Planning Irrigation
and Drainage
Investment Projects
Technical Paper 11
1996
FAO Investment Centre
Table of Contents
Preface 1
Introduction 2
Why New Guidelines? 2
Objective and Organisation of the Guidelines 3
Complementarity with Previous Investment
Centre Guidelines and Papers 4
Effective Implementation 15
Implementation Capacity and External Technical Assistance 16
Participation, Ownership and Commitment 17
A Possible Role for Non-Governmental Organizations (NGOs)
in Participatory Development 19
Fiscal Sustainability 20
The Need for Cost Recovery 20
Cost Recovery, O&M and Water Charges 21
Users’ Contributions to Capital Costs 22
Preface
This Investment Centre Technical Paper was prepared by Tony Peacock
(consultant), with technical and editorial guidance from Simon Hocombe
and Andrew MacMillan, Senior and Principal Advisers respectively in the
FAO Investment Centre Division. The paper benefited from consultations
with Volker Branscheid, Alice Carloni, Jacques Chabloz, Kingsley De
Alwis, Random DuBois, Michael Fitzpatrick, Paolo Lucani, Romano
Pantanali, Peter Smith, Michael Wales and several other staff of the
Investment Centre, as well as Hans Wolter of the Land and Water
Development Division of FAO. Constructive comments were made on the
draft by external reviewers including: staff of the Asian Development Bank,
coordinated by Robert May; Timothy Stephens, Senior Irrigation Engineer,
African Development Bank; staff of the Agriculture and Natural Resources
Department of the World Bank, coordinated by Hervé Plusquellec; Linden
Vincent, Lucas Horst and Frans Huibers of Wageningen Agricultural
University; Laurence Smith of Wye College, University of London; Brian
Albinson and Donald Campbell (consultants) on behalf of the International
Irrigation Management Institute; and James Dempster, Jan Doorenbos, Peris
Sinnett-Jones, Robert Rangeley and Tony Zagni (consultants). Orla White-
Natalizia, Janet Francis and Marilou Mechitarian formatted the final text.
Introduction
WHY NEW GUIDELINES?
A recent World Bank review of its experience with irrigation investment projectsa
found that, of 208 Bank-funded irrigation projects evaluated, only two thirds had
satisfactory outcomes. Even those projects rated as satisfactory indicated a
substantially lower economic rate of return at evaluation (average 15%) than
expected at appraisal (average 22%). Twenty of the projects were later subjected to
impact evaluation by the Bank's Operations Evaluation Department (OED), and for
these the average outcomes were 17.7% at appraisal, 14.8% at project completion
audit, and only 9.3% at OED impact evaluation. The Bank concluded that the initial
assessment that two thirds of its projects had satisfactory outcomes may be too
sanguine, and that there is ample room for improvement.
1: For brevity, the single word "irrigation" is most often used for the rest of the text. However it should be
taken to include drainage as appropriate throughout; it may also imply reclamation or water control generally.
2: Effective Implementation: Key to Development Impact. Report of the World Bank's Portfolio Management
Task Force (often referred to as the Wapenhans Report). World Bank, Washington DC (1992).
Guidelines for Planning Irrigation and Drainage Investment Projects 3
The World Bank Task Force stressed that the ultimate success of a
project is to a significant degree determined by what happens in the
“upstream” planning process, and that many implementation problems can
clearly be traced to deficiencies here. These findings are now considered
generally valid by other international financing institutions and donors. The
lessons learned regarding these problems, and the new approaches that
have been developed to tackle them, therefore make new guidelines
essential and timely.
The Guidelines are divided into two main parts. Following this
introduction (white paper), the first part (blue paper) briefly discusses the
main lessons learned in recent years and their implications for the project
planning process. The second part (yellow paper) describes the process itself,
the roles of the borrowers, lenders and planning teams in it, and the
1: Economic rent is the income earned from the use of an input (in this case water) in excess of its cost.
Economic rent can be earned even in the case of an activity that is socially unprofitable, ie uneconomic,
if government subsidies relieve the farmer from the requirement to pay for part or all of the input.
Guidelines for Planning Irrigation and Drainage Investment Projects 4
1: For example Donald Campbell, World Bank Technical Paper 256, Design and Operation of Smallholder
Irrigation in South Asia. World Bank, Washington DC (1995) which addresses most of the technical and
operational issues and problems arising in irrigation/drainage system design. Numerous other sources are listed
in References and Bibliography, at the end of the document.
Guidelines for Planning Irrigation and Drainage Investment Projects 5
PART 1:
Recent lessons and
implications for planning
Since the ultimate success of an investment is largely determined by the
quality of the upstream process of planning, it is pertinent to examine
recent lessons learned from experience and their implications for future
planning. The main lessons are that water is an increasingly scarce resource
for which there are many competing demands that are more profitable,
socially and economically, than irrigation; also that low world prices for
basic food and fibre crops, together with typically high development costs,
have recently made new irrigation development increasingly difficult to
justify. Even so, world food supply will depend even more on irrigation in
the next century than in the present. Future irrigation investment must
therefore focus on lower cost solutions, both for new development and
rehabilitation, on making better use of existing irrigation facilities and on
increasing output value per unit of water used. Planners should seek to
establish the conditions that will promote this focus.
Cities and industries can afford to pay more for, and earn a higher
economic rate of return from, a unit of water than agriculture. Hence
governments and financing institutions are being forced to reconsider the
economic, social and environmental implications of investment in
irrigation. As a result, it is likely that in future the water sector will be less
1: The background to this is described, for example, in the World Bank Policy Paper Water Resources
Management, World Bank, Washington DC (1993) and in Land and Water Bulletin 3 Water Sector Policy
Review and Strategy Formulation: A General Framework (prepared jointly by the World Bank, UNDP and
FAO), FAO, Rome (1995).
Guidelines for Planning Irrigation and Drainage Investment Projects 6
These Guidelines however start from the assumption that water policy
reviews have indicated that irrigation is a justifiable option within the
context of a country’s overall water resources management strategy, and
that investment finance could be made available for its development. The
Guidelines therefore do not cover the principles and processes involved in
water resources management strategy formulation, which are well covered
elsewhere1. The need for project planning to be in strict conformity with
such strategies nevertheless cannot be overemphasised.
Irrigation Typologies
With about 250 million hectares irrigated throughout the world in vastly
different climatic and socio-political environments, some categorisation of
irrigation may be thought desirable. Numerous typologies are commonly
used, such as size, the nature of the water source, and whether schemes
are operated publicly or privately. Definition by size presents difficulties on
a global level, since, for example, what might be considered large-scale in
some countries in Sub-Saharan Africa would be considered as only small
or medium-scale in South Asia. Furthermore, many of the problems
confronting publicly financed irrigation transcend scale, and some
attempts at categorisation have confused “small-scale” with “traditional” or
“informal” irrigation.
1: See for example: Land and Water Bulletin 3, Water Sector Policy Review and Strategy Formulation: A
General Framework (prepared jointly by the World Bank, UNDP and FAO), FAO, Rome (1995); Water
Report 6 Methodology for Water Policy Review and Reform (Proceedings of the Expert Consultation on Water
Policy and Reform - Rome, January 1995), FAO, Rome (1995); Irrigation and Drainage Paper 52 Reforming
Water Resources Policy: A Guide to Methods, Processes and Practices, FAO, Rome (1995).
Guidelines for Planning Irrigation and Drainage Investment Projects 7
Definition by the type or nature of the water source does not recognise the
very different characteristics of major public surface water schemes based
on dams in the USA, for example, and small community-managed tank
irrigation schemes in Sri Lanka.
1: Rice schemes nevertheless require adequate surface drainage, as total inundation of the crop leads to
significant yield losses.
Guidelines for Planning Irrigation and Drainage Investment Projects 8
It includes:
There are numerous other arguments for and against large or small
irrigation schemes: for example, the obvious economies of scale and
multiplier effects of large schemes (see Box I-1). Many of the arguments are
valid in some countries, for certain irrigation types, but not in others. Thus,
generalisation should be avoided and the issue of scale should be
approached considering the individual circumstances of the project and
institutional capacities in the country concerned. As will be seen, there are
more important issues than scale: the overwhelming experience is that what
is important in predisposing irrigation to success is the extent to which it
enjoys the commitment of stakeholders2 to good engineering design, quality
construction, efficient operation and adequate and timely maintenance.
1: Report No 13676: A Review of World Bank Experience in Irrigation. Operations and Evaluation
Department, World Bank, Washington DC (1994).
2: The term stakeholders includes all individuals who may be positively or adversely affected by the project:
government planning agencies (planning units, senior decision-makers, Ministers); government implementing
and operating agencies (senior and middle level management of line ministries) who may be subsequently
responsible for project implementation, operation and management; community-based organisations,
including water users' associations (WUAs) or other farmers' organisations; individual farmers; public interest
groups; non-governmental organisations; (NGOs) and private sector companies; financing institutions; and
international project planning teams such as those provided by the Investment Centre.
Guidelines for Planning Irrigation and Drainage Investment Projects 10
For: For:
Engineering economies of scale usually Usually less exacting technical
possible, hence lower unit costs. demands for high level professional
skills for planning, implementing,
Borrowers more disposed to take the operating and maintaining.
actions necessary to ensure that project
succeeds. Greater opportunity for farmers to
participate in planning, financing,
Economies of scale result in cost- implementing, operating and
effective provision of extension services maintaining.
and social/economic infrastructure.
Better adapted to supplying local
Greater regional impact of secondary markets with (high value) horticultural
benefits. products without depressing prices.
1: See Soils Bulletin 57: Soil and Water Conservation in Semi Arid Areas, Land and Water Division, FAO,
Rome (1987); Investment Centre Technical Paper 10: Agricultural Investment to Promote Improved Capture
and Use of Rainfall in Dryland Farming, FAO, Rome (1995); also Technical Paper 221: Conserving Soil
Moisture and Fertility in the Warm Seasonally Dry Tropics, World Bank, Washington DC (1993).
Guidelines for Planning Irrigation and Drainage Investment Projects 12
1: Paradoxically perhaps, the expansion of irrigation over the last 50 years has been a major factor in the
decline in prices, since it has caused relatively strong growth in supply of rice and wheat compared with
growth in demand.
2: Investment Centre Technical Paper 5, Irrigation in Africa South of the Sahara, FAO, Rome (1986).
3: Doubts over the use of World Bank price forecasts for food and fibre crops have often been expressed.
However, in the absence of any better alternatives, the analyst can do no more than attempt best guesses
based on the Bank's forecasts, or explore possible future differences between forecast and actual prices
through sensitivity analysis.
Guidelines for Planning Irrigation and Drainage Investment Projects 13
The introduction and rapid spread of high-yielding rice and wheat varieties
combined with heavy investment in irrigation and rapid growth in fertiliser use in the
late 1960s and the 1970s resulted in strong growth in output of these crops in Asia.
For rice, the rate of growth of yields increased from 1.7% per annum during 1958-66
(before the spread of modern technology) to 2.9% during 1974-82. However, growth
in rice yield, the primary contributor to rice output growth throughout these periods,
has slowed to 1.9% annually since the early 1980s.
Area expansion contributed about one-third of Asian rice output growth during
1966-74, but little after that. The annual growth rate in rice output therefore declined
in the 1980s, from 3.1% in 1974-82, to 2.2% during the period beginning in 1982.
Similar trends have occurred with wheat output.
However, the main reasons for declining investment are the increasing real costs per
hectare of new irrigation development and decline in world rice and wheat prices.
Rosegrant and Svendsen presented real capital costs for construction of new
irrigation systems in five countries in South and SE Asia over the period 1966-88, the
unweighted average for which increased by a factor of 2.5, from US$1,744 to
US$4,385 per ha, over the period. The real price of rice and wheat over this period
was halved, representing a swing of a factor of 5 in the ratio of costs to benefits.
a: World Bank, Asian Development Bank, Japanese Overseas Economic Cooperation Fund, and US Agency
for International Development.
Source: Mark W Rosegrant and Mark Svendsen (1993), Asian Food Production
in the 1990s: Irrigation Investment and Management Policy,
“Food Policy”, February 1993.
1: There are exceptions to this rule: one such system has been satisfactorily demonstrated for the irrigation of
cassava in some Sahelian countries.
Guidelines for Planning Irrigation and Drainage Investment Projects 15
EFFECTIVE IMPLEMENTATION
Experience to date, well summarised in the 1992 report of the World
Bank’s Portfolio Management Task Force referred to earlier, makes it clear
that a key condition for sustainable development impact from irrigation
investments is implementability. This requires:
International donors, including the World Bank, are fast destroying the development
capacity of Africa due to conditionalities tied to their aid, Mr Edward Jaycox, the World
Bank vice-president for Africa region has said and warned that this could defeat the
continent’s economic recovery programmes. “The donors and African governments together
have, in effect, undermined capacity building in Africa. They are undermining it faster than
they are building it, or at least as fast. This has got to stop, otherwise we are not going to
succeed in the development effort in Africa,” Mr Jaycox said in Washington last week.
He charged that resident expatriate technical assistance officials were systematic destructive
forces, undermining the development capacity in Africa because most of their technical
assistance was imposed. “It (technical assistance) is not welcome, there is no demand for it
really, except on the donor side. When I talk about donors, I am including the World Bank
... I, for one, would like to see this changed,” he said.
He said very scant attention was paid to appropriate project design. “We design a project
and then we find a big mismatch between the project design and the local capacity to carry
it out. So we throw money and technical assistance at this, thinking that will bridge the gap.
Well, it has not and I do not think it will ... This is in fact, an endemic problem in the donor
community - expatriate management substituting for domestic management”. Mr Jaycox
said to alleviate Africa’s capacity building problems, there was a need to create a demand
for professionalism on the continent.
Guidelines for Planning Irrigation and Drainage Investment Projects 17
1: This is the basis of genuine demand-driven development. Soliciting or orchestrating requests from farmers
for government investments in irrigation is not - even if the prospective users promise or agree to make a
contribution at some later date. Often farmers are driven by other motives in these circumstances, such as
temporary wage employment on scheme construction, and they later lose interest in the irrigation scheme.
Guidelines for Planning Irrigation and Drainage Investment Projects 18
The most common kinds of alterations observed were channels being relocated,
streams being diverted or ponded, project channels being abolished or not used, and
channel offtakes or division points being relocated. Other actions included redirecting
project channels into drains or streams, making new channels, adjusting division box
gates to alter water divisions, making new flumes, destroying project flumes and lining
channels. Several cases involved relocating channels to follow farm boundaries, to
accommodate low water requirement crops or to continue to make use of pre-existing
farmer-built structures such as small weirs, channels and ponds.
The most frequent reasons reported by farmers for making design changes related to
questions of conveyance and distribution efficiencies, farm boundaries and the
conjunctive use of alternative water sources (in this case from natural waterways or
from return flow).
1: Some reports define all groups which operate outside the public sector as NGOs. In the context of these
Guidelines the acronym NGO is used in a narrower sense, to mean a charitable, non-profit making
organization, generally working at the grassroots level.
2: For example, the National Irrigation Administration in the Philippines. See An Evaluation of NIA's
Participatory Communal Programme, Public Intervention in Farmer-Managed Irrigation Systems, IIMI,
Colombo (1987).
