Vous êtes sur la page 1sur 24

Leader in Electrics & Automation

Tri-MEC

LOAD BREAK SWITCH

Electric Equipment
Leader in the field of industrial electricity & automation
creating the comfortable and productive society through
providing Total-Solution.
Enabling you to feel the difference in the performance and technology of improved product of
Load Break Switch completed with LG technology and testing equipments.

2
Contents
Features 4 Installation 17
Rating 10 Dimensions 18
Ordering Information 11 Power Fuse 20
External View 12 Coordination Graph 21
Accessories 14 Power Fuse Selection Tables 22
Operation Principle 16

3
Applied by new mechanism

LG Load Break Switch


Being applied by new concept bendable type blade structure
LG Air Insulated Load Break Switch has further been intensified with safety and reliability
and upgraded to higher stage with the performance realization through accurate
technology interpretation and actual testing.

Incorporation of maximum Optimization design of Optimization design of


strength through CAE discharge input for stable 3D for maximization of
interpretation Arc extinction extinction force

General features
In application of new concept mechanism of bendable type blade structure LG Tri-MEC Air Insulited Load
Break Switch (LBS) has been equipped with further advanced technology and in a system switching the
circuits when checking, measuring, testing and repairing the instruments. at branch point with 3 phase
load break switch designed customer-orientedly and considerably.

In particular, a bendable type blade structure is significantly small in operation radius in contrast with
existing direct line one and an arc discharge angle at the time of breaking operation is under 50°,
thereby reducing the danger of accident by an arc remarkably.

And it is suitable for a metal Enclosed, Pad-Mounted Switchgear and Package Substation thanks to
higher insulation-resistant power and is equipped with durability, stability and economical efficiency. E2
class mechanical strength based on new standard application.

4
Operation conditions
•Standard ambient temperature: under+ 35℃ (24hrs in average)
•Standard temperature: -20℃~+40℃
•Standard storage: -25℃~+60℃
•Humidity: +40℃/85% below
+20℃/90% below
•Place : Indoor place with clean ambient air not being contaminated with dust, smoke,
corrosion substance or combustible substance, salty materials, etc. Never use,
store or leave alone this product in the place with sulfuric gas, ammonia gas and
corrosive gas. (HS≤0.01ppm, SO2≤0.01ppm, NH3≤a few ppm)
•Altitude: above sea level 1000m below

Applied standards
IEC 62271-105, 60265-1, 60694, 60282-1
5
Performance Up-Grade by New Standard

Reliable Technology
This product has been verified for its excellency in quality through passing
the development test strictly in accordance with New Standard
IEC 62271-105 (Switch Fuse) and 60265-1 (Load Break Switch)

Design Characteristics
•KERI type test in application of IEC New Standard
Power Testing &
Technology Institute - Approved by KOLAS
Global key technology accumulation through self
development test and analysis by PT & T of public test
institute.
•Compact & space saving design
•3 phase collective operation
•Application with combustion-resistant and high strength
engineering
•Compressed air mode arch extinction
•Break switch-fuse combination (24kV 25kA switching, 40kA max)
•Fuse striker automatic trip (DIN 43625)

6
The Highest Performance
in Domestic Market
This product has succeeded in attaining the highest performance
in Korea through passing electrical performance test with
New Standard E2 test grade.

Verification of the most duration times Comparison of development test major items.
of load break in the country
Test class
The performance of this new standard product has been improved by 300% in E1 class E2 class
Test item
comparison with old standard one through passing the load break test in
application of IEC 60265-1, and an excellent performance has been verified
successfully by completing the load break test in application of E2 grade Rated load current break 10 times 30 times
intensified further than new standard E1 grade.
•Load break 100 times
•No load break 1000 times Short current imput (52kA) 2 times 3 times

Passed in transfer current test Note) E2 grade : test condition requiring the performance higher by
of fuse combination type maximum 300% than E1 grade in accordance with IEC standard.
Having been passed recently in the transition current test in accordance with
modern international standard 62271-105, this product has increased the
reliability sufficiently in application of self developed power-fuse.

