ 5% of cost, if required. metre 8649.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 15452.00
b Add 5% of cost for dewatering on the cost, if required metre 20281.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 19315.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 36713.00
b Add 5% of cost for dewatering, if required metre 46258.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 44055.00
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 6682.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8161.00
b Add for dewatering @ 5% of cost, if required. metre 8569.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12417.00
b Add for dewatering @ 5% of cost, if required. metre 13037.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 23291.00
b Add 5% of cost for dewatering on the cost, if required metre 30569.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 29114.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 55337.00
b Add 5% of cost for dewatering, if required metre 69725.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 66404.00
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.15 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 1182.00
(ii) Beyond 3m upto 10m depth metre 1437.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1897.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3557.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 4269.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8451.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 10141.00
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 1502.00
(ii) Beyond 3m upto 10m depth metre 1878.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2481.00
b Add for dewatering @ 5% of cost, if required. metre 2606.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4656.00
b Add 5% of cost for dewatering on the cost, if required metre 6111.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 5820.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11063.00
b Add 5% of cost for dewatering, if required metre 13939.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 13275.00
Page 61 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock ( 9m dia well )
(i) Depth upto 3m metre 4753.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5806.00
b Add for dewatering @ 5% of cost, if required. metre 6096.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8834.00
b Add for dewatering @ 5% of cost, if required. metre 9276.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 16569.00
b Add 5% of cost for dewatering on the cost, if required metre 21747.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 20712.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 39368.00
b Add 5% of cost for dewatering, if required metre 49603.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 47241.00
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 7469.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9121.00
b Add for dewatering @ 5% of cost, if required. metre 9577.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13879.00
b Add for dewatering @ 5% of cost, if required. metre 14572.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 26033.00
b Add 5% of cost for dewatering on the cost, if required metre 34168.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 32541.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 61850.00
b Add 5% of cost for dewatering, if required metre 77932.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 74221.00
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.16 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 1242.00
(ii) Beyond 3m upto 10m depth metre 1568.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2071.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3885.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 4662.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9231.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 11077.00
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 1976.00
(ii) Beyond 3m upto 10m depth metre 2136.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 2821.00
b Add for dewatering @ 5% of cost, if required. metre 2963.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5294.00
'b Add 5% of cost for dewatering on the cost, if required metre 6948.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 6617.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 12579.00
b Add 5% of cost for dewatering, if required metre 15850.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 15095.00
Page 62 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 5290.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6462.00
b Add for dewatering @ 5% of cost, if required. metre 6785.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9834.00
b Add for dewatering @ 5% of cost, if required. metre 10325.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 18446.00
b Add 5% of cost for dewatering on the cost, if required metre 24211.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 23058.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 43825.00
b Add 5% of cost for dewatering, if required metre 55220.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 52591.00
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 7332.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8955.00
b Add for dewatering @ 5% of cost, if required. metre 9403.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13626.00
b Add for dewatering @ 5% of cost, if required. metre 14307.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 25557.00
b Add 5% of cost for dewatering on the cost, if required metre 33544.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 31947.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 60721.00
b Add 5% of cost for dewatering, if required metre 76508.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 72865.00
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.17 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 2395.00
(ii) Beyond 3m upto 10m depth metre 3257.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 4302.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8071.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 9685.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 19174.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 23008.00
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 3259.00
(ii) Beyond 3m upto 10m depth metre 4659.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 6154.00
b Add for dewatering @ 5% of cost, if required. metre 6461.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 11541.00
b Add 5% of cost for dewatering on the cost, if required metre 15148.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 14427.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 27419.00
b Add 5% of cost for dewatering, if required metre 34548.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 32903.00
Page 63 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 11728.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 14324.00
b Add for dewatering @ 5% of cost, if required. metre 15040.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 21795.00
b Add for dewatering @ 5% of cost, if required. metre 22884.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 40881.00
b Add 5% of cost for dewatering on the cost, if required metre 53656.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 51101.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 97126.00
b Add 5% of cost for dewatering, if required metre 122379.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 116551.00
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 15600.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 19052.00
b Add for dewatering @ 5% of cost, if required. metre 20005.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 28991.00
b Add for dewatering @ 5% of cost, if required. metre 30440.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 54380.00
b Add 5% of cost for dewatering on the cost, if required metre 71374.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 67975.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 129200.00
b Add 5% of cost for dewatering, if required metre 162792.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 155040.00
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
12.18 namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 5708.00
(ii) Beyond 3m upto 10m depth metre 7304.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 9645.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 18092.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 21711.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 42986.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 51583.00
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7532.00
(ii) Beyond 3m upto 10m depth metre 9849.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13009.00
b Add for dewatering @ 5% of cost, if required. metre 13659.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 24402.00
b Add 5% of cost for dewatering on the cost, if required metre 32028.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 30503.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 57977.00
b Add 5% of cost for dewatering, if required metre 73051.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 69572.00
Page 64 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 25921.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 31657.00
b Add for dewatering @ 5% of cost, if required. metre 33240.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 48170.00
b Add for dewatering @ 5% of cost, if required. metre 50579.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 90355.00
b Add 5% of cost for dewatering on the cost, if required metre 118591.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 112944.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 214671.00
b Add 5% of cost for dewatering, if required metre 270486.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 257606.00
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 30592.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 37362.00
b Add for dewatering @ 5% of cost, if required. metre 39230.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 56850.00
b Add for dewatering @ 5% of cost, if required. metre 59693.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 106636.00
b Add 5% of cost for dewatering on the cost, if required metre 139960.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 133295.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 253353.00
b Add 5% of cost for dewatering, if required metre 319224.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 304023.00
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.19 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 1236.00
(ii) Beyond 3m upto 10m depth metre 1379.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 1821.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3415.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 4098.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8114.00
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 9737.00
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 1629.00
(ii) Beyond 3m upto 10m depth metre 2327.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 3072.00
b Add for dewatering @ 5% of cost, if required. metre 3226.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5761.00
b Add 5% of cost for dewatering on the cost, if required metre 7561.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 7201.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13687.00
b Add 5% of cost for dewatering, if required metre 17246.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 16425.00
Page 65 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 4825.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 5892.00
b Add for dewatering @ 5% of cost, if required. metre 6186.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8964.00
b Add for dewatering @ 5% of cost, if required. metre 9413.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 16814.00
b Add 5% of cost for dewatering on the cost, if required metre 22069.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 21018.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 39949.00
b Add 5% of cost for dewatering, if required metre 50336.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 47939.00
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 7331.00
(ii) Beyond 3m upto 10m depth
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 8954.00
b Add for dewatering @ 5% of cost, if required. metre 9402.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 13625.00
b Add for dewatering @ 5% of cost, if required. metre 14306.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 25555.00
b Add 5% of cost for dewatering on the cost, if required metre 33542.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 31944.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter metre 60717.00
b Add 5% of cost for dewatering, if required metre 76503.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 72860.00
Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by
competent and trained personnel and comprising of compression and decompression chambers, reducers,
two air locks separately for men and plant & materials, arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made from steel plates of riveted construction not less than
6 mm thick to withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required,
12.20 staircases and 1 m wide landing plate forms with railing, arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.
12.21 Sand filling in wells complete as per drawing and technical specifications cum 1014.00
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting
12.22 out as per detailed drawing tonne 73688.00
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.23 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm) metre 5110.00
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.24 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) metre 8409.00
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.25 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm) metre 10862.00
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and &
12.26 Technical Specification (Pile diameter - 750 mm) metre 2556.00
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.27 Technical Specification (Pile diameter - 1000 mm) metre 4551.00
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.28 Technical Specification (Pile diameter - 1200 mm) metre 6552.00
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.29 Technical Specification (Pile Diameter=500 mm) metre 1153.00
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.30 Technical Specification (Pile Diameter=750 mm) metre 2587.00
Page 66 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.31 Technical Specification (Pile Diameter=1000 mm) metre 4811.00
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.32 Technical Specification (Size of pile - 300 mm x 300 mm) metre 535.00
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.33 Technical Specification (Size of pile - 500 mm x 500 mm) metre 1472.00
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.34 Technical Specification (Size of pile - 750 mm x 750 mm) metre 3298.00
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section
12.35 steel column 400 x 250 mm (ISHB Series) ) metre 5309.00
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section
12.36 steel column 450 x 250 mm (ISHB Series) ) metre 5981.00
12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 4871.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 4980.00
B RCC Grade M25
(i) Using concrete mixer. cum 5222.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5330.00
C RCC Grade M30
(i) Using concrete mixer. cum 5266.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5374.00
D RCC Grade M35
(i) Using concrete mixer. cum 5359.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5467.00
12.39 Levelling course for Pile cap cum 4272.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing
12.40 and technical specifications tonne 66617.00
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and
12.41 technical specification tonne 37160.00
Page 67 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and
13.1 technical specifications cum 8139.00
13.2 Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications sqm 366.00
13.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications sqm 844.00
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications
13.4
Page 68 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5718.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6193.00
(r) Height above 10m
Case I Using concrete Mixer cum 5940.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6434.00
H RCC Grade M35
(p) Height upto 5m
Case I Using concrete Mixer cum 5658.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6135.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5782.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6269.00
(r) Height above 10m
Case I Using concrete Mixer cum 5967.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6469.00
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical
13.6 specifications tonne 66707.00
Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and technical
13.7 specification tonne 36730.00
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm
13.8 dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. each 136.00
Complete as per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
13.9
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per tonne
13.11 1.00
drawing and Technical Specifications. capacity
Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per tonne
13.12 1.00
drawing and Technical Specifications. capacity
Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, tonne
13.13 4.00
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications. capacity
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and cubic
13.14 2.00
Technical Specifications. centimetre
Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix complete including all accessories as per drawing and tonne
13.15 3.00
Technical Specifications. capacity
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals,
PTFE surface sliding against stainless steel mating surface, completre assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts tonne
13.16 166.00
conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing capacity
and approved technical specifications.
Page 69 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and
14.1 Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5610.00
(q) Height 5m to 10m cum 5844.00
(r) Height above 10m cum 6078.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 5844.00
(q) Height 5m to 10m cum 6078.00
(r) Height above 10m cum 6312.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6048.00
(q) Height 5m to 10m cum 6300.00
(r) Height above 10m cum 6552.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6300.00
(q) Height 5m to 10m cum 6552.00
(r) Height above 10m cum 6804.00
B RCC Grade M25
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6015.00
(q) Height 5m to 10m cum 6265.00
(r) Height above 10m cum 6516.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6265.00
(q) Height 5m to 10m cum 6516.00
(r) Height above 10m cum 6766.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6516.00
(q) Height 5m to 10m cum 6787.00
(r) Height above 10m cum 7059.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6787.00
(q) Height 5m to 10m cum 7059.00
(r) Height above 10m cum 7330.00
C RCC Grade M 30
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6083.00
(q) Height 5m to 10m cum 6336.00
(r) Height above 10m cum 6590.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6336.00
(q) Height 5m to 10m cum 6590.00
(r) Height above 10m cum 6843.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6578.00
(q) Height 5m to 10m cum 6852.00
(r) Height above 10m cum 7126.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6852.00
(q) Height 5m to 10m cum 7126.00
Page 70 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(r) Height above 10m cum 7400.00
D RCC/PSC Grade M35
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6086.00
(q) Height 5m to 10m cum 6344.00
(r) Height above 10m cum 6602.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6344.00
(q) Height 5m to 10m cum 6602.00
(r) Height above 10m cum 6860.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7118.00
(q) Height 5m to 10m cum 7634.00
(r) Height above 10m cum 8150.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6583.00
(q) Height 5m to 10m cum 6862.00
(r) Height above 10m cum 7140.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6862.00
(q) Height 5m to 10m cum 7140.00
(r) Height above 10m cum 7419.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7698.00
(q) Height 5m to 10m cum 8256.00
(r) Height above 10m cum 8814.00
E PSC Grade M-40
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6695.00
(q) Height 5m to 10m cum 6974.00
(r) Height above 10m cum 7253.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6974.00
(q) Height 5m to 10m cum 7253.00
(r) Height above 10m cum 7532.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6649.00
(q) Height 5m to 10m cum 6930.00
(r) Height above 10m cum 7212.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6930.00
(q) Height 5m to 10m cum 7212.00
(r) Height above 10m cum 7494.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7775.00
(q) Height 5m to 10m cum 8339.00
(r) Height above 10m cum 8902.00
F PSC Grade M-45
(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
(p) Height upto 5m cum 6805.00
(q) Height 5m to 10m cum 7098.00
(r) Height above 10m cum 7392.00
For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31% of cost of
(ii) concrete.
(p) Height upto 5m cum 7098.00
(q) Height 5m to 10m cum 7392.00
Page 71 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(r) Height above 10m cum 7685.00
(iii) For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of concrete.
(p) Height upto 5m cum 7978.00
(q) Height 5m to 10m cum 8565.00
(r) Height above 10m cum 9151.00
G PSC Grade M-50
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 8143.00
(q) Height 5m to 10m cum 8746.00
(r) Height above 10m cum 9350.00
H PSC Grade M- 55
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 8493.00
(q) Height 5m to 10m cum 9123.00
(r) Height above 10m cum 9751.78
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and
14.2 technical specifications tonne 67500.00
High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting
14.3 complete as per drawing and Technical Specifications tonne 10161.00
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per
14.4 drawing and Technical Specifications cum 10377.00
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat
with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained
14.5 hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm sqm 258.00
center to center in both directions, pressed into surface when the temperature of surfaces not less than 100 deg. C,
protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and
grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post
14.6 not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per metre 1774.00
approved drawings and technical specifications.
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade,
tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to
14.7 exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved metre 1721.00
drawings and technical specifications.
14.8 Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification metre 3014.00
14.9 Drainage Spouts complete as per drawing and Technical specification each 1214.00
14.10 PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification cum 4448.00
Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and
14.11 Technical specification cum 9969.00
Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) (To be
14.12 taken as per the prevailing market rates.) tonne
Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast pretensioned
14.13 concrete girders as per drawing and technical specifications) cum 14246.00
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 56.00
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal
14.15 beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete
14.16 surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. ) metre 66.00
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick,
200 mm wide galvanised wieldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint,
14.17 resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 metre 843.00
mm c/c along the centre line of the plate, all as specified in clause 2604.)
Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing &
(ii) Technical Specification. metre 4.00
Page 72 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply
(iii) supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant metre 344.00
complete as per drawing and technical specifications.
Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand
(iv) and 6% bitumen by weight metre 16.00
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic
14.19 plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a metre 523.00
heat resistant foam caulking/backer rod, all as per approved drawings and specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint, catering to
right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per
approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised
14.20 representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH metre 29.00
specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at two edges
of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint
14.21 sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm metre 18.00
and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal
movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the
14.22 manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for metre 22429.00
installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including anchorage
catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard
14.23 specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the metre 27.00
manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a horizontal
movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be
14.24 installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's metre 33.00
instructions for installation.)
Page 73 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not
15.1 less than 40 kg each complete as per drawing and Technical specification.
A Boulder laid dry without wire crates. cum 1190.00
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire
15.2 conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra for laps and joints laid cum 1123.00
with stone boulders weighing not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of size
15.3 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of cum 4537.00
250 kg/cum as per IRC: 21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front
15.4 of toe of embankment complete as per drawing and Technical specifications
A Stone/Boulder cum 1836.00
B Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 cum 4537.00
Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical
15.5 specification cum 1389.00
Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent
15.6 escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free sqm 9.00
movement of water without creating any uplift head on the pitching.)
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching
with stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been used for pitching . Rates
15.7 for toe wall can be adopted from respective clauses depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)
Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete
15.8 bedding.
A Rubble stone laid in cement mortar 1:3 cum 3865.00
B Cement Concrete blocks Grade M15 cum 5975.00
15.9 Dry rubble Flooring cum 1409.00
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 3177.00
B Cement concrete Grade M15 cum 4448.00
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less
15.11 than 40 kg beyond curtain wall. cum 1230.00
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments
of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and
15.12 galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, cum 1732.00
filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel wire)
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing
gabain structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m
each divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having
15.13 minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into cum 1738.00
mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm,
all loose ends to be securely tied with 4 mm galvanised steel wire.)
Page 74 of 378
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-16
REPAIR AND REHABILITATION
Removal of existing cement concrete wearing coat including its disposal complete as per Technical
16.1 specification without causing any detrimental effect to any part of the bridge structure and removal of sqm 77.00
dismantled material with all lifts and lead upto 1000m(Thickness 75 mm)
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick
16.2 mastic asphalt including disposal with all lift and lead upto 1000m. sqm 59.00
Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying
16.3 with epoxy complete as per Technical specification sqm 460.00
Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical
16.4 specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after each 57.00
completion of grouting with Cement/Epoxy
Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical
16.5 specification.
A Cement Grout kg 17.00
B Cement mortar (1:1) Grouting kg 67.00
Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter,
16.6 available in present formulations, to be applied as per instructions of manufacturer and as approved by the sqm 36.00
Engineer.
Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1.
16.7 kg 208.00
Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel
16.8 reinforcement complete as per Technical specification sqm 24.00
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically
with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick
setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383
16.9 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less sqm 228.00
than 2000 kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6.
Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled
16.10 concrete sqm 24.00
Providing external prestressing with high tensile steel wires/strands including drilling for passage of
16.13 prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing tonne 172993.00
and Technical specification
Providing external prestressing with high tensile steel wires/strands including drilling for passage of
16.14 prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing tonne 156213.00
and Technical specification
16.22 Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) metre 119.00
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 269.00
Page 75 of 378
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-1
CARRIAGE OF MATERIALS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
1.1 Loading and Unloading of Stone Boulder/Stone cum
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 261.00 86.13
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 679.00 224.07
cum/hour
b) Overhead charges @ 08 % on (a) 24.82
c) Contractor's profit @ 10 % on (a+b) 33.50
Cost for 5.5 cum = a+b+c 368.52
Rate per cum = (a+b+c)/ 5.5 67.00
Note Unloading will be by tipping. say 67.00
1.2 Loading and Unloading of Boulders by Manual Means
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 155.00 17.05
Mazdoor for loading and unloading day 0.750 155.00 116.25
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 261.00 195.75
c) Overhead charges @ 08 % on (a+b) 26.32
d) Contractor's profit @ 10 % on (a+b+c) 35.54
Cost for5.5 cum = a+b+c+d 390.91
Rate per cum = (a+b+c+d)/5.5 71.07
Note Unloading will be by tipping. say 71.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor for loading and unloading day 2.000 155.00 310.00
b) Machinery
Truck 10 tonne capacity hour 2.000 243.00 486.00
c) Overhead charges @ 08 % on (a+b) 64.67
d) Contractor's profit @ 10 % on (a+b+c) 87.31
Cost for10 tonnes = a+b+c+d 960.38
Rate per tonnes = (a+b+c+d)/10 96.04
say 96.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km
(i) Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 261.00 104.40
Time taken for empty return trip. hour 0.290 261.00 75.69
b) Overhead charges @ 08 % on (a) 14.41
c) Contractor's profit @ 10 % on (a+b) 19.45
cost for 100 t km = a+b+c 213.95
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per t.km = (a+b+c)/100 2.14
say 2.10
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 261.00 130.50
Time taken for empty return trip hour 0.330 261.00 86.13
b) Overhead charges @ 08 % on (a) 17.33
c) Contractor's profit @ 10 % on (a+b) 23.40
Cost for 100 t .km = a+b+c 257.36
Rate per t.Km = (a+b+c)/100 2.57
say 2.60
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 261.00 261.00
Time taken for empty return trip hour 0.670 261.00 174.87
b) Overhead charges @ 08 % on (a) 34.87
c) Contractor's profit @ 10 % on (a+b) 47.07
Cost for 100 t .km = a+b+c 517.81
Rate per t.Km = (a+b+c)/100 5.18
say 5.20
1.5 Hand Broken Stone Aggregates 63 mm Nominal Size
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Integrated stone crusher of 200 TPH including belt Hour 6.000 15354.00 92124.00
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 679.00 13580.00
Tipper 5.5 cum capacity Hour 20.000 261.00 5220.00
d) Overhead charges @ 08 % on (a+b+c) 9122.30
e) Contractor's profit @ 10 % on (a+b+c+d) 12315.11
Cost for 600 cum = a+b+c+d+e 135466.21
Rate per cum = (a+b+c+d+e)*0.95/600 214.49
say 214.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
1.7 Crushing of Stone Aggregates 20 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 155.00 117.80
Mazdoor Skilled day 2.000 176.00 352.00
Mazdoor including breaking of any size boulder. day 17.000 155.00 2635.00
b) Material
Stone Boulder of size 150 mm and below cum 800.000 0.00 0.00
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 15354.00 92124.00
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 679.00 13580.00
Tipper 5.5 cum capacity Hour 20.000 261.00 5220.00
d) Overhead charges @ 08 % on (a+b+c) 9122.30
e) Contractor's profit @ 10 % on (a+b+c+d) 12315.11
Cost for 670 cum = a+b+c+d+e 135466.21
Rate per cum = (a+b+c+d+e)*0.90/670 181.97
say 182.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Stone Boulder of size 150 mm and below cum 800.000 0.00 0.00
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 15354.00 92124.00
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 679.00 13580.00
Tipper 5.5 cum capacity Hour 20.000 261.00 5220.00
d) Overhead charges @ 08 % on (a+b+c) 9122.30
e) Contractor's profit @ 10 % on (a+b+c+d) 12315.11
Cost for 750 cum = (a+b+c+d+e)x0.85 115146.28
Rate per cum = (a+b+c+d+e)x0.85/750 153.53
say 154.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
CHAPTER-2
SITE CLEARANCE
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches
and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 155.00 3.10
Mazdoors for cutting trees including cutting, refilling, day 0.600 155.00 93.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 306.00 30.60
c) Overhead charges @ 08 % on (a+b) 10.14
d) Contractor's profit @ 10 % on (a+b+c) 13.68
Rate for each tree = a+b+c+d 150.52
say 151.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 155.00 6.20
Mazdoors for cutting trees including cutting, refilling, day 0.900 155.00 139.50
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 306.00 91.80
c) Overhead charges @ 08 % on (a+b) 19.00
d) Contractor's profit @ 10 % on (a+b+c) 25.65
Rate for each tree = a+b+c+d 282.15
say 282.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoors for cutting trees including cutting, refilling, day 2.000 155.00 310.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 306.00 122.40
c) Overhead charges @ 08 % on (a+b) 35.58
d) Contractor's profit @ 10 % on (a+b+c) 48.04
Rate for each tree = a+b+c+d 528.42
say 528.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 155.00 24.80
Mazdoors for cutting trees including cutting, refilling, day 4.000 155.00 620.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 306.00 183.60
c) Overhead charges @ 08 % on (a+b) 66.27
d) Contractor's profit @ 10 % on (a+b+c) 89.47
Rate for each tree = a+b+c+d 984.14
say 984.00
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
a) Labour
Mate day 2.000 155.00 310.00
Mazdoor day 50.000 155.00 7750.00
b) Overhead charges @ 08 % on (a) 644.80
c) Contractor's profit @ 10 % on (a+b) 870.48
Rate per Hectare = a+b+c 9575.28
say 9575.00
2.3 8.01 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.
Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 155.00 24.80
Mazdoor day 4.000 155.00 620.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 3133.00 31330.00
stumps
Tractor-trolley hour 1.000 306.00 306.00
c) Overhead charges @ 08 % on (a+b) 2582.46
d) Contractor's profit @ 10 % on (a+b+c) 3486.33
Rate per Hectare = a+b+c+d 38349.59
say 38350.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 12.000 3133.00 37596.00
stumps
Tractor-trolley hour 1.500 306.00 459.00
c) Overhead charges @ 08 % on (a+b) 3121.78
d) Contractor's profit @ 10 % on (a+b+c) 4214.40
Rate per Hectare = a+b+c+d 46358.37
say 46358.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
2.4 8.03 II By Mechanical Means for items No. 202( b)& ( c)
2.4 II B Prestressed / reinforced cement concrete grade M-20
& above
a) Labour
Mate day 0.050 155.00 7.75
Mazdoor with Pneumatic breaker day 0.660 176.00 116.16
Blacksmith day 0.250 196.00 49.00
Mazdoor for loading and unloading day 0.250 155.00 38.75
b) Machinery
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Air Compressor 250 cfm with 2 leads of pneumatic hour 1.000 269.00 269.00
breaker @ 1.00 cum per hour
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 45.06
d) Contractor's profit @ 10 % on (a+b+c) 60.83
Cost for 1.25 cum = a+b+c+d 669.18
Rate per cum = (a+b+c+d)/ 1.25 535.34
say 535.00
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor for dismantling, loading and unloading day 0.500 155.00 77.50
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 13.06
d) Contractor's profit @ 10 % on (a+b+c) 17.63
Cost for 1.25 cum = a+b+c+d 193.91
Rate per cum = (a+b+c+d)/ 1.25 155.12
say 155.00
2.4 (ii) B In cement mortar
a) Labour
Mate day 0.030 155.00 4.65
Mazdoor for dismantling, loading and unloading day 0.750 155.00 116.25
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 16.28
d) Contractor's profit @ 10 % on (a+b+c) 21.98
Cost for 1.25 cum = a+b+c+d 241.78
Rate per cum = (a+b+c+d)/ 1.25 193.43
say 193.00
2.4 (ii) C In mud mortar
a) Labour
Mate day 0.016 155.00 2.48
Mazdoor for dismantling and loading day 0.400 155.00 62.00
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 11.77
d) Contractor's profit @ 10 % on (a+b+c) 15.89
Cost for 1.25 cum = a+b+c+d 174.75
Rate per cum = (a+b+c+d)/ 1.25 139.80
say 140.00
2.4 (ii) D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 155.00 2.17
Mazdoor for Dismantling, loading and unloading day 0.350 155.00 54.25
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 11.12
d) Contractor's profit @ 10 % on (a+b+c) 15.02
Cost for 1.25 cum = a+b+c+d 165.18
Rate per cum = (a+b+c+d)/ 1.25 132.14
say 132.00
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mate day 0.024 155.00 3.72
Mazdoor for dismantling, loading and unloading. day 0.600 155.00 93.00
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 14.35
d) Contractor's profit @ 10 % on (a+b+c) 19.37
Cost for 1.25 cum = a+b+c+d 213.06
Rate per cum = (a+b+c+d)/ 1.25 170.44
say 170.00
2.4 (iii) B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 155.00 4.65
Mazdoor for dismantling, loading and unloading. day 0.750 155.00 116.25
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 16.28
d) Contractor's profit @ 10 % on (a+b+c) 21.98
Cost for 1.25 cum = a+b+c+d 241.78
Rate per cum = (a+b+c+d)/ 1.25 193.43
say 193.00
2.4 (iii) C Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor for dismantling, loading and unloading. day 0.500 155.00 77.50
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 13.06
d) Contractor's profit @ 10 % on (a+b+c) 17.63
Cost for 1.25 cum = a+b+c+d 193.91
Rate per cum = (a+b+c+d)/ 1.25 155.12
say 155.00
2.4 (iii) D Dry rubble masonry
a) Labour
Mate day 0.018 155.00 2.79
Mazdoor for dismantling, loading and unloading. day 0.450 155.00 69.75
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 12.41
d) Contractor's profit @ 10 % on (a+b+c) 16.76
Cost for 1.25 cum = a+b+c+d 184.33
Rate per cum = (a+b+c+d)/ 1.25 147.46
say 147.00
2.4 (iii) E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 155.00 2.48
Mazdoor for dismantling, loading and unloading. day 0.400 155.00 62.00
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 11.77
d) Contractor's profit @ 10 % on (a+b+c) 15.89
Cost for 1.25 cum = a+b+c+d 174.75
Rate per cum = (a+b+c+d)/ 1.25 139.80
say 140.00
2.4 (iii) F Dismantling boulders laid in wire crates including
opening of crates and stacking dismantled materials.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor for dismantling, loading and unloading day 0.500 155.00 77.50
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 13.06
d) Contractor's profit @ 10 % on (a+b+c) 17.63
Cost for 1.25 cum = a+b+c+d 193.91
Rate per cum = (a+b+c+d)/ 1.25 155.12
say 155.00
2.4 (iv) Wood Work wrought framed and fixed in frames of
trusses upto a height of 5 m above plinth level
a) Labour
Mate day 0.060 155.00 9.30
Carpenter day 0.500 196.00 98.00
Mazdoor for dismantling, loading and unloading. day 1.000 155.00 155.00
b) Machinery
Tractor-trolley hour 0.270 306.00 82.62
c) Overhead charges @ 08 % on (a+b) 27.59
d) Contractor's profit @ 10 % on (a+b+c) 37.25
Cost for 1.25 cum = a+b+c+d 409.76
Rate per cum = (a+b+c+d)/ 1.25 327.81
say 328.00
2.4 (v) Steel Work in all types of sections upto a height of 5 m
above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 155.00 21.70
Blacksmith day 1.000 196.00 196.00
Mazdoor for dismantling, loading and unloading day 2.500 155.00 387.50
Add 2.5 per cent of cost of labour for gas cutting, ropes, 15.13
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 306.00 52.02
c) Overhead charges @ 08 % on (a+b) 53.79
d) Contractor's profit @ 10 % on (a+b+c) 72.61
Rate per tonne = a+b+c+d 798.75
say 799.00
2.4 (v) B Excluding dismembering.
a) Labour
Mate day 0.220 155.00 34.10
Mazdoor for dismantling, loading and unloading day 2.000 155.00 310.00
Blacksmith day 0.500 196.00 98.00
Add 2.5 per cent of cost of labour for gas cutting, ropes, 11.05
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 306.00 52.02
c) Overhead charges @ 08 % on (a+b) 40.41
d) Contractor's profit @ 10 % on (a+b+c) 54.56
Rate per tonne = a+b+c+d 600.14
say 600.00
2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mate day 0.010 155.00 1.55
Blacksmith day 0.130 196.00 25.48
Mazdoor day 0.130 155.00 20.15
b) Overhead charges @ 08 % on (a) 3.77
c) Contractor's profit @ 10 % on (a+b) 5.10
Cost for 10 rivets = a+b+c 56.05
Rate for each rivet = ( a+b+c)/10 5.60
say 6.00
2.4 (vi) Scraping of Bricks Dismantled from Brick Work
including Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 155.00 21.70
Mazdoor day 3.500 155.00 542.50
b) Overhead charges @ 08 % on (a) 45.14
c) Contractor's profit @ 10 % on (a+b) 60.93
Rate per1000 Nos = a+b+c 670.27
say 670.00
2.4 (iv) B In mud mortar
a) Labour
Mate day 0.050 155.00 7.75
Mazdoor day 1.250 155.00 193.75
b) Overhead charges @ 08 % on (a) 16.12
c) Contractor's profit @ 10 % on (a+b) 21.76
Rate per1000 Nos = a+b+c 239.38
say 239.00
2.4 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 155.00 9.30
Mazdoor day 1.400 155.00 217.00
b) Overhead charges @ 08 % on (a) 18.10
c) Contractor's profit @ 10 % on (a+b) 24.44
Rate per cum = a+b+c 268.84
say 269.00
2.4 B In Mud mortar
(vii)
a) Labour
Mate day 0.010 155.00 1.55
Mazdoor day 0.300 155.00 46.50
b) Overhead charges @ 08 % on (a) 3.84
c) Contractor's profit @ 10 % on (a+b) 5.19
Rate per cum = a+b+c 57.08
say 57.00
2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/
Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 155.00 24.80
Mazdoor for scarping and loading day 4.000 155.00 620.00
b) Machinery
Tractor-trolley hour 0.320 306.00 97.92
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Overhead charges @ 08 % on (a+b) 59.42
d) Contractor's profit @ 10 % on (a+b+c) 80.21
Cost for 100 sqm = a+b+c+d 882.35
Rate per sqm = (a+b+c+d)/100 8.82
say 9.00
2.4 (ix) Removing all type of Hume Pipes and Stacking within
a lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.520 155.00 80.60
b) Overhead charges @ 08 % on (a) 6.70
c) Contractor's profit @ 10 % on (a+b) 9.04
Rate per metre = a+b+c 99.44
say 99.00
2.4 (ix) B Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 155.00 4.65
Mazdoor day 0.700 155.00 108.50
b) Overhead charges @ 08 % on (a) 9.05
c) Contractor's profit @ 10 % on (a+b) 12.22
Rate per metre = a+b+c 134.42
say 134.00
2.4 (ix) C Above 900 mm
a) Labour
Mate day 0.050 155.00 7.75
Mazdoor day 1.200 155.00 186.00
b) Overhead charges @ 08 % on (a) 15.50
c) Contractor's profit @ 10 % on (a+b) 20.93
Rate per metre = a+b+c 230.18
say 230.00
Note 1. The excavation of earth, dismantling of stone masonry
work in head walls and protection works is not included
which is to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be
taken as per actual availability.
2.5 9.02 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 155.00 9.30
Mazdoor for dismantling, loading and unloading day 1.500 155.00 232.50
b) Machinery
Tractor-trolley hour 0.380 306.00 116.28
c) Overhead charges @ 08 % on (a+b) 28.65
d) Contractor's profit @ 10 % on (a+b+c) 38.67
Rate per cum = a+b+c+d 425.40
say 425.00
2.5 I B Granular courses
a) Labour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mate day 0.040 155.00 6.20
Mazdoor for dismantling, loading and unloading. day 1.000 155.00 155.00
b) Machinery
Tractor-trolley hour 0.330 306.00 100.98
c) Overhead charges @ 08 % on (a+b) 20.97
d) Contractor's profit @ 10 % on (a+b+c) 28.32
Rate per cum = a+b+c+d 311.47
say 311.00
2.5 II By Mechanical Means
202 A Bituminous course
a) Labour
Mate day 0.010 155.00 1.55
Mazdoor day 0.300 155.00 46.50
b) Machinery
Tractor-trolley hour 0.380 306.00 116.28
Farm tractor with ripper @ 60 cum per hour hour 0.017 329.00 5.59
c) Overhead charges @ 08 % on (a+b) 13.59
d) Contractor's profit @ 10 % on (a+b+c) 18.35
Rate per cum = a+b+c+d 201.87
say 202.00
2.6 202 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by mechanical
means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 155.00 4.65
Semi skilled mazdoor for operating pneumatic tools day 0.500 176.00 88.00
Mazdoors as helpers including loading and unloading day 0.500 155.00 77.50
b) Machinery
Air compressor 250 cfm with two leads for pneumatic hour 1.000 269.00 269.00
cutters/ hammers @ 1 cum per hour
Tractor-trolley hour 0.400 306.00 122.40
Joint Cutting Machine with 2-3 blades hour 1.000 0.00 0.00
c) Overhead charges @ 08 % on (a+b) 44.92
d) Contractor's profit @ 10 % on (a+b+c) 60.65
Rate per cum = a+b+c+d 667.12
say 667.00
Note The above analysis is for removal of complete pavement. In
case full depth repair work is required to be done after
dismantling, provision of a concrete cutting and sawing
machine may be added for 0.25 hours.
2.7 202 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable materials and unserviceable
materials separately.
Unit = running metre
Taking output = 1 metre
a) Labour
Mate day 0.006 155.00 0.93
Mazdoor including loading and unloading day 0.150 155.00 23.25
b) Machinery
Tractor-trolley hour 0.050 306.00 15.30
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Overhead charges @ 08 % on (a+b) 3.16
d) Contractor's profit @ 10 % on (a+b+c) 4.26
Rate per metre = a+b+c+d 46.90
say 47.00
2.8 202 Dismantling of Kerb Stone
Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.010 155.00 1.55
Mazdoor including loading and unloading day 0.150 155.00 23.25
b) Machinery
Tractor-trolley hour 0.200 306.00 61.20
c) Overhead charges @ 08 % on (a+b) 6.88
d) Contractor's profit @ 10 % on (a+b+c) 9.29
Cost for 10 m = a+b+c+d 102.17
Rate per metre = (a+b+c+d)/10 10.22
say 10.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.015 155.00 2.33
Mazdoor including loading and unloading day 0.225 155.00 34.88
b) Machinery
Tractor-trolley hour 0.300 306.00 91.80
c) Overhead charges @ 08 % on (a+b) 10.32
d) Contractor's profit @ 10 % on (a+b+c) 13.93
Cost for 10 m = a+b+c+d 153.25
Rate per metre = (a+b+c+d)/10 15.33
say 15.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 155.00 20.15
Mazdoor day 0.750 155.00 116.25
b) Machinery
Tractor-trolley hour 0.150 306.00 45.90
c) Overhead charges @ 08 % on (a+b) 14.58
d) Contractor's profit @ 10 % on (a+b+c) 19.69
Rate for one 5th KM stone = a+b+c+d 216.57
say 217.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.500 155.00 77.50
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) Machinery
Tractor-trolley hour 0.120 306.00 36.72
c) Overhead charges @ 08 % on (a+b) 9.39
d) Contractor's profit @ 10 % on (a+b+c) 12.67
Rate for one ordinary KM stone = a+b+c+d 139.38
say 139.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 155.00 0.62
Mazdoor day 0.100 155.00 15.50
b) Machinery
Tractor-trolley hour 0.020 306.00 6.12
c) Overhead charges @ 08 % on (a+b) 1.78
d) Contractor's profit @ 10 % on (a+b+c) 2.40
Rate for one Hectometre stone = a+b+c+d 26.42
say 26.00
2.11 202 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing
including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with
all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.13 202 Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including
disposal with all lifts and up to a lead of 1000 metres and
stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of
masonry works.