FISCAL SUSTAINABILITY
It has also been argued that the complexity of some irrigation and
drainage schemes justifies state intervention and subsidising of part of the
investment costs, without which some worthwhile projects may not have
been constructed. In these cases capital costs not recovered may not really
be subsidies if all the secondary benefits of irrigation development are
taken into account. In a case study of the Muda Irrigation Project in
Malaysia, for example, it was found that for every dollar of value added
generated directly by the project, another 80 cents were generated
downstream1.
1: Bell, Clive, Peter Hazell and Roger Slade, Project Evaluation in Regional Perspective. Johns Hopkins
University Press (1982).
Guidelines for Planning Irrigation and Drainage Investment Projects 21
1: See Vollrath T.L., The Role of Agriculture and its Prerequisites in Economic Development: A Vision for
Foreign Development Assistance. In: Food Policy 1994 19 (5) 469-478.
Guidelines for Planning Irrigation and Drainage Investment Projects 22
incentive for the efficient use of water and may thus contribute to wasteful
usage. Even if it were possible to charge individual farmers for water on a
volumetric basis, which it seldom is for most surface irrigation systems
involving smallholders, setting an appropriate charge may present some
difficulty because of local economic distortions (see Box I-5 above).
Nevertheless, without some form of volumetric charging, individual
irrigators have little incentive to make more efficient use of water.
1: Drawn from Irrigation and Drainage Cluster - Module: The Role of Water User’s Associations, IFAD, Rome
(Draft 20/10/94).
Social research and experience have shown that irrigation projects in some
developing countries provide irrigation engineers and other operational personnel
with opportunities to raise significant amounts of illicit revenue from the distribution
of water and contracts, some of which is redistributed to superior officers and
politicians. Thus, in return for financial inducements, irrigation engineers will award
contracts to high-priced or unqualified, incompetent contractors, and “turn a blind
eye” to substandard work that saves costs for the contractor and increases his profit.
The results of such corruption are not usually immediately apparent, but substandard
work obviously has a detrimental impact on subsequent maintenance requirements
and costs, contributes to the vicious circle of poor maintenance-poor cost recovery-
poor maintenance, and hence has an obvious bearing on sustainability. Financial
inducements may also be used to bribe ditch-riders and other operational personnel
to enhance water supplies to one farmer, or a group of farmers, at the expense of
others, usually the poorest and least powerful, which often means tailenders.
1: Kerry J Byrnes, World Bank Technical Paper Number 173, Water Users Associations in World Bank-Assisted
Irrigation Projects in Pakistan, World Bank, Washington DC, 1992.
2: Meinzen-Dick R. et al., Sustainable Water User Associations: Lessons from a Literature Review.
Paper prepared for World Bank Water Resources Seminar, 1994.
Guidelines for Planning Irrigation and Drainage Investment Projects 26
• WUAs are stronger if they can build upon existing “social capital”, or
patterns of cooperation. It is therefore advantageous to work with
existing successful organisations wherever possible. Whether existing
or new organisations are involved in irrigation management, the
organisations should be adaptable - to their local conditions and to
changes over time. WUAs are also likely to be stronger if they are
relatively homogenous in terms of members’ background, and assets.
However, heterogeneity is manageable (or even, in some instances,
desirable), and defining membership to include all stakeholders -
including tenants and women - improves equity.
• There is no single “optimal size” for WUAs. As size increases,
transaction costs increase and it becomes more difficult for members
to monitor each other. However, larger WUAs can achieve
economies of scale, and take on more tasks in irrigation
management. Federation allows WUAs to expand and operate on a
larger scale, while still maintaining manageable interactions among
members of base-level groups.
• The structure and role of WUAs depend on their degree of
commercialisation. Greater commercialisation allows WUAs to
replace direct labour or in-kind participation of members by hiring
specialists, and allows them to expand in size. However, it also
creates a much greater need for accountability of leaders and
employees to the membership.
• The range of WUAs shows great variability, but two broad models can
be identified. The first, (or “Asian model”) typically relies on direct
participation of all members, with smaller base units. These are often
socially based, multipurpose organisations and are likely to be most
appropriate in socially cohesive societies with smaller land holdings,
low market penetration and simpler irrigation technology. The second,
(or “American model”) is a more specialised organisation based on
hydraulic boundaries, and the organisations are focused on irrigation
rather than multiple activities. Such organisations are appropriate to
situations of larger land holdings, greater market development, and
more complex technology.
• In any type of WUA, the benefits to farmers should outweigh the cost
of membership. The benefits of improved water supply, increased
farm income, and conflict resolution obtained through WUAs should
offset the substantial time, materials, cash, and interpersonal
transaction costs of being involved in the WUA. This implies that
irrigated agriculture should be profitable enough to create a demand
for water, and WUAs should have a demonstrable effect in improving
farmers’ control over water.
• Organised farmers in WUAs can manage more advanced technology,
and higher levels of irrigation systems. Their expanded role in main
system management can provide a greater degree of control over
water supplies, which is a major incentive for farmers to participate
in WUAs.
Guidelines for Planning Irrigation and Drainage Investment Projects 27
Despite the years of experience and the lessons learned - and despite
the existence of clear operational guidelines for dealing with social and
environmental issues - governments, financing institutions, project planners
and implementers have in the past often paid only lip service to the need
for systematic problem identification, assessment and mitigation. In the
past one of the reasons for this was that promoters and implementers of
irrigation projects found that addressing such issues was an inconvenience,
as well as a likely source of project delays or cancellations. And even
though environmental legislation existed, environmental agencies
generally did not have the teeth to implement regulations; if planners
wished to strengthen these agencies in parallel with the formulation of
irrigation investment proposals, it was already too late.
1: Practitioners are referred to Orstrom, E., Crafting Institutions - Self-Governing Irrigation Systems, ICS Press,
San Francisco, California (1992) which covers some practical planning principles which can be applied in most
cases. Also Yoder, R., Locally Managed Irrigation Systems - Essential Tasks for Assistance, Management
Transfer and Turnover Programmes, IIMI, Colombo, Sri Lanka (1994).
2: According to the 1990 FAO report An International Action Programme for Water and Sustainable
Agricultural Development: A Strategy for the Implementation of the Mar del Plata Action Plan of the 1990s,
20 to 30 million hectares (or about 10 percent of the world's irrigation) is severely affected by salinity and an
additional 60-80 million hectares are affected to some extent.
Guidelines for Planning Irrigation and Drainage Investment Projects 29
Box I-7 - Some Social and Environmental Issues in World Bank-Financed Irrigation
Project Planning
The 1994 World Bank review of its irrigation experience commented as follows on
the coverage of gender issues in its sector work:
“Irrigation affects men and women differently. Even if they have equal roles in
agriculture, which they usually do not, women almost always have primary
responsibility for such household tasks as food preparation, washing and
providing drinking water. However, except for the most recent studies on
Mexico and India, none of those (sector reports) analysed was found to have
addressed the subject.”
CHOICE OF TECHNOLOGY
Commonsense dictates that the choice of technology for irrigation
should be based on its appropriateness for the cropping patterns intended
and should also consider cost-effectiveness. Irrigation engineers have in
the past tended to overlook an additional need: for the technology also to
be matched to the level of sophistication or operational capacity of the
users. It has become increasingly obvious that the design process must
start from a consideration of how the users will operate the system; this
should then be designed to provide the optimum combination of efficiency
in water use and cost effective operation and maintenance.
Guidelines for Planning Irrigation and Drainage Investment Projects 30
Equally important, the designer must consider how the user will cultivate
his land, and the implications that this may have for scheme layout. Thus it
may be that the design which involves the lowest investment cost per
hectare may not be the most cost effective solution if it also involves large
numbers of staff for its operation, or if, because of operational difficulty, it
cannot be utilised to capacity. On the other hand, a design to improve
water use efficiency on a traditional irrigation system by the introduction
of “modern” water control structures may not result in overall efficiency
gains if the users reject the modern controls in favour of their traditional
proportional dividers.
1: Burns R., Irrigated Rice Culture in Monsoon Asia: The Search for an Effective Water Control Technology,
World Development XXI, (May 1993), pp771-789.
2: e.g. in World Bank Technical Paper 246, Modern Water Control in Irrigation (1994) by Plusqullec et al.,
World Bank Technical Paper 256, Design and Operation of Smallholder Irrigation in South Asia (1995) by
Donald Campbell, and numerous IIMI publications.
Guidelines for Planning Irrigation and Drainage Investment Projects 31
past. At the same time there is a need to improve water use efficiency to
reduce the drainage demands of the future.
1: Campbell D., Design and Operation of Smallholder Irrigation in South Asia, World Bank Technical Paper
256, World Bank, Washington DC (1995).
Guidelines for Planning Irrigation and Drainage Investment Projects 32
• Although world food supply will depend even more on irrigation in the
next century than it has in the past, the per hectare capital costs of
typical new irrigation development may be difficult to justify by the
returns from basic food crops alone. Until lower cost solutions can be
found, or demand forces the price of basic food crops up, irrigation
investment to achieve incremental food production may be limited to
upgrading existing formal and traditional irrigation systems.
• Apart from the obvious technical and financial conditions, the key
condition for sustainable development impact from an irrigation
investment project is its implementability. This requires that the
institutional demands of the project are matched to local institutional
capacity, and that stakeholders are genuinely committed to the project
through participation and local ownership. The conventional project
identifiation/preparation approach of the past has militated against these
requirements being met.
• Economic efficiency and fiscal sustainability demand that the O&M
costs and at least a part of the capital costs of irrigation should be
recovered from the users. However, in practice this is rarely achieved.
Fiscal crises in many developing countries are now forcing
governments to devolve responsibility for existing schemes to the
users or private companies, and to ensure that users of new schemes
accept responsibilty for O&M from the outset. This often requires
institutional reorientation of irrigation bureaucracies, the formation of
users’ groups or WUAs, and an even greater need for participation
and local ownership.
• Adverse social and environmental impacts are significant contributors to
project failures. Despite past mistakes, governments, financing
institutions, planners and implementaers continue to pay only lip service
to the need for impact assessment. The consensus now is that social and
environmental impact assessment is as essential and important a tool as
economic analysis in planning successful projects and programmes.
• Drainage should be given much more prominence than in the past, in
both strategy formulation and the planning of individual projects.
The implications of these lessons for the planning process are that:
• Project planning needs to centre more on the borrower and the users,
and less on the requirements of the lender, and to emphasise
participation and capacity-building features. Whilst project planning has
always been a government responsibility, there needs to be even greater
insistence on international project planning teams, such as those
provided by the Investment Centre, facilitating and assisting in the
planning process by complementing and supporting local preparation
groups, and even greater reluctance to give outside teams direct
responsibility for the tasks involved. Increasingly therefore, external
technical support should involve providing inputs and support to a
process that is driven by the borrower and involves contributions from
many, diverse local stakeholders.
Guidelines for Planning Irrigation and Drainage Investment Projects 33
PART 2:
The planning process
GENERAL
justify, given the prevailing low prices for basic food and fibre crops.
Together, these factors have led to modified approaches to lending in the
subsector: most financing institutions have become more concerned with
the objectives of participation, ownership and capacity building than they
have been in the past. Lending has increasingly tended to take the form of
sectoral loans, to support these objectives and to finance more efficient
investments in terms of costs, benefits and water use. Projects tend to
favour rehabilitation and/or modernisation of existing schemes, and the
transfer of part or all of the management responsibility to the users.
Investments may be made on a national or regional basis, at a pace that is
matched to local capacity for implementation.
intended to:
1: If a water resources management strategy has not yet been prepared, it will be necessary for the subsector
review team to make its own assessment of potential and competing demands. The opportunity cost of water
should have been determined in the water resources strategy study; if not, in view of the complexity of the
issues involved, it is unlikely to be possible to determine this within the time frame of a subsector review, so
that this may need to be the subject of a separate supporting study.
Guidelines for Planning Irrigation and Drainage Investment Projects 39
1: An international waterway can be defined as any river, canal, lake or similar body of water that forms a
boundary between or flows through, two or more states, and can include any tributary of these. However, an
exception would be any tributary of an international waterway that runs exclusively in one state and the state
is the lowest downstream riparian. See Operational Policy OP 7.50 (October 1994) from the World Bank’s
Operational Manual for further details of the Bank’s definition and its policy on this matter.
Guidelines for Planning Irrigation and Drainage Investment Projects 40
If time and staff resources permit, the opportunity should be taken here to
assess the scarcity value of water to farmers, ie the price that they would be
prepared to pay for water in a competitive market. This may be considerably
more than they are actually paying at present, particularly if they are
irrigating high value crops, and may have a bearing on fixing the appropriate
water charge where improved water use efficiency is being sought1.
Such an analysis can help to identify any crops for which there may be
comparative advantage under the various options for irrigation
development, although possible market constraints should be clearly
flagged, particularly when considering high-value crops.
1: See Ronald G Cummings and Vahram Nercissiantz, The Use of Water Pricing to Enhance Water Use
Efficiency in Irrigation: Case Studies from Mexico and the United States, in World Bank Technical Paper No
249, Water Policy and Water Markets. Eds. Le Moigne et al., World Bank, Washington DC, (1994).
2: A good example is given in Jansen D J, Economics of Irrigation: A Modular Methodology for Comparing
the Benefits with the Costs. Background Paper prepared for the Planning and Research Unit, Ministry of Lands
Agriculture and Water Development, Government of Zimbabwe, as an input to the National Irrigation Policy
(1993). Also Working Paper: Estimating the Economic Efficiency of Irrigation: The Case of Brazil.
FAO/World Bank Cooperative Programme, Rome (1989).
Guidelines for Planning Irrigation and Drainage Investment Projects 41
The issues that will arise could include those described below, but the
importance of each will differ from country to country. The planning team
should take care to focus on those that are relevant and not waste effort on
those that are not.
1: This is a common constraint in many parts of Sub-Saharan Africa for example, where family labour shortages
oblige farmers to consider agricultural activities in terms of the returns to labour rather than unit of land.
Returns to labour in dryland farming can often be greater than for irrigation, and in these circumstances when
family labour is short farmers may neglect irrigated plots in favour of dryland crops.
Guidelines for Planning Irrigation and Drainage Investment Projects 42
• the domestic and export demand and market prospects for irrigated
crops and the extent to which limited demand, especially for high
value crops, could set a ceiling on the area of new irrigation which
might feasibly be developed; and
• the extent to which the country or region enjoys a comparative
advantage in the production of specific irrigated commodities.
• insecurity of land tenure and the constraint that this may place on
private sector investment, by both large and small-scale farmers;
• constraints to irrigation development posed by land fragmentation,
and obstacles to land consolidation;
• legal and administrative problems of land re-distribution and
restitution to previous owners, for example in Central and Eastern
European countries and in others where individual tenure was not
previously allowed;
• similar problems related to consolidation of fragmented land1;
• provision for legal establishment of users’ groups, and implications for
subsequent operation and maintenance; and
• security of water rights, tradeability, equitable compensation for rights
rescinded, and impact on private sector investment;
• equity considerations, especially if farmers do not pay for land on
public irrigation schemes;
• the effect of all the above on users’ commitment to the proposed
development and O&M;
• regulations and controls on environmental impacts, and the existing
institutional capacity and legal framework for enforcement;
• dam safety regulations and means of enforcement;
1: For detailed treatment of this topic see forthcoming FAO Irrigation and Drainage Paper Land Consolidation
in Irrigation and Drainage Projects.
