BADAN PEMELIHARAAN KEAMANAN POLRI

DIREKTORAT POLISI SATWA


JL.KOMJEN POL.M.JASIN - CIMANGGIS DEPOK

PENGADAAN POLSATWA TAHAP 2

BILL OF QUANTITY (BQ)


VII A RELOCATION INDOOR HORSE TREADMILL / LONDSAY

NO. DESCRIPTION SPESIFICATION QTY UNIT

I DEMOLITION WORK
1 Unloding steel frame & roof 314.00 m²
2 Debris cleaning 1.00 lot
Sub Total

II STRUCTURE WORK
1 Measurement and Attach Bouwplank 81.64 m¹
2 Ecavation 1.50 m³
3 Back fill 444.23 m³
4 Soil compaction 314.00 m²
5 Sand fill under structur 10 cm 6.86 m³
6 Lean concrete 5 cm 3.43 m³
7 Concrete foundation 0.00 m³
8 Concrete beam 0.00 m³
9 Pratical concrete 0.00 m³
10 Heble install 15 cm 62.40 m³
11 Wood wall 62.40 m³
12 Wall plastering 124.80 m³
13 Instal steel strukture 5,024.00 kg
14 Instal railling hollow steel 78.50 m¹
15 Zincalum roof 379.94 m²
16 Sand filling 70 cm 219.80 m³
17 Attach the dinamo 1.00 unit
18 Electrical instalation 1.00 lot
19 Steel door 260 x 150 cm 2.00 nos
20 Painting stell structure 615.65 m²
21 Painting wood 124.80 m²
Sub total

TOTAL 314.00 m²
UNIT PRICE (RP.) TOTAL PRICE (RP.)

67,489.47 21,191,693.10
5,500,000.00 5,500,000.00

40,340.00 3,293,357.60
61,440.00 92,160.00
29,436.00 13,076,295.41
20,100.00 6,311,400.00
397,680.00 2,727,289.44
945,353.46 3,241,617.02
-
-
-
95,000.00 5,928,000.00
215,000.00 13,416,000.00
70,430.40 8,789,713.92
29,000.00 145,696,000.00
425,000.00 33,362,500.00
90,518.12 34,391,454.51
15,873.00 3,488,885.40
2,500,000.00 2,500,000.00
123,000.00 123,000.00
4,750,000.00 9,500,000.00
66,562.05 40,979,058.78
58,767.50 7,334,184.00

360,942,609.18
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN LATIHAN INDOOR 27.00 x 55.00
JL.KOMJEN.POL.M.JASIN - CIMANGGIS DEPOK

NO. JENIS PEKERJAAN

I. PEKERJAAN Bongkaran
1 bongkar atap
galian pasir 50 cm
2 buang pasir keluar lokasi
bongkar rangka atap dan kolom
rangka atap`kuda - kuda besi C 2 x 100.100.2³

kolom luar wf 150


kolom ke 2 . Hollow 5/5 t= 200 cm (relling)
kolom ke 3 . Hollow 5/5 t= 200 cm (relling)
bongkar dudkan mesin

I. PEKERJAAN PERSIAPAN
1 buat bouwplank
1 galian pasir 70 cm

2 buang pasir keluar lokasi


galian tanah pondasi
pondasi

sloof
lantai 70 cm
1 urugan dan perataan galian
1 pemadatan tanah
1 urugan pasir bawah pondasi & sloof

pondasi

sloof

1 Urugan pasir 70 cm

struktur beton
pondasi

sloof

pasangan dinding bata merah


plesteran
beton praktis kolom
ring balok
dinding papan
pintu besi sorong
2 pasang atap zinkalumn

1 pasang listplank GRC

cat konstruksi baja


2 cat reling pagar t = 120 cm

cat rangka baja


rangka atap`kuda - kuda besi C 2 x 100.100.2³

kolom luar wf 150


kolom ke 2 . Hollow 5/5 t= 200 cm (relling)
kolom ke 3 . Hollow 5/5 t= 200 cm (relling)
bongkar dudkan mesin
rangka atap
cat sloof
SAT.

3.14 x 10.00 x 10.00 x 1.00 = 314.00


3.14 x 10.00 x 10.00 x 0.50 = 157.00
157.00 x 1.20 x 1.00 x 1.00 = 188.40
314.00 x 20.00 x 0.80 x 1.00 = 5,024.00
11.00 x 2.00 x 4.07 x 12.00 = 1,073.60
0.50 x 2.00 x 4.07 x 144.00 = 585.60
6.00 x 18.10 x 12.00 x 1.00 = 1,303.20
3.14 x 2.00 x 7.50 x 1.00 = 47.10
3.14 x 2.00 x 5.00 x 1.00 = 31.40
1.00 x 1.00 x 1.00 x 1.00 = 1.00

3.14 x 2.00 x 13.00 x 1.00 = 81.64


3.14 x 100.00 x 0.70 x 1.00 = 219.80

219.80 x 1.20 x 1.00 x 1.00 = 263.76


370.19
1.50 x 1.50 x 2.00 x 12.00 = 54.00
1.00 x 1.00 x 1.50 x 36.00 = 54.00
0.30 x 1.00 x 3.14 x 10.00 = 9.42
0.30 x 1.00 x 3.14 x 15.00 = 14.13
0.30 x 1.00 x 3.14 x 20.00 = 18.84
3.14 x 100.00 x 0.70 x 1.00 = 219.80
370.19 x 1.20 x 1.00 x 1.00 = 444.23
3.14 x 10.00 x 10.00 x 1.00 = 314.00

6.86
1.20 x 1.20 x 0.10 x 12.00 = 1.73
0.80 x 0.80 x 0.10 x 36.00 = 2.30
0.20 x 0.10 x 3.14 x 10.00 = 0.63
0.20 x 0.10 x 3.14 x 15.00 = 0.94
0.20 x 0.10 x 3.14 x 20.00 = 1.26
3.14 x 100.00 x 0.70 x 1.00 = 219.80

270.37
1.20 x 1.20 x 0.18 x 12.00 = 3.02
0.80 x 0.80 x 0.15 x 36.00 = 3.46
1.00 x 1.20 x 1.00 x 1.00 = 1.20
0.20 x 0.40 x 3.14 x 10.00 = 2.51
0.20 x 0.40 x 3.14 x 15.00 = 3.77
0.20 x 0.40 x 3.14 x 20.00 = 5.02

2.60 x 2.00 x 12.00 x 1.00 = 62.40


62.40 x 2.00 x 1.00 x 1.00 = 124.80
2.00 x 2.00 x 12.00 x 0.02 = 1.08
5.20 x 6.00 x 0.15 x 0.15 = 0.70
2.60 x 2.00 x 12.00 x 1.00 = 62.40
2.00 x 1.00 x 1.00 x 1.00 = 2.00
3.14 x 11.00 x 11.00 x 1.00 = 379.94