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.100 155.00 15.50
Mazdoor day 2.500 155.00 387.50
b) Machinery
Crane 5 tonne capacity hour 0.300 0.00 0.00
Truck flat body 10 tonne hour 1.000 243.00 243.00
c) Overhead charges @ 08 % on (a+b) 51.68
d) Contractor's profit @ 10 % on (a+b+c) 69.77
Cost for 10 metres = a+b+c+d 767.45
Rate per metre = (a+b+c+d)/10 76.74
say 77.00
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.14 202 Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the
supervision of concerned department, disposal with all lifts
and up to a lead of 1000 metres and stacking the
serviceable and unserviceable material separately
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor day 10.000 155.00 1550.00
Electrician/Lineman day 2.000 196.00 392.00
b) Machinery
Tractor-trolley hour 1.500 306.00 459.00
c) Overhead charges @ 08 % on (a+b) 198.03
d) Contractor's profit @ 10 % on (a+b+c) 267.34
Cost for 30 poles = a+b+c+d 2940.78
Rate per pole = (a+b+c+d)/30 98.03
say 98.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
3.1 9.05 d 301 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 155.00 279.00
Mazdoor day 45.000 155.00 6975.00
b) Machinery
Truck 5.5 cum capacity hour 10.000 243.00 2430.00
c) Overhead charges @ 08 % on (a+b) 774.72
d) Contractor's profit @ 10 % on (a+b+c) 1045.87
Cost of 120 cum = a+b+c+d 11504.59
Rate per cum = (a+b+c+d)/120 95.87
say 96.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
3.2 301 Excavation in Ordinary Rock by Manual Means
Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 155.00 434.00
Mazdoor day 70.000 155.00 10850.00
b) Machinery
Truck 5.5 cum capacity hour 10.000 243.00 2430.00
c) Overhead charges @ 08 % on (a+b) 1097.12
d) Contractor's profit @ 10 % on (a+b+c) 1481.11
Cost for 120 cum = a+b+c+d 16292.23
Rate per cum = (a+b+c+d)/120 135.77
say 136.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
3.3 301 Excavation in Soil with Dozer with lead upto 100
metres
Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3133.00 18798.00
c) Overhead charges @ 08 % on (a+b) 1529.63
d) Contractor's profit @ 10 % on (a+b+c) 2065.00
Cost for 180 cum = a+b+c+d 22715.04
Rate per cum = (a+b+c+d)/180 126.19
say 126.00
3.4 301 Excavation in Ordinary Rock with Dozer with lead upto
100 metres
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 3.000 155.00 465.00
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 3133.00 18798.00
c) Overhead charges @ 08 % on (a+b) 1542.53
d) Contractor's profit @ 10 % on (a+b+c) 2082.41
Cost for 108 cum = a+b+c+d 22906.54
Rate per cum = (a+b+c+d)/108 212.10
say 212.00
3.5 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 155.00 34.10
Mazdoor day 3.000 155.00 465.00
Driller day 2.000 155.00 310.00
Blaster day 0.250 155.00 38.75
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3133.00 18798.00
Air compressor, 250 cfm with 2 jack hammer hour 6.000 269.00 1614.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper10 tonne capacity hour 11.250 261.00 2936.25
c) Materials
Gelatin 80 per cent kg 63.000 0.00 0.00
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 0.00 0.00
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 0.00 0.00
per cent quantity blasted
d) Overhead charges @ 08 % on (a+b+c) 2261.61
e) Contractor's profit @ 10 % on (a+b+c+d) 3053.17
Cost for 180 cum = a+b+c+d+e 33584.88
Rate per cum = (a+b+c+d+e)/180 186.58
say 187.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
3.6 1.01 301 Excavation in Soil using Hydraulic Excavator CK 90
and Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 155.00 12.40
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor day 2.000 155.00 310.00
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 1097.00 6582.00
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 261.00 4176.00
c) Overhead charges @ 08 % on (a+b) 886.43
d) Contractor's profit @ 10 % on (a+b+c) 1196.68
Cost for 360 cum = a+b+c+d 13163.52
Rate per cum = (a+b+c+d)/360 36.57
say 37.00
3.7 301 Excavation in Ordinary Rock using Hydraulic
Excavator CK-90 and Tippers with Disposal upto 1000
metres.
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 1097.00 6582.00
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 261.00 2871.00
c) Overhead charges @ 08 % on (a+b) 782.03
d) Contractor's profit @ 10 % on (a+b+c) 1055.74
Cost for 240 cum = a+b+c+d 11613.18
Rate per cum = (a+b+c+d)/240 48.39
say 48.00
3.8 301 Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 155.00 62.00
Mazdoor for trimming slopes including mannul loading day 10.000 155.00 1550.00
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 1097.00 6582.00
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 261.00 1696.50
Credit for excavated rock found suitable for use @ 50 cum 18.000 0.00 0.00
per cent of excavated quantity
c) Overhead charges @ 08 % on (a+b) 791.24
d) Contractor's profit @ 10 % on (a+b+c) 1068.17
Cost for 36 cum = a+b+c+d 11749.91
Rate per cum = (a+b+c+d)/36 326.39
say 326.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 155.00 254.20
Mazdoor including loading in truck day 16.000 155.00 2480.00
Chiseller day 24.000 176.00 4224.00
Blacksmith day 1.000 196.00 196.00
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 261.00 756.90
Credit for excavated rock found suitable for use @ 50 cum 8.000 0.00 0.00
per cent of excavated
c) Overhead charges @ 08 % on (a+b) 632.89
d) Contractor's profit @ 10 % on (a+b+c) 854.40
Cost for 16 cum = a+b+c+d 9398.39
Rate per cum = (a+b+c+d)/16 587.40
say 587.00
Note 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 301 Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 155.00 34.10
Mazdoor day 3.000 155.00 465.00
Driller day 2.000 155.00 310.00
Blaster day 0.500 155.00 77.50
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 3133.00 18798.00
Air compressor, 250 cfm with 2 jack hammers hour 6.000 269.00 1614.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 261.00 2140.20
c) Materials
Gelatin 80 per cent kg 63.000 0.00 0.00
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 0.00 0.00
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 0.00 0.00
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 1375.64
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 08 % on (a+b+c) 2311.08
e) Contractor's profit @ 10 % on (a+b+c+d) 3119.95
Cost for 180 cum = a+b+c+d+e 34319.47
Rate per cum = (a+b+c+d+e)/180 190.66
say 191.00
Note 1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 301 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 1097.00 6582.00
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 261.00 3560.04
c) Overhead charges @ 08 % on (a+b) 837.16
d) Contractor's profit @ 10 % on (a+b+c) 1130.16
Cost for 300 cum = a+b+c+d 12431.75
Rate per cum = (a+b+c+d)/300 41.44
say 41.00
3.11 301 Removal of Unserviceable Soil with Disposal upto
1000 metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour 6.000 1097.00 6582.00
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 261.00 4269.96
c) Overhead charges @ 08 % on (a+b) 893.95
d) Contractor's profit @ 10 % on (a+b+c) 1206.83
Cost for 360 cum = a+b+c+d 13275.14
Rate per cum = (a+b+c+d)/360 36.88
say 37.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock
face)
a) Labour
Mate day 0.600 155.00 93.00
Mazdoor day 15.000 155.00 2325.00
b) Machinery
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 269.00 1614.00
hour
Dozer, 80 HP hour 6.000 3133.00 18798.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
c) Materials
Gelatin 80 per cent kg 42.000 0.00 0.00
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 0.00 0.00
of 125 gms each
d) Overhead charges @ 08 % on (a+b+c) 2152.32
e) Contractor's profit @ 10 % on (a+b+c+d) 2905.63
Cost for 400 sqm = a+b+c+d+e 31961.95
Rate per sqm = (a+b+c+d+e)/400 79.90
say 80.00
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 155.00 49.60
Mazdoor day 8.000 155.00 1240.00
b) Overhead charges @ 08 % on (a) 103.17
c) Contractor's profit @ 10 % on (a+b) 139.28
Cost for 10 cum = a+b+c 1532.04
Rate per cum = (a+b+c)/10 153.20
say 153.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 155.00 49.60
Mazdoor day 8.000 155.00 1240.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1097.00 6582.00
c) Overhead charges @ 08 % on (a+b) 629.73
d) Contractor's profit @ 10 % on (a+b+c) 850.13
Cost for 300 cum = a+b+c+d 9351.46
Rate per cum = (a+b+c+d)/300 31.17
say 31.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 155.00 62.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor day 10.000 155.00 1550.00
b) Overhead charges @ 08 % on (a) 128.96
c) Contractor's profit @ 10 % on (a+b) 174.10
Cost for 10 cum = a+b+c 1915.06
Rate per cum = (a+b+c)/10 191.51
say 192.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 B Mechanical Means
(ii)
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1097.00 6582.00
c) Overhead charges @ 08 % on (a+b) 603.94
d) Contractor's profit @ 10 % on (a+b+c) 815.31
Cost for 216 cum = a+b+c+d 8968.45
Rate per cum = (a+b+c+d)/216 41.52
say 42.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 155.00 82.15
ii) Driller day 0.840 155.00 130.20
iii) Blaster day 0.400 155.00 62.00
iv) Mazdoor day 12.000 155.00 1860.00
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 269.00 179.33
per hour
c) Material
Blasting Material kg 3.500 0.00 0.00
Detonator electric each 14.000 0.00 0.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 269.00 2690.00
breaker @ 1 cum per hour
c) Overhead charges @ 08 % on (a+b) 279.68
d) Contractor's profit @ 10 % on (a+b+c) 377.57
Cost for 10 cum = a+b+c+d 4153.25
Rate per cum = (a+b+c+d)/10 415.32
say 415.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 155.00 62.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Tractor-trolley hour 2.670 306.00 817.02
c) Material
Selected earth for refilling cum 5.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 194.32
e) Contractor's profit @ 10 % on (a+b+c+d) 262.33
Cost for 10 cum = a+b+c+d+e 2885.68
Rate per cum = ( a+b+c+d+e)/ 10 288.57
say 289.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.13 B Mechanical Means
(v)
a) Labour
i) Mate day 0.080 155.00 12.40
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 155.00 310.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 1097.00 186.49
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 261.00 117.45
c) Material
Selected earth for refilling cum 5.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 50.11
e) Contractor's profit @ 10 % on (a+b+c+d) 67.64
Cost for 10 cum = a+b+c+d+e 744.09
Rate per cum = (a+b+c+d+e)/10 74.41
say 74.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
3.14 305.4.3 Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 155.00 31.00
Mazdoor including loading and unloading day 5.000 155.00 775.00
b) Machinery
Tractor-trolley hour 1.670 306.00 511.02
d) Overhead charges @ 08 % on (a+b+c) 105.36
e) Contractor's profit @ 10 % on (a+b+c+d) 142.24
Cost for 100 sqm = a+b+c+d 1564.62
Rate per sqm = (a+b+c+d)/100 15.65
say 16.00
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of
50 mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 155.00 1.55
Mazdoor day 0.250 155.00 38.75
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 329.00 26.32
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 679.00 135.80
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 261.00 60.03
c) Overhead charges @ 08 % on (a+b) 21.00
d) Contractor's profit @ 10 % on (a+b+c) 28.34
Cost for 100 sqm = a+b+c+d 311.79
Rate per sqm = (a+b+c+d)/100 3.12
say 3.00
3.16 1.02 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1097.00 1831.99
per hour
Tipper 10 tonne capacity tonne.km 160 x L 2.00 3200.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1298.00 1298.00
c) Material
Cost of water KL 24.000 100.00 2400.00
Compensation for earth taken from private land cum 100.000 16.00 1600.00
d) Overhead charges @ 08 % on (a+b+c) 1235.10
e) Contractor's profit @ 10 % on (a+b+c+d) 1667.38
Cost for 100 cum = a+b+c+d+e 18341.16
Rate per cum = (a+b+c+d+e)/100 183.41
say 183.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
3.17 1.03 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.500 155.00 77.50
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3133.00 1566.50
Motor grader for grading @ 100 cum per hour hour 1.000 2017.00 2017.00
Water tanker6 KL capacity hour 4.000 261.00 1044.00
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1298.00 1298.00
c) Material
Cost of water KL 24.000 100.00 2400.00
d) Overhead charges @ 08 % on (a+b+c) 672.49
e) Contractor's profit @ 10 % on (a+b+c+d) 907.86
Rate for 100 cum = a+b+c+d+e 9986.45
Rate per cum = (a+b+c+d+e)/100 99.86
say 100.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
3.18 1.04 & 305 Construction of Subgrade and Earthen Shoulders
1.05 Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1097.00 1831.99
per hour
Tipper 10 tonne capacity tonne.km 175xL 2.00 3500.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Add 10 per cent of cost of carriage to cover cost of 350.00
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3133.00 1566.50
Motor grader for grading @ 50 cum per hour hour 2.000 2017.00 4034.00
Water tanker with 6 km lead hour 4.000 261.00 1044.00
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1298.00 1622.50
c) Material
Cost of water KL 24.000 100.00 2400.00
Compensation for earth taken from private land cum 100.000 16.00 1600.00
d) Overhead charges @ 08 % on (a+b+c) 1448.82
e) Contractor's profit @ 10 % on (a+b+c+d) 1955.90
Cost for 100 cum = a+b+c+d+e 21514.91
Rate per cum = (a+b+c+d+e)/100 215.15
say 215.00
3.19 305.3.4 Compacting Original Ground
Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 3.000 155.00 465.00
b) Machinery
Tractor with ripper attachment hour 9.000 329.00 2961.00
Motor grader for grading hour 6.000 2017.00 12102.00
Water tanker 6 KL capacity hour 4.000 261.00 1044.00
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1298.00 9735.00
c) Material
Cost of water KL 24.000 100.00 2400.00
d) Overhead charges @ 08 % on (a+b+c) 2298.05
e) Contractor's profit @ 10 % on (a+b+c+d) 3102.36
Cost for 600 cum = a+b+c+d+e 34126.01
Rate per cum = (a+b+c+d+e)/600 56.88
say 57.00
3.19 Case-II :Compacting original ground supporting embankment
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per sqm = (a+b+c+d+e)/600 30.64
say 31.00
3.20 305 Stripping and Storing Top Soil
Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 155.00 31.00
Mazdoor day 5.000 155.00 775.00
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 3133.00 313.30
c) Overhead charges @ 08 % on (a+b) 89.54
d) Contractor's profit @ 10 % on (a+b+c) 120.88
Cost for 10 cum = (a+b+c+d) 1329.73
Rate per cum = (a+b+c+d)/10 132.97
say 133.00
3.21 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Dozer, 80 HP hour 6.000 3133.00 18798.00
c) Overhead charges @ 08 % on (a+b) 1529.63
d) Contractor's profit @ 10 % on (a+b+c) 2065.00
Cost for 300 cum = (a+b+c+d) 22715.04
Rate per cum = (a+b+c+d)/300 75.72
say 76.00
3.22 1.06 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor for preparation of ground and fetching of sods day 3.000 155.00 465.00
b) Machinery
Water tanker including watering for 3 months hour 2.000 261.00 522.00
Tractor-trolley hour 1.000 306.00 306.00
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 336.78 60.62
work
Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 205.78
e) Contractor's profit @ 10 % on (a+b+c+d) 277.80
Cost for 100 sqm = a+b+c+d+e 3055.80
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per 100 sqm = (a+b+c+d+e)/100 30.56
say 31.00
3.23 308 Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 155.00 62.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 261.00 3654.00
months
Tractor-trolley hour 2.400 306.00 734.40
c) Material
Seeds kg 3.600 0.00 0.00
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 336.78 144.82
Bitumen Emulsion litre 55.200 26.95 1487.64
Jute netting, open weave, 2.5 cm square opening sqm 264.000 0.00 0.00
Cost of water for 3 months KL 84.000 100.00 8400.00
d) Overhead charges @ 08 % on (a+b+c) 1282.63
e) Contractor's profit @ 10 % on (a+b+c+d) 1731.55
Cost for 240 sqm = a+b+c+d+e 19047.03
Rate per sqm = (a+b+c+d+e)/240 79.36
say 79.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 155.00 1.55
Mazdoor for dressing of bed and side of drain day 0.250 155.00 38.75
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 1097.00 362.01
metres per hour
c) Overhead charges @ 08 % on (a+b) 32.18
d) Contractor's profit @ 10 % on (a+b+c) 43.45
Cost for 10 metres = a+b+c+d 477.94
Rate per metre = (a+b+c+d)/10 47.79
say 48.00
3.24 B Manual Means
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Overhead charges @ 08 % on (a) 25.79
c) Contractor's profit @ 10 % on (a+b) 34.82
Cost for 10 metres = a+b+c 383.01
Rate per metre = (a+b+c)/10 38.30
say 38.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
3.25 309 Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor for dressing of bed and side of drain day 0.500 155.00 77.50
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 1097.00 734.99
metres per hour
c) Overhead charges @ 08 % on (a+b) 65.25
d) Contractor's profit @ 10 % on (a+b+c) 88.08
Cost for 10 metres = a+b+c+d 968.92
Rate per metre = (a+b+c+d)/10 96.89
say 97.00
3.25 B Manual Means
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 3.000 155.00 465.00
b) Overhead charges @ 08 % on (a) 38.69
c) Contractor's profit @ 10 % on (a+b) 52.23
Cost for 10 metres = a+b+c 574.52
Rate per metre = (a+b+c)/10 57.45
say 57.00
3.26 309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
3.27 309 Sub-Surface Drains with Perforated Pipe
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor for excavation and back filling day 2.000 155.00 310.00
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 0.00 0.00
mm
Crushed stone as per table 300-3 (Filter Material class cum 2.400 700.49 1681.18
I -11.2mm-90 micron or class II- 26.5mm-90 micron or
class III- 53mm-90 micron)
d) Overhead charges @ 08 % on (a+b+c) 159.79
e) Contractor's profit @ 10 % on (a+b+c+d) 215.72
Cost for 10 metres = a+b+c+d+e 2372.88
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per metre = (a+b+c+d+e)/10 237.29
say 237.00
Note Type of pipe may be modified depending upon provision in
design.
3.28 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor for excavation and back filling with day 1.500 155.00 232.50
aggregates
b) Material
Crushed stone as per table 300-3 (Filter Material class cum 1.350 700.49 945.66
I -11.2mm-90 micron or class II- 26.5mm-90 micron or
class III- 53mm-90 micron)
c) Overhead charges @ 08 % on (a+b) 94.50
d) Contractor's profit @ 10 % on (a+b+c) 127.58
Cost for 10 metres = a+b+c+d 1403.34
Rate per metre = (a+b+c+d)/10 140.33
say 140.00
3.29 309 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in ordinary soil cum 1.500 31.00 46.50
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.500 155.00 232.50
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3133.00 1566.50
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1298.00 1298.00
Water tanker 6 KL, one trip per hour hour 2.000 261.00 522.00
c) Material
Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 386.02
e) Contractor's profit @ 10 % on (a+b+c+d) 521.12
Cost for 100 cum = a+b+c+d+e 5732.34
Rate per cum = (a+b+c+d+e)/100 57.32
say 57.00
Note It is assumed that rock is available locally at site from
roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD
3.32 301 Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor for trimming slopes and helping in excavation day 6.000 155.00 930.00
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3133.00 18798.00
Front end loader hour 6.000 679.00 4074.00
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 261.00 3132.00
c) Overhead charges @ 08 % on (a+b) 2157.70
d) Contractor's profit @ 10 % on (a+b+c) 2912.89
Cost for 260 cum = a+b+c+d 32041.79
Rate per cum = (a+b+c+d)/260 123.24
say 123.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mate day 0.320 155.00 49.60
Mazdoor day 8.000 155.00 1240.00
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3133.00 18798.00
Front end loader hour 7.000 679.00 4753.00
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 261.00 1827.00
c) Overhead charges @ 08 % on (a+b) 2133.41
d) Contractor's profit @ 10 % on (a+b+c) 2880.10
Cost for 170 cum = a+b+c+d 31681.11
Rate per cum = (a+b+c+d)/170 186.36
say 186.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 155.00 75.95
Mazdoor day 10.000 155.00 1550.00
Driller day 2.000 155.00 310.00
Blaster day 0.250 155.00 38.75
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3133.00 18798.00
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 269.00 1345.00
cum per hour
Front end loader hour 7.000 679.00 4753.00
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 261.00 1827.00
c) Materials
Gelatine 80 per cent kg 35.000 0.00 0.00
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 0.00 0.00
of 125 gms each
d) Overhead charges @ 08 % on (a+b+c) 2295.82
e) Contractor's profit @ 10 % on (a+b+c+d) 3099.35
Cost for 170 cum = a+b+c+d+e 34092.87
Rate per cum = (a+b+c+d+e)/170 200.55
say 201.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
3.35 Work in Urban Roads
The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 155.00 24.80
Mazdoor day 4.000 155.00 620.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 1097.00 6582.00
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 2.00 17280.00
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
4.1 401 Granular Sub-Base with Close Graded Material
(Table:- 400-1)
A Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage
of mixed Material to work site, spreading in uniform layers
with motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density,
complete as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 155.00 62.00
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 8.000 155.00 1240.00
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 0.00 0.00
Electric generator 125 KVA hour 6.000 588.00 3528.00
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 261.00 1174.50
hour
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note Any one of the grading for material may be adopted as per
design
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor unskilled day 10.000 155.00 1550.00
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 2017.00 12102.00
Vibratory roller 8 -10 tonne hour 6.000 1298.00 7788.00
Tractor - Rotavator hour 12.000 320.00 3840.00
Water tanker 6 KL capacity hour 3.000 261.00 783.00
c) Material
Close graded Granular sub-base Material as per table 400-1
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note Any one of the grading for material may be adopted as per
design
4.2 2.01 401 Granular Sub-Base with Coarse Graded Material
(Table:- 400- 2)
Construction of granular sub-base by providing coarse
graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with vibratory roller
to achieve the desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 155.00 62.00
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 8.000 155.00 1240.00
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2017.00 12102.00
Vibratory roller 8 -10 tonne hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 3.000 261.00 783.00
c) Material
For coarse graded Granular sub-base Materials per table
400-2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 1369.00 183993.60
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 1408.00 243302.40
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 982.00 75417.60
Cost of water KL 18.000 100.00 1800.00
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 1408.00 405504.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note Any one of the grading for material may be adopted as per
design
4.3 402 Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader
and compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)
A By Mechanical Means
a) Labour
Mate day 0.360 155.00 55.80
Skilled mazdoor for alignment and geometrics day 1.000 196.00 196.00
Mazdoor for spraying lime day 8.000 155.00 1240.00
b) Machinery
Tractor with ripper and rotavator attachments @ 60 hour 12.000 329.00 3948.00
cum per hour for ripping and 25 cum per hour for
mixing
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2017.00 12102.00
Vibratory roller 8 - 10 tonne capacity hour 6.00x0.65* 1298.00 5062.20
Water tanker 6 KL capacity hour 12.000 261.00 3132.00
c) Material
Lime at site tonne 15.750 4400.00 69300.00
Cost of water KL 72.000 100.00 7200.00
d) Overhead charges @ 08 % on (a+b+c) 8178.88
e) Contractor's profit @ 10 % on (a+b+c+d) 11041.49
Cost for 300 cum= a+b+c+d+e 121456.37
Rate per cum =( a+b+c+d+e)/300 404.85
say 405.00
Note * Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours
as other machines for spreading and mixing will take 6
hours. The usage rates of roller have been multiplied with a
factor of 0.65.
4.3 B By Manual Means
Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate day 1.440 155.00 223.20
Mazdoor skilled day 1.000 196.00 196.00
Mazdoor day 35.000 155.00 5425.00
b) Machinery
Vibratory roller 8 - 10 tonne @ 60 cum per hour hour 2.500 1298.00 3245.00
Water tanker 6 KL capacity hour 6.000 261.00 1566.00
c) Material
Lime at site tonne 8.000 4400.00 35200.00
Cost of water KL 36.000 100.00 3600.00
d) Overhead charges @ 08 % on (a+b+c) 3956.42
e) Contractor's profit @ 10 % on (a+b+c+d) 5341.16
Cost for 150 cum= a+b+c+d+e 58752.78
Rate per cum =( a+b+c+d+e)/150 391.69
say 392.00
4.4 402 Lime Treated Soil for Sub- Base
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Providing, laying and spreading soil on a prepared sub
grade, pulverising, mixing the spread soil in place with
rotavator with 3 per cent slaked lime with minimum content
of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to achieve at least
98 per cent of the max dry density to form a layer of sub
base.
Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1097.00 6582.00
Tipper for carriage of soil tonne.km 525 x L 2.00 10500.00
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1097.00 6582.00
Tipper for carriage of soil tonne.km 525 x L 2.00 10500.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 4400.00 92400.00
Cost of water KL 72.000 100.00 7200.00
d) Overhead charges @ 08 % on (a+b+c) 11728.83
e) Contractor's profit @ 10 % on (a+b+c+d) 15833.92
Cost for 300 cum = a+b+c+d+e 174173.16
Rate per cum= (a+b+c+d+e)/300 580.58
say 581.00
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity
of crushed rock by weight.
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2017.00 12102.00
Vibratory roller 8 - 10 tonne hour 6.000 1298.00 7788.00
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 320.00 3840.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
d) Overhead charges @ 08 % on (a+b+c) 46757.22
e) Contractor's profit @ 10 % on (a+b+c+d) 63122.24
Cost for 300 cum = a+b+c+d+e 694344.66
Rate per cum = (a+b+c+d+e)/300 2314.48
say 2314.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.7 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Tractor-trolley hour 0.200 306.00 61.20
c) Overhead charges @ 08 % on (a+b) 30.69
d) Contractor's profit @ 10 % on (a+b+c) 41.43
Cost for 210 sqm= a+b+c+d 455.72
Rate per sqm =(a+b+c+d)/210 445.72
say 446.00
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 155.00 24.80
Mazdoor day 4.000 155.00 620.00
b) Machinery
Tractor-trolley hour 0.400 306.00 122.40
c) Overhead charges @ 08 % on (a+b) 61.38
d) Contractor's profit @ 10 % on (a+b+c) 82.86
Cost for 210 sqm= a+b+c+d 911.43
Rate per sqm =(a+b+c+d)/210 901.43
say 901.00
4.8 404.3.2 Inverted Choke
Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse sand of
specified grade in uniform layer on a prepared surface with
motor grader and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 155.00 142.60
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 21.000 155.00 3255.00
b) Machinery
Motor Grader 110 HP hour 6.000 2017.00 12102.00
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 18.000 261.00 4698.00
c) Material
Screening type 'B' or coarse sand cum 720.000 750.00 540000.00
Cost of water KL 108.000 100.00 10800.00
d) Overhead charges @ 08 % on (a+b+c) 46334.21
e) Contractor's profit @ 10 % on (a+b+c+d) 62551.18
Cost for 600 cum = a+b+c+d+e 688062.99
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per cum = ( a+b+c+d+e)/600 1146.77
say 1147.00
4.9 404 Water Bound Macadam
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with 3 wheeled steel/ vibratory roller 8-10
tonnes in stages to proper grade and camber, applying and
brooming requisite type of screening/ binding Materials to fill
up the interstices of coarse aggregate, watering and
compacting to the required density.
A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 155.00 1562.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 250.000 155.00 38750.00
b) Machinery
Vibratory roller 8 - 10 tonne @ 60cum per hour hour 6.000 1298.00 7788.00
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000
Water tanker 6 KL capacity hour 24.000 261.00 6264.00
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1142.00 497455.20
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 1419.00 137926.80
OR
Crushable type such as Moorum or Gravel for cum 108.000 0.00 0.00
grading-I @ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9A (i) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 08 % on (a+b+c) 45328.93
e) Contractor's profit @ 10 % on (a+b+c+d) 61194.05
Cost for 360 cum = a+b+c+d+e 673134.58
Rate per cum = (a+b+c+d+e)/360 1869.82
say 1870.00
OR
4.9A (i) (b) Using Scrining Type-A (13.2mm agg.)
d) Overhead charges @ 08 % on (a+b+c) 56363.07
e) Contractor's profit @ 10 % on (a+b+c+d) 76090.15
Cost for 360 cum = a+b+c+d+e 836991.62
Rate per cum = (a+b+c+d+e)/360 2324.98
say 2325.00
4.9A (ii) Grading-II
Aggregate
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1150.00 500940.00
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 1419.00 81734.40
OR
Crushable type such as Moorum or Gravel for grading cum 105.590 0.00 0.00
II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1376.00 118886.40
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 08 % on (a+b+c) 45607.71
e) Contractor's profit @ 10 % on (a+b+c+d) 61570.41
Cost for 360 cum = a+b+c+d+e 677274.52
Rate per cum = (a+b+c+d+e)/360 1881.32
say 1881.00
OR
4.9A (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 08 % on (a+b+c) 52146.46
e) Contractor's profit @ 10 % on (a+b+c+d) 70397.73
Cost for 360 cum = a+b+c+d+e 774374.99
Rate per cum = (a+b+c+d+e)/360 2151.04
say 2151.00
4.9A (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 08 % on (a+b+c) 55118.62
e) Contractor's profit @ 10 % on (a+b+c+d) 74410.14
Cost for 360 cum = a+b+c+d+e 818511.57
Rate per cum = (a+b+c+d+e)/360 2273.64
say 2274.00
4.9A (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 1369.00 596336.40
for compacted thickness of 75 mm
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1376.00 118886.40
OR
Crushable type such as Moorum or Gravel for grading cum 105.590 0.00 0.00
II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 08 % on (a+b+c) 53239.42
e) Contractor's profit @ 10 % on (a+b+c+d) 71873.22
Cost for 360 cum = a+b+c+d+e 790605.45
Rate per cum = (a+b+c+d+e)/360 2196.13
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 2196.00
OR
4.9A (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 08 % on (a+b+c) 62750.34
e) Contractor's profit @ 10 % on (a+b+c+d) 84712.95
Cost for 360 cum = a+b+c+d+e 931842.49
Rate per cum = (a+b+c+d+e)/360 2588.45
say 2588.00
( Anyone of the aggregate grading, screening and binding
material may be used as per design)
4.9 B By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 155.00 105.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 15.000 155.00 2325.00
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 2017.00 14522.40
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1298.00 7788.00
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Water tanker 6 KL capacity hour 24.000 261.00 6264.00
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1142.00 497455.20
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 1419.00 137926.80
OR
Crushable type such as Moorum or Gravel for cum 108.000 0.00 0.00
grading-I @ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(i)
d) Overhead charges @ 08 % on (a+b+c) 43460.16
e) Contractor's profit @ 10 % on (a+b+c+d) 58671.22
Cost for 360 cum = a+b+c+d+e 645383.38
Rate per cum = (a+b+c+d+e)/360 1792.73
say 1793.00
OR
4.9B (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 08 % on (a+b+c) 54494.30
e) Contractor's profit @ 10 % on (a+b+c+d) 73567.31
Cost for 360 cum = a+b+c+d+e 809240.41
Rate per cum = (a+b+c+d+e)/360 2247.89
say 2248.00
4.9B (ii) Grading-II
Aggregate
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1150.00 500940.00
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 1419.00 81734.40
OR
Crushable type such as Moorum or Gravel for grading cum 105.590 0.00 0.00
II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1376.00 118886.40
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 08 % on (a+b+c) 43738.94
e) Contractor's profit @ 10 % on (a+b+c+d) 59047.57
Cost for 360 cum = a+b+c+d+e 649523.32
Rate per cum = (a+b+c+d+e)/360 1804.23
say 1804.00
OR
4.9B (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 08 % on (a+b+c) 50277.70
e) Contractor's profit @ 10 % on (a+b+c+d) 67874.89
Cost for 360 cum = a+b+c+d+e 746623.79
Rate per cum = (a+b+c+d+e)/360 2073.95
say 2074.00
4.9B (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 08 % on (a+b+c) 53249.86
e) Contractor's profit @ 10 % on (a+b+c+d) 71887.31
Cost for 360 cum = a+b+c+d+e 790760.36
Rate per cum = (a+b+c+d+e)/360 2196.56
say 2197.00
4.9B (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 1369.00 596336.40
for compacted thickness of 75 mm
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1376.00 118886.40
OR
Crushable type such as Moorum or Gravel for grading cum 105.590 0.00 0.00
II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 0.00 0.00
material
Cost of water KL 144.000 100.00 14400.00
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 08 % on (a+b+c) 51370.66
e) Contractor's profit @ 10 % on (a+b+c+d) 69350.39
Cost for 360 cum = a+b+c+d+e 762854.24
Rate per cum = (a+b+c+d+e)/360 2119.04
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 2119.00
OR
4.9B (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 08 % on (a+b+c) 60881.57
e) Contractor's profit @ 10 % on (a+b+c+d) 82190.12
Cost for 360 cum = a+b+c+d+e 904091.28
Rate per cum = (a+b+c+d+e)/360 2511.36
say 2511.00
Note As three wheeled smooth rollers are also very commonly
used, the same has been provided as an alternative.
4.10 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not
exceeding 75 mm as specified in table 400.7 transporting
the aggregates obtained from breaking of cement concrete
slabs at a lead of L km., laying and compacting the same as
sub base/ base course, constructed as WBM to clause 404
except the use of screening or binding Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 155.00 644.80
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor for crushing broken cement concrete day 102.000 155.00 15810.00
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 2017.00 12102.00
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 1298.00 7788.00
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 720 x L 2.00 17280.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 155.00 86.80
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 12.000 155.00 1860.00
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 300.00 1800.00
Hydraulic self propelled chips spreader hour 6.000 2220.00 13320.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity hour 6.000 261.00 1566.00
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 1298.00 5062.20
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 903.00 3864.84
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 1376.00 134160.00
Bitumen (60-70 grade) tonne 0.250 35472.00 8868.00
d) Overhead charges @ 08 % on (a+b+c) 14004.31
e) Contractor's profit @ 10 % on (a+b+c+d) 18905.81
Cost for 7500 sqm = a+b+c+d+e 207963.96
Rate per sqm = (a+b+c+d+e)/7500 27.73
say 28.00
Note Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6
hours to match with other machines. The usage rates of
vibratory roller may be multiplied with a factor of 0.65.
