Académique Documents
Professionnel Documents
Culture Documents
Essentials
Proudly presented by:
Stamford Global
&
1
Welcome
• Orientation
• Who is Stamford?
Organize premium professional workshop in Central
and Eastern Europe
Working with internationally recognized experts from
the Global Marketplace
Wide range of exclusive events across several verticals
2
Your Trainer
• Mr Roger Wild
Managing Director of Project Associates UK
PMP
MCIOB
PRINCE2 Practitioner
Over 25 years experience managing projects
Email : roger@project-associates.co.uk
3
Project Management Essentials
Course Objectives :
4
Agenda
5
Introductions
6
Unit 1 ~ Project Management Concepts
Objectives:
7
Project Definitions
8
Projects vs Programs
Start Finish
PROJECT
Handover to operations
Business as usual
or operational work
9
Project vs Product Life Cycle
Product Life Cycle
Business
Operations
Strategy
Tools
People Processes
11
Useful References
Project Management Institute
PMBOK ~ “Project Management Body of Knowledge”
OPM3 ~ “Organizational Project Management Maturity Model”
www.pmi.org
13
Why do projects fail?
¾ Organisational factors
¾ Poor communications
14
The Triple Constraints
“Stakeholders”
Scope / Quality
Effective project management is balancing the expected scope, costs and time
in a way which fulfils and satisfies customer’s requirements
15
SMART Objectives
An objective is something toward which work is to be directed:
A strategic position to be attained
A purpose to be achieved
A result to be obtained
A product to be produced
A service to be performed
Project Management
PMI’s PMBOK Guide describes knowledge Body of Knowledge
18
Phases & Gate Reviews
19
Project Management Process Groups
Application of the project management processes to a project is iterative
and many processes are repeated and revised during the project lifecycle.
Project teams must select appropriate processes within the five “Process Groups”
that are required to meet the project objectives.
The five process groups are NOT project phases
20
Process Group Triangle
Process groups are linked by the objectives they produce, the output of one process
generally becomes an input to another process or is a project deliverable.
22
Three Major Documents
Formally authorises the project
23
Project Integration Management
Integration is primarily concerned with effectively integrating the appropriate
processes, from the five “Project Management Process Groups”
24
PRINCE2
PRINCE covers management of the project and management
of the resources involved in carrying out the activities of the project.
PRojects
IN
Controlled
Environments
25
History of PRINCE2
26
Eight Major Processes of PRINCE2
Directing a Project
Initiating
a Project
Managing
Starting up Controlling Closing a
Stage
a Project a Stage Project
Boundaries
Managing
Product
Delivery
Planning
27
Components of PRINCE2
Configuration Organisation
Management
Quality in a
project Plans
Environment
Management of Controls
Risk
28
Benefits of using PRINCE2
29
Unit 2 ~ Organisations & Projects
Objectives:
30
Project Human Resource Management
Roles Staffing
and Management
Responsibilities Plan
31
Cross-functional project teams
Functional Projectized
Organisation Organisation
Matrixed
Organisation
Project Coordination ?
9 Regulators…
33
Project Relationships
“The project management team must identify stakeholders, determine their
requirements / expectations and manage their influence to ensure a successful project”
Project
Sponsor
Project
Manager
Project Management
Team
Project Team
Project Stakeholders
(Source: PMBOK Guide Third Edition ~ p24)
34
Project Manager as an Influencer
“Example is not the main thing in influencing others. It is the only thing.”
~ Albert Schweitzer
Project
Sponsor
Other Senior
Stakeholders Management
PROJECT
MANAGER
Project Customer
Team / User
PMO
There are two things people want more than sex and money… recognition and praise
~ Mary Kay Ash
35
Stakeholder Map
Stakeholder Power / Motivation / Desires Actions to be taken Status
Influence
36
Effective Communications
What are the most effective forms of communication?