7
Reliability and Stability for User

Employment of Bendable Type


Blade Structure
Through employing a bendable type blade being a double joint type
drive structure the stability and the worldwide technology
have been recognized successfully.

Spacing the maximum


inter-phase distance
No need to install the separate insulation barrier
when assembling Bus-bar at load side equipped
210mm

300mm

with a power fuse.


•Metal to Metal : 210mm
•Center to Center : 300mm

8
Metal Screen Test
Through passing the Metal Screen Test for the verification of
insulation resistance conducted at the distance of 300mm from
a panel door, the stability and reliability has been
attained to the full satisfaction.

°
50°

panel
door
Arc

300mm

Minimization of break distance


Through employing a direct line flexible type Knife drive
structure the break distance and panel depth comparing to
an existing direct line type can be reduced remarkably.

And an existing product may require a sufficient insulation


distance at 90°against the side of installation in the eruption
angle, but for Tri-MEC LBS of a direct line flexible type Knife
structure the stability in use has been intensified further since
Direct line blade structure Bendable type blade the eruption angle of arc becomes under 50°.
structure

9
Rating

LG Tri-MEC LBS is air insulation type and has a major instrument


equipped with the function of a rated load break and a short
protection (when a fuse is installed) in nominal voltage 22.9kV
distribution system LG and as an indoor installation type it is
used in the leading-in instruments and high voltage branch
system of user side such as unit type transformer room,
general cubicle and panel, protection of transformer and
cable in transformer room, condenser bank, motor, etc.

Type LGS-L-M-24-6 LGS-L-B-24-6

Break switch grade [IEC] E2, M1

Rated voltage [kV] 24

Rated current [A] 630

Rated frequency [Hz] 60

Rated short time current-resistant [kA] 20

A short input current [kAp] 52

Commercial frequency Inter-earth [kV] 50

voltage-resistant Inter-polarity [kV] 60

Electroencephalo Inter-earth [kV] 125

impulse voltage-resistant Inter-polarity [kV] 145

630A 30
Load current
31.5A 20

Loop current 630A 20


Current break times
Cable charging 31.5A 10

current 9.45A 10

Line charging current 1.5A 10

Rated transition current [A] 500

Rated transition voltage [Vdc] 110 -

Rated transition current [A] 5 -

No voltage break times 1000

Operation Motor powered Manual

Non fuse [kg] 70


Weight
Fuse [kg] 80

Note) Above weight does not include fuse weight.

10
Ordering Information

Air Insulated Load Break Switch

LG Load break Kind of break Control method Rated Rated Control Number Composition Manual operation
switch switch voltage (kA) current (A) power of circuits cable
Motor S LBS single type
M powered
Air LBS 24 24kV 6 630A D1 DC 110V 1 1 circuit 20 2.0mm
F Fuse
L (Vacuum B Manual D2 DC 220V interlocked type 10 1.0mm
load type)
A1 AC 110V 15 1.5mm
A2 AC 220V 18 1.8mm
None 26 2.6mm
00
(manual) 35 3.5mm
00 None
Note) 1. Left attaching type of drive mechanism is separate order product (See page 13)
2. A power fuse is only available in DIN product.

Power Fuse

General Rated current Modification


LG power fuse Rated voltage
load use 5A 10A 20A 30A 40A 50A 63A No.
20 24kV

11
External View

➏ ➐




➐ ➒

➊ ➓

➊ Source side terminal


➋ Load side terminal
➌ Main contact (fixed)
➍ Main contact (movable)
➎ Arc contact (fixed)
➏ Arc contact (movable)
➐ Arc extinction nozzle
➑ Insulation rod
➒ Puffer
➓ Motor
Base frame
Fuse clip ➋
Voltage trip device
Aux. switch
Connector
Counter
Fuse trip device
Fuse check switch
Manual operation cable
Manual operation handle

12
Left & right drive mechanism
Easy input operation and trip operation through employing independently
developed mechanism and capable of left & right drive mechanism.

Standard type Left side attaching type

Note) Left side attaching type is a separate ordering product.

