Vous êtes sur la page 1sur 12

SCOPE SHEET

10

11

12

13

14
SCOPE SHEET

10

11

12

13

14

15

15a

15b

15c

15d

A
SCOPE SHEET

10

11

12

13

13a
13b
13c

4
SCOPE SHEET
5

10
SCOPE SHEET
PLASTER: Approved Suppliers: Dubai plaster, Jupitar chemicals
Subcontractor to supply all Labour, Material, equipment and
Accessories to complete the Plaster works including but not limited
to items mentioned below.
MEP clearance required after conduit fixing

Surface preparation including hacking, concrete surface chipping, fixing guide points.

Supply and fixing approved G.I mesh, angle beads etc

Prepare safe staging /scaffolding by trained/certified scafolders, needs checking / approval

of safety personal prior to use of the same,

Application of Rush Coat as per specification

With clearance of surface preparation & MEP from consultant Contractor can proceed for plastering

Material stacking to be done in such a manner that there should be clear access to villa/workplace

After Completion of the Villa , Final approval of consultant required

Curing to be done as per specification

Regular House keeping to be done and required safety to be adopted as per Jafza regulation,

failing which any action or penalties to be borne by the contractor

Pullout and cube test to be done as when required

Surfaces to be accepted as is. Responsibility of the subcontractor to visit site and be familiar

with existing site conditions,No variations whatsoever will be entertained at later stage.

All required plant&equipment to accomplish the plastering work including material handling must be mobilized
including its periodic maintenance.
by the subcontractor. The plant and equipment must include the following

a) Mortar mixing machine of required capacity and nos.

b) Boom loaders for material handling

c) Jack hammers, chisels etc

d) any other equipments.

Door subframes made of 18mm thk.marine plywood to be fixed around the door openings before plaster work.

Casting of cill concrete where ever required to make up levels.

BLOCK WORK: Approved Suppliers: Apex, ABMCO, Emirates Thermostone, Delm


SCOPE SHEET
Subcontractor to supply all Labour, Material, equipment and
Accessories to complete the Plaster works including but not limited
to items
Work mentioned
Place to be cleaned properlybelow.

Layout for the villa as per drawing to be done with one layer of AAC blocks

After layout approval of the consultant, blockwork t o commence

GI wire mesh to be laid after the 1st layer and then every 3rd layer fixed with GI hold fast

Proper window/door openings as per drawing to be done with plastering tolerance

Approved GI / Precast /cast In Situ lintels to be placed as per drawing.

Work to be done as per plumb and right angle.

Work includes parapet wall

Gap between Blocks and soffit to be closed by approved filler board and cement mortar as required .

After completion the approval of consultant to be done.

Prepare safe staging /scaffolding by trained/certified scafolders, needs checking / approval

of safety personal prior to use of the same,

Regular House keeping to be done and required safety to be adopted as per Jafza regulation,

Failing which any action or penalties to be borne by the contractor

Material stacking to be done in such a manner that there should be clear access to villa/workplace

Testing of blocks to be done as when required

Plant and equipmnet for the proper material handling, mixing mortar etc. must be mobilized by the Subcontractor
including its periodic maintenance.
Boom loaders for Block shifting

Mixer machine for mortar mixing

Dumpers

Any other equipements

Ceramic Tile Fixing


Floor Tiles
SCOPE SHEET
Subcontractor to supply all Labour, Material, equipment and
Accessories to complete the Plaster works including but not limited
to items mentioned below.
Surface preparation which includes cleaning the surface to receive tiles free from dust,
loose particles, projections etc, to the satisfaction of consultant.
Marking levels and provide slopes as per approved shop drawings.
Follow shop drawings for laying tiles.
If the tile requires to be cut, it has to be cut properly to required sizes using tile cutting m
The backing screed mortar for tile fixing must prepared only after
consultant's clearance for the tiling works
The mortar must be prepared using approved proportions of cement and sand.
Mixer machines must be used whenever hand mixing is not permitted.
Tiles must be laid immediately on the mortar bed using approved size
tile spares to provide uniform joint
Proper tamping must be done to ensure that no air gaps are left.
Any hollow tiles noticed must removed and replaced.
Tile damaged due to bad workmanship will be charged.
Proper joint grouting must be done after approved by consultant with matching tile colou
Proper housekeeping and protection works must be exercised.
Plant and equipmnet for the proper material handling, mixing mortar etc. must be
mobilized by the Subcontractor including its periodic maintenance.

Boom loaders for material handling and shifting


Tile cutting machine
Any other equipements

Wall Tiles

Wall tiles must be fixed using approved tile adhesive on a pre-plastered wall surfaces.

Water proof adhesive must be used wherever specified.

Tiles must be laid truly vertical.

Both horizontal and vertical joints must be at right angles to each other and uniform in size.
SCOPE SHEET
Border tiles if any shall be fixed at height approved in the shop drawings.

Proper jointing and grouting must be done as per approved sample and color.

The adhesive must be spread to required thickness on the back of the tile and

wall surface as per manufacturer's recommendations and any hollow tile must be

removed and replaced.

All damaged wall tiles cost will be charged to subcontractor's account.

Proper house keeping and protection must exercised.

Plant and equipmnet for the proper material handling, mixing mortar etc. must be
mobilized by the Subcontractor including its periodic maintenance.
elmon
g machine

lour.

Vous aimerez peut-être aussi