Guidelines for Planning Irrigation and Drainage Investment Projects 43
Where a single, centralised financially autonomous irrigation agency exists, fees can
be either project-specific or uniform. If there is no inherent reason for project-
specific fees, the administrative simplicity of uniform fees is an attractive option; the
question of charging different rates among different water users does not arise. There
may however be a logical basis for charging different fees to different users between
or within projects if the costs of providing water to them are different. It can be
argued that each set of water users should pay the cost of providing water to them,
and not some average, possibly subsidised, cost; higher fees should be charged to
those for whom the cost of providing water is greater. In practice, however, the
administrative burden of collecting differential fees is usually too great to warrant
such an approach.
The question of the “right” charge for irrigation water therefore needs to be put in
perspective in formulating strategy: in reality, true water pricing is seldom practised.
In situations where pricing is possible, the establishment of the price system itself -
giving water a positive marginal cost to the users - may be more important than the
precise level at which the price is set. Nevertheless, if financial autonomy is a real
possibility, then it will be essential to design a pricing system which generates
sufficient revenues to cover the irrigation agency’s recurrent O&M costs.
1: Settlement schemes for example can influence who benefits by setting criteria for settler selection.
Guidelines for Planning Irrigation and Drainage Investment Projects 45
Strategy Formulation
Defining Strategic Options and Measures
On the basis of the review of the topics discussed above it should first
be decided whether there are more cost effective alternatives than
irrigation for meeting government’s objectives, such as intensified rainfed
production. If not, the most appropriate type and scale of support for
irrigation and drainage development should be identified, and the options,
physical and other, for achieving this in a sustainable way considered.
These may consist of improving the performance of existing irrigation
development; new development, where this can be achieved
economically. The key elements are: average crop yields under the various
farming systems (irrigated, non-irrigated, public smallholder scheme, large
privately-owned commercial farm, surface irrigation, sprinkler irrigation,
and so on); financial and economic crop prices; average input
requirements and production costs for each of the crop/farming system
options; average irrigation costs, including capital and O&M costs of
storage and conveyance works, distribution and in-field works, for each of
the categories involved. It is however unnecessary or even undesirable to
spend much time and effort in collecting and preparing new data during
strategy formulation. Ideally the review team should work with existing
data which should be already available from the planning branch of the
irrigation agency; alternatively the agency should be requested to assemble
the data in advance of the review/strategy formulation work.
Approximations can be made, as the purpose is to provide a quick
comparison between crop and farming system optio encouraged by
financial disincentives to wasteful use, such as charging for water at or
near its scarcity value. In some countries significant gains can be made by
Guidelines for Planning Irrigation and Drainage Investment Projects 46
1: This does not mean merely soliciting requests for more government investments from farmers.
2: Farmers are unlikely to contribute to capital costs without security of land tenure and water rights.
Commitment can be enhanced by allowing farmers to pay for irrigated land, either on a freehold or leasehold
basis. Thus land tenure policy changes, legislation, and provision for cadastral mapping may be required. An
alternative to the provision of free labour might be to employ prospective users as labour on a wage basis at
the market rate, but to make an agreed deduction from wages to cover the required contribution to
construction costs.
Guidelines for Planning Irrigation and Drainage Investment Projects 48
Objectives
The main objective of this part of the planning process, which may be
compared with identification in the conventional sequence, is the
conceptualisation and preliminary examination of one or more investment
options that conform with subsector priorities. Alternatively, if options have
already been suggested as part of a subsector review and strategy
formulation, they should be explored further. In either case, the intention is
to assist the government in selecting its preferred option, to plan next
steps, and to promote rapid progression to the final stage of the planning
process. Experience has shown that this is the most crucial and sensitive
stage of planning because it leads to the critical decisions on project
1: For methodologies see De Alwis K and Sonn L, Workshops as a Means of Promoting Ownership in Policy
Formulation and Project Preparation. Draft. FAO Investment Centre, Rome (1994).
Guidelines for Planning Irrigation and Drainage Investment Projects 50
The work may be carried out entirely by the borrower or its LPGs,
including local consultants or local consulting companies. Alternatively
there may be a need for external support from the Investment Centre or
international consultants; involvement will depend on the complexity of
the investment options and the capacity of the borrower and LPGs to
undertake the work within the required timeframe. Where the work is to
be carried out with external support, in most cases it will be advantageous
for the leader of the support team to make a brief preliminary visit to the
country concerned in advance of the main work, to:
• explain the objective of this part of the planning process, what may
be expected from government, and the need for building consensus
among all stakeholders;
• make a preliminary assessment of the available database for the
project, identify any gaps in knowledge and possible sources of ready
additional information, and make arrangements for obtaining it;
• plan the work, including arrangements for field visits;
1: Investment Centre Technical Paper No 6, The Design of Agricultural Investment Projects: Lessons from
Experience. FAO Rome (1989).
Guidelines for Planning Irrigation and Drainage Investment Projects 51
Activities
Review of Available Database
The level of information required for the purpose of conceptualisation
and comparison of options will vary widely according to the scale and
nature of the development. Appendix 1 (at the end of Part II of the
Guidelines) gives an indication of typical requirements. However, sound
professional judgement is required to decide on the needs and to avoid
unnecessary detail.
Guidelines for Planning Irrigation and Drainage Investment Projects 52
For new development, this may include some (but is unlikely to include all,
unless in exceptional circumstances) of the following:
In most cases there will be large gaps in the above, and only a part of
this information is likely to be available; it may require specific studies and
surveys to obtain it. Cases may occasionally occur in which the lack of
data makes it impossible to achieve the objective of guiding a decision on
1: See Soils Bulletin 42, Soil Survey Investigations for Irrigation. FAO, Rome (1979).
Guidelines for Planning Irrigation and Drainage Investment Projects 53
the options. In this case, arrangements should be made to fill the gaps, and
for specialist(s) to return later to assess the new information and form an
opinion on how the new information affects choices open to the
government. What is important is that the process should be kept moving
forward, to avoid unnecessary delay in eventual implementation.
During the field visits the team should always involve government
representatives and members of any LPG. Provided the external team
meets in the evenings for an exchange of information and ideas,
operationally it is usually more practical for the various members to work
independently of the others during the day’s field work, to make the best
use of the time available. The engineer for example may be too busy with
investigations to spend time listening to the agronomist carrying out
interviews. However if there is a sociologist on the team it is usually
appropriate for him/her to work closely with the agronomist, to avoid
duplication not only of their own efforts but also those of the interviewees.
For any major structures there will be a need for geological and/or
geotechnical investigations for foundation design, seepage predictions,
slope stability analysis and availability of naturally occurring construction
materials. If not already available, these investigations will have to be
provided for and completed prior to final design.
1: Developed by the FAO Land and Water Development Division, and presented in FAO Irrigation and
Drainage Paper 46 (1992).
2: A climatic data base, in diskette form, of 3,261 stations in 144 countries in Asia, Africa, the Near East, South
Europe, Middle and South America, presented in FAO Irrigation and Drainage Paper 49. Most planning teams
will find this of practical use.
Guidelines for Planning Irrigation and Drainage Investment Projects 55
1: Irrigation and Drainage Paper 24: Crop Water Requirements, FAO Rome (as revised 1992).
Guidelines for Planning Irrigation and Drainage Investment Projects 56
The team should use field visits and review available databases to
screen the investment options, preferably using the ICID Environmental
Checklist, or an alternative checklist that may be preferred by government
or the financing institution1. Should it be obvious at this stage that any of
1: The ICID checklist, recommended in FAO/ODA Irrigation and Drainage Paper 53, Environmental Impact
Assessment of Irrigation and Drainage Projects, is intended for non-specialists and enables otherwise time-
consuming work to be carried out in advance of expert input. Its simple layout enables an overview of impacts
to be presented clearly, which is of particular value for scoping the subsequent EIA (if one is required) and it
can also be used as a management tool for monitoring purposes at different stages of the EIA, with varying
levels of detail. The ICID checklist is also available as a WINDOWS-based software package, which enables
rapid production of a report directly from the field study.
Guidelines for Planning Irrigation and Drainage Investment Projects 57
1: For previous internationally financed projects valuable information can be obtained from project or
implementation completion reports, supervision reports, etc.
Guidelines for Planning Irrigation and Drainage Investment Projects 58
The World Bank’s approach, as set out in its Operational Directive 4.01, is to
categorise and act upon projects, or project components, under three headings:
2: This software is available from FAO to staff and consultants of FAO and the World Bank, FAO member
government institutions, other multilateral financing institutions and universities at no cost.
3: See Annex 3 for suggested contents and coverage of typical terms of reference.
Guidelines for Planning Irrigation and Drainage Investment Projects 61
1: The use of WINDOWS-based proprietary software, such as Microsoft Project greatly facilitates this and
subsequent progress monitoring, although the use of squared paper and pencil may be more appropriate in
some circumstances.
Guidelines for Planning Irrigation and Drainage Investment Projects 62
although this may not be strictly necessary if an aide mémoire has been
produced: the object should be to move to the next stage of planning as
quickly as possible, rather than redrafting earlier work.
The World Bank-financed Irrigation and Drainage Sector Project in Mexico, prepared
with Investment Centre assistance, is intended to help Government to:
• sustain the irrigation and drainage sector through investments selected on the basis
of rigorous economic and technical criteria, procured competitively and
implemented efficiently;
• decentralise irrigation funding and management through institutional reforms that
would gradually move funding of irrigation and drainage investments from a
centrally managed system of government grants towards a system based on
regional and local public utilities which would help to recover costs through
user charges and collection instruments, and thus help sustain the investments by
the beneficiaries;
• fully utilise existing irrigation schemes by finishing uncompleted works, upgrading
deteriorated infrastructure, and rehabilitating irrigated land affected by
waterlogging, salinity problems and lack of maintenance;
• improve water use efficiency by introducing better water management techniques,
the conjunctive use of surface and ground water, volumetric measurement of
water, providing more adaptive research results, and training of technicians and
farmers in better operation and maintenance of irrigation infrastructure;
• strengthen the institutional capacity of the National Water Commission (CNA) and
user organisations to implement policy programmes, investments and maintenance;
• monitor and help prevent environmental and natural resource degradation; and
• optimise the use of land and water resources in the Irrigation Districts and Units.
Source: Staff Appraisal Report: Mexico - Irrigation and Drainage Sector Project.
Agriculture Operations Division, World Bank, (1991).
Guidelines for Planning Irrigation and Drainage Investment Projects 64
Box II-4 - Suggested Procedure for Screening and Appraisal of Small Dams
for The Highlands Horticultural Development Project, Eritreaa
Following detailed analysis of the costs and performance of a number of existing dams
in the project area, a methodology was developed for the rapid screening of potential
dam sites and subsequent appraisal of the more promising sites. This consists of:
• First stage screening based on rapid survey using reconnaissance equipment and
techniques, including altimeter readings for dam height, and “Abbey level” and
rangefinder measurements for dam crest length and reservoir throwback. From this,
the estimated dam height, embankment volume and storage capacity is estimated
using formulae developed for the purpose. The information derived is then
evaluated against criteria for maximum and minimum required storage ratio (ie the
ratio of mean annual inflow to storage capacity) and the ratio of storage capacity
to embankment volume.
• Second stage screening of those sites passing the first stage, to confirm that
irrigable land is available downstream within 1 km of the proposed dam, that the
area of land to be inundated does not greatly exceed the irrigable area, and that
there is a demand for the dam from the community, evidenced by declared
willingness to contribute towards capital cost.
Once screening has indicated that a dam site is worthy of further consideration for
development it is elevated from the status of “potential” to “promising”, and
prepared for appraisal by carrying out topographic surveys, detailed designs,
estimation of the reliable annual availability of water (using standard formulae
developed for the purpose) and potentially irrigable area (assuming standard
cropping patterns and generalised irrigation requirements based thereon). From this
information investment costs per ha are compared with a budget investment ceiling
that has been determined from cost-benefit analysis, assuming the standard cropping
pattern, typical yields and prices. Provided estimated costs are below the ceiling, and
farmers are still prepared to contribute to the cost, investment is approved.
a: Source: Document No 122/94 TCP-ERI 6 WP2: Eritrea: Agricultural Development Project in Seraye
Province - Working Paper 2: Investigation of Water Resources Development Options in High Potential
Areas of Seraye Province. Investment Centre, FAO, Rome (1995).
Guidelines for Planning Irrigation and Drainage Investment Projects 66
The work involved and level of detail required for planning the
preferred option will vary, depending on the nature of the project or
programme, its information needs, and what has already been achieved in
terms of data collection, analysis and engineering design. For example
there are obvious differences between a project using groundwater and
sprinklers for the intensive production of vegetables by commercial
farmers, and one using a simple river diversion for surface irrigation of rice
by small farmers. These projects are not only different physically, but also
in terms of organisation, markets, need for credit, extension, and so on.
Whether a conventional project approach or the alternative of a
programme approach is adopted, it will still be necessary before funds are
finally committed to demonstrate that individual investments can satisfy
the technical, social, environmental, financial and economic criteria for
viability. What will vary is the timing of the various planning activities in
relation to appraisal. The list of activities which follows should be read
with that in mind - as should Appendix 1, which gives a suggested outline
for a typical project dossier.
1: For an example of a spreadsheet for doing this, see Paper No 78 in Branscheid V, Irrigation Water
Management Briefs: 100 Collected Papers, Investment Centre, FAO, Rome.
2: See: FAO Irrigation and Drainage Paper 29, Water Quality for Agriculture (revised 1985), and FAO
Irrigation and Drainage Paper 48, The Use of Saline Waters for Crop Production (1993).
3: For example the use of locally developed Et/Eo ratios and US Class A pan evaporation data, as is the
widespread practice in Southern Africa.
Guidelines for Planning Irrigation and Drainage Investment Projects 69
FAO Irrigation and Drainage Paper 33a provides a detailed exposition of the
relationship between water supply and yield for various crops. Drought tolerance
varies considerably between species and stage of growth, but the yield/water response
curves of most field crops, with the exception of rice, have flat peaks around the
maximum evapotranspiration. The point at which the response curve flattens out
marks the beginning of diminishing marginal returns to additional water: small
reductions in water supply below that required for maximum evapotranspiration
therefore tend to result in only marginal reductions in yield, and maximum yield is
unlikely to be the optimum yield per unit volume of water applied.
The social and economic efficiency implications of deficit irrigation are obvious:
commercial operators apply the concept to increase farm profit; on public schemes
more people benefit when water is spread over a larger area; in any case the ratio of
the value of goods produced to the amount of water consumed is increased.
Planning for deficit irrigation can lead to substantial capital cost savings, as peak
irrigation requirements and canal discharges are reduced, and this can sometimes
mean the difference between viability or otherwise, provided the cost of developing
the incremental area is low. Deficit irrigation can also lead to even greater economic
gains than maximising yields per unit of water for a given crop: farmers are more
inclined to use water more efficiently and returns can be optimized through more
water-efficient cash crop selection, for example by planting cotton rather than
sugarcane or rice.
a: FAO Irrigation and Drainage Paper 33, Yield Response to Water, FAO, Rome (1979).
2: Soils Bulletin 42: Soil Survey Investigations for Irrigation. FAO Rome (1979).