9 One to ones
9 Telephone
9 Teleconferencing / Videoconferencing
9 MBWA
9 Management reports
Communications Change
Management Request
Plan
Issues
Log
Performance
Reports
9 Project Charter
9 Project Schedules
9 Status/Progress Reports
9 Change Requests
“The project team is comprised of the people who have assigned roles
and responsibilities for completing the project
(Source: PMBOK Guide Third Edition ~ p199)
41
What is a Team?
A group of individuals with a common goal?
9 Complementary skills
9 Mutual accountability
Storming
Issues:
Power, control,
and influence
Stage 3 Stage 1
Norming Forming
Issues: Issues:
Affection and Inclusion and
Intimacy trust
Stage 4 Stage 5
Performing Adjourning
Issues: Issues:
No major issues Loss and
separation
B.W. Tuckman and M.A.C. Jensen. “Stages of Small Group Development.” Group and Organizational Studies, Volume 2.
Copyright © 1977 by Sage Publications.
43
Roles & Responsibilities
The following should be addressed when defining roles and responsibilities
9 Role ~ label describing the portion of a project for which you are accountable
9 Authority ~ right to apply project resources, make decisions and sign approvals
44
Project Roles
“Other
Project Management Stakeholders”
Office (PMO)
“Manages on a
Project Manager
day to day basis”
A R I I
Phases or WP’s?
46
Energizer
The Project Manager must fill several roles in the completion of a project.
9 Identify the key activities you expect the Project Manager to perform.
47
Role of the Project Manager
Project Manager (PM) ~ The person responsible for managing the project
(Source: PMBOK Guide Third Edition ~ p26)
48
Project Sponsor Role
Sponsor ~ The person or group that provides the financial resources, in cash
or in kind, for the project
(Source: PMBOK Guide Third Edition ~ p376)
9 Arbitrating on conflicts
49
Project Management Office (PMO)
The PMO is an organisational unit to centralise and coordinate
the management of projects under its domain.
May oversee the management of projects, programs or a combination of both.
50
Staffing Management Plan
A subset of the “Project Management Plan”
9 Staff acquisition ~ internal or external, and how will you get them
51
Acquire the Project Team
The process of obtaining the human resources
9 Virtual Teams ~ groups of people with a shared goal, who fulfill their roles
with little or no time spent meeting face to face.
52
Develop Project Team
Improving the competencies and interaction of team members to
53
Conflict Management
Successful conflict management results in greater productivity and
positive working relationships.
9 Confronting (Problem Solving) ~ parties working together to solve the real problem
54
Unit 3 ~ Project Initiation
Objectives:
¾ Stimuli for new projects
¾ Project selection
55
Energizer
You have been asked to lead a new project that shows great promise for
your business unit, it aligns well with corporate strategy!
9 Identify the key elements that you are typically concerned about
56
Where do projects originate?
Market demand
Technological advance
Product obsolescence
?
Chartering a project, links the project to the ongoing work of the organisation,
often proceeded by needs assessment, feasibility study…
57
Understanding the Enterprise Environment
Aircraft
Development
Time Pharmaceuticals
Military weapons
IT & Telecommunication
Foods
Financial Services
“If everything seems under control, you're just not going fast enough” - Mario Andretti
58
Scope Definition
59
Finding Requirements
Objectives
If a satisfactory Business Case does not exist, a project should not be started
61
Business Needs
A good “Business Case” is a pre-requisite for success!
Defines why the project is being undertaken & benefits that should be derived from it
9 Business Risks
Limitation ~ the ratio does not take into consideration the effect of timescale
64
PV ~ Present Value
Present value is the value today of a future cash flow
PV = FV / ( 1 + i ) n
Where:
PV = Present value of money
FV = Future value
i = interest rate or “cost of capital”
n = number of time periods from today
What’s the value of $4,000 revenue due in two years at interest rate of 15%?
PV = $4,000 / (1 + 0.15) 2
PV = $3,025
65
NPV ~ Net Present Value
NPV = PV revenues – PV costs
Assume “cost of capital” is 15%, compare two possible project cash flows:
67
Effective time management?
68
Project Charter
A document that formally authorises a project.