Horizon & vertical installation of manual cable


Capable of attaching 90°∆ turn of manual operation cable in case of manual type, thereby minimizing
distorting and twisting of cables by reducing the stress of remote operation flexible joint part depending
upon attaching angle of LBS.

Manual operation
cable

Vertical mounted
position

Horizontal mounted
position

Mechanism

Vertical type Horizon type

Manual operation cable and handle.

Note) Manual operation cable is standard and in case of horizontal installation the use is possible through
installation by changing cable kit with simple operation (See manual)

13
Accessories

Fuse trip device


A device preventing the defect phase operation by opening a load break switch through
interlocking mechanically with a striker at the fusing time.

Voltage trip device


A coil for tripping remotely at the time of system accident or load break
Control circuit Scope of Value of incoming
Normal current Trip time
rated voltage operation voltage current wave
(V) (%) (A) (A) (ms)
DC 110V 70~110 3 2 75

Manual operation device


It is composed of manual operation cable and manual handle as a device used for
manual ON/OFF outside a panel and at far distance.
Manual operation cable can be mounted at 90°turn, thus reducing the stress of cable
when attaching it vertically or horizontally.

Electric operation device


As advice for ON/OFF of a load break switch at far distance the standard supply
voltage is DC 110V.

Scope of Value of incoming


Rated voltage operation voltage current wave Normal current Change time
(V) (%) (A) (A) (sec)
DC 110V 85~110 3 2 7.5

Fuse check switch


In case a fuse in fuse interlocked load break switch is melted, as a contact to be
operated mechanically through interlocking with a striker it is used in the display of fuse.

Note) The capacity of contact is same as that of Aux. switch.

14
Counter
A device displaying the operating times of a break switch in application of 5 Digits

Aux. switch
As a contact to be operated through interlocking mechanically according to ON/OFF
condition of main contact of a load break switch it is used in the display or control of
condition of a load break switch.

Classification Resistance Inductive


load load
440V 3A 1.5A
AC 220V 5A 2.5A
Contact
110V 10A 5A
capacity
220V 5A 2.5A
DC
110V 10A 5A
Contact number AX2/AX4 2a2b/4a4b

Control circuits

Auxiliary Switch *
Fuse Check
ON OFF 4a 4b Limit Switch

3 1 5 34 36 38 50 22 24 26 28 F9 M : Charging Motor
TC : Trip Coil
RY : Motor Operation Relay
12 9 30 AUX : Auxiliary Switch
RY-a RY-a AUX-a **
A B
8 5 31
1 2
14 1 1 3 4
34 36 38 50 22 24 26 28 COM
5 6
RY M TC LS-a
13 2 2 35 37 39 51 23 25 27 29 NO F9 F10
6
AUX-b 10 33
34 35 38 39
6' RY-a AUX-a 36 37 50 51
20
6 32
AUX-b 22 23 26 27
21 24 25 28 29

4 2 6 35 37 39 51 23 25 27 29 F10

15
Operation Principle

Motor powered type


A spring for input is enlarged as the turn movement of a drive motor and
at this time an accumulated energy to input or open a break switch is
conveyed to an axis. As a result, regardless of operator a blade to flow
main circuit and to block it is moved at designated speed.
An input instrument part provides a strong force so that a break switch
may overcome the explosive force likely to take place in case of inputting
under the system accident.
At this time the force is not conveyed to an operation handle and the
input can be made even under the rated short accident. A load break
switch is composed of a main blade and an arc blade. When a break
switch is opened the main blade is opened first and all of currents and
extinct through the arc blade. And through dispersing and cooling down Trip Condition

the arc with a proper operation of Puffer by Air Piston the damage of an
instrument and system can be blocked off early.