Guidelines for Planning Irrigation and Drainage Investment Projects 71
• present land use, farm size, farming systems and practices, crop
varieties and yields, use of inputs, and availability of draught power;
• extent and methods of existing irrigation, if any, in the project area;
• if irrigation already exists, past and present irrigated cropping
patterns, yields and trends, on-farm irrigation practices compared
with expectations at initial project planning; an explanation for any
differences, and the reasons for any decline in areas planted or yields
obtained under irrigation;
• for farmers in development schemes similar to those proposed, an
indication of yields and production;
• the existence of any group activities within the area (eg for marketing
and input supply, irrigation O&M) that might have a bearing on the
potential for management transfer to irrigators;
• people’s aspirations and expectations, especially the extent of farmer
interest in the project and implications for project planning;
problems, constraints and means of overcoming them, from the
farmers’ perspective;
• intra-household dynamics; gender relations and disaggregation of
labour; access to and control over land, labour and capital; control of
crops and income from their sale, and the responsibilities of husband
and wife as family providers;
• the household economy, and alternative sources of income from off-
farm employment, on-farm production, petty trading and remittances,
time available for crop and livestock production and other activities;
• any conflicting or competing demands for labour;
• the likely impact of the project on any of the above;
• market opportunities and the implications for potential cropping patterns;
• the respective roles of the public and private sectors in input supply
and marketing;
• the scope for cost recovery, including contributions towards capital
costs and recovery of O&M costs.
1: FAO Investment Centre Technical Paper 9: Sociological Analysis in Agricultural Investment Project Design,
FAO Rome (1992).
Guidelines for Planning Irrigation and Drainage Investment Projects 72
For category “B” projects, although a separate EIA or LAA will not
usually be required, it will normally be necessary to prepare a mitigation
plan for reversible impacts, which may include a monitoring and
evaluation system, again possibly based on the ICID checklist.
The following are some essential considerations for institutional capacity analysis.
Objective: To understand the way the institution currently behaves, and to attempt to
anticipate its reaction to possible alternative interventions, additions and restrictions.
This should enable the planner to understand its likely relationship with a new
project, and if necessary to redesign working arrangements.
• That the “rational actor model” of organisations is the most appropriate. According to
this, organisations should behave like a very clear-headed individual, pursuing some
line of action with an unambiguous intention, using the best available approach.
• That all reasonable people share the same view of the working situation, ie what
the task is, what is sound managerial practice, what strategy and tactics will best
achieve a given end, etc.
• That there is something called leadership, and if it is exercised, it will lead to high
productivity from a given set of staff and resources, by “motivating” staff.
• That there is something called morale, a general mood affecting the quantity and
quality of effort put into work.
Guidelines for Planning Irrigation and Drainage Investment Projects 76
The above approach is part of an orientation towards management that goes back to
the early part of the 20th century, and which emphasises what people should do, as
governed by “logic” (and some set of assumptions, such as those above). More
recently, the emphasis in management science has moved towards examining what
managers (and other inhabitants of organisations) actually do, and using these data to
construct the conceptual framework for the subject. This is a more radical change
than may appear: from the analytic approach, which assumes it is normally possible
to work out the basic structure of a problematic situation by reason alone, to a
synthetic one, which implies that uncovering the most potent ideas about the basic
structure and phenomena in a situation may require field investigation.
The synthetic approach has called into question all the assumptions listed above.
First, it suggests that real organisations typically behave as coalitions of individuals
and interest groups, which may compete for control of policy and other parts of the
action, and which may be subject to partly contradictory pressures from the external
coalition, ie parent bodies, regulators, the public, etc. It accepts that organisational
politics are real - and their effects can be anticipated. From this perspective, an
organisation’s configuration - the fit between its task load, the way its internal
activities are orchestrated, and the nature of its external coalition - is very important.
Secondly, it suggests that different institutions may come to very different
understandings of how best to get things done, ie organisational cultures are part of
the situation; among other things, these define “reasonable” working roles and
behaviour. Finally, it has produced very different models of leadership and
motivation. Most importantly, it has suggested that the knowledge of the formal
structure alone is not enough to indicate whether or not a particular institution will
fulfil some intended function.
1: For guidance on this aspect, see the World Bank/USAID Irrigation Training in the Public Sector: Guidelines for
Preparing Strategies and Programs. Economic Development Institute of the World Bank, Washington DC, 1989.
Guidelines for Planning Irrigation and Drainage Investment Projects 78
• Civil Works
• Equipment
• Technical Assistance
• Training
• Incremental Operating Costs
Economic Analysis
Economic Rate of Return
There are several measures that can be used to demonstrate the
economic feasibility of the project: each has its own advantages and
disadvantages. However, attention here is confined to the Economic Rate
of Return (ERR) which may be defined as “the rate of discount at which
the total present value of costs incurred during the life of the project is
equal to the total present value of benefits accruing during the same
period”. For most investment projects, including irrigation and drainage
projects in particular, costs are bunched at the beginning of the project,
while benefits only begin to accrue after a lapse of time. Consequently
benefits earned and costs incurred in the near future have higher values
than similar benefits or costs arising several years hence. The application
of a discount factor enables these costs and benefits to be compared on a
present value basis, taking into account differences in the timing of
expenditure and income.
The cost streams used in the construction of the COSTAB tables referred
to above should, as mentioned, include the capital costs of the project
(including physical - but not price - contingencies) plus the operating,
maintenance and replacement costs1 of project works, and any
quantifiable social - such as land acquisition and resettlement - or
environmental costs. They should also include the operating costs incurred
by the farmers, as well as those arising from providing services and
running the organisation and management system for the project.
Operating costs for participating farmers may be derived from the crop
budgets and representative farm models aggregated to give the overall
project estimates. Residual values of project-funded assets should be taken
into account as benefits, usually at the end of the project life, although in
some cases - for example when equipment used in construction is
transferred to another project - a residual value may be applied earlier in
the project life and attributed to project income. The life of the project is
usually taken as the period corresponding with the useful life of the major
investment components, and typically ranges from around 15 to 25 years
for irrigation and drainage investments.
1: If the life of certain project-financed investments is less than the assumed life of the project (which is nearly
always the case), provision should be made for the cost of their replacement when this is needed.
Guidelines for Planning Irrigation and Drainage Investment Projects 80
All costs and benefits should be expressed in economic terms. For those
inputs which could have a significant bearing on the viability of the
project, a distinction must be made between traded and non-traded goods,
and a decision must be taken as to whether to compensate for distortions
in the pricing of foreign exchange through the use of a shadow exchange
rate or through the application of conversion factors to the price of non-
traded goods. However, the use of conversion factors is to be preferred
since it allows for differentiated treatment of different categories of traded
goods1. In the case of internationally traded commodities such as fertiliser,
grains or oilseeds, prices are usually derived from forecasts prepared
periodically by the World Bank. The accuracy of these forecasts and the
related assumptions on inflation have often been questioned on the basis
of retrospective assessments of earlier forecasts, but no better series has
been developed and their use has the advantage of ensuring a measure of
consistency in pricing between projects and countries. Nevertheless they
should be interpreted with caution. Before use, the forecast prices should
be converted to constant prices for, say, the date of compilation of the
project dossier or appraisal. It is then usually necessary to convert these
figures to farm-gate prices by working backwards from the international
forecast price, making adjustments for the cost of shipping, handling,
internal transport and distribution, and making allowances if necessary for
quality differences. Direct and indirect transfers (such as taxes or subsidies)
are eliminated in the calculation.
1: If the analyses are carried out correctly, the final result should be the same.
Guidelines for Planning Irrigation and Drainage Investment Projects 81
The rate of return can be calculated using the COSTBEN module of PC-
COMPASS. This may then be judged against criteria such as the
opportunity cost of capital in the particular country where the project is to
be implemented. As a very rough rule of thumb, the project analyst might
recognise that the project is in the “danger zone” if the rate arrived at is
less than about 10 to 12% - the minimum ERR conventionally acceptable
to many financing institutions (but one which is probably still considerably
above the long-term opportunity cost of capital).
There are also risks that do not lend themselves to quantitative analysis.
The case of government commitment is one. The efficiency of the public
administration (unless it can be linked to a quantifiable determinant of
output such as irrigation efficiency) is another. Availability of domestic
financial resources to cover the government share of project costs is a third
example. Securing beneficiaries’ participation is a fourth one, and several
other examples could be quoted. The discussion of the risk factors should
not be limited to quantitative analysis, but expand to cover the other major
areas of concern, drawing attention to the possible need to take corrective
measures before or during project implementation.
• preparing an annual work plan and budget for the first year of the
project, and entering this into government’s budget for the financial year;
• opening a special bank account to receive project funds for local
disbursement;
• arranging staffing for project implementation, including recruiting or
redeploying staff with the required skills and experience, and training
staff for new functions that they will have to perform;
• initiating necessary institutional reforms;
• drafting and initiating the enactment of legal provisions (eg for WUAs,
creation of autonomous authorities for bulk irrigation water supply);
• preparing operational and accounting manuals, setting out procedures
to be followed in project implementation, and allocating
responsibilities to the different categories of implementer (eg the
ministry of finance, irrigation agency, NGOs and farmers);
• informing intended beneficiaries of the impending availability of
funds for community-based or individual demand-driven
developments and creating the conditions for them to generate
proposals that meet their own aspirations and qualify for assistance;
• preparing procurement packages for plant and equipment, satellite
imagery, aerial photography and mapping;
• drafting requests for proposals/bids for external technical assistance
(eg from NGOs or consultants);
• carrying out topographic surveys, engineering investigations and
designs for initial construction work.
2: For this purpose, reference may be made to the various guidelines that may be issued from time to time by
the financing institutions, eg the World Bank’s Procurement Under IBRD Loans and IDA Credits, and Use of
Consultants by World Bank Borrowers and by the World Bank as Executing Agency, as well as their sample
bidding documents if necessary.
Guidelines for Planning Irrigation and Drainage Investment Projects 85
• The irrigation and drainage works and other hardware which are
proposed for financing.
• The expected phasing of this development.
• Institutional responsibilities and staffing requirements for project
implementation, with job descriptions, for project coordination and
each of the project components.
• The implementation plan.
• Mechanisms adopted for users’ participation in design or proposals
for participation in implementation.
• Procedures and criteria for screening subprojects for selection within
sectoral programmes, for quality control of design and construction, and
the administrative mechanisms for a rolling annual expenditure plan and
the flow of funds - with particular attention to funding channels if
expenditure is to be made by local or regional administrations.
• Details of expected supervision of implementation by the financing or
cooperating institution, including any special supervision
requirements for subproject approvals within a programme of support.
• The organisational structure decided upon for O&M, which may
include allocating or transferring responsibility to the users1, or to a
financially autonomous irrigation authority dependent on the users for
financing, and/or participatory joint management.
• The suggested legislative and regulatory framework for WUAs and
other management organisations proposed.
• The proposals for water charges and cost recovery mechanisms,
reflecting subsectoral strategy.
• Technical assistance and training requirements.
• The estimated changes in cropping patterns and yields expected as a
result of the development, and the rate at which these are expected
to occur.
• Marketing possibilities and forecast prices.
1: Practitioners are referred to Water Report 5, Irrigation Management Transfer, published by FAO with IIMI,
which contains selected papers from the International Conference on Irrigation Management Transfer held in
Wuhan, China in September 1994. This provides a useful source book on management transfer.
Guidelines for Planning Irrigation and Drainage Investment Projects 86
The final version of the project dossier should then be prepared on the
basis of the consensus or conclusions reached.
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
A. Hydrological Identify main water As 1, reworking data if Further refinement of 2 if All outstanding issues
Aspects of Major sources, collect available necessary. Revise basin necessary to resolve resolved. On-going data
Works data on basin rainfall and water balance or outstanding issues. collection for future
flows. Review data and if hydrological model. If updating of water
necessary visit stations to necessary generate availability and sediment
assess data quality. sequences of daily, yield.
Recommend any monthly and annual
necessary improvements flows, with probability
to network or processing analysis. Simulate annual
of data. Note details of water availability over life
recorded floods and of project using
compare with regional spreadsheet analysis.
envelopes. Analyse flows Confirm design flood(s)
and frequency of floods. and carry out flood
Sample and test quality routing. Refine estimates
for use for irrigation of sediment yield. Install
purposes. Estimate additional measuring
sediment yields. Prepare devices if this will
preliminary estimate of usefully add to
basin water balance and hydrological knowledge
round-figure estimates of (which it will only in
area each source will certain circumstances, eg
irrigate, power potential for measuring annual
or other use. Prepare floods).
indicative basin plan for
optimum water use.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
B. Hydrogeological Collect and study As 1, plus geophysical Further refinement of 2 if All outstanding issues
Aspects of Major available data on surveys drilling test wells, necessary to resolve resolved. Establish
Groundwater groundwater occurrence pump tests, and outstanding issues. groundwater monitoring
Development and use. From desk study preparation of simple programme.
identify areas worthy of model of aquifer
further exploration. recharge, storage,
Review well logs and transmissivity and yield.
existing yields. Sample Design of wells, specify
and test water quality. pumps and drilling
Map preliminary methods. Define
assessment of monitoring system.
groundwater potential.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
C. Topography of Sites Obtain satellite imagery As 1 plus orthophoto As 2 plus maps of larger Further survey and setting
of Major Structures at 1:100,000 for mapping (preferably, scales for selected out for construction
and Scheme Area catchment area and at otherwise line mapping) structures. If necessary, purposes.
1:50,000 of command for the command area at additional survey of in-
area for reconnaissance. 1:10,000 with 1 m field, to permit designs of
Mapping of catchment contour interval, or better. at least the first year's
and command areas at 1:2,500 scale mapping work.
1:50,000 with 10 m with 1 m contour interval
contour interval, or better. or better for main canals
Uncontrolled, or better and major structures.
controlled, air-photo
mosaics of sites of major Manual survey (at least
structures and main canal 10% of command area) of
alignments, at a scale of a sample of the infield
1:10,000. Better still, area for designing sample
orthophoto or line in-field layout and land
mapping at this scale with levelling requirements.
2 m contour interval.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
D. Land Capability Review of following data: As 1 plus interpretation of More intensive soil survey Establish monitoring
for Irrigation LANDSAT/SPOT imagery new air photography. with observation in system for potential
at 1:100,000 or larger; air Identify and quantify soils representative areas of 1 waterlogging and salinity
photography at 1:50,000 and land forms. Define observation per 10 ha build-up.
or larger; geological and crop-specific land average, to confirm
soil maps at 1:250,000 or utilization types. Soil boundaries, and to further
better; and land use maps survey at 1 observation per investigate any drainage
at 1:50,000 or better. 25-50 ha. Consider erosion problems.
Review reports and maps hazard, fertility, toxicity,
of soil survey institutions, drainage.
universities, consultants,
etc. Hence identify
principal land systems.
Interpretation of available
air photographs at
1:25,000 or better.
Reconnaissance soil survey
at observation density of 1
sample per 100-200 ha
(depending on magnitude
of scheme and mapping
scale) plus sampling and
testing for physical and
chemical properties; 10%
of observations consisting
of deep pitting to check
drainage.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
F. Civil and Irrigation Outline main water Refine estimates of Detailed designs, Continue with detailed
Engineering sources and irrigable project water construction drawings, designs. Arrange for
land. Define areas of requirements for the bills of quantities, tendering of works if
swamp or seasonal preferred option and specifications and tender financing institution has
inundation. likely cropping pattern. documents, or operational approved.