4.12 2.02 406 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Wet mix plant of 60 tonne hourly capacity hour 9.000 1014.00 9126.00
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum capacity hour 6.000 679.00 4074.00
Paver finisher hour 6.000 821.00 4926.00
Vibratory roller 8 - 10 tonne hour 6x0.65 1298.00 5062.20
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 261.00 783.00
Tipper tonne.km 495 x L 2.00 11880.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
45 mm to 22.4 mm@ 30 per cent cum 89.100 1404.67 125155.80
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 261.00 261.00
Plate compactor @ 3.5 cum per hour hour 6.000 65.00 390.00
c) Material
Cost of water KL 6.000 100.00 600.00
d) Overhead charges @ 08 % on (a+b+c) 177.46
e) Contractor's profit @ 10 % on (a+b+c+d) 239.57
Cost for 21 cum = a+b+c+d+e 2635.22
Rate per cum = (a+b+c+d+e)/21 125.49
say 125.00
Note This analysis provides for median and island with earthen
top. In case the surface is required to be turfed or planted
with shrubs, the same is required to be provided separately
as per analysis given in the chapter on horticulture. In case
granular fill is required to be paved, quantities of paving are
required to be calculated as per approved design and paid
separately.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Plate Compactor @ 3.5 cum per hour hour 6.000 65.00 390.00
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 1097.00 548.50
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 2.00 1050.00
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 261.00 522.00
Concrete mixer 0.4/0.28 cum per hour hour 6.000 196.00 1176.00
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 1369.00 28461.51
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 1408.00 37635.84
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Cement tonne 1.830 4400.00 8052.00
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 34.50 113850.00
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 0.00 0.00
vi) Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 18595.76
e) Contractor's profit @ 10 % on (a+b+c+d) 25104.28
Cost for 300 sqm = a+b+c+d+e 276147.11
Rate per sqm = (a+b+c+d+e)/300 920.49
say 920.00
4.17 410 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and mixing
with a motor grader, watering and compacting with a
vibratory roller to clause 410 to form a layer of sub-
base/Base
Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor skilled day 2.000 196.00 392.00
Mazdoor day 10.000 155.00 1550.00
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 320.00 3840.00
Motor grader 110 HP hour 6.000 2017.00 12102.00
Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 6.000 261.00 1566.00
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 1150.00 181079.00
22.5 mm to5.6 mm@ 32 per cent cum 151.060 1408.00 212692.48
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 2029.00
Note Any one of the aggregate grading may be adopted
4.17 B By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 155.00 43.40
Mazdoor skilled day 1.000 196.00 196.00
Mazdoor day 6.000 155.00 930.00
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 0.00 0.00
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Motor grader 110 HP hour 6.000 2017.00 12102.00
Vibratory roller 8 - 10 tonne hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 3.000 261.00 783.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
Or
ii) For 45 mm maximum size
45 mm to22.5 mm@ 5 per cent cum 15.060 1379.00 20767.74
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 1408.00 209088.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material
or clayey silts and low plasticity clays having PI between 5
and 20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than
50 per cent, Flyash to conform to gradation as per clause
4.3 of IRC: 88-1984, lime + Flyash content ranging between
10 to 30 per cent, the minimum un-confined compressive
strength and CBR value after 28 days curing and 4 days
soaking to be 7.5kg/sq, cm and 25 per cent respectively, all
as specified in IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50
t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
Mazdoor (Skilled) day 1.000 196.00 196.00
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ hour 6.000 1097.00 6582.00
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes tonne.km 576 x L 2.00 11560.00
Tipper 10T capacity for carriage of 115 tonnes Flyash tonne.km 115 x L 2.00 4600.00
Tipper 10T capacity for carriage of 29 tonnes of lime hour 3.000 261.00 783.00
from store to work site
Add 10 per cent of cost of carriage to cover cost of 78.30
loading and unloading
Tractor with disc harrows for pulverisation hour 6.000 306.00 1836.00
Motor Grader 110 HP @ 50 cum per hour for mixing in- hour 9.600 2017.00 19363.20
place and grading
Vibratory roller 8 - 10 tonne hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 12.000 261.00 3132.00
c) Material
Slaked Lime tonne 29.000 4400.00 127600.00
Compensation for earth taken from private source cum 360.000 16.00 5760.00
d) Overhead charges @ 08 % on (a+b+c) 15219.66
e) Contractor's profit @ 10 % on (a+b+c+d) 20546.54
Cost for 480 cum = a+b+c+d+e 226011.89
Rate per cum= (a+b+c+d+e)/480 470.86
say 471.00
Note 1.Compensation for earth will vary from place to place and
will have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
3.Lime + Flyash has been taken as 20 per cent of total
mass and ratio of lime and Flyash as 1:4 for estimating
purposes. Total quantities will be as per approved design.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
5.1 3.01 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 300.00 840.00
Air compressor 250 cfm hour 2.800 269.00 753.20
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 903.00 1806.00
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 261.00 261.00
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 26950.00 56595.00
Cost of water KL 6.000 100.00 600.00
d) Overhead charges @ 08 % on (a+b+c) 4894.21
e) Contractor's profit @ 10 % on (a+b+c+d) 6607.18
Cost for 3500 sqm = a+b+c+d+e 72678.99
Rate per sqm = (a+b+c+d+e)/3500 20.77
say 21.00
Note Bitumen primer has been provided @ 0.60 kg per sqm as
per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
5.2 3.02(II 503 Tack Coat
)& A Providing and applying tack coat with bitumen emulsion
3.02 using emulsion pressure distributor at the rate of 0.20 kg per
(III) sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 300.00 840.00
Air compressor 250 cfm hour 2.800 269.00 753.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 903.00 1806.00
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 26950.00 18865.00
d) Overhead charges @ 08 % on (a+b+c) 1806.93
e) Contractor's profit @ 10 % on (a+b+c+d) 2439.35
Cost for 3500 sqm = a+b+c+d+e 26832.88
Rate per sqm = (a+b+c+d+e)/3500 7.67
say 8.00
5.2 3.02(I) B Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.25 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 300.00 840.00
Air compressor 250 cfm hour 2.800 269.00 753.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 903.00 1806.00
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 26950.00 23581.25
d) Overhead charges @ 08 % on (a+b+c) 2184.23
e) Contractor's profit @ 10 % on (a+b+c+d) 2948.71
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Cost for 3500 sqm = a+b+c+d+e 32435.79
Rate per sqm = (a+b+c+d+e)/3500 9.27
say 9.30
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.
5.3 3.03 504 Bituminous Macadam
Providing and laying bituminous macadam with 100-120
TPH hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, mechanical broom, paver, day 16.000 155.00 2480.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 19715.00 118290.00
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 300.00 660.00
Air compressor 250 cfm hour 2.200 269.00 591.80
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Generator 250 KVA hour 6.000 979.00 5874.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
5 mm and below15 per cent cum 43.510 1013.00 44075.63
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1408.00 163384.32
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 261.00 2610.00
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1298.00 7788.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 35472.00 798120.00
Crushed stone coarse aggregate passing 45 mm and cum 270.000 1315.00 355050.00
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 cum 67.500 1296.00 87480.00
mm sieve @ 0.015 cum per sqm
Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 261.00 2610.00
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1298.00 7788.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 35472.00 1085443.20
Crushed stone coarse aggregate (loose passing 63 cum 405.000 1282.00 519210.00
mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8 cum 81.000 1296.00 104976.00
mm sieve @ 0.018 cum per sqm
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each
layer, and with key aggregates placed on top of the second
layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being
75 mm
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 155.00 62.00
Mazdoor including for brooming of key aggregates day 8.000 155.00 1240.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2220.00 13320.00
aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 903.00 3097.29
sqm per hour
Tipper 5.5 cum capacity hour 10.000 261.00 2610.00
Vibratory roller 8 tonnes hour 6.000 1298.00 7788.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 9.000 35472.00 319248.00
each layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 1315.00 394500.00
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 1296.00 50544.00
mm sieve @ 0.13 cum per 10 sqm
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, mechanical broom, paver, day 16.000 155.00 2480.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 14580.00 87480.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Generator 250 KVA hour 6.000 979.00 5874.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, mechanical broom, paver, day 16.000 155.00 2480.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 14580.00 87480.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Generator 250 KVA hour 6.000 979.00 5874.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
13.2 - 10 mm20 per cent cum 57.300 1398.00 80105.40
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, mechanical broom, paver, day 16.000 155.00 2480.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 14580.00 87480.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Generator 250 KVA hour 6.000 979.00 5874.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, mechanical broom, paver, day 16.000 155.00 2480.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 14580.00 87480.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Generator 250 KVA hour 6.000 979.00 5874.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Filler @ 2 per cent of weight of aggregates. tonne 8.620 4400.00 37928.00
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1398.00 119529.00
Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour
Mate day 0.440 155.00 68.20
Mazdoor day 9.000 155.00 1395.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 300.00 2160.00
Air compressor 250 cfm hour 7.200 269.00 1936.80
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2220.00 13320.00
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 261.00 1566.00
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Bitumen pressure distributor hour 6.000 903.00 5418.00
Smooth wheeled roller 8-10 tonne weight hour 6.000 388.00 2328.00
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 35472.00 383097.60
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1423.00 192105.00
cum per sqm
d) Overhead charges @ 08 % on (a+b+c) 48628.85
e) Contractor's profit @ 10 % on (a+b+c+d) 65648.94
Cost for 9000 sqm = a+b+c+d+e 722138.39
Rate per sqm = (a+b+c+d+e)/9000 80.24
say 80.00
5.9 Case - 13 mm nominal size chipping
II
a) Labour
Mate day 0.440 155.00 68.20
Mazdoor day 9.000 155.00 1395.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 300.00 2160.00
Air compressor 250 cfm hour 7.200 269.00 1936.80
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2220.00 13320.00
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 261.00 1566.00
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00
Vibratory roller 8-10 tonne weight hour 6.000 1298.00 7788.00
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 35472.00 319248.00
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1419.00 127710.00
cum per sqm
d) Overhead charges @ 08 % on (a+b+c) 38806.08
e) Contractor's profit @ 10 % on (a+b+c+d) 52388.21
Cost for 9000 sqm = a+b+c+d+e 576270.29
Rate per sqm = (a+b+c+d+e)/9000 64.03
say 64.00
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the same
as per the Ist coat mentioned above
5.10 511 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.
Unit = sqm
Taking output = 10250 sqm (205 cum)
(i) Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less
than 75 tonnes/hour .
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, road sweeper, paver and day 16.000 155.00 2480.00
roller
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 19715.00 118290.00
ii) Electric Generator Set 250 KVA hour 6.000 979.00 5874.00
iii) Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
iv) Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
c) Material
Bitumen@ 14.60 kg per 10 sqm tonne 14.970 35472.00 531015.84
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum 276.750 1419.00 392708.25
cum per 10 sqm
d) Overhead charges @ 08 % on (a+b+c) 86938.26
e) Contractor's profit @ 10 % on (a+b+c+d) 117366.66
Cost for 10250 sqm = a+b+c+d+e 1291033.21
Rate per sqm = (a+b+c+d+e)/10250 125.95
say 126.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Note If a premix sand seal coat of 'B' type is proposed, the same
is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective working hours, 4.00 hours may be
utilised for laying of premix carpet and balance 2.00 hours
for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly
by utilising the HMP for 2.00 hours for the purpose of seal
coat. In case type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet as type 'A' seal
coat does not require the use of HMP.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor working with HMP, road sweeper, paver and day 16.000 155.00 2480.00
roller
Skilled mazdoor for checking line & levels day 5.000 196.00 980.00
b) Machinery
i) HMP of appropicate capacity. hour 6.000 19715.00 118290.00
ii) Electric Generator Set 250 KVA hour 6.000 979.00 5874.00
iii) Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
iv) Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2252.00 13512.00
iv) Smooth wheeled8-10 tonnes weight hour 6.000 388.00 2328.00
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.500 35472.00 798120.00
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 1104.00 305532.00
cum per 10 sqm
or
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.480 35472.00 690994.56
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 276.750 1104.00 305532.00
0.27 cum per 10 sqm
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor day 4.000 155.00 620.00
b) Machinery
HMP of 75 tonnes/hour. hour 2.000 14580.00 29160.00
Electric Generator Set 250 KVA hour 2.000 979.00 1958.00
Front end loader 1 cum bucket capacity hour 2.000 679.00 1358.00
Tipper 10 tonne capacity tonne.km 104 x 'L' 2.00 2496.00
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day 0.440 155.00 68.20
Mazdoor day 10.000 155.00 1550.00
Mazdoor skilled day 1.000 196.00 196.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 300.00 18.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Air compressor 250 cfm hour 0.060 269.00 16.14
Mastic cooker 1 tonne capacity hour 6.000 52.00 312.00
Bitumen boiler 1500 litres capacity hour 6.000 167.00 1002.00
Tractor for towing and positioning of mastic cooker and hour 1.000 306.00 306.00
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight tonne 0.204 35472.00 7236.29
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 982.00 382.98
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less tonne 0.360 4400.00 1584.00
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 1290.00 709.50
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 0.00 0.00
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight kg 0.500 35.00 17.50
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1047.00 6282.00
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 261.00 522.00
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 26950.00 521752.00
Fine aggregate 4.75 mm and below 87 per cent of cum 102.080 1074.00 109633.92
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 tonne 3.520 4400.00 15488.00
Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 53599.45
e) Contractor's profit @ 10 % on (a+b+c+d) 72359.26
Cost for 16000 sqm = a+b+c+d+e 795951.83
Rate per sqm = (a+b+c+d+e)/16000 49.75
say 50.00
5.15 (ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 155.00 31.00
Mazdoor day 5.000 155.00 775.00
b) Machinery
Mechanical broom hour 6.000 300.00 1800.00
Air compressor 250 cfm hour 6.000 269.00 1614.00
Mobile slurry seal equipment hour 6.000 849.00 5094.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00
stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 261.00 522.00
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x tonne 17.160 26950.00 462462.00
0.13
Fine aggregate 3 mm and below 85 per cent of total cum 74.800 982.00 73453.60
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 4400.00 11616.00
Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 45136.61
e) Contractor's profit @ 10 % on (a+b+c+d) 60934.42
Cost for 30000 sqm = a+b+c+d+e 670278.63
Rate per sqm = (a+b+c+d+e)/20000 33.51
say 34.00
5.15 (iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 155.00 31.00
Mazdoor day 5.000 155.00 775.00
b) Machinery
Mechanical broom hour 6.000 300.00 1800.00
Air compressor 250 cfm hour 6.000 269.00 1614.00
Mobile slurry seal equipment hour 6.000 849.00 5094.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 261.00 1566.00
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 261.00 522.00
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 26950.00 341456.50
Fine aggregate 2.36 mm and below,82 per cent of cum 43.300 982.00 42520.60
total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 4400.00 6952.00
Cost of water KL 12.000 100.00 1200.00
d) Overhead charges @ 08 % on (a+b+c) 32608.41
e) Contractor's profit @ 10 % on (a+b+c+d) 44021.35
Cost for 24000 sqm = a+b+c+d+e 484234.86
Rate per sqm = (a+b+c+d+e)/24000 20.18
say 20.00
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately
5.16 517 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
517.
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 155.00 74.40
Mazdoor day 10.000 155.00 1550.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 0.00 0.00
Mechanical broom @ 1250 sqm per hour hour 1.280 300.00 384.00
Air compressor 250 cfm hour 1.280 269.00 344.32
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 903.00 821.73
Hot mix plant 100-120 TPH producing an average of 75 hour 3.000 19715.00 59145.00
tonnes per hour
Electric generator set 250 KVA hour 3.000 979.00 2937.00
Front end loader 1.00 cum bucket capacity hour 3.000 679.00 2037.00
Tipper 5.5 cum capacity hour 18.000 261.00 4698.00
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 388.00 756.60
Vibratory roller 8 tonnes hour 3.00x0.65* 1298.00 2531.10
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 964.00 1879.80
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 tonne 1.987 35472.00 70489.96
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 tonne 7.728 35472.00 274127.62
x 0.04 = 7.73
ii) Aggregates
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Percentage of mix requiring fresh aggregates - 70 per cent
Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne 5.520 4400.00 24288.00
tonne
d) Overhead charges @ 08 % on (a+b+c) 47758.69
e) Contractor's profit @ 10 % on (a+b+c+d) 64474.24
Cost for 120 cum of DBM = a+b+c+d+e 709216.61
Rate per cum = (a+b+c+d+e)/120 5910.14
say 5910.00
Note Although the total rolling time is only 4 hours as per norms,
all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater for
their idling time, these have been multiplied with a factor of
0.65.
5.17 518 Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 3.000 155.00 465.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00
Air compressor 250 cfm hour 6.000 269.00 1614.00
Bitumen emulsion pressure distributor @ 1750 sqm per tonne 6.000 903.00 5418.00
hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 26950.00 212366.00
d) Overhead charges @ 08 % on (a+b+c) 17734.53
e) Contractor's profit @ 10 % on (a+b+c+d) 23941.61
Cost for 10500 sqm = a+b+c+d+e 263357.74
Rate per sqm = (a+b+c+d+e)/10500 25.08
say 25.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 155.00 24.80
Mazdoor for precoating of grit day 4.000 155.00 620.00
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 1074.00 28192.50
Bitumen emulsion for precoating grit @ 2 per cent of tonne 0.790 26950.00 21290.50
grit,39.38 x 0.02
50127.80
4.77
say 5.00
5.18 519 Bituminous Cold Mix ( Including Gravel Emulsion)
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent By weight
of total mix
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor day 16.000 155.00 2480.00
Mazdoor skilled day 5.000 196.00 980.00
b) Machinery
Drum mix plant for cold mixes of appropriate capacity hour 6.000 0.00 0.00
but not less than 75 tonnes/hour.
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 1376.00 119712.00
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 1013.00 109404.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
5.18 (ii) Using bitumen emulsion and 19 mm or 26.5 mm
nominal size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor day 16.000 155.00 2480.00
Mazdoor skilled day 5.000 196.00 980.00
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 0.00 0.00
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 1013.00 106365.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 155.00 130.20
Mazdoor day 16.000 155.00 2480.00
Mazdoor skilled day 5.000 196.00 980.00
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 0.00 0.00
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 1376.00 127968.00
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 1013.00 109404.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 0.00 0.00
producing output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 1013.00 115482.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65 388.00 1513.20
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 1298.00 5062.20
Finish rolling with 6-8 tonnes smooth wheeled tandom hour 6.00x0.65 964.00 3759.60
rollers.
c) Material
Composition of mix (450 tonne) is assumed to be
as under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 35472.00 798120.00
Filler (lime)@ 2 per cent tonne 9.000 4400.00 39600.00
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 750.00 216465.00
d) Overhead charges @ 08 % on (a+b+c) 93872.34
e) Contractor's profit @ 10 % on (a+b+c+d) 126727.65
Cost for 205 cum = a+b+c+d+e 1394004.19
Rate per cum = (a+b+c+d+e)/205 6800.02
say 6800.00
Note 1. Tack coat will be measured and paid separately
2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of this roller, their
usage rates has been multiplied by a factor of 0.65
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and
binder.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of use
and trials of the fibre, in any country having conditions
similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking,
trials may be required to be under taken before agreeing to
the use of the fibre.
Note 1. The modified binder is usually manufactured by `
specialised firms as a proprietary product. The rate for this
product is required to be as certained from the market.
2.The specifications for various item of road works using
polymer/rubber modified bitumens are same as those for
penetration grade bitumen except those for any special
conditions which the manufacturer may indicate
3.The other controls during mixing, laying shall be same as
specified in IRC - 14, 29, 94 and 95 for open graded premix
carpet, bituminous concrete, DBM and SDBC respectively
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00
Air compressor 250 cfm hour 6.000 269.00 1614.00
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00
Hydraulic Chip spreader hour 6.000 2220.00 13320.00
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00
c) Material
Modified binder tonne 9.450 41024.00 387676.80
Crushed stone aggregates 5.6 mm size cum 105.000 1074.00 112770.00
d) Overhead charges @ 08 % on (a+b+c) 42071.52
e) Contractor's profit @ 10 % on (a+b+c+d) 56796.55
Cost for 10500 sqm = a+b+c+d+e 624762.07
Rate per sqm = (a+b+c+d+e)/10500 59.50
say 60.00
5.21 (ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00
Air compressor 250 cfm capacity hour 6.000 269.00 1614.00
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00
Hydraulic Chip spreader hour 6.000 2220.00 13320.00
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00
c) Material
Modified binder tonne 11.550 41024.00 473827.20
Crushed stone chipping 11.2 mm size cum 105.000 1376.00 144480.00
d) Overhead charges @ 08 % on (a+b+c) 51500.35
e) Contractor's profit @ 10 % on (a+b+c+d) 69525.48
Cost for 10500 sqm = a+b+c+d+e 764780.23
Rate per sqm = (a+b+c+d+e)/10500 72.84
say 73.00
5.21 (iii) Stress absorbing membrane (SAM) crack width above
9 mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 6.000 155.00 930.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 300.00 1800.00
Air compressor 250 cfm capacity hour 6.000 269.00 1614.00
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 903.00 5418.00
Hydraulic Chip spreader hour 6.000 2220.00 13320.00
Smooth wheeled road roller 8-10 tonne hour 6.000 388.00 2328.00
c) Material
Modified binder tonne 15.750 41024.00 646128.00
Crushed stone aggregates 11.2 mm size cum 126.000 1376.00 173376.00
d) Overhead charges @ 08 % on (a+b+c) 67627.46
e) Contractor's profit @ 10 % on (a+b+c+d) 91297.07
Cost for 10500 sqm = a+b+c+d+e 1004267.72
Rate per sqm = (a+b+c+d+e)/10500 95.64
say 96.00
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per table 500-47.
5.21 (iv) Case - IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 703.4.5
Unit = sqm
Taking output = 3500 sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
a) Labour
Mate day 0.560 155.00 86.80
Mazdoor day 12.000 155.00 1860.00
Mazdoor skilled day 2.000 196.00 392.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 300.00 840.00
Air compressor 250 cfm capacity hour 2.800 269.00 753.20
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 903.00 1806.00
Pneumatic roller hour 2.000 1047.00 2094.00
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 34377.00 126507.36
kg per sqm
Geotextile including 10 per cent for overlaps sqm 3850.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 10747.15
e) Contractor's profit @ 10 % on (a+b+c+d) 14508.65
Cost for 10500 sqm = a+b+c+d+e 159595.16
Rate per sqm = (a+b+c+d+e)/3500 45.60
say 46.00
NOTE As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a bitumenious course in a day
Unit = cum
Taking output = 205 cum (450 tonnes)
(i) 75 mm thickness
a) Labour
Mate day 1.000 155.00 155.00
Mazdoor day 12.000 155.00 1860.00
Mazdoor skilled day 5.000 196.00 980.00
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 0.00 0.00
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum capacity hour 6.000 679.00 4074.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per sqm = (a+b+c+d+e)/205 5782.07
say 5782.00
Note (Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.
5.22 (ii) 40 mm thickness
a) Labour
Mate day 1.000 155.00 155.00
Mazdoor day 12.000 155.00 1860.00
Mazdoor skilled day 5.000 196.00 980.00
b) Machinery
Batch type cold mixing plant100-120 TPH capacity hour 6.000 0.00 0.00
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 588.00 3528.00
Front end loader 1 cum capacity hour 6.000 679.00 4074.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2252.00 13512.00
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 2.00 10800.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Smooth wheeled steel roller hour 6.00x0.65* 388.00 1513.20
Water tanker6 KL capacity hour 1.000 261.00 261.00
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 26950.00 1030837.50
Crushed stone aggregates 6 mm nominal size cum 270.000 1074.00 289980.00
Cost of water KL 6.000 100.00 600.00
d) Overhead charges @ 08 % on (a+b+c) 109061.12
e) Contractor's profit @ 10 % on (a+b+c+d) 147232.51
Cost for 10500 sqm = a+b+c+d+e 1619557.63
Rate per sqm = (a+b+c+d+e)/205 7900.28
say 7900.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-
10 tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 155.00 173.60
Mazdoor skilled day 6.000 196.00 1176.00
Mazdoor day 22.000 155.00 3410.00
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Cement concrete batch mix plant @ 55 cum per hour hour 6.000 0.00 0.00
Electric generator 100 KVA hour 6.000 588.00 3528.00
Paver with electronic sensor hour 6.000 2252.00 13512.00
Vibratory roller 8-10 t capacity hour 8.000 1298.00 10384.00
Water tanker6 KL capacity hour 8.000 261.00 2088.00
Tipper tonne.km 990 x L 2.00 23760.00
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 155.00 310.00
Mazdoor skilled day 15.000 196.00 2940.00
Mazdoor day 35.000 155.00 5425.00
b) Machinery
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Road Sweeper @ 1250 sqm per hour hour 2.800 300.00 840.00
Front end loader 1 cum bucket capacity hour 18.000 679.00 12222.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 0.00 0.00
(effective output)
Electric generator 250 KVA hour 6.000 979.00 5874.00
Slip form paver with electronic sensor hour 6.000 2415.00 14490.00
Water tanker6 KL capacity hour 36.000 261.00 9396.00
Transit truck agitator 5 cum capacity. tonne.km 2415xL 2.00 57960.00
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 155.00 186.00
Mazdoor skilled day 7.000 196.00 1372.00
Mazdoor day 23.000 155.00 3565.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 0.00 0.00
Electric generator 100 KVA hour 6.000 588.00 3528.00
Paver with electronic sensor @ 75 cum/hr. hour 6.000 2252.00 13512.00
Vibratory roller 8-10 t capacity hour 8.000 1298.00 10384.00
Water tanker with 5 km lead 6 KL capacity hour 8.000 261.00 2088.00
Tipper tonne.km 990xL 2.00 23760.00
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 155.00 173.60
Mazdoor skilled day 6.000 196.00 1176.00
Mazdoor day 22.000 155.00 3410.00
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 679.00 4074.00
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 0.00 0.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Electric generator 100 KVA hour 6.000 588.00 3528.00
Paver finisher with electronic sensor hour 6.000 2252.00 13512.00
Vibratory roller 8-10 t capacity hour 8.000 1298.00 10384.00
Water tanker6 KL capacity hour 8.000 261.00 2088.00
Tipper 10 T Capacity tonne.km 990 x L 2.00 23760.00
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 155.00 310.00
Mazdoor skilled day 15.000 196.00 2940.00
Mazdoor day 35.000 155.00 5425.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 300.00 840.00
Front end loader 1 cum bucket capacity hour 18.000 679.00 12222.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 0.00 0.00
(effective output)
Electric generator 250 KVA hour 6.000 979.00 5874.00
Slip form paver with electronic sensor hour 6.000 2415.00 14490.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Water tanker6 KL capacity hour 36.000 261.00 9396.00
Transit truck agitator 5 cum capacity. tonne.km 2415xL 7.00 202860.00
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
7.1 702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties
as given in clause 702.2.3 formed in to a stable network and
a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702
and approved drawings including excavation and backfilling
Unit = sqm
Taking output = 2800 sqm
a) Labour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mate day 0.800 155.00 124.00
Mazdoor day 20.000 155.00 3100.00
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 300.00 672.00
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1047.00 1465.80
Bitumen pressure distributor 1750 sqm per hour hour 1.680 903.00 1517.04
c) Material
Paving Fabric sqm 2940.000 0.00 0.00
Paving Bitumen 80-100 tonne 2.800 34377.00 96255.60
c) Overhead charges @ 08 % on (a+b) 8250.76
d) Contractor's profit @ 10 % on (a+b+c) 11138.52
Cost for 2800 sqm = a+b+c+d+e 122523.71
Rate per sqm =(a+b+c+d+e)/2800 43.76
say 44.00
7.4 704 Laying Boulder Apron in Crates of Synthetic Geogrids
Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 155.00 9.30
Mazdoor skilled day 0.500 196.00 98.00
Mazdoor day 1.500 155.00 232.50
b) Material
Geo grids sqm 21.000 0.00 0.00
Connectors/ Staples each 50.000 0.00 0.00
Polymer braids metre 20.000 0.00 0.00
Stones with minimum size of 200 mm cum 3.450 1105.00 3812.25
Stones spall for filling voids cum 0.450 553.66 249.15
c) Overhead charges @ 08 % on (a+b) 352.10
d) Contractor's profit @ 10 % on (a+b+c) 475.33
Cost for 3 cum = a+b+c+d 5228.62
Rate per cum = (a+b+c+d)/ 3 402.20
say 402.00
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of
the reinforcing elements.
d) Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of reinforcing elements.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 155.00 55.80
Mazdoor day 6.000 155.00 930.00
Mazdoor skilled day 3.000 196.00 588.00
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per
clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 0.00 0.00
or
2.Copper Strips metre 450*1.1 0.00 0.00
or
3.Aluminium Strips metre 450*1.1 0.00 0.00
or
4.Stainless steel strips metre 450*1.1 0.00 0.00
or
5.Glass reinforced polymer/fibre reinforced metre 450*1.1 0.00 0.00
polymer/polymeric strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia pannels, overlaps,
heat bonding or extension.
Type 1 1.Galvanised carbon steel strips
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 157.38
Cost of 450 m = a+b+c+d 1857.08
Rate per metre =(a+b+c+d)/450 4.13
say 4.00
Type 2 2.Copper Strips
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 157.38
Cost of 450 m = a+b+c+d 1857.08
Rate per metre =(a+b+c+d)/450 4.13
say 4.00
Type 3 3.Aluminium Strips
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 157.38
Cost of 450 m = a+b+c+d 1857.08
Rate per metre =(a+b+c+d)/450 4.13
say 4.00
Type 4 4.Stainless steel strips
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 157.38
Cost of 450 m = a+b+c+d 1857.08
Rate per metre =(a+b+c+d)/450 4.13
say 4.00
Type 5 5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 157.38
Cost of 450 m = a+b+c+d 1857.08
Rate per metre =(a+b+c+d)/450 4.13
say 4.00
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Taking output = 300 sqm
a) Labour
Mate day 0.360 155.00 55.80
Mazdoor day 6.000 155.00 930.00
Mazdoor skilled day 3.000 196.00 588.00
b) Material
Synthetic Geogrids as per clause 3102.8 and approved sqm 300.000 0.00 0.00
design and specifications.
Add 10 per cent of the cost of reinforcing elements 0.00
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other
protective elements for synthetic geogrids.
c) Overhead charges @ 08 % on (a+b) 125.90
d) Contractor's profit @ 10 % on (a+b+c) 169.97
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 1869.67
Rate per sqm = (a+b+c+d)/ 300 6.23
say 6.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 155.00 27.90
Mazdoor day 3.000 155.00 465.00
Mazdoor skilled day 1.500 196.00 294.00
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 300.00 1800.00
c) Material
Pre-cast RCC M-35 facing elements of size as per cu.m 13.500 4352.00 58752.00
design and 18 cm thick for 75 sqm. (Refer Item 12.8
(H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 66706.00 25348.28
Add 2 per cent of cost of facia pannels, for all necessary 1682.01
temporary form work, scaffolding and provision of loops/lugs
for lifting of pannels and joining the reinforcing elements.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
8.The type of reinforcing elements to be adopted shall be as
per approved design and specifications.
9.The market rate for supply of reinforcing elements and
their accessories are to be ascertained from reputed firms in
the field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 155.00 111.60
Mason day 2.000 196.00 392.00
Mazdoor day 16.000 155.00 2480.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 261.00 1566.00
Concrete mixer 0.48/0.28 cum capacity hour 12.000 196.00 2352.00
Water tanker6 KL capacity hour 5.000 261.00 1305.00
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1423.00 31007.17
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 750.00 8175.00
Cement 11 per cent tonne 5.700 4400.00 25080.00
Cost of water KL 30.000 100.00 3000.00
d) Overhead charges @ 08 % on (a+b+c) 6037.50
e) Contractor's profit @ 10 % on (a+b+c+d) 8150.63
Cost for 360 meter = a+b+c+d+e 89656.90
Rate per metre = (a+b+c+d+e)/360 249.05
say 249.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 155.00 18.60
Mason day 1.000 196.00 196.00
Mazdoor day 2.000 155.00 310.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 261.00 1566.00
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1567.00 2507.20
Water tanker6 KL capacity hour 5.000 261.00 1305.00
Tipper 5.5 cum capacity hour 6.000 261.00 1566.00
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1423.00 31007.17
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 750.00 8175.00
Cement 11 per cent tonne 5.700 4400.00 25080.00
Cost of water KL 30.000 100.00 3000.00
d) Overhead charges @ 08 % on (a+b+c) 5978.48
e) Contractor's profit @ 10 % on (a+b+c+d) 8070.94
Cost for 360 meter = a+b+c+d+e 88780.39
Rate per metre = (a+b+c+d+e)/360 246.61
say 247.00
8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Unit = Running metre 0.140
Taking output = 300 metre length 8.400
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 155.00 111.60
Mason day 2.000 196.00 392.00
Mazdoor day 16.000 155.00 2480.00
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 261.00 1566.00
hour 6.000
and channel
Concrete mixer 0.48/0.28 hour 16.000 196.00 3136.00
Water tanker6 KL capacity hour 6.000 261.00 1566.00
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1423.00 52067.57
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 750.00 13725.00
Cement 10 per cent tonne 9.010 4400.00 39644.00
Cost of water KL 36.000 100.00 3600.00
d) Overhead charges @ 08 % on (a+b+c) 9463.05
e) Contractor's profit @ 10 % on (a+b+c+d) 12775.12
Cost for 360 meter = a+b+c+d+e 140526.35
Rate per metre = (a+b+c+d+e)/300 468.42
say 468.00
8.2 B Using Concrete Batching and Mixing Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 155.00 18.60
Mason day 1.000 196.00 196.00
Mazdoor day 2.000 155.00 310.00
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 261.00 1566.00
hour 6.000
and channel
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1567.00 4230.90
Water tanker6 KL capacity hour 6.000 261.00 1566.00
Tipper of 5.5 cum capacity hour 6.000 261.00 1566.00
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1423.00 52067.57
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 750.00 13725.00
Cement 10 per cent tonne 9.010 4400.00 39644.00
Cost of water KL 36.000 100.00 3600.00
d) Overhead charges @ 08 % on (a+b+c) 9479.21
e) Contractor's profit @ 10 % on (a+b+c+d) 12796.93
Cost for 300 meter = a+b+c+d+e 140766.20
Rate per metre = (a+b+c+d+e)/300 469.22
say 469.00
8.3 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
(i)
Hindi ( Matras commas and the like not to be measured
and paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 155.00 18.60
Painter day 2.000 196.00 392.00
Mazdoor day 1.000 155.00 155.00
b) Material
Paint Litre 0.700 0.00 0.00
c) Overhead charges @ 08 % on (a+b) 45.25
d) Contractor's profit @ 10 % on (a+b+c) 61.08
Cost for 1600 cm = a+b+c+d 671.93
Rate per cm height per letter = (a+b+c+ d)/1600 0.42
say 0.40
8.3 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 155.00 10.85
Painter Ist class day 1.250 196.00 245.00
Mazdoor day 0.500 155.00 77.50
b) Material
Paint Litre 0.500 0.00 0.00
c) Overhead charges @ 08 % on (a+b) 26.67
d) Contractor's profit @ 10 % on (a+b+c) 36.00
Cost for 1600 cm = a+b+c+d 396.02
Rate per cm height per letter = (a+b+c +d)/1600 0.25
say 0.20
8.4 6.05 b 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
153.00 33.05
i) Excavation for foundation cum 0.216
4448.00 533.76
ii) Cement concrete M15 grade cum 0.120
iii) Painting angle iron post two coats sqm 0.430 16.00 6.88
a) Labour (For fixing at site)
Mate day 0.010 155.00 1.55
Mazdoor day 0.250 155.00 38.75
b) Material
46.30 879.70
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
or
( iii ) 60 cm circular sqm 0.283 5118.98 1448.67
or
( iv ) 80 cm x 60 cm rectangular sqm 0.480 5118.98 2457.11
or
(v) 60 cm x 45 cm rectangular sqm 0.270 5118.98 1382.12
or
(vi ) 60 cm x 60 cm square sqm 0.360 5118.98 1842.83
or
( vii ) 90 cm high octagon sqm 0.672 5118.98 3439.95
c) Machinery
Tractor-trolley hour 0.010 306.00 3.06
(i) 90 cm equilateral triangle
d) Overhead charges @ 08 % on (a+b+c) 217.18
e) Contractor's profit @ 10 % on (a+b+c+d) 293.19
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3798.76
say 3799.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 08 % on (a+b+c) 137.73
e) Contractor's profit @ 10 % on (a+b+c+d) 185.94
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2618.97
say 2619.00
( iii ) 60 cm circular
d) Overhead charges @ 08 % on (a+b+c) 189.74
e) Contractor's profit @ 10 % on (a+b+c+d) 256.15
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3391.30
say 3391.00
( iv ) 80 cm x 60 cm rectangular
d) Overhead charges @ 08 % on (a+b+c) 270.41
e) Contractor's profit @ 10 % on (a+b+c+d) 365.06
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4589.33
say 4589.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 08 % on (a+b+c) 184.41
e) Contractor's profit @ 10 % on (a+b+c+d) 248.96
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3312.25
say 3312.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 08 % on (a+b+c) 221.27
e) Contractor's profit @ 10 % on (a+b+c+d) 298.72
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3859.57
say 3860.00
( vii ) 90 cm high octagon
d) Overhead charges @ 08 % on (a+b+c) 349.04
e) Contractor's profit @ 10 % on (a+b+c+d) 471.21
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5756.95
say 5757.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Direction and Place Identification Signs upto 0.9 sqm
8.5 801
Size Board.
