: METHOD STATEMENT FOR ROOF REPLACEMENT
e
00 25.02.19 FI -
Status Code:
D : Draft FI : For Information FC : For Construction
FA : For Engineer Approval
This Work Method Statement describes the activities required for REPLACEMENT OF EXISTING
ASBESTOS SHEET with NON-ASBESTOS CEMENT SHEET
2.0 REFERENCES
Revision : 00 Page 1 of 5
3.0 WORK LOCATION/ACCESS REQUIREMENTS
_______________
4.0 METHODOLOGY/PROCEDURE
1. Checking all area from inside the status of corrosion of trusses and purlins.
2. Covering of all machineries with Tarpoline.
3. Safety net provision at truss bottom level.
4. Removing and replacement of existing roof.
5. Removing and Cleaning corrosion of trusses and purlins.
6. Painting of trusses and purlins.
Approved
______________
11.0 DISTRIBUTION
Revision : 00 Page 2 of 5
Copies of this Work Method Statement have also been issued to the following personnel for
action:-
Client/owner
Project Manager/Senior Site Engineer
Structural Consultant
Revision : 00 Page 3 of 5