9 Summary budget and schedule (Source: PMBOK Guide Third Edition ~ p81)
“Is developed from information provided by the sponsor… and is further refined
by the project management team in the Project Scope Statement…”
(Source: PMBOK Guide Third Edition ~ p86)
70
Example Initiation Process
Inputs can include: a “Contract”, “Statement of Work” (SOW), “Feasibility Study”…
Idea?
Project HOW?
Management Plan
Gate Review
Small projects may simply use a “Project Management Plan”
71
PRINCE2 Approach
Input Approval
Defining Planning an
Preparing a
Project Initiation
Project Brief
Approach Stage Authorising
(SU4)
(SU5) (SU6) Initiation
(DP1)
72
PRINCE2 ~ Initiating a Project
Input Approval
Authorising Project
Initiation Initiation
(DP1) Document
(PID)
Assembling
Setting up
a Project
Project
Initiation
Controls
Document
(IP4) Setting up Authorising
(IP6)
Project Files a Project
(IP5) (DP2)
73
Case Study
To get started address the following sections from the Project Scope Statement:
74
Unit 4 ~ Successful Project Planning
Objectives:
¾ Scope Planning
¾ Estimating techniques
¾ Network diagrams
¾ Schedule Development
76
Planning Process Group
(Source: PMBOK Guide Third Edition ~ p47)
Scope Project
Planning Scope
Statement
Work
Breakdown Schedule
Structure Development
(WBS)
Scope and
the WBS is key
for effecting planning
77
Scope Planning
The key output from “Scope Planning” is the “Scope Management Plan”,
this should define how scope will be defined, verified and controlled.
78
Project Scope Management
Scope Work
Management Breakdown
Plan Structure
Project
Scope
Statement
Primarily concerned with
defining & controlling
what is and what is not
included in the project
79
Example WBS
Office Move
Project
Unpack
Setup equipment
80
Work Breakdown Structure (WBS)
81
WBS Good Practice Tips
9 “Work Packages” start with a verb e.g. Produce design, or Review design
82
Project Time Management
Network
Activities Diagrams
and
Milestones
Activity
Resource
Estimates
Activity
Duration
Estimates
Schedule
Management
Plan
Project
Schedule
(Source: PMBOK Guide
Third Edition ~ p125)
83
Accuracy in Estimates
Et = 7 + ( 4 x 10 ) + 19 = 11 weeks
6
(Source: PMBOK Guide Third Edition ~ p142)
85
Estimating Guidelines
Top down or Bottom up?
9 Estimates produced from a WBS are most accurate
9 Don’t pad the estimate ~ you can track performance against real numbers
Deliverables Scheduled Finish Baseline Finish Actual Finish Finish Variance Notes
Project Charter
08/02/2005 08/02/2005
Issued
Project Start 26/02/2005 26/02/2005
87
Gantt Chart
88
Network Diagram
8 7
Task B Task E
5 5 5
Task A Task C Task F
20
Task D
89
Dependency Links (FS)
10 0 10
Task A Task B
10 5 10
Task A Task B Lag 5
90
Critical Path Method (CPM)
5 8 13 13 7 20
Task B Task E
0 5 5 5 5 10 25 5 30
Task A Task C Task F
5 20 25 Duration
Task D Early Start Early Finish
Task Name
Task A
Task B
Task C
Task D
Task E
Task F
92
Critical Path Method (CPM)
5 8 13 13 7 20
Task B Task E
10 18 18 25
0 5 5 5 5 10 25 5 30
Task A Task C Task F
0 5 20 25 25 30
5 20 25 Duration
Task D Early Start Early Finish
5 25 Task Name
93
Critical Path Method (CPM)
5 8 13 13 7 20
Task B Task E
10 5 18 18 5 25
0 5 5 5 5 10 25 5 30
Task A Task C Task F
0 0 5 20 15 25 25 0 30
5 20 25 Duration
Task D Early Start Early Finish
5 0 25 Task Name
94
Gantt Chart showing Critical Path
0 5 10 15 20 25 30
Task A
Task B
Task C
Task D
Task E
Task F
Total Slack
95
Case Study
96
Schedule Development
An iterative process for determining start and finish dates for activities.