Unit = sqm
Taking output = 0.9 sqm
153.00 33.05
i) Excavation for foundation cum 0.216
4448.00 533.76
ii) Cement concrete M15 grade cum 0.120
iii) Painting angle iron post two coats sqm 0.430 16.00 6.88
a) Labour (For fixing at site)
Mate day 0.010 155.00 1.55
Mazdoor day 0.200 155.00 31.00
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 46.30 879.70
kg 19.000
metres long
Aluminium sheeting fixed with encapsulated lens type 5118.98 4607.08
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 306.00 6.12
d) Overhead charges @ 08 % on (a+b+c) 442.04
e) Contractor's profit @ 10 % on (a+b+c+d) 596.75
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 7137.92
Rate per sqm (for sign having area upto 0.9 sqm) =
7931.03
(I+ii+iii+a+b+c+d+e)/0.90
say 7931.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
8.6 6.05 801
than 0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm
153.00 65.79
i) Excavation for foundation cum 0.430
4448.00 1067.52
ii) Cement concrete M15 grade cum 0.240
iii) Painting angle iron post 2 coats sqm 0.860 16.00 13.76
a) Labour (For fixing at site)
Mate day 0.010 155.00 1.55
Mazdoor day 0.300 155.00 46.50
b) Material
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 46.30 1759.40
kg 38.000
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type 5118.98 7678.47
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 306.00 6.12
d) Overhead charges @ 08 % on (a+b+c) 755.52
e) Contractor's profit @ 10 % on (a+b+c+d) 1024.76
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 12419.39
Rate per sqm ( for sign having area more than 0.9
13799.32
sqm) = ( i+ii+iii+a+b+c+d+e)/1.50
say 13799.00
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 155.00 37.20
Blacksmith day 2.000 196.00 392.00
Mazdoor including for handling & fixing at site. day 4.000 155.00 620.00
b) Material
Aluminium alloy/galvanised steel including 5 per cent 31500.00 33075.00
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
330.75
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
5010.86
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 300.00 900.00
Truck hour 0.500 243.00 121.50
d) Overhead charges @ 08 % on (a+b+c) 3238.99
e) Contractor's profit @ 10 % on (a+b+c+d) 4372.63
Rate per tonne = (a+b+c+d+e) 48098.93
say 48099.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 155.00 3.10
Blacksmith day 0.100 196.00 19.60
Mazdoor day 0.150 155.00 23.25
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 0.00 0.00
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
0.46
ladders, pulleys, ropes etc
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Overhead charges @ 08 % on (a+b) 3.71
d) Contractor's profit @ 10 % on (a+b+c) 5.01
Rate per sqm = (a+b+c+d) 55.13
say 55.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
Note
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.
8.8 6.09 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 155.00 18.60
Painter day 2.000 196.00 392.00
Mazdoor day 1.000 155.00 155.00
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 225.00 1350.00
Add for scaffolding @ 1 per cent of labour cost where
13.50
required
Add @ 5 per cent cost of labour and materials to 95.78
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 08 % on (a+b) 161.99
d) Contractor's profit @ 10 % on (a+b+c) 218.69
Cost for 40 sqm = a+b+c+d 2405.56
Rate per sqm = (a+b+c+d)/40 60.14
say 60.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 155.00 4.65
Painter day 0.450 196.00 88.20
Mazdoor day 0.250 155.00 38.75
b) Material
Paint ready mixed approved brand. Litre 1.250 0.00 0.00
Add @ 1 per cent on cost of material for scaffolding 0.00
Add @ 5 per cent cost of labour and materials to 6.58
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 08 % on (a+b) 11.05
d) Contractor's profit @ 10 % on (a+b+c) 14.92
Cost for 10 sqm = a+b+c+d 164.16
Rate per sqm= (a+b+c+d)/10 16.42
say 16.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Taking output = 10 sqm
a) Labour
Mate day 0.030 155.00 4.65
Painter day 0.500 196.00 98.00
Mazdoor day 0.200 155.00 31.00
b) Material
Paint ready mixed of approved brand. Litre 1.500 0.00 0.00
Add @ 1 per cent on cost of material for scaffolding 0.00
Add @ 5 per cent cost of labour and materials to 6.68
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 08 % on (a+b) 11.23
d) Contractor's profit @ 10 % on (a+b+c) 15.16
Cost for 10 sqm = a+b+c+d 166.72
Rate per sqm = (a+b+c+d)/10 16.67
say 17.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.11 803
Coats on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 155.00 13.95
Painter day 0.550 196.00 107.80
Mazdoor day 1.550 155.00 240.25
b) Material
Road marking Paint as per IS :164 Litre 1.480 225.00 333.00
c) Overhead charges @ 08 % on (a+b) 55.60
d) Contractor's profit @ 10 % on (a+b+c) 75.06
Cost for 10 sqm = a+b+c+d 825.66
Rate per sqm= (a+b+c+d)/10 82.57
say 83.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 155.00 10.85
Painter day 0.350 196.00 68.60
Mazdoor day 1.350 155.00 209.25
b) Material
Road marking paint Litre 1.480 225.00 333.00
c) Overhead charges @ 08 % on (a+b) 49.74
d) Contractor's profit @ 10 % on (a+b+c) 67.14
Cost for 10 sqm = a+b+c+d 738.58
Rate per sqm = (a+b+c+d)/10 73.86
say 74.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.12 803
Coats on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 155.00 9.30
Painter Ist class day 0.300 196.00 58.80
Mazdoor day 1.250 155.00 193.75
b) Material
Road marking paint Litre 0.900 225.00 202.50
c) Overhead charges @ 08 % on (a+b) 37.15
d) Contractor's profit @ 10 % on (a+b+c) 50.15
Cost for 10 sqm = a+b+c+d 551.65
Rate per sqm = (a+b+c+d)/10 55.16
say 55.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 155.00 10.85
Painter Ist class day 0.350 196.00 68.60
Mazdoor day 1.350 155.00 209.25
b) Material
Road marking Paint Litre 0.900 225.00 202.50
c) Overhead charges @ 08 % on (a+b) 39.30
d) Contractor's profit @ 10 % on (a+b+c) 53.05
Cost for 10 sqm= a+b+c+d 583.55
Rate per sqm = (a+b+c+d)/10 58.35
say 58.00
Road Marking with Hot Applied Thermoplastic
8.13 6.04 803 Compound with Reflectorising Glass Beads on
Bituminous Surface
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 155.00 4.65
Mazdoor day 0.750 155.00 116.25
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 78.00 780.00
Tractor-trolley hour 0.500 306.00 153.00
c) Material
Hot applied thermoplastic compound Litre 1500.000 296.36 444540.00
Reflectorising glass beads kg 150.000 80.82 12123.00
d) Overhead charges @ 08 % on (a+b+c) 36617.35
e) Contractor's profit @ 10 % on (a+b+c+d) 49433.43
Cost for 600 sqm = a+b+c+d+e 543767.68
Rate per sqm = a+b+c+d+e)/600 906.28
say 906.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
8.14 6.03 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
4448.00 10452.80
a) M-15 grade of concrete cum 2.350
153.00 257.04
c) Excavation in soil for foundation cum 1.680
66.71 1755.70
b) Steel reinforcement @ 5 kg per sqm kg 26.320
153.00 423.81
c) Excavation in soil for foundation cum 2.770
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
66.71 4402.60
b) Steel reinforcement @ 5 kg per sqm kg 66.000
153.00 1640.16
c) Excavation in soil cum 10.720
0.20 456.00
per letter
d) Lettering, each 10 cm high 2280.000
per cm high
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.090 155.00 13.95
Blacksmith day 0.250 196.00 49.00
Mazdoor day 2.000 155.00 310.00
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 54.00 1696.68
kg 31.420
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in 46.30 3727.15
kg 80.500
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
108.48
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 16.00 33.76
sqm 2.110
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 08 % on (a+b) 472.42
e) Contractor's profit @ 10 % on (a+b+d) 637.77
Cost for 30 metres fencing = a+b+c+d+e 7049.20
Rate per metre = (a+b+c+d+e)/30 234.97
say 235.00
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.
8.18 807 G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 155.00 18.60
Blacksmith day 0.400 196.00 78.40
Mazdoor day 2.500 155.00 387.50
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 54.00 2168.10
kg 40.150
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in 46.30 7037.60
kg 152.000
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
184.11
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 16.00 63.36
sqm 3.960
angle iron posts
d) Overhead charges @ 08 % on (a+b) 789.95
e) Contractor's profit @ 10 % on (a+b+d) 1066.43
Cost for 30 metres fencing = a+b+c+d+e 11794.05
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per metre fencing = (a+b+c +d+e)/30 393.13
say 393.00
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.
46.30 1203.80
ii) Runner flat 50 x 5 mm kg 26.000
iii) Welded steel wire fabric 75x50 mm mesh @ 4 0.00 0.00
kg 151.000
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg 293.000
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.100 306.00 30.60
d) Painting
Painting two coats including priming sqm 8.000 16.00 128.00
e) Overhead charges @ 08 % on (a+b+c) 533.34
f) Contractor's profit @ 10 % on (a+b+c+e) 720.01
Cost for 30 metre = a+b+c+d+e+f 8048.16
Rate per metre = (a+b+c+d+e+f)/30 268.27
say 268.00
i) Adopt any one type of welded steel wire fabric 75 x 50 mm
Note
or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
8.20 808
( ISMC series) 100 mm x 50 mm
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
a) Labour (For fixing at site)
Mate day 0.010 155.00 1.55
Mazdoor day 0.250 155.00 38.75
Plumber day 0.010 196.00 1.96
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 0.00 0.00
Medium weight steel channel (ISMC series) 100 mm x 46.30 4600.37
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 92.01
c) Machinery
Tractor-trolley hour 0.040 306.00 12.24
d) Overhead charges @ 08 % on (a+b+c) 634.01
e) Contractor's profit @ 10 % on (a+b+c+d) 855.92
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 9427.32
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 942.73
say 943.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m
8.21 808
High Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 153.00 198.29
cum 1.296
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 4448.00 2882.30
cum 0.648
x 0.6 x 0.3
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 5810.00 1859.20
cum 0.320
metres each
iv) Painting of pipe sqm 4.710 16.00 75.36
a) Labour
Mate day 0.014 155.00 2.17
Mazdoor day 0.350 155.00 54.25
Plumber day 0.010 196.00 1.96
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 0.00 0.00
c) Machinery
Tractor-trolley hour 0.250 306.00 76.50
d) Overhead charges @ 08 % on (a+b+c) 10.79
e) Contractor's profit @ 10 % on (a+b+c+d) 14.57
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 5175.39
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 517.54
say 518.00
8.22 809 Reinforced Cement Concrete Crash Barrier
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
5810.00 17430.00
M 20 grade concrete cum 3.000
b) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 46300.00 12964.00
Pre-moulded asphalt filler board sqm 0.320 0.00 0.00
d) Overhead charges @ 08 % on (b+c) 1050.02
e) Contractor's profit @ 10 % on (b+c+d) 1417.52
Cost for 10 metre = a+b+c+d+e 33022.74
Rate per metre = (a+b+c+d+e)/10 3302.27
say 3302.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
8.23 4.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor day 2.000 155.00 310.00
Blacksmith day 1.000 196.00 196.00
b) Material
46.30 8797.00
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000
ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 46.30 2129.80
kg 46.000
x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for 46.30 8722.92
kg 188.400
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent 0.00 0.00
kg 65.000
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
982.49
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 16.00 264.00
d) Machinery
Tractor-trolley hour 0.250 306.00 76.50
e) Overhead charges @ 08 % on (a+b+d) 1698.66
f) Contractor's profit @ 10 % on (a+b+d+e) 2293.20
Cost for 15 m = a+b+c+d+e+f 25489.17
Rate per m = (a+b+c+d+e+f)/15 1699.28
say 1699.00
The items of excavations and cement concrete works will be
Note measured and included separately as per the approved
designs and drawings.
Suggest
8.26 Anti-Glare Devices in Median
ive
A Plantation
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
Anti-glare screen with 25 mm steel pipe framework
B
fixed with circular and rectangular vans
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
The items of excavation and cement concrete as per
Note
approved design to be measured and paid separately
8.26 C Anti-glare screen with rectangular vane of MS sheet
46.30 416.70
ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000
Add 5 per cent of cost of material for fabrication, nuts, bolts
45.33
etc
c) Machinery
Tractor-trolley hour 0.100 306.00 30.60
d) Painting
Applying 2 coats of painting sqm 0.850 16.00 13.60
e) Overhead charges @ 08 % on (a+b+c) 79.89
f) Contractor's profit @ 10 % on (a+b+c+e) 107.85
Cost for 1.5 m = a+b+c+d+e+f 1199.94
Rate per metre = (a+b+c+d+e+f)/1.50 799.96
say 800.00
Suggest
8.27 Street Lighting
ive
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 155.00 4.65
Mazdoor day 0.500 155.00 77.50
Electrician day 0.250 196.00 49.00
b) Material
i) Steel circular hollow pole of standard specification for 0.00 0.00
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 0.00 0.00
Add 5 per cent of cost of material for holder, electric cable,
0.00
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 16.00 92.00
sqm 5.750
circular hollow pipe with overhang on both sides
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
For fixing in Footpath
Providing two coats of alluminium paint over steel 16.00 74.08
sqm 4.630
circular hollow pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 08 % on (a+b) 10.49
e) Contractor's profit @ 10 % on (a+b+d) 14.16
Rate per light for fixing in Median= a+b+c+d+e 247.81
say 248.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 229.89
say 230.00
The items of excavation and cement concrete foundation will
be measured and included separately in the estimate as per
Note
approved design and drawing. The rate for painting has
been analysed in this chapter.
Suggest
8.28 Lighting on Bridges
ive
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.400 155.00 62.00
Electrician day 0.200 196.00 39.20
b) Material
0.00 0.00
i) Steel circular hollow pole of standard specification for
each 1.000
street lighting to mount light at 5 m above deck level
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
a) Random Rubble masonry/Brick masonry in 3322.00 7839.92
cum 2.360
cement mortar 1:6 for head wall both side
b) Labour
Mate day 0.050 155.00 7.75
Mazdoor day 1.000 155.00 155.00
Mazdoor skilled day 0.250 196.00 49.00
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 20.000 0.00 0.00
Granular soil with PI less than 6 for bedding and sides 1369.00 9856.80
cum 7.200
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 9.000 0.00 0.00
3803.00 76.06
Cement mortar 1:2 for joints cum 0.020
d) Machinery
Tractor-trolley hour 0.500 306.00 153.00
e) Overhead charges @ 08 % on (b+c+d) 823.81
f) Contractor's profit @ 10 % on (b+c+d+e) 1112.14
Cost for 20 metre = a+b+c+d+e+f 20073.48
Rate per metre = (a+b+c+d+e+f)/20 1003.67
say 1004.00
8.29 (ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 3322.00 11195.14
cum 3.370
mortar 1:6 for head wall both sides.
b) Labour
Mate day 0.050 155.00 7.75
Mazdoor day 2.000 155.00 310.00
Mazdoor skilled day 0.250 196.00 49.00
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 0.00 0.00
Granular soil with PI less than 6 for bedding and sides 1369.00 19713.60
cum 14.400
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 0.00 0.00
3803.00 152.12
Cement mortar 1:2 for joints cum 0.040
d) Machinery
Tractor-trolley hour 1.000 306.00 306.00
e) Overhead charges @ 08 % on (b+c+d) 1643.08
f) Contractor's profit @ 10 % on (b+c+d+e) 2218.15
Cost for 20 metre = a+b+c+d+e+f 35594.84
Rate per metre = (a+b+c+d+e+f)/20 1779.74
say 1780.00
8.29 (iii) Triple rRow for three utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 3322.00 14550.36
cum 4.380
mortar 1:6 for head wall both sides.
b) Labour
Mate day 0.160 155.00 24.80
Mazdoor day 3.000 155.00 465.00
Mazdoor skilled day 1.000 196.00 196.00
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 0.00 0.00
Granular soil with PI less than 6 for bedding and sides 1369.00 29570.40
cum 21.600
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each 27.000 0.00 0.00
3803.00 228.18
Cement mortar 1:2 for joints cum 0.060
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
d) Machinery
Tractor-trolley hour 1.500 306.00 459.00
e) Overhead charges @ 08 % on (b+c+d) 2475.47
f) Contractor's profit @ 10 % on (b+c+d+e) 3341.89
Cost for 20 metre = a+b+c+d+e+f 51311.10
Rate per metre = (a+b+c+d+e+f)/20 2565.55
say 2566.00
1.Inspection chamber at both ends is the responsibility of the
Note
agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Suggest
8.30 Highway Patrolling and Traffic Aid Post
ive
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Suggest Items Related to Underpass/ Subway/ Overhead
8.31
ive Bridge/ Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings
Suggest
8.32 Traffic Control System and Communication System
ive
Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location
Suggest
8.33 Gantry Mounted Variable Message Sign Board
ive
Providing and erecting gantry mounted variable message
sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i) Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 2.000 155.00 310.00
Blacksmith day 1.000 196.00 196.00
b) Material
Alluminium alloy/galvanised steel including 5 per cent 31500.00 33075.00
tonne 1.050
wastage
Add 15 per cent of cost of material for fabrication and
4961.25
erection.
Add 1 per cent of cost of material for nuts, bolts and
330.75
welding
c) Machinery
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Truck 10 tonne hour 1.000 243.00 243.00
d) Overhead charges @ 08 % on (a+b+c) 3130.77
e) Contractor's profit @ 10 % on (a+b+c+d) 4226.54
Rate per tonne = a+b+c+d+e 46491.90
say 46492.00
8.33 (ii) Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above
Suggest
8.34 Traffic Impact Attenuators at Abutments and Piers
ive
A With Scrap Tyres
Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 1.500 155.00 232.50
Blacksmith day 0.250 196.00 49.00
b) Material
Scrap tyres of size 900 x 20 each 80.000 0.00 0.00
20 mm steel wire rope kg 150.000 0.00 0.00
Add 1 per cent of cost of wire rope for clamps etc. 0.00
c) Machinery
Tractor-trolley hour 3.000 306.00 918.00
d) Overhead charges @ 08 % on (a+b+c) 96.95
e) Contractor's profit @ 10 % on (a+b+c+d) 130.89
Cost for 20 sqm = a+b+c+d+e 1439.74
Rate per sqm = (a+b+c+d+e)/20 71.99
say 72.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 155.00 20.15
Mazdoor day 3.000 155.00 465.00
Blacksmith day 0.250 196.00 49.00
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 0.00 0.00
Sand cum 8.000 750.00 6000.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
20 mm steel wire rope kg 15.000 0.00 0.00
Add 1 per cent of cost of wire rope for clamps etc. 0.00
c) Machinery
Tractor-trolley hour 2.000 306.00 612.00
d) Overhead charges @ 08 % on (a+b+c) 571.69
e) Contractor's profit @ 10 % on (a+b+c+d) 771.78
Cost for 20 sqm = a+b+c+d+e 8489.63
Rate per sqm = (a+b+c+d+e)/20 424.48
say 424.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 155.00 15.50
Mazdoor day 2.500 155.00 387.50
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 0.00 0.00
Cost of water KL 12.000 100.00 1200.00
20 mm steel wire rope kg 100.000 0.00 0.00
Add 1 per cent of cost of wire rope for clamps etc. 0.00
c) Machinery
Tractor-trolley hour 2.000 306.00 612.00
Water tanker6 KL capacity hour 2.000 261.00 522.00
d) Overhead charges @ 08 % on (a+b+c) 218.96
e) Contractor's profit @ 10 % on (a+b+c+d) 295.60
Cost for 10 sqm = a+b+c+d+e 3251.56
Rate per sqm = (a+b+c+d+e)/10 325.16
say 325.00
Suggest
8.35 Road Markers/Road Stud with Lense Reflector
ive
Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Material
Aluminium studs 100 x 100 mm fitted with lense 0.00 0.00
each 50.000
reflectors
Add 10 per cent of cost of material for fixing and installation 0.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Suggest
8.36 Traffic Cone
ive
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE) material
with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.500 155.00 77.50
b) Material
Traffic cones with 150 mm reflective sleeve each 68.000 0.00 0.00
c) Machinery
Tractor-trolley hour 0.100 306.00 30.60
d) Overhead charges @ 08 % on (a+b+c) 8.90
e) Contractor's profit @ 10 % on (a+b+c+d) 12.01
Cost for 68 Nos. = a+b+c+d+e 132.11
Rate per metre = (a+b+c+d+e)/68 1.94
say 2.00
Suggest
8.37 Roadside Amenities
ive
A Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions
Parking areas and bus laybyes for trucks, buses and
B
light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
C Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings
Suggest
8.38 Rumble Strips
ive
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings
Suggest
8.39 Policeman Umbrella
ive
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Unit = each
Taking output = one number
Earthwork Quantities of these items to be cum
Cement Concrete calculated as per approved design and cum
cost added as per rates of these items
brick masonry or given in chapter 3 and 13 cum
stone masonry cum
Painting sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on (a+b+c)
e) Contractors Profit@ per cent on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e
suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
h) Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
8.42 Safety Devices and Signs in Construction Zones
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 155.00 3.10
Mazdoor day 0.250 155.00 38.75
Painter day 0.500 196.00 98.00
Welder day 0.250 196.00 49.00
b) Material
46.30 694.50
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
8.44 B With wooden components
Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 155.00 7.75
Mazdoor day 0.300 155.00 46.50
Painter day 0.600 196.00 117.60
Carpenter day 0.600 196.00 117.60
b) Material
Timber cum 0.180 0.00 0.00
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 0.00
c) Overhead charges @ 08 % on (a+b) 23.16
d) Contractor's profit @ 10 % on (a+b+c) 31.26
Rate per barricade = a+b+c+d 343.87
say 344.00
8.44 C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 155.00 37.20
Mazdoor day 3.000 155.00 465.00
Painter day 1.000 196.00 196.00
Mason day 2.000 196.00 392.00
b) Material
Brick each 1800.000 9.64 17352.00
4.40 96.80
Cement kg 22.000
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Overhead charges @ 08 % on (a+b) 7.27
d) Contractor's profit @ 10 % on (a+b+c) 9.81
Rate per drum delineator = a+b+c+d 107.93
say 108.00
suggesti
8.46 Flagman
ve
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 0.00 0.00
Wooden staff for fastening of flag 25 mm dia, one m 0.00 0.00
each 1.000
long
c) Overhead charges @ 08 % on (a+b) 12.90
d) Contractor's profit @ 10 % on (a+b+c) 17.41
Rate per flagman = a+b+c+d 191.51
say 192.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-9
PIPE CULVERTS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 155.00 99.20
Mason day 1.000 196.00 196.00
Mazdoor day 15.000 155.00 2325.00
b) Material
40mm Aggregate at site cum 13.800 1379.00 19030.20
Sand at site cum 6.900 750.00 5175.00
Cement at site tonne 3.300 4400.00 14520.00
Cost of water KL 18.000 100.00 1800.00
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 196.00 1176.00
Generator set 33 KVA hour 6.000 313.00 1878.00
Water tanker6 KL capacity hour 3.000 261.00 783.00
d) Overhead charges @ 08 % on (a+b+c) 3758.59
e) Contractor's profit @ 10 % on (a+b+c+d) 5074.10
Cost for 15 cum = a+b+c+d+e 55815.09
Rate per cum = (a+b+c+d+e)/15 3721.01
say 3721.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.180 155.00 27.90
Mason day 0.500 196.00 98.00
Mazdoor day 4.000 155.00 620.00
b) Material
Sand at site cum 0.070 750.00 52.50
Cement at site tonne 0.050 4400.00 220.00
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 0.00 0.00
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 1369.00 6160.50
c) Overhead charges @ 08 % on (a+b) 574.31
d) Contractor's profit @ 10 % on (a+b+c) 775.32
Cost for 12.5 metres = a+b+c+d 8528.53
Rate per metre = (a+b+c+d)/12.5 682.28
say 682.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.2 B 1200 mm dia
a) Labour
Mate day 0.280 155.00 43.40
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mason day 1.000 196.00 196.00
Mazdoor day 6.000 155.00 930.00
b) Material
Sand at site cum 0.090 750.00 67.50
Cement at site tonne 0.070 4400.00 308.00
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 6196.66 77458.25
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 1369.00 6845.00
bedding
c) Overhead charges @ 08 % on (a+b) 6867.85
d) Contractor's profit @ 10 % on (a+b+c) 9271.60
Cost for 12.5 metres = a+b+c+d 101987.60
Rate per metre= (a+b+c+d)/12.5 8159.01
say 8159.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 4.11 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
9.3 B 1200 mm dia NP 4 Pipe
a) Labour
Mate day 0.560 155.00 86.80
Mason day 2.000 196.00 392.00
Mazdoor day 12.000 155.00 1860.00
b) Material
Sand at site cum 0.180 750.00 135.00
Cement at site tonne 0.140 4400.00 616.00
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 6196.66 154916.50
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 1369.00 18823.75
bedding
c) Overhead charges @ 08 % on (a+b) 14146.40
d) Contractor's profit @ 10 % on (a+b+c) 19097.65
Cost for 12.5 metres = a+b+c+d 210074.10
Rate per metre= (a+b+c+d)/12.5 16805.93
say 16806.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER- 10
MAINTENANCE OF ROADS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
10.1 3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.130 1097.00 142.61
Tipper ( L is average lead in km for borrow earth) tonne.km 24xL 2.00 480.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 65.00 260.00
c) Overhead charges @ 08 % on (a+b) 53.04
d) Contractor's profit @ 10 % on (a+b+c) 71.60
Cost for 100 sqm = a+b+c+d 787.64
Rate per sqm on = (a+b+c+d)100 7.88
say 8.00
Note The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
10.4 3004.2 Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 155.00 582.80
Mazdoor Day 90.000 155.00 13950.00
Mazdoor skilled Day 4.000 196.00 784.00
b) Machinery
Air compressor 250 cfm hour 6.000 269.00 1614.00
HMP 100-110 TPH Capacity hour 6.000 19715.00 118290.00
Tipper 10 tonnes capacity hour 45.000 261.00 11745.00
Smooth wheeled roller 8-10 tonnes hour 12.000 388.00 4656.00
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 1419.00 261805.50
Crushed stone aggregates nominal size 11.2mm cum 92.250 1376.00 126936.00
Bitumen 80/100 tonne 14.970 34377.00 514623.69
Bitumen emulsion for tack coat including vertical sides tonne 2.460 26950.00 66297.00
of pot hole.
d) Overhead charges @ 08 % on (a+b+c) 89702.72
e) Contractor's profit @ 10 % on (a+b+c+d) 121098.67
Cost for 10250 sqm = a+b+c+d+e 1332085.38
Rate per sqm = (a+b+c+d+e)/10250 129.96
say 130.00
10.5 3004.2 Filling Pot-holes and Patch Repairs with Bituminous
concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a) Labour
Mate Day 2.920 155.00 452.60
Mazdoor Day 70.000 155.00 10850.00
Mazdoor skilled Day 3.000 196.00 588.00
b) Machinery
Air compressor 250 cfm hour 6.000 269.00 1614.00
HMP 100-110 TPH Capacity hour 6.000 14580.00 87480.00
Tipper 10 tonnes capacity hour 45.000 261.00 11745.00
Smooth wheeled roller 8-10 tonnes hour 12.000 388.00 4656.00
c) Material
I) Bitumen tonne 22.500 34377.00 773482.50
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
ii) Bitumen emulsion for tack coat . tonne 1.180 26950.00 31801.00
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 99.750 1408.00 140448.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Taking output = 3500 sqm
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 2.000 155.00 310.00
b) Material
Stone crusher dust finer than 3mm with not more cum 6.250 982.00 6137.50
than 10 per cent passing 0.075 sieve.
c) Overhead charges @ 08 % on (a+b) 516.79
d) Contractor's profit @ 10 % on (a+b+c) 697.67
Cost for 3500sqm = a+b+c+d 7674.36
Rate per meter = (a+b+c+d)/3500 2.19
say 2.19
10.8 (A) Fog Seal sqm 30.00
3004.3.
2
(B) Crack Prevention courses.
3004.3.
4
(i) Stress Absorbing Membrane (SAM) crack width less than 6 sqm 60.00
mm
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to sqm 73.00
9 mm
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm sqm 96.00
and cracked area above 50 per cent
(iv) Bitumen Impregnated Geotextile sqm 46.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
10.10 3005.2 Repair of old Joints Sealant
Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 0.500 155.00 77.50
b) Material
Primer kg 0.250 0.00 0.00
Sealant kg 1.000 0.00 0.00
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 269.00 13.45
d) Overhead charges @ 08 % on (a+b+c) 7.77
e) Contractor's profit @ 10 % on (a+b+c+d) 10.49
Cost for 10 metres = a+b+c+d+e 115.41
Rate per metre = (a+b+c+d+e)/10 11.54
say 12.00
10.11 3000 Hill Side Drain Clearance
Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate day 0.080 155.00 12.40
Mazdoor day 1.000 155.00 155.00
b) Overhead charges @ 08 % on (a+b) 13.39
c) Contractor's profit @ 10 % on (a+b) 18.08
Cost for 10 metres = a+b+c 198.87
Rate per metre = (a+b+c)/10 19.89
say 20.00
10.12 3000 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock by a bull-
dozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Machinery
Dozer 180 HP @ 60 cum per hour hour 1.670 3133.00 5232.11
c) Overhead charges @ 08 % on (a+b) 431.46
d) Contractor's profit @ 10 % on (a+b+c) 582.48
Cost for 100 cum = a+b+c+d 6407.25
Rate per cum = (a+b+c+d)/100 64.07
say 64.00
Note Land Slide clearance involves pushing of loose earth slided
on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
10.13 3000 Landslide Clearance in Hard Rock Requiring Blasting
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Cost for 3600 cum (a+b+c+d) 383.01
Rate per cum = (a+b+c+d)/3600 0.11
say 0.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-11
HORTICULTURE
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
11.1 307 Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 155.00 6.20
Mazdoor day 1.000 155.00 155.00
b) Overhead charges @ 08 % on (a) 12.90
c) Contractor's profit @ 10 % on (a+b) 17.41
Cost for 15 cum= a+b+c 191.51
Rate per cum = (a+b+c)/15 12.77
say 13.00
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 155.00 26.35
Mazdoor for grassing day 0.750 155.00 116.25
Mazdoor for maintenance for 30 days day 1.000 155.00 155.00
b) Machinery
Water tanker6 KL capacity hour 0.500 261.00 130.50
c) Material
Doob grass kg 100.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 34.25
e) Contractor's profit @ 10 % on (a+b+c+d) 46.23
Cost for 100 sqm = a+b+c+d+e 508.58
Rate per sqm= (a+b+c+d+e)/100 5.09
say 5.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 155.00 34.10
Mazdoor for grassing. day 1.250 155.00 193.75
for maintenance for 30 days day 1.000 155.00 155.00
b) Machinery
Water tanker6 KL capacity hour 0.750 261.00 195.75
c) Material
Doob grass kg 200.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 46.29
e) Contractor's profit @ 10 % on (a+b+c+d) 62.49
Cost for 100 sqm = a+b+c+d+e 687.38
Rate per sqm = (a+b+c+d+e)/100 6.87
say 7.00
Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.3 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 155.00 23.25
Mazdoor for preparation of ground day 0.500 155.00 77.50
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 155.00 1550.00
b) Machinery
Water tanker6 KL capacity hour 15.000 261.00 3915.00
c) Material
Cost of water KL 90.000 100.00 9000.00
d) Overhead charges @ 08 % on (a+b+c) 1157.20
e) Contractor's profit @ 10 % on (a+b+c+d) 1562.22
Cost for 100 sqm = a+b+c+d+e 17184.42
Rate per sqm = (a+b+c+d+e)/100 171.84
say 172.00
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 155.00 38.75
Mazdoor for preparation of ground day 1.000 155.00 155.00
Mali for fetching doobs grass roots hedges and day 1.500 155.00 232.50
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 261.00 130.50
Tractor with tiller hour 0.010 306.00 3.06
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 336.78 202.07
per 100 sqm
Fine grass kg 100.000 0.00 0.00
d) Overhead charges @ 08 % on (a+b+c) 60.95
e) Contractor's profit @ 10 % on (a+b+c+d) 82.28
Cost for 100 sqm = a+b+c+d+e 905.11
Rate per sqm = (a+b+c+d+e)/100 9.05
say 9.00
11.6 307 Maintenance of Lawns with Fine Grassing for the First
Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor day 3.000 155.00 465.00
b) Machinery
Water tanker6 KL capacity hour 0.500 261.00 130.50
c) Material
Cost of water KL 3.000 100.00 300.00
d) Overhead charges @ 08 % on (a+b+c) 73.13
e) Contractor's profit @ 10 % on (a+b+c+d) 98.72
Cost for 100 sqm = a+b+c+d+e 1085.95
Rate per sqm = (a+b+c+d+e) 10.86
say 11.00
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 336.78 336.78
screened, loading, carriage, unloading and
stacking at site
b) Overhead charges @ 08 % on (a) 26.94
c) Contractor's profit @ 10 % on (a+b) 36.37
Rate per cum = (a+b+c) 400.09
400.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000
store/site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per quintal = a+b+c
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 155.00 0.31
Mason day 0.050 196.00 9.80
Mazdoor day 0.050 155.00 7.75
b) Material
Brick 2nd class including carriage each 50.000 9.64 482.00
c) Overhead charges @ 08 % on (a+b) 39.99
d) Contractor's profit @ 10 % on (a+b+c) 53.98
Cost for 10 metre = a+b+c+d 593.83
Rate per metre = (a+b+c+d)/10 59.38
say 59.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 155.00 3.10
Blacksmith day 0.150 196.00 29.40
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 155.00 6.20
Blacksmith day 0.200 196.00 39.20
Mazdoor 0.200 155.00 31.00
b) Material
Empty bitumen drum each 1.500 0.00 0.00
MS sheet50 x 0.5 mm kg 0.650 46.30 30.10
Add 5 per cent of cost of material for welding rods and other 239.22
welding accessories
c) Overhead charges @ 08 % on (a+b) 469.82
d) Contractor's profit @ 10 % on (a+b+c) 634.26
Rate per quintal = a+b+c+d 6976.89
say 6977.00
11.19 New Tree Guard with MS Iron
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 155.00 7.75
Blacksmith day 0.250 196.00 49.00
Mazdoor day 0.250 155.00 38.75
b) Material
MS iron 25 x 6 mm kg 19.200 46.30 888.96
CHAPTER-12
FOUNDATIONS
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
12.1 4.01 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
12.1 (I) B Mechanical Means
12.1 (I) B (ii) Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 155.00 49.60
Mazdoor day 8.00 155.00 1240.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1097.00 6582.00
c) Overhead charges @ 20% on (a+b) 1574.32
d) Contractor's profit @ 10 % on (a+b+c) 944.59
Cost for 210 cum = a+b+c+d 10390.51
Rate per cum = (a+b+c+d)/210 49.48
say 49.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 155.00 62.00
Mazdoor day 10.00 155.00 1550.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1097.00 6582.00
c) Overhead charges @ 20% on (a+b) 1638.80
d) Contractor's profit @ 10 % on (a+b+c) 983.28
Cost for 180 cum = a+b+c+d 10816.08
Rate per cum = (a+b+c+d)/180 60.09
say 60.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 155.00 31.00
Mazdoor day 5.00 155.00 775.00
b) Overhead charges @ 20% on (a) 161.20
c) Contractor's profit @ 10 % on (a+b) 96.72
Cost for 10 cum = a+b+c 1063.92
Rate per cum = (a+b+c)/10 106.39
say 106.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
2 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 155.00 37.20
Mazdoor day 6.00 155.00 930.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1097.00 6582.00
c) Overhead charges @ 20% on (a+b) 1509.84
d) Contractor's profit @ 10 % on (a+b+c) 905.90
Cost for 180 cum = a+b+c+d 9964.94
Rate per cum = (a+b+c+d)/180 55.36
say 55.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 155.00 54.25
Driller day 0.50 155.00 77.50
Blaster day 0.25 155.00 38.75
Mazdoor day 8.00 155.00 1240.00
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 269.00 269.00
c) Material
Blasting Material kg 3.50 0.00 0.00
Detonator electric each 14.00 0.00 0.00
d) Overhead charges @ 20% on (a+b+c) 335.90
e) Contractor's profit @ 10 % on (a+b+c+d) 201.54
Cost for 10 cum = a+b+c+d+e 2216.94
Rate per cum = (a+b+c+d+e)/10 221.69
say 222.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 155.00 31.00
Mazdoor day 5.00 155.00 775.00
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 269.00 1614.00
breaker
c) Overhead charges @ 20% on (a+b) 484.00
d) Contractor's profit @ 10 % on (a+b+c) 290.40
Cost for 10 cum = a+b+c+d 3194.40
Rate per cum = (a+b+c+d)/10 319.44
say 319.00
Note 1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 V Marshy Soil
Unit = cum
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
3 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 155.00 62.00
Mazdoor day 10.00 155.00 1550.00
b) Machinery
Tractor-trolley for removal. hour 2.67 306.00 817.02
c) Overhead charges @ 20% on (a+b) 485.80
d) Contractor's profit @ 10 % on (a+b+c) 291.48
Cost for 10 cum = a+b+c+d 3206.31
Rate per cum = ( a+b+c+d)/ 10 320.63
say 321.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
12.1 (V) B Mechanical Means
a) Labour
Mate day 0.08 155.00 12.40
Mazdoor for dressing sides, bottom and backfilling day 2.00 155.00 310.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1097.00 186.49
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 261.00 117.45
c) Overhead charges @ 20% on (a+b) 125.27
d) Contractor's profit @ 10 % on (a+b+c) 75.16
Cost for 10 cum = a+b+c+d 826.77
Rate per cum = (a+b+c+d)/10 82.68
say 83.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 155.00 18.60
Mazdoor for dressing sides, bottom and backfilling day 3.00 155.00 465.00
b) Machinery
Tractor-trolley for transportation hour 2.00 306.00 612.00
c) Overhead charges @ 20% on (a+b) 219.12
d) Contractor's profit @ 10 % on (a+b+c) 131.47
Cost for 6 cum = a+b+c+d 1446.19
Rate per cum = (a+b+c+d)/6 241.03
say 241.00
12.2 304 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
4 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Taking output = 1 cum
a) Labour
Mate day 0.01 155.00 1.55
Mazdoor day 0.30 155.00 46.50
b) Material
Sand (assuming 20 per cent voids) cum 1.20 600.00 720.00
c) Overhead charges @ 20% on (a+b) 153.61
d) Contractor's profit @ 10 % on (a+b+c) 92.17
Rate per cum = a+b+c+d 1013.83
say 1014.00
12.4 5.07 2100 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 155.00 99.20
Mason day 1.00 196.00 196.00
Mazdoor day 15.00 155.00 2325.00
b) Material
40 mm Aggregate cum 13.50 1379.00 18616.50
coarse Sand cum 6.75 750.00 5062.50
cement tonne 3.45 4400.00 15180.00
Cost of water KL 18.00 100.00 1800.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Water tanker 6 KL capacity hour 2.00 261.00 522.00
d) Overhead charges @ 20% on (a+b+c) 9371.04
e) Contractor's profit @ 10 % on (a+b+c+d) 5622.62
Cost for 15 cum = a+b+c+d+e 61848.86
Rate per cum = (a+b+c+d+e)/15 4123.26
say 4123.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
12.5 4.21 1300 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 9.64 24100.00
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 3177.00 3812.40
analysis)
b) Labour
Mate day 0.48 155.00 74.40
Mason day 4.00 196.00 784.00
Mazdoor day 8.00 155.00 1240.00
c) Overhead charges @ 20% on (a+b) 6002.16
d) Contractor's profit @ 10 % on (a+b+c) 3601.30
Cost for 5 cum = a+b+c+d 39614.26
Rate per cum (a+b+c+d)/5 7922.85
say 7923.00
12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analysis
Unit = 1 cum
Taking output = 1 cum
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
5 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Materials
Cement tonne 0.51 4400.00 2244.00
Sand cum 1.05 750.00 787.50
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.90 155.00 139.50
Total Material and Labour = (a+b) say 3177.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 4400.00 2956.80
Sand cum 0.93 750.00 697.50
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.90 155.00 139.50
Total Material and Labour = (a+b) say 3800.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 4400.00 1774.08
Sand cum 1.12 750.00 840.00
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.90 155.00 139.50
Total Material and Labour = (a+b) say 2760.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 4400.00 1267.20
Sand cum 1.34 750.00 1002.86
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.90 155.00 139.50
Total Material and Labour = (a+b) say 2416.00
12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (a) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 942.97 5186.34
Through and bond stone each 35.00 53.88 1885.80
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 3177.00 4765.50
analysis)
b) Labour
Mate day 0.66 155.00 102.30
Mason day 7.50 196.00 1470.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
6 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Mazdoor day 9.00 155.00 1395.00
c) Overhead charges @ 20% on (a+b) 2960.99
d) Contractor's profit @ 10 % on (a+b+c) 1776.59
Cost for 5 cum = a+b+c+d 19542.51
Rate per cum (a+b+c+d)/5 3908.50
say 3909.00
1405.3 (b) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 808.26 4445.43
Through and bond stone each 35.00 53.88 1885.80
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 3177.00 4924.35
analysis)
b) Labour
Mate day 0.62 155.00 96.10
Mason day 6.00 196.00 1176.00
Mazdoor day 9.00 155.00 1395.00
c) Overhead charges @ 20% on (a+b) 2784.54
d) Contractor's profit @ 10 % on (a+b+c) 1670.72
Cost for 5 cum = a+b+c+d 18377.94
Rate per cum (a+b+c+d)/5 3675.59
say 3676.00
Note The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.8 4.03 1500, Plain/Reinforced Cement Concrete in Open