3.14 x 2.00 x 11.00 x 1.00 = 69.08

408.10
82.00 x 2.00 x 1.00 x 1.00 = 164.00

615.65
11.00 x 2.00 x 0.30 x 12.00 = 79.20
0.50 x 2.00 x 0.30 x 144.00 = 43.20
6.00 x 0.60 x 12.00 x 1.00 = 43.20
3.14 x 2.00 x 7.50 x 1.00 = 47.10
3.14 x 2.00 x 5.00 x 1.00 = 31.40
6.00 x 0.80 x 1.00 x 1.00 = 4.80
379.94 x 0.80 x 1.00 x 1.00 = 303.95
3.14 x 25.00 x 0.80 x 1.00 = 62.80
harga sat jumlah harga
Harga Satuan Bahan
Buku Jurnal Edisi 38, Tahun : 2019

No. Jenis Bahan Satuan Harga Satuan

A. Bahan Alam
1 Tanah merah m3 Rp 104,000.00
2 Pasir urug m3 Rp 173,152.00
3 Pasir pasang m3 Rp 232,960.00
4 Pasir beton m3 Rp 284,000.00
5 Pasir putih m3 Rp 270,000.00
6 Split m3 Rp 254,016.00
7 Koral gundu m3 261,744.00
8 Sirdam m3 Rp 180,000.00
9 Batu bata kecil bh Rp 1,000.00
10 Batu bata jumbo bh Rp 3,000.00
11 Bataco press tangan bh Rp 4,000.00
12 Heble / bata ringan m3 Rp 1,280,000.00
13 Pavng block 8 cm m2 Rp 115,000.00
14 Pavng block 6 cm m2 Rp 100,000.00
15 Semen abu - abu zak Rp 75,000.00
16 Semen warna kg Rp 11,000.00
17 Semen MU 300 zak Rp 51,000.00
18 Beton jadi K 300 m3 Rp 1,324,000.00
19 Batu kali m3 Rp 186,144.00

B. Bahan Lantai
1 Keramik 20/20 m² Rp 90,000.00
2 Keramik 20/25 m²
3 HT 30/30 m²
4 HT 40/40 m²
5 Paving block 10/20 t = 8 cm m² Rp 115,000.00
6 HT (WALL) 30/60 MOSAIC m²
7 HT (WALL) 30/60 m²
8 Karpet m² Rp 48,000.00
9 Under layer m² Rp 109,000.00

C. Bahan Kayu

1 Dolken Ø 8 cm btg Rp 11,760.00


2 Balok kamper Samarinda m³ Rp 12,014,464.00
3 Papan kamper Samarinda m³ Rp 12,970,160.00
4 Papan terentang m³
5 Plywood 4 mm lbr Rp 55,850.00
6 Plywood 6 mm lbr Rp 69,850.00
7 Plywood 9 mm lbr Rp 98,850.00
8 Teakwood 4 mm lbr
9 Hpl m² Rp 92,288.00

Aluminium & Pengunci


1 Kusen aluminium 4" m¹ Rp 111,104.00
2 Profil ambang bawah m¹
3 Profil ambang samping m¹
4 Sealent tub Rp 58,240.00
5 Kunci pintu bh Rp 140,000.00
6 Kunci pintu sorong bh Rp 140,000.00
7 Engsel pintu swing 4" bh Rp 24,000.00
8 Rel pintu dorong eks Dekson bh
9 Floor hinge FH DKS 84 psg
10 Handle pintu kaca 60 cm psg Rp 250,000.00
11 Grendel tanam 45 cm psg Rp 115,000.00

D. Bahan Plafon

1 Accoustic Tile lbr


2 Gypsum 9 mm lbr Rp 113,904.00
3 Gypsum 12 mm lbr Rp 89,000.00
4 Gypsum water resistant 9 mm lbr Rp 105,200.00
5 Wall papaer W 1 m²
6 Wall papaer W 2 m²
7 Shadow line m¹

E. Bahan Kaca
1 Kaca polos 6 mm m² Rp 167,216.00
2 Kaca polos 8 mm m² Rp 250,000.00
3 Kaca polos 10 mm m² Rp 410,000.00
4 Kaca polos 12 mm m² Rp 460,000.00
5 Kaca TEMPERD 12 mm m² Rp 1,734,656.00

F. Bahan Cat
1 Lem Aibon kg Rp 65,000.00
2 Cat ICI luar kg
3 Cat ICI dalam kg Rp 30,912.00
4 Cat dasar kg Rp 32,000.00
5 Cat minyak kg Rp 62,000.00
6 Cat zincromate kg Rp 46,000.00
7 Meni besi kg Rp 49,616.00
8 Amplas lbr Rp 5,712.00
9 Kuas bh Rp 20,944.00
10 Tiner kg Rp 28,000.00
11 Floor hardener kg
12 Waterproofing coating kg

Bahan Basi
1 Paku < 7 cm kg Rp 36,000.00
2 Besi beton polos kg Rp 11,000.00
3 Besi beton ulir kg Rp 11,000.00
4 Besi hollow 4/4 x 400 btg
5 Besi hollow 2/4 x 400 btg
6 Besi hollow 4/6 x 400 t = 1.1 mm btg
7 Besi hollow 4/4 x 400 t = 1.1 mm btg
8 Baja WF kg Rp 16,000.00
9 Besi CNP 100 kg Rp 21,000.00
10 Baja siku 60.60.6 kg Rp 19,000.00
11 Baja ringan ex Bloscop m² Rp 135,000.00
12 Kawat beton kg Rp 18,000.00
13 Wire mesh M 8 lbr Rp 678,500.00
14 Wire mesh M 6 lbr Rp 478,000.00
15 Kawat burung m² Rp 20,000.00
16 Pipa galvanis 2" bh Rp 74,000.00
17 Pipa galvanis 4" m¹
18 Pipa stainless steel 2" bh Rp 607,000.00
19 Karet lembaran t = 1 cm m²
20 Timah hitam kg
Sanitary
1 Kloset jongkok bh Rp 628,000.00
2 Kloset duduk bh Rp 3,250,000.00
3 Jet washer bh Rp 616,000.00
4 Wastafel bh Rp 350,000.00
5 Shower dinding + kran bh Rp 7,100,000.00
6 Kran dinding bh Rp 301,000.00
7 Tempat sabun bh Rp 331,000.00
8 Tempat kertas bh Rp 678,000.00
9 Floor drain bh Rp 457,000.00
10 Cermin m²
11 Shower screen bh
12 LW540J - Toto Lavatory bh Rp 1,160,000.00
13 TX115LI - Toto Faucet bh Rp 2,970,000.00
14 TX403SMCRB - Toto Shower Spray bh Rp 616,000.00
15 Kitchen Sink ex Meiwha bh
16 Urinoir U 57 M bh
17 Tangki air Fiberglass 2 m3 bh
18 Devider' bh
19 Pilaster bh
20 Pintu toilet bh