Schedule development can require that duration and resource estimates
are revised to create an approved schedule…
(Source: PMBOK Guide Third Edition ~ p143)
Considerations include:
97
Task Constraints
Total Slack
As Soon As Possible (Default)
Delay
As Late As Possible
Date
99
Resource Levelling
100
Project Cost Management
Budgeting &
Cost
Baseline
Cost
Estimates Performance
Measurement
Equipment ~ Depreciation
Marketing costs...
Tip : Indirect costs are often overlooked completely, watch out for them!
102
Project Management Plan
The project management plan can be either summary level
or detailed and can include subsidiary plans.
Considerations include:
9 Project Management Methodology
9 Project Management Information System (PIMS)
Configuration Management System
Change Control System
103
Quality Management Processes
Quality Quality
Management Control
Plan Measurements
Quality Validated
Audits Deliverables
104
What is Quality?
The degree to which a set of inherent characteristics fulfils requirements
(Source: PMBOK Guide Third Edition ~ p371)
105
Unit 5 ~ Risk Management
Objectives:
¾ Risk terminology
¾ Issue Log
¾ Risk Register
106
Terminology
Page of
108
Risk Management Processes
Risk
Management
Plan
Risk
Register
Response
Planning
109
Risk Management is an iterative process
110
Risk Identification
An iterative process for determining which risks might effect the project
and documenting their characteristics
112
Risk Register
3, 2, 1 7, 3, 1
Project Title:
Date Issued:
Page of
113
Risk Response Planning
Developing options and determining actions to enhance opportunities
and reduce threats to the project’s objectives
9 Avoid ~ eliminate the threat, often by eliminating the cause
115
Unit 6 ~ Procurement Management
Objectives:
¾ What is a Contract?
116
Energizer
You have decided to use professional caterers for the forthcoming
“Opening Ceremony” buffet lunch. Management have warned you to be
careful with your choice of supplier, they want a high quality event!
9 Identify the key elements that you are typically concerned about
117
What is Procurement Management?
The processes to purchase or acquire the products, services or results
needed from outside the project team.
Procurement
Documents
Procurement Evaluation
Management Criteria
Plan
Contract
120
Procurement Management Plan
Describes how the procurement process will be managed
from developing procurement documentation through to contract closure.
The plan can include:
121
What is a Contract?
A mutually binding agreement that obligates the buyer
to provide specified products, services or results
and obligates the seller to provide monetary or other valuable consideration.
9 An offer
122
Contract Types
Fixed-price Cost-reimbursable
Lump-sum Time and Material Cost-plus…
(T&M)
Cost-Plus-Fee (CPF)
Cost-Plus-Percentage of Cost (CPPC)
Cost-Plus-Fixed-Fee (CPFF)
Cost-Plus-Incentive-Fee (CPIF)
Purchase orders are also a form of contract, although less complex to use
123
Factors effecting Contracts
9 more…
9 Invitation for bid (IFB) ~ one price for “Contract statement of work”
The complexity and level of detail should be consistent with the value of
and risk associated with the planned acquisition.
125
Selecting Sellers
Price is often the primary consideration, however what other criteria
might be considered when evaluating competitive bids?
9 Understanding of need
9 Overall or life-cycle cost
9 Technical approach & capability
9 Financial capability & production capacity
9 References
9 Management (Project Management) approach
(Source: PMBOK Guide Third Edition ~ p283)
The seller can be viewed during the contract lifecycle, first as a bidder,
then as the selected source, and then as the contracted supplier or vendor
126
Terms and Conditions
The primary purpose of contracting is to mitigate risk and uncertainties,
therefore Project Managers should consider :
127
Case Study
128
Project Management Plan
129
Unit 7 ~ Controlling Projects
Objectives:
¾ Project Baselines
¾ Understanding EVM
¾ Variance Analysis
130
Energizer
131
Project Execution
Your strategy should include managing, monitoring & controlling project work,
and also managing stakeholders expectations.