1700 & Foundation complete as per Drawing and Technical
2100 Specifications.
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 4400.00 18172.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 8.10 1379.00 11169.90
20 mm Aggregate cum 4.05 1423.00 5763.15
10 mm Aggregate cum 1.35 1376.00 1857.60
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 63 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3241.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1944.26
of material, labour and machinery
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 4400.00 22704.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3547.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2127.75
of material, labour and machinery
e) Overhead charges @ 20% on (a+b+c+d) 11064.31
f) Contractor's profit @ 10 % on (a+b+c+d+e) 6638.59
Cost for 15 cum = a+b+c+d+e+f 73024.45
Rate per cum = (a+b+c+d+e+f)/15 4868.30
say 4868.00
'12.8 5.08 C RCC Grade M20
12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 4400.00 183304.00
Coarse Sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 166.64 154.92 25815.87
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 km, L-lead in km tonne.km 300L 7.00 25200.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Material
Cement tonne 5.99 4400.00 26356.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3790.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 2131.72
e) Overhead charges @ 20% on (a+b+c+d) 11795.50
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7077.30
Cost for 15 cum = a+b+c+d+e+f 77850.32
Rate per cum = ( a+b+c+d+e+f )/15 5190.02
say 5190.00
12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 4400.00 210980.00
Coarse sand cum 54.00 750.00 40500.00
40 mm Aggregate cum 43.20 1379.00 59572.80
20 mm Aggregate cum 43.20 1423.00 61473.60
10 mm Aggregate cum 21.60 1376.00 29721.60
Admixture Kg 191.80 154.92 29713.66
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.00 25200.00
lead in Kilometer
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3815.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 2145.77
e) Overhead charges @ 20% on (a+b+c+d) 11873.25
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7123.95
cost of 15 cum = a+b+c+d+e+f 78363.47
Rate per cum (a+b+c+d+e+f )/15 5224.23
say 5224.00
'12.8 4.04 a ii E RCC Grade M25
12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 4400.00 212872.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 193.52 154.92 29980.12
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity 1 cum hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.00 25200.00
lead in Kilometer
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3817.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 2003.46
cost of material, labour and machinery
e) Overhead charges @ 20% on (a+b+c+d) 11849.05
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7109.43
cost of 15 cum = a+b+c+d+e+f 78203.75
Rate per cum (a+b+c+d+e+f )/15 5213.58
say 5214.00
12.8 F Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 4400.00 213840.00
Coarse sand cum 54.00 750.00 40500.00
40 mm Aggregate cum 43.20 1379.00 59572.80
20 mm Aggregate cum 43.20 1423.00 61473.60
10 mm Aggregate cum 21.60 1376.00 29721.60
Admixture Kg 194.40 154.92 30116.45
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.00 25200.00
lead in Kilometer
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Per Cum Basic Cost of Labour, Material & Machinery 3830.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 2010.42
cost of material, labour and machinery
e) Overhead charges @ 20% on (a+b+c+d) 11890.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7134.11
cost of 15 cum = a+b+c+d+e+f 78475.21
Rate per cum = (a+b+c+d+e+f)/15 5231.68
say 5232.00
'12.8 4.04 a iii G RCC Grade M30
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 4400.00 214720.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 195.20 154.92 30240.38
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader 1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.00 25200.00
lead in Kilometer
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Generator 100 KVA hour 6.00 588.00 3528.00
Loader1 cum capacity hour 6.00 679.00 4074.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 7.00 25200.00
lead in Kilometer
Mazdoor for bracing with 2" dia ballies day 12.00 155.00 1860.00
Mazdoor for filling sand bags, stitching and placing day 110.00 155.00 17050.00
c) Machinery
Crane with grab 1 cum capacity hour 50.00 718.00 35900.00
Consumables and other arrangements for piling ballies @ 1823.43
2.5 per cent of (a+b+c).
d) Overhead charges @ 20% on (a+b+c) 14952.11
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
13 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
e) Contractor's profit @ 10 % on (a+b+c+d) 8971.27
Rate per No. (a+b+c+d+e) 98683.92
say 98684.00
Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
'12.9 C Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 16.00 7200.00
Sand bags each 300.00 0.00 0.00
b) Labour
Mate day 0.24 155.00 37.20
Mazdoor for filling sand bags, stitching and placing day 6.00 155.00 930.00
c) Machinery
Front end Loader 1 cum capacity hour 27.00 679.00 18333.00
Tipper 5.5 cum capacity hour 28.00 261.00 7308.00
d) Overhead charges @ 20% on (a+b+c) 6761.64
e) Contractor's profit @ 10 % on (a+b+c+d) 4056.98
Cost for 30 m (a+b+c+d+e) 44626.82
Rate per m (a+b+c+d+e)/30 1487.56
say 1488.00
12.10 1200 & Providing and Laying Cutting Edge of Mild Steel
1900 weighing 40 kg per metre for Well Foundation
complete as per Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 46300.00 48615.00
cent wastage
Nuts & bolts Kg 20.00 67.35 1347.00
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 1.32 155.00 204.60
Fitter day 5.50 196.00 1078.00
Blacksmith day 5.50 196.00 1078.00
Welder day 5.50 196.00 1078.00
Mazdoor day 16.50 155.00 2557.50
Electrodes, cutting gas and other consumables @ 10 per 4996.20
cent of cost of (a) above
c) Overhead charges @ 20% on (a+b) 12190.86
d) Contractor's profit @ 10 % on (a+b+c) 7314.52
Rate per MT (a+b+c+d) 80459.68
say 80460.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation
1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (c) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
14 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3569.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 713.80
e) Overhead charges @ 20% on (a+b+c+d) 856.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 513.94
Rate perm (a+b+c+d+e+f) 5653.30
say 5653.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(i)
Per Cum Basic Cost of Labour, Material & Machinery 3850.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 770.00
e) Overhead charges @ 20% on (a+b+c+d) 924.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 554.40
Rate perm (a+b+c+d+e+f) 6098.40
say 6098.00
12.11 A (ii) RCC M25 Grade
Same as for 12.8 (e) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.5 per cent.
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3241.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 324.10
e) Overhead charges @ 20% on (a+b+c+d) 713.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 427.81
Rate perm (a+b+c+d+e+f) 4705.93
say 4706.00
12.11 B (ii) PCC M20 Grade
Same as for 12.8 (b) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Same as for 12.8 (e) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Same as for 12.8 (h) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixture Kg 18.60 154.92 2881.51
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 300.00 1800.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Taking output = 15 cum
a) Material
Cement tonne 5.99 4400.00 26356.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixture Kg 21.60 154.92 3346.27
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 300.00 1800.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 4134.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2857.21
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
'12.11 C (iii) PCC Grade M30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 4400.00 26752.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixture Kg 21.60 154.92 3346.27
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 300.00 1800.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 4160.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2877.01
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
cost of 120 cum = a+b+c+d+e 680319.93
Rate per cum = (a+b+c+d+e)/120 5669.33
say 5669.00
'12.11 C (iv) PCC Grade M35
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 4400.00 27676.00
Coarse sand cum 6.75 750.00 5062.50
40 mm Aggregate cum 5.40 1379.00 7446.60
20 mm Aggregate cum 5.40 1423.00 7684.20
10 mm Aggregate cum 2.70 1376.00 3715.20
Admixture Kg 21.60 154.92 3346.27
b) Labour
Mate day 0.90 155.00 139.50
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 300.00 1800.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 4222.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2923.21
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Add 5 per cent of cost of material and labour towards cost 22183.51
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3241.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 648.20
e) Contractor's profit @ 10 % on (a+b+c+d) 388.92
Rate per cum = (a+b+c+d+e) 4278.12
say 4278.00
'12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3547.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 709.40
e) Contractor's profit @ 10 % on (a+b+c+d) 425.64
Rate per cum = (a+b+c+d+e) 4682.04
say 4682.00
'12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3790.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 758.00
e) Contractor's profit @ 10 % on (a+b+c+d) 454.80
Rate per cum = (a+b+c+d+e) 5002.80
say 5003.00
12.11 E Case II Using Batching Plant, Transit Mixer and
(iii) Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 4105.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 821.00
e) Contractor's profit @ 10 % on (a+b+c+d) 492.60
Rate per cum = (a+b+c+d+e) 5418.60
say 5419.00
'12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3817.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 763.40
e) Contractor's profit @ 10 % on (a+b+c+d) 458.04
Rate per cum = (a+b+c+d+e) 5038.44
say 5038.00
12.11 E Case II Using Batching Plant, Transit Mixer and
(iv) Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 4133.00
(a+b+c)
d) Overhead charges @ 20% on (a+b+c) 826.60
e) Contractor's profit @ 10 % on (a+b+c+d) 495.96
Rate per cum = (a+b+c+d+e) 5455.56
say 5456.00
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 4400.00 22528.00
Coarse sand cum 6.75 750.00 5062.50
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
24 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Form Work @ 4 per cent of a+b+c 2125.14
d) Overhead charges @ 20% on (a+b+c) 11050.73
e) Contractor's profit @ 10 % on (a+b+c+d) 6630.44
cost of 15 cum = a+b+c+d+e 72934.80
Rate per cum = (a+b+c+d+e)/15 4862.32
say 4862.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete
(i) Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 4400.00 180048.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 163.68 154.92 25357.31
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader (capacity 1 cum) hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Form Work @ 3.75 per cent of a+b+c 2145.77
d) Overhead charges @ 20% on (a+b+c) 11873.25
e) Contractor's profit @ 10 % on (a+b+c+d) 7123.95
cost of 15 cum = a+b+c+d+e 78363.47
Rate per cum = (a+b+c+d+e)/15 5224.23
say 5224.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete
(ii) Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 4400.00 212960.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 193.60 154.92 29992.51
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader (capacity 1 cum) hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
say 5232.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete
(iii) Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 4400.00 214676.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 195.16 154.92 30234.19
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader (capacity 1 cum) hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 202.56 154.92 31380.60
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader (capacity 1 cum) hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
12.12 Section Sinking of 6 m external diameter well (other than
1200 pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 155.00 18.60
Sinker ( skilled ) day 1.00 196.00 196.00
Sinking helper ( semi-skilled ) day 2.00 176.00 352.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 113.32
d) Contractor's profit @ 10 % on (a+b+c) 67.99
Rate per metre = (a+b+c+d) 747.91
say 748.00
12.12 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 155.00 23.25
Sinker day 1.25 196.00 245.00
Sinking helper ( semi-skilled ) day 2.50 176.00 440.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 0.00 0.00
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 141.65
d) Contractor's profit @ 10 % on (a+b+c) 84.99
Rate per metre = (a+b+c+d) 934.89
say 935.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 982.00
12th m 5% 1031.00
13th m 5% 1083.00
14th m 5% 1137.00
15th m 5% 1194.00
16th m 5% 1254.00
17th m 5% 1317.00
18th m 5% 1383.00
19th m 5% 1452.00
20th m 5% 1525.00
Total Cost from 10m upto 20m 12358.00
Avg Rate per metre 1236.00
12.12 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 1639.00 1967.00
22nd m 7.5% 1762.00 2114.00
23rd m 7.5% 1894.00 2273.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
29 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
24th m 7.5% 2036.00 2443.00
25th m 7.5% 2189.00 2627.00
26th m 7.5% 2353.00 2824.00
27th m 7.5% 2529.00 3035.00
28th m 7.5% 2719.00 3263.00
29th m 7.5% 2923.00 3508.00
30th m 7.5% 3142.00 3770.00
Total Cost from 20m upto 30m 23186.00 27824.00
Avg Rate per metre 2319.00 2782.00
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
31st m 10% 3456.00 4147.00
32nd 10% 3802.00 4562.00
33rd m 10% 4182.00 5018.00
34th m 10% 4600.00 5520.00
35th m 10% 5060.00 6072.00
36th m 10% 5566.00 6679.00
37th m 10% 6123.00 7348.00
38th m 10% 6735.00 8082.00
39th m 10% 7409.00 8891.00
40th m 10% 8150.00 9780.00
Total Cost from 30m upto 40m 55083.00 66099.00
Avg Rate per metre 5508.00 6610.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 155.00 23.25
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 2.25 176.00 396.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 0.00 0.00
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 142.65
d) Contractor's profit @ 10 % on (a+b+c) 85.59
Rate per metre = (a+b+c+d) 941.49
say 941.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 155.00 46.50
Sinker day 3.00 196.00 588.00
Sinking helper ( semi-skilled ) day 4.50 176.00 792.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 285.30
d) Contractor's profit @ 10 % on (a+b+c) 171.18
Rate per metre = (a+b+c+d) 1882.98
say 1883.00
12.12 B (iii) Beyond 10 m upto 20 m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
30 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 1977.00 2076.00
12th m 5% 2076.00 2180.00
13th m 5% 2180.00 2289.00
14th m 5% 2289.00 2403.00
15th m 5% 2403.00 2523.00
16th m 5% 2523.00 2649.00
17th m 5% 2649.00 2781.00
18th m 5% 2781.00 2920.00
19th m 5% 2920.00 3066.00
20th m 5% 3066.00 3219.00
Total Cost from 10m upto 20m 24864.00 26106.00
Avg Rate per metre 2486.00 2611.00
12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 3296.00 4120.00 4326.00
22nd m 7.5% 3543.00 4429.00 4650.00
23rd m 7.5% 3809.00 4761.00 4999.00
24th m 7.5% 4095.00 5119.00 5375.00
25th m 7.5% 4402.00 5503.00 5778.00
26th m 7.5% 4732.00 5915.00 6211.00
27th m 7.5% 5087.00 6359.00 6677.00
28th m 7.5% 5469.00 6836.00 7178.00
29th m 7.5% 5879.00 7349.00 7716.00
30th m 7.5% 6320.00 7900.00 8295.00
Total Cost from 20m upto 30m 46632.00 58291.00 61205.00
Avg Rate per metre 4663.00 5829.00 6121.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 6952.00 8342.00 8759.00
32nd 10% 7647.00 9176.00 9635.00
33rd m 10% 8412.00 10094.00 10599.00
34th m 10% 9253.00 11104.00 11659.00
35th m 10% 10178.00 12214.00 12825.00
36th m 10% 11196.00 13435.00 14107.00
37th m 10% 12316.00 14779.00 15518.00
38th m 10% 13548.00 16258.00 17071.00
39th m 10% 14903.00 17884.00 18778.00
40th m 10% 16393.00 19672.00 20656.00
Total Cost from 30m upto 40m 110798.00 132958.00 139607.00
Avg Rate per metre 11080.00 13296.00 13961.00
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
31 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 155.00 142.60
Sinker ( skilled ) day 3.00 196.00 588.00
Sinking helper ( semi-skilled ) day 20.00 176.00 3520.00
Diver day 0.50 196.00 98.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 434.86
Add for dewatering @ of 5 per cent of (a+b), if 239.17
required
c) Overhead charges @ 20% on (a+b) 1004.53
d) Contractor's profit @ 10 % on (a+b+c) 602.72
Rate per metre = (a+b+c+d) 6629.88
say 6630.00
12.12 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 6962.00 7310.00
5th m 5% 7310.00 7676.00
6th m 5% 7676.00 8060.00
7th m 5% 8060.00 8463.00
8th m 5% 8463.00 8886.00
9th m 5% 8886.00 9330.00
10th m 5% 9330.00 9797.00
Total Cost from 4m upto 10m 56687.00 59522.00
Avg Rate per metre 8098.00 8503.00
12.12 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 9797.00 10287.00
12th m 5% 10287.00 10801.00
13th m 5% 10801.00 11341.00
14th m 5% 11341.00 11908.00
15th m 5% 11908.00 12503.00
16th m 5% 12503.00 13128.00
17th m 5% 13128.00 13784.00
18th m 5% 13784.00 14473.00
19th m 5% 14473.00 15197.00
20th m 5% 15197.00 15957.00
Total Cost from 10m upto 20m 123219.00 129379.00
Avg Rate per metre 12322.00 12938.00
12.12 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 16337.00 20421.00 21442.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
32 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
32nd 7.5% 17562.00 21953.00 23051.00
33rd m 7.5% 18879.00 23599.00 24779.00
34th m 7.5% 20295.00 25369.00 26637.00
35th m 7.5% 21817.00 27271.00 28635.00
36th m 7.5% 23453.00 29316.00 30782.00
37th m 7.5% 25212.00 31515.00 33091.00
38th m 7.5% 27103.00 33879.00 35573.00
39th m 7.5% 29136.00 36420.00 38241.00
40th m 7.5% 31321.00 39151.00 41109.00
Total Cost from 30m upto 40m 231115.00 288894.00 303340.00
Avg Rate per metre 23112.00 28889.00 30334.00
12.12 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 34453.00 41344.00 43411.00
32nd 10% 37898.00 45478.00 47752.00
33rd m 10% 41688.00 50026.00 52527.00
34th m 10% 45857.00 55028.00 57779.00
35th m 10% 50443.00 60532.00 63559.00
36th m 10% 55487.00 66584.00 69913.00
37th m 10% 61036.00 73243.00 76905.00
38th m 10% 67140.00 80568.00 84596.00
39th m 10% 73854.00 88625.00 93056.00
40th m 10% 81239.00 97487.00 102361.00
Total Cost from 30m upto 40m 549095.00 658915.00 691859.00
Avg Rate per metre 54910.00 65892.00 69186.00
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 0.00 0.00
Electric Detonators each 18.00 0.00 0.00
b) Labour
Mate day 1.56 155.00 241.80
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 12.00 155.00 1860.00
Mazdoor (Skilled) day 4.00 196.00 784.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 0.00 0.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 161.73
Consumables in sinking @ 10 per cent of cost of (b). 0.00
d) Overhead charges @ 20% on (a+b+c) 679.26
e) Contractor's profit @ 10 % on (a+b+c+d) 407.55
Rate per metre = (a+b+c+d+e) 4483.09
say 4483.00
12.12 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
33 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 4707.00 4942.00
5th m 5% 4942.00 5189.00
6th m 5% 5189.00 5448.00
7th m 5% 5448.00 5720.00
8th m 5% 5720.00 6006.00
9th m 5% 6006.00 6306.00
10th m 5% 6306.00 6621.00
Total Cost from 4m upto 10m 38318.00 40232.00
Avg Rate per metre 5474.00 5747.00
(iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 6621.00 6952.00
12th m 5% 6952.00 7300.00
13th m 5% 7300.00 7665.00
14th m 5% 7665.00 8048.00
15th m 5% 8048.00 8450.00
16th m 5% 8450.00 8873.00
17th m 5% 8873.00 9317.00
18th m 5% 9317.00 9783.00
19th m 5% 9783.00 10272.00
20th m 5% 10272.00 10786.00
Total Cost from 10m upto 20m 83281.00 87446.00
Avg Rate per metre 8328.00 8745.00
12.12 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 11042.00 13803.00 14493.00
32nd 7.5% 11870.00 14838.00 15580.00
33rd m 7.5% 12760.00 15950.00 16748.00
34th m 7.5% 13717.00 17146.00 18003.00
35th m 7.5% 14746.00 18433.00 19355.00
36th m 7.5% 15852.00 19815.00 20806.00
37th m 7.5% 17041.00 21301.00 22366.00
38th m 7.5% 18319.00 22899.00 24044.00
39th m 7.5% 19693.00 24616.00 25847.00
40th m 7.5% 21170.00 26463.00 27786.00
Total Cost from 30m upto 40m 156210.00 195264.00 205028.00
Avg Rate per metre 15621.00 19526.00 20503.00
12.12 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 23287.00 27944.00 29341.00
32nd 10% 25616.00 30739.00 32276.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
34 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
33rd m 10% 28178.00 33814.00 35505.00
34th m 10% 30996.00 37195.00 39055.00
35th m 10% 34096.00 40915.00 42961.00
36th m 10% 37506.00 45007.00 47257.00
37th m 10% 41257.00 49508.00 51983.00
38th m 10% 45383.00 54460.00 57183.00
39th m 10% 49921.00 59905.00 62900.00
40th m 10% 54913.00 65896.00 69191.00
Total Cost from 30m upto 40m 371153.00 445383.00 467652.00
Avg Rate per metre 37115.00 44538.00 46765.00
12.13 Section Sinking of 7 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 155.00 23.25
Sinker ( skilled ) day 1.25 196.00 245.00
Sinking helper ( semi-skilled ) day 2.50 176.00 440.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 141.65
d) Contractor's profit @ 10 % on (a+b+c) 70.83
Rate per metre = (a+b+c+d) 920.73
12.13 A (ii) Beyond 3m upto 10m depth 1841.45
Rate of sinking = 0.22 m per hour. say 1841.00
a) Labour
Mate day 0.18 155.00 27.90
Sinker day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 3.00 176.00 528.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 169.98
d) Contractor's profit @ 10 % on (a+b+c) 101.99
Rate per metre = (a+b+c+d) 1121.87
say 1122.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 1178.00
12th m 5% 1237.00
13th m 5% 1299.00
14th m 5% 1364.00
15th m 5% 1432.00
16th m 5% 1504.00
17th m 5% 1579.00
18th m 5% 1658.00
19th m 5% 1741.00
20th m 5% 1828.00
Total Cost from 10m upto 20m 14820.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
35 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Avg Rate per metre 1482.00
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge
21st m 7.5% 1965.00 2358.00
22nd m 7.5% 2112.00 2534.00
23rd m 7.5% 2270.00 2724.00
24th m 7.5% 2440.00 2928.00
25th m 7.5% 2623.00 3148.00
26th m 7.5% 2820.00 3384.00
27th m 7.5% 3032.00 3638.00
28th m 7.5% 3259.00 3911.00
29th m 7.5% 3503.00 4204.00
30th m 7.5% 3766.00 4519.00
Total Cost from 20m upto 30m 27790.00 33348.00
Avg Rate per metre 2779.00 3335.00
12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 4143.00 4972.00
32nd 10% 4557.00 5468.00
33rd m 10% 5013.00 6016.00
34th m 10% 5514.00 6617.00
35th m 10% 6065.00 7278.00
36th m 10% 6672.00 8006.00
37th m 10% 7339.00 8807.00
38th m 10% 8073.00 9688.00
39th m 10% 8880.00 10656.00
40th m 10% 9768.00 11722.00
Total Cost from 30m upto 40m 66024.00 79230.00
Avg Rate per metre 6602.00 7923.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 155.00 27.90
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 3.00 176.00 528.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
d) Overhead charges @ 20% on (a+b) 169.98
e) Contractor's profit @ 10 % on (a+b+c) 101.99
Rate per metre = (a+b+c+d) 1121.87
say 1122.00
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 155.00 40.30
Sinker day 2.00 196.00 392.00
Sinking helper ( semi-skilled ) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
36 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Air compressor with pneumatic chisel attachment for hour 3.25 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 227.26
d) Contractor's profit @ 10 % on (a+b+c) 136.36
Rate per metre = (a+b+c+d) 1499.92
say 1500.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 1575.00 1654.00
12th m 5% 1654.00 1737.00
13th m 5% 1737.00 1824.00
14th m 5% 1824.00 1915.00
15th m 5% 1915.00 2011.00
16th m 5% 2011.00 2112.00
17th m 5% 2112.00 2218.00
18th m 5% 2218.00 2329.00
19th m 5% 2329.00 2445.00
20th m 5% 2445.00 2567.00
Total Cost from 10m upto 20m 19820.00 20812.00
Avg Rate per metre 1982.00 2081.00
12.13 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 2628.00 3285.00 3449.00
32nd 7.5% 2825.00 3531.00 3708.00
33rd m 7.5% 3037.00 3796.00 3986.00
34th m 7.5% 3265.00 4081.00 4285.00
35th m 7.5% 3510.00 4388.00 4607.00
36th m 7.5% 3773.00 4716.00 4952.00
37th m 7.5% 4056.00 5070.00 5324.00
38th m 7.5% 4360.00 5450.00 5723.00
39th m 7.5% 4687.00 5859.00 6152.00
40th m 7.5% 5039.00 6299.00 6614.00
Total Cost from 30m upto 40m 37180.00 46475.00 48800.00
Avg Rate per metre 3718.00 4648.00 4880.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 5543.00 6652.00 6985.00
32nd 10% 6097.00 7316.00 7682.00
33rd m 10% 6707.00 8048.00 8450.00
34th m 10% 7378.00 8854.00 9297.00
35th m 10% 8116.00 9739.00 10226.00
36th m 10% 8928.00 10714.00 11250.00
37th m 10% 9821.00 11785.00 12374.00
38th m 10% 10803.00 12964.00 13612.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
37 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
39th m 10% 11883.00 14260.00 14973.00
40th m 10% 13071.00 15685.00 16469.00
Total Cost from 30m upto 40m 88347.00 106017.00 111318.00
Avg Rate per metre 8835.00 10602.00 11132.00
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
(i) Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 155.00 89.90
Sinker ( skilled ) day 4.00 196.00 784.00
Sinking helper ( semi-skilled ) day 10.00 176.00 1760.00
Diver day 0.75 196.00 147.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ of 5 per cent of (a+b), if 139.05
required
c) Overhead charges @ 20% on (a+b) 583.99
d) Contractor's profit @ 10 % on (a+b+c) 350.39
Rate per metre = (a+b+c+d) 3854.33
say 3854.00
12.13 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 4047.00 4249.00
5th m 5% 4249.00 4461.00
6th m 5% 4461.00 4684.00
7th m 5% 4684.00 4918.00
8th m 5% 4918.00 5164.00
9th m 5% 5164.00 5422.00
10th m 5% 5422.00 5693.00
Total Cost from 4m upto 10m 32945.00 34591.00
Avg Rate per metre 4706.00 4942.00
12.13 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 5693.00 5978.00
12th m 5% 5978.00 6277.00
13th m 5% 6277.00 6591.00
14th m 5% 6591.00 6921.00
15th m 5% 6921.00 7267.00
16th m 5% 7267.00 7630.00
17th m 5% 7630.00 8012.00
18th m 5% 8012.00 8413.00
19th m 5% 8413.00 8834.00
20th m 5% 8834.00 9276.00
Total Cost from 10m upto 20m 71616.00 75199.00
Avg Rate per metre 7162.00 7520.00
12.13 C (iv) Beyond 20m upto 30 m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
38 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 9497.00 11871.00 12465.00
32nd 7.5% 10209.00 12761.00 13399.00
33rd m 7.5% 10975.00 13719.00 14405.00
34th m 7.5% 11798.00 14748.00 15485.00
35th m 7.5% 12683.00 15854.00 16647.00
36th m 7.5% 13634.00 17043.00 17895.00
37th m 7.5% 14657.00 18321.00 19237.00
38th m 7.5% 15756.00 19695.00 20680.00
39th m 7.5% 16938.00 21173.00 22232.00
40th m 7.5% 18208.00 22760.00 23898.00
Total Cost from 30m upto 40m 134355.00 167945.00 176343.00
Avg Rate per metre 13436.00 16795.00 17634.00
12.13 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 20029.00 24035.00 25237.00
32nd 10% 22032.00 26438.00 27760.00
33rd m 10% 24235.00 29082.00 30536.00
34th m 10% 26659.00 31991.00 33591.00
35th m 10% 29325.00 35190.00 36950.00
36th m 10% 32258.00 38710.00 40646.00
37th m 10% 35484.00 42581.00 44710.00
38th m 10% 39032.00 46838.00 49180.00
39th m 10% 42935.00 51522.00 54098.00
40th m 10% 47229.00 56675.00 59509.00
Total Cost from 30m upto 40m 319218.00 383062.00 402217.00
Avg Rate per metre 31922.00 38306.00 40222.00
12.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
(i) Depth in Hard rock strata up to 3 m
a) Material
Gelatine 80 per cent Kg 7.00 0.00 0.00
Electric Detonators each 30.00 0.00 0.00
b) Labour
Mate day 1.60 155.00 248.00
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 18.00 155.00 2790.00
Mazdoor (Skilled) day 4.00 196.00 784.00
Diver day 0.50 196.00 98.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 0.00 0.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 213.44
Consumables in sinking @ 10 per cent of cost of (b). 21.34
d) Overhead charges @ 20% on (a+b+c) 900.71
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
39 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
e) Contractor's profit @ 10 % on (a+b+c+d) 540.42
Rate per metre = (a+b+c+d+e) 5944.66
say 5945.00
12.13 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 6242.00 6554.00
5th m 5% 6554.00 6882.00
6th m 5% 6882.00 7226.00
7th m 5% 7226.00 7587.00
8th m 5% 7587.00 7966.00
9th m 5% 7966.00 8364.00
10th m 5% 8364.00 8782.00
Total Cost from 4m upto 10m 50821.00 53361.00
Avg Rate per metre 7260.00 7623.00
12.13 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 8782.00 9221.00
12th m 5% 9221.00 9682.00
13th m 5% 9682.00 10166.00
14th m 5% 10166.00 10674.00
15th m 5% 10674.00 11208.00
16th m 5% 11208.00 11768.00
17th m 5% 11768.00 12356.00
18th m 5% 12356.00 12974.00
19th m 5% 12974.00 13623.00
20th m 5% 13623.00 14304.00
Total Cost from 10m upto 20m 110454.00 115976.00
Avg Rate per metre 11045.00 11598.00
12.13 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 14645.00 18306.00 19221.00
32nd 7.5% 15743.00 19679.00 20663.00
33rd m 7.5% 16924.00 21155.00 22213.00
34th m 7.5% 18193.00 22741.00 23878.00
35th m 7.5% 19557.00 24446.00 25668.00
36th m 7.5% 21024.00 26280.00 27594.00
37th m 7.5% 22601.00 28251.00 29664.00
38th m 7.5% 24296.00 30370.00 31889.00
39th m 7.5% 26118.00 32648.00 34280.00
40th m 7.5% 28077.00 35096.00 36851.00
Total Cost from 30m upto 40m 207178.00 258972.00 271921.00
Avg Rate per metre 20718.00 25897.00 27192.00
12.13 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
40 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 30885.00 37062.00 38915.00
32nd 10% 33974.00 40769.00 42807.00
33rd m 10% 37371.00 44845.00 47087.00
34th m 10% 41108.00 49330.00 51797.00
35th m 10% 45219.00 54263.00 56976.00
36th m 10% 49741.00 59689.00 62673.00
37th m 10% 54715.00 65658.00 68941.00
38th m 10% 60187.00 72224.00 75835.00
39th m 10% 66206.00 79447.00 83419.00
40th m 10% 72827.00 87392.00 91762.00
Total Cost from 30m upto 40m 492233.00 590679.00 620212.00
Avg Rate per metre 49223.00 59068.00 62021.00
12.14 Section Sinking of 8 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 155.00 27.90
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 3.00 176.00 528.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 169.98
d) Contractor's profit @ 10 % on (a+b+c) 101.99
Rate per metre = (a+b+c+d) 1121.87
say 1122.00
12.14 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 155.00 38.75
Sinker day 1.75 196.00 343.00
Sinking helper ( semi-skilled ) day 3.50 176.00 616.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 199.55
d) Contractor's profit @ 10 % on (a+b+c) 119.73
Rate per metre = (a+b+c+d) 1317.03
say 1317.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 1383.00
12th m 5% 1452.00
13th m 5% 1525.00
14th m 5% 1601.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
41 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
15th m 5% 1681.00
16th m 5% 1765.00
17th m 5% 1853.00
18th m 5% 1946.00
19th m 5% 2043.00
20th m 5% 2145.00
Total Cost from 10m upto 20m 17394.00
Avg Rate per metre 1739.00
12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 2306.00 2767.00
22nd m 7.5% 2479.00 2975.00
23rd m 7.5% 2665.00 3198.00
24th m 7.5% 2865.00 3438.00
25th m 7.5% 3080.00 3696.00
26th m 7.5% 3311.00 3973.00
27th m 7.5% 3559.00 4271.00
28th m 7.5% 3826.00 4591.00
29th m 7.5% 4113.00 4936.00
30th m 7.5% 4421.00 5305.00
Total Cost from 20m upto 30m 32625.00 39150.00
Avg Rate per metre 3263.00 3915.00
12.14 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 4863.00 5836.00
32nd 10% 5349.00 6419.00
33rd m 10% 5884.00 7061.00
34th m 10% 6472.00 7766.00
35th m 10% 7119.00 8543.00
36th m 10% 7831.00 9397.00
37th m 10% 8614.00 10337.00
38th m 10% 9475.00 11370.00
39th m 10% 10423.00 12508.00
40th m 10% 11465.00 13758.00
Total Cost from 30m upto 40m 11465.00 13758.00
Avg Rate per metre 1147.00 1376.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 155.00 34.10