Prepare preliminary Carry out plans for direct labour
estimates of irrigation operational/simulation construction with farmer
water requirements for studies to optimise participation.
possible typical cropping dam/reservoir/ scheme
patterns. Link present or area. Prepare feasibility
potential irrigation level preliminary designs
demands with possible for the system, to the
water sources. Hence level of detail that ensures
identify possible schemes that no significant
for irrigation, drainage, or changes will be necessary
flood control. Prepare later.
outline designs of the
options.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
G. Civil and Irrigation Preliminary cost estimates Refine quantities and cost Refine quantities and Arrange for farmers'
Infrastructure Costs (including O&M) for estimates, accurate to say costs in the light of further contribution to be made.
engineering works, on- 15%. Tabulate investigations and
farm development and foreign/local costs and designs, with schedule of
any land acquisition. programme of disbursements.
expenditure for
engineering works, land
development, land
acquisition etc. Identify
scope for and nature of
farmers' contribution to
capital costs.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
H. Agricultural Review general policies for Carry out SEPSS if required Refine recommendations Arrange for tendering for
Development and irrigated crops, rainfed and from this prepare in 2. Refine quantities and supply of plant and
Marketing crops, food versus recommendations on costs for agricultural equipment, storage
industrial crops, general possible or likely cropping development and facilities etc. if financing
assumptions on crop patterns, estimates of yields marketing in the light of agency has approved.
yields, cropping intensity. with and without project. final planning of
List local crops. Note Jointly with component, with schedule
development constraints engineering/hydrology of disbursements. Prepare
(lack of water, seeds, study, refine estimates of tender documents for plant
O&M, extension, research, crop water requirements. and equipment (including
finance, markets etc.). Make more detailed marketing plant and
Preliminary agronomic equipment) storage
recommendations on recommendations and on facilities etc.
strategy for irrigated marketing, storage, credit
agricultural development: and technical support.
cropping patterns, Refine cost estimates,
intensity, needs for accurate to say 15%.
extension and other Tabulate foreign/local costs
services. and programme of
Design SEPSS if considered expenditure for works.
necessary.
Preliminary cost estimates
(including O&M) for any
likely marketing
infrastructure, eg storage
and grading sheds,
covered markets etc., and
any land acquisition costs..
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
J. Generation, Testing Identify institutions Define institutional Fine-tune cost estimates. Complete recruitment and
and Transfer of currently involved in responsibilities for Prepare tender documents first round of
Agricultural research or extension agricultural research, for key items. Initiate training/PRAs. Initiate
Production related to irrigated technology testing and recruitment of extra staff monitoring and
Technology agriculture (public, extension. Plan means to and/or pre-implementation evaluation. Maintain
private sector, farmers' link their activities, and to training for new roles. training and re-training,
organisations, NGOs, ensure adequate Organise pre-project M&E.
technical assistance participation of irrigators seminars or PRA for
agencies). Assess the to ensure client-oriented existing field-level
relevance of their present approach. Define field extension and research
organisation, programmes modus operandi of staff.
and field deployment to services, extra resources
supporting the irrigation needed for them to
project alternatives under operate as defined, and
consideration. Make estimate costs. Define
preliminary classification monitoring and
of strengths and evaluation system. Ensure
weaknesses. Review key researchers or
options for improving extensionists who will be
relevance or impact of involved in
their work and possible implementation
roles for investment in participate in SEPSS.
achieving such
improvements.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
K. Participation and Involvement of Consultations with Finalisation of project Prepare farmers for
Water Users' stakeholders in evolution farmers directly or planning with all making contribution to
Associations of development concepts through local stakeholders, from capital costs. Obtain
and comparison of authorities/village farmers' representatives to written commitment to
investment options councils etc. and SEPSS. financing institution at provide construction
through interviews and Establish demand for concluding workshop. If labour and to accept
participative project or subprojects, necessary, assist farmers O&M responsibility.
approaches/workshops. preferably by example (eg with electoral formalities
demonstrations of for WUA committee and
previous farmer drafting constitution.
commitment on other
demand-led development
such as community
contribution to school
buildings). Assess need
for/feasibility/prospects for
success of WUA.
Consultation with farmers
with regard to scope and
layout of scheme.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
L. Environmental Initial environmental If recommended by the Refine actions plans in Establish environmental
Impact evaluation (IEE) using IEE, carry out EIA, the light of further monitoring system.
ICID checklist to assess including if required land information collected or
the need for acquisition assessment received. Specify
environmental impact (LAA), and prepare any indicators, organisation
assessment (EIA). necessary environmental and responsibilities for
action plans (EAPs) and environmental
resettlement action plans monitoring. Enact any
(RAPs). Otherwise prepare necessary legislation to
mitigation plan. Modify enable plans to be
project planning implemented.
necessary to
accommodate
recommendations.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
M. Institutions, Initial institutional Carry out ICA covering Finalise arrangements or Implement any
Organisation and evaluation (IIE). Describe assessment of concerned any organisation organisational changes
Management, Cost institutional framework departments/private sector initiatives/institutional necessary; establish
Recovery, Operation for irrigation, organisations, their reforms. Enact any project entity if necessary.
and Maintenance environmental protection staffing and capacity, necessary legislation to Appoint key project staff.
and, if appropriate, social morale, internal culture enable changes to be Set up accounts and
welfare. Preliminary and performance. Match implemented, including procurement
assessment of institutional project design to capacity legal establishment of arrangements. Arrange
strengths and weaknesses to implement, allowing WUAs. Plan any pre- bidding and contracts
(ability, capacity and for proposed implementation training with NGOs and
funding). Relate to strengthening or or seminars. consultants if required.
possible project(s) being adjustments. Prepare Implement training and
identified. Decide on proposals for institutional start-up seminars or
needs for institutional development/strengthenin workshops.
capacity assessment (ICA). g, including TA and
training needs, and
contracting out to private
sector. Recommendations
for project organisation
and management,
including formation of
WUAs if appropriate.
Specify
arrangements/pricing for
water charges and
collection. Specify
arrangements for O&M.
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
APPENDIX 1 - Activities to be completed and level of detail required at successive stages of the planning process
1: Note that in a programme approach, eg under a sectoral loan, feasibility activities for subprojects may be deferred until after appraisal (see Part II, Chapter 4).
Guidelines for Planning Irrigation and Drainage Investment Projects 101
Currency Equivalents
Acronyms
SUMMARY (3 to 5 pages)
INTRODUCTION (1 TO 2 PAGES)
Objectives of strategy formulation: including whether intended to
update an existing subsector review, or to support an existing or proposed
Agricultural Sector Review or Water Resources Management
Strategy/Strategy Study.
Origin and authorship: origin of request and reasons for review and
strategy formulation, and details of the review/strategy formulation team.
Intended readership
Land Resources: total arable land resources of the country (region), the
limitations (eg soils and topography) for irrigation suitability; significant
salinity or drainage problems, whether man-made or natural, and whether
they offer potential for reclamation and development.
Existing Irrigation and Drainage: the main categories (eg public large-
scale/small-scale, private large-scale/small-scale, traditional water control
systems etc.), and types (eg surface/sprinkler/drip, drainage only etc.);
history of development and areas of each category developed/cropped;
crops grown, production systems, productivity, water use efficiency,
present condition; responsibilities for/adequacy of O&M, and levels of cost
recovery on public schemes; farmers experiences with irrigation;
Guidelines for Planning Irrigation and Drainage Investment Projects 103
Irrigation costs and benefits: typical capital and O&M costs for the
various categories and types of irrigation, and typical crop budgets/farm
models.
Subsectoral finances: the main sources of finance for public and private
irrigation, cost recovery and taxation regimes, and the fiscal sustainability
of present arrangements or levels of application or regulations.
Guidelines for Planning Irrigation and Drainage Investment Projects 104
Opportunities: from the previous chapters identify the potential for new
irrigation or for improvements to existing irrigation; assess the value of
existing development as a model for future development; flag any key
1: For an example, see Annex 2 in Investment Centre Technical Paper 5, Irrigation in Africa South of the
Sahara, FAO, Rome (1986)
Guidelines for Planning Irrigation and Drainage Investment Projects 105
1: A workshop is often held for the purpose of reaching a consensus on the options before finalisation of the
strategy paper (see Part II, Chapter 2).
Guidelines for Planning Irrigation and Drainage Investment Projects 106
To set the scene for this, the most important chapter of the Paper, it is
useful to set out the main sub-sectoral issues to which the strategy being
proposed is intended to respond. Issues will often echo those first raised at
the Preliminary Brief stage (see Annex 3), but now refined or modified in
the light of the review/strategy formulation (in which government has fully
participated through the medium of workshops and other activities).
These two sections should be closely linked and will tend to integrate a
wide variety of previous information - for instance on food supply and
demand, local or export markets, the comparative advantage of various
forms of irrigation (both nationally and versus rainfed opportunities),
availability of or competition for natural resources, adverse social and
environmental impacts, under-used or neglected infrastructure, farmer
motivation, social needs, labour demand or supply, agro-processing, road
access, power supplies, and so on. They should take full account of the
lessons of experience or precedent regarding the ease or difficulty of
exploiting particular opportunities, or of overcoming key sub-sectoral
constraints - especially those relating to institutional capacity for
development. The government’s future intentions, commitments or
priorities as well as its real capacity to influence or undertake irrigation
development must also be taken into account. If strategic choices centre
on production under rainfed versus irrigated conditions, or under
alternative systems or different scales of irrigation, arguments can be
supported with the simple production models developed in Chapter 5 to
demonstrate likely economic efficiency, comparative advantage or
financial attractiveness of growing alternative commodities by different
means. The models may also be used to compare economic returns per
unit volume of water - usually the limiting resource - per hectare
developed, or per labour day. In many countries a balance may need to
be struck between new construction and the rehabilitation of existing
facilities: illustrative summary tables of relative costs and benefits can also
be given for each of these, to guide national decision-makers. The
principles that should orient future institutional and social arrangements
for irrigation planning, construction, operation and management should
also be set out, indicating whether a participatory approach is appropriate.
A strategy will need to be included to prevent rehabilitated systems, once
repaired, from degenerating again.
The final section of the strategy chapter will often compare the strategic
suggestions just given to the present policies and plans of the government.
Treatment is likely to be partly reassuring (“...... strategic proposals are in
line with government’s thinking, as elucidated at the concluding workshop
.....”) and partly a matter of foreshadowing the issues which should be
Guidelines for Planning Irrigation and Drainage Investment Projects 109
MAPS
Maps included might be:
1. Agro-ecological Zones and Land Use
2. Hydrological Zones and Rainfall Isohyets
3. Groundwater Potential
4. Location of Existing and Proposed/Possible Irrigation Development
ANNEXES
Annexes might include:
1. Existing Irrigation Database
2. Basis of Estimates of Typical Irrigation Costs
3. Marketing and Prices of Agricultural Products
4. Typical Crop Budgets for Irrigated Crops
5. Financial and Economic Viability of Irrigation
BIBLIOGRAPHY
Guidelines for Planning Irrigation and Drainage Investment Projects 112
ANNEX 2:
Outline of a typical project
document or dossier
This annex, read in conjunction with Investment Centre Technical Paper
7 , seeks to cover the great majority of the topics likely to be dealt with in
1
1: Investment Centre Technical Paper 7: Guidelines for the Design of Agricultural Investment Projects.
FAO, Rome (1993).
Guidelines for Planning Irrigation and Drainage Investment Projects 113
The summary should normally cover topics in the order in which they
are treated in the main text of the document, with one paragraph for each
chapter of the main text. The summary can usually only be written after
the main report has been completed. It should not exceed four pages or
ten percent of the length of the main report, whichever is the shorter.
INTRODUCTION (1 PAGE)
This chapter is administrative and should state the purpose of the report
and to whom it is addressed. It should indicate how, when and by whom
(eg LPGs, consulting firms, individuals and/or FAO Investment Centre
missions) the project has been prepared. It should also state the origin of
the project, ie whether in a national development plan, from subsectoral
strategy formulation, or from previous examination of the available options.
A. The Economy
This should describe the contribution of agriculture and irrigated
agriculture to GDP, per caput income, national dependence on particular
imports and exports, balance of payment considerations, inflation,
indebtedness, exchange rate adjustments, public investment programme,
adequacy of revenue to meet recurrent funding requirements, macro-
economic distortions and other features of economic development that have
a bearing on the project. Recent changes and trends should be highlighted.
Together with its supporting annexes and maps, this chapter should
describe the features of the project area that have implications for the
planning of the proposed investment. It should evaluate the development
opportunities and potential as well as the limitations, focusing throughout
on the investment which is being proposed. It is likely to contain the
sections described below.
Geology, Soils and Land Capability for Irrigation. Land in the project
area should be described with reference to topographic, geological, soil or
land classification surveys and maps. Limiting factors should be
highlighted. The degree of detail required in land evaluation surveys will
vary between projects depending on the characteristics (soil variability,
salinity problems, etc.) of the project lands: guidelines are available in the
FAO Guidelines: Land Evaluation for Irrigated Agriculture1 (see also
Appendix 1 to the main text of these Guidelines). The use of remote
sensing methods and geographic information systems to evaluate the
1: FAO, Rome (1985). See also FAO Soils Bulletin 42: Soil Survey Investigations for Irrigation,
FAO Rome (1979).
Guidelines for Planning Irrigation and Drainage Investment Projects 117
Climate. The purpose here is not to describe the climate in detail but to
demonstrate its influence on and importance to the project concept. It
should deal with the main climatic features2 affecting irrigation
requirements and system design: ie rainfall (monthly, annual and its
probability) temperature, sunshine hours, humidity and wind, as well as
reference evapotranspiration. Data should be summarised in tables, with
detailed analysis consigned to an annex. This section should summarise
the agronomic justification for irrigated, as opposed to rainfed, cropping.
Any serious climatic hazards (eg frosts, hail, typhoons) should be noted.
1: See FAO Remote Sensing Centre, Remote Sensing and its Application to Investment Project Identification
and Preparation: A Study With Special Reference to the FAO Investment Centre, FAO Rome (1993). Modern
computer graphics packages, such as CorelDraw, used in conjunction with flatbed or even hand scanners can
be most useful.
2: Long term data for many climate stations throughout the world are available in FAO's computerised
CLIMWAT database (FAO Irrigation and Drainage Paper 49, 1993), but these can be updated with the most
recent data if necessary.
Guidelines for Planning Irrigation and Drainage Investment Projects 118
their impact on demand for basic foods or horticultural crops, the effects of
growth in the industrial sector on the demand for labour and the extent to
which this affects labour availability and wage rates in rural areas, or the
emergence of competing demands for water for urban and industrial uses
that could reduce availability for irrigation.
The People. The people of the project area should be described and
their expected reaction to the project should be assessed. The description
of the socio-economic situation should give special attention to those
aspects that could affect the rate at which the target population for the
project will accept changes.
1: For methods of Rapid Rural Appraisal see FAO Investment Centre Technical Paper No 9, Sociological
Analysis in Agricultural Investment Project Design. FAO Rome (1992).
Guidelines for Planning Irrigation and Drainage Investment Projects 119
Factors that might affect the community’s response to the project or the
strategy to be adopted should also be reviewed. These might include
nutritional standards and food security, land tenure and the availability of
labour during the various seasons of the year. In particular, any experience
of group activities within the area (eg for marketing and input supply,
irrigation system O&M), that might have a bearing on the potential for
future cooperation in scheme organisation and management and O&M,
should be rigorously analysed. The socio-economic studies that may have
been conducted in the project area, their findings on people’s aspirations,
especially the extent of farmer interest in the project, should be
summarised, and conclusions drawn on their implications for project
planning. The full findings of the studies may be presented in an annex.