Atap
1 Atap transparant m²
2 Kawat ayam m² Rp 20,000.00
3 Sika waterproofingRain Tite m²
4 Atapzincalum m²
5 Aluminium foil doubleside m²
6 Listplank GRC 30 cm m¹
7 Seng plat BJLS 30 lbr Rp 162,000.00
8 Nok zincalum m²
9 GRC listplank 20 cm m¹
10 Paku GRC bh
11 Flashing atap m¹

Bahan Elektrikal
Kabel listrik NYM 2 mx2.5 mm m Rp 10,000.00
Kabel listrik NYM 3x2.5 mm m Rp 12,500.00
Kabel CCTV coaxial RG-11 m Rp 6,000.00
Saklar tunggal standar bh Rp 11,000.00
Saklar seri standar bh Rp 14,750.00
Saklar tukar/hotel m
Stop kontak standar m Rp 12,800.00
Pipa listrik 5/8 PVC m
Blower 30 cm bh
Kabel tray m

Pipa PVC 1/2" bh Rp 40,000.00


Pipa PVC 3/4" bh Rp 11,000.00
Pipa PVC 1" bh Rp 21,000.00
Pipa PVC 1 1/2" bh Rp 31,000.00
Pipa PVC 2" bh Rp 36,000.00
Pipa PVC 2 1/2" bh Rp 42,000.00
Pipa PVC 3" bh Rp 14,448.00
Pipa PVC 4" bh Rp 78,000.00
Pipa PVC 6" m
U dicth 30 m
Tutup U ditch m

DAFTAR UPAH

1 Tukang Gali hr
2 Tukang Batu hr Rp 146,944.00
3 Tukang Kayu hr Rp 150,416.00
4 Tukang Kusen hr
5 Tukang B e s i hr Rp 144,256.00
6 Tukang C a t hr Rp 95,760.00
7 Tukang Listrik hr Rp 92,288.00
8 Tukang Plumbing hr
9 Kepala Tukang hr
10 Mandor hr Rp 246,176.00
11 P e k e r j a hr
12
13
n
n : 2019

Keterangan

warna abu - abu


warna abu - abu
RP. 72.000,-- per zak @ 50 kg

ex Roman
ex Roman
ex Roman
ex Roman
natural
ex Roman
ex Roman
ex Alexindo

SR 8901

0,50 x 10,00 m
0,50 x 10,00 m

Rp. 288.750,-- per 3,5 kg


Rp. 210.000,-- per 3,5 kg
Rp. 110.000,-- per 3,5 kg

0Ø 10 mm =Rp. 72.000,--/btg ex SNI


Ø 16 mm =Rp. 188.800,--/btg ex SNI
Rp. 252000,-- / 6 m
Rp. 409.500,-- / 6m

Rp. 610.000,-- / 6 m diambil rata rata


Rp. 1.465.000,-- / 6 m 17,500

- type CE 6 ex Toto
- type C 421 J ex Toto
- type TX 403 CSMCR ex Toto
- type L 34 ex Toto
- type TX 432 SG ex Toto
- type T 23 B13V7NB ex Toto
- type S 186 ex Toto
- type TX 703 AC ex Toto
- type TX 1 BN ex Toto
- ex Asahi Mas tebal 6 mm
- kaca temperd T = 12 mm

180 x 200 cm per m2


40 x 200 cm
70 x 200 cm
Wavin type AW
Wavin type AW
Wavin type AW
Wavin type AW
Wavin type D
Wavin type D
Wavin type D
Wavin type D
Wavin type D
ANALISA HARGA SATUAN (AHS)
TAHUN 2019

MA
No URAIAN PEKERJAAN
KOEF.

I. PEKERJAAN PERSIAPAN

Pembersihan 1 m2 lapangan dan peralatan


Upah
Pekerja 0.100
Mandor 0.050

1 m' Pengukuran & Pemasangan Bowplank


SNI 03 - 2835 - 2002
Bahan
- Kayu Kelas III 0.019
- Paku Biasa 0.020
- Kayu papan 3/20 0.007

Upah
- Pekerja 0.100
- Tukang Batu 0.100
- Kepala tukang 0.010
- Mandor 0.005

1 m2 Direksi Keet
SNI 03 - 2835 - 2002
Bahan
- Dolken Kayu 1.250
- Kayu Kelas III 1.030
- Paku Biasa 1.100
- Semen 0.700
- Pasir Pasang 0.150
- Pasir Beton 0.100
- Batu Koral/Kerikil 0.150
- Batu Bata 30.000
- seng plat BJLS 30 0.250
- Kaca Nako + Rangka 2.000
- Kaca Polos 5 mm 0.080
- kunci Tanam 0.150
- Multiplex 3.6 mm 0.060

Upah
- Tukang Kayu 2.000
- Tukang Batu 1.000
- Pekerja 2.000
- Kepala Tukang 0.300
- Mandor 0.050

1 m2 Gudang
SNI 03 - 2835 - 2002
Bahan
- Dolken Kayu 1.700
- Kayu Kelas III 0.210
- Paku Biasa 0.300
- Semen 0.210
- seng plat BJLS 30 1.500

Upah
- Pekerja 1.000
- Tukang Kayu 2.000
- Kepala Tukang 0.200
- Mandor 0.050

1 m2 Jalan Sementara Proyek


SNI 03 - 2835 - 2002
Bahan
- Batu Belah 15/20 0.275
- Batu split/pecah 5/7 0.030
- Pasir Pasang 0.010

Upah
- Pekerja 1.000
- Mandor 0.050

1 m' Pagar Pengaman Proyek


SNI 03 - 2835 - 2002
Bahan
- Dolken Kayu 1.250
- Semen 0.050
- Seng gelombang 1.200
- Pasir Beton 0.005
- Batu Koral 0.009
- Kayu Kelas III 0.072
- Paku Biasa 0.060
- Pengecatan bagian luar 0.450

Upah
- Pekerja 0.200
- Tukang Batu 0.400
- Kepala tukang 0.020
- Mandor 0.020

1 m3 Galian Tanah Biasa sedalam 2 m


SNI DT - 91- 0006 - 2007
Upah
- Pekerja 0.900
- Mandor 0.045

1 m3 Urugan Pasir t =10 cm


SNI DT - 91- 0006 - 2007
Bahan
- Pasir urug 1.200

Upah
- Pekerja 0.300
- Mandor 0.010

1 m3 Urugan Pasir putih


SNI DT - 91- 0006 - 2007
Bahan
- Pasir Bangka 1.200

Upah
- Pekerja 0.300
- Mandor 0.010
1 m3 Urugan sirdam 15 cm
SNI DT - 91- 0006 - 2007
Bahan
- Sirdam 1.200