Sinker ( skilled ) day 3.50 196.00 686.00
Sinking helper ( semi-skilled ) hour 5.50 176.00 968.00
b) Machinery
Hire & running charges of crane with grab bucket of 5.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 337.62
d) Contractor's profit @ 10 % on (a+b+c) 202.57
Rate per metre = (a+b+c+d) 2228.29
say 2228.00
12.14 B (ii) Beyond 3m upto 10m depth
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
42 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 155.00 49.60
Sinker day 2.50 196.00 490.00
Sinking helper ( semi-skilled ) day 4.50 176.00 792.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 266.32
d) Contractor's profit @ 10 % on (a+b+c) 159.79
Rate per metre = (a+b+c+d) 1757.71
say 1758.00
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 1846.00 1938.00
12th m 5% 1938.00 2035.00
13th m 5% 2035.00 2137.00
14th m 5% 2137.00 2244.00
15th m 5% 2244.00 2356.00
16th m 5% 2356.00 2474.00
17th m 5% 2474.00 2598.00
18th m 5% 2598.00 2728.00
19th m 5% 2728.00 2864.00
20th m 5% 2864.00 3007.00
Total Cost from 10m upto 20m 23220.00 24381.00
Avg Rate per metre 2322.00 2438.00
12.14 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 3079.00 3849.00 4041.00
32nd 7.5% 3310.00 4138.00 4345.00
33rd m 7.5% 3558.00 4448.00 4670.00
34th m 7.5% 3825.00 4781.00 5020.00
35th m 7.5% 4112.00 5140.00 5397.00
36th m 7.5% 4420.00 5525.00 5801.00
37th m 7.5% 4752.00 5940.00 6237.00
38th m 7.5% 5108.00 6385.00 6704.00
39th m 7.5% 5491.00 6864.00 7207.00
40th m 7.5% 5903.00 7379.00 7748.00
Total Cost from 30m upto 40m 43558.00 54449.00 57170.00
Avg Rate per metre 4356.00 5445.00 5717.00
12.14 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
43 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
31st m 10% 6493.00 7792.00 8182.00
32nd 10% 7142.00 8570.00 8999.00
33rd m 10% 7856.00 9427.00 9898.00
34th m 10% 8642.00 10370.00 10889.00
35th m 10% 9506.00 11407.00 11977.00
36th m 10% 10457.00 12548.00 13175.00
37th m 10% 11503.00 13804.00 14494.00
38th m 10% 12653.00 15184.00 15943.00
39th m 10% 13918.00 16702.00 17537.00
40th m 10% 15310.00 18372.00 19291.00
Total Cost from 30m upto 40m 103480.00 124176.00 130385.00
Avg Rate per metre 10348.00 12418.00 13039.00
12.14 C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
(i) Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 155.00 105.40
Sinker ( skilled ) day 4.00 196.00 784.00
Sinking helper ( semi-skilled ) day 12.00 176.00 2112.00
Diver day 1.00 196.00 196.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ of 5 per cent of (a+b), if 159.87
required
c) Overhead charges @ 20% on (a+b) 671.45
d) Contractor's profit @ 10 % on (a+b+c) 402.87
Rate per metre = (a+b+c+d) 4431.60
say 4432.00
12.14 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 4654.00 4887.00
5th m 5% 4887.00 5131.00
6th m 5% 5131.00 5388.00
7th m 5% 5388.00 5657.00
8th m 5% 5657.00 5940.00
9th m 5% 5940.00 6237.00
10th m 5% 6237.00 6549.00
Total Cost from 4m upto 10m 37894.00 39789.00
Avg Rate per metre 5413.00 5684.00
12.14 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 6549.00 6876.00
12th m 5% 6876.00 7220.00
13th m 5% 7220.00 7581.00
14th m 5% 7581.00 7960.00
15th m 5% 7960.00 8358.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
44 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
16th m 5% 8358.00 8776.00
17th m 5% 8776.00 9215.00
18th m 5% 9215.00 9676.00
19th m 5% 9676.00 10160.00
20th m 5% 10160.00 10668.00
Total Cost from 10m upto 20m 82371.00 86490.00
Avg Rate per metre 8237.00 8649.00
12.14 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 10922.00 13653.00 14336.00
32nd 7.5% 11741.00 14676.00 15410.00
33rd m 7.5% 12622.00 15778.00 16567.00
34th m 7.5% 13569.00 16961.00 17809.00
35th m 7.5% 14587.00 18234.00 19146.00
36th m 7.5% 15681.00 19601.00 20581.00
37th m 7.5% 16857.00 21071.00 22125.00
38th m 7.5% 18121.00 22651.00 23784.00
39th m 7.5% 19480.00 24350.00 25568.00
40th m 7.5% 20941.00 26176.00 27485.00
Total Cost from 30m upto 40m 154521.00 193151.00 202811.00
Avg Rate per metre 15452.00 19315.00 20281.00
12.14 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 23035.00 27642.00 29024.00
32nd 10% 25339.00 30407.00 31927.00
33rd m 10% 27873.00 33448.00 35120.00
34th m 10% 30660.00 36792.00 38632.00
35th m 10% 33726.00 40471.00 42495.00
36th m 10% 37099.00 44519.00 46745.00
37th m 10% 40809.00 48971.00 51420.00
38th m 10% 44890.00 53868.00 56561.00
39th m 10% 49379.00 59255.00 62218.00
40th m 10% 54317.00 65180.00 68439.00
Total Cost from 30m upto 40m 367127.00 440553.00 462581.00
Avg Rate per metre 36713.00 44055.00 46258.00
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 0.00 0.00
Electric Detonators each 32.00 0.00 0.00
b) Labour
Mate day 1.09 155.00 168.95
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 20.00 155.00 3100.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
45 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Mazdoor (Skilled) day 4.00 196.00 784.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 0.00 0.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 220.09
Consumables in sinking @ 10 per cent of cost of (b). 440.17
d) Overhead charges @ 20% on (a+b+c) 1012.39
e) Contractor's profit @ 10 % on (a+b+c+d) 607.43
Rate per metre = (a+b+c+d+e) 6681.78
say 6682.00
12.14 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 7016.00 7367.00
5th m 5% 7367.00 7735.00
6th m 5% 7735.00 8122.00
7th m 5% 8122.00 8528.00
8th m 5% 8528.00 8954.00
9th m 5% 8954.00 9402.00
10th m 5% 9402.00 9872.00
Total Cost from 4m upto 10m 57124.00 59980.00
Avg Rate per metre 8161.00 8569.00
12.14 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 9872.00 10366.00
12th m 5% 10366.00 10884.00
13th m 5% 10884.00 11428.00
14th m 5% 11428.00 11999.00
15th m 5% 11999.00 12599.00
16th m 5% 12599.00 13229.00
17th m 5% 13229.00 13890.00
18th m 5% 13890.00 14585.00
19th m 5% 14585.00 15314.00
20th m 5% 15314.00 16080.00
Total Cost from 10m upto 20m 124166.00 130374.00
Avg Rate per metre 12417.00 13037.00
12.14 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 16463.00 20579.00 21608.00
32nd 7.5% 17698.00 22123.00 23229.00
33rd m 7.5% 19025.00 23781.00 24970.00
34th m 7.5% 20452.00 25565.00 26843.00
35th m 7.5% 21986.00 27483.00 28857.00
36th m 7.5% 23635.00 29544.00 31021.00
37th m 7.5% 25408.00 31760.00 33348.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
46 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
38th m 7.5% 27314.00 34143.00 35850.00
39th m 7.5% 29363.00 36704.00 38539.00
40th m 7.5% 31565.00 39456.00 41429.00
Total Cost from 30m upto 40m 232909.00 291138.00 305694.00
Avg Rate per metre 23291.00 29114.00 30569.00
12.14 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 34722.00 41666.00 43749.00
32nd 10% 38194.00 45833.00 48125.00
33rd m 10% 42013.00 50416.00 52937.00
34th m 10% 46214.00 55457.00 58230.00
35th m 10% 50835.00 61002.00 64052.00
36th m 10% 55919.00 67103.00 70458.00
37th m 10% 61511.00 73813.00 77504.00
38th m 10% 67662.00 81194.00 85254.00
39th m 10% 74428.00 89314.00 93780.00
40th m 10% 81871.00 98245.00 103157.00
Total Cost from 30m upto 40m 553369.00 664043.00 697246.00
Avg Rate per metre 55337.00 66404.00 69725.00
12.15 Section Sinking of 9 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 155.00 29.45
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 3.25 176.00 572.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 179.09
d) Contractor's profit @ 10 % on (a+b+c) 107.45
Rate per metre = (a+b+c+d) 1181.99
say 1182.00
12.15 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 155.00 41.85
Sinker day 1.75 196.00 343.00
Sinking helper ( semi-skilled ) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 217.77
d) Contractor's profit @ 10 % on (a+b+c) 130.66
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
47 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Rate per metre = (a+b+c+d) 1437.28
say 1437.00
12.15 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 1509.00
12th m 5% 1584.00
13th m 5% 1663.00
14th m 5% 1746.00
15th m 5% 1833.00
16th m 5% 1925.00
17th m 5% 2021.00
18th m 5% 2122.00
19th m 5% 2228.00
20th m 5% 2339.00
Total Cost from 10m upto 20m 18970.00
Avg Rate per metre 1897.00
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 2514.43 3017.00
22nd m 7.5% 2703.00 3244.00
23rd m 7.5% 2906.00 3487.00
24th m 7.5% 3124.00 3749.00
25th m 7.5% 3358.00 4030.00
26th m 7.5% 3610.00 4332.00
27th m 7.5% 3881.00 4657.00
28th m 7.5% 4172.00 5006.00
29th m 7.5% 4485.00 5382.00
30th m 7.5% 4821.00 5785.00
Total Cost from 20m upto 30m 35574.43 42689.00
Avg Rate per metre 3557.00 4269.00
12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 5303.10 6364.00
32nd 10% 5833.00 7000.00
33rd m 10% 6416.00 7699.00
34th m 10% 7058.00 8470.00
35th m 10% 7764.00 9317.00
36th m 10% 8540.00 10248.00
37th m 10% 9394.00 11273.00
38th m 10% 10333.00 12400.00
39th m 10% 11366.00 13639.00
40th m 10% 12503.00 15004.00
Total Cost from 30m upto 40m 84510.10 101414.00
Avg Rate per metre 8451.00 10141.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 155.00 37.20
Sinker ( skilled ) day 2.25 196.00 441.00
Sinking helper ( semi-skilled ) day 3.75 176.00 660.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
48 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 227.64
d) Contractor's profit @ 10 % on (a+b+c) 136.58
Rate per metre = (a+b+c+d) 1502.42
say 1502.00
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 155.00 52.70
Sinker day 2.50 196.00 490.00
Sinking helper ( semi-skilled ) day 5.00 176.00 880.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 284.54
d) Contractor's profit @ 10 % on (a+b+c) 170.72
Rate per metre = (a+b+c+d) 1877.96
say 1878.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 1972.00 2071.00
12th m 5% 2071.00 2175.00
13th m 5% 2175.00 2284.00
14th m 5% 2284.00 2398.00
15th m 5% 2398.00 2518.00
16th m 5% 2518.00 2644.00
17th m 5% 2644.00 2776.00
18th m 5% 2776.00 2915.00
19th m 5% 2915.00 3061.00
20th m 5% 3061.00 3214.00
Total Cost from 10m upto 20m 24814.00 26056.00
Avg Rate per metre 2481.00 2606.00
12.15 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 3291.00 4114.00 4320.00
32nd 7.5% 3538.00 4423.00 4644.00
33rd m 7.5% 3803.00 4754.00 4992.00
34th m 7.5% 4088.00 5110.00 5366.00
35th m 7.5% 4395.00 5494.00 5769.00
36th m 7.5% 4725.00 5906.00 6201.00
37th m 7.5% 5079.00 6349.00 6666.00
38th m 7.5% 5460.00 6825.00 7166.00
39th m 7.5% 5870.00 7338.00 7705.00
40th m 7.5% 6310.00 7888.00 8282.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
49 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Total Cost from 30m upto 40m 46559.00 58201.00 61111.00
Avg Rate per metre 4656.00 5820.00 6111.00
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 6941.00 8329.00 8745.00
32nd 10% 7635.00 9162.00 9620.00
33rd m 10% 8399.00 10079.00 10583.00
34th m 10% 9239.00 11087.00 11641.00
35th m 10% 10163.00 12196.00 12806.00
36th m 10% 11179.00 13415.00 14086.00
37th m 10% 12297.00 14756.00 15494.00
38th m 10% 13527.00 16232.00 17044.00
39th m 10% 14880.00 17856.00 18749.00
40th m 10% 16368.00 19642.00 20624.00
Total Cost from 30m upto 40m 110628.00 132754.00 139392.00
Avg Rate per metre 11063.00 13275.00 13939.00
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
(i) Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 155.00 117.80
Sinker ( skilled ) day 4.00 196.00 784.00
Sinking helper ( semi-skilled ) day 14.00 176.00 2464.00
Diver day 1.20 196.00 235.20
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ of 5 per cent of (a+b), if 0.00
required
c) Overhead charges @ 20% on (a+b) 720.20
d) Contractor's profit @ 10 % on (a+b+c) 432.12
Rate per metre = (a+b+c+d) 4753.32
say 4753.00
12.15 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 4991.00 5241.00
5th m 5% 5241.00 5503.00
6th m 5% 5503.00 5778.00
7th m 5% 5778.00 6067.00
8th m 5% 6067.00 6370.00
9th m 5% 6370.00 6689.00
10th m 5% 6689.00 7023.00
Total Cost from 4m upto 10m 40639.00 42671.00
Avg Rate per metre 5806.00 6096.00
12.15 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
50 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 7023.00 7374.00
12th m 5% 7374.00 7743.00
13th m 5% 7743.00 8130.00
14th m 5% 8130.00 8537.00
15th m 5% 8537.00 8964.00
16th m 5% 8964.00 9412.00
17th m 5% 9412.00 9883.00
18th m 5% 9883.00 10377.00
19th m 5% 10377.00 10896.00
20th m 5% 10896.00 11441.00
Total Cost from 10m upto 20m 88339.00 92757.00
Avg Rate per metre 8834.00 9276.00
12.15 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 11713.00 14641.00 15373.00
32nd 7.5% 12591.00 15739.00 16526.00
33rd m 7.5% 13535.00 16919.00 17765.00
34th m 7.5% 14550.00 18188.00 19097.00
35th m 7.5% 15641.00 19551.00 20529.00
36th m 7.5% 16814.00 21018.00 22069.00
37th m 7.5% 18075.00 22594.00 23724.00
38th m 7.5% 19431.00 24289.00 25503.00
39th m 7.5% 20888.00 26110.00 27416.00
40th m 7.5% 22455.00 28069.00 29472.00
Total Cost from 30m upto 40m 165693.00 207118.00 217474.00
Avg Rate per metre 16569.00 20712.00 21747.00
12.15 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 24701.00 29641.00 31123.00
32nd 10% 27171.00 32605.00 34235.00
33rd m 10% 29888.00 35866.00 37659.00
34th m 10% 32877.00 39452.00 41425.00
35th m 10% 36165.00 43398.00 45568.00
36th m 10% 39782.00 47738.00 50125.00
37th m 10% 43760.00 52512.00 55138.00
38th m 10% 48136.00 57763.00 60651.00
39th m 10% 52950.00 63540.00 66717.00
40th m 10% 58245.00 69894.00 73389.00
Total Cost from 30m upto 40m 393675.00 472409.00 496030.00
Avg Rate per metre 39368.00 47241.00 49603.00
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
51 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Material
Gelatine 80 per cent Kg 10.00 0.00 0.00
Electric Detonators each 40.00 0.00 0.00
b) Labour
Mate day 1.17 155.00 181.35
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 22.00 155.00 3410.00
Mazdoor (Skilled) day 4.00 196.00 784.00
Diver day 1.00 196.00 196.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 0.00 0.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 246.01
Consumables in sinking @ 10 per cent of cost of (b). 492.01
d) Overhead charges @ 20% on (a+b+c) 1131.62
e) Contractor's profit @ 10 % on (a+b+c+d) 678.97
Rate per metre = (a+b+c+d+e) 7468.71
say 7469.00
12.15 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 7842.00 8234.00
5th m 5% 8234.00 8646.00
6th m 5% 8646.00 9078.00
7th m 5% 9078.00 9532.00
8th m 5% 9532.00 10009.00
9th m 5% 10009.00 10509.00
10th m 5% 10509.00 11034.00
Total Cost from 4m upto 10m 63850.00 67042.00
Avg Rate per metre 9121.00 9577.00
12.15 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 11034.00 11586.00
12th m 5% 11586.00 12165.00
13th m 5% 12165.00 12773.00
14th m 5% 12773.00 13412.00
15th m 5% 13412.00 14083.00
16th m 5% 14083.00 14787.00
17th m 5% 14787.00 15526.00
18th m 5% 15526.00 16302.00
19th m 5% 16302.00 17117.00
20th m 5% 17117.00 17973.00
Total Cost from 10m upto 20m 138785.00 145724.00
Avg Rate per metre 13879.00 14572.00
12.15 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
52 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 18401.00 23001.00 24151.00
32nd 7.5% 19781.00 24726.00 25962.00
33rd m 7.5% 21265.00 26581.00 27910.00
34th m 7.5% 22860.00 28575.00 30004.00
35th m 7.5% 24575.00 30719.00 32255.00
36th m 7.5% 26418.00 33023.00 34674.00
37th m 7.5% 28399.00 35499.00 37274.00
38th m 7.5% 30529.00 38161.00 40069.00
39th m 7.5% 32819.00 41024.00 43075.00
40th m 7.5% 35280.00 44100.00 46305.00
Total Cost from 30m upto 40m 260327.00 325409.00 341679.00
Avg Rate per metre 26033.00 32541.00 34168.00
12.15 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 38808.00 46570.00 48899.00
32nd 10% 42689.00 51227.00 53788.00
33rd m 10% 46958.00 56350.00 59168.00
34th m 10% 51654.00 61985.00 65084.00
35th m 10% 56819.00 68183.00 71592.00
36th m 10% 62501.00 75001.00 78751.00
37th m 10% 68751.00 82501.00 86626.00
38th m 10% 75626.00 90751.00 95289.00
39th m 10% 83189.00 99827.00 104818.00
40th m 10% 91508.00 109810.00 115301.00
Total Cost from 30m upto 40m 618503.00 742205.00 779316.00
Avg Rate per metre 61850.00 74221.00 77932.00
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 155.00 31.00
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper ( semi-skilled ) day 3.50 176.00 616.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 188.20
d) Contractor's profit @ 10 % on (a+b+c) 112.92
Rate per metre = (a+b+c+d) 1242.12
say 1242.00
12.16 A (ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
53 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Labour
Mate day 0.31 155.00 48.05
Sinker day 2.00 196.00 392.00
Sinking helper ( semi-skilled ) day 4.25 176.00 748.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 237.61
d) Contractor's profit @ 10 % on (a+b+c) 142.57
Rate per metre = (a+b+c+d) 1568.23
say 1568.00
12.16 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 1647.00
12th m 5% 1729.00
13th m 5% 1815.00
14th m 5% 1906.00
15th m 5% 2001.00
16th m 5% 2101.00
17th m 5% 2206.00
18th m 5% 2316.00
19th m 5% 2432.00
20th m 5% 2554.00
Total Cost from 10m upto 20m 20707.00
Avg Rate per metre 2071.00
12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 2746.00 3295.00
22nd m 7.5% 2952.00 3542.00
23rd m 7.5% 3173.00 3808.00
24th m 7.5% 3411.00 4093.00
25th m 7.5% 3667.00 4400.00
26th m 7.5% 3942.00 4730.00
27th m 7.5% 4238.00 5086.00
28th m 7.5% 4556.00 5467.00
29th m 7.5% 4898.00 5878.00
30th m 7.5% 5265.00 6318.00
Total Cost from 20m upto 30m 38848.00 46617.00
Avg Rate per metre 3885.00 4662.00
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 5792.00 6950.00
32nd 10% 6371.00 7645.00
33rd m 10% 7008.00 8410.00
34th m 10% 7709.00 9251.00
35th m 10% 8480.00 10176.00
36th m 10% 9328.00 11194.00
37th m 10% 10261.00 12313.00
38th m 10% 11287.00 13544.00
39th m 10% 12416.00 14899.00
40th m 10% 13658.00 16390.00
Total Cost from 30m upto 40m 92310.00 110772.00
Avg Rate per metre 9231.00 11077.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
54 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 155.00 38.75
Sinker ( skilled ) day 2.50 196.00 490.00
Sinking helper ( semi-skilled ) day 5.50 176.00 968.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 299.35
d) Contractor's profit @ 10 % on (a+b+c) 179.61
Rate per metre = (a+b+c+d) 1975.71
say 1976.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 155.00 62.00
Sinker day 3.00 196.00 588.00
Sinking helper ( semi-skilled ) day 5.50 176.00 968.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 0.00 0.00
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 323.60
d) Contractor's profit @ 10 % on (a+b+c) 194.16
Rate per metre = (a+b+c+d) 2135.76
say 2136.00
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 2243.00 2355.00
12th m 5% 2355.00 2473.00
13th m 5% 2473.00 2597.00
14th m 5% 2597.00 2727.00
15th m 5% 2727.00 2863.00
16th m 5% 2863.00 3006.00
17th m 5% 3006.00 3156.00
18th m 5% 3156.00 3314.00
19th m 5% 3314.00 3480.00
20th m 5% 3480.00 3654.00
Total Cost from 10m upto 20m 28214.00 29625.00
Avg Rate per metre 2821.00 2963.00
12.16 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 3741.00 4676.00 4910.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
55 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
32nd 7.5% 4022.00 5028.00 5279.00
33rd m 7.5% 4324.00 5405.00 5675.00
34th m 7.5% 4648.00 5810.00 6101.00
35th m 7.5% 4997.00 6246.00 6558.00
36th m 7.5% 5372.00 6715.00 7051.00
37th m 7.5% 5775.00 7219.00 7580.00
38th m 7.5% 6208.00 7760.00 8148.00
39th m 7.5% 6674.00 8343.00 8760.00
40th m 7.5% 7175.00 8969.00 9417.00
Total Cost from 30m upto 40m 52936.00 66171.00 69479.00
Avg Rate per metre 5294.00 6617.00 6948.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 7893.00 9472.00 9946.00
32nd 10% 8682.00 10418.00 10939.00
33rd m 10% 9550.00 11460.00 12033.00
34th m 10% 10505.00 12606.00 13236.30
35th m 10% 11556.00 13867.00 14560.35
36th m 10% 12712.00 15254.00 16016.70
37th m 10% 13983.00 16780.00 17619.00
38th m 10% 15381.00 18457.00 19379.85
39th m 10% 16919.00 20303.00 21318.15
40th m 10% 18611.00 22333.00 23449.65
Total Cost from 30m upto 40m 125792.00 150950.00 158498.00
Avg Rate per metre 12579.00 15095.00 15850.00
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
(i) Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 155.00 133.30
Sinker ( skilled ) day 4.00 196.00 784.00
Sinking helper ( semi-skilled ) day 16.00 176.00 2816.00
Diver day 1.40 196.00 274.40
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ 5 per cent of cost, if required 0.00
c) Overhead charges @ 20% on (a+b) 801.54
d) Contractor's profit @ 10 % on (a+b+c) 480.92
Rate per metre = (a+b+c+d) 5290.16
say 5290.00
12.16 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 5555.00 5833.00
5th m 5% 5833.00 6125.00
6th m 5% 6125.00 6431.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
56 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
7th m 5% 6431.00 6753.00
8th m 5% 6753.00 7091.00
9th m 5% 7091.00 7446.00
10th m 5% 7446.00 7818.00
Total Cost from 4m upto 10m 45234.00 47497.00
Avg Rate per metre 6462.00 6785.00
12.16 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 7818.00 8209.00
12th m 5% 8209.00 8619.00
13th m 5% 8619.00 9050.00
14th m 5% 9050.00 9503.00
15th m 5% 9503.00 9978.00
16th m 5% 9978.00 10477.00
17th m 5% 10477.00 11001.00
18th m 5% 11001.00 11551.00
19th m 5% 11551.00 12129.00
20th m 5% 12129.00 12735.00
Total Cost from 10m upto 20m 98335.00 103252.00
Avg Rate per metre 9834.00 10325.00
12.16 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 13039.00 16299.00 17114.00
32nd 7.5% 14017.00 17521.00 18397.00
33rd m 7.5% 15068.00 18835.00 19777.00
34th m 7.5% 16198.00 20248.00 21260.00
35th m 7.5% 17413.00 21766.00 22854.00
36th m 7.5% 18719.00 23399.00 24569.00
37th m 7.5% 20123.00 25154.00 26412.00
38th m 7.5% 21632.00 27040.00 28392.00
39th m 7.5% 23254.00 29068.00 30521.00
40th m 7.5% 24998.00 31248.00 32810.00
Total Cost from 30m upto 40m 184461.00 230578.00 242106.00
Avg Rate per metre 18446.00 23058.00 24211.00
12.16 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 27498.00 32998.00 34648.00
32nd 10% 30248.00 36298.00 38113.00
33rd m 10% 33273.00 39928.00 41924.00
34th m 10% 36600.00 43920.00 46116.00
35th m 10% 40260.00 48312.00 50728.00
36th m 10% 44286.00 53143.00 55800.00
37th m 10% 48715.00 58458.00 61381.00
38th m 10% 53587.00 64304.00 67519.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
57 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
39th m 10% 58946.00 70735.00 74272.00
40th m 10% 64841.00 77809.00 81699.00
Total Cost from 30m upto 40m 438254.00 525905.00 552200.00
Avg Rate per metre 43825.00 52591.00 55220.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 0.00 0.00
Electric Detonators each. 44.00 0.00 0.00
b) Labour
Mate day 1.27 155.00 196.85
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 24.00 155.00 3720.00
Mazdoor (Skilled) day 4.00 196.00 784.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 0.00 0.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 0.00
Consumables in sinking @ 10 per cent of cost of 504.96
(b+c).
d) Overhead charges @ 20% on (a+b+c) 1110.91
e) Contractor's profit @ 10 % on (a+b+c+d) 666.55
Rate per metre = (a+b+c+d+e) 7332.02
say 7332.00
12.16 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 7699.00 8084.00
5th m 5% 8084.00 8488.00
6th m 5% 8488.00 8912.00
7th m 5% 8912.00 9358.00
8th m 5% 9358.00 9826.00
9th m 5% 9826.00 10317.00
10th m 5% 10317.00 10833.00
Total Cost from 4m upto 10m 62684.00 65818.00
Avg Rate per metre 8955.00 9403.00
12.16 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 10833.00 11375.00
12th m 5% 11375.00 11944.00
13th m 5% 11944.00 12541.00
14th m 5% 12541.00 13168.00
15th m 5% 13168.00 13826.00
16th m 5% 13826.00 14517.00
17th m 5% 14517.00 15243.00
18th m 5% 15243.00 16005.00
19th m 5% 16005.00 16805.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
58 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
20th m 5% 16805.00 17645.00
Total Cost from 10m upto 20m 136257.00 143069.00
Avg Rate per metre 13626.00 14307.00
12.16 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 18065.00 22581.00 23710.00
32nd 7.5% 19420.00 24275.00 25489.00
33rd m 7.5% 20877.00 26096.00 27401.00
34th m 7.5% 22443.00 28054.00 29457.00
35th m 7.5% 24126.00 30158.00 31666.00
36th m 7.5% 25935.00 32419.00 34040.00
37th m 7.5% 27880.00 34850.00 36593.00
38th m 7.5% 29971.00 37464.00 39337.00
39th m 7.5% 32219.00 40274.00 42288.00
40th m 7.5% 34635.00 43294.00 45459.00
Total Cost from 30m upto 40m 255571.00 319465.00 335440.00
Avg Rate per metre 25557.00 31947.00 33544.00
12.16 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 38099.00 45719.00 48005.00
32nd 10% 41909.00 50291.00 52806.00
33rd m 10% 46100.00 55320.00 58086.00
34th m 10% 50710.00 60852.00 63895.00
35th m 10% 55781.00 66937.00 70284.00
36th m 10% 61359.00 73631.00 77313.00
37th m 10% 67495.00 80994.00 85044.00
38th m 10% 74245.00 89094.00 93549.00
39th m 10% 81670.00 98004.00 102904.00
40th m 10% 89837.00 107804.00 113194.00
Total Cost from 30m upto 40m 607205.00 728646.00 765080.00
Avg Rate per metre 60721.00 72865.00 76508.00
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 155.00 32.55
Sinker ( skilled ) day 1.50 196.00 294.00
Sinking helper (semi-skilled) day 3.30 176.00 580.80
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
59 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Consumables in sinking @10 per cent of (b) 0.00
d) Overhead charges @ 20% on (a+b+c) 181.47
e) Contractor's profit @ 10 % on (a+b+c+d) 108.88
Cost for 0.5m = a+b+c+d 1197.70
Rate per metre = (a+b+c+d)/0.50 2395.40
say 2395.00
12.17 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 155.00 49.60
Sinker day 2.00 196.00 392.00
Sinking helper (semi-skilled) day 4.50 176.00 792.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b+c) 246.72
d) Contractor's profit @ 10 % on (a+b+c+d) 148.03
Cost for 0.5m = a+b+c+d 1628.35
Rate per metre = (a+b+c+d)/0.50 3256.70
say 3257.00
12.17 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 3420.00
12th m 5% 3591.00
13th m 5% 3771.00
14th m 5% 3960.00
15th m 5% 4158.00
16th m 5% 4366.00
17th m 5% 4584.00
18th m 5% 4813.00
19th m 5% 5054.00
20th m 5% 5307.00
Total Cost from 10m upto 20m 43024.00
Avg Rate per metre 4302.00
12.17 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 5705.00 6846.00
22nd m 7.5% 6133.00 7360.00
23rd m 7.5% 6593.00 7912.00
24th m 7.5% 7087.00 8504.00
25th m 7.5% 7619.00 9143.00
26th m 7.5% 8190.00 9828.00
27th m 7.5% 8804.00 10565.00
28th m 7.5% 9464.00 11357.00
29th m 7.5% 10174.00 12209.00
30th m 7.5% 10937.00 13124.00
Total Cost from 20m upto 30m 80706.00 96848.00
Avg Rate per metre 8071.00 9685.00
12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 12031.00 14437.00
32nd 10% 13234.00 15881.00
33rd m 10% 14557.00 17468.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
60 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
34th m 10% 16013.00 19216.00
35th m 10% 17614.00 21137.00
36th m 10% 19375.00 23250.00
37th m 10% 21313.00 25576.00
38th m 10% 23444.00 28133.00
39th m 10% 25788.00 30946.00
40th m 10% 28367.00 34040.00
Total Cost from 30m upto 40m 191736.00 230084.00
Avg Rate per metre 19174.00 23008.00
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 155.00 40.30
Sinker ( skilled ) day 2.50 196.00 490.00
Sinking helper (semi-skilled) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 246.86
d) Contractor's profit @ 10 % on (a+b+c) 148.12
Cost for 0.5m = a+b+c+d 1629.28
Rate per metre = (a+b+c+d)/0.50 3258.55
say 3259.00
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 155.00 66.65
Sinker day 3.50 196.00 686.00
Sinking helper (semi-skilled) day 5.75 176.00 1012.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 0.00 0.00
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 352.93
d) Contractor's profit @ 10 % on (a+b+c) 211.76
Cost for 0.5m = a+b+c+d 2329.34
Rate per metre = (a+b+c+d)/0.50 4658.68
say 4659.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 4892.00 5137.00
12th m 5% 5137.00 5394.00
13th m 5% 5394.00 5664.00
14th m 5% 5664.00 5947.00
15th m 5% 5947.00 6244.00
16th m 5% 6244.00 6556.00
17th m 5% 6556.00 6884.00
18th m 5% 6884.00 7228.00
19th m 5% 7228.00 7589.00
20th m 5% 7589.00 7968.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
61 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Total Cost from 10m upto 20m 61535.00 64612.00
Avg Rate per metre 6154.00 6461.00
12.17 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 8158.00 10198.00 10708.00
32nd 7.5% 8770.00 10963.00 11511.00
33rd m 7.5% 9428.00 11785.00 12374.00
34th m 7.5% 10135.00 12669.00 13302.00
35th m 7.5% 10895.00 13619.00 14300.00
36th m 7.5% 11712.00 14640.00 15372.00
37th m 7.5% 12590.00 15738.00 16525.00
38th m 7.5% 13534.00 16918.00 17764.00
39th m 7.5% 14549.00 18186.00 19095.00
40th m 7.5% 15640.00 19550.00 20528.00
Total Cost from 30m upto 40m 115411.00 144266.00 151479.00
Avg Rate per metre 11541.00 14427.00 15148.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 17204.00 20645.00 21677.00
32nd 10% 18924.00 22709.00 23844.00
33rd m 10% 20816.00 24979.00 26228.00
34th m 10% 22898.00 27478.00 28852.00
35th m 10% 25188.00 30226.00 31737.00
36th m 10% 27707.00 33248.00 34910.00
37th m 10% 30478.00 36574.00 38403.00
38th m 10% 33526.00 40231.00 42243.00
39th m 10% 36879.00 44255.00 46468.00
40th m 10% 40567.00 48680.00 51114.00
Total Cost from 30m upto 40m 274187 329025 345476
Avg Rate per metre 27419.00 32903.00 34548.00
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
(i) Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 155.00 147.25
Sinker ( skilled ) day 4.25 196.00 833.00
Sinking helper (semi-skilled) day 18.00 176.00 3168.00
Diver day 1.50 196.00 294.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ 5 per cent of cost, if required 0.00
c) Overhead charges @ 20% on (a+b) 888.45
d) Contractor's profit @ 10 % on (a+b+c) 533.07
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
62 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Cost for 0.5m = a+b+c+d 5863.77
Rate per metre = (a+b+c+d)/0.50 11727.54
say 11728.00
12.17 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 12314.00 12930.00
5th m 5% 12930.00 13577.00
6th m 5% 13577.00 14256.00
7th m 5% 14256.00 14969.00
8th m 5% 14969.00 15717.00
9th m 5% 15717.00 16503.00
10th m 5% 16503.00 17328.00
Total Cost from 4m upto 10m 100266.00 105280.00
Avg Rate per metre 14324.00 15040.00
12.17 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 17328.00 18194.00
12th m 5% 18194.00 19104.00
13th m 5% 19104.00 20059.00
14th m 5% 20059.00 21062.00
15th m 5% 21062.00 22115.00
16th m 5% 22115.00 23221.00
17th m 5% 23221.00 24382.00
18th m 5% 24382.00 25601.00
19th m 5% 25601.00 26881.00
20th m 5% 26881.00 28225.00
Total Cost from 10m upto 20m 217947.00 228844.00
Avg Rate per metre 21795.00 22884.00
12.17 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 28897.00 36121.00 37927.00
32nd 7.5% 31064.00 38830.00 40772.00
33rd m 7.5% 33394.00 41743.00 43830.00
34th m 7.5% 35899.00 44874.00 47118.00
35th m 7.5% 38591.00 48239.00 50651.00
36th m 7.5% 41485.00 51856.00 54449.00
37th m 7.5% 44596.00 55745.00 58532.00
38th m 7.5% 47941.00 59926.00 62922.00
39th m 7.5% 51537.00 64421.00 67642.00
40th m 7.5% 55402.00 69253.00 72716.00
Total Cost from 30m upto 40m 408806.00 511008.00 536559.00
Avg Rate per metre 40881.00 51101.00 53656.00
12.17 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
63 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 60942.00 73130.00 76787.00
32nd 10% 67036.00 80443.00 84465.00
33rd m 10% 73740.00 88488.00 92912.00
34th m 10% 81114.00 97337.00 102204.00
35th m 10% 89225.00 107070.00 112424.00
36th m 10% 98148.00 117778.00 123667.00
37th m 10% 107963.00 129556.00 136034.00
38th m 10% 118759.00 142511.00 149637.00
39th m 10% 130635.00 156762.00 164600.00
40th m 10% 143699.00 172439.00 181061.00
Total Cost from 30m upto 40m 971261.00 1165514.00 1223791.00
Avg Rate per metre 97126.00 116551.00 122379.00
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
(i) Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 0.00 0.00
Electric Detonators each. 48.00 0.00 0.00
b) Labour
Mate day 1.35 155.00 209.25
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 26.00 155.00 4030.00
Mazdoor (Skilled) day 4.00 196.00 784.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 0.00 0.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 0.00
Consumables in sinking @ 10 per cent of cost of 537.20
(b+c).