Land Tenure. The rules or customs for land tenure should be described.
The size and distribution of properties and farms, degrees of fragmentation,
proportion of owner and tenant-operated farms, type of tenure, etc. should
be summarised. The basis for, and reliability of the figures should be given
with reference to cadastral surveys and maps. Dynamic factors in the
situation (trends in tenure arrangements, increasing fragmentation,
consolidation, etc.) should be described. The situation should be evaluated
in terms of development opportunities and obstacles (eg would land titling,
redistribution or consolidation be necessary and practicable?).
1: FAO's forthcoming computer model SIMIS (Scheme Irrigation Management Information System) will play
an increasingly useful role in such work.
2: FAO Irrigation and Drainage Paper 46: CROPWAT - A Computer Program for Irrigation Planning and
Management. FAO Rome (1992).
Guidelines for Planning Irrigation and Drainage Investment Projects 123
1: FAO Irrigation and Drainage Paper 49: CLIMWAT for CROPWAT. FAO Rome (1993).
Guidelines for Planning Irrigation and Drainage Investment Projects 124
A. Project Rationale
Against the background of the previous chapter, this should discuss the
objectives of government’s strategy for the irrigation subsector, the criteria
which have led to the selection of the type (eg subsectoral investment, new
irrigation, rehabilitation, drainage) and/or location of the project, and the
constraints imposed by existing institutional capacity or fiscal
arrangements. It may also explain how the proposed project meets the
financing criteria of the financing institution, for example targeting small
farmers in a project proposed for IFAD financing.
B. Planning Considerations
Once the conceptual case for a project has been made under the
section on project rationale, attention needs to be directed to defining the
specific form that it should assume and to explaining this to the reader.
• selection of the target population for the project and any special
targeting measures required to ensure that the project really does
benefit these people (the complex issue of how to prevent project
resources bringing undue benefits to persons outside the target group,
but without whose influence the project might nevertheless not
succeed, needs special treatment);
• the demand for the project, expressed in terms of demonstrable
willingness of the potential users to commit themselves to
contributing towards the capital cost and acceptance of responsibility
for O&M, and in terms of markets for irrigated crops of sufficient
value to justify the investment costs incurred by government and
farmers;
• the commitment and capacity of government to implement the
project;
• the justification for a programme approach, where the aim is build
demand for subproject investments and to encourage participation in
planning, design, construction and O&M;
Guidelines for Planning Irrigation and Drainage Investment Projects 126
• the appropriate scale for the project: this should give special
importance to an analysis of the scale and success of any precedents,
to assessments of institutional capabilities and to matching the project
scale with these; it should also examine the implications on project
size of market possibilities, economic and financial viability,
environmental concerns and risk exposure;
• the scope for achieving efficiency gains at low incremental cost by
rehabilitating and upgrading existing irrigation systems, including
traditional irrigation systems;
• the choice of technical strategy and technology to match O&M capacity
(eg upstream versus downstream control, automation etc.) and/or
traditional water rights and methods of distribution (eg division structures
that maintain traditional rights and farmers’ operational preferences);
• the selection of organisational arrangements for the project: for
example whether to reinforce the existing entity to run the project
(on financially autonomous lines), to create a new organisation or to
privatise it; the strategy for eliciting and sustaining the commitment of
the intended beneficiaries to the project, particularly the means of
securing their effective participation in project management and costs
through WUAs and/or apex organisations; whether WUAs should be
built on existing structures, traditional or other;
• the appropriate time frame for the project and phasing within this;
and
• the need for any ancillary adjustments in laws, regulatory
mechanisms, policies and institutions.
This is also the place to mention to the need to build flexibility into the
project, to accommodate capacity-building measures, and to say how this
could be done in ways which are consistent with the funding practices of
the financing agency. There is often little scope for flexibility in “hard”
projects centering on, for instance, the construction of major civil works;
but there are many advantages in planning “soft” projects - for demand-
driven development - so that these can readily respond to new information
or opportunities that arise in the course of implementation.
A project normally has specific objectives that can be expressed in relatively simple
terms, such as:
Each of the above may in turn be broken down into a series of items and ultimately
into a set of detailed specifications for goods and services.
Guidelines for Planning Irrigation and Drainage Investment Projects 128
A. General Description
This section, which generally should be no longer than one page,
presents the reader with a brief overview of the proposed project or
programme. It can often be quoted more or less intact in the Summary and
Conclusions at the beginning of the Report. The usual content is:
B. Detailed Features
The aim of this section is to describe the project in more detail so that
the reader acquires a fuller understanding of each of its components and
the inter-relationships between them. The nature and scope of project
actions should be described in sufficient detail for the general reader to
appreciate their relevance and technical soundness, but lengthy
descriptions, specifications, engineering design details and cost estimates
should remain in annexes or working papers.
The section usually contains a separate résumé for each of the project
components, quantifying the main physical items that are proposed for
financing, grouped under expenditure categories if appropriate. Although
the cost estimates are only presented in detail in Section F of this chapter,
it often helps to note in brackets at the start of the component description
its total cost and the percentage of project base cost which this represents.
Increasingly, also, financing agencies prefer each component résumé to
end with brief reference to the field level implementation arrangements,
leaving the description of the broader (not component-specific)
institutional arrangements for section C of this chapter.
For a sectoral project the components may include some of the above
as well as:
Similarly the intended location of all project staff and the expected
duration of their assignments should be clearly indicated. If technical
assistance is proposed, draft terms of reference (see Annex 3) should be
given and functions, objectives, measurable performance indicators and
reporting arrangements specified. The minimum qualifications for
candidates should be defined as precisely as possible. If the technical
assistance is not for the completion of a finite task, such as the completion
of engineering designs, it should be explained how it would be phased out
and how the functions would be subsequently assumed by regular staff.
F. Project Costs
The importance of sound cost estimates cannot be over-emphasised:
they provide the basis of determining the project’s economic and financial
viability and also its funding. Estimates should include all capital costs and
incremental operating costs incurred by government during the
disbursement period and for the subsequent operation of the project. In
principle the engineering cost estimates should include all incremental
goods and services required to complete the planned works. Cost estimates
for the main civil engineering works should be based on bills of quantities,
derived from preliminary designs and justified unit rates. Costs of major
equipment items are normally based on recent quotations from potential
suppliers. Costs of on-farm development may be drawn from an
aggregation of representative farm models but it should be clearly
indicated whether or not these include cash or non-cash contributions
(eg in the form of family labour or locally available materials) by farmers.
• Incremental operating costs - ie. recurrent costs over and above the
“normal” running costs of the concerned agencies - incurred during
the disbursement period specifically for the implementation,
management and monitoring of the project.
• Technical cooperation, either foreign or national, aimed at increasing
the capacity of concerned institutions to implement the project. Note
that such technical assistance is often treated as a category of
investment expenditure, related to specific project components such
as “project management”, rather than as a project component in its
own right. This may not be the case however if capacity building
becomes one of the major objectives.
• Training, both overseas and local, aimed at improving staff
capabilities: most frequently training is related to meeting the staffing
requirements for implementing the project, but usually training aimed
at more general institutional strengthening also qualifies for project
financing.
• Feasibility study and project planning costs, if these have been
financed by reimbursable loans from the financing agency, for
instance under the World Bank’s Project Preparation Facility.
• Engineering costs and fees that would be incurred during the
disbursement period.
• Interest during construction: some financing agencies are prepared
to consider as a project cost interest payable during the disbursement
period of the loan. Amounts, however, can only be calculated once a
financing plan has been finalised.
Guidelines for Planning Irrigation and Drainage Investment Projects 135
Project Costs. The text of the main report conventionally refers to the
total costs implied by the project proposal (ie to all incremental
expenditures which should be incurred during the course of the proposed
disbursement period). Up to five summary project cost estimate tables can
usefully be included in the main report.
For projects being prepared for financing by IFAD, additional cost tables
are required to show a cost breakdown which separates out direct support
to farmers (eg. credit, inputs) from funding for government institutions
Guidelines for Planning Irrigation and Drainage Investment Projects 136
The text of this section of the document is usually “written around” the
tables. It should :
• indicate the sources (and dates) of unit costs from which the estimates
are derived, giving an indication of their accuracy;
• highlight the importance of any major elements;
• provide an estimate of the total costs of the foreign exchange
component of project costs: this includes both the outlay on fully
imported items and the estimated import content of goods and
services paid for in local currency (eg. the imported elements of
locally-assembled pumps);
• distinguish between capital costs and those recurrent costs (eg for
training) which have been treated, for the purposes of estimating
project costs, as investment costs;
• explain assumptions on physical and price contingency rates.
Annual cost estimates, both for the economic analysis of the project
and also for setting water charges, should include inter alia the following:
Annual Maintenance
Cost as Percentage of
Type of Works Initial Capital Cost
Replacement costs are forecast for the year in which they are expected
to occur, but using constant prices, ie similar to those used in the initial
capital cost estimates.
Other annual recurring costs may include the incremental annual costs
of other public services, eg extension services.
G. Financing
Some financing agencies, but not the World Bank or IFAD, expect a
preliminary financing plan to be proposed by the country submitting the
project before appraisal. Such a plan, in the form of a table, would indicate
for each main expenditure category the amount proposed for financing by
external financing agencies, the government, implementing agencies (from
their own resources), credit institutions and beneficiaries. Since the final
plan will be a matter for negotiation between the financing agencies and
the country concerned, and in any case it is the prerogative of the financing
agency to determine what it will or will not finance, care must be taken not
to imply a commitment of the agencies to the proposal. It is perhaps
pertinent to point out that some financing agencies restrict financing to the
direct and indirect foreign exchange component of the project. More
frequently, however, a proportion of local costs may also be financed.
Assurances of government capacity to meet its proposed share of project
costs should be sought, especially for projects in countries which have a
record of failure to meet counterpart funding obligations in earlier projects.
A. Agricultural Production
The chapter usually starts with a review of the cropping patterns it is
assumed will be introduced, followed by an assessment, drawing on crop
budgets and farm models, of the impact on the output and income of
typical participants. It should explain the assumptions made on the rates at
which yields and cropping intensities will rise and, derived from these and
the models, arrive at estimates of the overall impact of the project on farm
development and output.
Earlier sections should have indicated the nature of the constraints and
needs faced by each type of producer, the opportunities for increased
production, and the technical strategy by which it is intended to open
these opportunities to them. The results summarised at this point should
focus on the same strategy and opportunities but express the expected
results in financial terms, using estimated prices justified in Chapter 9 or
an attached table or annex.
Farm models also provide the basis for estimating the likely long and
short term credit needs of project participants, and for forecasting their
debt service obligations. Particular care needs to be taken by the analyst in
estimating working capital requirements and the means by which these
can be financed1 .
The cost and return implications derived from the financial analysis of
the crop or enterprise budgets can usefully be summarised in a short text
table which may also compare financial return per unit of land, labour,
cash expenditure, cubic metre of water etc., without and with the project.
Only after it is clear that all activities amongst the building blocks of
models are financially viable is it justified to proceed to an analysis of a
financial model of the complete farm or enterprise over time. A further
summary table or tables should be given for the key results from the
analysis of the annexed financial models.
Financial models should assume constant financial unit costs and prices
over the period of analysis, unless there is any special reason to depart
from such assumptions - for instance, if the expected output from the
project would be big enough to depress product prices. If, as is the case in
inflationary situations, there is a major discrepancy between nominal and
real interest rates, it is appropriate to adopt the real rate in calculating debt
service obligations, while at the same time also holding prices constant.
The basic models that are analysed in annexes and summarised in the
main text should aim to represent average situations. In practice however,
1: Chapter X, FAO Investment Centre Technical Paper No 8 Financial Analysis in Agricultural Project
Preparation, FAO Rome (1991).
Guidelines for Planning Irrigation and Drainage Investment Projects 142
results are likely to vary significantly from one year to another, often
because of variations in water availability. It is for this reason that, where
available data permit, fluctuations in water supply should be simulated for
the period of intended economic analysis, rather than simply assuming that
the 80 percent exceedance probability flows would be available in all
years1. For such reasons, a series of variants on the basic financial models
may need to be run to demonstrate the extent of their sensitivity to risk or
changes. The purpose of these variants is to show whether or not the
project’s technical strategy is robust enough to sustain project beneficiaries
through misfortunes such as a series of consecutive years of unfavourable
weather or a drought falling in the first year of their project participation.
The variants may also be used to assess the implications for project
participants of alternative pricing policies or market scenarios, or of partial
adoption of technology. Such financial examinations of risk and uncertainty
are now relatively easy to run using computer programs such as the
FARMOD module of PC-COMPASS; the FAO Investment Centre Design
Study2 suggests that many cases of under-performance could have been
anticipated if these analyses had been made. Additional tests for risk and
sensitivity which can be applied in financial analysis are discussed below.
Tests for Sensitivity. Some simple tests can be made on the financial results
of enterprise budgets or farm models summarised earlier. The overall aim of
1: For details of possible techniques, see Paper 81 A Methodology of Irrigation Water Budgeting, in
Branscheid V, Irrigation Water Management Briefs: 100 Collected Papers, FAO Investment Centre,
Rome 1989.
2: FAO Investment Centre Technical Paper 6 The Design of Agricultural Investment Projects: Lessons from
Experience, FAO Rome (1989).
Guidelines for Planning Irrigation and Drainage Investment Projects 143
The text of this final section of the chapter should indicate briefly the
approach to aggregation which has been used. Short text tables should
then summarise estimates of total and incremental physical quantities for
inputs and outputs, plus their financial values where appropriate.
The above information can be presented using the ICID checklist. All
negative impacts identified should be highlighted in the text. Action plans
for mitigation, such as resettlement and rehabilitation plans or special
designs for structures, should be briefly described. The costs of such action
plans should be presented, as should estimates of the environmental costs1
for inclusion in the economic analysis of the project.
The point must also be emphasised that economic analysis should not
be used simply to provide a proof of project viability. Rather it should be
used as a tool in the planning process to arrive at the option that is likely
to produce the best all-round results from all the choices considered. It
should also illuminate the strengths - and reveal any weaknesses - of the
project. The use of sensitivity analysis techniques is important in showing
the nature and extent of risk to which the project is exposed and to point
to possible means for improving robustness.
1: For guidance see Dixon J A et al, Economic Analysis of Environmental Impacts. Earthscan Publications,
London (1994).
Guidelines for Planning Irrigation and Drainage Investment Projects 145
A. Issues
As a project moves through the planning process to appraisal and
negotiation, various problems or issues usually arise which need to be
resolved by decisions of the government and/or the financing institution.
Those concerned should be alerted to problems which - if not resolved in
due time - would delay or materially influence the successful
implementation of the project. It is most important to bring such issues out
into the open as early as possible in the planning process and to
encourage their rapid resolution, especially if they could have a major
bearing on the feasibility of the eventual project. To gloss over fundamental
issues in the hope that they will disappear may simply raise false
expectations. It is equally important, however, not to overload this section
with trivial matters which can be readily resolved in the normal course of
appraisal and subsequent project processing.
legislation for water users’ associations, and means of ensuring the users’
involvement in design and construction.