Manual type
Through turning clockwisely and continuously in application of an
exclusive handle supplied together with a break switch the input is made,
and an opening operation is made by LATCH instrument part through
turning the exclusive handle clockwisely and continuously.
Inputting condition

Operation of instrument part


A reduction gear and mechanism axis located at the side of base frame
is equipped with a spring cap and lever and it takes a turn exercise of Advance in High Voltage Insulation
360°counter-clockwisely. When a hook lever linked to the main axis of a
switch takes an up-down turn exercise a moving rod connects a main
PRESURE
blade to and an arc blade in conduction part and disconnects them,
and opens a load circuit.
CONTACT
TRAVEL
Inputting operation 100%

CONTAC
OPENING
PRESURE
50% AT NO-LOAD

0 TIME IN Ms
CURRENT

Blocking operation

WINDOW FOR
ARC EXTINCTION

Puffer Type pressure-time characteristics curves

16
Installation

Installation method

Panel frame

Panel frame

Vertical installation Horizontal installation

Cable installation by manual operation

Note) 1. The length of the cable for remote manual operation is mounted on 2.0m basis.
2. Fix the cable attaching key on to the distribution board frame with bolt & nut. Maintain the
cable curve radius above R150 and fix it on to the panel pole and etc solidly so that the
insulation distance from the earth may be spaced.
3. In case of manual type others than a motor and a trip coil are same as those of electric one.
Attaching key Manual handle

17
Dimensions (Motor powered type)

Fuse combination type (Unit : mm)

Attaching dimension

LBS single type

Attaching dimension

18
Dimensions (Manual type)

Fuse combination type (Unit : mm)

Attaching dimension

LBS single type

Attaching dimension

19
Power Fuse

Applied power fuse


LG Prime-MEC Power Fuse is used for protecting circuits and system
instruments by severe accident current and in general for protecting
transformer circuits, condenser circuits, motor circuits, etc.
24kV (fusing-Upholstery)
features curve
The silver is used in elements and through using high quality silica and
ceramic magnetic rod and insulating tube the safety and reliability of the
product has been improved remarkably.

The cautions in applying Fuse

← Operation time (sec)


•A fuse has to be selected only for protecting a short circuit accident.
(Overcurrent can not be protected.)
•A fuse can not use again after operation.
•A proper rated current shall be selected so that a fuse action may not be damaged.
•The most suitable rated current shall be selected in consideration of the fuse use
and circuit features since the fuse operation features are fixed according to
respective ones.
•It is recommended that the protection be made from other instruments under
minimum breaking current, and a proper rated fuse incapable of fuse operating
shall be selected.
- In case of protecting an overload field (under minimum breaking current)
a lower fuse in minimum breaking current shall be used or a fuse shall be
used through combining the overcurrent breaking devices in series. Agreed current (effective value : A) →
•Check if a voltage of circuit is higher than overload voltage of fuse.
•Since a fuse may cause the deterioration even without operation, thereby
generating a rated current with a sufficient capacity shall be selected.
•Replace at the time of fuse current.
24kV Current limiting
features curve

A selection table of a power fuse for the


protection of transformer circuits
selection condition
← Current limiting value (peak value)

Transformer Circuit
Rated
Phase rated capacity voltage
fuse
(kVA) (kV)
36~75 LFL-20G-5B
75~157 LFL-20G-10B
172~358 LFL-20G-20B
258~538 LFL-20G-30B
464~965 LFL-20G-40B
598~1246 LFL-20G-50B
3Ø 22.9
745~1554 LFL-20G-60B
1000~1983 LFL-20G-75B
1600~2645 LFL-20G-100B
2362~3304 LFL-20G-125B
3680~4232 LFL-20G-160B
4593~5287 LFL-20G-200B
Selection condition
Agreed current (effective value : A) →
1. A transformer incoming current was selected on the assumption that it is 10 times
as full load of transformer for 0.1 sec.
2. A fuse rated current was selected so that 1.5 times as a transformer rated current
may be flowed continuously.
3. A transformer fuse was selected on the assumption that it is broken within 2 secs
in 25 times as a transformer rated current when the secondary current is short.