d) Overhead charges @ 20% on (a+b+c) 1181.84
e) Contractor's profit @ 10 % on (a+b+c+d) 709.10
Cost for 0.5m = a+b+c+d 7800.14
Rate per metre = (a+b+c+d)/0.50 15600.29
say 15600.00
12.17 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 16380.00 17199.00
5th m 5% 17199.00 18059.00
6th m 5% 18059.00 18962.00
7th m 5% 18962.00 19910.00
8th m 5% 19910.00 20906.00
9th m 5% 20906.00 21951.00
10th m 5% 21951.00 23049.00
Total Cost from 4m upto 10m 133367.00 140036.00
Avg Rate per metre 19052.00 20005.00
12.17 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
64 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 23049.00 24201.00
12th m 5% 24201.00 25411.00
13th m 5% 25411.00 26682.00
14th m 5% 26682.00 28016.00
15th m 5% 28016.00 29417.00
16th m 5% 29417.00 30888.00
17th m 5% 30888.00 32432.00
18th m 5% 32432.00 34054.00
19th m 5% 34054.00 35757.00
20th m 5% 35757.00 37545.00
Total Cost from 10m upto 20m 289907.00 304403.00
Avg Rate per metre 28991.00 30440.00
12.17 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 38439.00 48049.00 50451.00
32nd 7.5% 41322.00 51653.00 54236.00
33rd m 7.5% 44421.00 55526.00 58302.00
34th m 7.5% 47753.00 59691.00 62676.00
35th m 7.5% 51334.00 64168.00 67376.00
36th m 7.5% 55184.00 68980.00 72429.00
37th m 7.5% 59323.00 74154.00 77862.00
38th m 7.5% 63772.00 79715.00 83701.00
39th m 7.5% 68555.00 85694.00 89979.00
40th m 7.5% 73697.00 92121.00 96727.00
Total Cost from 30m upto 40m 543800.00 679751.00 713739.00
Avg Rate per metre 54380.00 67975.00 71374.00
12.17 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 81067.00 97280.00 102144.00
32nd 10% 89174.00 107009.00 112359.00
33rd m 10% 98091.00 117709.00 123594.00
34th m 10% 107900.00 129480.00 135954.00
35th m 10% 118690.00 142428.00 149549.00
36th m 10% 130559.00 156671.00 164505.00
37th m 10% 143615.00 172338.00 180955.00
38th m 10% 157977.00 189572.00 199051.00
39th m 10% 173775.00 208530.00 218957.00
40th m 10% 191153.00 229384.00 240853.00
Total Cost from 30m upto 40m 1292001.00 1550401.00 1627921.00
Avg Rate per metre 129200.00 155040.00 162792.00
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
65 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 155.00 34.10
Sinker ( skilled ) day 1.75 196.00 343.00
Sinking helper (semi-skilled) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 216.22
d) Contractor's profit @ 10 % on (a+b+c) 129.73
Cost for 0.25m = a+b+c+d 1427.05
Rate per metre = (a+b+c+d)/0.25 5708.21
say 5708.00
12.18 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 155.00 57.35
Sinker day 2.50 196.00 490.00
Sinking helper (semi-skilled) day 4.75 176.00 836.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 276.67
d) Contractor's profit @ 10 % on (a+b+c) 166.00
Cost for 0.25m = a+b+c+d 1826.02
Rate per metre = (a+b+c+d)/0.25 7304.09
say 7304.00
12.18 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 7669.00
12th m 5% 8052.00
13th m 5% 8454.60
14th m 5% 8877.33
15th m 5% 9321.20
16th m 5% 9787.26
17th m 5% 10276.62
18th m 5% 10790.45
19th m 5% 11329.97
20th m 5% 11896.47
Total Cost from 10m upto 20m 96454.90
Avg Rate per metre 9645.00
12.18 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 12789.00 15347.00
22nd m 7.5% 13748.00 16498.00
23rd m 7.5% 14779.00 17735.00
24th m 7.5% 15887.00 19064.00
25th m 7.5% 17079.00 20495.00
26th m 7.5% 18360.00 22032.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
66 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
27th m 7.5% 19737.00 23684.00
28th m 7.5% 21217.00 25460.00
29th m 7.5% 22808.00 27370.00
30th m 7.5% 24519.00 29423.00
Total Cost from 20m upto 30m 180923.00 217108.00
Avg Rate per metre 18092.00 21711.00
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 26971.00 32365.00
32nd 10% 29668.00 35602.00
33rd m 10% 32635.00 39162.00
34th m 10% 35899.00 43079.00
35th m 10% 39489.00 47387.00
36th m 10% 43438.00 52126.00
37th m 10% 47782.00 57338.00
38th m 10% 52560.00 63072.00
39th m 10% 57816.00 69379.00
40th m 10% 63598.00 76318.00
Total Cost from 30m upto 40m 429856 515828
Avg Rate per metre 42986.00 51583.00
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 155.00 46.50
Sinker ( skilled ) day 3.00 196.00 588.00
Sinking helper (semi-skilled) day 4.50 176.00 792.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 285.30
d) Contractor's profit @ 10 % on (a+b+c) 171.18
Cost for 0.25m = a+b+c+d 1882.98
Rate per metre = (a+b+c+d)/0.25 7531.92
say 7532.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 155.00 74.40
Sinker day 3.75 196.00 735.00
Sinking helper (semi-skilled) day 6.00 176.00 1056.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 373.08
d) Contractor's profit @ 10 % on (a+b+c) 223.85
Cost for 0.25m = a+b+c+d 2462.33
Rate per metre = (a+b+c+d)/0.25 9849.31
say 9849.00
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
67 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 10342.00 10859.00
12th m 5% 10859.00 11402.00
13th m 5% 11402.00 11972.00
14th m 5% 11972.00 12571.00
15th m 5% 12571.00 13200.00
16th m 5% 13200.00 13860.00
17th m 5% 13860.00 14553.00
18th m 5% 14553.00 15281.00
19th m 5% 15281.00 16045.00
20th m 5% 16045.00 16847.00
Total Cost from 10m upto 20m 130085.00 136590.00
Avg Rate per metre 13009.00 13659.00
12.18 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 17248.00 21560.00 22638.00
32nd 7.5% 18542.00 23178.00 24337.00
33rd m 7.5% 19933.00 24916.00 26162.00
34th m 7.5% 21428.00 26785.00 28124.00
35th m 7.5% 23035.00 28794.00 30234.00
36th m 7.5% 24763.00 30954.00 32502.00
37th m 7.5% 26620.00 33275.00 34939.00
38th m 7.5% 28617.00 35771.00 37560.00
39th m 7.5% 30763.00 38454.00 40377.00
40th m 7.5% 33070.00 41338.00 43405.00
Total Cost from 30m upto 40m 244019 305025 320278
Avg Rate per metre 24402.00 30503.00 32028.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 36377.00 43652.00 45835.00
32nd 10% 40015.00 48018.00 50419.00
33rd m 10% 44017.00 52820.00 55461.00
34th m 10% 48419.00 58103.00 61008.00
35th m 10% 53261.00 63913.00 67109.00
36th m 10% 58587.00 70304.00 73819.00
37th m 10% 64446.00 77335.00 81202.00
38th m 10% 70891.00 85069.00 89322.00
39th m 10% 77980.00 93576.00 98255.00
40th m 10% 85778.00 102934.00 108081.00
Total Cost from 30m upto 40m 579771 695724 730511
Avg Rate per metre 57977.00 69572.00 73051.00
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
68 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Labour
Mate day 1.06 155.00 164.30
Sinker ( skilled ) day 4.50 196.00 882.00
Sinking helper (semi-skilled) day 20.00 176.00 3520.00
Diver day 1.75 196.00 343.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ 5 per cent, if required 0.00
c) Overhead charges @ 20% on (a+b) 981.86
d) Contractor's profit @ 10 % on (a+b+c) 589.12
Cost for 0.25m = a+b+c+d 6480.28
Rate per metre = (a+b+c+d)/0.25 25921.10
say 25921.00
12.18 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 27217.00 28578.00
5th m 5% 28578.00 30007.00
6th m 5% 30007.00 31507.00
7th m 5% 31507.00 33082.00
8th m 5% 33082.00 34736.00
9th m 5% 34736.00 36473.00
10th m 5% 36473.00 38297.00
Total Cost from 4m upto 10m 221600.00 232680.00
Avg Rate per metre 31657.00 33240.00
12.18 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 38297.00 40212.00
12th m 5% 40212.00 42223.00
13th m 5% 42223.00 44334.00
14th m 5% 44334.00 46551.00
15th m 5% 46551.00 48879.00
16th m 5% 48879.00 51323.00
17th m 5% 51323.00 53889.00
18th m 5% 53889.00 56583.00
19th m 5% 56583.00 59412.00
20th m 5% 59412.00 62383.00
Total Cost from 10m upto 20m 481703.00 505789.00
Avg Rate per metre 48170.00 50579.00
12.18 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 63868.00 79835.00 83827.00
32nd 7.5% 68658.00 85823.00 90114.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
69 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
33rd m 7.5% 73807.00 92259.00 96872.00
34th m 7.5% 79343.00 99179.00 104138.00
35th m 7.5% 85294.00 106618.00 111949.00
36th m 7.5% 91691.00 114614.00 120345.00
37th m 7.5% 98568.00 123210.00 129371.00
38th m 7.5% 105961.00 132451.00 139074.00
39th m 7.5% 113908.00 142385.00 149504.00
40th m 7.5% 122451.00 153064.00 160717.00
Total Cost from 30m upto 40m 903549.00 1129438.00 1185911.00
Avg Rate per metre 90355.00 112944.00 118591.00
12.18 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 134696.00 161635.00 169717.00
32nd 10% 148166.00 177799.00 186689.00
33rd m 10% 162983.00 195580.00 205359.00
34th m 10% 179281.00 215137.00 225894.00
35th m 10% 197209.00 236651.00 248484.00
36th m 10% 216930.00 260316.00 273332.00
37th m 10% 238623.00 286348.00 300665.00
38th m 10% 262485.00 314982.00 330731.00
39th m 10% 288734.00 346481.00 363805.00
40th m 10% 317607.00 381128.00 400184.00
Total Cost from 30m upto 40m 2146714.00 2576057.00 2704860.00
Avg Rate per metre 214671.00 257606.00 270486.00
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 0.00 0.00
Electric detonator each. 56.00 0.00 0.00
b) Labour
Mate day 1.44 155.00 223.20
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 28.00 155.00 4340.00
Mazdoor (Skilled) day 4.50 196.00 882.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 0.00 0.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 0.00
Consumables in sinking @ 10 per cent of (c). 0.00
d) Overhead charges @ 20% on (a+b+c) 1158.79
e) Contractor's profit @ 10 % on (a+b+c+d) 695.27
Cost for 0.25m = a+b+c+d+e 7648.01
Rate per metre = (a+b+c+d+e)/0.25 30592.06
say 30592.00
12.18 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
70 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 32122.00 33728.00
5th m 5% 33728.00 35414.00
6th m 5% 35414.00 37185.00
7th m 5% 37185.00 39044.00
8th m 5% 39044.00 40996.00
9th m 5% 40996.00 43046.00
10th m 5% 43046.00 45198.00
Total Cost from 4m upto 10m 261535.00 274611.00
Avg Rate per metre 37362.00 39230.00
12.18 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 45198.00 47458.00
12th m 5% 47458.00 49831.00
13th m 5% 49831.00 52323.00
14th m 5% 52323.00 54939.00
15th m 5% 54939.00 57686.00
16th m 5% 57686.00 60570.00
17th m 5% 60570.00 63599.00
18th m 5% 63599.00 66779.00
19th m 5% 66779.00 70118.00
20th m 5% 70118.00 73624.00
Total Cost from 10m upto 20m 568501.00 596927.00
Avg Rate per metre 56850.00 59693.00
12.18 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 75377.00 94221.00 98932.00
32nd 7.5% 81030.00 101288.00 106352.00
33rd m 7.5% 87107.00 108884.00 114328.00
34th m 7.5% 93640.00 117050.00 122903.00
35th m 7.5% 100663.00 125829.00 132120.00
36th m 7.5% 108213.00 135266.00 142029.00
37th m 7.5% 116329.00 145411.00 152682.00
38th m 7.5% 125054.00 156318.00 164134.00
39th m 7.5% 134433.00 168041.00 176443.00
40th m 7.5% 144515.00 180644.00 189676.00
Total Cost from 30m upto 40m 1066361.00 1332952.00 1399599.00
Avg Rate per metre 106636.00 133295.00 139960.00
12.18 D (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 158967.00 190760.00 200298.00
32nd 10% 174864.00 209837.00 220329.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
71 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
33rd m 10% 192350.00 230820.00 242361.00
34th m 10% 211585.00 253902.00 266597.00
35th m 10% 232744.00 279293.00 293258.00
36th m 10% 256018.00 307222.00 322583.00
37th m 10% 281620.00 337944.00 354841.00
38th m 10% 309782.00 371738.00 390325.00
39th m 10% 340760.00 408912.00 429358.00
40th m 10% 374836.00 449803.00 472293.00
Total Cost from 30m upto 40m 2533526.00 3040231.00 3192243.00
Avg Rate per metre 253353.00 304023.00 319224.00
12.19 1200 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 155.00 31.00
Sinker ( skilled ) day 1.25 196.00 245.00
Sinking helper (semi-skilled) day 3.75 176.00 660.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 187.20
d) Contractor's profit @ 10 % on (a+b+c) 112.32
Rate per metre = (a+b+c+d) 1235.52
say 1236.00
12.19 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 155.00 46.50
Sinker day 1.50 196.00 294.00
Sinking helper (semi-skilled) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 208.90
d) Contractor's profit @ 10 % on (a+b+c) 125.34
Rate per metre = (a+b+c+d) 1378.74
say 1379.00
12.19 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 1448.00
12th m 5% 1520.00
13th m 5% 1596.00
14th m 5% 1676.00
15th m 5% 1760.00
16th m 5% 1848.00
17th m 5% 1940.00
18th m 5% 2037.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
72 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
19th m 5% 2139.00
20th m 5% 2246.00
Total Cost from 10m upto 20m 18210.00
Avg Rate per metre 1821.00
12.19 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 2414.00 2897.00
22nd m 7.5% 2595.00 3114.00
23rd m 7.5% 2790.00 3348.00
24th m 7.5% 2999.00 3599.00
25th m 7.5% 3224.00 3869.00
26th m 7.5% 3466.00 4159.00
27th m 7.5% 3726.00 4471.00
28th m 7.5% 4005.00 4806.00
29th m 7.5% 4305.00 5166.00
30th m 7.5% 4628.00 5554.00
Total Cost from 20m upto 30m 34152.00 40983.00
Avg Rate per metre 3415.00 4098.00
12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 5091.00 6109.00
32nd 10% 5600.00 6720.00
33rd m 10% 6160.00 7392.00
34th m 10% 6776.00 8131.00
35th m 10% 7454.00 8945.00
36th m 10% 8199.00 9839.00
37th m 10% 9019.00 10823.00
38th m 10% 9921.00 11905.00
39th m 10% 10913.00 13096.00
40th m 10% 12004.00 14405.00
Total Cost from 30m upto 40m 81137.00 97365.00
Avg Rate per metre 8114.00 9737.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 155.00 40.30
Sinker ( skilled ) day 2.50 196.00 490.00
Sinking helper (semi-skilled) day 4.00 176.00 704.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 0.00 0.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 246.86
d) Contractor's profit @ 10 % on (a+b+c) 148.12
Rate per metre = (a+b+c+d) 1629.28
say 1629.00
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 155.00 69.75
Sinker day 3.25 196.00 637.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
73 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Sinking helper (semi-skilled) day 6.00 176.00 1056.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 0.00 0.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 0.00
c) Overhead charges @ 20% on (a+b) 352.55
d) Contractor's profit @ 10 % on (a+b+c) 211.53
Rate per metre = (a+b+c+d) 2326.83
say 2327.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 2443.00 2565.00
12th m 5% 2565.00 2693.00
13th m 5% 2693.00 2828.00
14th m 5% 2828.00 2969.00
15th m 5% 2969.00 3117.00
16th m 5% 3117.00 3273.00
17th m 5% 3273.00 3437.00
18th m 5% 3437.00 3609.00
19th m 5% 3609.00 3789.00
20th m 5% 3789.00 3978.00
Total Cost from 10m upto 20m 30723.00 32258.00
Avg Rate per metre 3072.00 3226.00
12.19 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 4073.00 5091.00 5346.00
32nd 7.5% 4378.00 5473.00 5747.00
33rd m 7.5% 4706.00 5883.00 6177.00
34th m 7.5% 5059.00 6324.00 6640.00
35th m 7.5% 5438.00 6798.00 7138.00
36th m 7.5% 5846.00 7308.00 7673.00
37th m 7.5% 6284.00 7855.00 8248.00
38th m 7.5% 6755.00 8444.00 8866.00
39th m 7.5% 7262.00 9078.00 9532.00
40th m 7.5% 7807.00 9759.00 10247.00
Total Cost from 30m upto 40m 57608.00 72013.00 75614.00
Avg Rate per metre 5761.00 7201.00 7561.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 8588.00 10306.00 10821.00
32nd 10% 9447.00 11336.00 11903.00
33rd m 10% 10392.00 12470.00 13094.00
34th m 10% 11431.00 13717.00 14403.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
74 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
35th m 10% 12574.00 15089.00 15843.00
36th m 10% 13831.00 16597.00 17427.00
37th m 10% 15214.00 18257.00 19170.00
38th m 10% 16735.00 20082.00 21086.00
39th m 10% 18409.00 22091.00 23196.00
40th m 10% 20250.00 24300.00 25515.00
Total Cost from 30m upto 40m 136871.00 164245.00 172458.00
Avg Rate per metre 13687.00 16425.00 17246.00
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
(i) Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 155.00 133.30
Sinker ( skilled ) day 4.50 196.00 882.00
Sinking helper (semi-skilled) day 15.00 176.00 2640.00
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 0.00 0.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 0.00 0.00
Consumables in sinking @ 10 per cent of (b) 0.00
Add for dewatering @ 5 per cent, if required 0.00
c) Overhead charges @ 20% on (a+b) 731.06
d) Contractor's profit @ 10 % on (a+b+c) 438.64
Rate per metre = (a+b+c+d) 4825.00
say 4825.00
12.19 C (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 5066.00 5319.00
5th m 5% 5319.00 5585.00
6th m 5% 5585.00 5864.00
7th m 5% 5864.00 6157.00
8th m 5% 6157.00 6465.00
9th m 5% 6465.00 6788.00
10th m 5% 6788.00 7127.00
Total Cost from 4m upto 10m 41244.00 43305.00
Avg Rate per metre 5892.00 6186.00
12.19 C (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 7127.00 7483.00
12th m 5% 7483.00 7857.00
13th m 5% 7857.00 8250.00
14th m 5% 8250.00 8663.00
15th m 5% 8663.00 9096.00
16th m 5% 9096.00 9551.00
17th m 5% 9551.00 10029.00
18th m 5% 10029.00 10530.00
19th m 5% 10530.00 11057.00
20th m 5% 11057.00 11610.00
Total Cost from 10m upto 20m 89643.00 94126.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
75 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Avg Rate per metre 8964.00 9413.00
12.19 C (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 11886.00 14858.00 15601.00
32nd 7.5% 12777.00 15971.00 16770.00
33rd m 7.5% 13735.00 17169.00 18027.00
34th m 7.5% 14765.00 18456.00 19379.00
35th m 7.5% 15872.00 19840.00 20832.00
36th m 7.5% 17062.00 21328.00 22394.00
37th m 7.5% 18342.00 22928.00 24074.00
38th m 7.5% 19718.00 24648.00 25880.00
39th m 7.5% 21197.00 26496.00 27821.00
40th m 7.5% 22787.00 28484.00 29908.00
Total Cost from 30m upto 40m 168141.00 210178.00 220686.00
Avg Rate per metre 16814.00 21018.00 22069.00
12.19 C (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 25066.00 30079.00 31583.00
32nd 10% 27573.00 33088.00 34742.00
33rd m 10% 30330.00 36396.00 38216.00
34th m 10% 33363.00 40036.00 42038.00
35th m 10% 36699.00 44039.00 46241.00
36th m 10% 40369.00 48443.00 50865.00
37th m 10% 44406.00 53287.00 55951.00
38th m 10% 48847.00 58616.00 61547.00
39th m 10% 53732.00 64478.00 67702.00
40th m 10% 59105.00 70926.00 74472.00
Total Cost from 30m upto 40m 399490.00 479388.00 503357.00
Avg Rate per metre 39949.00 47939.00 50336.00
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 0.00 0.00
Electric detonators each. 40.00 0.00 0.00
b) Labour
Mate day 1.34 155.00 207.70
Driller day 2.00 155.00 310.00
Blaster day 0.25 155.00 38.75
Mazdoor day 25.00 155.00 3875.00
Mazdoor (Skilled) day 4.25 196.00 833.00
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 0.00 0.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 0.00 0.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 263.22
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
76 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Consumables in sinking @ 10 per cent of (b). 26.32
d) Overhead charges @ 20% on (a+b+c) 1110.80
e) Contractor's profit @ 10 % on (a+b+c+d) 666.48
Rate per metre = (a+b+c+d+e) 7331.27
say 7331.00
12.19 D (ii) Beyond 3 m upto 10 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
4th m 5% 7698.00 8083.00
5th m 5% 8083.00 8487.00
6th m 5% 8487.00 8911.00
7th m 5% 8911.00 9357.00
8th m 5% 9357.00 9825.00
9th m 5% 9825.00 10316.00
10th m 5% 10316.00 10832.00
Total Cost from 4m upto 10m 62677.00 65811.00
Avg Rate per metre 8954.00 9402.00
12.19 D (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 10832.00 11374.00
12th m 5% 11374.00 11943.00
13th m 5% 11943.00 12540.00
14th m 5% 12540.00 13167.00
15th m 5% 13167.00 13825.00
16th m 5% 13825.00 14516.00
17th m 5% 14516.00 15242.00
18th m 5% 15242.00 16004.00
19th m 5% 16004.00 16804.00
20th m 5% 16804.00 17644.00
Total Cost from 10m upto 20m 136247.00 143059.00
Avg Rate per metre 13625.00 14306.00
12.19 D (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 18064.00 22580.00 23709.00
32nd 7.5% 19419.00 24274.00 25488.00
33rd m 7.5% 20875.00 26094.00 27399.00
34th m 7.5% 22441.00 28051.00 29454.00
35th m 7.5% 24124.00 30155.00 31663.00
36th m 7.5% 25933.00 32416.00 34037.00
37th m 7.5% 27878.00 34848.00 36590.00
38th m 7.5% 29969.00 37461.00 39334.00
39th m 7.5% 32217.00 40271.00 42285.00
40th m 7.5% 34633.00 43291.00 45456.00
Total Cost from 30m upto 40m 255553.00 319441.00 335415.00
Avg Rate per metre 25555.00 31944.00 33542.00
12.19 D (v) Beyond 30m upto 40 m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
77 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 38096.00 45715.00 48001.00
32nd 10% 41906.00 50287.00 52801.00
33rd m 10% 46097.00 55316.00 58082.00
34th m 10% 50707.00 60848.00 63890.00
35th m 10% 55778.00 66934.00 70281.00
36th m 10% 61356.00 73627.00 77308.00
37th m 10% 67492.00 80990.00 85040.00
38th m 10% 74241.00 89089.00 93543.00
39th m 10% 81665.00 97998.00 102898.00
40th m 10% 89832.00 107798.00 113188.00
Total Cost from 30m upto 40m 607170.00 728602.00 765032.00
Avg Rate per metre 60717.00 72860.00 76503.00
12.20 1200 Pneumatic sinking of wells with equipment of approved
design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than
6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with
railing, arrangement for compression and
decompression, electric lighting of 50 V maximum,
proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all
as per clause1207.6 of MoRTH Specifications.
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 5744.00 45952.00
equipment (Dimensions as per ground conditions).
Rate may be adopted vide Item 12.8 (h)
HYSD bar reinforcement in corbel tonne 0.48 46300.00 22224.00
Blasting material
Gelatine 80 per cent Kg 1.50 0.00 0.00
Electric detonators each 6.00 0.00 0.00
b) Labour
Medical Officer day 0.50 0.00 0.00
Para medical personnel day 1.00 0.00 0.00
Mate day 1.86 155.00 288.30
Driller day 1.00 155.00 155.00
Blaster day 0.50 155.00 77.50
Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 155.00 4650.00
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 196.00 1960.00
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Erection at site and commissioning L.S 150000.00
Usage of plant and equipment for pneumatic method of hour 6.00 3512.00 21072.00
well sinking
Air compressor 250 cfm, 2 nos. hour 2x6 269.00 3228.00
Hire and running charges of crane of 15 tonne capacity hour 6.00 0.00 0.00
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 46300.00 48615.00
b) Labour
Mate day 1.24 155.00 192.20
Fitter day 6.00 196.00 1176.00
Blacksmith day 5.00 176.00 880.00
Welder day 5.00 196.00 980.00
Mazdoor day 10.00 155.00 1550.00
Electrodes, cutting gas and other consumables @ 5 2430.75
per cent on cost a (a) above.
c) Overhead charges @ 20% on (a+b) 11164.79
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
79 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
d) Contractor's profit @ 10 % on (a+b+c) 6698.87
Rate for per MT (a+b+c+d) 73687.61
say 73688.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 5753.00 38084.86
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
e) Contractor's profit @ 10 % on (b+c+d) 3538.80
Cost for 10 m = a+b+c+d+d+e 84087.89
Rate per metre (a+b+c+d+e)/10 8408.79
say 8409.00
12.25 10.21 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5753.00 58508.01
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Cost for 40 m = a+b+c+d+e 102236.33
Rate per metre (a+b+c+d+e)/40 2555.91
say 2556.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 5753.00 135483.15
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
i) C.I. shoes for the pile Kg 160.00 0.00 0.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 0.00 0.00
iii) Steel helmet on top of casing head during driving Kg 50.00 0.00 0.00
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 0.00 0.00
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 0.00 0.00
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 155.00 27.90
Mazdoor day 4.50 155.00 697.50
e) Overhead charges @ 20% on (b+c+d) 145.08
f) Contractor's profit @ 10 % on (b+c+d+e) 87.05
Cost for 20 m = a+b+c+d+e 131032.86
Rate per metre (a+b+c+d+e)/20 6551.64
say 6552.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 5744.00 67664.32
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 5744.00 126827.52
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
12.32 1100&1 Driven precast vertical M35 grade R.C.C. Piles
700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 5744.00 31017.60
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 240.00 0.00 0.00
b) M. S shoes kg 105.00 0.00 0.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.12 155.00 18.60
Mazdoor day 3.00 155.00 465.00
Add 1 per cent of (a+b+c) for carriage of piles from 315.01
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 20% on (b+c+d) 159.72
f) Contractor's profit @ 10 % on (b+c+d+e) 95.83
Cost for 60 m = a+b+c+d+e+f 32071.77
Rate per metre (a+b+c+d+e+f)/60 534.53
say 535.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 5744.00 71800.00
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 160.00 0.00 0.00
b) M. S shoes kg 70.00 0.00 0.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.16 155.00 24.80
Mazdoor day 4.00 155.00 620.00
Add 1 per cent of (a+b+c) for carriage of piles from 724.45
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 20% on (b+c+d) 273.85
f) Contractor's profit @ 10 % on (b+c+d+e) 164.31
Cost for 50 m = a+b+c+d+e+f 73607.41
Rate per metre (a+b+c+d+e+f)/50 1472.15
say 1472.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
85 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 5744.00 129240.00
plug vide item no. 13.11( F ) (IV)
b ) Material
Pile shoes
a) C I shoes kg 160.00 0.00 0.00
b) M. S shoes kg 70.00 0.00 0.00
c) Steel helmet and cushion block on top of pile head Kg 30.00 0.00 0.00
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
d ) Labour
Mate/Supervisor day 0.18 155.00 27.90
Mazdoor day 4.50 155.00 697.50
Add 1 per cent of (a+b+c) for carriage of piles from 1299.65
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 20% on (b+c+d) 405.01
f) Contractor's profit @ 10 % on (b+c+d+e) 243.01
Cost for 40 m = a+b+c+d+e+f 131913.07
Rate per metre (a+b+c+d+e+f)/40 3297.83
say 3298.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing
1900 and & Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 46300.00 279652.00
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and other accessories.
c) Labour
Mate/Supervisor day 0.12 155.00 18.60
Mazdoor day 3.00 155.00 465.00
Add 0.5 per cent of (a+b+c) for providing steel 1400.68
helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.
d) Overhead charges @ 20% on (a+b+c) 56307.26
e) Contractor's profit @ 10 % on (a+b+c+d) 33784.35
Cost for 70 m = a+b+c+d+e 371627.89
Rate per metre (a+b+c+d+e)/70 5308.97
say 5309.00
12.36 1100 Driven Vertical Steel Piles complete as per Drawing
&1900 and & Technical Specification
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
86 15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 tonnes 5.83 46300.00 269929.00
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 0.00 0.00
Vibrating Pile driving hammer complete with power unit hour 6.00 0.00 0.00
and accessories.
c) Labour
Mate/Supervisor day 0.14 155.00 21.70
Mazdoor day 3.50 155.00 542.50
Add 0.5 per cent of (a+b+c) for providing steel 1352.47
helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Material
Cement tonne 5.12 4400.00 22528.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.16 155.00 24.80
Mason day 0.38 155.00 58.90
Mazdoor for concreting day 2.50 155.00 387.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 155.00 155.00
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1880.00 1410.00
Generator 100 KVA hour 0.75 588.00 441.00
Loader (capacity 1 cum) hour 0.75 679.00 509.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 783.00 1566.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.00 3150.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.16 155.00 24.80
Mason day 0.38 155.00 58.90
Mazdoor for concreting day 2.50 155.00 387.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 155.00 155.00
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1880.00 1410.00
Generator 125 KVA hour 0.75 588.00 441.00
Loader (capacity 1 cum) hour 0.75 679.00 509.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 783.00 1566.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.00 3150.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Mazdoor for concreting day 2.50 155.00 387.50
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 155.00 155.00
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1880.00 1410.00
Generator 100 KVA hour 0.75 588.00 441.00
Loader (capacity 1 cum) hour 0.75 679.00 509.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 783.00 1566.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.00 3150.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
Generator 125 KVA hour 0.75 588.00 441.00
Loader (capacity 1 cum) hour 0.75 679.00 509.25
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 783.00 1566.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 7.00 3150.00
Sr No BOQ Ref. to
Item No. MoRTH Description Unit Quantity Rate Rs Cost RS
Spec.
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 24921.35 26167.42
Binding wire Kg 6.00 78.13 468.78
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.43 155.00 66.65
Blacksmith day 2.25 196.00 441.00
Mazdoor day 6.50 155.00 1007.50
c) Overhead charges @ 20% on (a+b) 5630.27
d) Contractor's profit @ 10 % on (a+b+c) 3378.16
Rate for per MT (a+b+c+d) 37159.78
say 37160.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-13
SUB-STRUCTURE
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
13.1 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 9.64 4820.00
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 3177.00 762.48
analysis)
b) Labour
Mate day 0.06 155.00 9.30
Mason day 0.80 196.00 156.80
Mazdoor day 0.80 155.00 124.00
Add for scaffolding @ 5 per cent of cost of material 293.63
and labour
c) Overhead charges @ 20% on (a+b) 1233.24
d) Contractor's profit @ 10 % on (a+b+c) 739.95
Rate per cum (a+b+c+d) 8139.40
say 8139.00
13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.03 3177.00 95.31
analysis)
b) Labour
Mate day 0.04 155.00 6.20
Mason day 0.50 196.00 98.00
Mazdoor day 0.50 155.00 77.50
c) Overhead charges @ 20% on (a+b) 55.40
d) Contractor's profit @ 10 % on (a+b+c) 33.24
Rate per 10 sqm (a+b+c+d) 365.65
say 366.00
Note Scaffolding is already included in item 13.1
13.3 4.24 1300 & Plastering with cement mortar (1:3 ) on brick work in
2200 sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.144 3177.00 457.49
analysis)
b) Labour
Mate day 0.04 155.00 6.20
Mason day 0.50 196.00 98.00
Mazdoor day 0.50 155.00 77.50
c) Overhead charges @ 20% on (a+b) 127.84
d) Contractor's profit @ 10 % on (a+b+c) 76.70
Rate per 10 sqm (a+b+c+d) 843.73
say 844.00
Note 1.Scaffolding is already included in item no. 13.1
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and Technical
Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 808.26 808.26
Through and bond stone No 7.00 53.88 377.16
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.33 3177.00 1048.41
analysis)
b) Labour
Mate day 0.10 155.00 15.50
Mason day 1.20 196.00 235.20
Mazdoor day 1.20 155.00 186.00
Add for scaffolding @ 5 per cent of cost of a) 133.53
Material and b) Labour
c) Overhead charges @ 20% on (a+b) 560.81
d) Contractor's profit @ 10 % on (a+b+c) 336.49
Rate per cum (a+b+c+d) 3701.35
say 3701.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 808.26 889.09
Through and bond stone each 7.00 53.88 377.16
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.30 3177.00 953.10
analysis)
b) Labour
Mate day 0.12 155.00 18.60
Mason day 1.50 196.00 294.00
Mazdoor day 1.50 155.00 232.50
Add for scaffolding @ 5 per cent of cost of material 138.22
and labour
c) Overhead charges @ 20% on (a+b) 580.53
d) Contractor's profit @ 10 % on (a+b+c) 348.32
Rate per cum (a+b+c+d) 3831.52
say 3832.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 942.97 1046.70
Through and bond stone each 7.00 53.88 377.16
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.33 3177.00 1048.41
analysis)
b) Labour for masonry work
Mate day 0.20 155.00 31.00
Mason day 2.50 196.00 490.00
Mazdoor day 2.50 155.00 387.50
Add for scaffolding @ 5 per cent of cost of a) 169.04
Material and b) Labour
c) Overhead charges @ 20% on (a+b) 709.96
d) Contractor's profit @ 10 % on (a+b+c) 425.98
Rate per cum (a+b+c+d) 4685.74
say 4686.00
Note The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3241.00
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 324.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 713.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 427.81
Rate perm (a+b+c+d+e+f) 4705.93
say 4706.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3547.00
(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 354.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 780.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 468.20
Rate perm (a+b+c+d+e+f) 5150.24
say 5150.00
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3790.00
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 454.80
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 75.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 864.12
f) Contractor's profit @ 10 % on (a+b+c+d+e) 518.47
Rate perm (a+b+c+d+e+f) 5703.19
say 5703.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 4105.00
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 492.60
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 82.10
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 935.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 561.56
Rate perm (a+b+c+d+e+f) 6177.20
say 6177.00
13.5 C (r) Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3790.00
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 568.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 151.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 902.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 541.21
Rate perm (a+b+c+d+e+f) 5953.33
say 5953.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 4105.00
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 615.75
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 164.20
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 976.99
f) Contractor's profit @ 10 % on (a+b+c+d+e) 586.19
Rate perm (a+b+c+d+e+f) 6448.13
say 6448.00
13.5 D PCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3817.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 381.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 839.74
f) Contractor's profit @ 10 % on (a+b+c+d+e) 503.84
Rate perm (a+b+c+d+e+f) 5542.28
say 5542.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 4133.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 413.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 909.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 545.56
Rate perm (a+b+c+d+e+f) 6001.12
say 6001.00
13.5 D (q) Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3817.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 458.04
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 76.34
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 870.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 522.17
Rate perm (a+b+c+d+e+f) 5743.82
say 5744.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 4133.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 495.96
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 82.66
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 942.32
f) Contractor's profit @ 10 % on (a+b+c+d+e) 565.39
Rate perm (a+b+c+d+e+f) 6219.34
say 6219.00
13.5 D (r) Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3817.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Add 15 per cent of cost of material, labour and 15.00 572.55
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 152.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 908.45
f) Contractor's profit @ 10 % on (a+b+c+d+e) 545.07
Rate perm (a+b+c+d+e+f) 5995.74
say 5996.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 4133.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 619.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 165.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 983.65
f) Contractor's profit @ 10 % on (a+b+c+d+e) 590.19
Rate perm (a+b+c+d+e+f) 6492.12
say 6492.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3569.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 356.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 785.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 471.11
Rate perm (a+b+c+d+e+f) 5182.19
say 5182.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3850.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 385.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 847.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 508.20
Rate perm (a+b+c+d+e+f) 5590.20
say 5590.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 488.24
Rate perm (a+b+c+d+e+f) 5370.63
say 5371.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3850.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 462.00
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 77.00
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 877.80
f) Contractor's profit @ 10 % on (a+b+c+d+e) 526.68
Rate perm (a+b+c+d+e+f) 5793.48
say 5793.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3569.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 535.35
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 142.76
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 849.42
f) Contractor's profit @ 10 % on (a+b+c+d+e) 509.65
Rate perm (a+b+c+d+e+f) 5606.19
say 5606.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3850.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 577.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 154.00
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 916.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 549.78
Rate perm (a+b+c+d+e+f) 6047.58
say 6048.00
13.5 4.04 b F RCC Grade M25
i
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 4131.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 413.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 908.82
f) Contractor's profit @ 10 % on (a+b+c+d+e) 545.29
Rate perm (a+b+c+d+e+f) 5998.21
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 5998.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3815.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 450.17
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 68.67
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 866.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 520.06
Rate perm (a+b+c+d+e+f) 5720.67
say 5721.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 4131.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 487.46
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 74.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 938.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 563.14
Rate perm (a+b+c+d+e+f) 6194.52
say 6195.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3815.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 572.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 152.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 907.97
f) Contractor's profit @ 10 % on (a+b+c+d+e) 544.78
Rate perm (a+b+c+d+e+f) 5992.60
say 5993.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 4131.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 619.65
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 165.24
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 983.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 589.91
Rate perm (a+b+c+d+e+f) 6488.97
say 6489.00
13.5 G RCC Grade M30
(p) Height upto 5m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3830.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 383.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 842.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 505.56
Rate perm (a+b+c+d+e+f) 5561.16
say 5561.00
13.5 G RCC Grade M30
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 4148.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 414.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d) 912.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 547.54
Rate perm (a+b+c+d+e+f) 6022.90
say 6023.00
13.5 4.04 b G RCC Grade M30
ii
13.5 G (q) Height 5m to 10m
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 4148.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 477.02
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 66.37
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 938.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 562.97
Rate perm (a+b+c+d+e+f) 6192.63
say 6193.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3830.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 536.20
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 134.05
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 900.05
f) Contractor's profit @ 10 % on (a+b+c+d+e) 540.03
Rate perm (a+b+c+d+e+f) 5940.33
say 5940.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 4148.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Add 14 per cent of cost of material, labour and 14.00 580.72
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 145.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 974.78
f) Contractor's profit @ 10 % on (a+b+c+d+e) 584.87
Rate perm (a+b+c+d+e+f) 6433.55
say 6434.00
13.5 4.04 b H RCC Grade M35
iii
13.5 H (q) Height 5m to 10m
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 4225.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 464.75
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 59.15
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 949.78
f) Contractor's profit @ 10 % on (a+b+c+d+e) 569.87
Rate perm (a+b+c+d+e+f) 6268.55
say 6269.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3897.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 506.61
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 116.91
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 904.10
f) Contractor's profit @ 10 % on (a+b+c+d+e) 542.46
Rate perm (a+b+c+d+e+f) 5967.09
say 5967.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 4225.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 549.25
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 126.75
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d) 980.20
f) Contractor's profit @ 10 % on (a+b+c+d+e) 588.12
Rate perm (a+b+c+d+e+f) 6469.32
say 6469.00
Note The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.