D. Procurement
Most multilateral and bilateral financing institutions have their own
requirements for procurement that are set out in guidelines issued for
borrowers1. These should be referred to and their applicability to the items
to be procured under the project should be explained. The major financing
institutions usually require that borrowers obtain goods above a certain
value and contract major civil works through international competitive
bidding (ICB) open to suppliers and contractors in all of their member
countries. Under prescribed conditions preference may however be
permitted for local and regional manufacturers and, where appropriate,
local contractors. Programmatic work consisting of many small scattered
subprojects is not generally attractive to international companies and does
not usually require ICB. However, the principle of competitive bidding will
still apply for local purchases or the use of local contractors. Whatever the
expected procurement procedures they should be summarised here, with,
if appropriate, an assessment of local capacity to supply different
categories of goods or services.
1: See, for example, World Bank and Inter-American Development Bank, Sample Bidding Documents:
Procurement of Goods and Procurement of Works, (1985, 1986).
Guidelines for Planning Irrigation and Drainage Investment Projects 152
Total PROJECT COSTOS 3.027,0 2.937,7 3.017,5 2.959,5 1.185,7 13.127,4 7.663,3 7.437,2 7.639,3 7.492,3 3.001,7 33.233,9
Taxes 221,7 179,8 168,0 145,7 54,4 769,5 561,2 455,1 425,2 368,7 137,7 1.948,0
Foreign Exchange 206,9 72,5 56,1 66,4 31,8 433,7 523,9 183,6 141,9 168,0 80,6 1.098,1
Example: Project Cost Summari by Expenditure Category
% % Total
(Pesos Million) (US$ ‘000) Foreign Base
Local Foreign Total Local Foreign Total Exchange Costs
I. Investment Costs
A. Equipment 823,6 62,2 885,7 2.085,0 157,3 2.242,4 7 7
B. Civil Works 1.525,2 202,1 1.727,3 3.861,2 511,7 4.372,8 12 14
C. Technical Assistance (local) 1.682,4 - 1.682,4 4.259,2 - 4.259,2 - 13
D. Technical Assistance (external) 4,1 37,3 41,5 10,5 94,5 105,0 90 -
E. Training 352,2 3,0 355,2 891,6 7,6 899,2 1 3
F. Studies 221,2 94,8 316,0 560,0 240,0 800,0 30 2
G. Vehicles 31,2 6,3 37,5 79,0 16,0 95,0 17 -
H. Off-farm Investment 701,5 - 701,5 1.775,8 - 1.775,8 - 6
I. Supplies 75,1 - 75,1 190,1 - 190,1 - 1
J. Research 1.697,3 - 1.697,3 4.297,0 - 4.297,0 - 13
K. On-Farm Investment /a 3.694,2 - 3.694,2 9.352,4 - 9.352,4 - 29
Total Investment Costs 10.807,9 405,7 11.213,6 27.361,8 1.027,1 28.388,9 4 88
II. Recurrent Costs
A. Operation & Maintenance
O&M Works 268,2 - 268,2 679,0 - 679,0 - 2
O&M Equipment 537,4 - 537,4 1.360,5 - 1.360,5 - 4
Subtotal Operation & Maintenance 805,6 - 805,6 2.039,5 - 2.039,5 - 6
B. Vehicles O & M 18,0 12,0 30,1 45,7 30,5 76,2 40 -
C. Supplies 10,0 - 10,0 25,3 - 25,3 - -
D. Staff 315,7 - 315,7 799,2 - 799,2 - 2
E. Other 192,5 - 192,5 487,4 - 487,4 - 2
F. Gasoline 22,9 - 22,9 57,9 - 57,9 - -
G. Travel 135,6 - 135,6 343,3 - 343,3 - 1
Total Recurrent Costs 1.500,3 12,0 1.512,4 3.798,3 30,5 3.828,8 1 12
Total BASELINE COSTOS 12.308,3 417,7 12.726,0 31.160,2 1.057,6 32.217,7 3 100
Physical Contingencies 385,4 16,0 401,4 975,7 40,5 1.016,2 4 3
Price Contingencies - - - - - - - -
Total PROJECT COSTOS 12.693,7 433,7 13.127,4 32.135,8 1.098,1 33.233,9 3 103
\a Includes: improved rainfed farming and on-farm erosion control (US$ 5.5 Mill.); pasture and livestock improvement (US$ 3.7 Mill.); and forestry (US$ 2.9 Mill.).
Example: Project Cost Summari and Year
Base Cost (Pesos Million) Base Cost (US$ ‘000) Foreign Exchange
1995 1996 1997 1998 1999 Total 1995 1996 1997 1998 1999 Total % Amount
I. Investment Costs
A. Equipment 552,6 62,4 88,9 110,7 71,2 885,7 1.398,9 158,0 225,0 280,2 180,2 2.242,4 7,0 157,3
B. Civil Works 495,1 509,0 400,3 291,2 31,6 1.727,3 1.253,4 1.288,6 1.013,5 737,2 80,0 4.372,8 11,7 511,7
C. Technical Assistance (local) 336,7 443,2 451,9 368,9 81,6 1.682,4 852,4 1.122,0 1.144,1 933,9 206,7 4.259,2 - -
D. Technical Assistance (external) 17,8 11,9 5,9 5,9 - 41,5 45,0 30,0 15,0 15,0 - 105,0 90,0 94,5
E. Training 157,0 149,2 24,5 24,5 - 355,2 397,6 377,7 62,0 62,0 - 899,2 0,8 7,6
F. Studies 131,1 47,4 - 68,7 68,7 316,0 332,0 120,0 - 174,0 174,0 800,0 30,0 240,0
G. Vehicles 37,5 - - - - 37,5 95,0 - - - - 95,0 16,8 16,0
H. Off-farm Investment 12,6 233,8 227,5 227,5 - 701,5 32,0 591,9 576,0 576,0 - 1.775,8 - -
I. Supplies 75,1 - - - - 75,1 190,1 - - - - 190,1 - -
J. Research 650,6 461,8 330,6 254,4 - 1.697,3 1.647,0 1.169,0 837,0 644,0 - 4.297,0 - -
K. On-Farm Investment /a 214,8 601,8 1.073,4 1.184,4 619,9 3.694,2 543,7 1.523,5 2.717,5 2.998,4 1.569,3 9.352,4 - -
Total Investment Costs 2.680,9 2.520,4 2.603,1 2.536,2 873,0 11.213,6 6.787,1 6.380,7 6.590,2 6.420,8 2.210,2 28.388,9 3,6 1.027,1
II. Recurrent Costs
A. Operation & Maintenance
O&M Works 17,7 37,4 59,9 76,6 76,6 268,2 44,8 94,6 151,7 194,0 194,0 679,0 - -
O&M Equipment 107,4 107,5 107,5 107,5 107,4 537,4 272,0 272,1 272,2 272,2 272,0 1.360,5 - -
Subtotal Operation & Maintenance 125,1 144,8 167,4 184,1 184,1 805,6 316,8 366,7 423,9 466,1 466,0 2.039,5 - -
B. Vehicles O & M 5,9 6,0 6,0 6,1 6,1 30,1 15,0 15,1 15,3 15,4 15,4 76,2 40,0 30,5
C. Supplies - 2,0 4,0 4,0 - 10,0 - 5,1 10,1 10,1 - 25,3 - -
D. Staff 43,2 74,7 69,3 69,3 59,3 315,7 109,3 189,0 175,4 175,4 150,0 799,2 - -
E. Other 34,2 43,9 42,6 43,4 28,5 192,5 86,5 111,1 107,8 109,9 72,3 487,4 - -
F. Gasoline - 7,6 7,6 7,6 - 22,9 - 19,3 19,3 19,3 - 57,9 - -
G. Travel 36,4 29,4 24,8 23,7 21,3 135,6 92,2 74,4 62,8 60,0 53,9 343,3 - -
Total Recurrent Costs 244,8 308,3 321,8 338,2 299,2 1.512,4 619,7 780,6 814,6 856,3 757,6 3.828,8 0,8 30,5
Total BASELINE COSTOS 2.925,7 2.828,7 2.924,9 2.874,4 1.172,3 12.726,0 7.406,8 7.161,3 7.404,8 7.277,0 2.967,8 32.217,7 3,3 1.057,6
Physical Contingencies 101,3 109,0 92,6 85,0 13,4 401,4 256,5 276,0 234,5 215,3 33,9 1.016,2 4,0 40,5
Total PROJECT COSTOS 3.027,0 2.937,7 3.017,5 2.959,5 1.185,7 13.127,4 7.663,3 7.437,2 7.639,3 7.492,3 3.001,7 33.233,9 3,3 1.098,1
Taxes 221,7 179,8 168,0 145,7 54,4 769,5 561,2 455,1 425,2 368,7 137,7 1.948,0 - -
Foreign Exchange 206,9 72,5 56,1 66,4 31,8 433,7 523,9 183,6 141,9 168,0 80,6 1.098,1 - -
\a Includes: improved rainfed farming and on-farm erosion control (US$ 5.5 Mill.); pasture and livestock improvement (US$ 3.7 Mill.); and forestry (US$ 2.9 Mill.).
Example: Breakdown of Expenditure Categories, Local Currency
Physical
Cont.
Plus
Base Cost Physical Contingencies Total Incl. Cont. Base Costs Price
Local Local Local + Price Cont. on
For. (Excl. Duties & For. (Excl. Duties & For. (Excl. Duties & Cont. on Physical
Exch. Taxes) Taxes Total Exch. Taxes) Taxes Total Exch. Taxes) Taxes Total Base Costs Cont.
I. Investment Costs
A. Equipment 62,2 712,1 111,5 885,7 3,1 50,7 8,9 62,7 65,3 762,8 120,4 948,5 885,7 62,7
B. Civil Works 202,1 1.214,2 310,9 1.727,3 12,1 102,9 25,2 140,2 214,2 1.317,1 336,1 1.867,5 1.727,3 140,2
C. Technical Assistance (local) - 1.514,1 168,2 1.682,4 - 77,6 8,6 86,2 - 1.591,8 176,9 1.768,6 1.682,4 86,2
D. Technical Assistance (external) 37,3 4,1 - 41,5 - - - - 37,3 4,1 - 41,5 41,5 -
E. Training 3,0 352,2 - 355,2 0,3 35,2 - 35,5 3,3 387,4 - 390,7 355,2 35,5
F. Studies 94,8 221,2 - 316,0 - - - - 94,8 221,2 - 316,0 316,0 -
G. Vehicles 6,3 24,5 6,8 37,5 - 1,2 0,3 1,5 6,3 25,7 7,0 39,0 37,5 1,5
H. Off-farm Investment - 698,1 3,4 701,5 - 69,8 0,3 70,1 - 767,9 3,7 771,6 701,5 70,1
I. Supplies - 63,4 11,7 75,1 - - - - - 63,4 11,7 75,1 75,1 -
J. Research - 1.697,3 - 1.697,3 - - - - - 1.697,3 - 1.697,3 1.697,3 -
K. On-Farm Investment /a - 3.694,2 - 3.694,2 - - - - - 3.694,2 - 3.694,2 3.694,2 -
Total Investment Costs 405,7 10.195,4 612,5 11.213,6 15,5 337,5 43,4 396,3 421,2 10.532,9 655,9 11.609,9 11.213,6 396,3
II. Recurrent Costs
A. Operation & Maintenance
O&M Works - 219,9 48,3 268,2 - - - - - 219,9 48,3 268,2 268,2 -
O&M Equipment - 483,7 53,7 537,4 - - - - - 483,7 53,7 537,4 537,4 -
Subtotal Operation & Maintenance - 703,6 102,0 805,6 - - - - - 703,6 102,0 805,6 805,6 -
B. Vehicles O & M 12,0 12,6 5,4 30,1 0,5 0,5 0,2 1,3 12,6 13,2 5,6 31,4 30,1 1,3
C. Supplies - 8,2 1,8 10,0 - - - - - 8,2 1,8 10,0 10,0 -
D. Staff - 315,7 - 315,7 - - - - - 315,7 - 315,7 315,7 -
E. Other - 192,5 - 192,5 - 0,3 - 0,3 - 192,8 - 192,8 192,5 0,3
F. Gasoline - 18,8 4,1 22,9 - - - - - 18,8 4,1 22,9 22,9 -
G. Travel - 135,6 - 135,6 - 3,5 - 3,5 - 139,1 - 139,1 135,6 3,5
Total Recurrent Costs 12,0 1.387,0 113,3 1.512,4 0,5 4,3 0,2 5,1 12,6 1.391,3 113,6 1.517,5 1.512,4 5,1
Total 417,7 11.582,4 725,9 12.726,0 16,0 341,8 43,6 401,4 433,7 11.924,2 769,5 13.127,4 12.726,0 401,4
\a Includes: improved rainfed farming and on-farm erosion control (US$ 5.5 Mill.); pasture and livestock improvement (US$ 3.7 Mill.); and forestry (US$ 2.9 Mill.).
Example: Breakdown of Expenditure Categories, US$000
Physical
Cont.
Plus
Base Cost Physical Contingencies Total Incl. Cont. Base Costs Price
Local Local Local + Price Cont. on
For. (Excl. Duties & For. (Excl. Duties & For. (Excl. Duties & Cont. on Physical
Exch. Taxes) Taxes Total Exch. Taxes) Taxes Total Exch. Taxes) Taxes Total Base Costs Cont.
I. Investment Costs
A. Equipment 157,3 1.802,8 282,2 2.242,4 7,9 128,4 22,5 158,8 165,2 1.931,2 304,8 2.401,2 2.242,4 158,8
B. Civil Works 511,7 3.074,0 787,1 4.372,8 30,6 260,5 63,9 354,9 542,2 3.334,5 851,0 4.727,8 4.372,8 354,9
C. Technical Assistance (local) - 3.833,3 425,9 4.259,2 - 196,5 21,8 218,3 - 4.029,7 447,7 4.477,5 4.259,2 218,3
D. Technical Assistance (external) 94,5 10,5 - 105,0 - - - - 94,5 10,5 - 105,0 105,0 -
E. Training 7,6 891,6 - 899,2 0,8 89,2 - 89,9 8,4 980,8 - 989,1 899,2 89,9
F. Studies 240,0 560,0 - 800,0 - - - - 240,0 560,0 - 800,0 800,0 -
G. Vehicles 16,0 61,9 17,1 95,0 - 3,1 0,7 3,8 16,0 65,0 17,8 98,8 95,0 3,8
H. Off-farm Investment - 1.767,2 8,6 1.775,8 - 176,7 0,9 177,6 - 1.943,9 9,5 1.953,4 1.775,8 177,6
I. Supplies - 160,4 29,7 190,1 - - - - - 160,4 29,7 190,1 190,1 -
J. Research - 4.297,0 - 4.297,0 - - - - - 4.297,0 - 4.297,0 4.297,0 -
K. On-Farm Investment /a - 9.352,4 - 9.352,4 - - - - - 9.352,4 - 9.352,4 9.352,4 -
Total Investment Costs 1.027,1 25.811,1 1.550,7 28.388,9 39,2 854,4 109,8 1.003,4 1.066,3 26.665,5 1.660,5 29.392,3 28.388,9 1.003,4
II. Recurrent Costs
A. Operation & Maintenance
O&M Works - 556,8 122,2 679,0 - - - - - 556,8 122,2 679,0 679,0 -
O&M Equipment - 1.224,5 136,0 1.360,5 - - - - - 1.224,5 136,0 1.360,5 1.360,5 -
Subtotal Operation & Maintenance - 1.781,3 258,2 2.039,5 - - - - - 1.781,3 258,2 2.039,5 2.039,5 -
B. Vehicles O & M 30,5 32,0 13,7 76,2 1,3 1,4 0,6 3,3 31,8 33,4 14,3 79,5 76,2 3,3
C. Supplies - 20,8 4,6 25,3 - - - - - 20,8 4,6 25,3 25,3 -
D. Staff - 799,2 - 799,2 - - - - - 799,2 - 799,2 799,2 -
E. Other - 487,4 - 487,4 - 0,6 - 0,6 - 488,1 - 488,1 487,4 0,6
F. Gasoline - 47,5 10,4 57,9 - - - - - 47,5 10,4 57,9 57,9 -
G. Travel - 343,3 - 343,3 - 8,9 - 8,9 - 352,2 - 352,2 343,3 8,9
Total Recurrent Costs 30,5 3.511,4 286,9 3.828,8 1,3 10,9 0,6 12,8 31,8 3.522,4 287,5 3.841,6 3.828,8 12,8
Total 1.057,6 29.322,5 1.837,6 32.217,7 40,5 865,3 110,4 1.016,2 1.098,1 30.187,8 1.948,0 33.233,9 32.217,7 1.016,2
\a Includes: improved rainfed farming and on-farm erosion control (US$ 5.5 Mill.); pasture and livestock improvement (US$ 3.7 Mill.); and forestry (US$ 2.9 Mill.).
