Académique Documents
Professionnel Documents
Culture Documents
TOTAL 73
SHUTTERING WORK: south side Retating wall(2nd lift) & STP shuttering is in u/p.
Anand Landmark BARBENDING WORK: North side retating wall raft and columns.
2 UNSKILLED WORK: Material shifting is in u/p 14 11 - 6 31
(pragathi nagar)
SHUTTERING WORK:Phase1: Second floor beam framing & Phase2: second floor
beam sides Deshuttering is in u/p.
Anand Fourtune BARBENDING WORK: Phase 3: first floor slab reinforcement &
3 10 17 - - 27
(pragathi nagar) ground floor Electrical pipe laying work in progress
7 Tellapur (Nirupama) Total station (TS) - Footing markings ,Existing levels and boundaries of Excavation area survey is in progress 4
BARBENDING WORK: 6th slab column Reinforcement is in progres
Road no:- 36 SHUTTERING WORK: 6th slab columns shuttering is in progress
8 commerical 6 12 6 2 26
BLOCK WORK : Lift Area & staircase area brickwork is in u/p
N- Convenction
17 (commerical) Excavation is in progress
TOTAL 68
SHUTTERING WORK: south side Retating wall& East side Retaining wall Raft & STP
shuttering is in u/p.
Anand Landmark BARBENDING WORK: North side retating wall raft and columns &STP
2 UNSKILLED WORK: Material shifting for STP concrete purpose 14 18 2 8 42
(pragathi nagar)
Soil Dressing in sump area
4 Ameenpur (Site office Truss work completed ) foundation Excavation & satircase fixing is in progress 4
7 Tellapur (Nirupama) Total station (TS) - Footing markings ,Existing levels and boundaries of Excavation area survey is in progress 4
BARBENDING WORK: 6th slab column Reinforcement is in progres
SHUTTERING WORK: 6th slab columns shuttering is in progress
8 Road no:- 36 BLOCK WORK : Lift Area & staircase area brickwork is in u/p 4 10 4 6 24
commerical PTWORK: Stressing pockets are opening in progress -4nos
N- Convenction
17 (commerical) work is in hold (due to objection from Neighbour site)
18 Ayyappa society Excavation is in progress (Today levels are taken with Auto level)