Upah
- Pekerja 0.300
- Mandor 0.010

1 m3 Urugan Tanah Kembali


SNI DT - 91- 0006 - 2007
Upah
- Pekerja 0.192
- Mandor 0.019

1 m3 Urugan Tanah Padat


SNI DT - 91- 0006 - 2007
Bahan
- Tanah 1.000

Upah
- Pekerja 0.192
- Mandor 0.019

II. PEKERJAAN BETON


SNI DT - 91 - 0008 - 2007

1 m3 Lantai Kerja 1:3:5 ,Tebal = 5 cm


SNI - 2002
Bahan
- Pasir beton 0.520
- Semen PC 4.360
Koral 0.870

Upah
- Pekerja 1.650
- Tukang batu 0.250
- Kepala Tukang Batu 0.025
- Mandor 0.080

1 m2 Bekisting Batako

Bahan
- Batako 14.000
- Spesi ad. 1 : 5 0.127
- Peralatan bantu 1.000

Upah
- Pekerja 0.100
- Tukang batu 0.120
- Kepala Tukang batu 0.035
- Mandor 0.035

1 m3 Readymix K-350
SNI DT - 91 - 0008 - 2007
Bahan

- Beton Readymix K-300 1.030

Alat
- Concrete Pump 1.000

Upah
- Pekerja 0.700
- Tukang batu 0.250
- Kepala Tukang batu 0.100
- Mandor 0.100

Per 3 m' Kolom Praktis+Bekisting


1 m' Kolom Praktis+Bekisting(11 x11)cm
SNI DT - 91 - 0008 - 2007
Bahan
- Kayu klas III 0.002
Paku 5-12 cm 0.010
Besi Beton Polos 3.000
Kawat Bendrat 0.450
PC 4.000
Pasir Beton 0.006
Split 0.009
Upah
- Pekerja 0.180
- Tukang batu 0.020
Tukang Kayu 0.020
Tukang Besi 0.020
Kepala Tukang 0.006
- Mandor 0.009

1 kg Besi Beton
10 Kg Pembesian Polos atau Ulir
SNI DT - 91 - 0008 - 2007
Bahan
- Besi Beton Polos 10.500
- Kawat Beton 0.150

Upah
- Tukang besi 0.070
Pekerja 0.070
- Kepala tukang besi 0.007
Mandor 0.004

1 m2 Bekisting Balok Beton di pakai 2 kali


SNI DT - 91 - 0008 - 2007
Bahan
- Kayu rangka bekisting Kls III 0.040
- Multiplex 9 mm (2 kali pakai) 0.350
- Paku 5 cm-12 cm 0.400
- Dolken kayu galam (dia 8-10)cm,L= 4 m 2.000
- Minyak Bekisting 0.200
- Balok Kls II 0.018

Upah Tenaga
- Pekerja 0.660
- Tukang kayu 0.330
- Kepala Tukang kayu 0.033
- Mandor 0.033

1 m2 Bekisting Plat lantai dipakai 2 kali


SNI DT - 91 - 0008 - 2007
Bahan
- Kayu rangka bekisting Kls III 0.040
- Multiplex 9 mm (2 kali pakai) 0.350
- Paku 5 cm-12 cm 0.400
- Dolken kayu galam (dia 8-10)cm,L= 4 m 6.000
- Minyak Bekisting 0.200
- Balok Kls II 0.015

Upah Tenaga
- Pekerja 0.660
- Tukang kayu 0.330
- Kepala Tukang kayu 0.033
- Mandor 0.033

1 m2 Bekisting Kolom dipakai 2 kali


SNI DT - 91 - 0008 - 2007
Bahan
- Kayu rangka bekisting Kls III 0.040
- Multiplex 9 mm (2 kali pakai) 0.350
- Paku 5 cm-12 cm 0.400
- Dolken kayu galam (dia 8-10)cm,L= 4 m 2.000
- Minyak Bekisting 0.200
- Balok Kls II 0.015

Upah Tenaga
- Pekerja 0.660
- Tukang kayu 0.330
- Kepala Tukang kayu 0.033
- Mandor 0.033

1 m2 Plat Bondex

Bahan
- Bondex 1.050
- Peralatan bantu 1.000

Upah pasang
- Pekerja 0.200
- Tukang Batu 0.250
- Kepala Tukang batu 0.050
- Mandor 0.050

III PEKERJAAN DINDING


SNI DT - 91 - 0009- 2007

1 m2 Pasangan dinding Bata ringan)

Bahan
- Bata Ringan 1.100
- Semen Portland PM 100 3.150

Upah
- Pekerja 0.300
- Tukang batu 0.100
- Kepala Tukang batu 0.010
- Mandor 0.015

1 m2 Pasangan Bata Merah 1/2 bata ad. 1 : 3

Bahan
- Semen Portland 14.370
- Pasir Pasang 0.040
- Bata Merah 70.000

Upah
- Pekerja 0.300
- Tukang Batu 0.100
- Kepala Tukang Batu 0.010
- Mandor 0.015

1 m2 Pasangan Bata Merah 1/2 bata ad. 1 : 5

Bahan
- Semen Portland 9.680
- Pasir Pasang 0.040
- Bata Merah 70.000

Upah
- Pekerja 0.300
- Tukang Batu 0.100
- Kepala Tukang Batu 0.010
- Mandor 0.015

1 m2 Plesteran Dinding ad 1 : 3, tebal = 20 mm

Bahan
- Semen Portland 10.368
- Pasir pasang 0.031

Upah `
- Pekerja 0.260
- Tukang batu 0.200
- Kepala Tukang batu 0.020
- Mandor 0.013

1 m2 Plesteran Dinding ad 1 : 5, tebal = 20 mm

Bahan
- Semen Portland 6.920
- Pasir pasang 0.035

Upah `
- Pekerja 0.260
- Tukang batu 0.200
- Kepala Tukang batu 0.020
- Mandor 0.013

1 m2 Acian Biasa

Bahan
- Semen Portland 3.250

Upah
- Pekerja 0.150
- Tukang batu 0.100
- Kepala Tukang batu 0.010
- Mandor 0.008

1 m2 Acian PM 300 untuk Beton

Bahan
- Semen Portland PM 300 3.250
Upah
- Pekerja 0.150
- Tukang batu 0.100
- Kepala Tukang batu 0.010
- Mandor 0.008

1 m2 Plesteran PM 200
Bahan
- Semen PM 200 20.000

Upah
- Pekerja 0.150
- Tukang batu 0.100
- Kepala Tukang batu 0.010
- Mandor 0.008

IV PEKERJAAN PENUTUP LANTAI DAN DINDING


SNI DT - 91 - 0012- 2007

1 m Pasangan Plint Lantai keramik 5 cm


SNI DT - 91 - 0012 - 2007
Bahan
- Plint keramik 5 cm 5.300
- Semen Portland 1.140
- Pasir Pasang 0.003
- Semen Warna 0.100

Upah
- Pekerja 0.090
- Tukang Batu 0.090
- Kepala Tukang Batu 0.009
- Mandor 0.005

1 m2 Pasangan Lantai Keramik 40 x 40 EX. Roman


SNI DT - 91 - 0012 - 2007
Bahan
- Lantai Keramik 40 x 40 1.050
- Semen Portland 0.430
- Pasir Pasang 0.0215
- Semen Warna 1.300