20
Coordination Graph

[5]

[4] [2]
[3]
[1]
[6] Characteristic curve of a secondary
circuit breaker or low voltage fuse
(Converted into the primary values)
Fuse
Permissible overload
characteristic curve of a transformer
Time/Current characteristic curve of a Fuse

Blow-out characteristic curve of a Fuse


Transformer
Operation characteristic curve of a Fuse

Circuit breaker Time


or low voltage fuse

Full load current of a transformer


The lowest interrupting current of the
secondary circuit breaker
Permissible overload current of a transformer
Rated current of a fuse
Lowest blow-out current of a fuse
Lowest interrupting current of a fuse
Inrush current at no load of a transformer Current
Secondary short-circuit current
A. Permissible overload current/time of a transformer
Rated interrupting current of B. Permissible overload characteristic of a transformer, Operation characteristic curve of a Fuse
a secondary circuit breaker C. inrush current and time at no load of a transformer
Primary short-circuit current
Rated interrupting current of a fuse

When any protection device is not installed


in the secondary of a transformer
•Permissible overload current of a transformer (point ③)) must lie to the left of the curve ⓒ
(time/current characteristic curve of a Fuse)
※ Coordination in the graph Full load current of a transformer ① ≤ Rated current of a fuse ④
•Zone of [1] : Protection of primary side from •Point C(inrush current and time at no load of a transformer) must lie to the left of the point
short-circuit by a fuse ⓒ(time/current characteristic curve of a Fuse)
•Zone of [2] : Protection of a transformer
•Secondary short-circuit current⑧ > Lowest interrupting current of a fuse ⑥
•Zone of [3] : Out of the scope of fuse operation
Point B must lie to the left of the secondary short-circuit current⑧.
•Zone of [4] : Interruption is not ensured even
•Primary short-circuit current⑩ < Rated interrupting current of a fuse⑪
though the fuse blows.
•Zone of [5] : Protection of a transformer is
not ensured even though the When a circuit breaker or fuse is installed
fuse interrupts the circuit. in the secondary of a transformer
•Zone of [3]+[4]+[5] : No protection zone of a
•Must meet the requirements above mentioned in ①
transformer Circuit
•The characteristic curve of a secondary circuit breaker or low voltage fuse ⓐ must lie to
breaker or low voltage
the left of permissible overload characteristic curve of a transformer ⓑ and under the
fuse required for the
transformer protection
point B
•The characteristic curve of a secondary circuit breaker or low voltage fuse ⓐ must lie to
the Time/Current characteristic curve of a Fuse and under the Secondary short-circuit
current ⑧.
•Secondary short-circuit current ⑧ < Characteristic curve of a secondary circuit breaker or
low voltage fuse ⓐ
•The secondary circuit breaker or low voltage fuse should meet the above mentioned
requirements to each branch circuit.
•Another medium voltage protection device is required for the ensured protection against
the fault happening between the secondary protection devices and the internal short-
circuit of a transformer in the zone of [3]+[4]+[5].

21
Power Fuse Selection Tables

Fuse Link Specification Fuse selection by load


Application
Rated Rated Rated Minimum
DIN type voltage current
breaking breaking
current current
Transformer load (kVA) Condenser load(kVA)