13.6 4.10 Section Supplying, fitting and placing HYSD bar reinforcement
1600 & in sub-structure complete as per drawing and
2200 Technical Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 46300.00 48615.00
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor day 0.25 155.00 38.75
c) Overhead charges @ 20% on (a+b) 620.43
d) Contractor's profit @ 10 % on (a+b+c) 372.26
Cost for 30 m = a+b+c+d 4094.84
Rate per m (a+b+c+d)/30 136.49
say 136.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 155.00 49.60
Mazdoor for filling, watering, ramming etc. day 7.00 155.00 1085.00
Mazdoor (Skilled) day 1.00 196.00 196.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 700.49 8405.88
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 261.00 15.66
d) Overhead charges @ 20% on (a+b+c) 1950.43
e) Contractor's profit @ 10 % on (a+b+c+d) 1170.26
cost for 10 cum of Fiter Media = a+b+c+d+e 12872.82
Rate per cum = (a+b+c+d+e)/10 1287.28
say 1287.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
13.11 2000, Supplying, fitting and fixing in position true to line and
1000 & level cast steel rocker bearing conforming to IRC:
2200 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 155.00 9.30
Mazdoor (Skilled) day 0.50 196.00 98.00
Mazdoor day 1.00 155.00 155.00
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 0.00 0.00
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 0.00
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20% on (a+b) 52.46
d) Contractor's profit @ 10 % on (a+b+c) 31.48
cost for 250 tonnes capacity bearing = a+b+c+d 346.24
Rate per tonne capacity = (a+b+c+d)/250 1.38
say 1.00
13.12 2000 , Supplying, fitting and fixing in position true to line and
1000 & level forged steel roller bearing conforming to IRC:
2200 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 155.00 9.30
Mazdoor day 1.00 155.00 155.00
Mazdoor (Skilled) day 0.50 196.00 98.00
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 0.00 0.00
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 0.00
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20% on (a+b) 52.46
d) Contractor's profit @ 10 % on (a+b+c) 31.48
cost for 250 tonnes capacity bearing = a+b+c+d 346.24
Rate per tonne capacity = (a+b+c+d)/250 1.38
say 1.00
13.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE) and clause 2004
of MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 155.00 9.30
Mazdoor day 1.00 155.00 155.00
Mazdoor (Skilled) day 0.50 196.00 98.00
b) Material
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 0.00 0.00
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and 0.00
consumables.
c) Overhead charges @ 20% on (a+b) 52.46
d) Contractor's profit @ 10 % on (a+b+c) 31.48
cost for 80 tonnes capacity bearing = a+b+c+d 346.24
Rate per tonne capacity = (a+b+c+d)/80 4.33
say 4.00
13.14 4.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 155.00 9.30
Mazdoor day 1.00 155.00 155.00
Mazdoor (Skilled) day 0.50 196.00 98.00
b) Material
Elastomeric bearing assembly consisting of 7 internal each. 1.00 25662.25 25662.25
layers of elastomer bonded to 6 nos. internal
reinforcing steel laminates by the process of
vulcanisation, complete with all components as per
drawing and Technical Specifications.
Add 1 per cent of cost of bearing assembly for 256.62
foundation anchorage bolts and consumables.
c) Overhead charges @ 20% on (a+b) 5236.23
d) Contractor's profit @ 10 % on (a+b+c) 3141.74
cost for 19200cc of elastomeric bearing = a+b+c+d 34559.15
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.80
say 2.00
13.15 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.75 155.00 116.25
Mazdoor (Skilled) day 0.35 196.00 68.60
b) Material
Supply of sliding plate bearing of 80 tonne design each. 1.00 0.00 0.00
capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 0.00
foundation anchorage bolts and consumables.
c) Overhead charges @ 20% on (a+b) 38.21
d) Contractor's profit @ 10 % on (a+b+c) 22.93
cost for 80 tonnes of capacity bearing = a+b+c+d 252.19
3.15
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City(Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Sr No BOQ Ref. to
Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 3.00
13.16 10.14 2000 & Supplying, fitting and fixing in position true to line and
2200 level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainless steel
mating surface, complete assembly to be of cast
steel/fabricated structural steel, metal and elastomer
elements to be as per IRC: 83 part-I & II respectively
and other parts conforming to BS: 5400, section 9.1 &
9.2 and clause 2006 of MoRTH Specifications
complete as per drawing and approved Technical
Specifications.
CHAPTER-14
SUPER-STRUCTURE
Ref. to
BOQ
Sr No MoRTH Description Unit Quantity Rate Rs Cost RS
Item No.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed
&1600 cement concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 4400.00 22528.00
Coarse sand cum 6.75 750.00 5062.50
20 mm Aggregate cum 8.10 1423.00 11526.30
10 mm Aggregate cum 5.40 1376.00 7430.40
b) Labour
Mate day 0.86 155.00 133.30
Mason day 1.50 196.00 294.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 196.00 1176.00
Generator 33 KVA hour 6.00 313.00 1878.00
Basic Cost of Labour, Material & Machinery (a+b+c) 53129.00
for 15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 53129.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 10625.80
e) Overhead charges @ 20% on (a+b+c+d) 12750.96
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7650.58
Cost for 15 cum = a+b+c+d+e+f 84156.34
Rate per cum = (a+b+c+d+e+f)/15 5610.42
say 5610.00
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 53129.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 13282.25
e) Overhead charges @ 20% on (a+b+c+d) 13282.25
f) Contractor's profit @ 10 % on (a+b+c+d+e) 7969.35
Cost for 15 cum = a+b+c+d+e+f 87662.85
Rate per cum = (a+b+c+d+e+f)/15 5844.19
say 5844.00
14.1A (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 53129.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15938.70
e) Overhead charges @ 20% on (a+b+c+d) 13813.54
f) Contractor's profit @ 10 % on (a+b+c+d+e) 8288.12
Cost for 15 cum = a+b+c+d+e+f 91169.36
Rate per cum = (a+b+c+d+e+f)/15 6077.96
say 6078.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 4400.00 210980.00
Coarse sand cum 54.20 750.00 40650.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 191.80 154.92 29713.66
b) Labour
Mate day 0.84 155.00 130.20
Mason day 3.00 196.00 588.00
Mazdoor day 18.00 155.00 2790.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 19.00 155.00 2945.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
say 7634.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 58614.00
15 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 33996.12
e) Overhead charges @ 20% on (a+b+c+d) 18522.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11113.21
Cost for 15 cum = a+b+c+d+e+f 122245.36
Rate per cum = (a+b+c+d+e+f)/15 8149.69
say 8150.00
14.1 D RCC/PSC Grade M35
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 4400.00 222816.00
Coarse sand cum 54.00 750.00 40500.00
20 mm Aggregate cum 64.80 1423.00 92210.40
10 mm Aggregate cum 43.20 1376.00 59443.20
Admixture Kg 202.56 154.92 31380.60
b) Labour
Mate day 0.88 155.00 136.40
Mason day 3.00 196.00 588.00
Mazdoor day 19.00 155.00 2945.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1880.00 11280.00
Generator 100 KVA hour 6.00 588.00 3528.00
Loader hour 6.00 679.00 4074.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 783.00 11745.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 25200.00
Cement for grouting including 3 per cent wastage @ tonne 0.125 4400.00 550.00
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
Unit = sqm
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Cement concreteM30 Grade Refer relevant item of cum 4.09 4003.00 16380.28
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 5 per cent of above cost for form work for casting 819.01
in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.87 51136.00 44232.64
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of 3071.60
precast panels in position
b) Overhead charges @ 20% on (a) 12900.71
c) Contractor's profit @ 10 % on (a+b) 7740.42
Rate for 48 m (a+b+c) 85144.65
Rate per metre (a+b+c)/48 1773.85
say 1774.00
Note 1.Quantities of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of
24 m span.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with
1500, 20 mm nominal size aggregate, true to line and grade,
1600 & tolerance of vertical RCC post not to exceed 1 in 500,
1700 centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 4003.00 16380.28
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 46300.00 136399.80
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 13.2 (a) cum 1.00 4448.00 4448.00
b) Labour
(i) Cutting, bending, making reinforcement cage,
placing in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate day 0.06 155.00 9.30
Mazdoor (Skilled) day 0.35 196.00 68.60
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 0.00 0.00
Cost of formwork, steam curing arrangement, 508.81
pretensioning arrangement etc @ 5 per cent of cost
material, labour and machinery
d) Overhead charges @ 20% on (a+b+c) 2158.55
e) Contractor's profit @ 10 % on (a+b+c+d) 1295.13
Rate per cum = (a+b+c+d+e) 14246.43
say 14246.00
14.14 1700 & Providing and fixing Helical pipes in voided concrete
1800 slabs
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.00 0.00 0.00
Tie rods 20mm diameter each 1.00 0.00 0.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 155.00 1.55
Painter day 0.25 196.00 49.00
Mazdoor (Skilled) day 0.25 196.00 49.00
b) Material
Water based paint of approved quality for cement Litres 5.00 80.82 404.10
concrete surface
c) Overhead charges @ 20% on (a+b) 100.73
d) Contractor's profit @ 10 % on (a+b+c) 60.44
Cost for 10 sqm (a+b+c+d) 664.82
Rate per sqm (a+b+c+d)/10 66.48
say 66.00
14.17 4.15 2604 Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12 mm
thick, 200 mm wide galvanised weldable structural
steel plate as per IS: 2062, placed symmetrical to
centre line of the joint, resting freely over the top
surface of the deck concrete, welding of 8 mm dia. 100
mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause
2604.
Note Guidelines laid down vide the MoRTH circular No. RW/NH-
34059/1/96-S&R dated 30.11.2000 and subsequent
corrigendum dated 25.01.2001 may be reffered for
expansion joints.
14.18 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate
in expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 155.00 6.20
Mazdoor day 0.50 155.00 77.50
Mazdoor (Skilled) day 0.50 196.00 98.00
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 0.00 0.00
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c) Overhead charges @ 20% on (a+b) 36.34
d) Contractor's profit @ 10 % on (a+b+c) 21.80
Cost for 12 m = (a+b+c+d) 239.84
Rate per m = (a+b+c+d)/12 19.99
say 20.00
14.18 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 155.00 1.24
Mazdoor day 0.10 155.00 15.50
Mazdoor (Skilled) day 0.10 196.00 19.60
b) Material
20 mm thick compressible fibre board 12 m long x 25 sqm 3.00 0.00 0.00
cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20% on (a+b) 7.27
d) Contractor's profit @ 10 % on (a+b+c) 4.36
Cost for 12 m = (a+b+c+d) 47.97
Rate per m = (a+b+c+d)/12 4.00
say 4.00
14.18 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.01 155.00 1.55
Mazdoor day 0.20 155.00 31.00
Mazdoor (Skilled) day 0.10 196.00 19.60
b) Material
Premoulded joint filler 12 m long,20 mm thick and 300 sqm 3.60 855.40 3079.44
mm deep.
c) Overhead charges @ 20% on (a+b) 626.32
d) Contractor's profit @ 10 % on (a+b+c) 375.79
Cost for 12 m = (a+b+c+d) 4133.70
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
say 18.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 600.00 600.00
Stone Spalls cum 0.20 553.66 110.73
b) Labour
Mate day 0.04 155.00 6.20
Mason day 0.35 196.00 68.60
Mazdoor * day 0.75 155.00 116.25
c) Overhead charges @ 20% on (a+b) 180.36
d) Contractor's profit @ 10 % on (a+b+c) 108.21
Rate per cum = (a+b+c+d) 1190.35
say 1190.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has been
taken into account while making provision for labour.
15.2 2503 Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826
in 100mm x 100mm mesh (weaved diagonally) including 10
per cent extra for laps and joints laid with stone boulders
weighing not less than 40 kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x sqm 22.00 0.00 0.00
100 mm.
Stone cum 5.63 600.00 3378.00
Stone Spalls cum 1.13 553.66 625.63
b) Labour
Mate day 0.18 155.00 27.90
Mazdoor (Skilled) day 1.50 196.00 294.00
Mazdoor day *3.00 155.00 465.0
c) Overhead charges @ 20% on (a+b) 958.1
d) Contractor's profit @ 10 % on (a+b+c) 574.86
Cost for 5.63 cum = a+b+c+d 6323.50
Rate per cum = (a+b+c+d)/5.63 1123.18
say 1123.00
* Including excavation for trimming for preparation of bed.
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
15.3 2503 Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of
size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of
M-15 grade cement concrete with a minimum cement
content of 250 kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (a) cum 1.00 4448.00 4448.00
including OH & CP
Add 2 per cent of cost to account for excavation for 88.96
preparation of bed, nominal surface reinforcement and
filling of granular material in recesses between blocks.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
15.4 4.27 2504 Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per drawing
and Technical specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 1089.00 1089.00
Stone spalls of minimum 25 mm size cum 0.20 553.66 110.73
b) Labour
Mate day 0.04 155.00 6.20
Mason day 0.35 196.00 68.60
Mazdoor day 0.75 155.00 116.25
c) Overhead charges @ 20% on (a+b) 278.16
d) Contractor's profit @ 10 % on (a+b+c) 166.89
Rate per cum = (a+b+c+d) 1835.83
say 1836.00
15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (a) cum 1.00 4448.00 4448.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Overhead charges @ 20% on (a+b) 13.84
d) Contractor's profit @ 10 % on (a+b+c) 8.30
Cost for 10 sqm = a+b+c+d 91.34
Rate per sqm = (a+b+c+d)/10 9.13
say 9.00
15.7 2504.4 Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix if
cement concert block have been used for pitching . Rates for
toe wall can be adopted from respective clauses depending
upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been
analysed and given in respective chapters.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
b) Labour
Mate day 0.10 155.00 15.50
Mason day 0.50 196.00 98.00
mazdoor day 1.50 155.00 232.50
Add 1 per cent of (b) for trimming and preparation 10.57
of base.
c) Overhead charges @ 20% on (a+b) 213.46
d) Contractor's profit @ 10 % on (a+b+c) 128.08
Rate per cum = (a+b+c+d) 1408.83
say 1409.00
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 3177.00 3177.00
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 155.00 43.40
Mazdoor day 5.00 155.00 775.00
Mazdoor (Skilled) day 2.00 196.00 392.00
b) Material
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Galvanised steel wire crates of mesh size 100 mm x sqm 61.00 0.00 0.00
100 mm woven with 4mm dia. GI wire in rolls of
required size.
Stone boulders with least dimension of 200 mm cum 12.60 1105.00 13923.00
Stone spalls of minimum size 25 mm cum 2.52 553.66 1395.22
c) Overhead charges @ 20% on (a+b) 3305.72
d) Contractor's profit @ 10 % on (a+b+c) 1983.43
Cost for 12.60 cum (a+b+c+d) 21817.78
Rate per cum (a+b+c+d)/12.60 1731.57
say 1732.00
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
15.13 2503.3 Gabian Structure for Erosion Control, River Training
Works and Protection works
Providing and constructing gabian structures for erosion
control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m
compartments by cross netting, made from 4 mm galvanised
steel wire @ 32 kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm x 100 mm, filled with
boulders with least dimension of 200 mm, all loose ends to
be securely tied with 4 mm galvanised steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 155.00 21.70
Mazdoor day 2.50 155.00 387.50
Mazdoor (Skilled) day 1.00 196.00 196.00
b) Material
Galvanised steel wire crates of mesh size 100 mm x sqm 65.00 0.00 0.00
100 mm woven with 4mm dia. GI wire in rolls of
required size to cover 6.00 cum.
Stone boulders with least dimension of 200 mm cum 6.00 1105.00 6630.00
Stone spalls of minimum size 25 mm cum 1.20 553.66 664.39
c) Overhead charges @ 20% on (a+b) 1579.92
d) Contractor's profit @ 10 % on (a+b+c) 947.95
Cost for 6.00 cum (a+b+c+d) 10427.46
Rate per cum (a+b+c+d)/6.00 1737.91
say 1738.00
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
CHAPTER-16
REPAIR AND REHABILITATION
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
16.1 2809 Removal of existing cement concrete wearing coat
including its disposal complete as per Technical
Specification without causing any detrimental effect to
any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000 m
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 4.40 70.40
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
16.4 2800 Providing and inserting nipples with approved fixing
compound after drilling holes for grouting as per
Technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary
of nipples after completion of grouting with
Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 0.00 0.00
Cement, fixing compound and consumables @ 15 per 0.00
cent of cost of nipple
b) Labour
Mate day 0.01 155.00 1.55
Mazdoor (Skilled) labour for drilling day 0.08 196.00 15.68
Mazdoor (Skilled) labour for fixing nipple and sealing day 0.08 196.00 15.68
inlets
Mazdoor for cutting and removing of nipples day 0.04 155.00 6.20
Add 10 per cent of labour cost for drilling holes etc 3.91
c) Overhead charges @ 20 % on (a+b) 8.60
d) Contractor's profit @ 10 % on (a+b+c) 5.16
Rate per No. = (a+b+c+d) 56.79
say 57.00
16.5 2806 Sealing of cracks/porous concrete by injection process
through nipples/Grouting complete as per Technical
Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 4.40 4.84
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Rate per kg = (a+b+c+d+e) 66.90
say 67.00
16.6 2800 Patching of damaged concrete surface with polymer
concrete and curing compounds, initiator and
promoter, available in present formulations, to be
applied as per instructions of manufacturer and as
approved by the Engineer.
Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.06 155.00 9.30
Mazdoor (Skilled) day 0.75 196.00 147.00
Mazdoor day 0.75 155.00 116.25
b) Material
Pre-packed polymer concrete based on epoxy system kg 315.00 0.00 0.00
complete with curing compound, intiator and promoter
including 5 per cent wastage.
c) Machinery
Grout pump with agitator and accessories hour 2.00 0.00 0.00
d) Overhead charges @ 20 % on (a+b+c) 54.51
e) Contractor's profit @ 10 % on (a+b+c+d) 32.71
Cost for 10 sqm = a+b+c+d+e 359.77
Rate per sqm = (a+b+c+d+e)/10 35.98
say 36.00
Note This item is a proprietory item available in market as pre-
packed polymer concrete and is required to be applied as
per instructions of the manufacturer.
16.7 2803 Sealing of crack / porous concrete with Epoxy Grout
by injection through nipples complete as per clause
2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 100.00 110.00
b) Labour
Mate day 0.08 155.00 12.40
Mazdoor (Skilled) day 0.10 196.00 19.60
Mazdoor day 0.10 155.00 15.50
c) Machinery
Epoxy Injection gun hour 0.10 0.00 0.00
d) Overhead charges @ 20 % on (a+b+c) 31.50
e) Contractor's profit @ 10 % on (a+b+c+d) 18.90
Rate per kg = (a+b+c+d+e) 207.90
say 208.00
16.8 2804 Applying epoxy mortar over leached, honey combed
and spalled concrete surface and exposed steel
reinforcement complete as per Technical Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 0.00 0.00
Epoxy mortar kg 2.20 0.00 0.00
Epoxy resin -hardener mix for seal coat. kg 2.00 0.00 0.00
Add 3 per cent cost of material for other consumables 0.00
like acetone etc and to cover wastage.
b) Labour
Mate day 0.04 155.00 6.20
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor (Skilled) day 0.50 196.00 98.00
Mazdoor day 0.50 155.00 77.50
c) Overhead charges @ 20 % on (a+b) 36.34
d) Contractor's profit @ 10 % on (a+b+c) 21.80
Cost for 10 sqm = a+b+c+d 239.84
Rate per sqm = (a+b+c+d)/10 23.98
say 24.00
16.9 2807 Removal of defective concrete, cleaning the surface
thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water
and quick setting compound in the proportion as per
clause 2807.1., sand and coarse aggregates
conforming to IS: 383 and table 1 of IS: 9012
respectively, water cement ratio ranging from 0.35 to
0.50, density of gunite not less than 2000 kg/cum,
strength not less than 25 Mpa and workmanship
conforming to clause 2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate day 0.04 155.00 6.20
Mazdoor day 0.50 155.00 77.50
Mazdoor (Skilled) day 0.50 196.00 98.00
b) Machinery
Air compressor 250 cfm hour 1.00 269.00 269.00
Shotcreteing equipment hour 1.00 457.00 457.00
water tanker 6 KL capacity hour 0.02 261.00 5.22
c) Material
Cement kg 120.00 4.40 528.00
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
say 24.00
16.11 2805 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes kg 8.00 0.00 0.00
and satisfying testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage. 0.00
b) Labour
Mate day 0.04 155.00 6.20
Mazdoor (Skilled) day 0.50 196.00 98.00
Mazdoor day 0.50 155.00 77.50
c) Overhead charges @ 20 % on (a+b) 36.34
d) Contractor's profit @ 10 % on (a+b+c) 21.80
Cost for 10 sqm = a+b+c+d 239.84
Rate per sqm = (a+b+c+d)/10 23.98
say 24.00
16.12 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 1.05 0.00 0.00
length for jacking
HDPE pipes 75mm dia including 5 per cent wastage metre 112.00 0.00 0.00
Cement for grouting kg 400.00 4.40 1760.00
Tube anchorage set complete with bearing plate, each 8.00 0.00 0.00
permanent wedges etc
Epoxy kg 6.00 100.00 600.00
MS plates for deviator (where deviator blocks are not tonne 2.10 46300.00 97230.00
provided)
Add 20 per cent cost of material for other materials 19918.00
like lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 155.00 37.20
Mazdoor Semi-skilled) day 3.00 176.00 528.00
Mazdoor day 3.00 155.00 465.00
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 0.44 155.00 68.20
Blacksmith day 3.00 196.00 588.00
Mazdoor day 8.00 155.00 1240.00
iii) For prestressing
Mate/Supervisor day 0.13 155.00 20.15
Fitter day 0.70 196.00 137.20
Mazdoor day 2.65 155.00 410.75
iv) For grouting
Mate/Supervisor day 0.13 155.00 20.15
Mason day 0.70 196.00 137.20
Mazdoor day 2.65 155.00 410.75
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
c) Machinery
Stressing jack with pump hour 4.00 108.00 432.00
Grouting pump with agitator hour 1.35 0.00 0.00
d) Overhead charges @ 20 % on (a+b+c) 24800.52
e) Contractor's profit @ 10 % on (a+b+c+d) 14880.31
Rate per MT = (a+b+c+d+e) 163683.43
say 163683.00
16.13 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 3.10 0.00 0.00
length for jacking
HDPE pipes 90mm dia including 5 per cent wastage metre 224.00 0.00 0.00
Cement for grouting tonne 1.01 4400.00 4444.00
Tube anchorage set complete with bearing plate, each 8.00 0.00 0.00
permanent wedges etc
Epoxy kg 10.00 100.00 1000.00
MS plates for deviator (where deviator blocks are not tonne 7.00 46300.00 324100.00
provided)
Add 20 per cent cost of material for other materials 65908.80
like lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 155.00 12.40
Mazdoor Semi-skilled) day 8.00 176.00 1408.00
Mazdoor day 8.00 155.00 1240.00
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.28 155.00 198.40
Blacksmith day 7.00 196.00 1372.00
Mazdoor day 25.00 155.00 3875.00
iii) For prestressing
Mate/Supervisor day 0.20 155.00 31.00
Fitter day 1.00 196.00 196.00
Mazdoor day 4.00 155.00 620.00
iv) For grouting
Mate/Supervisor day 0.26 155.00 40.30
Mason day 1.50 196.00 294.00
Mazdoor day 5.00 155.00 775.00
c) Machinery
Stressing jack with pump hour 7.00 108.00 756.00
Grouting pump with agitator hour 3.00 0.00 0.00
d) Overhead charges @ 20 % on (a+b+c) 81254.18
e) Contractor's profit @ 10 % on (a+b+c+d) 48752.51
Cost for 3.10 MT = a+b+c+d+e 536277.59
Rate per MT = (a+b+c+d+e)/3.10 172992.77
say 172993.00
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
16.14 2810 Providing external prestressing with high tensile steel
wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 9.28 0.00 0.00
length for jacking
HDPE pipes 90 mm dia including 5 per cent wastage metre 672.00 0.00 0.00
Cement for grouting tonne 3.04 4400.00 13376.00
Tube anchorage set complete with bearing plate, each 12.00 0.00 0.00
permanent wedges etc
Epoxy kg 14.00 100.00 1400.00
MS plates for deviator (where deviator blocks are not tonne 20.00 46300.00 926000.00
provided)
Add 20 per cent cost of material for other materials 188155.20
like lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 1.72 155.00 266.60
Mazdoor Semi-skilled) day 18.00 176.00 3168.00
Mazdoor day 25.00 155.00 3875.00
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 4.00 155.00 620.00
Blacksmith day 20.00 196.00 3920.00
Mazdoor day 80.00 155.00 12400.00
iii) For prestressing
Mate/Supervisor day 0.30 155.00 46.50
Fitter day 1.50 196.00 294.00
Mazdoor day 6.00 155.00 930.00
iv) For grouting
Mate/Supervisor day 1.00 155.00 155.00
Mason day 5.00 196.00 980.00
Mazdoor day 20.00 155.00 3100.00
c) Machinery
Stressing jack with pump hour 10.00 108.00 1080.00
Grouting pump with agitator hour 10.00 0.00 0.00
d) Overhead charges @ 20 % on (a+b+c) 231953.26
e) Contractor's profit @ 10 % on (a+b+c+d) 139171.96
Cost for 9.28 MT = a+b+c+d+e 1530891.52
Rate per MT = (a+b+c+d+e)/9.28 156213.42
say 156213.00
16.15 2808 Replacement of Bearings complete as per Technical
Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length of
30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 0.00 0.00
Mate day 0.64 155.00 99.20
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Mazdoor (Skilled) day 4.00 196.00 784.00
Mazdoor day 12.00 155.00 1860.00
v) Wooden packing cum 0.15 0.00 0.00
b) Replacement of bearing
Cost of bearing. each 3.00 0.00 0.00
c) Overhead charges @ 20 % on (a+b) 548.64
d) Contractor's profit @ 10 % on (a+b+c) 329.18
Cost of repair of 3 bearings = a+b+c+d 3621.02
Rate of repair per bearing = (a+b+c+d)/3 1207.01
say 1207.00
Note The work entails replacement of all the bearings on one side
of the span.
16.16 2808 Rectification of Bearings as per Technical
Specifications
Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from
below i.e. by placing the jacks on pier/abutment caps
for span length of 30m.
i) Hire charges for jack of 40 tonne lifting capacity. each 3.00 0.00 0.00
Mate day 0.64 155.00 99.20
Mazdoor (Skilled) day 4.00 196.00 784.00
Mazdoor day 12.00 155.00 1860.00
v) Wooden packing cum 0.15 0.00 0.00
b) Cost of parts to be replaced for 3 bearings. each 3.00 0.00 0.00
c) Overhead charges @ 20 % on (a+b) 548.64
d) Contractor's profit @ 10 % on (a+b+c) 329.18
Cost of repair of 3 bearings = a+b+c+d 3621.02
Rate of repair per bearing = (a+b+c+d)/3 1207.01
say 1207.00
Note The rectification of 3 bearings included in this analysis are
on the same side of the span.
16.17 Replacement of Expansion Joints complete as per
drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg 9.60 100.00 960.00
kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate cum 3.60 4803.00 17290.80
as per items 14.1 C (i)
b) Labour
Removal of old expansion joint including breaking of
concrete, cutting of lugs and shifting of broken material etc.
Mate day 0.26 155.00 40.30
Mazdoor day 6.00 155.00 930.00
Mazdoor (Skilled) day 0.50 196.00 98.00
c) Overhead charges @ 20 % on (a+b) 3863.82
d) Contractor's profit @ 10 % on (a+b+c) 2318.29
Cost for replacement of 12 RM = a+b+c+d 25501.21
Rate per RM = (a+b+c+d)/12 2125.10
say 2125.00
Note The rate for the installation of new expansion joints may be
taken from the chapter on superstructure. Broken concrete
will have to be replaced which has been included in this
analysis.
16.18 Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through Lucknow City (Package EW-
15A/UP)
Rate Analysis for Cost Estimation
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.20 155.00 31.00
Mazdoor day 5.00 155.00 775.00
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 306.00 306.00
c) Overhead charges @ 20 % on (a+b) 222.40
d) Contractor's profit @ 10 % on (a+b+c) 133.44
Cost for 10 m = a+b+c+d 1467.84
Rate per metre = (a+b+c+d)/10 146.78
say 147.00
Note The rate for the provision of new railing may be adopted
from the chapter on superstructure.
16.19 Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.40 155.00 62.00
Mazdoor day 10.00 155.00 1550.00
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 306.00 306.00
c) Overhead charges @ 20 % on (a+b) 383.60
d) Contractor's profit @ 10 % on (a+b+c) 230.16
Cost for 10 m = a+b+c+d 2531.76
Rate per metre = (a+b+c+d)/10 253.18
say 253.00
Note The rate for the construction of new crash barrier may be
adopted from chapter 8 on Traffic and Transportation.
16.20 Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate day 0.16 155.00 24.80
Mazdoor day 4.00 155.00 620.00
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 306.00 306.00
c) Overhead charges @ 20 % on (a+b) 190.16
d) Contractor's profit @ 10 % on (a+b+c) 114.10
Cost for 10 m = a+b+c+d 1255.06
Rate per metre = (a+b+c+d)/10 125.51
say 126.00
16.21 Repair of Crash Barrier
Repair of concrete crash barrier with cement concert of M-30
grade by cutting and trimming the damaged portion to a
regular shape, cleaning the area to be repaired thoroughly,
applying cement concert after erection of proper form work.
BOQ Ref. to
Sr No Item MoRTH Description Unit Quantity Rate Rs Cost RS
No. Spec.
* For dismantling and trimming the surface to a regular shape
and removal of damaged material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.30 4803.00 1440.90
as per items 14.1 C (i)
This may be priced based on the rate given the chapter of
superstructure.
c) Overhead charges @ 20 % on (a) 32.24
d) Contractor's profit @ 10 % on (a+c) 19.34
Cost for 10 m = a+b+c+d 1653.68
Rate per m = (a+b+c+d)/10 165.37
say 165.00
16.22 Repair of RCC Railing
Carrying out repair of RCC M30 railing to bring it to the
original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.10 4803.00 480.30
as per items 14.1 C (i)
HYSD bar reinforcement Rate as per item No tonne 0.01 51136.00 664.77
14.2(Excluding OH & CP)
b) Labour*
Mate day 0.016 155.00 2.48
mazdoor day 0.20 155.00 31.00
* For dismantling and trimming the surface to a regular shape
and removal of damaged material.
c) Overhead charges @ 20 % on (b) 6.70
d) Contractor's profit @ 10 % on (b+c) 4.02
Cost for 10 m = a+b+c+d 1189.26
Rate per m = (a+b+c+d)/10 118.93
say 119.00
16.23 Repair of Steel Railing
Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the
extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series kg 29.00 46.30 1342.70
9.3 8.08 2900 Laying Reinforced Cement Concrete Relaying & Refixing
Pipe NP4 / Prestressed Concrete Pipe
on First Class Bedding in Double Row .
Unit = metre
Taking output = 12.5 metres ( 10 pipes
of 2.5 m length each in two rows.)
Unit = cum
Taking output = 225 cum (495 tonnes)
Unit = cum
Taking output = 300 cum
c) Material
For coarse graded Granular sub-base
Materials per table 400-2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 1369.00 183993.60
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 1408.00 243302.40
2.36 mm below @ 20 per cent (Coarse cum 76.800 982.00 75417.60
Sand)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.100 155.00 15.50
Mazdoor skilled day 0.500 196.00 98.00
Mazdoor day 2.000 155.00 310.00
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour 1.500 2017.00 3025.50
hour
Vibratory roller 8 -10 tonne hour 6.000 1298.00 7788.00
Water tanker 6 KL capacity hour 3.000 261.00 783.00
c) Material
For coarse graded Granular sub-base
Materials per table 400-2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 33.600 1369.00 45998.40
26.5 mm to 4.75 mm @ 45 per cent cum 43.200 1408.00 60825.60
2.36 mm below @ 20 per cent (Coarse cum 19.200 982.00 18854.40
Sand)
Cost of water KL 18.000 100.00 1800.00
4.2 Rate per cum for grading-I Material
d) Overhead charges @ 08 % on 11159.87
(a+b+c)
e) Contractor's profit @ 10 % on 15065.83
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 165724.10
Rate per cum = (a+b+c+d+e)/300 552.41
say 552.00
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.120 155.00 18.60
Mazdoor skilled day 0.500 196.00 98.00
Mazdoor day 2.500 155.00 387.50
b) Machinery
Wet mix plant of 60 tonne hourly hour 2.250 1014.00 2281.50
capacity
Electric generator 125 KVA hour 1.500 588.00 882.00
Front end loader 1 cum capacity hour 1.500 679.00 1018.50
Paver finisher hour 1.500 821.00 1231.50
Completion of Balance Works of Segment of Lucknow Bypass Connecting NH-25 NH-28 via NH-56 passing through
Lucknow City (Package EW-15A/UP)
Rate Analysis for Cost Estimation
PK Road
Starting Chainage End Chainage Eff. Length width Thickness Qty
Tack Coat RHS 157.462 158.17 708 3.5 2478
LHS 157.694 158.17 476 3.5 1666
LHS 157.532 157.694 162 3.5 567
RHS 156.741 157.462 721 3.5 2523.5
LHS 156.56 157.532 972 3.5 3402
RHS 156.384 156.741 357 3.5 1249.5
LHS 156.384 156.56 176 3.5 616
RHS 156 156.384 384
LHS 156 156.384 384
DBM 156.39 158.17 1780 7 0.05 623
156 156.39 390 7 0.05 136.5
423.5
770
616
154
1963.5
770
2478
1666
2478
1666
567
2523.5
3402
1881.9