Topic 3 - Tutorial
Consent to commence works
• Plans were approved and documents duly
submitted for consent to commence works. The
application was rejected by reason of not lodging
or not providing proper supervision plan for the
works. It the developer appeals against the
decision of BA, is there any chance to succeed in
the appeal?
• Alternatively, consent was granted. Later, it came
to the knowledge of the BA that the supervision
plan was incomplete or defective. Would the
consent be still valid within the meaning of BO?
Mag Appeal no. 493 of 1997 - 1