Model (kV) (A) (kA) (kA) Single phase Three phase Three phase
LFL - 3/6G - 5B 5 4 ~ 8 ※( 8 ~ 16 ) 6.7 ~ 14 ※( 13 ~ 28 ) 9.8up to ※( 9.8up to )
LFL - 3/6G - 10B 10 6 ~ 13 ( 13 ~ 25 ) 11 ~ 22 ( 21 ~ 44 ) 9.8 ~ 12 ( 19 ~ 24 )
LFL - 3/6G - 20B 20 15 ~ 31 ( 30 ~ 62 ) 25 ~ 53 ( 51 ~ 107 ) 12 ~ 31 ( 24 ~ 61 )
LFL - 3/6G - 30B 30 21 ~ 42 ( 40 ~ 84 ) 35 ~ 73 ( 70 ~ 145 ) 31 ~ 46 ( 61 ~ 92 )
LFL - 3/6G - 40B 3.6 40 40 ~ 82 ( 80 ~ 165) 69 ~ 143 (137 ~ 286) 46 ~ 64 ( 92 ~ 128)
LFL - 3/6G - 50B 50 49 ~ 102 ( 98 ~ 204) 85 ~ 117 (170 ~ 354 ) 64 ~ 81 (128 ~ 163 )
(7.2)
LFL - 3/6G - 60B 63 66 ~ 137 (132 ~ 275) 114 ~ 238 (229 ~ 476 ) 181 ~ 105 (163 ~ 210 )
4In
LFL - 3/6G - 75B 75 68 ~ 165 (134 ~ 330) 117 ~ 285 (233 ~ 571 ) 105 ~ 150 (210 ~ 300 )
LFL - 3/6G - 100B 100 128 ~ 220 (256 ~ 440) 222 ~ 381 (443 ~ 762 ) 150 ~ 222 (300 ~ 445 )
LFL - 3/6G - 125B 125 151 ~ 275 (302 ~ 550) 261 ~ 476 (522 ~ 952 ) 222 ~ 275 (445 ~ 550 )
LFL - 3G - 160B 160 40 211 ~ 352 ( - ) 365 ~ 610 ( - ) 275 ~ 370 ( - )
3.6
LFL - 3G - 200B 200 265 ~ 440 ( - ) 495 ~ 762 ( - ) 370 ~ 550 ( - )
LFL - 6G - 160B 160 - (425 ~ 704) - (735~1,220 ) - (550~742 )
7.2 200 - (437 ~ 880) - ※ (755~1,520 ) - (742~1,000 )
LFL - 6G - 200B
LFL - 20G - 5B 5 20 ~ 43 36 ~ 75 46up to
LFL - 20G - 10B 10 43 ~ 90 75 ~ 157 46 ~ 83
LFL - 20G - 20B 20 99 ~ 206 172 ~ 358 83 ~ 203
LFL - 20G - 30B 30 149 ~ 310 258 ~ 538 203 ~ 317
LFL - 20G - 40B 40 267 ~ 557 464 ~ 965 317 ~ 425
LFL - 20G - 50B 24 50 345 ~ 719 598 ~ 1,246 425 ~ 564
5In
LFL - 20G - 60B 60 430 ~ 897 745 ~ 1,554 564 ~ 710
LFL - 20G - 75C 75 580 ~ 1,145 1,000 ~ 1,983 710 ~ 1,021
LFL - 20G - 100C 100 923 ~ 1,527 1,600 ~ 2,645 1,021 ~ 1,655
LFL - 20G - 125B 125 25 1,364 ~ 1,908 2,362 ~ 3,304 1,655 ~ 2,370
LFL - 20G - 160B 160 2,125 ~ 2,443 3,680 ~ 4,232 2,370 ~ 3,170
LFL - 20G - 200B 200 2,650 ~ 3,050 4,593 ~ 5,287 3,170 ~ 4,000

Fuse Link Specification Fuse selection by load


Application
Rated Rated Rated Minimum
KS type breaking breaking
voltage current current current
Transformer load (kVA) Condenser load(kVA)

Model (kV) (A) (kA) (kA) Single phase Three phase Three phase
G(General use) type LFL - 3/6G - 5 5 - ※ ( 5up to ) 5up to ※( 15up to ) - ※( - )
LFL - 3/6G - 10 10 10up to ( 15up to ) 15up to ( 30up to ) 10up to ( 25up to )
LFL - 3/6G - 20 20 20up to ( 50up to ) 30up to ( 75up to ) 30up to ( 50up to )
LFL - 3/6G - 30 3.6 30 30up to ( 75up to ) 75up to ( 150up to ) 50up to ( 100up to )
LFL - 3/6G - 40 (7.2) 40 50up to ( 100up to ) 100up to ( 200up to ) 75up to ( 150up to )
LFL - 3/6G - 50 50 75up to ( 150up to ) 150up to ( 300up to ) 100up to ( 200up to )
LFL - 3/6G - 60 63 - ( - ) - ( - ) - ( - )
LFL - 3/6G - 75 75 150up to ( 200up to ) 200up to ( 400up to ) 200up to ( 400up to )
LFL - 3/6G - 100 100 40 5In 200up to ( 400up to ) 375up to ( 750up to ) 300up to ( 600up to )
LFL - 3G - 150 150 300up to ( - ) 500up to ( - ) 400up to ( - )
LFL - 3G - 200 200 400up to ( - ) 750up to ( - ) 600up to ( - )
LFL - 3G - 300 3.6 300 625up to ( - ) 1,000up to ( - ) 1,000up to ( - )
LFL - 3G - 400 400 750up to ( - ) 1,500up to ( - ) - ( - )
LFL - 6G - 150 150 - ( 500up to ) - (1,000up to) - ( 800up to )
LFL - 6G - 200 200 - ( 750up to ) - (1,500up to) - (1,200up to)
LFL - 6G - 300 7.2 300 - (1,250up to) - (2,000up to) - ( - )
LFL - 6G - 400 400 - ( - ) - (2,500up to) - ( - )
M(Motor protection) type LFL - 3M - 20 20 - 50up to ※( - )
LFL - 3M - 50 50 - 150up to ( - )
LFL - 3M - 100 100 - 300up to ( - )
LFL - 3M - 150 3.6 150 - 400up to ( - )
LFL - 3M - 200 200 - 800up to ( - )
LFL - 3M - 300 300 - 1,000up to ( - )
LFL - 3M - 400 400 - - ( - )
40 7In
LFL - 6M - 20 20 - - ( 100up to )
LFL - 6M - 50 50 - - ( 300up to )
LFL - 6M - 100 100 - - ( 600up to )
LFL - 6M - 150 7.2 150 - - ( 800up to )
LFL - 6M - 200 200 - - ( - )
LFL - 6M - 300 300 - - ( - )
LFL - 6M - 400 400 - - ( - )

