I declare that the information contained in this Application is correct and that the Tow
will not commence until all Department requirements relating to operational systems and
procedures for the above named vessels have been met.
Department of Transport
Commercial Vessel Safety Branch
1 Essex Street, PO Box 402, Fremantle, Western Australia 6959
Telephone: (08) 9216 8240 Fax: (08) 9216 8978 Website: www.transport.wa.gov.au/imarine
CVS Form 033 Revised: 01/07/10
Commercial Vessel Safety Branch Offices:
ABN No: 27 285 64 3255
1 Essex Street or 65 Chapman Road
PO Box 402 PO Box 68
FREMANTLE 6959 GERALDTON 6530
Tel: (08) 9216 8237 Tel: (08) 9956 0115
Fax: (08) 9216 8978 Fax: (08) 9921 8364
E-mail: Commercial.Vessels-Surveys@transport.wa.gov.au
Payment of Fees
Payment may be made personally or by forwarding the necessary remittance to the above offices.
• Cheques /Money Orders are to be marked “not negotiable” and made payable to Department Transport
• Bankcard, MasterCard and Visa Card payments may be made by mail, in person, by phone or Facsimile or
by email.
• All fees must be paid prior to any service being performed or Certificate being issued.
Name: ___________________________________________
Address: ___________________________________________
___________________________________________
________________________ Postcode: __________
Details of Payment
Type of Survey Cost Item $ Amount
1 Towed Vessel
1.2 Ensure that current survey certificate is valid for the tow.
1.3 Check Stability Book to ensure that towed vessel as loaded has sufficient
stability.
1.8 Ventilators and vent pipes to be closed except for oil tanks.
1.9 Windows and port holes to be closed and deadlights down where applicable.
1.10 Large front facing windows such as ferries to be covered over with sheet
plywood.
1.16 White band approximately 300 high by 1000mm long to be painted near the
waterline on each side.
1.17 Main towing bridle to be made fast to two sets of bitts, stoppered to the deck
cleats and connected to a monkey face plate at the other end.
1.18 Protection to be provided against chaffing at the fairleads for the wire pendants.
1.19 Emergency towing pendant to be becketed along one side of the town.
1.24 Battery or gas operated navigation lights to be fitted with sufficient life 50% in
excess of the estimated towing time.
1.25 Towing lights and shapes to be in line with Prevention at Sea Collision
Regulations – Rule24.
1.26 Portable diesel pump with suction and discharge hoses for bilge pumping and
fire fighting.
2 Towing Vessel
2.1 Towing vessel to be suitable for towing and to have a current survey certificate
valid for the tow.
2.4 Check fuel on board and ensure sufficient for tow, plus 25% reserve.
2.5 Voyage plan, fuel consumption and capacity to be checked (note: 0.30 litres per
KW hour for main and aux engines can be used to calculate).
2.6 Engineer to familiarise himself with the pumping arrangements of the towed
vessel.
2.7 Towing vessel to be suitable for towing displacement hull deep draft with towing
winch is preferred.
2.8 If vessel is not set up for towing ensure that bollards and bitts are of sufficient
strength.
2.9 Tug to be fitted with the appropriate towing lights to Prevention at Sea Collision
Regulations – Rule24..
3.1 Required strength of towline and tug bollard pull is to be determined from the
anchor line breaking strength for vessels up to 25 metres and by the equation Pull in
Tonnes = EN + 17/16.67 for vessels over 25 metres. The EN (equipment numeral is
calculated from the formula in USL Code 13 App H).
3.2 If the bollard pull cannot be proved by a Bollard Pull Certificate, then it can be
calculated as follows:
3.2.1 For slow turning propellers (up to 300rpm) running a Kort nozzle the
bollard pull in tonnes is the kWP multiplied by 0.0192.
3.2.2 For slow turning propellers running in open water (no nozzle) the bollard
pull in tonnes is the kWP Multiplied by 0.0134.
3.2.3 For all other situations the bollard pull in tonnes is the KWP multiplied by
0.0168. (where kWP is the total propulsive power and bollard pull is in tonnes).
All components of the towline are to be checked to ensure that each connection has a