INSPECTION & TEST PLAN
FOR I&C
LOW CURRENT SYSTEM
SITE INSPECTION & TEST PLAN
FOR I&C
LOW CURRENT WORKS
A ITP FOR I&C LOW CURRENT SYSTEM REMARKS
1 INSTALLATION OF CLOCK SYSTEM DEVICES & EQUIPMENTS
2 INSTALLATION OF PAGING SYSTEM DEVICES & EQUIPMENTS
3 INSTALLATION OF TELEPHONE & LAN SYSTEM DEVICES & EQUIPMENTS
4 INSTALLATION OF INDUSTRIAL SYSTEM DEVICES & EQUIPMENTS
5 INSTALLATION OF AUDIO & VIDEO SYSTEM DEVICES & EQUIPMENTS
6 INSTALLATION OF WEATHER STATION DEVICES & EQUIPMENTS
7 INSTALLATION OF HVAC SYSTEM DEVICES & EQUIPMENTS
CONSTRUCTION OF COMBINE CYCLE POWER PLANT no: 12
( AFC/ IFC )
1 INSPECTION OF CLOCK SYSTEM INSTALLATION A H W W
PTS PP12
( AFC/ IFC )
2 INSPECTION OF PAGING SYSTEM INSTALLATION B H W W
PTS PP12
( AFC/ IFC )
3 INSPECTION OF TELEPHONE & LAN SYSTEM INSTALLATION C H W W
PTS PP12
( AFC/ IFC )
4 INSPECTION OF INDUSTRIAL SECURITY SYSTEM INSTALLATION D H W W
PTS PP12
( AFC/ IFC )
5 INSPECTION OF AUDIO & VIDEO SYSTEM INSTALLATION E H W W
PTS PP12
( AFC/ IFC )
6 INSPECTION OF WEATHER STATION SYSTEM INSTALLATION F H W W
PTS PP12
( AFC/ IFC )
7 INSPECTION OF HVAC SYSTEM INSTALLATION G H W W
PTS PP12
LEGEND:
R: REVIEW S: SURVEILLANCE W: WITNESS H: HOLD
CONSTRUCTION OF COMBINE CYCLE POWER PLANT no: 12
GENERAL NOTES
ABBREVIATION: S: Surveillance, R: Reports Review, W: Witness Inspection, H: Hold Points
Surveillance Monitoring the work in progress without notice from Construction.
Review Document/ Report review.
Concern party shall be notified of the timing of the inspection or test in advance. However, the Inspection or Test shall be performed as scheduled if the Concern
Witness
Party representative is not present.
Concern party shall be notified of the timing of inspection or test in advance. Inspection or test shall be performed as scheduled if the concern party representative in
Hold Points
attendance.