Guidelines for Planning Irrigation and Drainage Investment Projects 160
ANNEX 3:
Other documentation
THE PRELIMINARY PLANNING BRIEF
As a prelude to the planning process and before commencing any
studies or field work, it will generally be found useful to produce a
preliminary planning brief (PPB) as an aid to focusing the team’s thinking
on the tasks that await it. The PPB is a short (3-5 page), ephemeral
document covering the main topics or issues that the forthcoming work is
expected to address, explains how it is proposed to tackle them, and
indicates the intended outcome. As such, a PPB may be little more than a
listing of tasks which the team leader might in any case note informally
before departure. However, committing thoughts to paper encourages more
focused and deeper thinking, and allows the sharing of ideas with others,
both inside and outside the team, who should be stimulated to provide
additional thoughts of their own and to guide the team towards relevant
reference material.
The PPB is thus a document which the team leader uses mainly to pick
the brains of others and to ensure that team members have a common
starting point. The team leader should be both the author and the ultimate
judge of what the PPB should contain.
• An aide mémoire is the team’s own view, and does not represent an
official position of either the government or the external assistance
organisation: this is inevitable for a document written under time
pressure in the field and without consultation with the
organisation’s management. As a result, views presented in the aide
mémoire, and in particular the commitment of further resources to
follow-up action, must be provisional, and clearly stated as being
subject to subsequent agreement.
1: This may be aided through bibliographic searches using FAO's AGRIS (International Information System for
agricultural Sciences and Technology) or other computerised bibliographies.
Guidelines for Planning Irrigation and Drainage Investment Projects 162
BACK-TO-OFFICE REPORTS
The back-to-office report (BTOR) is the vehicle through which
Investment Centre teams present their broad findings to their own
management and the concerned financing institution within a few days of
their return to headquarters. While still in draft, the BTOR provides the
written material on which the team’s debriefing is based. The BTOR also
informs other staff of work which may be relevant to their assignments,
and serves to attract comments from a peer review.
The content of the BTOR will vary according to the type of assignment,
but should be broadly similar to that of an aide mémoire, although slanted to
address the information requirements of the Investment Centre management.
Guidelines for Planning Irrigation and Drainage Investment Projects 163
All BTORs should also include a brief section which explains how the
mission has examined and addressed the possible social and
environmental impact of the project. BTORs should be succinct and
generally not more than four pages in length. If no other reports are to be
issued by the team, however, a BTOR may not have such a restriction on
its length.
1: Further guidance on preparation of terms of reference may be found in The Investment Centre and
Consulting Firms: A Guideline. FAO Investment Centre, Rome (1983)
Guidelines for Planning Irrigation and Drainage Investment Projects 165
However it is the intended audience and the tone, rather than the
content, which principally distinguishes the project brief from other
planning documents. Project briefs are usually aimed at keeping the
responsible task managers or project controllers in the financing institution
informed of progress, and to focus on facts and issues as they are
understood at the time, rather than leaving these to the end of the stage
concerned, when it may be inconveniently late to take account of other
views. Rather than building the logical case for a project brick-by-brick for
a wide audience, they therefore aim more to respond to the management
question “Where have you got to?”. They are also intended to allow
management to respond to the planning team’s question “Are we on the
right track?”. Since a degree of prior knowledge can generally be assumed,
background information and scene-setting can usually be much truncated.
Project briefs should involve the planning team in just as much careful
thought as a final project document, but they should generally be briefer,
and quicker to write. As a general rule, if the planning team has reached
an in-between stage in its work and is thinking of issuing a “preliminary”
or “interim” report, it should consider writing a project brief instead. At
such a stage it may be a more cost-effective use of reporting time.
1: Investment Centre Technical Paper No 7: Guidelines for the Design of Agricultural Investment Projects.
FAO Investment Centre, Rome (1993).
Guidelines for Planning Irrigation and Drainage Investment Projects 166
Baudelaire, J-P
1994. Structured Irrigation Systems in India. Paper prepared for the
1994 World Bank Water Resources Seminar.
Branscheid, V.
1989. Irrigation Water Management Briefs - 100 Collected Papers.
(FAO Investment Centre Division, Rome)
Irrigation Investment Briefs. 10 Collected Papers.
(FAO Investment Centre Division, Rome)
Burns, R.
1993. Irrigated Rice Culture in Monsoon Asia: The Search for Effective
Water Control Technology. World Development XXI (May, 1993), 771-789.
Byrnes, Kerry J.
1992. Water Users’ Associations in World Bank-Assisted Irrigation
Projects in Pakistan. World Bank Technical Paper No 173.
Guidelines for Planning Irrigation and Drainage Investment Projects 167
Campbell, Donald
1995. Design and Operation of Smallholder Irrigation in South Asia.
World Bank Technical Paper No 256.
Carruthers, Ian
The Case for Irrigation: An Assessment of Need for and the Risk of
Neglecting Sustainable Irrigation Investment. MAINTAIN Working Paper
on Irrigation No 1. (Wye College, University of London/GTZ).
Cernea, Michael M.
1988. Involuntary Resettlement in Development Projects: Policy
Guidelines in World Bank-Financed Projects.
World Bank Technical Paper No 80.
FAO
1976. Water Quality for Agriculture. FAO Irrigation and Drainage Paper
No 29, (FAO, Rome)
1977. Crop Water Requirements. FAO Irrigation and Drainage Paper 24.
(rev.) (FAO, Rome)
1979. Soil Survey Investigations for Irrigation. Soils Bulletin No 42
(FAO, Rome) FAO (1979)
Guidelines for Planning Irrigation and Drainage Investment Projects 168
FAO
Yield Response to Water. FAO Irrigation and Drainage Paper No 33.
(FAO, Rome)
1981. Arid Zone Hydrology. FAO Irrigation and Drainage Paper No 37.
(FAO, Rome)
1983. The Investment Centre and Consulting Firms: A Guideline.
(FAO Investment Centre, Rome)
1985. Guidelines: Land Evaluation for Irrigated Agriculture.
(FAO, Rome)
1986. Guide for Training in the Formulation of Agricultural and Rural
Investment Projects. (FAO, Rome)
1986. Organisation, Operation and Maintenance of Irrigation Schemes.
FAO Irrigation and Drainage Paper No 40. (FAO, Rome)
1986. Design and Operation of Irrigation Systems for Smallholder
Agriculture in South Asia. FAO Investment Centre Technical Papers
No 3/1 and 3/2. (FAO, Rome)
1986. Irrigation in Africa South of the Sahara. FAO Investment Centre
Technical Paper No 5. (FAO, Rome)
1987. Soil and Water Conservation in Semi-Arid Areas.
FAO Soils Bulletin No 57. (FAO, Rome).
1989. Estimating the Economic Efficiency of Irrigation: The Case of
Brazil. Working Paper (FAO/World Bank Cooperative Programme, Rome)
1989. The Design of Agricultural Investment Projects: Lessons from
Experience. FAO Investment Centre Technical Paper No 6. (FAO, Rome)
1989. Water Quality for Agriculture. (rev. 1) FAO Irrigation and
Drainage Paper No 29. (FAO, Rome)
1991. Water Harvesting. (FAO, Rome)
1991. Financial Analysis in Agricultural Project preparation.
FAO Investment Centre Technical Paper No 8. (FAO, Rome)
1991. Guidelines for Report Format.
(FAO, Investment Centre Division, Rome).
1992. CROPWAT - A Computer Program for Irrigation Planning and
Management. FAO Irrigation and Drainage Paper No 46 (FAO, Rome)
1992. Sociological Analysis in Agricultural Investment Project Design.
FAO Investment Centre Technical Paper No 9 (FAO, Rome)
1992. The Use of Saline Waters for Crop Production.
FAO Irrigation and Drainage Paper No 48. (FAO, Rome)
1992. Wastewater treatment and use in agriculture.
FAO Irrigation and Drainage Paper No 47. (FAO, Rome)
1993. CLIMWAT for CROPWAT. FAO Irrigation and Drainage Paper
No 49. (FAO, Rome)
Guidelines for Planning Irrigation and Drainage Investment Projects 169
FAO
1993. Water Report 1: Prevention of Water Pollution by Agriculture and
Related Activities. Proceedings of the FAO Expert Consultation,
Santiago, Chile October 1992. (FAO, Rome)
1993. Integrated Rural Water Management. Proceedings of the
Technical Consultation on Integrated Rural Water Management 15-19
March 1993 Rome. (FAO, Rome)
1993. Guidelines for Land-Use Planning. (FAO, Rome) FAO (1993)
Water Policies and Agriculture. Special chapter of The State of Food and
Agriculture Report 1993. (FAO, Rome)
1993. Remote Sensing and its Application to Investment Project
Identification and Preparation. FAO Remote Sensing Centre Series
No 65. (FAO, Rome)
1993. CLIMWAT for CROPWAT: A Climatic Database for Irrigation
Planning and Management. FAO Irrigation and Drainage Paper No 49.
(FAO, Rome)
1994. User’s Manual of SIMIS (Scheme Irrigation Management
Information System) (Version 1.3). Provisional Text. (FAO Land and
Water Development Division Water Resources, Development and
Management Service).
1995. Reforming Water Resources Policy. FAO Irrigation and Drainage
Paper No 52. (FAO Rome)
1995. Water Report No 5: Irrigation Management Transfer. Selected
Papers from the International Conference on Irrigation Management
Transfer, Wuhan, China, September 1994. (FAO, Rome)
1995. Water Report No 6: Methodology for Water Policy Review and
Reform. Proceedings of the Expert Consultation on Water Policy and
Reform, January 1995. (FAO, Rome)
1995. Building Local Commitment During the Design of Agricultural
Investment Projects: The Experience of FAO’s Investment Centre (Draft)
(FAO, Rome)
1995. Agricultural Investment to Promote Improved Capture and use of
rainfall in Dryland Farming. FAO Investment Centre Technical Paper No
10. (FAO, Rome)
FAO/ODA
1995. Environmental Impact Assessment of Irrigation and Drainage
Projects. FAO Irrigation and Drainage Paper No 53. (FAO, Rome)
FAO/UNDP/WB
1995. Water Sector Policy Review and Strategy Formulation: A General
Framework. FAO Land and Water Bulletin 3. (FAO, Rome)
Guidelines for Planning Irrigation and Drainage Investment Projects 170
FAO/USAID
1987. Expert Consultation on Irrigation Charges (2 vols). (FAO/USAID)
Frederiksen, Harald D.
1992. Drought Planning and Water Efficiency Implications in Water
Resources Management. World Bank Technical Paper No 185.
Goussard, Jean
1993. Automation of Canal Irrigation Systems. Int. Commission on
Irrigation and Drainage, New Delhi (India)
IFAD
1994. The IFAD Experience with Project Design and Implementation:
A Consolidated Review of 26 Closed Projects. Loan Implementation
Unit, Project Management Department. (IFAD, Rome)
ISPAN
1994. Tradable Water Rights: Experience in Reforming Water Allocation
Policy. An applied study prepared for the Bureau for Asia and the Near
East of the U.S. Agency for International Development.
Jansen, Doris J.
1993. Economics of Irrigation: A Modular Methodology for Comparing
the Benefits with the Costs. (Ministry of Lands, Agriculture and Water
Development, Zimbabwe)
Le Moigne, Guy, Ashok Subramanian, Mei Xie and Sandra Giltner (Editors)
1994. A Guide to the Formulation of Water Resources Strategy.
World Bank Technical Paper No 263.
Ostrom, Elinor
1992. Crafting Institutions. Self-Governing Irrigation Systems, Institute of
Contemporary Studies, San Francisco
Guidelines for Planning Irrigation and Drainage Investment Projects 172
Plusquellec, H., Kathryn McPhail and Christian Polti Author’s First Proof
1990. Review of Irrigation System Performance with Respect to Initial
Objectives. (Kluwer Academic Publishers)
Plusquellec, H.
1993. The Value of Performance Studies of Irrigation Projects for
Lending Agencies. (Kluwer Academic Publishers)
1988. Improving the Operation of Canal Irrigation Systems.
(World Bank)
Repetto, Robert
1986. Skimming the Water: Rent-seeking and the Performance of Public
Irrigation Systems. World Resources Institute Research Report No 4.
Smith, Martin
1992. CROPWAT: A computer program for irrigation planning and
management. FAO Irrigation and Drainage Paper No 46. (FAO, Rome)
Guidelines for Planning Irrigation and Drainage Investment Projects 173
Umali, Dina L.
1993. Irrigation-Induced Salinity: A Growing Problem for Development
and the Environment. World Bank Technical Paper No 215.
Uphoff, Norman
Drawing on Social Energy in Project Implementation:
The Results of a Learning Process Approach to Improving Irrigation
Management in Sri Lanka.
Vollrath, T.L.
1994. The Role of Agriculture and its Prerequisites for Economic
Development: A Vision for Foreign Development Assistance.
Food Policy 19, (5), 469-478.
Wade, Robert
1982? The System of Administrative and Political Corruption:
Canal Irrigation in South India.
World Bank
1986. Design and Operating Guidelines for Structured Irrigation
Networks. Irrigation II Division South Asia Projects Department.
1991. Environmental Assessment Sourcebook. vol. 1 World Bank
Technical Paper No 139.
1992. Effective Implementation: Key to Development Impact.
Report of the World Bank’s Portfolio Management Task Force.
1993. Water Resources Management.
1993. Conserving Soil Moisture and Fertility in the Warm Seasonally
Dry Tropics. World Bank Technical Paper No 221.
1994. A review of World Bank Experience With Irrigation
(Operations and Evaluation Department). World Bank Report 13676.
1994. World Bank Sourcebook on Participation.
(Environment Department)
1994. Resettlement and Development. The Bankwide review of projects
involving involuntary resettlement 1986-1993. (Environment Department)
World Bank/USAID
1990. Irrigation Training in the Public Sector:
Guidelines for Preparing Strategies and Programs.
(Economic Development Institute of the World Bank)
Guidelines for Planning Irrigation and Drainage Investment Projects 174
Yoder, Robert
1994. Locally Managed Irrigation Systems. Essential Tasks and
Implications for Assistance, Management Transfer and Turnover
Programs. (International Irrigation Management Institute).
Guidelines for Planning Irrigation and Drainage Investment Projects 175