Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Rhoads Elementary School
Renovation 226
Budget Adjustments Total Original Program Budget 397 (397) 8 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Cost
Titre original
Rhoads Elementary School/Houston ISD construction and renovation budget
Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Rhoads Elementary School
Renovation 226
Budget Adjustments Total Original Program Budget 397 (397) 8 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Cost
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PDF, TXT ou lisez en ligne sur Scribd
Capital Improvement Program
Proposed Budget
2007 Facilities Capital Program
Rhoads Elementary School
Renovation 226
Budget Adjustments Total Original Program Budget 397 (397) 8 -
Summary for New Construction and Renovation
Project Data for New and Renovation Existing Building(s) Sq. Ft. New Sq. Ft. Demolition Sq. Ft. Proposed Total Sq. Ft. # of T-Buildings (2007) Student Enrollment (2007) New Construction and Renovation Cost Total Estimated New Construction Cost Total Estimated Renovation Cost
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PDF, TXT ou lisez en ligne sur Scribd
Capital Improvement Program Rhoads Elementary School
Proposed Budget Renovation
2007 Facilities Capital Program 226 Budget Adjustments
Original Admin B C D F Total Original
Summary for New Construction and Renovation Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget Project Data for New and Renovation Existing Building(s) Sq. Ft. 38,986 Proposed Classroom Capacity - - New Sq. Ft. 0 Current Classroom Capacity 397 397 Demolition Sq. Ft. 0 New Seats Gained (397) (397) Proposed Total Sq. Ft. 38,986 Proposed Core Capacity - - # of T-Buildings (2007) 2 Current Site Acres 8 8 Student Enrollment (2007) 338 Proposed Site Acres - -
New Construction and Renovation Cost
Total Estimated New Construction Cost - - - - - - - Total Estimated Renovation Cost 2,211,010 - - - - - 2,211,010 Total Estimated New Construction and Renovation Cost 2,211,010 - - - - - 2,211,010 Other Program Costs for New and Renovation Proposed Actual T-Building Costs - - - - - - - Contingency (Various% of Construction Costs) 110,551 8.94% 197,563 - - - - - 197,563 Design Fees (Various% of Construction Costs) 198,991 6.25% 138,294 - - - - - 138,294 Management Fee (Various% of Construction Costs) 88,440 8.30% 183,480 - - - - - 183,480 Soft Costs, Testing, Surveys, Printing, etc. (Various% of Constr. Costs) 0 12.69% 280,605 - - - - - 280,605 Project Reserves 265,779 - - - - - 265,779 Total Estimated Other Program Costs for New and Renovation 1,065,721 - - - - - 1,065,721 Furnishings/Equipment for New and Renovation Proposed Actual Furnishings and Equipment (Various% of Constr. Cost) 221,101 0.00% - - - - - - - Replacement Media Center Books & Materials - - - - - - - Media Center Books & Materials for Increased Capacity - - - - - - - Technology Equipment ($600,000 + $5.00 per sq ft) - - - - - - - Technology Cabling 59,269 - - - - - 59,269 Other Equipment - - - - - - - Science Equipment and Furnishings Upgrades - - - - - - - Total Estimated Furnishings and Equipment for New and Renovation 59,269 - - - - - 59,269 Land Purchase for New and Renovation Additional Site Area 0 acres x $1 per acre = - - - - - - - Total Estimated Land Purchase for New and Renovation - - - - - - -
Grand Total of New Construction and Renovation Cost 3,336,000 - - - - - 3,336,000
Anticipated Bid Date July-09 11/4/2010 TEA 226 Page 1 of 5 Proposed Budget v:9/2010 Capital Improvement Program Rhoads Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 226 Estimate Date September-07 Grand Total with Inflation 3,336,000 - - - - - 3,336,000
11/4/2010 TEA 226 Page 2 of 5 Proposed Budget v:9/2010
Capital Improvement Program Rhoads Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 226
Original Admin B C D F Total Original
New Construction Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget New Construction Costs Building Construction 0 s.f. x $0 per s.f. = - - Site Development 0 acres x $0 per acre = - - Site Utilities - - Demolition Costs - - Other Costs (Specify) - - Total Estimated New Construction Cost - - - - - - - Other Program Costs New Construction Proposed Actual T-Building Costs - - Contingency (5% of Construction Costs) 0 0.00% - - Design Fees (6.5% of Construction Costs) 0 0.00% - - Management Fee (3.5% of Construction Costs) 0 0.00% - - Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 0 0.00% - - Project Reserves - - Total Estimated New Construction, Soft Costs & Fees - - - - - - - Furnishings/Equipment for New construction Proposed Actual Furnishings and Equipment (10% of Construction Cost 0 0.00% - - Replacement Media Center Books & Materials - - Media Center Books & Materials for Increased Capacity - - Technology Equipment ($600,000 + $5.00 per sq ft) - - Technology Cabling - - Other Equipment - - Science Equipment and Furnishings Upgrades - - Total Estimate New Construction Furnishings and Equipment - - - - - - -
Land Purchase For New Construction
Additional Site Area 0 acres x $0 per acre = - - Total Estimated Land Purchase for New Construction - - - - - - -
Total Estimate New Construction Costs(Current $) - - - - - - -
11/4/2010 TEA 226 Page 3 of 5 Proposed Budget v:9/2010
Capital Improvement Program Rhoads Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 226
Original Admin B C D F Total Original
Renovations to Existing Facility Adjustment Trustee Allot P1 HVAC Athletics Sci Equip Adj Program Budget Budget Construction Costs for Renovations to Existing Facility Site 307,147 307,147 Roofing 63,108 63,108 Structural - - Exterior 231,373 231,373 Interior 319,348 319,348 Mechanical 159,378 159,378 Electrical 374,442 374,442 Plumbing 385,755 385,755 Fire/Life Safety 14,467 14,467 Technology Infrastructure 181,437 181,437 Conveyances 16,765 16,765 Specialties 157,791 157,791 Other Needs - - Science Infrastructure - - Rounding Adjustments - - Total Estimated Renovation Cost 2,211,010 - - - - - 2,211,010 Other Program Costs Renovations to Existing Facility Proposed Actual T-Building Costs - - Contingency (5% of Construction Costs) 110,551 8.94% 197,563 197,563 Design Fees (9% of Construction Costs) 198,991 6.25% 138,294 138,294 Management Fee (4% of Construction Costs) 88,440 8.30% 183,480 183,480 Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 280,605 280,605 Project Reserves 265,779 265,779 Total Estimated Renovation, Soft Costs & Fees 1,065,721 - - - - - 1,065,721 Furnishings/Equipment for Renovations to Existing Facility Proposed Actual Furnishings and Equipment (10% of Construction Cost 221,101 0.00% - - Replacement Media Center Books & Materials - - Media Center Books & Materials for Increased Capacity - - Technology Equipment ($600,000 + $5.00 per sq ft) - - Technology Cabling 59,269 59,269 Other Equipment - - Science Equipment and Furnishings Upgrades - - Total Estimated Renovation Furnishings and Equipment 59,269 - - - - - 59,269
Land Purchase for Renovations to Existing Facility
Additional Site Area 0 acres x $0 per acre = - - Total Estimated Land Purchase for Renovation Construction - - - - - - - 11/4/2010 TEA 226 Page 4 of 5 Proposed Budget v:9/2010 Capital Improvement Program Rhoads Elementary School Proposed Budget Renovation 2007 Facilities Capital Program 226 Total Estimate Renovation Costs (Current $) 3,336,000 - - - - - 3,336,000
11/4/2010 TEA 226 Page 5 of 5 Proposed Budget v:9/2010