Note) Above condition table is used only for reference. LG Tri-MEC Air Insulated Load Break Switch can be equipped only with 24kV DIN standard products.

22
Fuse selection by load Dimensions(mm) Selecting conditions and warning
Applicable holder 1. ※ The values in ( ) apply to the loads of 7.2kV.
Motor load (kVA)
A B C D 2. It is assumed that the inrush current of a transformer is 10
Three phase times of the full load current of a motor for 0.1 second.
6.5 ~10.7 ※( 13 ~ 22 ) - The rated current of a fuse is selected to carry
10.7 ~ 28 ( 22 ~ 36 )
continuously the current of 1.5 times of rated current of a
28 ~ 57 ( 36 ~ 86 )
50 ~ 85 ( 86 ~ 117 ) 195 55 - - transformer.(1.3 times in the case of ※)
85 ~ 115 (117 ~ 230) LFH-6G-D1HB - In the transformer load table it is assumed that the
115 ~ 142 (230 ~ 284 )
interruption will be made at 25 times of rated current
138 ~ 191 (276 ~ 382 )
181 ~ 252 (362 ~ 503 ) 192 77 - - within 2 seconds.
253 ~ 369 (469 ~ 739 ) 3. It is assumed that the inrush current of a motor is 5 times of
293 ~ 435 (556 ~ 870 )
full load current for 10 seconds.
343 ~ 572 ( - )
375 ~ 630 ( - ) 292 77 - - LFH-6G-D2HB 4. In the case of using the M(motor protection) type fuses for
- (751~1,223 ) the purpose of the short-circuit protection of a motor or a
- (1,154~1,760 )
starter select the proper rating in addition refer to the
-
- 442 55 - - characteristic curves on the catalog to make the device
- protected from overload by a circuit breaker or a
-
contactor.
-
442 77 - - 5. It is assumed that the inrush current of a capacitor is 71
- LFH-20G-D2HB
- times of its rated current for 0.002 second.
-
- The rated current of a fuse is selected to carry
-
- 442 87 - - continuously the current of 1.43 times of rated current of a
- capacitor.
-
- In case service life of more than 1000 operations is
required select in the M( motor protection) type fuse
table.
Fuse selection by load Dimensions(mm)
6. The above mentioned comments are according to
Motor load (kVA) Applicable holder KS(Korean Industrial Standard) and subject to the real
A B C D
situation.
Three phase
-
-
-
- 261 50 47 25 LFH-6G-D60
-
-
-
-
-
- 311 60 57 30 LFH-6G-D1H
-
-
-
311 77 73 43 LFH-6G-D2H
-
-
-
- 350 110 108 55 LFH-6G-D4H
37 ~ 75 ※( - )
90 ~ 200 ( - ) 200 60 58 30 LFH-3M-100
220 ~ 400 ( - )
450 ~ 630 ( - )
200 77 73 43 LFH-3M-200
710 ~ 800 ( - )
900 ~1250 ( - )
250 87 84 50 LFH-3M-400
1,500 ( - )
- ( 75 ~ 160 )
311 60 58 30 LFH-6M-50
- (185 ~ 400 )
- (450 ~ 800 )
- (900 ~ 1,250) 350 77 73 43 LFH-6M-200
- ( 1,500 )
- ( 2,500 )
- ( 3,000 ) 450 87 84 50 LFH-6M-400