Upah
- Pekerja 0.620
- Tukang Batu 0.350
- Kepala Tukang Batu 0.035
- Mandor 0.030

1 m2 Pasangan dinding keramik Toilet 20 x 25 ex. Roman


SNI DT - 91 - 0012 - 2007
Bahan
- Lantai Keramik 25 x 20 1.050
- Semen Portland 10.000
- Pasir Pasang 0.045
- Semen Warna 1.500

Upah
- Pekerja 0.620
- Tukang Batu 0.350
- Kepala Tukang Batu 0.035
- Mandor 0.030

1 m2 Pasangan Lantai keramik 20 x 20 ex.Roman


SNI DT - 91 - 0012 - 2007
Bahan
- Lantai Keramik 20 x 20 1.050
- Semen Portland 10.400
- Pasir Pasang 0.045
- Semen Warna 1.620

Upah
- Pekerja 0.620
- Tukang Batu 0.350
- Kepala Tukang Batu 0.035
- Mandor 0.030

1 m Pasangan Nozing Tangga (10 x20 ) cm


SNI DT - 91 - 0012 - 2007
Bahan
- Nozing tangga 5.300
- Semen Portland 1.140
- Pasir Pasang 0.003
- Semen Warna 0.025

Upah
- Pekerja 0.090
- Tukang Batu 0.090
- Kepala Tukang Batu 0.009
- Mandor 0.005

1 m2 Pasangan LantaiPaving 20 x 20
Bahan
- Paving block 20/20 1.050
- Pasir Pasang 0.045

Upah
- Pekerja 0.025
- Tukang Batu 0.125
- Kepala Tukang Batu 0.050
- Mandor 0.050

V. PEKERJAAN PENGECATAN
SNI DT - 03 - 2408-1991/SK SNI T-09-1990-F, DAN ANALISA BOW 1921

1m2 Cat Tembok Luar Baru dengan cat weathershield ( 1 lapis cat dasar/sealer, 2 lapis cat penutup
SNI DT - 03 - 2408-1991/SK SNI T-09-1990-F, DAN ANALISA BOW 1921
Bahan
- Filler/Sealer 0.150
- Cat Tembok Elastomeric 0.360
- Roll Cat 0.100
- Amplas 0.333

Upah
- Pekerja 0.028
- Tukang Cat 0.042
- Kepala Tukang 0.004
- Mandor 0.003

1m2 Cat Tembok Dalam Baru Setara DULUX / ICI


SNI DT - 03 - 2408-1991/SK SNI T-09-1990-F, DAN ANALISA BOW 1921
Bahan
- Plamir 0.100
- Sealer 0.100
- Cat Penutup Standard 0.260

Upah
- Pekerja 0.023
- Tukang Cat 0.063
- Kepala Tukang 0.006
- Mandor 0.003

1m2 Cat Besi cat anti karat ( 1 lapis cat dasar/meni, 2 lapis cat penutup)
SNI DT - 03 - 2408-1991/SK SNI T-09-1990-F, DAN ANALISA BOW 1921
Bahan
- Cat Besi Anti Karat/Zincromat 0.350
- Meni Besi 0.167
Plamuur 0.083
Thinner 0.700
Kuas 0.050
Amplas 0.500

Upah
- Pekerja 0.060
- Tukang Cat 0.006
- Kepala Tukang 0.023
- Mandor 0.008

1m2 Floor Hardener


SNI -2002
Bahan
- Floor hardener 5.000

Upah
- Pekerja 0.120
- Tukang Cat 0.120
- Kepala Tukang 0.012
- Mandor 0.006

1m2 Coating Waterproofing


SNI -2002
Bahan
- Waterproofing 0.750

Upah
- Pekerja 0.060
- Tukang Cat 0.060
- Kepala Tukang 0.006
- Mandor 0.003

1m2 Screed Waterproofing


SNI -2002
Bahan
- PC 13.620
- Pasir Pasang 0.027
- Kawat ayam 1.100

Upah
- Pekerja 0.260
- Tukang Cat 0.200
- Kepala Tukang 0.020
- Mandor 0.013

VI PEKERJAAN BESI DAN ALUMUNIUM


SNI DT - 91 - 0014- 2007

Pas. 1 kg Rangka Kuda -Kuda Besi pipa


SNI DT - 91 - 0014 - 2007
Bahan
- Besi Wf 1.150
- Kawat las 0.020

Upah
- Pekerja 0.036
- Tukang Las 0.040
- Kepala Tukang 0.006
- Mandor 0.003

1 m Kusen Pintu Alluminium


SNI DT - 91 - 0014 - 2007
Bahan
- profil alluminium 1.100
- skrup fixer 2.000
- sealant 0.060

Upah
- Pekerja 0.043
- Tukang Besi 0.043
- Kepala Tukang 0.004
- Mandor 0.002

VII PEKERJAAN LANGIT-LANGIT


SNI DT - 91 - 0013- 2007

1 m2 Pasangan Langit-langit Gypsum board, tebal 9 mm


SNI DT -91 - 0013 - 2007
Bahan
- Gypsum Board (120 x 240 x 9)mm + rangka Holow 0.364
- Angle bracket PN 220 1.000
- Main runner PN 400 , l = 3.60 m 0.250
- Cross tee PN 402 , l = 1.20 m 1.500
- Suspension rod PN 409 Ø 3 mm x 2.40 m 1.000
- Suspension clip PN 410 1.000

Upah
- Pekerja 0.500
- Tukang 0.500
- Kepala Tukang 0.050
- Mandor 0.025

1 m2 Pasangan Langit-langit Calsiboard 6mm


SNI DT -91 - 0013 - 2007
Bahan
- Calsiboard 6mm+ rangka Holow 0.364
- Angle bracket PN 220 1.000
- Main runner PN 400 , l = 3.60 m 0.250
- Cross tee PN 402 , l = 1.20 m 1.500
- Suspension rod PN 409 Ø 3 mm x 2.40 m 1.000
- Suspension clip PN 410 1.000

Upah
- Pekerja 0.500
- Tukang 0.500
- Kepala Tukang 0.050
- Mandor 0.025

1 m1 Drop Ceilling Gypsum board, tebal 9 mm

Bahan
- Gypsum Board (120 x 240 x 9)mm + rangka Holow 0.278
- Angle bracket PN 220 0.500
- Main runner PN 400 , l = 3.60 m 0.125
- Cross tee PN 402 , l = 1.20 m 0.750
- Suspension rod PN 409 Ø 3 mm x 2.40 m 0.500
- Suspension clip PN 410 0.500

Upah
- Pekerja 0.250
- Tukang 0.250
- Kepala Tukang 0.025
- Mandor 0.013
1 m2 Pekerjaan dinding flat gipsum jayaboard 9mm rangka hollow (2 muka/double sided)
Bahan
- Gypsum Board (120 x 240 x 9)mm + rangka Holow 0.600
- Main runner PN 400 , l = 3.60 m 0.520
- Cross tee PN 402 , l = 1.20 m 1.140

