Managment information system Date: 17-03-2020

Actual Man Power (DLR&DPR)

Sl.no Name of Project DESCRIPTION unskilled Remarks


Fitters Carpenter Masons TOTAL
(m/c+f/c)
SHUTTERING WORK: 3rd floor (302,306 flats)&LF4 lift shuttering in progress
Tower-1 BARBENDING WORK:3rd floor (304,307,308 flats) 19 35 - 4 58
Reinforcement is in u/p
Tower-2 Transverse slab Deshuttering & material shifting in progress - 8 - - 8
1 Karhtikeya panorama
(kp) Tower-3 Due to the Insufficient Manpower labours has not being Engaged - - - - 0
STP Due to the Insufficient Manpower labours has not being Engaged - - - - 0

Club house 2nd floor Brick Masonry is in progress - - 7 - 7

TOTAL 73
SHUTTERING WORK: south side Retating wall(2nd lift) & STP shuttering is in u/p.
Anand Landmark BARBENDING WORK: North side retating wall raft and columns.
2 UNSKILLED WORK: Material shifting is in u/p 14 11 - 6 31
(pragathi nagar)

SHUTTERING WORK:Phase1: Second floor beam framing & Phase2: second floor
beam sides Deshuttering is in u/p.
Anand Fourtune BARBENDING WORK: Phase 3: first floor slab reinforcement &
3 10 17 - - 27
(pragathi nagar) ground floor Electrical pipe laying work in progress

4 Ameenpur Site office Truss work completed &foundation Excavation is in progress 4

5 Nanakramguda Sump Excavation is in progress ( 1 breaker &1 hitachi ) 5


(commerical)

6 Rolling hills Loose boulders removing & dumping at west side

7 Tellapur (Nirupama) Total station (TS) - Footing markings ,Existing levels and boundaries of Excavation area survey is in progress 4
BARBENDING WORK: 6th slab column Reinforcement is in progres
Road no:- 36 SHUTTERING WORK: 6th slab columns shuttering is in progress
8 commerical 6 12 6 2 26
BLOCK WORK : Lift Area & staircase area brickwork is in u/p

1.5th floor tiles laying 06 nos


2.GF brick work &TMC Brick work
is in progress 12
Kondapur 3. Manjera line Excavation 04
9 (commerical) 4. Cable laying 20
work 04
5. NMR (ptach work)
02
1.Electricial : 1st6. Lift switches
floor Electricalfixing
work 02 nos 02
2.4th floor MD cabin Furniture
10 Road no :- 54 Fixing 02 7
(villa 02) 3. plumbing : 4th floor wash basin fixing 01
4. NMR (house Keeping)
02
11 P3 0
No work
1. PAINTING : 4th & 5th floor 2nd coat putti is in progress 02 nos
2.TILES : 503&504 flats Flooring
12 P4 work is progress 04 8
3. ELECTRICAL : 5th floor TV and net piping wiring work
02 4.
Dismetal lifting work in progress
13 Jubilee Enclave No work 0
1.4th floor Robo sand shifting in progress
Bonguluru 2.2nd floor Rooms cleaning
14 (school&Hostel) 2
3.staircase side walls curing in progress
15 Khajaguda work stopped due to MRO permissions
(commerica)

16 Asaram Footing pits Dressing is in progress 2

N- Convenction
17 (commerical) Excavation is in progress

18 Ayyappa society Excavation is in progress

19 Kompally Excavation is in progress

20 Rd no12:Banjara hills Excavation is in progress


Managment information system Date: 18-03-2020
Actual Man Power (DLR&DPR)