23
Leader in Electrics & Automation

• For your safety, please read user's manual thoroughly before operating.
• Contact the nearest authorized service facility for examination, repair, or adjustment.
• Please contact a qualified service technician when you need maintenance.
Do not disassemble or repair by yourself!
Safety Instructions • Any maintenance and inspection shall be performed by the personnel having expertise concerned.

www.lgis.com

HEAD OFFICE Global Network


•LG Industrial Systems Tokyo Office Japan
LG TWIN TOWERS, 20 Yoido-dong, Youngdungpo-gu, Address: 16F, Higashi-Kan, Akasaka Twin Towers 17-22, 2-chome,
Akasaka, Minato-ku Tokyo 107-8470, Japan
Seoul, 150-721, Korea Tel: 81-3-3582-9128 Fax: 81-3-3582-0065 e-mail: dongjins@lgis.com
•LG Industrial Systems Dubai office UAE
Tel. (82-2)3777-4870 Address: P.O.Box-114216, API World Tower, 303B, Sheikh Zayed road, Dubai, UAE.
Tel: 971-4-3328289 Fax: 971-4-3329444 e-mail: hwyim@lgis.com
Fax. (82-2)3777-4713 •LG-VINA Industrial Systems Co., Ltd Vietnam
Address: LGIS VINA Congty che tao may dien Viet-Hung Dong Anh Hanoi, Vietnam
http://www.lgis.com Tel: 84-4-882-0222 Fax: 84-4-882-0220 e-mail: srjo@hn.vnn.vn
•LG Industrial Systems Hanoi Office Vietnam
Address: Room C21, 5Th Floor, Horison Hotel, 40 Cat Linh , Hanoi, Vietnam
Tel: 84-4-736-6270/1 Fax: 84-4-736-6269
•Dalian LG Industrial Systems Co., Ltd China
Address: No. 15 Liaohexi 3 Road, economic and technical
development zone, Dalian, China
Tel: 86-411-8731-8210 Fax: 86-411-8730-7560 e-mail: youngeel@lgis.com
•LG Industrial Trading (Shanghai) Co., Ltd China
Address: Room 1705-1707, 17th Floor Xinda Commercial Building No 322,
Xian Xia Road Shanahai, China
Tel: 86-21-6252-4291 Fax: 86-21-6278-4372 e-mail: hgseo@lgis.com
•LG Industrial Systems Beijing Office China
Address: Room 303, 3F North B/D, EAS 21 XIAO YUN ROAD,
Dong San Huan Bei Road, Chao Yang District, Beijing, China
Tel: 86-10-6462-3259/4 Fax: 86-10-6462-3236 e-mail: sclim@mx.cei.gov.cn
•LG Industrial Systems Shanghai Office China
Address: Room 1705-1707, 17th Floor Xinda Commercial Building
No 318, Xian Xia Road Shanahai, China
Tel: 86-21-6278-4370 Fax: 86-21-6278-4301 e-mail: sdhwang@lgis.com
•LG Industrial Systems Guangzhou Office China
Address: Room 303, 3F, Zheng Sheng Building, No 5-6, Tian He
Bei Road, Guangzhou, China
Specifications in this catalog are subject to change without notice due to Tel: 86-20-8755-3410 Fax: 86-20-8755-3408
continuous product development and improvement. e-mail: lgisgz@public1.guangzhou.gd.cn

2004. 11 Load Break Switch 2004. 11/(01) 2004. 11 Printed in Korea STAFF