Upah
- Pekerja 0.250
- Tukang 0.250
- Kepala Tukang 0.025
- Mandor 0.013

VIII PEKERJAAN KHUSUS/NON STANDARD


ANALISA BOW 1921

1 m2 Dinding Partis Double Gypsum 12 mm


NON STANDARD
Bahan
- Metal wall stud 35mm x 40mm 2.00
- Metal wall track 30mm x 40mm 0.75
- Paku rivet 4.00
- Sekrup 6x1-1,5 8.00
- Gypsumboard 120x240 cm 12 mm 0.75
- Textile tape 0.24
- Compound gypsum 0.12
- Sekrup gypsum 24.00
- Amplas 0.50

Upah
- Pekerja 0.200
- Tukang Gypsum 0.600
- Kepala Tukang 0.060
- Mandor 0.100

1 m2 Dinding Partis Multiplek 9 mm satu muka

Bahan
- Metal wall stud 35mm x 40mm 2.00
- Metal wall track 30mm x 40mm 0.75
- Paku rivet 4.00
- Sekrup 6x1-1,5 8.00
- Triplek 120x240 cm 9 mm 0.38
- Textile tape 0.24
- Compound gypsum 0.12
- Sekrup gypsum 24.00
- Amplas 0.50

Upah
- Pekerja 0.200
- Tukang Gypsum 0.600
- Kepala Tukang 0.060
- Mandor 0.100

1 m2 Pasang Timah Hitam


NON STANDARD
Bahan
- Timah hitam (PB) 2 mm 27.50
- Lem aibon 0.30
- Amplas baut dan lain - lain 1.00

Upah
- Pekerja 1.500
- Tukang Kaca 0.150
- Kepala Tukang 0.015
- Mandor 0.015

1 m2 Pasang pelapis dinding karet


NON STANDARD
Bahan
- Pasang karet 1.10
- Lem aibon 0.30
- Amplas baut dan lain - lain 1.00

Upah
- Pekerja 1.500
- Tukang Kaca 0.150
- Kepala Tukang 0.015
- Mandor 0.015

1 m2 Pekerjaan pelapis dinding stainless stell1 muka t,2mm rangka baja propil CNP
NON STANDARD
Bahan
- Besi baja kanal profil CNP/ UNP 22.410
- plat stainlessteel plate t:2mm 100.000
- Zinchromate 2.400
Alat bantu 0.580

Upah
- Pekerja/kenek 2.010
- Tukang besi/ plumbing 2.281
- Kepala tukag 0.351
- Mandor/pengawas 0.351

1 m' Pekerjaan Handrail besi galvanis dia 2" finish cat (tangga darurat)
NON STANDARD
Bahan
- Besi baja kanal profil CNP/ UNP 7.000
- Zinchromate 0.100
- Alat bantu 0.100

Upah
- Pekerja/kenek 0.600
- Tukang besi/ plumbing 1.500
- Kepala tukang 0.288
- Mandor/pengawas 0.288

1 m' Pekerjaan Railling besi galvanis dia 2" finish cat (tangga darurat)
NON STANDARD
Bahan
- Besi baja kanal profil CNP/ UNP 20.000
- Besi plat 3.000
- Besi tulangan beton ulir 6.000
Zinchromate 0.100
Alat bantu 0.100

Upah
- Pekerja/kenek 0.840
- Tukang besi/ plumbing 1.980
- Kepala tukang 0.288
- Mandor/pengawas 0.288

1 m'Pekerjaan Handrail stainless steel dia 2" (tangga publik)


NON STANDARD
Bahan
- Pipa stainless steel dia 2" 2.380
- Alat bantu 0.100

Upah
- Pekerja/kenek 0.600
- Tukang besi/ plumbing 1.500
- Mandor/pengawas 0.250

1 m'Pekerjaan Handrail stainless steel dia 2"+Dudukan Kayu (tangga publik)


NON STANDARD
Bahan
- Pipa stainless steel dia 2" 13.000
- Alat bantu 0.500

Upah
- Pekerja/kenek 1.200
- Tukang besi/ plumbing 3.000
- Mandor/pengawas 0.500
1 m'Pekerjaan railing stainless steel dia 2"
NON STANDARD
Bahan
- Pipa stainless steel dia 2" 13.000
- Alat bantu 0.100

Upah
- Pekerja/kenek 0.840
- Tukang besi/ plumbing 1.980
- Mandor/pengawas 0.288

1 m2 Pasangan dinding batu tempel andesit


NON STANDARD
Bahan
- Batu tempel 1.050
- Pasir Pasang 0.035
- Semen Portland 11.750
- Coating +Pemotongan Pola 1.000
Upah
- Pekerja 0.620
- Tukang Batu 0.350
- Kepala Tukang Batu 0.035
- Mandor 0.030

1 m2 Pasangan Atap Zincalumunium gelombang

Bahan
- Atap Zincalume Tebal 0.5 1.050
- Paku haak Panjang 4.000
Upah
- Pekerja 0.075
- Tukang Kayu 0.375
- Kepala Tukang Kayu 0.008
- Mandor 0.005

1 m2 Pasangan Atap transparant

Bahan
- Atap Zincalume Tebal 0.5 1.050
- Paku haak Panjang 4.000

Upah
- Pekerja 0.075
- Tukang Kayu 0.375
- Kepala Tukang Kayu 0.008
- Mandor 0.005

1 m' Pasangan Nok Atap Zincalumunium

Bahan
- Nok Atap Zincalume 0.833
- Paku haak Panjang 4.000

Upah
- Pekerja 0.038
- Tukang Kayu 0.188
- Kepala Tukang Kayu 0.004
- Mandor 0.003

1 m' Pasangan listplank GRC

Bahan
- Lisplank GRC 30 cm 2.200
- Paku haak Panjang 6.000

Upah
- Pekerja 0.100
- Tukang Kayu 0.200
- Kepala Tukang Kayu 0.020
- Mandor 0.005
1 m² Pasangan aluminium foil

Bahan
- Aluminium foil double sheet 1.100
- Kawat ayam 1.100

Upah
- Pekerja 0.100
- Tukang Kayu 0.200
- Kepala Tukang Kayu 0.000
- Mandor 0.000

1 m¹ Pasangan Flasing Atap

Bahan
- Flashing atap 1.100
- Paku haak Panjang 4.000

Upah
- Pekerja 0.050
- Tukang Kayu 0.100
- Kepala Tukang Kayu 0.010
- Mandor 0.003

1 set Pasang Kitchen sink ex. TK-KS2015 (teka) u/ cuci alat


(Pemasangan Kering)
Bahan
- Kitchen sink ex. TK-KS2015 (teka) 1.000

Upah
- Terpasang 1.000

1 bh Pasang kloset jongkok

Bahan
- kloset jongkok CE 6 ex Toto 1.000
- Pasir pasang 0.010
- Semen abu - abu 10.000
- Batu bata 20.000

