SL. PKG NO Package Name Major/ Draft TS FTS Price Bid Contract Turn Non-
NO. Balance Issued Opened Signed key Turnkey
(T) (N-T)
T NT T NT T NT T NT T NT
Major
1 001-SE-01 Coke Oven Battery no. 11 M 1 1 1 1 1
2 001-SE-02 Coke Oven Machines M 1 1 1 1 1
3 001-SR-03 COB-11 - Silica Bricks & Mortar M 1 1 1 1 1
4 001-SR-04 COB-11 - Fire Clay Bricks & Mortar` M 1 1 1 1 1
5 001-SR-05 COB-11 - Insulation Bricks & Mortar M 1 1 1 1 1
6 002 CDCP M 1 1 1 1 1
7 003A COB-11 - By Products proper & H2S M 1 1 1 1 1
8 010 BF # 8 M 1 1 1 1 1
9 011-01A Boiler Pkg M 1 1 1 1 1
11 011-01C DM Plant M 1 1 1 1 1
Balance
1 021A New Cold sinter Screening System & Hearth Layer B 1 1 1 1 1
Feeding Arrangement, Sampler (including
electricmotors) & Dismantling of existing Lab
Building
2 021B Lime Dosing alongwith tankers & compressor, B 1 1 1 1 1
Sinter cooler (Sealing & segregation Chute), PU/PE
liners in bunkers (12Nos.)
3 021C Replacement to B.W.F. & belt weigh scales, Load B 1 1 1 1 1
cell mounting of mix bins above roll feeders (4Nos.)
PLC/PC based automation & control as well as
instrumentation including N2 network for control
valve actuation (including electrics of 021A & B as
required) complete with associated civil work.
file:///conversion/tmp/scratch/472271567.xls Page 1 of 3
SL. PKG NO Package Name Major/ Draft TS FTS Price Bid Contract Turn Non-
NO. Balance Issued Opened Signed key Turnkey
(T) (N-T)
6 011-03 Relocation of SMS Repair shop & SMS Testing B 1 1 1 1
laboratory 1
file:///conversion/tmp/scratch/472271567.xls Page 2 of 3
SL. PKG NO Package Name Major/ Draft TS FTS Price Bid Contract Turn Non-
NO. Balance Issued Opened Signed key Turnkey
(T) (N-T)
50 098-III Procurement of Fire Tender. B 1 1 1 1
51 098-4 Procurement of fire extinguishers for service B 1 1 1
1
building beyond respective packages 1
52 099A RAIL & Road Weigh Bridge B 1 1 1 1 1
53 099B Hot Metal Rail Weighbridge(Re-Tender)
54 100-2 Roads B 1 1 1 1 1
55 100-3 Storm water draingae system. B 1 1
1
56 100-4 Road Toping
57 110 Survey of new sites and soil testing. B 1 1 1 1 1
58 111-01 Construction of Flyovers and Road Network. B 1 1 1 1 1
59 113 Relocation of TSS and construction power. B 1 1 1 1 1
60 114A CAS for Mills 1 1 1 1 1
61 116A PSS Stores. B 1 1 1 1 1
62 116B1 Installation of LT Substation in Tap Hole Mass Shop. B 1 1 1 1
1
76 125-02 ACVS for Bar & Rod Mill , URM & Rail welding B 1 1 1 1
1
77 126-01 Gas & Water based Firefighting System for BOF & B 1 1 1 1
CCP, 1
78 126-02 Gas & Water based Firefighting System for Bar & B 1 1 1 1
Rod Mill , URM & Rail Welding 1
Major 33 7 33 7 33 7 33 7 33 7
Balance 57 36 56 36 45 34 37 34 57 36
Total 90 43 89 43 78 41 70 41 90 43
133 132 119 111 133