Aircon Capacity for EB L6

(A1)
Cooling Load Total
Aircon
considering Electrical cooling Selection
Sl No Room Name Equipment Load(KW) (A2) Cooling load(Ton) Remark
load for (Ton)
Room A=A1+A2
space(Ton) electrical
equipment(T
on)
0.79 72 2.04 2.83 3
1 UPS Room 01 For all OT
2 UPS room 2 0.46 48 1.364 1.824 2
3 UPS Room 3 0.72 56 1.632 2.352 3
4 UPS Room 4(Angio-01) 0.4 24 0.6824 1.0824 1.5
5 UPS Room 5(Angio-02) 0.42 24 0.6824 1.1024 1.5
Aircon Capacity for Elevator

(A1)
Cooling Load Total
Aircon
considering Electrical cooling
Sl No Room Name (A2) Cooling Selection Remark
Equipment Load(KW) load(Ton)
load for (Ton)
Room A=A1+A2
space(Ton) electrical
equipment(T
on)
1 SB 1 0.6 10 0.2843 0.8843 1.5
2 AB1,AB2 1.16 30 0.853 2.013 2
3 AB3,AB4 1.16 30 0.853 2.013 2
4 EB1,EB2 1.05 17 0.4833 1.5333 2
5 EB3,EB4 1 12.4 0.3525 1.3525 2
5 EB5 1.17 22 0.6255 1.7955 2