Upah Tenaga
- Pekerja 0.200
- Tukang batu 0.300
- Kepala Tukang 0.030
- Mandor 0.010

1 bh Pasang kloset duduk

Bahan
- kloset duduk CW 420 J 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 3.300
- Tukang batu 1.100
- Kepala Tukang 0.001
- Mandor 0.160

1 bh Pasang kloset duduk

Bahan
- kloset duduk CW 826 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 3.300
- Tukang batu 1.100
- Kepala Tukang 0.001
- Mandor 0.160

1 bh Pasang wastafel gantung

Bahan
- wastafel L 220 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 1.500
- Tukang batu 0.150
- Kepala Tukang 0.075
- Mandor 0.015

1 bh Pasang wastafel meja

Bahan
- wastafel LW 830 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 2.000
- Tukang batu 0.200
- Kepala Tukang 0.100
- Mandor 0.020

1 bh Pasang urinoar

Bahan
- urinoar U 57 M 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 2.000
- Tukang batu 0.200
- Kepala Tukang 0.100
- Mandor 0.020

1 bh Pasang service sink

Bahan
- sink SKW 322 B 1.000
- perlengkapan 6 % 6%

Upah Tenaga
- Pekerja 2.000
- Tukang batu 0.200
- Kepala Tukang 0.100
- Mandor 0.020

1 m3 Beton pondasi

Bahan
- Beton K 300 1.050
- Pembesian 135.00
- Bekisting batako 6.00

Upah Tenaga
- Beton K 300 1.050
- Pembesian 135.00
- Bekisting batako 6.00
1 m3 Beton sloof

Bahan
- Beton K 300 1.050
- Pembesian 220.00
- Bekisting batako 8.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 220.00
- Bekisting batako 8.00

1 m3 Beton kolom

Bahan
- Beton K 300 1.050
- Pembesian 195.00
- Bekisting triplek 10.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 195.00
- Bekisting batako 10.00

1 m3 Beton balok

Bahan
- Beton K 300 1.050
- Pembesian 185.00
- Bekisting batako 10.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 185.00
- Bekisting batako 10.00

1 m3 Beton plat lantai atas

Bahan
- Beton K 300 1.050
- Pembesian 110.00
- Bekisting bondex 8.00
Upah Tenaga
- Beton K 300 1.000
- Pembesian 110.00
- Bekisting bondex 8.00

1 m3 Beton plat lantai dasar 10 cm

Bahan
- Beton K 300 1.050
- Pembesian 110.00
- Plastik cor 10.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 110.00
- Bekisting bondex 10.00

1 m3 Beton penahan tanah

Bahan
- Beton K 300 1.050
- Pembesian 150.00
- Bekisting triplek 8.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 150.00
- Bekisting triplek 8.00

1 m3 Beton tangga

Bahan
- Beton K 300 1.050
- Pembesian 150.00
- Bekisting triplek 8.00

Upah Tenaga
- Beton K 300 1.000
- Pembesian 150.00
- Bekisting bondex 8.00

Pemasangan 1 m3 batu kosong (anstamping)


Bahan
Batu belah 1.2000
Pasir urug 0.4320

Upah Tenaga
Pekerja 0.7800
Tukang batu 0.3900
Kepala Tukang 0.0390
Mandor 0.0390

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP

Bahan
Batu belah 1.200
Semen abu - abu 163.000
Pasir pasang 0.520

Upah Tenaga
Pekerja 1.5000
Tukang batu 0.7500
Kepala Tukang 0.0750
Mandor 0.0750

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP

Bahan
Batu belah 1.200
Semen abu - abu 117.000
Pasir pasang 0.561

Upah Tenaga
Pekerja 1.5000
Tukang batu 0.7500
Kepala Tukang 0.0750
Mandor 0.0750

1 m Pasangan kanstein
Bahan
- Semen Portland 14.370
- Pasir Pasang 0.040
- Kanstein mulut air 15.30.40. 2.500
Upah
- Pekerja 0.300
- Tukang Batu 0.100
- Kepala Tukang Batu 0.100
- Mandor 0.015

Memasang 1 m2 Jalan Aspal Hotmix

Kebutuhan
Lapisan Pasir Urug darat 15 cm padat 1.000
Lapisan Pasir Pasang 20 cm padat 1.000
Terpasang(Bahan +Upah)
Lapisan Makadam 15 cm padat 1.000
Lapisan Sirtu 15 cm padat 1.000
Lapisan Giling Matang 5 cm 1.000
Lapisan Hotmix tebal 5 cm 97-100 % 1.000
Memasang 1 m2 pelapisan Jalan Aspal Hotmix
Terpasang(Bahan +Upah)
Lapisan Giling Matang 5 cm 1.000
Lapisan Hotmix tebal 5 cm 97-100 % 1.000

A.6.2.1Instalasi 1 titik listrik/stop kontak kabel NYM 2 x2.5 mm


A Tenaga Kerja
Pekerja OH
Tukang listrik OH
Kepala Tukang OH
Mandor OH
Jumlah
B Bahan
Kabel listrik NYM 2x2.5 mm m1
Pipa listrik 5/8 PVC m1
Terminal kabel bh
J

A.6.2.1Instalasi 1 titik listrik/stop kontak kabel NYM 3x2.5 mm


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Kabel listrik NYM 3x2.5 mm m
Pipa listrik 5/8 PVC m
Terminal kabel bh
J

Instalasi 1 titik CCTV kabel coaxial RG-11 + power


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Kabel CCTV coaxial RG-11 m
Pipa listrik 5/8 PVC m
Terminal kabel bh
J

Instalasi 1 titik Blower


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Kabel listrik NYM 3x2.5 mm m
Blower d 30 bh
Pipa listrik 5/8 PVC m
Terminal kabel bh
J

Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 1/2" m
Perlengkapan 35 % bh
J

Pemasangan 1 m' pipa PVC tipe AW diameter 3/4 "


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 3/4" m
Perlengkapan 35 % bh
J

Pemasangan 1 m' pipa PVC tipe AW diameter 1 "


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 1" m
Perlengkapan 35 % bh
J

Pemasangan 1 m' pipa PVC tipe AW diameter 1 1/2 "


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 1 1/2" m
Perlengkapan 35 % bh
J

Pemasangan 1 m' pipa PVC tipe D diameter 3 "


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 3 " m
Perlengkapan 35 % bh
J

Pemasangan 1 m' pipa PVC tipe D diameter 4 "


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
Pipa PVC 4 " m
Perlengkapan 35 % bh
J

Pemasangan 1 m' saluran terbuka U ditch 30 cm


A Tenaga Kerja
Pekerja oh
Tukang listrik oh
Kepala Tukang oh
Mandor oh
Jumlah
B Bahan
U ditch 30 cm m
Pasir pasang m
J
MATERIAL + UPAH