Sl.no Name of Project DESCRIPTION unskilled Remarks


Fitters Carpenter Masons TOTAL
(m/c+f/c)
SHUTTERING WORK: 3rd floor (302,306 flats)&LF4 lift shuttering in progress
Tower-1 BARBENDING WORK:3rd floor (303,307,310 flats) 18 26 - 2 46
Reinforcement is in u/p
Tower-2 Transverse slab Deshuttering & material shifting in progress - 0 - 7 7
1 Karhtikeya panorama
(kp) Tower-3 Due to the Insufficient Manpower labours has not being Engaged - - - - 0
STP wall shuttering work - 8 - - 8

Club house 1 st floor Brick Masonry is in progress - - 7 - 7

TOTAL 68
SHUTTERING WORK: south side Retating wall& East side Retaining wall Raft & STP
shuttering is in u/p.
Anand Landmark BARBENDING WORK: North side retating wall raft and columns &STP
2 UNSKILLED WORK: Material shifting for STP concrete purpose 14 18 2 8 42
(pragathi nagar)
Soil Dressing in sump area

SHUTTERING WORK:Phase1: First floor slab


Anand Fourtune BARBENDING WORK: Phase 2: second floor columns
3 (pragathi nagar) reinforcement is in u/p 6 17 - - 23
concrete pouring : Night concrete done by IJM Phase 3 first floor (96 cum-M30)

4 Ameenpur (Site office Truss work completed ) foundation Excavation & satircase fixing is in progress 4

5 Nanakramguda Sump Excavation is in progress ( 1 breaker &1 Hitachi ) 5


(commerical)

6 Rolling hills Loose boulders removing & dumping at west side 4

7 Tellapur (Nirupama) Total station (TS) - Footing markings ,Existing levels and boundaries of Excavation area survey is in progress 4
BARBENDING WORK: 6th slab column Reinforcement is in progres
SHUTTERING WORK: 6th slab columns shuttering is in progress
8 Road no:- 36 BLOCK WORK : Lift Area & staircase area brickwork is in u/p 4 10 4 6 24
commerical PTWORK: Stressing pockets are opening in progress -4nos

1.5th floor tiles laying 02 nos


2.GF brick work &TMC Brick work
is in progress 12
Kondapur 3. Manjera line Excavation 02
9 4. Cable laying 22
(commerical)
work 02
5. NMR (ptach work)
02
6. Lift Electrical work 02
1.Electricial : 1st floor switches fixing 02
2. 4th floor AC indoor
Road no :- 54 Units fixing in progress 02
10 10
(villa 02) 3. kurmaiah (waste material lifting to tractor)
04
4. Interior worked place (house Keeping) 02
No work :
Mason work: (External ramp flooring finshing purpose man power shortage)
Painting work : (colour code to be finalised )
11 P3 Parking Tiles: (work pending due to shortage of workers) 0
Pluming work : sanitary fittings work pending due to shortage manpower , work
will start from friday too

1. PAINTING : 4th floor 2nd coat putti is in progress 02 nos


2.TILES : 501&505 flats Flooring
work is progress 04
12 P4 3. ELECTRICAL : 4th floor internal toilets 22
02 4. Robo
sand lifting to 4th floor (contract Apparao) 12 5.East
side compound beam purpose barbending & centering 2
13 Jubilee Enclave 8th slab beam bottom (backprop)deshuttering in progress 5
1.south side compound wall plastering & STP brick masonry in progress 12 nos
2.Painting
1st & 2nd floor patch putty work 11 3. 2nd
floor commods &washbasins fixing in progress 03
14 Bonguluru 4. Tiles 3rd floor Dado fixing 05 42
(school&Hostel) 5.Windows & glass frames fixing in progress 04

6.staircase curing& Rooms cleaning in progress


02 7.North side Pile foundation work is in progress
05
Khajaguda
15 (commerica) MRO permissions

16 Kokapet Asaram Footing pits Dressing is in progress 6

N- Convenction
17 (commerical) work is in hold (due to objection from Neighbour site)

18 Ayyappa society Excavation is in progress (Today levels are taken with Auto level)

19 Kompally Excavation is in progress

20 Rd no12:Banjara hills Excavation is in progress