Académique Documents
Professionnel Documents
Culture Documents
00 28-Feb-19
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pre-Test Punch Listing of Cross Country Pipeline SAIC-L-2139 30-May-19 Piping-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Note Use Pre- test Punch List Form, SATR-A-2007, for listing of specific deficiencies, indicating location &/or references.
SAES-A-004
A2 Test manifold is available and validated to meet the SA requirements. Para 5.7.4,
Appendix B & C
For internally Fusion Bonded Epoxy (FBE) coated piping system, the
test pressure shall not produce hoop stresses in the pipe that could
damage the internal coating.
SAES-L-150,
A4 However, it shall not be less than the minimum required by the
Para. 5.13
applicable Code. Deviation to this requirement shall be approved by
both the Chairman of the Paints and Coatings Standards Committee
and the Chairman of the Piping Standards Committee
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
All welds on submarine and offshore pipelines, risers, and associated SAES-W-012
B2 spool pieces were 100% radiographed, except for open non-pressure Para. 16.7.1.2
vents and drains which shall be radiographed 10%.
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
Weld Map was verified for all branch connection welds (including
sockolet, weldolet, welding bosses). MPT at a minimum inspection
rate of 10% was accepted except for the following applications which
were inspected 100%:
a) Offshore lines
b) All welds within 60 m of road, railroad, and airport crossings SAES-W-012,
B5
(for the carrier pipe only). Para. 16.8.2
c) All welds in Class 3 or 4 locations, as defined in SAES-B-064.
d) All welds over water, over tidal flats, or within 30 m of the
shoreline.
e) All welds that cannot be hydrostatically tested.
f) All lateral branch connections.
SAEP-1160 &
All welds rejected by NDE/RT were verified to be repaired,
B6 NDE Process,
re-tested and accepted. Repair Backlog was verified as ZERO.
Para.7
Schedule-'Q'
POST TEST NDE IS IDENTIFIED/LISTED IN REINSTATEMENT Attach-VI ,NDE
B10
PROCEDURE (SEAL WELDED JTS, ETC) PROCESS
CONTROL
C Pipeline Walkthrough: (List specific description and location of deficiencies in the Pre-test Punch List Form)
Drains shall not be installed at the bottom of the pipe for buried SAES-L-450,
C1
pipelines Para. 9.3
SAES-L-105,
Vents and drain valves, both temporary and permanent, conforms
C5 Para. 7.1.1 &
with the piping class or rating.
7.4.1
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
Expansion joints and spring hangers or spring supports are provided SAES-L-150,
C7
with temporary restraints. Para. 6.4
During application of Test Pressure, all in line valves, that are not SAES-A-004,
C9
used as Test isolation valves, are in partially open position. Para 6.1.3
Soft seated valves and control valves shall not be installed until after SAES-A-004,
C10
the lines have been thoroughly flushed. Para 5.12.3
The test fluid shall be injected at the lowest point in the system to SAES-A-004,
C12
minimize entrapped air.All vents shall be open during filling. Para 6.1.1
Drains shall be provided at all low points in the system and SAES-A-004,
C13
immediately above check valves in vertical lines. Para. 5.14.2
The disc of the check valve is removed, unless the check valve has a SAES-A-004,
C14
by-pass. Para. 5.14.3
For pressure testing of any check valves, verify the body and seat
SAES-L-108,
C15 tests requirements. API - 598, Table - I .
Para. 3
SAES-L-110,
C16 Spare taps of orifice flanges are plugged and seal welded.
Para. 9.2
All threaded joints up to the first block valve of hydrocarbon pipeline SAES-L-110,
C17
are seal welded. Para. 9.2
New piping systems shall be flushed clean of loose scale and debris
or scraped prior to commencement of pressure testing. (Refer SAES-
SAES-A-004,
C20 L-350)
Para. 5.12.2
(NOTE: Internal Cleaning procedure for pipe shall be submited for
review and approval)
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
NDT in-lieu of hydro test weld joint is identified and the required NDE
SAES-A-004,
C26 procedures (RT,AUT,MT,PT) for 100% NDE joints is/are available and
Para.5.16
approved.
REMARKS:
REFERENCE DOCUMENTS:
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
B The following information shall be included in each test procedure as a minimum as per GI 002-102
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.