JOB TITLE / AIM: JSA for aligmment of vessel and drum


JSA DATE: 25/12/2006 JSA NO./ REVISION:
SUPERVISOR/ JSA LEADER: Rafiq SCRIBE: Masood Memon
PARTICIPANTS: Ismail, Mubashar, Asghar
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps: List the main sequential steps. Each step should accomplish a specific component of the task.

1. Mobilization of Equipment & Workers.


2- Alignment with jackhammer
3- Nut bolts tightening
4-Demobilization.

Alternatives Considered:

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the HSE personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of Equipment & Unauthorised Tools brought on to site. Ensure all tools shall be inspected & tagged prior
workers. starting the job.
Un inducted &Unskilled Persons All persons are skilled and trained for the job&
they are fully aware of all hazards.
Ensure that all personnel are fit for the job prior
starting the job.
All personnel must be Undergone fitness for work
Un fit workers for Job.
assessment thru Del Doctor.

JSA must be in place prior to start the work.


Ensure that all personnel take part in the toolbox
Workers starting the job without JSA meeting discussion& they are fully aware of Job
hazards.
Ensure Proper shelter& provision of cold water at
the job site for the workers.
Heat Stress. Ensure all workers are using right teqnique for
manual handling.
Back Injury.

2 Alignment With Jack Hammer Jack slippage Ensure that the skilled worker is doing the job

Back Injury Proper posture is maintained during whole activity.

Loosening of nut Ensure that nut and bolts are properly fixed after
finishing the activity.
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)

3 Nut Bolt Tightening Hand Injury Ensure that the Hand gloves shall be worn at all the
times.

Uninspected tools are used Prior to work tools are must be inspected and
colour coded.(like Wrenches, Screw drivers,
Spanners, hammers )

Improper using of tools


Use the right tool according to nature of work

Good quality of tools & inspected tools to save the


Slipping of tools
slipping hazards

Same as
4 Demobilization Same