HARGA SATUAN JUMLAH HARGA


SAT. ( Rp ) ( Rp )

116,928
246,176

m3
kg
m3

oh
oh
oh
oh

btg
m3
kg
zak
m3
m3
m3
bh
lbr
set
m2
set
lbr

oh
oh
oh
oh
oh

btg
m3
kg
zak
lbr

oh
oh
oh
oh

m3
m3
m3

oh
oh

btg
zak
lbr
m3
m3
m3
kg
kg

oh
oh
oh
oh

oh
oh

mᶟ

oh
oh

mᶟ

oh
oh
m^3

oh
oh

oh
oh

m3

oh
oh

m3
zak
m3

oh
oh
oh
oh

bh
m2
Ls

Hari
Hari
Hari
Hari

m3

m3

oh
oh
Hari
oh

m^3
kg
kg
kg
kg
m3
m3
oh
oh
oh
oh
oh
oh

Kg
Kg

oh
oh
oh
oh

m^3
lbr
kg
btng
ltr
m3

oh
oh
oh
oh
m^3
lbr
kg
btng
ltr
m3

oh
oh
oh
oh

m^3
lbr
kg
btng
ltr
m3

oh
oh
oh
oh

m2
Ls

Hari
Hari
Hari
Hari
m2
kg

oh
oh
oh
oh

kg
M3
bh

oh
oh
oh
oh

kg
M3
bh

oh
oh
oh
oh
kg
m3

oh
oh
oh
oh

kg
m3

oh
oh
oh
oh

kg

oh
oh
oh
oh

kg

oh
oh
oh
oh
kg

oh
oh
oh
oh

bh
kg
M3
kg

oh
oh
oh
oh

m2
Zak
M3
kg

oh
oh
oh
oh
m2
kg
M3
kg

oh
oh
oh
oh

m2
kg
M3
kg

oh
oh
oh
oh

bh
kg
M3
kg

oh
oh
oh
oh
m2
M3

oh
oh
oh
oh

er, 2 lapis cat penutup)

kg
kg
bh
Lbr

oh
oh
oh
oh

kg
kg
kg

oh
oh
oh
oh
kg
kg
kg
Ltr
bh
Lbr

oh
oh
oh
oh

kg

oh
oh
oh
oh

kg

oh
oh
oh
oh

kg
m3
m2
oh
oh
oh
oh

kg
kg

oh
oh
oh
oh

m'
bh
tube

oh
oh
oh
oh

lbr
bh
btg
btg
kg
bh

oh
oh
oh
oh

lbr
bh
btg
btg
kg
bh

oh
oh
oh
oh

lbr
bh
btg
btg
kg
bh

oh
oh
oh
oh
lbr
btg
btg

oh
oh
oh
oh

m'
m'
bh
bh
lbr
roll
zak
bh
lbr

oh
oh
oh
oh

m'
m'
bh
bh
lbr
roll
zak
bh
lbr

oh
oh
oh
oh

kg
kg
ls

oh
oh
oh
oh

m2
kg
ls

oh
oh
oh
oh

kg
cm2
kg
set

oh
oh
oh
oh

kg
kg
set

oh
oh
oh
oh

kg
kg
kg
kg
set

oh
oh
oh
oh

m'
set
oh
oh
oh

m'
set

oh
oh
oh

m'
set

oh
oh
oh

m2
m3
kg
ls

oh
oh
oh
oh

m2
bh
oh
oh
oh
oh

m2
bh

oh
oh
oh
oh

m1
bh

oh
oh
oh
oh

m
bh

oh
oh
oh
oh

oh
oh
oh
oh

m1
bh

oh
oh
oh
oh

set

set

bh
m3
kg
bh

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

bh
m3

oh
oh
oh
oh

m3
kg
m2

m3
kg
m2
m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2
m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2
m3
m3

oh
oh
oh
oh

m3
kg
m3

oh
oh
oh
oh

m3
kg
m3

oh
oh
oh
oh

kg
M3
bh
oh
oh
oh
oh

m2
m2

m2
m2
m2
m2

m2
m2

0.3000 0.00
0.3000 0.00
0.0600 0.00
0.0060 0.00
Jumlah Harga Tenaga Kerja 0.00

10.0000 0.00
4.0000 0.00
1.0000 0.00
Jumlah Harga Bahan 0.00
0.00

0.3000 0.00
0.3000 0.00
0.0600 0.00
0.0060 0.00
Jumlah Harga Tenaga Kerja 0.00
10.0000 12,500.00 125,000.00
4.0000 - 0.00
1.0000 - 0.00
Jumlah Harga Bahan 125,000.00
125,000.00

0.3000 0.00
0.3000 0.00
0.0600 0.00
0.0060 0.00
Jumlah Harga Tenaga Kerja 0.00

10.0000 6,000.00 60,000.00


4.0000 - 0.00
1.0000 - 0.00
Jumlah Harga Bahan 60,000.00
60,000.00

0.3000 - 0.00
0.3000 - 0.00
0.0600 - 0.00
0.0060 - 0.00
Jumlah Harga Tenaga Kerja 0.00

10.0000 12,500.00 125,000.00


1.0000 - 0.00
4.0000 - 0.00
1.0000 - 0.00
Jumlah Harga Bahan 125,000.00
125,000.00

0.0360 - 0.00
0.0600 - 0.00
0.0060 - 0.00
0.0020 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 40,000.00 48,000.00


0.3500 40,000.00 14,000.00
Jumlah Harga Bahan 62,000.00
62,000.00

0.0360 - 0.00
0.0600 - 0.00
0.0060 - 0.00
0.0020 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 11,000.00 13,200.00


0.3500 11,000.00 3,850.00
Jumlah Harga Bahan 17,050.00
17,050.00

0.0360 - 0.00
0.0600 - 0.00
0.0060 - 0.00
0.0020 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 21,000.00 25,200.00


0.3500 21,000.00 7,350.00
Jumlah Harga Bahan 32,550.00
32,550.00

0.0360 - 0.00
0.0600 - 0.00
0.0060 - 0.00
0.0020 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 31,000.00 37,200.00


0.3500 31,000.00 10,850.00
Jumlah Harga Bahan 48,050.00
48,050.00

0.0810 - 0.00
0.1350 - 0.00
0.0135 - 0.00
0.0040 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 14,448.00 17,337.60


0.3500 14,448.00 5,056.80
Jumlah Harga Bahan 22,394.40
22,394.40

0.0810 - 0.00
0.1350 - 0.00
0.0135 - 0.00
0.0040 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.2000 78,000.00 93,600.00


0.3500 78,000.00 27,300.00
Jumlah Harga Bahan 120,900.00
120,900.00

1.0000 - 0.00
0.3000 - 0.00
0.0600 - 0.00
0.0600 - 0.00
Jumlah Harga Tenaga Kerja 0.00

1.1000 - 0.00
0.0250 232,960.00 5,824.00
Jumlah Harga Bahan 5,824.00
5,824.00