Stakeholders
132
Project Integration Management
133
Project Execution Processes
4.4 Direct and Manage Project Execution
This process requires the project manager and team to perform multiple
actions to execute the “Project Management Plan” to accomplish the
work defined in the project scope statement.
4.5 Monitor and Control Project Work
Continuous monitoring gives the project management team insight into the
health of the project and identifies areas that require special attention.
4.6 Integrated Change Control
The project scope must be maintained by carefully and continuously
managing changes, either by rejecting or approving changes so those
revised changes are incorporated into a revised baseline.
(Source: PMBOK Guide Third Edition ~ p91)
134
Performance Measurement Baselines
Scope/Quality
Cost Time
An approved plan for the project work against which project execution
is compared and deviations are measured for management control.
135
Kickoff Meeting
136
Documentation & Reports
138
Status Reporting
Deliverables Scheduled Finish Baseline Finish Actual Finish Finish Variance Notes
Project Charter
08/02/2005 08/02/2005 08/02/2005 0 Days
Issued
Project Start 26/02/2005 26/02/2005 26/02/2005 0 Days
140
Variance Analysis
Task A 100%
Task B 25%
Task C 50%
Task D 25%
Task E
Schedule Progress
142
Earned Value Concepts
Project A Project B
Planned
Value
Earned
Cost
Cost
Value
Actual Earned
Cost Value
143
Earned Value Management (EVM)
A management methodology for integrating scope, schedule and resources
for objectively measuring project performance and progress.
(Source: PMBOK Guide Third Edition ~ p359)
Our plan is to build 10 boxes in a two day schedule, cost estimate of $1000
Status after
Planned Value one day Cost estimate
$500 $1000
Task reported
What is the value of work done?
40% complete
CV = EV - AC SV = EV - PV
CPI = EV SPI = EV
AC PV
Ratios greater than 1 are good (cost under spent or ahead of schedule)
Ratios less than 1 are bad (cost over spent or behind schedule)
146
Energizer
147
Integrated Change Control
9 Have the right attitude – be positive and try and protect your team
148
Configuration Management System
The configuration management system with change control provides a
standardised, effective and efficient process to centrally manage changes within
a project. Effectively a subsystem of the overall project management system.
(Source: PMBOK Guide Third Edition p97)
Author:
Decision:
Sign-off
150
Change Control System
Change
Request
Escalate to
Project Sponsor
Cancel Implement
Change Request Change
151
Unit 8 ~ Project Closeout
Objectives:
152
Energizer
153
Close Project
Includes the processes used to formally terminate all activities of the project or phase
hand off the completed product to others or close a cancelled project
154
Close Project
Administrative closure
9 Stakeholder approval of all deliverables
9 Facilitate the transfer of products / services to “business as usual”
9 Closure event, celebration / party?
Contract closure
9 Close all contracts associated with the project, check T&C’s
9 Make final payments / send invoices
Final Product, Service or Result
9 Formal acceptance documentation and handover of the final product
Organisational Process Assets (Updates)
9 Collect historical information / lessons learned
9 Project Closure documentation, plan for “Post Project Review”
9 Archive the “Project Files” (Source: PMBOK Guide Third Edition ~ p100)
155
Documenting Lessons Learned
156
Performance Analysis
Whilst project objectives are established from the top down
Evaluating the project’s metrics or measures goes in reverse order
Project
Objectives Strategy
Deliverables Project
Time Cost Scope Quality CSF’s Measures
157
Post Project Reviews
Individual Team
Performance Performance
Process Product
Review Review
158
Unit 9 ~ Learning review
Objectives:
¾ PMI Membership
¾ PMP Certification
159
Software Tools
General Reporting Tools
Microsoft Office ~ Word, Excel & PowerPoint
Microsoft Visio ~ Charts & Presentations
E-mail ~ Communications
Timesheet Reporting ~ see scheduling tools
161
Project Management Professional
162
What’s Next?
9 Final questions
9 Bon voyage
163